Page 1: Kanban boards step by step

Kanban Boards step-by-step V0.5– beta

See all credits on next slide! by Giulio Roggero under CC 3.0 license

Normal Flow & WIP Urgencies Swarming People Sprint (a proposal)

Support team Personal Time driven Linked Kanban Cross-functional teams

Scatter merge Program Lead Time Portfolio Examples

Page 2: Kanban boards step by step

Credits V0.5 – beta by Giulio Roggero – Creative Common 3.0 License – http://www.agilereloaded.it

Work inspired by great slides and posts written by: •  Joakim Sundén, Marcus Hammarberg and Christophe Achouiantz -

http://www.slideshare.net/marcusoftnet/kanbanboards •  Antonio Lucca - http://tonyxzt.blogspot.it/2011/09/measurment-is-quantitatively-expressed.html •  Claudio Perrone - http://www.slideshare.net/cperrone/a3-kaizen-heres-how •  Benjamin Mitchell - http://blog.benjaminm.net/2012/06/26/how-to-study-the-flow-or-work-with-kanban-cards/ •  Gaetano Mazzanti - http://www.slideshare.net/mgaewsj/agile-in-the-bathtub •  David Anderson - http://agilemanagement.net/index.php/kanbanbook/ •  Fabio Armani - http://www.slideshare.net/tangram77/scrumban-a-methodology-fusion-bettersoftware-2011 •  Yuval Yeret - http://www.slideshare.net/yyeret/explaining-cumulative-flow-diagrams-cfd

Graphics elements by Emanuele Mantovani – http://www.intre.it Great feedbacks by Fabio Armani, Gaetano Mazzanti, Marco Bresciani, Dario Giannoccaro, Stefano Leli, Fabio Ghislandi

Page 3: Kanban boards step by step

Let’s start from a task list …

Page 4: Kanban boards step by step

Todo

Page 5: Kanban boards step by step

… and add statuses

Page 6: Kanban boards step by step

Todo

Page 7: Kanban boards step by step

Todo In Progress

Page 8: Kanban boards step by step

Todo In Progress Done

Page 9: Kanban boards step by step

… add some process

Page 10: Kanban boards step by step

Todo In Progress Done

Page 11: Kanban boards step by step

Todo In Progress Done

Page 12: Kanban boards step by step

Todo Done AnalYze

Page 13: Kanban boards step by step

Todo Done AnalYze WoRK

Page 14: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Page 15: Kanban boards step by step

… and queues

Page 16: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing

Page 17: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done

Page 18: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing

Page 19: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

Page 20: Kanban boards step by step

… and work-in-progress limits

Page 21: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

Page 22: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

2

Page 23: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

2 3

Page 24: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 25: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

WIP LIMITS!

Page 26: Kanban boards step by step

Kanban step-by-step

Page 27: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 28: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 29: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 30: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 31: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 32: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 33: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

FLOW à

Page 34: Kanban boards step by step

Bottlenecks!

Page 35: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 36: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 37: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

WIP Limit of verify is 2! Complete one task before starting a new one…

Page 38: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

STOP STARTING, START FINISHING!

Page 39: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 40: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 41: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 42: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 43: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Remove the bottleneck and the pull system restart the flow!

Page 44: Kanban boards step by step

Waitings!

Page 45: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 46: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

NOTHING TO WORK ON, SPEED Up the analyze!

Page 47: Kanban boards step by step

Say ciao to team members!

Carlo Elena

Marc Jean

Emma

Page 48: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 49: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 50: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 51: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 52: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Elena completed the verification AND now WHAT ITEM SHE WILL TAKE?

Page 53: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

SHE HELPS JEAN IF PAIRING reduce the time to complete the task

Page 54: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 55: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 56: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Another solution if support to jean is not feasible

Page 57: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

ELENA WILL TAKE ANOTHer activity in queue

Page 58: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 59: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 60: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 61: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 62: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

ELENA and jean are free, how to take a new task?

Page 63: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Take the most important TASK togheter to speed the flow

Page 64: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 65: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 66: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 67: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

OR …

Page 68: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

… work in parallel if working together is not effective

Page 69: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

… work in parallel if working together is not effective

Page 70: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

… work in parallel if working together is not effective

Page 71: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

… work in parallel if working together is not effective

Page 72: Kanban boards step by step

Urgencies!

Page 73: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 74: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 75: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 76: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 77: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent à This is a swim lane, max speed here! à

Page 78: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 79: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 80: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 81: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 82: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 83: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 84: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 85: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 86: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3

Page 87: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3

Page 88: Kanban boards step by step

More urgencies levels?

