KAIA Development Project Project Management Plan Design and Engineering Services for King Abdul Aziz International Airport Development Project – Jeddah for Saudi Binladin Group Project Management Works Plan Issue No. 1 Issue Date: 18 th February 2011 Page | 1 وه ك ار ش م وز ي ا ر ف هي ر ون ي ار ش ست اZuhair Fayez Partnership Consultants Architecture, Engineering and Information Systems Prepared by: Dr Andrew Kimmance (Project Director) 7165 Reviewed by: Basim Hasaballah (admin director) 2180 Approved by: Hazem Ibrahim (senior board director) 1826
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
KAIA Development Project Project Management Plan
Design and Engineering Services forKing Abdul Aziz International Airport
Development Project – Jeddah for Saudi Binladin Group
Project Management Works Plan
Issue No. 1
Issue Date: 18th February 2011
Page | 1
زهــــــير فايـــــــز ومشــــــــاركـــــوهاستشــاريـــــــــــــــــــــــــــــــــــــــــــونعمارة – هندسة – نظـم معلومــات
جدة5445صندوق بريد
Zuhair Fayez PartnershipConsultantsArchitecture, Engineering and Information SystemsP.O. Box 5445, Jeddah 21422Saudi ArabiaTelephone: 6129999Facsimile: 6129955
Prepared by: Dr Andrew Kimmance (Project Director) 7165Reviewed by: Basim Hasaballah (admin director) 2180Approved by: Hazem Ibrahim (senior board director) 1826
Table 12: Change Control Process Sheet................................................................................................37
Table 13: Change Control Register.........................................................................................................39
Page | 4
KAIA Development Project Project Management Plan
MANUAL TITLE: PROJECT WORK PLAN Doc Ref:
DOCUMENT TITLE:Fast Track ‘Design and Engineering Service for the King Abdul Aziz International Airport Development Project’ KAIA, Jeddah.
Issue No.: 1
Page: 5 of 48
Written by: Dr - AGK (7165) Approved by: BMH (2180)
PREFACE
The purpose of the project works report plan presented in is to demonstrate an awareness and understanding of the project deliverables and scope of work, and to provide a detailed account to the client of the approach and methodology used to meet project objectives. As well to all concerned Zuhair Fayez Partnership (ZFP) parties a common source of information regarding project goals, project scope, services description, project participants, time schedule, production budget, quality procedures, and other pertinent data in order to establish and communicate project performance expectations to the Client. Zuhair Fayez Partnership’s primary goals for this project are:
1. Higher Perceived Quality.
2. Improved Customer Satisfaction.
3. Competitive Edge.
These benefits achieved by:
1. Improved Management Control, Organization, and Planning.
2. Improved Customer Services.
3. Consistency in Product and Process.
To meet the Owner’s project goals, design the highest quality project for an appropriate construction cost and do so as efficiently and expeditiously as possible. Both Owner and ZFP goals will be realized through effective communication, creative design, technical capability, and dedicated effort by all project participants.
This document will be distributed to all concerned parties and as contents are revised or pertinent additional information becomes available, copies will be distributed for inclusion in the originally distributed copy. Each recipient of distributed revision items is to remove the superseded items and insert the revised items.
Page | 5
Zuhair Fayez Partnership Consultants شركة زهير فايز ومشاركوه لإلستشاراتArchitecture, Engineering and Information Systems عمارة - هندسة – نظم معلومات
_______________________________________________________________________________ 966 2 6129955+ فاكس: 966 2 6129999 – المملكة العربية السعودية - هاتف : +21422 جدة 5445ص . ب:
P. Box 5445 Jeddah 21422 – Saudi Arabia - Tel: +966 2 6129999 Fax: 966 2 6129955
KAIA Development Project Project Management Plan
Figure 11: Project Management Work Plan (Kimmance, 2010)
Page | 6
Proposed Work PlanTech. PhasesProject TeamTime Schedule
PROJECT WORK PLAN
Yes
START
STOP
No
Comments
Prepare Work Plan detailing methodology to execute the ProjectPM
Submit to Client for Approval
Ensure Conformity of Work Plan to Scope of Proposal & ContractPM
Client to issue “Notice to Proceed”
Contract to be as mutually
agreed between ZFP &
Client
Include the Required Sections & the Client’s
RequirementsPM
Basic Tech. DataObjectiveDurationScopeWork Stages
Submit Completed Work Plan to TM for Review & Approval
EIS/PMF01PM/TM
Assign Core Team Engineer to Review &
Finalize with PM
EIS/PMF02TM/CT Engineer
Submit Finalized Work Plan to TM for Review
& Approval
EIS/PMF03CT Engineer/TM
Review By PDYes
No
Comments
Distribute Approved Work Plan to PM, PCE, & Team Leaders
Zuhair Fayez Partnership Consultants شركة زهير فايز ومشاركوه لإلستشاراتArchitecture, Engineering and Information Systems عمارة - هندسة – نظم معلومات
_______________________________________________________________________________ 966 2 6129955+ فاكس: 966 2 6129999 – المملكة العربية السعودية - هاتف : +21422 جدة 5445ص . ب:
P. Box 5445 Jeddah 21422 – Saudi Arabia - Tel: +966 2 6129999 Fax: 966 2 6129955
KAIA Development Project Project Management Plan
MANUAL TITLE: PROJECT WORK PLAN Doc Ref:
DOCUMENT TITLE:Fast Track ‘Design and Engineering Service for the King Abdul Aziz International Airport Development Project’ KAIA, Jeddah.
