HONOLULU RAIL TRANSIT PROJECT June 2020 MONTHLY PROGRESS REPORT www.HonoluluTransit.org
128

June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Sep 29, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

 

 

HONOLULU RAIL TRANSIT PROJECT 

 

 

June 2020 MONTHLY PROGRESS REPORT 

  

   

www.HonoluluTransit.org  

  

Page 2: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

2 | P a g e

DISCLAIMER NOTICE This document is disseminated under the sponsorship of the United States Department of Transportation, Federal Transit Administration (FTA), in the interest of information exchange. The United States Government assumes no liability for the contents or use thereof. The United States Government does not endorse products or manufacturers. Any trade or manufacturers' names appear herein solely because they are considered essential to the contents of the report.

NO RELIANCE BY THIRD PARTIES This report and all subsidiary reports are prepared solely for the FTA, and should not be relied upon by any party, except the FTA, its Project Management Oversight Contractors (PMOC), and the Honolulu Authority for Rapid Transportation (HART) Board of Directors, in accordance with the purpose as described in the next section.

REPORT FORMAT AND FOCUS This document is submitted in compliance with the terms of FTA Contract No. DTFT60-09-D-00012, Task Order No. 2. Its purpose is to provide information and data to assist the FTA as it continually monitors HART's technical capability and capacity to execute a project efficiently and effectively, and hence, whether HART continues to be ready to receive federal funds for further project development. This document covers the project and quality management activities on the Honolulu Rail Transit Project managed by HART as the project sponsor and partially financed by the FTA under the Full Funding Grant Agreement (FFGA). Concurrent non-project activities and other items not covered by the FFGA may not be included.

INFORMATION REGARDING FORWARD-LOOKING STATEMENTS This document includes forward-looking information. The words "believe”, "anticipate", "expect", "intend", "aim", "plan", "predict", "continue", "assume", "positioned", "may", "will", "should", "shall", "risk" and any other similar expressions that are predictions of or indicate future events and future trends identifies forward-looking information. Forward-looking information includes all matters that are not historical facts. Readers should not place undue reliance on forward-looking information because it involves known and unknown risks, uncertainties and other factors that are in many cases beyond HART's control. By its nature, forward-looking information involves risks and uncertainties because it relates to events and depends on circumstances that may or may not occur in the future. Forward-looking information is not a guarantee of future performance, and HART's actual results of operations, financial condition, and the development of the industry in which it operates may differ materially from those made in or suggested by forward-looking information contained in this document. The cautionary statements set forth above should be considered in connection with any subsequent forward-looking information that HART, or persons acting on its behalf, may issue. Factors that may cause HART's actual results to differ materially from those expressed or implied by the forward-looking statements in this document include but are not limited to the risks described in HART's annual report. For projects funded through the FTA's New Starts program, the FTA and its PMOC use a risk-based assessment process to review and validate a project sponsor's budget and schedule. Any results of an FTA or PMOC risk-based assessment represent a "snapshot in time" for a particular project under the conditions known at that same point in time. The status of any assessment may be altered at any time by new information, changes in circumstances, or further developments in the project. Furthermore, any forward looking statements contained in this document are made as of the date of this report, and HART does not undertake any obligation to update publicly or to revise any of the included forward-looking statements, whether as a result of new information, future events or otherwise, except as expressly required by law. ON THE COVER: Left: Guideway construction on the eastern section of the alignment. Upper Right: Construction at the Honolulu International Airport Station site. Lower Right: West Loch Station construction.

Page 3: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

3 | P a g e

Table of Contents LIST OF ACRONYMS .......................................................................................................................................................................... 4 PROJECT MAP ................................................................................................................................................................................... 9 1 SUMMARY .............................................................................................................................................................................. 10 2 OVERALL PROJECT PROGRESS AND FINANCIALS ................................................................................................................... 13

2.1 Project Progress .................................................................................................................................................... 13 2.2 Project Budget ...................................................................................................................................................... 15 2.3 Project Funding ..................................................................................................................................................... 16

3 SCHEDULE .............................................................................................................................................................................. 18 4 CONTRACT STATUS ................................................................................................................................................................ 22

4.1 System-wide .......................................................................................................................................................... 24 4.2 Section I – West O'ahu/Farrington Highway: East Kapolei to Pearl Highlands ..................................................... 38 4.3 Section II – Kamehameha Highway: Pearl Highlands to Aloha Stadium ............................................................... 50 4.4 Section III – Airport: Aloha Stadium to Middle Street Transit Center Station ...................................................... 59 4.5 Section IV – City Center: Middle Street Transit Center Station to Ala Moana Center .......................................... 62 4.6 Professional Services ............................................................................................................................................. 70 4.7 Contract Status by Contract Packaging Plan (CPP) Number ................................................................................. 82

5 OVERALL PROJECT-WIDE ACTIVITIES ..................................................................................................................................... 84 5.1 Overall Key Issues ................................................................................................................................................. 84 5.2 Permits .................................................................................................................................................................. 85 5.3 Hawai'i Department of Transportation (HDOT) Agreements ............................................................................... 85 5.4 Utility Agreements ................................................................................................................................................ 86 5.5 Right-of-Way ......................................................................................................................................................... 88

6 MANAGEMENT AND ADMINISTRATIVE UPDATES ................................................................................................................. 97 6.1 Safety and Security (S&S) ...................................................................................................................................... 97 6.2 Quality Management .......................................................................................................................................... 101 6.3 Buy America Compliance (49 CFR 661 and 49 CFR 663) ..................................................................................... 103 6.4 Disadvantaged Business Enterprise (DBE) .......................................................................................................... 103 6.5 Art-in-Transit (AIT) Program ............................................................................................................................... 104 6.6 Planning and Environment .................................................................................................................................. 105 6.7 Risk Management ............................................................................................................................................... 107 6.8 Construction Claims ............................................................................................................................................ 115 6.9 Community Outreach .......................................................................................................................................... 115 6.10 Staffing ................................................................................................................................................................ 116 6.11 HART Baseline Plans and Procedures Status List ................................................................................................ 118 6.12 Readiness and Activation .................................................................................................................................... 121

APPENDICES ................................................................................................................................................................................. 123 A. Project Costs by SCC – Level 2 ............................................................................................................................ 124 B. Core Accountability Items Including Major Issues .............................................................................................. 126 C. Construction Progress Interim Opening ............................................................................................................. 127 D. Project Organization Chart ................................................................................................................................. 128

Table of Figures Figure 1. Overall Project Progress (% Complete) ..................................................................................................................................... 13 Figure 2. Construction Progress (% Complete) ........................................................................................................................................ 13 Figure 3. Design Progress (% Complete) .................................................................................................................................................. 14 Figure 4. Planned vs. Received Project Funding ...................................................................................................................................... 16 Figure 5. New Starts Drawdown by Federal Fiscal Year ........................................................................................................................... 17 Figure 6. HRTP Master Project Schedule Summary (MPSS) ..................................................................................................................... 21 Figure 7. Right-of-Way Status for the Parcels .......................................................................................................................................... 89 Figure 8. Relocation Status for the Occupants ......................................................................................................................................... 89 Figure 9. Temporary Construction Easements and Utility ....................................................................................................................... 90 Figure 10. Inter-Governmental Agreement Status .................................................................................................................................. 90 Figure 11. Cost Probability Curve, June 2020 Risk Data ......................................................................................................................... 113 Figure 12. Schedule Probability Curve, June 2020 Risk Data ................................................................................................................. 114 Figure 13. Staffing Activities .................................................................................................................................................................. 117

Page 4: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

4 | P a g e

A&E Architect/Engineer AAN Accepted as Noted

AANR Accepted as noted, resubmit AC Asphalt Concrete

ACB Articulated Concrete Block ACHP Advisory Council on Historic Preservation

ACI Application Centric Infrastructure ACS Access Control System ADA Americans with Disabilities Act AFA Air Force Association AFE Authorized for Expenditure AG Attorney General

AGS Airport Guideway and Stations AIS Archaeological Inventory Survey AIT Art-in-Transit ALS Aloha Stadium Station

AMP Archaeological Monitoring Plan ANR Accepted as Noted–Resubmit APE Area of Potential Effect API Application Program Interface APS Auxiliary Power Supply

APTA American Public Transportation Association ARRA American Recovery and Reinvestment Act

ASG Airport Station Group ASI Architect Supplemental Information

ASTM American Society for Testing and Materials ASU Airport Section Utilities ATB Asphalt Treated Base

ATFAC Active Transportation and Food Access Committee ATC Automatic Train Control ATO Automatic Train Operation ATP Automatic Train Protection ATS Automatic Train Supervision AVA Anil Verma Associates, Inc. AVS Address Verification Systems

AW0 Assigned Weight, Empty Vehicle (rail car weight with no passengers) AW3 Assigned Weight, Crush Load (empty weight plus crush load of

standees) BA Buy America

BAC Buy America Compliance BACM Buy America Compliance Matrix BAFO Best and Final Offer

BANCT Best Available Noise Control Technology BAP Buy America Plan

BART Bay Area Rapid Transit BCS Balanced Cantilever System

BFMP Bus Fleet Management Plan BFS Budget and Fiscal Services BIC Ball in Court

BLNR Board of Land and Natural Resources BLS Blue Light Station

BMP Best Management Practice BOC Backup Operations Center BOD Board of Directors BOH Bank of Hawaii BPS Baseline Project Schedule BUE Bottom-Up Estimate

BUEG Back-up Emergency Generator BUILD Better Utilizing Investments to Leverage Development

BWS Board of Water Supply C2C Cost to Cure C&C City and County CAD Computer-Aided Design

CAM Construction Access Milestone CAP Corrective Action Plan CAR Corrective Actions

Cat Ex Categorical Exclusion CC2 City Center Phase 2 CC3 City Center Phase 3 CCC Contract Change Committee ccd Consecutive Calendar Days

CCGS City Center Guideway and Stations CCH City and County of Honolulu

CCO Contract Change Order CCTV Closed Circuit Television CCUG City Center Section Utilities and Guideway CCUR City Center Utilities Relocation

CDC Compendium of Design Criteria CDL Commercial Driver License CDR Conceptual Design Review

CDRL Contract Document Requirements List CEB Civil Engineering Branch CEI Construction Engineering and Inspection CEL Certifiable Elements List

CFM Configuration Management CFMP Configuration Management Plan

CFO Chief Financial Officer CHB Car History Book CIC Communication Interface Cabinet CID Customer Installation Department CIL Certifiable Items List CIP Cast-in-place CJA Condon‐Johnson & Associates

CLOMR Conditional Letter of Map Revision CLR Cultural Landscape Report

CLSM Controlled Low-strength Material CM Construction Manager

CMP Construction Management Plan CMS Contract Management System CMU Concrete Masonry Unit

CNMMP Construction Noise Mitigation and Monitoring Plan CO Change Order

COI Conflict of Interest COMMs Communications CONRAC Consolidated Rental Car Facility

COO Chief Operating Officer COR Corporation Counsel

CORP Central Oahu Regional Park CP Contractor Proposed

CPC Cost Proposals by Consultant CPM Critical Path Method CPO Chief Procurement Officer CPP Contract Packaging Plan

CR Consolidated Resolution CRM Customer-Relationship Management

CRMS Customer Relational Management System CROE Construction Right-of-Entry CRRB Car Readiness Review Board

CSC Core Systems Contractor CSCC Construction Specification Conformance Checklist

CSD Department of Customer Services CSDBOM Core System Design-Build-Operate-Maintain

CSL Cross Hole Sonic Logging CSOC Core Systems Oversight Consultant CSSC Core System Support Consultant

CSSM Construction Safety and Security Manager CSSP Construction Safety & Security Plan

CST Customer Service Terminal CTP Central Test Procedure CTS Communications Transmission System CW Contract-Wide

CWA Clean Water Act CWR Continuous Welded Rail

CWRM Commission on Water Resource Management CZM Coastal Zone Management D&C Design & Construction

DAGS Department of Accounting & General Services DAV Disabled American Veterans

DB Design-Build DBB Design-Bid-Build DBE Disadvantaged Business Enterprise

DBEDT Department of Business, Economic Development and Tourism DBF Design-Build-Finance

DBFOM Design-Build-Finance-Operate-Maintain DBOM Design-Build-Operate-Maintain DCAB Disability and Communication Access Board

LIST OF ACRONYMS

Page 5: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

5 | P a g e

DCCA Department of Commerce and Consumer Affairs DCCC Design Criteria Conformance Checklists DCN Design Change Notice

DD Definitive Design DDC Department of Design and Construction

DDC-MED Department of Design & Construction-Mechanical & Electrical Division

DED Deputy Executive Director DES Department of Environmental Services

DF Direct Fixation DFF Direct Fixation Fastener

DFIM Design Furnish Install Maintain DFM Department of Facility Maintenance

DHHL Department of Hawaiian Homelands DHR Department of Human Resources DIT Department of Information Technology

DKSG Dillingham and Kaka'ako Station Group DLIR Hawai'i Department of Labor and Industrial Relations

DLNR Department of Land and Natural Resources DOE Department of Education DOH Department of Health DOJ Department of Justice DOL Department of Labor DOT Department of Transportation DPM Deputy Project Managers DPP Department of Planning and Permitting DPR Department of Parks and Recreation DPS Department of Public Safety DRH D.R. Horton

DS Downstream DSDC Design Services During Construction

DTS Department of Transportation Services DTU Dillingham Temporary Utilities DUF Division of Urban Forestry

DURP Department of Urban and Regional Planning DVT Design Verification Test E&E Elevators and Escalators E&O Errors and Omissions

EA Environmental Assessment EAC Estimate at Completion

EB East Bound EC Environmental Compliance

ECP Environmental Compliance Plan ED-CEO Executive Director and Chief Executive Officer

EDD Executive Decision Document E/E Elevator/Escalator EEC Elevators & Escalators Contractor

EHE-EHMP Environmental Hazard Evaluation and Environmental Hazard Management Plan

EIS Environmental Impact Statement EJ Expansion Joint

EKP East Kapolei EMC Electromagnetic Compatibility EMF Electromagnetic Forces EMI Electromagnetic Interference

EMP Emergency Management Panel EMR Elevator Machine Room EMT Electrical Metallic Tubing ENV City and County of Honolulu Department of Environmental Services

EOM End of Month EOR Engineer of Record EOS Electrically Operated Switch EPA Environmental Protection Agency EPB Emergency Push Button ERD Environmental Review Documents ESA Environmental Site Assessment ETA Estimated Time of Arrival ETC Estimate to Complete EV Expected Value

EVC Electronic Vehicle Counter FAA Federal Aviation Administration FACI First Article Configuration Inspection

FAI First Article Inspection FAR Floor Area Ratios

FAT Factory Acceptance Tests FC Fare Collection

FCC Federal Communications Commission FCN Field Change Notice FCU Fan Coil Units

FD Final Design FDAS Fire Detection Alarm System

FDC Field Design Change FDR Final Design Review FEIS Final Environmental Impact Statement

FEMA Federal Emergency Management Agency FFC Fixed Facility Contractor

FFGA Full Funding Grant Agreement FHB First Hawaiian Bank

FHSG Farrington Highway Station Group FHWA Federal Highway Administration

FISC Fleet and Industrial Supply Center FIT Field Integration Test

FLSWG Fire/Life-Safety Working Group FM Force Main

FMB Fasi Municipal Building FMEA Failure Modes and Effects Analysis

FMECA Failure Modes, Effects, and Criticality Analysis FO Fiber Optic

FOCN Fiber Optic Communication Network FOM Finding of Merit/No Merit

FP Fix Panel FPM Fix Panel Mono FPO Federal Preservation Officer FRB Failure Review Board FSC Fare Systems Contract FTA Federal Transit Administration FTB Fluidized Thermal Backfill FTE Full-Time Equivalent FUT Functional Unit Testing FWS Fish and Wildlife Service

FY Fiscal Year GAT Great Aleutian Tsunami GBS Gap Breaker Station GDR Geotechnical Data Report GEC General Engineering Consultant GER Geotechnical Engineering Report GET General Excise and Use Tax GGP General Growth Properties GIS Geographic Information System

GOE Grant of Easement GPR Ground Penetrating Radar GRP Glass Reinforced Plastic GSA General Services Administration

GT General Terms GW Guideway HA Hazard Analysis

HABS Historic American Buildings Survey HACBED Hawai‘i Alliance for Community-Based Economic Development

HAER Historic American Engineering Record HALS Historic American Landscape Survey HAR Hawai‘i Administrative Rules

HART Honolulu Authority for Rapid Transportation HCC Honolulu Community College

HCDA Hawai‘i Community Development Authority HCS Historic Context Studies

HCSD Hawai'i Capital Special District HDCC Hawaiian Dredging Construction Company HDD Horizontal Directional Drilling

HDOE Hawai'i Department of Education HDOH Hawai'i Department of Health HDOT Hawai'i Department of Transportation

HDOT-A Hawai'i Department of Transportation Airports Division HDPE High-density polyethylene HECO Hawaiian Electric Company

HEI High Energy Inc. HFD Honolulu Fire Department HH Handhole

HHC Howard Hughes Corp

Page 6: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

6 | P a g e

HHF Historic Hawai'i Foundation HHFDC Hawaii Housing Finance & Development Corporation

HHM Hardy Heck Moore HHPRB Hawai'i Historic Places Review Board

HIA Honolulu International Airport HIE Hawaii Independent Energy

HILT Hawaiian Islands Land Trust HIOSH Hawaii Occupational Safety and Health Division

HOP Ho'opili HP Historic Preservation

HPC Historic Preservation Committee HPCA Historic Preservation Certification Application

HPCAT Historic Preservation & Cultural Awareness Training HPD Honolulu Police Department HPF Historic Preservation Fund HPL Horizon Partners Ltd. HPU Hawai‘i Pacific University HRH Hitachi Rail Honolulu Joint Venture

HRHP Hawai'i Register of Historic Places HRI Hitachi Rail Italy

HRR Heat Release Rate HRTP Honolulu Rail Transit Project HRU Hitachi Rail USA, Inc.