Page 89: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent

Page 90: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent More levels of urgencies?

Page 91: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

2 3 2

URGENT

You can highlight urgencies moving them on the top

Page 92: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

2 3 2

CRITICAL!

URGENT And draw lanes with different priority

Page 93: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY

Doing Done Doing Done

2 3 2

CRITICAL! 2

4 URGENT ADDing WIP LIMIT to each lane

Page 94: Kanban boards step by step

Hey guys here there is a problem!

Page 95: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3

Page 96: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3 This work it’s not ok!

Page 97: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3

Page 98: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3 Option 1 – add to work queue the blocking issue

Page 99: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3

Page 100: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3 Option 2 – add to work urgent lane the blocking issue

Page 101: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Urgent 3 Option 3 - SWARMING! ALL on the bloCking issue!

Page 102: Kanban boards step by step

Limit team activities with avatars

Page 103: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

I’M Free! 2 TASKS x PERSON

Page 104: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

I’M Free! 2 TASKS x PERSON I’m working on other stuff

Page 105: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

I’M Free! 2 TASKS x PERSON I’m working on other stuff SICK VACATION

Page 106: Kanban boards step by step

Forecasts

Page 107: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 108: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

5 days from hereà

Page 109: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

5 days from hereà

10 days from here à

Page 110: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

5 days from hereà

10 days from here à

Using historical data you can estimate the flow

Page 111: Kanban boards step by step

Planning

Page 112: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 113: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 114: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

Add the sprint concept to plan the priority of todoS every week

Page 115: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

Page 116: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

Page 117: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

Page 118: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

Page 119: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

Page 120: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

PLAN Plan for the next sprint during current sprint

Page 121: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

THIS SPRINT

NEXT

PLAN Sprint completed, ready for next sprint

Page 122: Kanban boards step by step

Linked Kanban boards, Scrum example

Page 123: Kanban boards step by step

BACKLOG ACCEPT SELECTED WORK TEST

Doing Done READY OK

20 SP

TODO IN PROGR DONE

FREE - max 2 avatars x person

ß PROduct backlog

SPRINT backlog à

Page 124: Kanban boards step by step

BACKLOG ACCEPT SELECTED WORK TEST

Doing Done READY OK

20 SP

TODO IN PROGR DONE

ß STORIES

Tasks à FREE - max 2 avatars x person

Page 125: Kanban boards step by step

BACKLOG ACCEPT SELECTED WORK TEST

Doing Done READY OK

20 SP

TODO IN PROGR DONE

STORY

FREE - max 2 avatars x person

Page 126: Kanban boards step by step

BACKLOG ACCEPT SELECTED WORK TEST

Doing Done READY OK

20 SP

TODO IN PROGR DONE

STORY

Related tasks FREE - max 2 avatars x person

Page 127: Kanban boards step by step

BACKLOG ACCEPT SELECTED WORK TEST

Doing Done READY OK

20 SP

TODO IN PROGR DONE

FREE - max 2 avatars x person

Live sprint!

Page 128: Kanban boards step by step

Personal kanban board

Page 129: Kanban boards step by step

IDEAS doing DONE 3 20

Page 130: Kanban boards step by step

IDEAS failed doing success 3 20

Page 131: Kanban boards step by step

IDEAS failed planned doing success 8 3 20

Page 132: Kanban boards step by step

IDEAS failed planned doing success 8 3 20

THIS MONTH

Page 133: Kanban boards step by step

IDEAS failed planned doing success 8 3 20

THIS MONTH

NEXT MONTH

Page 134: Kanban boards step by step

Support Team kanban board

Page 135: Kanban boards step by step

tickets closed doing resolved 3 20 8

Page 136: Kanban boards step by step

tickets closed doing resolved 3 20 8

Urgent 3

Page 137: Kanban boards step by step

tickets closed planned doing resolved 8 3 20

Urgent 3

8

Page 138: Kanban boards step by step

tickets closed planned doing resolved 8 3 20

Urgent 3

8

Today

Page 139: Kanban boards step by step

tickets closed planned doing resolved 8 3 20

Urgent 3

8

Today

tomorrow

Page 140: Kanban boards step by step

tasks

bugs

change requests

new features

Page 141: Kanban boards step by step

tickets closed planned doing resolved 8 3 20

Today

tomorrow

Urgent

8

Use colors for activities types

Page 142: Kanban boards step by step

tasks

bugs

change requests

new features

20%

20%

20%

40%

Limit mix of items types

Page 143: Kanban boards step by step

Cross-functional team kanban board

Page 144: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

4 6 4

Page 145: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done SW Done

4 6 4

SW – software devel!