Issue No.: 1
Page: 7 of 48
Written by: Dr - AGK (7165) Approved by: BMH (2180)
1 Introduction
King Abdul Aziz International Airport (henceforth referred to as KAIA) is the hub of Air Transport
in the Kingdom of Saudi Arabia. The airport was inaugurated in 1981 and comprises of two
passenger terminals and three runways. The airport is in all honesty unique, as it is the principal
gateway into the Kingdom for millions of Pilgrims performing Hajj and Umrah each year.
The Western boundary of King Abdul Aziz International Airport (KAIA) is just 4 kilometres to the
East of the Red Sea and converging with the Eastern boundary in the midst of the mountainous
region of the Arabian Shield, as illustrated in Figure 2.
, and at a cost of £400million.The airport is roughly situated 20 kilometres to the North of
Jeddah City and 90 km West of Makkah (ARP: Lat 21°-40’-52’’N: Long 39° 09’ 18.5’’E). The
location of the site is virtually flat with a small slope running from East to West. The airport
occupies a vast site of approximately 10,500 hectares (25,946 acres); although, both Dammam
and Riyadh Airports occupy a larger area. The airport has three runways:
Runway 16R/34L is 3,800 meters in length and 60 meters wide
Runway 16C/34C is 3,300 meters in length and 60 meters wide
Runway 16L/34L is 3,690 meters in length and 60 meters wide
The airport has two passenger terminals. The North, deal with foreign airlines and the South,
which for the use for Saudi domiciled airlines Nasair and Saudi Arabian Airlines (and their code
share partner Air France) with both terminal sharing 46 remote stands. In addition, the airport
also has a Royal terminal with 2 stands, a cargo terminal with 7 stands and a Hajj terminal with
34 stands. The ATC tower at the airport is located between the two terminals and is 60 meters
tall.
Page | 7
KAIA Development Project Project Management Plan
The airport is situated to the South of Obhur and North of the industrial city of Jeddah. Three
main roads surround the bounder of the airport with the Al-Haramain Expressway running along
the Eastern boundary, Madinah Road to the North and West and Al Nuzhah Street to the South.
1.1 Project History
The redevelopment of KAIA has long been anticipated. The GACA did appoint an international
consultant to produce the final designs for a new terminal building and associated infrastructure.
However, they decided to curtail this project and re-tender the project as fast track design and
build. Thus, the design process will run in parallel with construction. The KAIA Development
Project was awarded to the Saudi Bin Laden Group (SBG) in September 2010 with the GACA
being advised by Dar Al-Handasah. ZFP has been sub contracted out by SBG to provide the
final designs up to tender documents for key components of the terminal and associated
infrastructure. The NTP (Notice to Proceed) is expected to be issued on 8th January 2011 with
ZFP’s involvement lasting for 300 days from this date, and at a cost of £400million.
Figure 12: Jeddah Airport and surrounding area
Page | 8
Jeddah CityJeddah City
Red Sea
Jeddah Airport
KAIA Development Project Project Management Plan
2 Project Description
Current airport infrastructure cannot adequately accommodate passenger demand during peak
operations. This situation is expected to deteriorate as passenger demand continues to rise.
The General Authority of Civil Aviation (henceforth referred to as the GACA) has decided that a
new terminal is to be built in which all airlines will collocate. This will alleviate congestion and
will permit future expansion.
Three stages of expansion have been envisaged with the first to be completed in 2013 with
capacity for 30 million passengers, the second to be completed in 2020 with capacity for 43
million, and the third phase to be completed in 2035 with capacity for 80 million. During the first
phase, a new terminal building will be located between runways 16C/34C and 16L/34R. The first
phase, design and build of the new terminal and associated infrastructure project is scheduled
to take 36 months and will see the airport’s capacity substantially increase from its current 17
million.
A fast track design and build contract was awarded by GACA to the Saudi Bin Laden Group
(henceforth referred to as SBG) for the construction of the new terminal building and associated
airport infrastructure at KAIA. ZFP has in turn been sub contracted by SBG to provide the final
designs up to tender documents for key components of the airport infrastructure.