HSNWG Hawaiian Station Naming Working Group HSQE Health, Safety, Quality and Environment

HSSQE Health Safety Security Quality and Environment HTI Hawaiian Telcom HTL Hazard Tracking Log HV High Voltage

HVAC Heating, Ventilation and Air Conditioning I&T Inspection & Testing

IAMR Interstate Access Modification Report IBEW International Brotherhood of Electrical Workers

IC Interim Certification ICCS Integrated Communications Control System ICD Interface Control Documents ICE Independent Cost Estimate

ICM Interface Control Manual ICWG Interim Certification Working Group

IDIQ Indefinite Delivery/Indefinite Quantity IDS Intrusion Detection System IFB Issued for Bid IFC Issued for Construction

IJ Isolation Joint IMP Interface Management Plan

INMS Integrated Network Management System I/O Interim Opening

IOMP Intermediate Operations and Maintenance Period IP Implementing Procedures

IRTP Individual Role Training Plans ITP Inspection and Test Plan ITS Intelligent Transportation Systems IVR Interactive Voice Response

JB Junction Box JTMC Joint Traffic Management Center JTMS Joint Traffic Management System JU&O Joint Use & Occupancy JUOA Joint Use and Occupancy Agreement

JV Joint Venture KCC Kapi‘olani Community College

KCDD Kaka'ako Community Development District KCH Kanehili Cultural Hui KHG Kamehameha Highway Guideway KHR Kamehameha Highway Resurfacing

KHSG Kamehameha Highway Station Group KIWC Kiewit Infrastructure West Company KKJV Kiewit/Kobayashi Joint Venture

KPI Key Performance Indicator KVIBE Kalihi Valley Instructional Bike Exchange KVM Keyboard Monitor Mouse

L+E Lea +Elliott LCC Leeward Community College LCP Local Control Panel LD Lagoon Drive

LDS Latter Day Saints LEED Leadership in Energy and Environmental Design

LF Linear Feet LOO Letter of Offer

LOTB Log of Test Borings LPR License Plate Reader LRV Light Rail Vehicle

LT Load Test LTC Load Tap Changer LV Low Voltage

LVPS Low Voltage Power Supply MAI Mason Architects MCY Makai Casting Yard MDS Mobile Data System MED Mechanical/Electrical Division MEP Mechanical, Electrical and Plumbing MH Manhole

MIM Manufacture-Install-Maintain MIP Manufacturing and Inspection Plans

MITT Multimodal Integration Technical Team MMIS Maintenance Management Information System MMP Mitigation Monitoring Program MOA Memorandum of Agreement MOS Minimum Operable Segment MOT Maintenance of Traffic MOU Memorandum of Understanding

MOW Maintenance of Way MPD Multiple Property Documentation MPIS Master Project Integrated Schedule MPS Master Project Schedule

MPSS Master Project Schedule Summary MPV Multiple Purpose Vehicle MPY Makai Precast Yard MS4 Municipal Separate Storm Sewer System

MSDS Material Safety Data Sheet MSE Mechanically Stabilized Earth MSF Maintenance and Storage Facility MSP Maintenance Service Plan

MSTC Middle Street Transit Center MSTCS Middle Street Transit Center Station

MTM Modern Track Machineries MV Medium Voltage

NAICS North American Industry Classification System NCE Non-Conformance Evaluation NCR Non-Conformance Report NDC Notice of Design Change

NEPA National Environmental Policy Act NFPA National Fire Protection Association NGO Non-governmental Organization NHL National Historic Landmark NOI Notice of Intent

NPDES National Pollutant Discharge Elimination System NPS National Park Service

NPW Non-Potable Waterline NR National Register

NRHP National Register of Historic Places NSM Negotiation Strategy Memo NTE Not to Exceed NTP Notice to Proceed NTS Network Time Server

NUC Next Unit of Computing O&M Operations and Maintenance

OahuMPO Oahu Metropolitan Planning Organization OCC Operations Control Center

OCCC Oahu Community Correctional Center OCCL Office of Conservation and Coastal Lands OCIP Owner-Controlled Insurance Program ODC Other Direct Costs

OEQC Office of Environmental Quality Control OH Overhead

OHA Office of Hawaiian Affairs OIBC O'ahu Island Burial Council

OIC Officer-in-Charge OIL Open Items List

Page 7: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

7 | P a g e

OIP Order of Immediate Possession OMP Operation and Management Plan

OMPO Oahu Metropolitan Planning Organization OP Oversight Procedure

OR&L Oahu Railway & Land Co. ORCC Operational Readiness Conformance Checklist

OSB Operations and Servicing Building OSHA Occupational Safety and Health Administration

OSIT On-Site Inspection Test OSM Owner Supplied Materials

OTDR Optical Time Domain Reflectometer OTR One-Time Review OTS Oahu Transit Services

OTW Oceanic Time Warner OTWC Oceanic Time Warner Cable OWG Operation Working Group

P3 Public-Private Partnership PA Programmatic Agreement

PAIS Programmatic Agreement Implementation Schedule PARs Preventative Actions PAT Production Acceptance Test

PB Parsons Brinckerhoff, Inc. PCCP Portland Cement Concrete Pavement

PCI Payment Card Industry PCN Potential Change Notice PCY Precast Yard PD Position Description

PDR Preliminary Design Review PE Preliminary Engineering PF Power Frequency

PFP Project Financial Plan PGC Pacific Guardian Center PHA Preliminary Hazard Analysis

PHGTC Pearl Highlands Parking Garage and Transit Center PHL Pearl Highlands Station

PHNB Pearl Harbor Naval Base PHPR Pearl Highlands Park and Ride

PHPTR Pearl Highlands Parking Structure, Transit Center and Ramp H2R1 PHS Pearl Harbor Station

PI Public Involvement PICM Project Interface Control Manual

PID Parcel Identification Number PIG Permitted Interaction Group PIM Project Interface Manager PIP Public Involvement Plan PIS Passenger Information Systems

PLA Project Labor Agreement PLO Priority-Listed Offerors PLR Pearlridge Station PM Project Managers

PMC Project Management Consultant PMIM Project Management and Interface Management PMO Project Management Oversight

PMOC Project Management Oversight Contractor PMP Project Management Plan

PMSC Program Management Support Consultant PNR Park-and-Ride POC Project Oversight Committee POP Period of Performance POS Point of Sales PPE Personal Protective Equipment

PRTCC Pre-revenue Testing Conform Checklist PSC Personal Services Contract PSG Platform Screen Gate

PSGS Platform Screen Gate System PSIT Pre-shipment Inspection Test PSS Public Sector Solutions PT Post-tensioned

PTG Parsons Transportation Group PUA Possession and Use Agreements PUC Public Utilities Commission PUP Property Utilization Plan

PV Passenger Vehicle QA Quality Assurance

QAM Quality Assurance Manager QAP Quality Assurance Plan

QC Quality Control QMP Quality Management Plan QMS Quality Management System QTF Quality Task Force QTO Quantity Takeoff R&A Readiness and Activation R&R Revise & Re-submit

RA Risk Assessment RAC Rail Activation Committee

RAMP Real Estate Acquisition Management Plan RAP Rail Activation Plan RAT Routine Acceptance Test

RC Reinforced Concrete RCMP Risk and Contingency Management Plan

RCP Reinforced Concrete Pipe RE Resident Engineer

READ Real Estate Acquisition Database REC Real Estate Consultant RFB Request for Bids RFC Request for Change

RFCC Request for Change from Contractor RFCR Request for Change by HART RFHB Request for High Bids

RFI Request for Information RFID Request for Interface Data

RFMP Rail Fleet Management Plan RFP Request for Proposals RFQ Request for Qualifications RFV Request for Variance RHB Road and Highway Builders, LLC RLB Rider Levett Bucknall RLS Request for Legal Services

RMS Risk Management System RMTC R.M. Towill Corporation

RNR Revise and Resubmit ROC Rail Operations Center ROD Record of Decision ROE Right of Entry ROH Revised Ordinances of Honolulu

ROM Rough Order of Magnitude ROW Right-of-Way

RP Recovery Plan RR Risk Register

RSD Revenue Service Date RST Retail Sales Device Training RTE Request to Exceed Negotiation Strategy Memo Target

RTM Requirements Traceability Matrix RTSA Rapid Transit Stabilization Agreement

RVB+A Raul V. Bravo + Associates, Inc. S&S Safety and Security

S1 Segment 1 SA Supplemental Agreement

SAIS Supplemental Archaeological Inventory Survey SAMP System Assurance Monitoring Plan

SAT Site Acceptance Test SAV Shared Autonomous Vehicle

SC Substantial Completion SCADA Supervisory Control and Data Acquisition

SCAP Stream Channel Alteration Permit SCC Standard Cost Category SCH Satellite City Hall SDC Services During Construction

SHPD State Historic Preservation Division SHPO State Historic Preservation Officer

SIC Sandwich Isle Communications SIRP Safety Incident Review Panel

SIT System Integration Testing SITP System Integration and Test Plan SITR Site Inspection and Test Report

SL Street Light SLAN Secured Local Area Network

SLR Sea Level Rise

Page 8: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

8 | P a g e

SM Service Manager SMA Special Management Area SMS Structural Monitoring Solutions SOG Slab on Grade SOI Secretary of the Interior

SON Summary of Negotiations SOP Standard Operating Procedures

SOW Scope of Work SP Special Provisions

SQP Supplemental Quality Plan SS System Site

SSA System Service Availability SSC Safety Security Certification

SSCP Safety and Security Certification Plan SSCWG Safety and Security Certification Working Group

SSI Sensitive Security Information SSMP Safety and Security Management Plan SSRC Safety and Security Review Committee SSSP Site Safety Security Plan

STATCOM Static Synchronous Compensator STCC Specification Testing Conformance Checklists STCH Sustainable Transportation Coalition of Hawai‘i

STG Shimmick/Traylor/Granite, Joint Venture STP System Test Procedure

SUBD Subdivision Branch SUE Subsurface Utility Engineering

SuMo Sustainable Mobility SuMoLab Sustainable Mobility Lab

SWPPP Storm Water Pollution Prevention Plan SwRI Southwest Research Institute T&C Test & Commissioning

T&M Time and Material TAB Testing and Balancing TAC Transit Art Committee TAP Track Allocation Procedure TAT Transient Accommodation Tax

TC Train Control TCA Temporary Configuration Change

TCCR Train Control and Communications Room TCE Temporary Construction Easement TCO Temporary Certificate Occupancy TCP Traffic Control Plan TCS Train Control System

TDFM Travel Demand Forecasting Model TDM Transportation Demand Management

TES Traction Electrification System TIA Time Impact Analysis

TIGER Transportation Investment Generating Economic Recovery TIP Transportation Improvement Program

TMK Tax Map Key TMP Traffic Management Plan

TO Task Order TOC The Outdoor Circle TOD Transit-Oriented Development

TP Technical Provision TP&R Temporary Park & Ride TPBG Traction Power Backup Generator

TPBuGen Traction Power Backup Generator TPO Thermoplastic Polyolefin

TPSS Traction Power Substation TS Traffic Signal

TSA Transportation Security Administration TSI Transportation Safety Institute

TTSP Temporary Traffic Signal Plan TUT Temporary Utility Take TVA Threat and Vulnerability Assessment

TVM Ticket Vending Machine TWF Train Wash Facility UCA Utility Construction Agreement

UFRCRA Utility Facilities Relocation and Cost Reimbursement Agreement UG Underground UH University of Hawai'i

UHPRB UH West O‘ahu Park and Ride & UHWO Campus Road “B” UHWO University of Hawai'i West O'ahu

UL Underwriters Laboratories UPS Uninterruptible Power Supply URA Uniform Relocation Assistance and Real Property Acquisition

Policies Act USACE U.S. Army Corps of Engineers USDOE U.S. Department of Energy USDOL United States Department of Labor USDOT U.S. Department of Transportation

USN United States Navy USPS U.S. Postal Service

UST Underground Storage Tank UTR Under Technical Review VAR Volt-Ampere Reactive VCR Vertical Conduit Raceway

VE Value Engineering VECP Value Engineering Change Proposal

VISTA Volunteers in Service to America VMS Variable Message Sign VRC Vertical Raceway Column

VRCS Voice Radio Communication System VRF Variable Refrigerant Flow VTP Vehicle Test Procedure WA Work Area

WCS Wireless Communication System WHS Waipahu High School

WKM Walters, Kimoda, Motoda, Inc. WL West Loch

WLO West Loch WOEDA West Oahu Economic Development Association

WOFH West O'ahu/Farrington Highway WOSG West O'ahu Station Group

WQC Water Quality Certification WSS West Side Stations

WSSG West Side Stations Groups WTB Wheel Truing Building WTC Waipahu Transit Center WTP Wayside Test Procedure

WWB Wastewater Branch WWPS Wastewater pump station

WYL West Yard Lead YCB Yard Control Bungalow YKE Yogi Kwong Engineers YOE Year of Expenditure

Page 9: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

9 | P a g e

PROJECT MAP

Page 10: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

10 | P a g e

1 SUMMARY

REPORTING DATE AND SUBSEQUENT EVENTS This report was published on July 31, 2020, for the PMOC meeting scheduled for Aug. 12, 2020. Data is presented with a reporting cutoff

date of June 30, 2020, unless otherwise noted.

KEY ACTIVITIES IN JUNE Project Overview All seven of the trains that will be a part of the interim opening fleet are in the testing and commissioning phase. Segment 1 of the rail line is completely energized, and trains are actively being tested between Kualaka‘i (East Kapolei) Station and Hālawa (Aloha Stadium) Station. Record Column Foundation Constructed Airport Guideway and Stations (AGS) contractor Shimmick/Traylor/Granite, Joint Venture (STG) successfully constructed what is believed to be the world’s deepest and largest column foundation. At a depth of 357 feet, 4 inches, and measuring 10 feet in diameter, the column foundation is located in Kalihi Stream on Kamehameha Highway between Middle Street and Pu‘uhale Road. It will be used as a base for a column which will support the rail’s elevated guideway and the Kahauiki (Middle Street Transit Center) Station. The column’s depth at this location was needed to ensure that the station and guideway would be built on a solid underground foundation. Art Poster Contest At the June Honolulu Authority for Rapid Transportation (HART) Board of Directors meeting, HART recognized 12 winners of its 2020 Art Poster Contest. Nearly 90 entries were received, and posters were judged based on artistic merit, originality, and incorporation of the theme, “Welcome Aboard Next-Gen Riders,” which allowed submitters to highlight how enjoyable riding the trains will be.

COST (as of June 30, 2020)

Project Cost Summary ($ in millions)

Description Original FFGA

Budget Recovery Plan

Budget* Current Estimate at Completion (EAC)*

Incurred To Date

Project Capital Costs

Base Cost without Contingency $4,305 $7,312 $7,761 $4,306

Allocated Contingency $542 $765 $316** $0

Unallocated Contingency $102 $222 $88 $0

Total Project Capital Costs $4,949 $8,299 $8,165 $4,306

FFGA Finance Charges $173 $609 $547 $44

Total FFGA Project Costs $5,122 $8,908 $8,712 $4,350

Post-RSD Finance Charges $42 $231 $293 $0

Total Project Costs $5,164 $9,139 $9,005 $4,350 *Total Project Costs excludes Operations and Maintenance. **Please refer to the "Current Estimate at Completion" write up for further explanation.