Page 146: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 6 4

FW – firmware devel!

FW

SW

Page 147: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 6 4

HW – I build hardware!

FW

SW

HW

Page 148: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

WIP limits per lane

FW 2

SW 3

HW 1

Page 149: Kanban boards step by step

Scatter merge

Page 150: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Page 151: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Page 152: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Page 153: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

This features is cross

FW 2

SW 3

HW 1

Page 154: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Split the features in Sw, fw and hw

Page 155: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Page 156: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Page 157: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Merge taks for the feature

Page 158: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Merge taks for the feature

Page 159: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Merge taks for the feature

Page 160: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Done

4 4

FW 2

SW 3

HW 1

Merge taks for the feature

Page 161: Kanban boards step by step

Time driven kanban board

Page 162: Kanban boards step by step

program

project

change requests

new features

sub-project

Page 163: Kanban boards step by step

backlog DONE quarters MONTH DOING 8 5 20

current

next

3

next

current

Strategy board

Page 164: Kanban boards step by step

Program kanban board

Page 165: Kanban boards step by step

Issues Team Backlog with priorities

Todo this month 20  

Free person

Person on other projects

Prj A

Prj B

Prj C

Prj D

Prj E

Blockers

Crtical

Two avatars per person

20  

Devel Test Acceptance Released

Ready Accepted In prog Done

14   10   30  

5  

10  

Page 166: Kanban boards step by step

Portfolio kanban boards

Page 167: Kanban boards step by step

IDEAS Brainstorming APPROVAL

10 5

Idea generation phase

OK

DISCARDED

SIZE & PRODUCT/SERVICE VISION KPI to monitor after deploy

SIZING, VISION & KPI READY FOR FUNNEL

Innovation bubbleS

4

Pre-funnel

Page 168: Kanban boards step by step

Funnel backlog APPROVAL 10 Business &

TECH AnaLYSIS

7 5

OK

IN PROG DONE

DISCARDED

URGENCIES BACKLOG (WIP)

SIZED SIZED+ VISION

TEAM READY

starting In prog UAT completed APPROVED & Closed

IN Prod

Idea generation implementation 5

deploy

URGENCIES in progress (WIP)

Operations BACKLOG (WIP) Operations in progress (WIP)

Innovation bubble

incubators

Page 169: Kanban boards step by step

Lead time

Page 170: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 171: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Lead time – end to end

Page 172: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Lead time

Cycle time – working on…

Page 173: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Lead time

Cycle time – working on…

WIP LIMIT

Page 174: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Lead time

Cycle time – working on…

2 in verify!

Page 175: Kanban boards step by step

Draw them on cumulative flow diagram

Todo

In progress

Done

Page 176: Kanban boards step by step

Draw them on cumulative flow diagram

Todo

In progress

Done

Time à

Items

Page 177: Kanban boards step by step

Draw them on cumulative flow diagram

Todo

In progress

Done

Cycle time

WIP

Page 178: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 179: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 180: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 181: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 182: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 183: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 184: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 185: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 186: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 187: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 188: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 189: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 190: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 191: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

ß Cool first done!

Page 192: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 193: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 194: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 195: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 196: Kanban boards step by step

Todo Done AnalYze WoRK VERIFY Doing Done Doing Done

2 3 2

Page 197: Kanban boards step by step

Real Examples

Page 198: Kanban boards step by step
Page 199: Kanban boards step by step

Business  ideas  and  selec,on  

Urgencies  

Teams   Closing  

Page 200: Kanban boards step by step
Page 201: Kanban boards step by step
Page 202: Kanban boards step by step

Pre-­‐Funnel   Funnel

Vision and T-Shirt Sizing Business Model, Business Case, Backlog, Devel, UAT, Deploy

Initiatives Gathering Initiatives Analysis and Implementation

Page 203: Kanban boards step by step
Page 204: Kanban boards step by step

*http://trello.com

Page 205: Kanban boards step by step

Stay tuned for next versions: •  Portfolio kanban boards •  Prisoner metric •  Control Charts •  How-to reduce the WIP step-by-step from current situation to one-piece-flow

This is not the end … … is just the begin of your journey! Kanban is not only a board; Lean is not only Kanban. Be courios, respect people and improve, always!

Page 206: Kanban boards step by step

[email protected] @giulioroggero

Giulio Roggero

Visit www.agilereloaded.it for more informations