3 Assignment
The core assignment is to produce fast track designs up to tender documents, and to include all
required supporting documents and approvals to fulfil design deliverables associated with the
KAIA Development Project. ZFP has been entrusted to produce designs that will meet the
client’s primary objective, which is to produce fast track designs, on time, within budget and to
required schedule. To this end, it is ZFP’s desire to design functional, inspiring and
technological advanced designs that meet the client’s exacting standards within the allocated
time, within budget and to the highest quality standards. ZFP is fully committed to providing
excellent quality consultancy services that demonstrate our competency in producing designs
for the KAIA Development Project.
Page | 9
Zuhair Fayez Partnership Consultants شركة زهير فايز ومشاركوه لإلستشاراتArchitecture, Engineering and Information Systems عمارة - هندسة – نظم معلومات
_______________________________________________________________________________ 966 2 6129955+ فاكس: 966 2 6129999 – المملكة العربية السعودية - هاتف : +21422 جدة 5445ص . ب:
P. Box 5445 Jeddah 21422 – Saudi Arabia - Tel: +966 2 6129999 Fax: 966 2 6129955
KAIA Development Project Project Management Plan
To achieve such a goal it is imperative that both sides effectively communicate and are fully
committed to the project. The duration of ZFP’s involvement in this project will be 300 days from
the NTP. There are a number of key project objectives associated with the development:
To produce a design that inspires whilst technologically advanced and functional
To produce a design that takes into account the client’s requirements while adhering to
the allocated budget and schedule
To provide professional services to our client that ensures complete customer
satisfaction
To demonstrate ZFP’s capability in producing quality work
To ensure a suitable return on investment
4 Project Scope
The project is located at the existing KAIA site, with a new terminal building to be built between
runways 16C/34C and 16L/34R. The title of the project is ‘Design and Engineering Service for
the King Abdul Aziz International Airport Development Project’. ZFP is to provide SBG with the
designs up to tender documents for key components of airport infrastructure. The scope of
work consists of the following design stages:
Data collection and conceptual design stage
Schematic design and design development
Final design up to tender documents
Production of printed documentation
5 Major Milestones
The Project Management Team (i.e. Project Director and Project Co-ordinators) are to tracks all
major milestones. This will ensure that they have oversight of all key milestones and can
provide an overview to the Project Team associated with the design phase and senior
management. For simplicity, the contract awarded by SBG to ZFP has two packages 421 and
422 illustrated in Figure 13. However, to fully appreciate the divisions between the two packages
please refer to Figure 4. MANUAL TITLE: PROJECT WORK PLAN and Table 2 display the milestone
packages, and the work split for both 421 and 422 is illustrated in Figure 13: KAIA Project Schedule
Top Tier4.
Page | 10
KAIA Development Project Project Management Plan
Figure 13: KAIA Project Schedule Top Tier
Page | 11
KAIA Development Project Project Management Plan
Figure 14: Work Split for Contract 421 and 422
Page | 12
KAIA Development Project Project Management Plan
MANUAL TITLE: PROJECT WORK PLAN Doc Ref:
DOCUMENT TITLE:Fast Track ‘Design and Engineering Service for the King Abdul Aziz International Airport Development Project’ KAIA, Jeddah.
Issue No.: 1
Page: 13 of 48
Written by: Dr AGK (7165) Approved by: BMH (2180)
Table 1: Major Contract Milestones for Package 421
Milestone No. Milestone Description
Calendar Days from Notice to Proceed
1Mobilisation and submission of proper locations of E/M connection points for all buildings and submission of the Hydrogeological Studies
90
2 Complete Structural Design 120
3 Complete Overall Final Design works and Radio Sites Relocation and Dismantle 300
Table 2: Major Contract Milestones for Package 422
Milestone No. Milestone Description
Calendar Days from Notice to Proceed
1 Structural Design Completion for foundations of transportation Centre & Viaduct 75
2
Mobilization, submission of Hydrogeological Studies and submission of preliminary Architectural drawings to allow other Contractor to define E/M & ICT devices locations.
90
3 Structural Design Completion 1204 Submission of Regional Ground Water Control Study 1805 Complete Overall Final Design works 300
These milestones are included in the Master Deliverables List and will need to be
tracked with regards in the project schedule. The milestones will be constantly monitored
to ensure submittal deadlines are adhered to. In order to achieve this, a Milestone Chart
and Report will be completed when monitoring the progress. Examples of both the chart
and Report are shown in the following two pages.