Original FFGA Budget The Original FFGA Budget reflects the full build-out of the project as executed by the Full Funding Grant Agreement in December 2012. The contingency is a reserve to cover known and unknown, but anticipated, project execution costs and uncertainty due to risk factors such as unresolved design issues, unknown site conditions, schedule impacts and market fluctuations. The Original FFGA Budget reflects $644 million in total contingency.

Page 11: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

11 | P a g e

Recovery Plan Budget Total The approved Recovery Plan Project capital cost estimate is $8,299 million (excluding finance costs). The total project cost is $9,139 million, which includes post-Revenue Service Date (RSD) financing costs of $231 million and $8,908 million in FFGA project costs (which includes $765 million in allocated contingency, $222 million in unallocated contingency, and $609 million in financing costs). While this cost is $134 million greater than HART’s cost estimate of $8,165 million, HART has revised the Project cost estimate and identified the additional funding to meet the higher estimate. The Recovery Plan Budget reflects $987 million of total contingency or 13% of the base cost estimate which reflects available funding capacity. Based on FTA requirements on contingency for the current phase of the project, the 13% is sufficient reserve to cover against the risk of cost increases during development of the project. Current Estimate at Completion (EAC) The current project capital Estimate at Completion (EAC) is $8,712 million, including $404 million in total contingency ($316 million in allocated contingency and $88 million in unallocated contingency) and $547 million in financing costs. The total project costs including post-Revenue Service Date (RSD) financing costs of $293 million is $9,005 million. The total project contingency is based on a September 2026 RSD. At the May 2020 HART Board Project Oversight Committee meeting, a new EAC of $8,210 million, due to an increase in CCUR costs, was discussed. The CCUR costs have been incorporated this reporting period. HART is currently conducting an analysis of contingency levels per contract. The revised EAC will be reflected once the contingency analysis is completed. The Project budget continues to be forecast below the Recovery Plan values. Incurred to Date The Incurred-to-date costs are cumulative through June 2020, and exclude third-party reimbursement costs. The $4,350 million to date represents 56% of the base Current EAC. The Incurred-to-date costs increased by $77 million for the period. SCHEDULE The progress reported in the table below provides percent complete based on construction and design contracts. The early and late plans are based on baseline schedules for active contracts and forecasts of future contracts.

Project Progress* Through June 26, 2020

Actual Early Plan Late Plan

Overall Project Progress 58.8% 69.8% 63%

Construction Progress 54.5% 66% 60%

Design Progress 80.6% 82.6% 79.7%

*Reported percentages complete are based on the Estimate at Completion for the MOS and

December 2025 RSD. HART will revise its progress curves further when the in-progress change orders are executed and remaining construction projects are awarded and baselined. This

revision is expected to lower the plan values.

PROGRESS REPORT SUMMARY OF CHANGES The following is a brief summary of major changes that have occurred from the previous month’s report. For more information and detail, please refer to the respective pages in the report. Contract Status Core Systems Contract (CSC)

o The projected completion of work date has changed from July 2025 to March 2026. Please see page 24. o The schedule status has changed from “On time for 2025 opening” to “On time for 2026 opening.” Please

see page 24.

Page 12: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

12 | P a g e

Traction Power Backup Generators o A contract page for the MI-940 Traction Power Backup Generators contract has been included. Please see

page 30-31.

Fare Collection System o The projected completion of design-build work date has changed from December 2025 to March 2026.

Please see page 34.

Farrington Highway Station Group (FHSG) o The contract substantial completion date has changed from January 2019 to June 2020 due to a change

order. Please see page 45. o The projected completion of work date has changed from July 2020 to September 2020. Please see page

45. o The schedule status has changed from “18 month behind” to “3 months behind.” Please see page 45.

Kamehameha Highway Station Group (KHSG)

o The current contract value amount has increased due to a change order. Please see page 52.

Kamehameha Highway Resurfacing (KHR) o The projected completion of work date has changed from July 2020 to August 2020. Please see page 55. o The schedule status has changed from “10 months behind” to “11 months behind.” Please see page 55.

Airport Section Guideway and Stations (AGS)

o The current contract value amount has increased due to a change order. Please see page 59.

City Center Utilities Relocation (CCUR) Indefinite Delivery/Indefinite Quantity (IDIQ) o The projected completion of relocation work date has changed from December 2022 to February 2023.

Please see page 65. o The schedule status has changed from “7 months behind” to “9 months behind.” Please see page 65.

Page 13: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

13 | P a g e

2 OVERALL PROJECT PROGRESS AND FINANCIALS

2.1 Project Progress (data as of June 26, 2020) Reported percentages complete are based on the Estimate at Completion for the MOS and December 2025 RSD. HART will revise its progress curves further when the in-progress change orders are executed and remaining construction projects are awarded and baselined. This revision is expected to lower the plan values. Note:

Actual = Actual cost of work performed, based on reported work-in-place.

Early Plan = Earliest dates activities can begin and finish, based on logic and durations used in the schedule.

Late Plan = Latest dates activities can begin and finish and not have an impact on completion date, based on logic and durations used in the schedule.

Figure 1. Overall Project Progress (% Complete)

At present "overall" project progress is based on the weighted value progress of the individual construction and design contracts (Design-Build [DB], Design-Bid-Build [DBB], Design-Build-Operate-Maintain [DBOM], Elevator/Escalator Manufacture-Install-Test-Maintain [MIM], Final Design [FD] and DB-DBOM design levels of effort), not including City or non-design consultant labor.

Figure 2. Construction Progress (% Complete)

Overall construction progress is based on the weighted average progress of the individual DBB and E/E MIM construction contracts and the DB-DBOM construction levels of effort, not including consultant Construction Engineering and Inspection (CEI) services.

Page 14: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

14 | P a g e

Figure 3. Design Progress (% Complete)

Overall design progress is based on the weighted average progress of the individual FD contracts and the design levels of effort of the DB and DBOM construction contracts, not including City or non-design consultant labor.

Page 15: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

15 | P a g e

2.2 Project Budget (data as of June 30, 2020)

Project Cost Summary ($ in millions)

Description Original FFGA

Budget Recovery Plan

Budget* Current Estimate at Completion (EAC)*

Project Capital Costs

Base Cost without Contingency $4,305 $7,312 $7,761

Allocated Contingency $542 $765 $316**

Unallocated Contingency $102 $222 $88

Total Project Capital Costs $4,949 $8,299 $8,165

FFGA Finance Charges $173 $609 $547

Total FFGA Project Costs $5,122 $8,908 $8,712

Post-RSD Finance Charges $42 $231 $293

Total Project Costs $5,164 $9,139 $9,005 *Total Project Costs excludes Operations and Maintenance. **Please refer to the write up below for further explanation.

The Original FFGA Budget reflects the full build-out of the project as executed by the Full Funding Grant Agreement in December 2012. The approved Recovery Plan Project capital cost estimate is $8,299 million (excluding finance costs). While this cost is $134 million greater than HART’s cost estimate of $8,165 million, HART has revised the Project cost estimate and identified the additional funding to meet the higher estimate. At the May 2020 HART Board Project Oversight Committee meeting, a new EAC of $8,210 million, due to an increase in CCUR costs, was discussed. The CCUR costs have been incorporated this reporting period. HART is currently conducting an analysis of contingency levels per contract. The revised EAC will be reflected once the contingency analysis is completed. The Project budget continues to be forecast below the Recovery Plan values. Total project contingency decreased to $404 million ($316 million in allocated contingency and $88 million in unallocated contingency) since last updated.

Contingency Drawdown Curve

Date Sep-2020 Mar-2021 Dec-2021 Feb-2023 Jun-2025 Sep-2026

Milestone P3 NTP Interim

Opening

DB450 Construction

Complete

DBB511 Construction

Complete

P3 Construction

Complete RSD

FTA Minimum Level ($M)

638

546

462

375

174

32

HART Minimum Level ($M)

504

412

328

241

108

8

Page 16: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

16 | P a g e

2.3 Project Funding

Figure 4. Planned vs. Received Project Funding

Planned vs. Received Project Funding

Funding Source

Pre-FFGA Project1

Project Funding Total

Project

2007 - 2009 Actuals

Received

Planned2 2009 -

Present Actuals

Received

2007 - Present Actuals

Received

Actuals Received in June 2020 ($YOE M)

Beginning Project Cash Balance3 - 298 298 - -

Interest Income on Cash Balance5 7 1 9 16 0

FTA Section 5309 New Starts Revenue4 - 1,550 806 806 -

ARRA Funds - 4 4 4 -

EPA Brownfields Grant (FY2018-FY2021)6 - 1 0 0 -

Net General Excise Tax (GET) Surcharge revenues FY2010-FY2031 378 5,990 2,350 2,728

-

Transient Accommodation Tax (TAT) revenue FY2018-FY2031 - 1,182 130 130

-

City Subsidy - HART Administration FY2018-FY2031 - 214 69 69 -

Total 385 9,240 3,667 3,754 0

1 GET and Interest Income received during Pre-Preliminary Engineering (pre-PE) phase prior to entry into PE. 2 Updated to Chapter 6 - Project Finance, Figure 6-2 of HART's Approved Recovery Plan (for beginning cash balance, GET, TAT, grant revenue, city subsidy and interest income).

3 Beginning Project Cash Balance at Entry into Preliminary Engineering (PE) on October 16, 2009 (the FFGA Project start date) = Pre-PE GET, investment and miscellaneous income minus pre-PE expenditures. The $298 million is included in the Pre-FFGA actual amounts received between 2007-2009 of $378 million.

4 New Starts Funds Obligated Through Federal Fiscal Year 2014 Totals $806.3 million. 5 Interest Income received in June 2020 - $257,057.68

6 EPA $900,000 Brownfields Grant must be used by 12/31/2020 - to plan and subsidize the environmental cleanup activities.

EPA Brownfields Grant revenue received to date - $55,260.87

Page 17: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

17 | P a g e

Figure 5. New Starts Drawdown by Federal Fiscal Year

New Starts Grant Information by Federal Fiscal Year (Amounts in Italics are Pending)

Federal Fiscal Year (FFY) Allocation

FTA Obligated Amounts

Actual Drawdown Amounts to Date

Available Balance FFGA Base Case Cash Flow

2008 $15,190,000 $15,190,000 $0

2009 $19,800,000 $19,800,000 $0

2010 $30,000,000 $30,000,000 $0

2011 $55,000,000 $55,000,000 $0 $20,607,242

2012 $200,000,000 $200,000,000 $0 $99,382,758

2013 $236,277,358 $236,277,358 $0 $258,280,277

2014 $250,000,000 $249,991,376 $8,624 $441,719,724

2015* $250,000,000 $0 $0 $0

2016* $250,000,000 $0 $0 $0

2017* $243,732,642 $0 $0 $0

2018 $0 $0 $0 $0

2019 $0 $0 $0 $0

2020 $0 $0 $100,000,000 $100,000,000

2021 $0 $0 $150,000,000 $150,000,000

2022 $0 $0 $150,000,000 $150,000,000

2023 $0 $0 $150,000,000 $150,000,000

2024 $0 $0 $100,000,000 $100,000,000

2025 $0 $0 $50,000,000 $50,000,000

2026 $0 $0 $43,732,642 $30,010,000

Total $1,550,000,000 $806,258,734 $743,741,266 $1,550,000,000

Note: * The funds for years 2015, 2016 and 2017 have not yet been obligated. The amounts represent the allocation for the fiscal year noted in the first column. No moneys can be drawn on awards not yet obligated.

Page 18: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

18 | P a g e

3 SCHEDULE (data as of June 26, 2020)

Critical Path Analysis Interim Revenue Service Date is planned for no earlier than March 31, 2021. The Projected Revenue Service date,

currently forecasted for March 4, 2021, defines operational readiness of the system. The Department of Transportation Services (DTS) makes the final determination of passenger service.

o In the June 2020 update, forecasted completion of operational readiness has been extended by 9 days due to a later forecasted canopy completion date at Aloha Stadium Station.

o The critical path for the Operational Readiness of the passenger rail system from East Kapolei Station to Aloha Stadium Station is the fabrication, delivery, and installation of canopy arms, as well as the follow-on communications cables installation at Aloha Stadium Station, and Core Systems testing activities.

o For the near critical path, activities include communications subsystem acceptance, as well as Fire Detection Alarm System (FDAS) testing and the Functional testing of the west side stations.

The Recovery Plan Revenue Service Date (RSD) is Sept. 1, 2026. The Projected Revenue Service date, currently

forecasted for March 16, 2026, defines operational readiness of the system. DTS makes the final determination of passenger service.

o Given uncertainties arising as a result of the COVID-19 pandemic and the need to incorporate proper buffer in access dates provided to the P3 developers in order to de-risk the project, the operational readiness of the final segment, previously forecasted as Dec. 31, 2025, continues to be March 16, 2026. Actual schedule will be set once a contract with the P3 developer has been established.

o The critical path begins with completion of Kapalama utility bridge design, construction of the Kapalama utility bridge, and utility relocation work (AT&T, Hawaiian Electric Company [HECO] 46kV, Hawaiian Telcom, Oceanic Time Warner Cable) in City Center Utilities Relocation (CCUR) Area 1C. After the utility relocation is complete, drilled shafts, columns and segments for Area 1C continue into platform and structure construction for Kapalama Station, followed by Core Systems installation and testing.

o The near critical path includes completion of design packages and permit approvals in Area 1B, Right Of Way acquisition of a property required for utility relocation work, and procurement of the Public-Private Partnership (P3)/City Center Guideway and Stations (CCGS) contract.

Three-Month Look Ahead Station construction for the west station groups continues to include the following:

o Canopies: The Aloha Stadium canopy steel is scheduled to be received mid-July and installed by mid-August. The Aloha Stadium tension fabric is forecasted to be installed in mid-October. These activities are on the critical path for Kamehameha Highway Station Group substantial completion.

o University of Hawai‘i West O‘ahu (UHWO) Temporary Park and Ride (“Road B”): Close out outstanding submittals and quality test reports. Finalize verification of remaining punchlist items. Road B lighting testing and irrigation testing are pending HECO meter installation.

o Elevators and Escalators: Complete installation of Pearlridge Station Escalators #1 and 2. Complete installation of Pearl Highlands Station Elevators #1 and 2 and remaining escalators. Complete installation of Aloha Stadium Station Elevators #1 and 2. Continue to perform commissioning activities in preparation for State elevator inspections. Continue construction interface for Airport Guideway and Stations (AGS).

CSC

o Continue System Integration Testing in the Functional Section. o Complete Supervisory Control and Data Acquisition (SCADA) installation for Aloha Stadium Station and

commence SCADA testing at West O‘ahu and Farrington Highway Station Groups. o Install and test Platform Screen Gate System (PSGS) at Kamehameha Highway Station Group (KHSG). o Complete COMM (Closed Circuit Television [CCTV]/Access Control System [ACS]-Intrusion Detection System

[IDS]) installation and testing at West O‘ahu and Farrington Highway Station Groups.

Page 19: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

19 | P a g e

o Complete installations of the Mobile Data System (MDS) network for the west side stations. o Complete Segment 1 Wayside Automatic Train Control (ATC) testing. o Seven (7) Segment 1 trains will be ready for system integration testing.

AGS

o Reach A: Complete utility relocations. Complete traffic signal conduit work on Kamehameha Highway at Halawa, Radford and Center Drive. Complete installation of the sidewalk, curb, and gutter at Halawa Drive and Kamehameha Highway.

o Reach B: Complete wet utility relocations. Continue column and pier cap work. Continue span erection. o Reach C: Continue guideway foundations. Continue column and pier cap work. Complete Aolele Street and

Nimitz roadwork. Complete underground utility relocations for street lights, water and drainage. Continue span erection.

o Reach D: Complete infrastructure for Hawaiian Telcom (HTI) and Oceanic Time Warner Cable (OTWC) communication utilities relocations on Ualena Street with the implementation of nightly Maintenance of Traffic (MOT). Continue utility relocations for street lights, water and drainage. Continue column and pier cap work.

o Reach E: Continue guideway foundations. Continue column and pier cap work. Continue column rebar erection and formwork. Continue segment erection. Continue utility relocation work. Complete HECO Zone 9 construction.

o Pearl Harbor Station (Makalapa): Complete platform girder reinforcing steel installation. Complete underground site utilities. Continue electrical rough-in work.

o Airport Station (Lelepaua): Complete foundations for elevator and escalator pits. Continue underground conduit installation and plumbing. Begin Train Control and Communications Room (TCCR) foundations.

o Lagoon Station (Āhua): Complete TCCR building construction. Complete station structural steel erection. Complete site utility, water, sewer, and storm connections.

o Middle Street Station (Kahauiki): Begin electrical rough-in work at TCCR. Excavate station entrance and elevator pit. Complete foundations for elevator and escalator pits. Commence station structural steel erection. Complete pedestrian bridge column hammerhead construction.