Page | 13
KAIA Development Project Project Management Plan
Milestone Chart
Main milestone phases shown on the higher chart, and sub-milestones for each phase on charts below
TIME [in suitable units -days, weeks, months, etc.]MILESTONES Responsibility
Page | 14
KAIA Development Project Project Management Plan
Milestone ReportProject No:
Date of Milestone meeting/discussion:
Deliverables due Due date R/Y/G* Action to take to bring deliverable or task back on schedule
* R = RED Flags [critical, off plan - describe in detail: quality, cost, time]
Y = YELLOW [is almost off schedule or will definitely be off schedule, the precise definition shall be agreed before use]
G = GREEN Flags [to plan or better - show savings]
Page | 15
1
1.1
2.1
2
3
4
5
6 Team identification
The associated project team consists of Project Management, Design and Quality
Assurance Team members, and all speciality groups that need to be involved with the
development of the project. The speciality groups shall be involved in project planning,
scheduling, development and maintenance, and endorsement of the Work Plan. The
following speciality groups are involved:
Land Surveying
Architecture
Roadside and Pavement Development
Bridges and Structures
Civil Engineering
Mechanical, Electrical and Plumbing (MEP)
Rapid Development
Program Management
Environmental Services
Geotechnical Services
Utilities
Abundance of Authories
KAIA Development Project Project Management Plan
2
3
4
5
6
6.1 Project Team Roles and Responsibilities
The structure of the project team roles and responsibilities are in accordance with the
Project Organisation Chart shown in Figure 5. A number of project team roles have been
described in further detail in order for the titleholder/client to further appreciate the
responsibilities associated with these roles. The Project Production Arrangement is
shown in Figure 16 and illustrates how Project Mangers are to interact with department
disciple leads, the Project Director, CAD technicians and drawers, designers, quality
control and assurance.
6.1.1 Senior Programme Director
Adel Wehbi Communicate with the client and ensuring all client’s requirements are all met
To be the main interface for all external communication
Communicate with external partners and other stakeholders
6.1.2 Technical Airport’s Project Director and Principal Project Manager
Dr Andrew Kimmance (author) Manage and Coordinate the KAIA Development designs and Project Teams
Set-up and manage the Project Management Framework, Communications,
Production and Operations, Performance and Progress Methodologies
Page | 17
KAIA Development Project Project Management Plan
To liase and coordinate with the Strategic Corporate Board, Senior Project
Director, Clients, Stakeholders, Consultants, and Supply Chain
6
6.1
6.2
6.1.3 Project Managers
Nicolas Mohammed Abboud and team Package 421
Luis Kusters Viale and team Package 422
To be responsible and coordinate a package for which they are assigned in
addtion to the duties outlined under Project Coordinator.
6.1.4 Project Coordinators and Planners
Nicolas Abboud: 421.3 Passenger Terminal Complexes
421.4 Air Traffic Control Complex
Richard Fuentes: 422.2 Load Centres
422.4 Utilities and Main Distribution
Luis Kusters Viale: 421.1 Radio Sites Relocation & Dismantling,
421.2 Interim Facilities,
421.5 Support Facilities
422.6 Support Facilities
Mohamed Yousef: 422.1 Viaduct Transportation Centre & Multi-storey Car Park,
422.3 Land Side Ground Access Components
422.7 Aprons and Taxiways
Responsible for coordinating technical issues of the project and identifying and
analysing project requirements.
Identify resource requirements for the project
Page | 18
KAIA Development Project Project Management Plan
Coordinate the procurement of products/services from suppliers and sub
contractors
Assure that project records, data and documents are properly maintained and
stored for future reference
Coordinate the development of project design specifications and development
plans
To be responsible for their various parts of Package 421 and 422 as previously
The requirements specified do not match the project/client needs The requirements specified are not measurable
1.11.21.3
Benefits The business benefits have not been identified The business benefits are not quantifiable The final solution delivered does not achieve the required benefits
2.12.22.3
Schedule The schedule doesn’t provide enough time to complete the project The schedule doesn’t list all of the activities and tasks required The schedule doesn’t provide accurate dependencies
3.13.23.3
Budget The project exceeds the budget allocated There is unaccounted expenditure on the project There is no single resource accountable for recording budgeted
spending
4.14.24.3
Deliverables The deliverables required by the project are not clearly defined Clear quality criteria for each deliverable have not been defined The deliverable produced doesn’t meet the quality criteria defined
5.15.25.3
Scope The scope of the project is not clearly outlined The project is not undertaken within the agreed scope Project changes negatively impact on the project
6.16.26.3
Issues Project issues are not resolved within an appropriate timescale Similar issues continually reappear throughout the project Unresolved issues become new risks to the project
7.17.27.3
Suppliers The expectations for specialists/supplier delivery are not defined Specialists/suppliers do not meet the expectations defined Specialists/Supplier issues negatively impact on the project
8.18.28.3
Acceptance The criteria for accepting project deliverables aren’t clearly defined Clients do not accept the final deliverables of the project The acceptance process leaves the customer dissatisfied
9.19.29.3
Communication Lack of controlled communication causes project issues Key project stakeholders are ‘left in the dark’ about progress
10.110.210.3
Resource Staff allocated to the project are not suitably skilled Insufficient equipment is available to undertake the project There is a shortage of materials available when required
Highly unlikely to occur; however, still needs to be monitored as certain circumstances could result in this risk becoming more likely to occur during the project
Low 40Unlikely to occur, based on current information, as the circumstances likely to trigger the risk are also unlikely to occur
Medium 60 Likely to occur as it is clear that the risk will probably eventuate
High 80 Very likely to occur, based on the circumstances of the project
Very High 100Highly likely to occur as the circumstances which will cause this risk to eventuate are also very likely to be created
Project Name: KAIA Development ProjectProject Manager: Dr Andrew Kimmance
RISK DETAILS
Risk ID: 10.1Raised By: George AllenDate Raised: 15/01/2011Risk Description:
Current IT infrastructure does not have the required capacity to host all KAIA related data.
This will impact on the productivity as personnel may not be able to work on the project or have problems accessing work. Furthermore, it will impact on the budget as this is an unforeseen capital expenditure. Finally, it will also affect the schedule, caused by delivery and installation of new hardware.
Risk Likelihood:
Very High: 100
Risk Impact:
High: 80
RISK MITIGATION
Recommended Preventative Actions:
Liaise with ICT to ensure that all available capacity is made available for the KAIA project. Suggest that some folders are archived and taken off the serve to release capacity.
Recommended Contingent Actions:
Order a new server to provide the additional capacity or ensure contact has been made with suppliers in order to quickly obtain and install a new server.
Communicate projectprogress to senior PM Project Manager as requested as appropriate
Communication among all teams
All e-mail/phone/memo every Tuesday
Distribute & maintain schedule
Quality Control e-mail/WEB
Create organisational chart that identifies
Team Structure
Project Director
Technical Director
computer software 20/01/2011
Request information Project director e-mail 23/01/2011
How do team communicate
All e-mail/phone
Facilitate distribution of information
Design team- project manager
e-mail/verbal as appropriate
11 Change Management
During the life of the KAIA project changes to the project scope, schedule, and
resources may occur. The sources of these changes may be internal or external initiated
by the client/customers. External changes can also result from other stakeholders,
availability of resources, changes in technologies, designs, etc. Whether the effects of
changes are positive or negative, managing change is an important factor for success.
Managing change will require planning, discipline, and communication among the project
team, customers and stakeholders.
Page | 39
KAIA Development Project Project Management Plan
7
8
9
10
11
11.1 Change Management Plan
As the Change Management Plan is executed, the following should occur:
Improved relationship with clients, contractors, other stakeholders, improved
financial performance, reduced project delays, better project teamwork, and
improved project quality.
There a number of changes that can be anticipated on the KAIA Development Project,
including but not limited to the following:
1. Scope creep
2. Staff changes
3. Schedule change
4. Change in deliverables
5. Technical change
6. Process/Policy change
7. Resources/Technologies/Materials changes
Page | 40
KAIA Development Project Project Management Plan
Figure 19: Internal Communication Protocol (developed by Dr Andrews)
Page | 41
ZFP Communication Protocol for King Abdul-Aziz International Airport Project
OutgoingInformation
Document ControllerSystem
Record Log
KAIA Development Project Project Management Plan
11.2 Change Control Process
12
13
14
Changes that could impact on the design (whether they are initiated by the client or through design development) shall be communicated to the appropriate parties at the earliest opportunity. Table 12 exhibits a step by step change review process form which shall be initiated to manage all changes that may occur during the project duration. These changes shall be documented in the Change Control Register, as shown in Table 13, in order to give advanced warnings of a potential risk or issue in the form of a Consultants Notification. Such notice shall be issued to the client as soon as the team becomes aware of any matter that may:
Increase the cost
Delay completion or delay meeting a key date
Impair the performance of the Works in use.
The following steps have been identified as critical in the process to manage change:
1. Identify source and nature of the change
Determine the type of change (work plan, schedule, technical, etc.)
Determine the potential impact and process (formal/informal)
Document origin of change (who initiated it, what precipitated it)
Identify potentially affected customers and suppliers
Identify who should lead the analysis/rest of process
Communicate potential to rest of team as needed
1.
2. Analyse the effects of the change
Page | 42
KAIA Development Project Project Management Plan
How does it relate to purpose/mission?