CCUR

o Area 1A (Middle to Mokauea): Order HECO long lead 138kV utility poles. Start 12kV critical dry utility infrastructure work. Complete AT&T communication infrastructure work. Start 138kV underground (UG) infrastructure work.

o Area 1B (Mokauea to Waiakamilo): Finalize wet and dry design and receive permits for wet utility task order 02 and dry utility task order 22. Complete critical Area 1B drainage box culvert modifications. Commence Dillingham 1B controlled access. Finalize Kapalama Stream crossing design.

o Area 1C (Waiakamilo to Ka‘aahi): Finalize dry design and receive permits for dry utility task orders 25 and 26. Commence Dillingham 1C controlled access.

o Area 2 (Ka‘aahi): Complete all wet utility relocations. Complete all dry utility jet grouting soil stabilization work. Continue 12kV critical dry utility infrastructure work. Start communication infrastructure work.

o Area 3 (Nimitz): Complete all wet utility relocations. Finalize dry design and receive permits for dry utility task order 27. Complete all dry utility jet grouting soil stabilization work. Start dry utility infrastructure work for 12kV and 25kV.

o Area 4 (Halekauwila): Finalize dry design and receive permits for dry utility task order 32. Complete dry utility jet grouting soil stabilization work.

o Area 5 (Queen): Finalize dry design and receive permits for dry utility task order 17. Complete all wet utility relocations. Complete all dry utility jet grouting soil stabilization work. Start 12kV dry utility infrastructure work.

o Area 6 (Kona): Finalize dry design and receive permits for dry utility task order 28. Complete all dry utility jet grouting soil stabilization work. Start 12kV critical dry utility infrastructure work.

CCGS

o Technical and price submittal.

Page 20: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

20 | P a g e

Key Schedule Issues AGS’ Shimmick/Traylor/Granite, Joint Venture (STG) mitigation schedule has been Accepted as Noted and is

currently showing a December 2021 completion date. The contractor is required to respond to review comments and uphold commitments for schedule improvement over the next few months as outlined in the conditional acceptance letter in order to alleviate further delays, as well as work towards the current contractual completion date.

The AGS contractor submitted a Time Impact Analysis (TIA) schedule in October, requesting a schedule extension and time-related overhead costs. Construction Engineering and Inspection (CEI) and HART reviewed and responded to the TIA schedule.

Schedule Contingency Drawdown Curve

The graph has been updated from the May 2020 Monthly Progress Report to match the current contingency.

The critical path begins with completion of Kapalama utility bridge design, construction of the Kapalama utility bridge, and utility relocation work (AT&T, HECO 46kV, Hawaiian Telcom, Oceanic Time Warner Cable) in CCUR Area 1C. After the utility relocation is complete, drilled shafts, columns and segments for Area 1C continue into platform and structure construction for Kapalama Station, followed by Core Systems installation and component testing and Full System Integration Testing, Trial Run and Pre-Revenue Service Demonstration achieving operational readiness date for Segment 3. The assumed CCGS schedule has not been revised. Secondary mitigation is being explored and will be implemented.

Page 21: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

21 | P a g e

Figure 6. HRTP Master Project Schedule Summary (MPSS) The Master Program Summary Schedule reflects currently approved schedule end dates for contracts that have been awarded, and planned dates for future contracts.

Page 22: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

22 | P a g e

4 CONTRACT STATUS

Contracts in Procurement

Overview Awarded Contracts:

o HOLO Fare System Fiber contract was awarded on June 30, 2020 to Hawaiian Telcom, Inc. o Passenger WiFi System contract was awarded on June 30, 2020 to Icomera US, Inc.

Active Procurements:

o City Center Guideway and Stations / Pearl Highlands Design-Build Finance Operate and Maintain Request for Proposals (RFP) qualifications proposals in response to RFP Part 1 were received on April 12, 2019. HART released RFP Part 2 to the priority list of offerors on May 3, 2019. Due to recent COVID-19 events, the offerors requested additional time to prepare their proposals; the due date for the technical proposals has been extended to July 2020. As such, the Notice to Proceed (NTP) date has moved to September 2020.

o Art-in-Transit: HART continues its negotiations with the highest-ranked artists for each of the stations. To date, twelve (12) contracts have been awarded.

o HDOT/DTS Traffic Management Coordination Request for Qualifications was issued on Jan. 17, 2020. Statements of Qualification submissions were received on Feb. 19, 2020 and are currently being evaluated.

o Outside Claims Counsel Request for Sealed Proposals was re-issued on April 13, 2020 as a multi-award solicitation to avoid potential conflicts of interest. Sealed proposals were received on May 18, 2020 and are currently being evaluated.

o Archaeological & Cultural Monitoring “II” Request for Sealed Proposals was issued on March 9, 2020. Sealed proposals were received on April 9, 2020 and are currently being evaluated.

o Real Estate Contractor “III” Request for Sealed Proposals was issued on April 20, 2020. Sealed proposals were received on May 22, 2020 and are currently being evaluated.

o Guideway Bridge Inspection Request for Qualifications was issued on April 13, 2020. Sealed Statements of Qualification were received on May 19, 2020 and are currently being evaluated.

o Independent Financial Auditor “III” Request for Sealed Proposals was issued on May 4, 2020. Sealed proposals were received on June 3, 2020 and are currently being evaluated.

o Marketing Research Services – Data Collection Tools for Public Involvement Request for Quotes was issued on June 2, 2020. Sealed quotes were received on June 18, 2020 and are currently being evaluated.

Active Procurements

Contract Code

Contract Name Advertise

Date

Bids or Proposals

Due Issue NTP

Projected Contract

Substantial Completion

Date

AP-00 Art-in-Transit May 09 '13

12 contracts awarded;

active procurement for remaining

stations

Staggered Staggered

DB-550 City Center Guideway and Stations / Pearl Highlands Design-Build Finance Operate And Maintain (DBFOM)

Sep 28 ‘18 Apr 12 ‘19 (RFP Pt. 1)

Sep ‘20 TBD

MM-915 HDOT/DTS Traffic Management Coordination

Jan 17 ‘20 Feb 19 ‘20 July‘20 TBD

MM-980 Outside Claims Counsel Apr 13 ‘20 May 18 ‘20 July ‘20 TBD

MM-960 Archaeological & Cultural Monitoring “II”

Mar 09 ‘20 Apr 09 ‘20 TBD TBD

Page 23: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

23 | P a g e

Active Procurements

Contract Code

Contract Name Advertise

Date

Bids or Proposals

Due Issue NTP

Projected Contract

Substantial Completion

Date

TBD Real Estate Contractor “III” Apr 20 ‘20 May 22 ‘20 July ‘20 TBD

TBD Guideway Bridge Inspection Apr 13 ‘20 May 19 ‘20 July ‘20 TBD

TBD Independent Financial Auditor “III” May 4 ‘20 June 3 ‘20 July‘20 TBD

HRT-201 Marketing Research Services – Data Collection Tools for Public Involvement Program

June 2 ‘20 June 18 ‘20 July ‘20 TBD

New awards/ contracts/NTP issued

Contract Code

Contract Name

Advertise Date

Due Date Contractor

Award Issue NTP

Term/Substantial Completion

Award Amount Contract Date

TBD HOLO Fare System Fiber

May 15 ‘20 June 9 ‘20

Hawaiian Telcom,

Inc. June 30 ‘20 TBD TBD $309,110.40

DBOM-920

Passenger WiFi System

Jan 17 ‘20 Mar 03 ‘20 Icomera US, Inc.

June 30 ‘20 TBD TBD $1,219,858.00

Upcoming Procurement Under Evaluation

Contract Code Contract Name Issue Date

Procurement Duration

Proposal Due Date Award

DBB-511 City Center Utility Relocation II July ‘20 2 Months Sept ‘20 Oct ‘20

HRT-201 HART Canvasser and Counselor Database Maintenance

July ‘20 1 Month Aug‘20 Sept ‘20

TBD LCC Switchgear July ‘20 1 Month Aug ‘20 Sept ‘20

TBD Keone’ae Station Park and Ride & Pouhala Station Makai Entrance (PRME)

Nov ‘20 3 – 4 Months Feb ‘21 March ‘21

Page 24: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

24 | P a g e

4.1 System-wide

A. Core Systems Contract (CSC) CPP No.: DBOM-920 DBOM Contractor: Hitachi Rail Honolulu Joint Venture (HRH) Contract Start Date: January 2012 Contract Substantial Completion: January 1, 2025 Projected Completion of Work: March 2026

Project Description: A design, build, operate and maintain contract to provide rail passenger vehicles, automated train control system, traction electrification system (TES), communication systems, passenger platform screen gates (PSGs), and operation and maintenance of the Core Systems.

Design & Construction Vehicles Schedule Status

Physical % Complete 68.5% 77.5% On time for 2026

opening Early Plan* 86.4% 96.2%

Late Plan* 67.0% 57.0%

*Data as of June 26, 2020. The progress chart reflects early program expectations. Progress is being tracked against interim Construction Access Milestone dates, which show the project is "On-Time".

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $419,568

DBE % Attained: 0.054%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $209,736,373

None N/A ---

Cumulative Current Report $209,736,373

Original Contract: $573,782,793 Incurred-to-Date: $432,745,999

Current Contract Value¹: $783,519,166 Incurred in June: $10,168,750

Outstanding Issues: 8 Contractor CP Amount: $1,787,499

1Current Contract Value = Original contract value (excluding original O&M budget) + executed Change Orders

Page 25: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

25 | P a g e

KEY INDICATORS FOR 2021 INTERIM OPENING 1:

June 2020 July 2020 August 2020

Completion of Mobile Data System (MDS) network to East Kapolei (EKP): Completed

Completion of MDS network to Aloha Stadium Station (ALS): 40% Complete

Energization of 3rd Rail to ALS (Energize Pearlridge Station [PLR] Traction Power Substation [TPSS]): Completed

Completion of Secured Local Area Network (SLAN) network to PLR TPSS: Completed

Completion of PLR Supervisory Control and Data Acquisition (SCADA) TPSS: Completed

Start of TPSS Capability Test

Completion of PLR Platform Screen Gate System (PSGS): Installation in progress

Completion of Pearl Highlands Station (PHL) PSGS: 35% Complete

Train #9 Completion of onboard Automatic Train Control (ATC): Completed

Train #9 Completion of onboard Communications (COMM): 25% Complete

Train #8 Completion of onboard ATC: 80% Complete

Train #8 Completion of onboard COMM: Completed

Train # 13 Interim Certified for Dynamic Testing & Dynamic Test Completed: Completed

Train #13 Completion of onboard ATC

Train #13 Completion of onboard COMM

Train #14 Interim Certified for Dynamic Testing & Dynamic Test Completed: 80% Complete

Train #14 Completion of onboard ATC

Train #14 Completion of onboard COMM

Completion of Waipahu Transit Center (WTC) Fire Detection Alarm System (FDAS): Completed

Completion of University of Hawai‘i West O‘ahu (UHWO) FDAS: Target to complete on 07/02.

Completion of PHL FDAS

Completion of PLR FDAS

Completion of ALS FDAS

FDAS integration test at stations (EKP to ALS)

Completion of COMM Closed Circuit Television (CCTV) at Ho‘opili (HOP): 95% Complete

Completion of COMM Access Control System (ACS)-Intrusion Detection System (IDS) at HOP: 15% Complete

Completion of COMM Passenger Information Systems (PIS) at HOP: 30% Complete

Completion of COMM PIS at LCC: 30% Complete

Completion of COMM CCTV at UHWO: Installation in progress

Completion of COMM PIS at UHWO: Installation in progress

Completion of COMM ACS-IDS at UHWO: Installation in progress

Completion of COMM CCTV at PHL: Installation in progress

Page 26: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

26 | P a g e

June 2020 July 2020 August 2020

Completion of COMM CCTV at Leeward Community College (LCC): 95% Complete

Completion of COMM ACS-IDS at LCC: 15% Complete

Completion of COMM CCTV at West Loch (WLO): Installation substantially completed

Completion of COMM PIS at WLO: Installation substantially completed

Completion of COMM ACS-IDS at WLO: Installation in progress

Completion of COMM CCTV at WTC: Installation substantially completed

Completion of COMM PIS at WTC: Installation substantially completed

Completion of COMM ACS-IDS at WTC: Installation in progress

Completion of COMM CCTV at EKP: Installation in progress

Completion of COMM PIS at EKP: Installation in progress

Completion of COMM ACS-IDS at EKP: Installation in progress

Completion of COMM PIS at PHL: Installation in progress

Completion of COMM ACS-IDS at PHL: Installation in progress

Completion of COMM CCTV at PLR: Installation in progress

Completion of COMM PIS at PLR: Installation in progress

Completion of COMM ACS-IDS at PLR: Installation in progress

Completion of Station SCADA HOP: 50% Complete

Completion of Station SCADA WLO: 30% Complete

Completion of Station SCADA WTC: 30% Complete

Completion of Station SCADA LCC: 30% Complete

Completion of Station SCADA EKP: Installation in progress

Completion of Station SCADA UHWO: 30% Complete

Completion of Station SCADA PHL

Completion of Station SCADA PLR

Completion of Station SCADA ALS

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Design: Review of design submittals is ongoing. Focus is to close out

communications, passenger vehicles and Requirements Traceability Matrix (RTM) issues.

Continued coordination between HRH and the AGS contractor for integration of Core Systems requirements.

Manufacturing: Hitachi Rail USA, Inc. (HRU) is continuing with the production of

Train #15 through #18 in Pittsburg, CA. Train #7 is being delivered to the MSF with the last car expected

to arrive on July 13. This train is for Interim Opening (I/O) #2. Testing of ventilation hole retrofit continues on Train #3.

Look Ahead: Design: Close out of open comments to finalize Final

Design of all subsystems. Continue coordination between HRH and

FHSG/KHSG/AGS. Complete Communications Final Design.

Manufacturing: Passenger Vehicle truck fabrication – continue

truck frame and bolster delivery from Italy. Complete car shell fabrication activities in Italy.

Three car shells will be fabricated in Reggio Calabria to replace the car shell used for roof and floor fire re-test and to replace Train #1 and Train #2 car shells with the extrusion defect.

Page 27: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

27 | P a g e

Activities this Month (continued): Fleet retrofit is substantially completed in Trains #8 and #13.

Hitachi Rail Italy (HRI) is working on the fleet retrofit for Trains #12 and #14.

Train #1 has been shipped back to the Final Assembly Facility. Installation, Testing and Commissioning: HRH completed the integration test between PLR TPSS to the

Operations Control Center (OCC). HRH continues with installation of Blue Light Stations in the

stations. HRH completed installation of PSGS at PHL Station and started

the initial testing at this station. HRH continues with PSGS electrical installation in PLR Station. HRH continues with the remediation of corrosion issues with the

PSGS components. HRH continues inter-station ATC Wayside Test Procedure (WTP)

testing between PHL and ALS. HRH completed onboard ATC testing with Train #9. HRH continues with routine acceptance test for onboard ATC

equipment in Train #8. HRH substantially completed routine acceptance test for

onboard COMM equipment in Train #9. HRH continues with routine acceptance test for onboard COMM

equipment in Train #9. HRH achieved interim certification and completed train static

and dynamic testing for Train #13. Train #13 is ready for onboard ATC and COMM testing.

HRH continues with static acceptance test on Train #14. HRH continues with the communication system installation at

EKP, UHWO, HOP, WTC, LCC, PHL and PLR stations. HRH continues to test MDS poles 6-19 in the functional section

and expanded to energize and configure poles 1-5. HRH continues COMM acceptance test at HOP Station. HRH started COMM acceptance test at LCC, WTC and WLO

stations. HRH continues with cable and fiber termination to MDS poles 20

through 29. HRH completed installation and testing of FDAS systems at WTC. HRH substantially completed FDAS cable and device installation

at UHWO station. HRH continues with SCADA cable installation at UWHO and LCC

Stations. HRH powered up and tested SCADA cabinets in UHWO, HOP,

WLO, WTC and LCC. HRH continued train testing in the entire Segment 1 alignment

(EKP to ALS). HRH continues with MSF COMM acceptance test. HRH performed platform gap measurement for Americans with

Disabilities Act (ADA) compliance in the first 8 stations (EKP to PLR) with AW0 train.

HRH performed platform gap measurement for ADA compliance in 3 stations (HOP to WTC) with AW3 train.

Look Ahead (continued): Installation, Testing and Commissioning: Complete SCADA testing with peripheral devices

in the MSF, after installation is completed. Complete MSF COMM Acceptance Test. Complete PSGS Commissioning test at PHL, PLR

and ALS. Complete Vehicle Test Procedure, Central Test

Procedure, and System Test Procedure in Segment 1.