Compare change against the current process
Quantify the change (how much, how long, how much risk)
Cause-effect analysis
Brainstorm, analyse, and prioritise strategies
Identify impacts against agreed upon requirements
Access profound knowledge
Table 12: Change Control Process Sheet
Project Title: KAIA Project NumberProject Director: Dr Andrew Kimmance
CHANGE REQUESTOriginatorPhone:
Date of request Change request no.allocated by Change Controller
Items to be changed Reference(s)
Description of change (reasons for change, benefits, date required)
Estimated cost and time to implement (quotation attached? Yes No)
Priority / Constraints (impact on other deliverables, implications of not proceeding, risks)
CHANGE EVALUATIONWhat is affected Work required (resources, costs, dates)
Related change requestsName of evaluator Date evaluated SignatureCHANGE APPROVAL Accepted Rejected Name Signed Date
Page | 43
KAIA Development Project Project Management Plan
DeferredComments
CHANGE IMPLEMENTATIONAsset Implementer Date
completedSignature
3. Develop a response/action plan strategy
Document analysis into proposal form
Identify customers/stakeholders/level of authority for endorsement
Plan steps for presentation by answering these questions:
o What needs to be done, who will do it, and by when?
o How will quality and customer service be ensured?
o What will be the effects on other project tasks?
o How will the team communicate with the other stakeholders?
4. Communicate strategy and gain endorsement
Schedule meeting(s)
Send letter/documentation package
Gain endorsement and/or feedback
Adjust strategy as needed and update database
5. Implement change plan and monitor the effects
Identify responsibilities and timelines for carrying out
Revise the work plan
Monitor and evaluate implementation
11.3 Change Management Record
The Change Management Record is a means to document, track, and measure the
impact of change on critical project factors. Use of this Change Management Record will
be considered mandatory, and will include the following information:
Page | 44
KAIA Development Project Project Management Plan
Description of Change
Decision Description
Type of Change
Decision Impact Discussion (quantity/quality)
Origin of Change
Who “helped” develop response?
Lead Manager and Related Project Names
Analyst
Location
Communication both external and internal
Cost Change estimate
Time Change Estimate
Decision Made by and Date
Justification Description
Table 13: Change Control Register
Project Title Project NumberProject Manager: Dr Andrew Kimmance
Change number
Description of change Date received
Date evaluated
Date approved
Date completed
Page | 45
KAIA Development Project Project Management Plan
12 Quality Assurance & Quality Control
The primary objective of the Project Quality Plan is to satisfy the client and meet all the
technical requirements of the project in a professional manner. The purpose of the
Project Quality Plan is to ensure all resources are focused on the quality of work. Quality
Control (QC) refers to the execution of the Quality Assurance (QA) program. QA is
conducted during the project development cycle. QA takes detailed technical
requirements and project objectives and applies a set of measurable methodologies and
standards to ensure that explicit requirements are met, objectives are achieved and the
product is free of defects while being in compliance with prevailing standards. The QC
program encompasses all operations to ensure that all phases of the design and related
work are technically correct, properly documents and all resources are focused on the
quality of the work so that deliverables are of the standard sought by the client and
strictly conform to the appropriate internationally recognised protocols.
12.1 Project Quality Plan
Project Quality Plan (PQP) has been developed and tailored for the KAIA development
Project for the aim of satisfying the clients, and to meet all the technical requirements of
the project in a professional manner. ZFP management is totally committed to total
quality management for all projects, large or small and for all works accomplished under
our name whether the work is done by our own employees or by subcontractors
The PQP is a mechanism that will highlight an actual or potential quality problem before
it causes significant hindrance, confusion or delay. The plan will initiate a systemic
process, which will contain or eliminate quality problems thus ensuring that the project is
not disrupted and remains on time and to budget. The PQP is an integral part of ZFP’s
Page | 46
KAIA Development Project Project Management Plan
KAIA development project strategy to ensure that we can achieve our primary goals, as
mentioned at the start of this document. The key sections of the Project Quality Plan is
summarised below and includes the following key elements:
Competence and expertise of the staff
Strict adherence to internationally accepted standards, protocols and practices
Consistent use of Relevant Standard Drafting Procedures
Adequate supervision of all technical work by management and senior personnel
MANUAL TITLE: PROJECT WORK PLAN Doc Ref:
DOCUMENT TITLE:Fast Track ‘Design and Engineering Service for the King Abdul Aziz International Airport Development Project’ KAIA, Jeddah.
Issue No.: 1
Page: 41 of 48
Written by: Dr AGK (7165) Approved by: BMH (2180)
12.2 Quality Control
All deliverables and other significant design information shall be checked, reviewed and
authorised in accordance with the process shown in Figure 10 prior to issue. This
verification will provide assurance that the deliverables meet the requirements of the
design standards and any customer requirements are met and any additional changes
incorporate risk mitigation and approval. The series of checks is as follows:
Single Discipline Check – in-discipline check undertaken by a member of the design
team prior to issue for inter-discipline check.
Inter-Discipline Check – three weeks before formal issue of a deliverable to SBG, it
will be checked by all disciplines. Comments will be returned after two weeks.
Technical Review – no later than 10 working days prior to submission, each drawing
or series of drawings and documents will be checked for technical content, accuracy
and completeness by the Design Lead or approved delegate.
ZFP recognize that quality assurance is an on-going inter disciplinary function involving
commitment from each member of the project. We know that the responsibility for
Page | 47
KAIA Development Project Project Management Plan
quality assurance and quality control must extend to all levels and divisions within our
organization. We insist that all our management and supervisory personnel make sure
that Engineers, CADD Operators, Draughts men, Technicians, Technical Secretaries
and all other staff members under their technical and administrative control scrupulously
follow ZFP’s quality assurance and quality control programs at all times and for all
projects.
Page | 48
KAIA Development Project Project Management Plan
Figure 20: Project Quality Plan (designed By Dr Andrews)
Page | 49
Zuhair Fayez Partnership Consultants شركة زهير فايز ومشاركوه لإلستشاراتArchitecture, Engineering and Information Systems عمارة - هندسة – نظم معلومات
_______________________________________________________________________________ 966 2 6129955+ فاكس: 966 2 6129999 – المملكة العربية السعودية - هاتف : +21422 جدة 5445ص . ب:
P. Box 5445 Jeddah 21422 – Saudi Arabia - Tel: +966 2 6129999 Fax: 966 2 6129955
KAIA Development Project Project Management Plan
12.3 Quality Control Checks – Authority and Responsibility
While experience provides the grounding forces for progress, it is the dedications of our
team of professionals that enable us to excel. ZFP’s Quality Assurance and Quality
Control system not only defines the objectives of Quality Assurance but also spells out in
clear terms the authorities and responsibilities of each person involved in the project.
Each Project Manager has the ultimate authority and responsibility for the quality of work
under taken in their area of jurisdiction. Disciplined Engineer Leads are also responsible
for their own quality of work with the project manager being overall responsible for the
quality of the project as a whole. The Lead Engineers and the quality assurance
manager are responsible to check the quality of the project outputs to ensure that all
relevant specifications, codes and standards have been followed in letter and spirit.
12.4 Key Elements of QA/QC Program
ZFP’s QA/QC Program places particular emphasis on the following major aspects of
Quality Assurances and Quality Control.
To make sure that only qualified and well-experienced personnel are put to work
on the project from the start through to the completion of the project.
Staff members are to feel appreciated, with appropriate remuneration offered for
meritorious work and exceptional performance.
All facilities required for smooth and uninterrupted performance on the project are
made available to the project working team.
Compliance to Client’s procedures in terms of quantities and dates of submittals
are strictly adhered to.
Timely resolution of any comments made by the Client to their satisfaction while
ensuring project requirements are met.
Co-ordination and interfaces with all agencies associated with the project
Holding regular progress meetings within the company to resolve any bottlenecks
in order to make sure that the project is completed as per the agreed schedule.
Page | 50
KAIA Development Project Project Management Plan
12.5 Project Quality Audit Program
The project quality audit program includes the planning, conducting, reporting of the
audit findings, corrective/preventive action plan and follow up. For this project it is
planned to conduct quality audits at 30% and 90% of project progress. The QA manger
is responsible to plan for these audits and to notify auditors and the audited with a
detailed audit schedule including the audit date, time and scope.
12.6 Design Calculations
Design calculations are an integral part of any design project. The accuracy and
reliability of design calculations are essential to ensure design work is based on sound
engineering practices and correct design parameters. Design calculations are the
foundation of any project and it is imperative that due care and attention is given to their
formulation. Their correct computation will ensure the client’s requirements are fully
satisfied and any structure once in situ will be able to function correctly in its
environment. There will be large variations in the requirement of design calculations
depending on the type and nature of the discipline. The respective discipline engineers
working on the airport development project will perform design calculations. However, it
is the Lead Engineers’ responsibility to review all calculations before submitting anything
to the client.
The Lead Engineer will review any calculation to see if they have been performed in
accordance with the requirements of the project ensuring the correctness of the basis
and criteria adopted for the calculation, and the references that have been made for
using different design parameters. Calculations that a Lead Engineer believes warrant
comment will be brought to the notice of the concerned engineer to resolve the issue. If
there is not a satisfactory resolution then the Lead Engineer will bring this to the
attention of the Technical Project Director or Manager for his advice.
The responsibility of checking design calculations will follow a three-step process:
The Originator – The engineer who performs the calculation
The Supervisor – The discipline Lead Engineer
Team Leader – The Project Manager or the Project coordinator
Page | 51
KAIA Development Project Project Management Plan
The design calculations will be checked to ensure that the following steps have been
considered:
Compliance with design guidelines
Compliance with the design code requirements
Applicability of assumptions
Providing all necessary references
Correctness of design loads, equipment ratings and other parameters
Proper selection and optimization of engineering system (VE)
Applicability and proper use of design equations and methodology
Sanity check of results to identify gross errors
Proper selection of designed sections, reinforcement, connection details,
materials, equipment, etc.