Continue System Integration Testing with train(s) in the Yard.

Continue System Integration Testing with train(s) in the Functional Section.

Complete the remediation of corrosion issues with the PSGS components.

Complete remaining ATC Wayside testing in Segment 1.

Complete Train #8, Train #9, Train #13 and Train #14 onboard ATC and onboard COMM testing.

Achieve Train #14 Interim Certificate for dynamic testing.

Continue SCADA and Blue Light Station (BLS) installation in the stations.

Start Blue Light Station testing in the stations. Continue SCADA testing in the stations. Continue TPSS COMM installation. Start testing with multiple trains in Segment 1.

Page 28: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

28 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

VMS Signs - AGS End of Platform

Vehicle Extended Warranty

Matcon Aug 2018 Lift Repair MSF

Changing of Vehicle "Square Key" Locks (square to triangle key)

Spare Parts

Pouhala (Waipahu) Makai Entrance

Automated Response to Loss of Traction Power

Increased CSC DB MOB Costs for IO#1

A P A A P A P P

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES: Interim Opening Fleet (7 trains) is on site. Interim Opening Fleet ready for System Integration Testing (3 of 7 trains are ready). Completion of System Integration Test. Trial Run.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT: Hitachi has indicated that the two remaining car shells that require replacement of the bolster assemblies due to

the aluminum extrusion defects, will be scrapped instead of repaired. Hitachi is in the process of ordering additional material for the fabrication of three (3) new car shells; one to replace the car shell used to expedite the floor and roof fire re-test and two to replace the car shells with extrusion defects.

End Car 1 of Train #12 was damaged (about 2.0 ft. long x ¾ in. wide x ¼ in. deep gouge on the left side, which did not penetrate the aluminum extrusion skin, and about ½ in. diameter penetration in the first set of the Door Panel on the right side of End Car 1) during transit from Pittsburg, CA to Honolulu, HI. Repair procedure is being developed.

CSC NCR Log (Issued by HRH)

Total Closed Open

HRH & Subs 58 57 1

Hitachi Rail 2,159 1,808 351

TOTAL 2,217 1,865 352

Page 29: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

29 | P a g e

TRAIN SCHEDULE:

Page 30: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

30 | P a g e

B. Traction Power Backup Generators CPP No.: MI-940 Contractor: PAC Electric Co., Inc. Contract Start Date: December 2019 Contract Substantial Completion: February 2021 Projected Completion of Work: February 2021 Project Description: Procurement of Traction Power Backup Generators, which are to be located at or near the Traction Power Substations (TPSSs) at the West Loch and Pearlridge passenger stations. The generators will provide the means for moving stranded trains into the HRTP passenger stations, in case of an island-wide or regional power outage event.

Progress Schedule Status

Physical % Complete 8.5%

On time Early Plan* 8.3%

Late Plan* 6.6% *Data as of June 26, 2020.

__________________________________________________________________________________________________ COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $0

None N/A ---

Cumulative Current Report $0

___________________________________________________________________________________________________ SCHEDULE:

Generators production to be completed early July 2020. Enclosures production to be completed early August 2020. Factory Acceptance Test to be completed end of August 2020. Generators onsite delivery to be completed in October 2020.

__________________________________________________________________________________________________ WORK PROGRESS: Activities this Month:

Working on project deliverables, such as Lift Plan and other documents.

Submitted 3 submittals to HART.

Look Ahead: Manufacturing of enclosures. Factory Acceptance Test

Original Contract: $8,965,000 Incurred-to-Date: $537,500

Current Contract Value¹: $8,965,000 Incurred in June: $537,500

Outstanding Issues: 1 Contractor CP Amount: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 31: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

31 | P a g e

Activities this Month (continued): Continued to interface with HRH regarding Medium

Voltage (MV) Switchgear Design, Relay Coordination Study, and site conditions.

Generators’ manufacturing in progress; 1 was completed at the end of June and another one is anticipated to be completed in early July.

__________________________________________________________________________________________________ KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Minor Field Work Allowance P

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal __________________________________________________________________________________________________ KEY MILESTONES: Factory Acceptance Test in August 2020. __________________________________________________________________________________________________ QUALITY MANAGEMENT:

Traction Power Backup Generators NCR Log (Issued by PAC Electric Co., Inc.)

Total NCRs Issued To Date Closed Open

0 0 0

Page 32: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

32 | P a g e

C. Elevators and Escalators Manufacture-Install-Maintain (MIM) CPP No.: MI-930 Contractor: Schindler Elevator Corporation Contract Start Date: August 2013 Contract Substantial Completion: May 2021 Projected Completion of Work: February 2024 (see the Schedule section below) Project Description: A contract to design, fabricate, install, test, commission, and maintain all elevators and escalators at all 21 stations.

Progress Schedule Status

Physical % Complete 47.7%

Just in Time** Early Plan* 58.3%

Late Plan* TBD *Data as of June 26, 2020. **The E&E schedule is dependent on other contractors' schedules. Actual release for manufacturing will be coordinated for a 'just in time' delivery.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $4,879,726

None N/A ---

Cumulative Current Report $4,879,726

_______________________________________________________________________________________________________

SCHEDULE: The Elevators and Escalators (E&E) contract substantial completion date is May 2021, based on the AGS contract

substantial completion date. The final completion date for the E&E contract will be based on the CCGS contract’s scheduled installation dates after award of the CCGS contract.

Original Contract: $50,982,714 Incurred-to-Date: $28,141,001

Current Contract Value¹: $55,862,440 Incurred in June²: $0

Outstanding Issues: 2 Contractor CP Amount: $106,154 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders

2Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system

Page 33: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

33 | P a g e

WORK PROGRESS: Activities this Month: Elevator CEI inspections are occurring for the WOSG and

FHSG to ensure that the required specifications for the State Inspections for elevators and escalators are met.

HART is continuing to coordinate with the AGS contractor and the E&E contractor to firm up required equipment installation dates.

At Pearlridge Station, Escalators #1 and #2 high-speed adjustments were completed.

At Pearl Highlands Station, Elevators #1 and #2 high-speed adjustments were completed.

At Aloha Stadium, installation of Elevators #1 and #2 are continuing.

In June, the State completed preliminary inspections at East Kapolei (all units) and will provide a punchlist for each. These punchlists will be shared with the station contractor so that these items can be addressed and corrected prior to the States final inspection and acceptance.

The State has completed Pre-inspections for all the equipment installed at WOSG and FHSG, so that when the Final inspections are called in, the acceptance should go smoothly.

Look Ahead: The E&E substantial completion date for the

remaining eight east-side stations will be established once the contract is awarded for the CCGS and the schedule for this contract is accepted.

At Pearl Highlands Station, final high-speed adjustments will be completed in:

o Escalators #3-#6 August 2020. At Aloha Stadium Station, final high-speed

adjustments will be completed in: o Elevators #1 and #2 July 2020.

Preliminary State Inspections for: o Pearl Highlands Station: Elevators #1

and #2, Escalators #1 and #2 – August 2020

o Pearl Highlands Station: Escalators #3-#6 – September 2020

o Pearlridge Station: all units – August 2020

o Aloha Stadium Station: Escalators #1 and #2 – August 2020

o Aloha Stadium Station: Elevators #1 and #2 – September 2020.

_______________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

EEC pre-operations maintenance delay

FCN Allowance

A P

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal

_______________________________________________________________________________________________________

KEY MILESTONES: Preventive maintenance requirements along with the required final testing is continuing for the elevators that

have been installed. Installation has continued at Aloha Stadium Station for the final 2 elevators, with anticipation of completion in July 2020.

State Pre-inspections on all of the equipment installed at WOSG and FHSG began in November 2019 and was completed in June 2020. This will facilitate the State Final Inspections which are required to allow the public to use the installed equipment.

_______________________________________________________________________________________________________

QUALITY MANAGEMENT:

Elevators and Escalators NCR Log (Issued by Schindler)

Total NCRs Issued To Date Closed Open

0 0 0

Page 34: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

34 | P a g e

D. Fare Collection System CPP No.: MI-900 Contractor: INIT, Innovations in Transportation, Inc. Contract Start Date: April 2016 Projected Completion of Design-Build Work: March 2026

Project Description: The fare collection system is a joint HART and City and County of Honolulu [Department of Transportation Services (DTS), Department of Information Technology (DIT), Budget and Fiscal Services (BFS)] project that will consist of a multi-modal, closed loop, account based smart card system. The Fare System vendor, INIT Innovations in Transportation, Inc., is responsible for design, manufacture, testing, installation and operation of the entire system inclusive of hardware and software. The rail portion of the project will consist of Ticket Vending Machines (TVMs) and fare gates at stations that accept smart cards which can also be used for payment on board TheBus and facilitate a seamless transfer between modes. Equipment and software to be used by both HART and the City and County will include transaction processing, fare equipment monitoring, and customer service systems, as well as a Data Warehouse. TheBus equipment will consist of stand-alone smart card readers on board.

Progress Schedule Status

Percent Complete 56.3% 12 Months Behind Milestone Schedule

Payment** Early Plan* 86.8%

Late Plan* 83.9% *Data as of June 26, 2020. Planned information is being evaluated based on the current (full-alignment) scope versus the revised requirements of the Interim Revenue Service completion date. **Although the contract is 12 months behind schedule, it does not impact the Interim Opening or the RSD.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $444,026

None N/A ---

Cumulative Current Report $444,026

_______________________________________________________________________________________________________

SCHEDULE: The projected completion of DB work date has changed to March 2026 to account for HART’s projected Revenue

Service Date of March 2026. Production Acceptance Test (PAT) for faregates and TVMS completed June 18, 2020. First station installation scheduled for July 7, 2020. Field Integration Test (FIT) still to be determined based on network installation and foreign staff availability on

island. Tentative schedule is Sept. 1, 2020.

Original Contract: $15,464,198 Incurred-to-Date: $7,570,108

Current Contract Value¹: $15,908,224 Incurred in June²: $0

Outstanding Issues: 4 Contractor CP Amount: $702,024 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders

2Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system

Page 35: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

35 | P a g e

WORK PROGRESS:

Activities this Month: Trained Waianae and Wahiawa Satellite City Hall (SCH) staff. Redrafted Amendment 9 for Rail Claim. Moved all language Interactive Voice Response (IVR) scripts to

test environment for review. Continued work on remaining language translations for the

website. Arranged container storage for containers 3-6 at the Pasha

yards. Provided PMOC and FTA with a fare systems briefing. Updated installation plans and coordinated the installation

schedule. Completed Finding of Merit/No Merit (FOM) and Negotiation

Strategy Memo (NSM) for Issue 18. Reviewed and commented on Failure Review Board (FRB). Reviewed Functional Unit Testing (FUT) Test Report and

approved. Created additional FIT cases for inclusion in vendor plan. Coordinated on-call request for concrete pours. Trouble shot user issues with Customer Service Terminal (CST)

and Customer-Relationship Management (CRM).

Look Ahead:

Begin installation at West Side Stations.

Arrange for Network fiber installation between Operations and Servicing Building (OSB) and Fasi Municipal Building (FMB).

Schedule installation for remaining TIMES retail locations and test 7-Eleven locations.

Implement Pilot changes. Confirm release of languages to website

and IVR. Certify FUT. Confirm FIT Test Plans.

_______________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Rail Restart

FDAS Bank Box and DIM Rail Clamps

Pilot Changes for Customers

Vendor Installation Work

A A A P

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________________________________________

KEY MILESTONES: Production Acceptance Testing June 2020. Equipment installation July 2020. Field Integration Testing September 2020.

_______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

Fare Collection NCR Log (Issued by INIT)

Total NCRs Issued To Date Closed Open

0 0 0

Page 36: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

36 | P a g e

E. On-Call Construction IV CPP No.: MM-949 Contractor: Royal Contracting Co., Ltd. Contract Start Date: January 2018 Contract Substantial Completion: January 2023 Projected Completion of Work: January 2023 Project Description: This is an on-call contract to perform a variety of construction services by issuance of Task Orders. The construction services to be provided will include, but are not limited to, maintenance, renovations to existing privately owned properties, demolition of buildings/structures, repairs to existing HART facilities, temporary utilities installations, utilities relocation, new construction projects or services, maintenance of roadways inclusive of, filling potholes, removing dead animals, landscape maintenance, repairing/replacing signage, and other such activities to HDOT and/or City and County of Honolulu standards, work in support of HART’s ongoing construction activities, and work in support of other HART contractors.

Progress Schedule Status

Physical % Complete* 93.0%

On Time Early Plan* 100%

Late Plan* TBD *Data as of June 26, 2020.

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

DBE Participation Task Orders

Actual DBE Participation: $0

Number of Task Orders Issued

Amount ($)

DBE % Attained: 0% Task Orders Previously Issued 73 $49,641,454

Task Orders Issued this Month 3 $1,155,956

Amendments to Task Orders 7 $1,611,427

Total Task Orders Issued 76 $52,408,837

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

SCHEDULE: The On-Call Contract is a Task Order based Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The work

consists of meeting the objectivities of HART’s Joint Use and Occupancy Agreements (JUOA) requirements, maintaining HART properties, performing Cost to Cure activities, and performing permanent utility relocation work. Each Task Order has its own start and finish date, and as such, there is no overall schedule requirements for the On-Call contract proper. The contract NTP was issued on Jan. 8, 2018 and ends on Jan. 7, 2023 with two one-year options.

Original Contract: $46,000,000 Incurred-to-Date: $38,728,685

Current Contract Value¹: $53,000,000 Incurred in June: $1,509,757

1Current Contract Value = Original contract value + executed Change Orders

Page 37: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

37 | P a g e

WORK PROGRESS: Activities this Month: Continued maintenance of the HDOT roadways along

Farrington Highway and Kamehameha Highway, per the JUOA.

Work at Cutter Dodge, Stuart Plaza and UH Urban Gardens was completed at the end of June; only punchlist items remain.

Continued to complete HDOT elements of work as required by the HDOT agreements.

Continued to work on AGS HECO Zone 9. HECO Zone 9 is made up of several independent duct banks, some of which are already completed.

Continued work at LCC on the Ka‘aahi Substation and storage area for HECO vehicles. Work is at 98% complete.

Completed work on AGS HECO Zone 8A. Completed Cost to Cure work at both Dillingham Plaza

and at Aala Tofu Co. on Kaaahi Street.

Look Ahead: Continue to maintain HDOT roadways, as required

by the JUOA. Complete punchlist item work at Cutter Dodge,

Stuart Plaza and UH Urban Gardens. Continue to complete HDOT elements of work as

required by the HDOT agreements. Complete infrastructure work in support of HECO

power line relocation at Kahi Mohala. Begin work to repair erosion damage at Kaloi

Channel and prevent erosion reoccurrence. Complete contamination mitigation at HART’s two

properties on Kaaahi Street.

_______________________________________________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font): Need to receive timely Right of Entry agreements.

Need to continue to have Maintenance of Traffic plans reviewed and accepted in a reasonable time frame. _______________________________________________________________________________________________________________________________________

KEY MILESTONES: The work at UH Urban Gardens – Cutter Dodge, completed in June, provides the required road widening at this

section of Kamehameha Highway. _______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

On-Call Construction IV NCR Log (Issued by Royal Contracting)

Total NCRs Issued To Date Closed Open

0 0 0

Page 38: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

38 | P a g e

4.2 Section I – West O'ahu/Farrington Highway: East Kapolei to Pearl Highlands

A. West O'ahu/Farrington Highway Guideway (WOFH) CPP No.: DB-120 DB Contractor: Kiewit Infrastructure West Company (KIWC) Contract Start Date: December 2009 Date of Substantial Completion Notification: December 13, 2018

Project Description: Design and construction of 6.8 miles of rail alignment, starting at the East Kapolei Station and ending at the Pearl Highlands Station.

Progress Schedule Status

Physical % Complete 100% Substantial Completion Obtained**

Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. **Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $17,119,976

DBE % Attained: 2.56%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $185,351,685

None N/A ---

Cumulative Current Report $185,351,685

_______________________________________________________________________________________________________

SCHEDULE: Acoustical Monitoring installation complete. Contract closeout – third quarter 2020.

_______________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Retention release routing.

Look Ahead: Route Contract Closeout Checklist for signature. Issue Final Acceptance letter, including the

Certificate and Release of Final Payment form.

Original Contract: $482,430,201 Incurred-to-Date: $667,781,886

Current Contract Value¹: $667,781,886 Incurred in June: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 39: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

39 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________

KEY MILESTONES: One-year project warranty period ended on Jan. 14, 2020.