Applicability of design to ease of construction
Correctness of computations
Completeness and clarify of calculations
12.7 Design Drawings
For engineering items, facilities or projects that shall be ultimately constructed or
operated, the development and presentation of proper drawings play a very important
role in the success of the project. Just as in the case for design calculations, drawings
will also be prepared and finalized by the team responsible. Each member of the team
will have to make a thorough check of each drawing before handing it over to their
colleague and will have to sign each drawing. The checking of drawings should take into
consideration the following:
Presentation of technical contents
Conformance to design calculations
Correctness of technical information
Completeness of information
Compliance with drafting standards
Proper lay-out
Consistency and clarity
Page | 52
KAIA Development Project Project Management Plan
Completeness of notes
Completeness of reference drawings
Correctness of title block information
The responsibility of checking design drawings will be based on the following three-step
process:
The Originator – The engineer who performs the design
The Supervisor – The discipline lead engineer
Team Leader – The Quality Assurance Manager or Project Manager
13 Transition and Closure Plan
Optimal success for this project – realisation of the project purpose - requires delivery of
a quality product resulting in satisfied customers and conducting a deliberate closure –
including an effective “hand-off” to the subsequent phase (construction) and team. Key
parts of the closure plan are:
1. Transition Points
This project will be transferred to the project Construction Office at the
completion of the design stage.
2. Acceptance of Work
The work will be accepted after all formal reviews are complete.
3. Demobilise staff and resources.
The next project for the Design team will be identified one-month prior to the Ad
date for this project. Team members will transition to the new project as their
individual tasks are completed.
4. Close technical elements of the project
All of the activities, steps and requirements for demobilising, returning or
terminating facilities, equipment and services will be complete.
5. Project closure meeting of ZFP design and management team
Expectations
Lessons learned from this project - Based on the requirements of the KAIA
Lessons Learned process, establish specific project team activities and
responsibilities for identifying, documenting, reporting and compiling Lessons
Page | 53
KAIA Development Project Project Management Plan
Learned during the course of the project and, as each transition point is reached,
compiling and reporting the complete Lessons Learned file for the appropriate
area or phase of the work.
6. Evaluate, reward and recognise team members.
Review requirements and policies regarding rewards and recognition with
Region/Organisation management.
Based on the work, the conditions under which it will be performed, and the roles,
responsibilities and performance expectations of team members, identify “target
Performance metrics in key areas that is critical to project success. Develop a
budget around the appropriate awards and targets.
7. Archive project material
What – Review current archiving requirements with Region/Organisation
management and administrators and determine the specific Archiving
requirements for the project.
How – Develop specific instructions for the project Team on Record-keeping,
Document
Management and Preparation for Archiving during the course of the project.
Include instructions for maintaining files, sequestering original documents, dates
and project information on documents, copying documents, and the maintenance
of document logs.
Based on Transition events, develop file structures that provide the capability of
preparing the appropriate files for archiving as each transition event is achieved
14 Work Plan Endorsement Statement
By committing to this project plan the project management Team Members and
Specialty Groups agree to undertake the duties, responsibilities and directives that it
contains. We the undersigned endorse this Project Management Work Plan and are
committed to actively supporting it. We accept responsibility for fulfilling any aspect of
the plan that applies to us, including providing resources, actively participating, and
effectively communicating. We know what to do and are prepared to act. Our
endorsement is an active and positive statement that ZFP are committed to fulfilling the
responsibilities designated in this Project Management Work Plan.
Page | 54
KAIA Development Project Project Management Plan
MANUAL TITLE: PROJECT WORK PLAN Doc Ref:
DOCUMENT TITLE:Fast Track ‘Design and Engineering Service for the King Abdul Aziz International Airport Development Project’ KAIA, Jeddah.
Issue No.: 1
Page: 48 of 48
Written by: Dr AGK (7165) Approved by: BMH (2180)
Page | 55
ANDREW G. KIMMANCEProject Director & Technical Manger Transportation and Aviation DepartmentZuhair Fayez Partnership Consultants
HAZIM M. ABDULWAHIDExecutive Director Transportation and Aviation DepartmentZuhair Fayez Partnership Consultants
BASIM M. A. HASABALLAHDirector of Aviation ProgrammeTransportation and Aviation DepartmentZuhair Fayez Partnership Consultants
ADEL WEHBISenior Project Director Transportation and Aviation DepartmentZuhair Fayez Partnership Consultants
Zuhair Fayez Partnership Consultants شركة زهير فايز ومشاركوه لإلستشاراتArchitecture, Engineering and Information Systems عمارة - هندسة – نظم معلومات
_______________________________________________________________________________ 966 2 6129955+ فاكس: 966 2 6129999 – المملكة العربية السعودية - هاتف : +21422 جدة 5445ص . ب:
P. Box 5445 Jeddah 21422 – Saudi Arabia - Tel: +966 2 6129999 Fax: 966 2 6129955