_______________________________________________________________________________________________________

SUBSTANTIAL COMPLETION: Substantial Completion was Dec. 13, 2018.

_______________________________________________________________________________________________________

QUALITY MANAGEMENT:

WOFH NCR LOG (Issued by KIWC)

Total NCRs Issued to Date Closed Open

586 586 0

Page 40: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

40 | P a g e

B. University of Hawai‘i West O‘ahu (UHWO) Station Temporary Park-and-Ride & UHWO Campus Road “B” CPP No.: DBB-602 Contractor: Nan, Inc. Contract Start Date: December 2017 Contract Substantial Completion: July 2019 Completion of Work: January 2020 Project Description: The project consists of the construction of a temporary park & ride, Road “B” and associated site work in the vicinity of UH West O‘ahu Station. The project includes clearing, grubbing, erosion and dust control, grading and hauling, drainage, installation of underground and overhead utilities, installation of traffic signal, street lighting, and park & ride area electrical and communication systems, concrete curbs, sidewalks and wheelchair ramps, asphalt and concrete pavement structures, signing and striping, bus shelters, landscaping including installation of an irrigation system, and other appurtenances associated with roadway and park & ride facilities.

Progress Schedule Status

Physical % Complete 100% Work

Completed** Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. NTP issued Dec. 15, 2017. **Pending contract actions will extend contract completion date.

_______________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $108,454

DBE % Attained: 0.82%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $1,607,232

None N/A ---

Cumulative Current Report $1,607,232

_______________________________________________________________________________________________________________________________________

SCHEDULE: Substantial completion date is Oct. 23, 2019, per substantial completion letter dated Dec. 13, 2019. A change order is pending to compensate the contractor for time.

Original Contract: $11,589,300 Incurred-to-Date: $12,908,138

Current Contract Value¹: $13,196,532 Incurred in June²: $0

Outstanding Issues: 1 Contractor CP Amount: $710,115

1Current Contract Value = Original contract value + executed Change Orders 2Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system

Page 41: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

41 | P a g e

WORK PROGRESS: Activities this Month: Continued to verify completion of punchlist items. Continued verifying completion of contract

documentation. Continued closing of grading permit and stockpile

transfer.

Look Ahead: Coordinate Board of Water Supply (BWS) meter

installation for Road B and Temporary Park & Ride (TP&R).

Coordinate HECO meter installation at Road B to complete lights testing and irrigation.

Complete remaining concrete issues at sidewalk cul-de-sac, per City and County (C&C) Inspector punchlist items.

Remove concrete rubble stockpile, per Field Change Notice (FCN) 22, pending PVT facility acceptance.

_______________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Project Time Delay [establish new Contract Substantial Completion Date] A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________________________________________

KEY MILESTONES:

Install BWS meter for Temporary Park and Ride. Install HECO meter for Road B. Complete punchlist work – July 2020.

_______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

UHWO Station Temporary Park-and-Ride & UHWO Campus Road “B” NCR Log

(Issued by Nan)

Total NCRs Issued to Date Closed Open

5 1 4

Page 42: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

42 | P a g e

C. West O'ahu Station Group (WOSG) CPP No.: DBB-171 Contractor: Nan, Inc. Contract Start Date: October 2015 Contract Substantial Completion: January 31, 2020 Date of Substantial Completion: January 31, 2020

Project Description: The West O'ahu Station Group construction contract includes services to build three (3) transit stations along Kualaka'i Parkway and Farrington Highway. The stations are East Kapolei (EKP), UH West O'ahu (UHWO), and Ho'opili (HOP) Stations. In addition to the transit stations, operational ancillary buildings, a traction power substation, and adjacent areas are included in this project.

Progress Schedule Status

Physical % Complete 99.3%** Substantial Completion

Obtained Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. **Remaining work includes punchlist, contract change orders and closeout.

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $993,708

DBE % Attained: 1.13%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $32,026,202

None N/A --- ---

Cumulative Current Report $32,026,202

Original Contract: $56,088,470 Incurred-to-Date: $82,722,876

Current Contract Value¹: $88,114,672 Incurred in June: $610,431

Outstanding Issues: 4 Contractor CP Amount: $1,048,400 1Current Contract Value = Original contract value + executed Change Orders

Page 43: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

43 | P a g e

SCHEDULE: Substantial Completion letter issued for Jan. 31, 2020. Coordinating with CSC and the contractor to establish the date to turn over the project to HRH. Prefinal Inspection for UHWO and EKP were held in the first week of May. Base contract work impacted by pending change orders, and pending change order work to be completed.

WORK PROGRESS: Activities this Month: East Kapolei

Completed installation of decorative floor tile at faregate. Completed installation of canopy base covers. Completed site furnishing at all rooms and common areas. Completed photocell testing for the lighting. Started station-wide signs installation. Continued station-wide painting of exposed pipes. Conducted pre-final walkthrough on all three stations. Continued station-wide correcting of punchlist and issues.

UH West O‘ahu

Continued traffic signal change (Request for Change by HART [RFCR] 41) at Road B intersection.

Landscaping work/maintenance ongoing. Continued painting of exposed pipes. Continued station-wide sign installation. Completed installing all site furnishings. Completed photocell testing for the lighting. Assisted in state inspections for the elevators and escalator. Continued station-wide completion of punchlist items/issues.

Ho‘opili

Landscaping work ongoing. Signage installation ongoing. Elevator and faregate storm drains installation ongoing. Continued painting of exposed pipes. Completed FCN 220 and 222 for permanent and temporary

irrigation. Completed photocell testing for the lighting. Completed canopy storm drain installation. Continued station-wide correcting of punchlist items/issues.

Look Ahead: East Kapolei

Complete site utility work. Complete site work and landscaping. Complete exterior signs installation. Complete exterior light posts and

testing. Pour back concrete road at Keahumoa

Parkway. Complete punchlist items. Turnover to HRH.

UH West O‘ahu

Complete contract change order (CCO) for 16” non-potable waterline (NPW).

Complete landscaping and irrigation. Complete sign installation. Complete traffic signal installation. Interior and exterior lighting – design

changes possible. Complete punchlist items. Turnover to HRH.

Ho‘opili

Complete signage installation. Complete elevator and faregate storm

drain installation. Complete painting of exposed pipes. Complete landscaping and sitework. Complete punchlist items. Turnover to HRH.

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Keone'ae Station (UHWO) 16-in Non-Potable Waterline Reconnection

Kualaka'i (EKP) 24-inch Sewer Line Differing Site Condition - RFI 01207

FM 200 System Upgrade from Class A to C

Added Lighting at Keone'ae Station (UHWO) and Kualaka'i (EKP)

A A A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

Page 44: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

44 | P a g e

KEY MILESTONES: UHWO Station:

Prefinal Inspections and HRH Turnover. EKP Station:

Site utility (24” and 8” sewer lines) installation.

Station turnover to HRH.

HOP Station:

Prefinal Inspections and HRH Turnover.

QUALITY MANAGEMENT: Conducted bi-weekly Quality Task Force Meetings.

WOSG NCR Log (Issued by Nan)

NCRs Issued to Date

Closed Open

East Kapolei 11 11 0

UH West O‘ahu 43 41 2

Ho‘opili 32 31 1

Contract Wide 12 12 0

TOTAL 98 95 3

Page 45: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

45 | P a g e

D. Farrington Highway Station Group (FHSG) CPP No.: DBB-271 Contractor: Hawaiian Dredging Construction Company, Inc. (HDCC) Contract Start Date: August 2015 Contract Substantial Completion: June 2020 Projected Completion of Work: September 2020

Project Description: The Farrington Highway Station Group construction contract includes services to build three (3) transit stations along Farrington Highway. The stations are West Loch (WLO), Waipahu Transit Center (WTC), and Leeward Community College (LCC) Stations. The station work includes operational ancillary buildings, a traction power substation at WLO, and a Kiss-and-Ride lot at WLO.

Progress Schedule Status

Physical % Complete 97.8% 3 months behind**

Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. **Further explanation is provided in the Schedule section.

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $4,509,709

DBE % Attained: 3.81%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $39,290,879

None N/A ---

Cumulative Current Report $39,290,879

Original Contract: $78,999,000 Incurred-to-Date: $92,755,232

Current Contract Value¹: $118,289,879 Incurred in June: $1,816,085

Outstanding Issues: 2 Contractor CP Amount: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 46: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

46 | P a g e

SCHEDULE:

Consolidated Resolution (CR) Change Order 037 extended contract completion to June 2020. HDCC deployed and tensioned fabric at both WLO platforms. HDCC also completed the fabric detailing on the

WTC platform fabric. HDCC continued to work through the COVID-19 epidemic, implementing many additional safety precautions to

minimize its team’s exposure to the virus. Final faregate canopy fabric installation to be completed in September 2020, due to contractor delay in

fabrication of faregate canopy steel. ________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: West Loch

● Partially erected faregate canopy steel. ● Received station signage. ● Deployed platform canopy. ● Completed punchlist items.

Leeward Community College ● Completed punchlist items. ● Post-installing sign anchors at stairs.

Waipahu Transit Center ● Platform fabric detailing. ● Grouted canopy base plates. ● Installed signage throughout the station.

All Stations ● Coordinated canopy fabric installation, train testing, NCRs,

change orders, and other closeout items. ● Faregate canopy fabrication (WLO/WTC). ● Signage fabrication. ● Signage delivery.

Look Ahead: West Loch

● Troubleshoot fit-up issues for mauka faregate steel.

● Makai faregate canopy shipment.

Leeward Community College ● Complete clamping and flashing

installation on canopy. ● Submit drain plug assembly.

Waipahu Transit Center ● Moloalo sidewalk redesign. ● Faregate canopy erection.

All Stations ● Complete punchlist activities. ● Signage delivery and installation. ● Miscellaneous FCN activities.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code ● Moloalo St. Redesign ● FM 200 Upgrade

P P

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES: Station turnover. Final Platform canopy detailing – August 2020. Faregate canopies – September 2020.

Page 47: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

47 | P a g e

QUALITY MANAGEMENT: The CEI team is working with HDCC to ensure required submittals are approved prior to related construction

activities.

FHSG NCR Log (Issued by HDCC)

NCRs Issued to Date

Closed Open

West Loch 33 31 2

Waipahu Transit Center 22 18 4

West Loch/Waipahu Transit Center 3 2 1

Leeward Community College 20 18 2

Contract Wide 19 17 2

Void 2 2 0

TOTAL 99 88 11

Page 48: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

48 | P a g e

E. Maintenance and Storage Facility (MSF) CPP No.: DB-200 Contractor: Kiewit/Kobayashi Joint Venture (KKJV) Contract Start Date: July 25, 2011 Contract Substantial Completion Date: July 2, 2016

Project Description: The MSF contract consists of the Operations and Servicing Building (OSB), Maintenance of Way (MOW), Train Wash Facility (TWF) and Wheel Truing Building (WTB). In addition to the four (4) facility buildings, MSF includes rail procurement, special trackwork, ties, third rail and other track material for the four guideway segments on the project.

Progress Schedule Status

Physical % Complete 100% Substantial Completion Obtained*

Early Plan 100%

Late Plan 100% *Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $710,987

DBE % Attained: 0.25%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $86,517,032

None N/A ---

Cumulative Current Report $86,517,032

______________________________________________________________________________________________________________________________________________________

SCHEDULE:

HART to close remaining issues third quarter 2020. ______________________________________________________________________________________________________________________________________________________

WORK PROGRESS:

Activities this Month: Final Acceptance Letter routing for signature.

Look Ahead: Final retention release. Final Acceptance Letter from HART. Process final payment.

MSF Construction Status 100% Complete Overall

Element % Complete*

OSB 100%

MOW Building 100%

WTB 100%

TWF 100%

Rail 100%

Paving 100% *Not including testing and commissioning.

Original Contract: $195,258,000 Incurred-to-Date: $281,775,032

Current Contract Value¹: $281,775,032 Incurred in June: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 49: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

49 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________

KEY MILESTONES:

None. _______________________________________________________________________________________________________

QUALITY MANAGEMENT: Overall quality of the contract is good.

MSF NCR Log (Issued by KKJV)

Total NCRs Issued to Date Closed Open

37 37 0

Page 50: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

50 | P a g e

4.3 Section II – Kamehameha Highway: Pearl Highlands to Aloha Stadium A. Kamehameha Highway Guideway (KHG)

CPP No.: DB-320 Contractor: Kiewit Infrastructure West Company (KIWC) Contract Start Date: June 2011 Date of Substantial Completion Notification: December 13, 2018

Project Description: Kamehameha Highway Guideway DB Contract (KHG) consists of 3.9 miles and starts 400 feet east of the Pearl Highlands Station and terminates 1,400 feet beyond the Aloha Stadium Station. KHG work scope is made up of utility relocations, traffic signal improvements, highway widening, drilled shaft foundations, columns, and aerial structure.

Progress Schedule Status

Physical % Complete 100% Substantial Completion Obtained**

Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. **Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $860,191

DBE % Attained: 0.21%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $31,405,774

None N/A ---

Cumulative Current Report $31,405,774

SCHEDULE: Close Contract – Pending signed Release and Certificate of Final Payment from KIWC.

_______________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Final Retention Release is routing.

Look Ahead: Receive the contractor’s signed Release and

Certificate of Final Payment. Payment of final retention release.

Original Contract: $372,150,000 Incurred-to-Date: $403,555,774

Current Contract Value¹: $403,555,774 Incurred in June: $0

1Current Contract Value = Original contract value + executed Change Orders

Page 51: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

51 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

None N/A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________

KEY MILESTONES: One-year project warranty ended on Jan. 14, 2020.

_______________________________________________________________________________________________________

SUBSTANTIAL COMPLETION: Substantial Completion was Dec. 13, 2018.

_______________________________________________________________________________________________________

QUALITY MANAGEMENT:

KHG NCR Log (Issued by KIWC)

Total NCRs Issued to Date Closed Open

252 252 0

Page 52: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

52 | P a g e

B. Kamehameha Highway Station Group (KHSG) CPP No.: DBB-371 Contractor: Nan, Inc. Contract Start Date:

Notice to Commence Administrative Work: April 2016 Notice to Commence Investigative/Pre-Construction Work at Pearl Highlands: July 2016 Full Notice to Proceed (NTP): October 3, 2016

Contract Substantial Completion: April 2020 Projected Completion of Work: October 2020

Project Description: The Kamehameha Highway Station Group construction contract includes services to build three (3) transit stations along Kamehameha Highway. The stations are Pearl Highlands Station (PHL), Pearlridge Station (PLR), and Aloha Stadium Station (ALS). Operational ancillary buildings, pedestrian crossing improvements, Train Control and Communications Rooms (TCCRs), and landscaping of the station sites are included in addition to the transit stations. The Pearl Highlands Station will include a transit center. The Pearl Highlands and Aloha Stadium Stations include both a Park-and-Ride lot and a Kiss-and-Ride lot.

Progress Schedule Status

Physical % Complete 94.2% 6 months behind**

Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. **Further explanation is provided in the Schedule section.

_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $15,219,828

00045 PLR Mauka Sewerline Changes $90,648

Cumulative Current Report $15,310,476

Original Contract: $115,805,845 Incurred-to-Date: $121,218,853

Current Contract Value¹: $131,116,321 Incurred in June: $1,405,800

Outstanding Issues: 5 Contractor CP Amount: $12,088,285

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders

Page 53: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

53 | P a g e

SCHEDULE:

Ongoing coordination with CSC and the contractor to meet HRH’s schedule for access turnover and interim opening.

Schedule delayed by canopy and fabric delivery. Pearlridge canopy fabric was installed in June at Pearlridge, with the exception of the center panels. Pearl Highlands’ canopy fabric is scheduled for July. Aloha Stadium arm installation to start in July with fabric installation starting in September. Working with the contractor to improve the schedule.

Working with the station and systems contractors to mitigate any impact on interim opening resulting from canopy design revisions in progress.

CCO 44 revised the contract substantial completion date to April 30, 2020 with the exception of canopies and fabric. Scheduled to be complete in October 2020.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Pearl Highlands

Continued painting of all steel. Continued ceramic tile installation. Continued articulated concrete block installation. Completed bipod modification work. Commenced parking lot work. Commenced canopy base plate installation. Commenced bipod installation. Commenced and completed wire mesh panel and

wire bench installation. Commenced architectural gate installation. Commenced canopy drain bowl installation. Continued Farrington Highway Barrier Improvements.

Pearlridge Continued painting all steel. Continued elevator Thermoplastic Polyolefin (TPO)

roofing installation. Completed elevator glazing and louver installation. Commenced and completed bipod installation. Commenced canopy fabric installation. Commenced and completed architectural fence gate

installation. Commenced wire mesh panel installation. Commenced and completed plumbing fixture

installation. Aloha Stadium

Continued driveway B rigid paving concrete pours. Completed elevator shaft roof and deck installation. Completed service stair gate installation. Continued concrete pavement striping work. Commenced escalator cladding installation. Commenced entrance area porcelain tile installation.

Look Ahead: Pearl Highlands

Complete articulated concrete block installation. Complete ceramic tile installation. Commence canopy fabric installation. Commence signage installation. Commence entrance ramp light pole installation. Commence installation of graffiti resistant coating. Commence wind screen installation.

Pearlridge Commence signage installation. Commence downspout installation. Commence architectural fence installation. Commence faregate canopy steel installation. Commence wind screen installation. Commence Fire Protection Accessories and

Cabinet installation. Commence parking lot striping. Commence wire bench installation. Commence landscape work.

Aloha Stadium Complete driveway B ridged paving concrete

pours. Commence elevator glazing installation. Commence canopy steel installation. Commence canopy fabric installation. Commence signage installation. Commence furniture installation. Commence PSG bolt grouting. Commence visual screen installation. Commence wire mesh and wire bench installation. Install fire protection cabinets.

Page 54: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

54 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

CW FM-200 Upgrade

PLR Art Program Changes

CW Elect. & Structural Canopy Changes (Construction Costs & Schedule - TIA-4)

PHL Concourse Railing Changes

PHL & PLR Canopy Bipod Strut & Cable Fix

A A C A A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES:

Pearlridge Station TCCR and UPS Building – Pathway to guideway conduit installation is complete. TCCR and UPS rooms are now being shared with the Core Systems Contractor.

Aloha Stadium Station TCCR and UPS Rooms – Pathway to guideway conduits complete. TCCR and UPS rooms are now being shared with the Core Systems Contractor.

Canopy arms are erected at Pearl Highlands and Pearlridge. Energization of Pearl Highlands and Pearlridge – February 2020. Fabric installation to begin at Pearlridge-June, Pearl Highlands- July, and Aloha Stadium- September.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

KHSG NCR Log (Issued by Nan)

NCRs Issued to Date

Closed Open

Pearl Highlands 29 26 3

Pearlridge 26 25 1

Aloha Stadium 7 5 2

Contract Wide 0 0 0

TOTAL 62 56 6

Page 55: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

55 | P a g e

C. Kamehameha Highway Resurfacing (KHR) CPP No.: DBB-701 Contractor: Road and Highway Builders, LLC (RHB) Contract Start Date: Notice to Proceed NTP #1: August 2018 Contract Substantial Completion: September 2019 Projected Completion of Work: August 2020

Project Description: The project consists of pavement resurfacing and other roadway reconstruction associated with completion of the Kamehameha Highway Guideway contract. Construction includes, but is not limited to, clearing, grubbing, erosion and dust control, grading and hauling, maintenance of traffic, pavement resurfacing, and installation of pavement markings and striping, roadway signs, curb ramps, drainage, waterlines, gas lines, traffic signal loop detectors, retaining wall, guard railing, fencing and bus shelters.

Progress Schedule Status

Physical % Complete 97.8% 11 months behind**

Early Plan* 100%

Late Plan* 100% *Data as of June 26, 2020. **Pending contract actions will extend contract completion date.

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $1,974,656

DBE % Attained: 6.94%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $2,455,926

None N/A ---

Cumulative Current Report $2,455,926

__________________________________________________________________________________________________________________________________________________________________________________________________________________________

SCHEDULE: The contract completion date will be extended due to delays in road widening at Kaahumanu Street, Construction

Right-of-Entry (CROE) for construction of retaining wall #9, and additional change work. A time extension is pending.

Developing additional change orders that could extend the completion date to October 2020. _______________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Prepared finding of merit for RFCR 00011 KHR

miscellaneous changes (CROE, bus shelter, electronic vehicle counter [EVC] loops and others).

Prepared finding of merit for RFCR 00013 Pearl City Stream Median Guardrail.

Look Ahead: Begin change order work.

Original Contract: $25,989,989 Incurred-to-Date: $27,703,164

Current Contract Value¹: $28,445,915 Incurred in June: $519,282

Outstanding Issues: 4 Contractor CP Amount: $14,072,952 1Current Contract Value = Original contract value + executed Change Orders

Page 56: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

56 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Kam Hwy/Ka'ahumanu St Changes

KHR Miscellaneous Changes

Left Turn at Kuala Street

Pearl City Stream Median Guardrail

P A C A

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal _______________________________________________________________________________________________________________________________________

KEY MILESTONES: Secure CROE for Pearlridge bus stop – July 2020.

_______________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT: KHR continues to follow established quality processes through quality monitoring and audits.

KHR NCR Log (Issued by Road and Highway Builders)

Total NCRs Issued to Date Closed Open

0 0 0

Page 57: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

57 | P a g e

D. Design Services for 138kV Utilities Relocation at KHG

CPP No.: FD-700 Contractor: R.M. Towill Corporation (RMTC) Contract Start Date: September 2018 Contract Substantial Completion: November 2021 Project Description: Architectural and Engineering Services for the final design to relocate the existing 138kV overhead electrical lines to underground lines at Kamehameha Highway Guideway and Stations.

Progress Schedule Status

Based on Expenditures* 47.9%

TBD Early Plan* 61.0%

Late Plan* 48.0% *Data as of June 26, 2020.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $0

DBE % Attained: 0%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $0

None N/A ---

Cumulative Current Report $0

_____________________________________________________________________________________________________

SCHEDULE: An updated preliminary design submittal (to HECO), incorporating additional HECO review comments on the

previously updated preliminary design submittal, was made on Feb. 21, 2020. These updated preliminary design drawings were used by HECO for sway calculations. We received final calculations for all areas except around pole 15, and between poles 18 and 20. The design consultant is updating the drawings as they receive final calculations from HECO.

_______________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: The design consultant traffic counting was temporarily

suspended due to unusual traffic patterns experienced during the COVID-19 shutdown.

The design consultant continued additional topographic survey work. This work is ongoing in reaction to comments received from affected agencies and consequential revisions being made.

The design consultant will be providing HECO with geotechnical engineering services. The geotechnical engineer continues to obtain permits for the work.

Look Ahead: Continue periodic HECO meetings. Continue refining preliminary design work. Continue to meet with third party agencies

to discuss their comments/concerns on the preliminary submittal.

Perform geotechnical investigation for the purpose of HECO’s pole foundation design, per HECO request.

Original Contract: $8,766,327 Incurred-to-Date: $4,305,543

Current Contract Value¹: $8,766,327 Incurred in June: $107,446 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders

Page 58: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

58 | P a g e

Activities this Month (continued): Our schedule has been revised to incorporate HECO

comments and recent developments regarding easements, acquisitions and HECO design tasks. The updated schedule was sent to HECO.

We received final sway calculations from HECO for all areas except around pole 15, and between poles 18 and 20. The design consultant is processing the results upon receipt of the final calculations. The schedule of this work is controlled by HECO.

The preliminary design has been submitted to affected third party agencies, and the design consultant continues to schedule meetings with each agency to discuss third party agency comments. Comments from the City and County of Honolulu Department of Environmental Services (ENV) and the Board of Water Supply (BWS) have been received by the design consultant, and consequential revisions to the design are being made.

A typical cross-section of the proposed Aiea Stream utility bridge was provided to HECO for review and comment. HECO confirmed that they will maintain the utility bridge following completion of construction.

_______________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font): The design consultant needs to continue to coordinate with third party agencies to identify portions of the

alignment that need to be revised. HECO needs to complete their final sway calculations.

_______________________________________________________________________________________________________

KEY MILESTONES:

Based on schedule information we currently have, key upcoming milestones are as follows: o Prefinal Design: Oct. 14, 2020. o Final Design: April 21, 2021.

Page 59: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

59 | P a g e

4.4 Section III – Airport: Aloha Stadium to Middle Street Transit Center Station A. Airport Section Guideway and Stations (AGS)

CPP No.: DB-450 Contractor: Shimmick/Traylor/Granite, JV (STG) Contract Start Date: December 2016

Contract Substantial Completion: May 2021

Projected Completion of Work: October 2021

Project Description: The Airport Guideway and Stations Design-Build contract consists of the design and construction of 5.2 miles of elevated guideway, four (4) stations, and associated facilities between Aloha Stadium and the Middle Street Transit Center. The contractor will begin by interfacing with design disciplines, third-party stakeholders, and construction contracts within the corridor of the project to coordinate and resolve utilities conflicts. Design field verification efforts (potholing and geotechnical exploration) will be followed by construction activities once design packages have been approved.

Progress Schedule Status

Physical % Complete* 71.3%

5 months behind** Early Plan* 92.4%

Late Plan 78.8% *Data as of June 26, 2020. **Further explanation is provided in the Schedule section.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $43,569,716

DBE % Attained: 4.91%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $11,684,752

00030 Zone 4 Additional Clearance Requirement $78,000

Cumulative Current Report $11,762,752

Original Contract: $874,750,000 Incurred-to-Date: $622,970,587

Current Contract Value¹: $886,512,752 Incurred in June: $38,204,598

Outstanding Issues: 14 Contractor CP Amount: $43,658,803 1Current Contract Value = Original contract value + executed Change Orders

Page 60: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

60 | P a g e

SCHEDULE: Mitigation Schedule Accepted as Noted. The Mitigation Schedule has a December 2021 completion date; however, we

are working to mitigate it, and HART and the contractor have agreed to an Oct. 31, 2021 completion date. Additional workshops are continuing to further define station activities for access milestones for CSC.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: AGS Construction Status as of 06/26/2020

Guideway Structure Element

Total to Date

Total Qty % Complete

Shafts 188 225 83.6%

Columns 176 232 75.9%

Segment Casting 2,652 2,708 97.9%

Spans Stressed 120 210 57.1%

Spans Grouted 110 210 52.4%

Track 1 rail work 1 210 0.5%

Track 2 rail work 9 210 4.3%

Track 1 Third Rail 0 210 0.0%

Track 2 Third Rail 0 210 0.0%

Mill & Overlay 0 * 0.0% * Amounts to be determined.

Activities this Month: Guideway, Rail and Utility Work

Gantry 1 crane continued; erected/stressed 5 spans at 498 through 502. Gantry 2 crane continued; erected/stressed 1 span at 543. Gantry 3 erected 3 spans at 603 through 605.

Utilities – HECO Zones 6A, 8B and 9 infrastructure continued. Traction Power ductbanks to System Site (SS) #25 are ongoing.

Installation of rail work continued in Reach A, iron horses and plinth forms installed. Plinths poured for 8 spans for Track 2 at Span 423 through 430, and 1 span for Track 1 at Span 422.

Reach A: Traffic Signal (TS) continued on Kamehameha Highway at Radford Drive and Center Drive. Median restoration finalized from Piers 433-462. Reach B Civil/Utilities was approved by HART/HDOT/DTS and is routing for signatures.

Reach B: Pier 504 cap completed. Traffic Signal work at Center Drive and Valkenburgh Street is ongoing.

Reach C: Street Light (SL) relocation continued at airport. Reach D: HECO Zone 8A (Ualena) completed electrical cutovers

to transformer vaults and service reconnections on Ualena Street. Comm. cable installation, including service lines for Hawaiian Telcom (HTI)/ Oceanic Time Warner Cable (OTWC) commenced. Traffic Signal work commenced at Lagoon.

Makalapa (Pearl Harbor Naval Base) Station Installation of rebar for platform girders on top of the guideway.

Ewa portion of platform girders tub poured. Lelepaua (Daniel K. Inouye International Airport) Station Excavation and installation of conduits from Elevators 1-3 (Lot J)

to TCCR. Āhua (Lagoon Drive) Station Completed underground conduits for electrical, fare gates and

city fiber infrastructure installation at Mauka Entrance. Kahauiki (Middle Street Transit Center) Station Continued excavation for station entrance.

Look Ahead: Guideway, Rail and Utility Work Design Submittals Approved:

o Reach E – Civil and Composite Utilities Issued for Construction (IFC)

o Civil Common Drawings and Intelligent Transportation Systems (ITS) IFC

o Middle Street Transit Center (MSTC) Station IFC

Form/rebar/pour Reaches C and E columns and segment casting.

Begin drilling shafts on Ualena Street in Reach D and continue in Reaches C and E.

Continue pouring C-Bents and Straddle Bents, and columns in Reach C and Reach E.

Continue installation of rail work. Complete electrical relocation work in HECO

Zones 6A, 8B and 9. Coordination taking place with third parties.

Makalapa (Pearl Harbor Naval Base) Station Finish platform girder rebar installation,

concrete and post-tensioned (PT). Await fabrication and delivery of structural steel in August 2020.

Lelepaua (Daniel K. Inouye International Airport) Station Start foundations for TCCR and Ancillary

Building. Āhua (Lagoon Drive) Station Begin forming concrete masonry unit (CMU)

walls and slab on grade for station rooms. Kahauiki (Middle Street Transit Center) Station Finish excavation and backfill for sub grade for

station entrance.

Page 61: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

61 | P a g e

KEY ISSUES:

Key Issues with Contractor Proposal Title CPC Code

Hurricane Lane

Access to Premium Property

Lagoon Dr Station - Additional Infrastructure for Interim Opening Part II

FCN-KJL Properties TCE Agreement Reimbursement

HIA Site Redevelopment

ITS IP Based Design

DPP Erosion Control Notes

Fare System Walker Duct

Fare Gate FDAS Relay Cable

Pier 505 Standby Drilling Equipment

Reach A Civil and Paving

SCADA Infrastructure

Additional VMS Boards at Station Platforms

Inefficient Utility Claim

A A B P B P P P P A P P P C

LEGEND: A = less than $1 million; B = $1 million-$5 million; C = greater than $5 million; P = pending contractor submittal ________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES: C-Bent Capital 504 (linked to the critical path) was completed on June 15, 2020. Span 422 Track 1 plinths was completed on June 25, 2020. Segment 2,650 (98% complete) was cast on June 26, 2020. Electrical cutovers to transformer vaults and service reconnections on Ualena Street was completed on June 27,

2020. Completed erection of 9 guideway spans in June 2020.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT:

Pre-Activity Meetings continue.

AGS NCR Log (Issued by STG)

NCRs Issued to Date

Closed Open

Guideway 341 266 75 Pearl Harbor Naval Base Station 33 21 12 Honolulu International Airport Station 30 23 7 Lagoon Drive Station 16 12 4 Middle Street Transit Center Station 8 5 3 Contract Wide 17 17 0 TOTAL 445 344 101

Page 62: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

62 | P a g e

4.5 Section IV – City Center: Middle Street Transit Center Station to Ala Moana Center A. City Center Section Utilities and Guideway

CPP No.: FD-530 Contractor: AECOM Technical Services, Inc., Final Design Consultant (Engineer of Record) Contract Start Date: July 2012 Contract Substantial Completion: July 2020 Projected Completion of Work: July 2020

Project Description: The original City Center Section Utilities and Guideway (CCUG) final design contract consisted of utility relocations, roadway widening, and 4.12 miles of elevated transit guideway serving eight (8) passenger stations. The scope of the CCUG contract has been reduced to include only the design of utility relocations and roadway widening to facilitate future guideway design and construction by others. The remaining work is herein referred to as the City Center Utilities Relocation (CCUR) design.

Progress Schedule Status

Based on Expenditures* 99.3% On time (based on contract substantial completion date)**

Early Plan* 100%

Late Plan* 99.9% *Data as of June 26, 2020. **Further explanation is provided in the Schedule section.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $191,227

DBE % Attained: 0.33%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $14,550,073

None N/A ---

Cumulative Current Report $14,550,073

SCHEDULE: Due to changes to save cost and delays by third party reviews, CCUR final design is scheduled to conclude in third

quarter 2020. A change order is currently being routed to account for the additional design changes as well as a time extension for the CCUR construction period.

__________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Coordination with City and utility third parties to address review

comments for Task Orders (TOs) within the review process: TO2A Draft Rev. 1 v2 (6/12/20), TO2B Draft Rev. 1 (6/12/20), TO22 Draft Rev. 0 Comment Resolution v2 (6/24/20), TO23A Draft Rev. 0 Comment Resolution v1 (6/29/20), TO23B Draft Rev. 0 Comment Resolution v1 (6/29/20), Traffic Signal (TS)/Street Light (SL) 1 Draft Rev. 0 v3 (6/29/20).

Look Ahead: Complete and submit final design

drawings for TOs 22, 24, 23A, 23B, 32, 25, 28, 2 and 13; the Traffic Signal/Street Light as well as update(s) to the Roadway design plan package, as required.

Original Contract: $43,948,220 Incurred-to-Date: $57,489,264

Current Contract Value¹: $58,498,293 Incurred in June²: $0 1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 2Work has progressed and incurred amounts will be reflected as invoices are approved in the City’s C2HERPS system

Page 63: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

63 | P a g e

Activities this Month (continued):

Design Package submittals/resubmittals this month included: TO2A Draft Rev. 1 V1 Comment Resolution Doc. to Hawai‘i Gas on 6/2/20, HDOT on 6/11/20 and City and County of Honolulu Department of Environmental Services (ENV) on 6/12/20. TO22 Draft Rev. 0 V3 Comment Resolution Doc. to HECO and Hawaiian Telcom (HTI) on 6/24/20. TO23A Draft Rev.0 v1 to AT&T, HECO and HTI on 6/2/20, Board of Water Supply (BWS) on 6/3/20, Civil Engineering Branch (CEB) on 6/5/20, DTS on 6/23/20, and Department of Design & Construction – Mechanical & Electrical Division (DDC-MED) on 6/29/20. TO23B Draft Rev.0 v1 to BWS on 6/3/20, DTS on 6/24/20, and DDC-MED on 6/29/20. Traffic Signal/Street Light Dillingham 1 Draft Rev. 0 v2 to BWS on 6/5/20 and DDC-MED on 6/29/20. TO24 Draft Rev. 0 Comment Resolution v2 to HECO/Customer Installation Department (CID) on 6/24/20. TO17 Draft Rev. 0 Comment Resolution Doc. V4 to HECO on 6/12/20, and Issued for Construction (IFC) Submittal 6/26/20. TO28 Draft Rev. 0 Comment Resolution Doc. v2 to HECO on 6/22/20.

Received official comments for: TO2A Draft Rev. 1 v2 from ENV (6/9/20), Hawai‘i Gas (6/10/20) and BWS (6/15/20); TO2B Draft Rev. 1 from BWS (6/9/20), ENV (6/9/20) and Hawai‘i Gas (6/10/20); TO22 Draft Rev. 0 V2 Comment Resolution Doc. from HECO (6/2/20); TO23A Draft Rev. 0 Comm. Reso Doc. from AT&T (6/2/20), BWS (6/9/20), HTI (6/10/20), CEB (6/12/20), DDC-MED (6/15/20), DTS (6/16/20 and 6/25/20), HDOT (6/18/20), HECO (6/26/20); TO23B Draft Rev. 0 Comment Resolution Doc. from BWS (6/9/20), HTI (6/10/20), DDC-MED (6/15/20), DTS (6/16/20 and 6/25/20), HECO (6/20/20); TO13 Draft Rev. 1 from Wastewater Branch (WWB) (6/17/20) and Subdivision Branch (SUBD) (6/18/20); TO25 Rev. D from WWB (6/10/20), SUBD (6/10/20) and HECO and HECO/CID (6/15/20); TO32 Draft Rev. 0 Comment Resolution Doc. from BWS (6/9/20), HECO and HECO/CID (6/7/20), SUBD (6/15/20); TO24 Draft Rev. 0 Comment Resolution Doc. From HECO/CID (6/30/20); TO17 Draft Rev. 0 Comment Resolution Doc. v4 from HECO (6/12/20); TS/SL Dillingham 1 Draft Rev. 0 from CEB (6/12/20) and BWS (6/30/20); and TS/SL Nimitz Draft Rev. 0 from DTS (5/15/20).

Continued coordination with HECO and other concerned third party utility agencies (i.e. BWS, HTI, etc.) to finalize utility concerns and comments for pending design package submittal.

Continued coordination with other agencies with projects within City Center, as well as landowners and their consultants/contractors for development projects.

Continued support during construction via Request for Information (RFI) with CCUR contractors.

Continued coordination with utilities for all utility layouts for remaining dry utility task order packages, Traffic Signal and Street Light, as well as the final Roadway Packages.

Coordination with City and State agencies to process One-Time Review (OTR) and required permit approvals to allow construction to start.

Continued coordination with ROW team for ongoing negotiations for acquisitions.

Continued coordination and bi-weekly meetings with the DPP Director and staff for ongoing design task order packages review.

Look Ahead (continued): Third party reviews and comments

for Task Orders 24, 28, 2, 13, 26, 25, and Street Lights and Traffic Signal Packages.

Finalize detail submittal for 138kV steel pole foundation design.

Finalize detail submittal for micropile needed for 138kV / BWS facilities crossing(s) on Dillingham Boulevard.

Final submittal for hydraulic/hydrology analysis for Kapalama Canal, per change order.

Page 64: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

64 | P a g e

KEY ISSUES (new issues are in bold font): Finding of Merit/No Merit (FOM) processed this month: (1) Additional Design Services during the June 4, 2020

Contract Change Committee (CCC) meeting. Executed June 9, 2020. Executive Decision Document (EDD) for additional services and time extension to the contract was routed on

June 12, 2020 for approval and signatures; final approval by CEO June 24, 2020. A presentation for the change order was provided by the Director of Construction to the Project Oversight Committee (POC) in early June and during the main HART Board meeting on June 25, 2020; request for change order was approved during this session. The change order is currently in process for execution.

HART is working with third party utilities as well as City agencies to better streamline reviews to prevent further slippage in design schedules.

____________________________________________________________________________________________________________________________________________________________________________________

KEY MILESTONES: TO2A Draft Rev. 1 V1 Comment Resolution Doc., TO22 Draft Rev. 0 V3 Comment Resolution Doc., TO23A Draft

Rev.0 v1, TO23B Draft Rev.0 v1, Traffic Signal/Street Light Dillingham 1 Draft Rev. 0 v2, TO24 Draft Rev. 0 Comment Resolution v2, TO17 Draft Rev. 0 Comment Resolution Doc. V4, IFC Submittal, TO28 Draft Rev. 0 Comment Resolution Doc. v2.

Page 65: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

65 | P a g e

B. City Center Utilities Relocation (CCUR) Indefinite Delivery/Indefinite Quantity (IDIQ) CPP No.: DBB-511 Contractor: Nan, Inc. Contract Start Date: May 2018 Contract Term Completion: May 2022 Projected Completion of Relocation Work: February 2023

Project Description: The CCUR contract is a unit priced, task order contract that relocates utilities in advance of the City Center Guideway and Stations construction work. It provides utility relocation construction services for a variety of utilities along the civil roadway construction throughout the City Center segment of the HRTP. The construction services to be provided will include, but are not limited to, permanent and temporary wet and dry utility relocation work which will include miscellaneous, as-needed site work, installation of permanent/temporary utility poles, duct bank construction, and other utility installation support structures.

Progress Schedule Status

Physical % Complete* 11.4%**

9 months behind*** Early Plan* 55.8%

Late Plan* 44.8% *Data as of June 26, 2020. **The percentages shown are based on installed work values against the current allocated amount. The contracted amount does not incorporate the full scope of the work. In May 2020, HART presented an Estimated Cost at Completion to the HART Board for all the work required prior to the P3 contractor commencing their work. HART Project Controls and CEI are now working to incorporate a quantity-based assessment that is being imported into the oversight schedule; the resulting percentages will be presented with the July update. ***The Execution Plan reflects the most current strategies to execute the work and status of progress.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

DBE Participation Task Orders

Actual DBE Participation: $0 Number of Task

Orders Issued Amount ($)

DBE % Attained: 0% Task Orders Previously Issued 14 $378,994,598

Task Orders Issued this Month 0 $0

Amendments to Task Orders 0 $0

Total Task Orders Issued 14 $378,994,598

Original Contract: $400,000,000 Incurred-to-Date: $32,800,101

Current Contract Value¹: $400,000,000 Incurred in June: $8,483,024 1Current Contract Value = Original contract value + executed Change Orders

Page 66: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

66 | P a g e

SCHEDULE: Multiple areas have been impacted this period. Projected Completion of CCUR by February 2023. All Traffic Signals and Street Lights pre-IFC design submitted by July 2020. Pre-IFC design complete Q2 2020. All Wet Utility task orders under construction Q3 2020. All Dry Utility task orders under construction Q4 2020. HECO completes all electrical design requirements Q1 2021. Final roadway revision encompassing all changes Q4 2020.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month:

All Area 1: Nan has initiated a Purchase Order Agreement with Rohn for the 138kV poles and will no longer pursue the Valmont poles. This reduces procurement cost and duration by approximately $800,000 and 18-weeks respectively, compared to Valmont. A letter is planned to be sent to Nan on July 2, 2020, for the approval to switch vendors.

Obtained HTI, Oceanic Time Warner Cable (OTWC) and AT&T’s concurrence for the use of HECO’s concrete mix when used in joint trenches, utilizing high slump mix and no vibration.

Area 1A: HECO approved HART’s formal request on June 8, 2020 to complete 12kv conduit installation between Laumaka and Pu‘uhale, pending certain conditions were followed, including inspection requests, meeting all HECO and manufacturer requirements and geotechnical engineer recommendations. AT&T temp connection proposal - CEI is currently working with AT&T to determine timelines and required coordination between AT&T Public Sector Solutions (PSS) and AT&T Corp.; updating the schedule accordingly. Obtained TO-22 (dry) 138kV OTR June 15, 2020.

Area 1B: Potholing for existing utilities continues, based on Rev. D submittal. Focus has been on IFC design resolution with all reviewing agencies for permitting of dry utility work from Mokauea to Kapalama Canal. HART understands DPP’s preference for trenchless crossings of the Kapalama Canal and has made a decision to go forward with it. AECOM provided a drainage report to DPP for review on June 2, 2020. Box culvert demo and temporary bypass – Nan has been directed to proceed, based upon the agreed pricing, upon receipt of the approved 2A, 2B, 23A and 23B trenching and street usage permits.

Area 1C: Potholing for existing utilities continues, based on Rev. D submittal.

Area 2: HECO and HTI duct bank installation continues. Collucio completed jet grouting activities. Hawaiian Electric Phase II Environmental remediation in the Makai yard is complete, allowing Nan access on June 27, 2020. Jensen provided a letter and revised shop drawing confirming manhole (MH) knockouts acceptable. Revised MicroStation files provided to HECO on June 22, 2020, allowing them to finalize their electrical design for the temporary connections between Area 1C and Area 2. Structural jet grout column alignment issue has been resolved by City and County (C&C) Wastewater Inspector correspondence stating they take no issue with the installation and it is accepted as installed.

Look Ahead: All Area 1: Advancing procurement with Rohn for

138kV poles is critical in order to maintain schedule. HECO is in agreement of 3” minimum, 6” maximum concrete cover tolerances for duct banks. RFI to be submitted to HECO for concurrence to cover both AGS and CCUR, and HECO will provide documentation confirming. Nan and HART continue resolution plan updates to address HDOT’s concerns on the progress of meeting HART’s commitments outlined in the Traffic Management Plan (TMP) Technical Memo comment matrix. Technical Memo approval anticipated by the end of July.

Area 1A: AT&T Temporary Connection Plan – planning for relocation through both 1A and 1B in a single phase can improve efficiency for implementation in conjunction with IFC’s and permitting for Area 1B. Obtain IFC for Traffic Signal and Street Lights Dillingham: Middle Street to Kapalama Canal - OTR received previously.

Area 1B: DTS request to assess impact to the Dillingham corridor will not hold up wet and dry IFC, due to the recent traffic analysis. AECOM anticipates providing the Turning Pocket Analysis by mid-July for DTS review. HART will pursue the necessary permitting for microtunneling of the Kapalama Canal utility crossings. Trenchless exhibit with means and method (including launch location and any Best Management Practices [BMPs]) will be prepared for the permit application. HART’s design allows for Mauka and Makai sides to occur concurrently. Finalizing details will be ongoing with HECO.

Area 1C: Initial Rev. D Traffic Signal & Street Light (TS/SL) package submittal delayed to July 10, 2020, due to edits needed during the Quality Assurance (QA)/Quality Control (QC) process and to incorporate lessons learned from the resolution of adjacent CCUR TS/SL packages, which will mitigate subsequent comments for this submittal leading to IFC. Potholing of existing utilities based on the latest design updates will be ongoing. Test trench along the proposed HECO 138kV duct line to determine potential root damage is dependent on finalizing the CROE with Honolulu Community College (HCC); discussions are ongoing.

Page 67: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

67 | P a g e

Activities this Month (continued):

Area 3: RFI submitted to AECOM for repair of seawall in conflict with proposed utility design; coordination is ongoing for acceptance by HDOT. An additional wall was discovered and is being investigated with HDOT to verify if it is abandoned. HDOT permit to perform work on state highways was received June 10, 2020. No trenching permit application needed within JUOA agreement limits. Nan and CEI are incorporating reduction of scope for the task order to reflect HECO variances as the design revisions are pending.

Area 4: CEI is preparing task order authorization to include the scope of all design task orders from Richards to Ward under construction TO-03. Nan is preparing work plans including potholing and jet grouting that can be performed. TO-24 potholing plan received and approved as noted. Obtained TO-32 (dry) OTR on June 12, 2020. The Hawai‘i Community Development Authority (HCDA) extended HART’s construction right-of-entry (CROE) contract through June 20, 2021.

Area 5: HECO and HTI manhole jet grouting commenced. Dry utility infrastructure focus will be ongoing for the next six months. Iwi Kupuna were found in front of Waimanu yard, all appropriate state and local officials were notified and the State Historic Preservation Division (SHPD) determined that the iwi will be relocated to the curation facility. TO-17 (dry) IFC obtained June 15, 2020.

Area 6: Nan has proceeded on additional jet grouting for dry utility lines outside of the 10-foot offset of HECO 138kV lines. CEI and Nan continue to work with HECO to investigate and remove Fluidized Thermal Backfill (FTB) overpour on the existing 138kV underground (UG) circuit to allow space for connection of a waterline. Further jet grouting work will be released once the HECO standby inspector request is approved. HECO has toned several times; further investigation will be performed with the HECO standby inspector onsite.

Look Ahead (continued): Area 2: Continue Dry infrastructure installation duct

banks and manholes. Coordination with HECO to determine pole placement as HECO completes their electrical design. Continue weekly discussions with HTI and OTWC to refine the construction schedule, production, and explore mitigations.

Area 3: Demolition/removal of existing and abandoned utilities and new dry utility infrastructure work continues. HART expects a Design Change Notice (DCN) approximately 4-6 weeks after all IFC agency signatures are completed, eta mid-July. DCN 01 will address design changes associated with previously approved HECO variances reducing dry utility scope and cost. Obtain City trenching permit required for gas line work in City ROW on TO-14 and commence work.

Area 4: Proceed with incorporating additional scoping work into the task order, this will encompass all the work along Halekauwila from Richards Street to Ward Avenue, inclusive of all related design task orders under construction TO-03. Halekauwila Staging Yard (Civic Center Station) Environmental Phase II Site Assessment is scheduled to begin the week of July 13, 2020. Remediation duration will take approximately 15-weeks; although Nan should be able to gain access back to the yard within 6-7 weeks, as remediation is not anticipated to be needed at this time.

Area 5: Finalize agreement with property owners/tenants for placement of the jet grout plant for continued jet grouting in preparation of wet and dry utility relocation.

Area 6: Continue jet grouting for dry utilities. HECO Standby Inspectors: Nan to submit a work plan addressing safety countermeasures for protection against a strike to the existing underground 138kV line during jet grouting activities. Nan to be provided decibel readings with jet grouting machinery before and after mitigations for a baseline prior to night work commencing, due to noise complaints to the Department of Health (DOH).

__________________________________________________________________________________________________________________________________________________________

KEY ISSUES (new issues are in bold font):

Cost or schedule for the CCUR contract may be impacted if these issues aren’t resolved: o Design Finalization: The schedule for completion of the dry utility plans by AECOM, and approval by all

stakeholders has impacted CCUR Area Target Finish dates due to ongoing and additional outstanding comment resolution items from the reviewing parties. Final design approvals are critical to meeting the projected construction duration.

o Mitigation efforts: AECOM completed draft IFC submittals for final review, except TS/SL Dillingham: Kapalama Canal through Iwilei. AECOM has increased the coordination frequency with utility agencies to expedite reviews by holding informal comment resolution review sessions. DPP reviewers have been requested to bring substantial review comments up during reoccurring bi-weekly meetings with all parties present. HART is continuously strategizing with utility stakeholders on steps to shorten review and approval response time. In parallel, HART,

Page 68: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

68 | P a g e

CEI and Nan, in coordination with the utility stakeholders, are analyzing and planning work scope that can start immediately upon receipt of the applicable permits. HECO, HTI and AT&T have all allowed HART the ability to move forward in Area 1A at risk as IFC is being signed off, under existing permits and with specific conditions. No new mitigations to the construction schedule were available to incorporate this month.

o HART Right-of-Way: Currently working to complete acquisition of property within CCUR. Current focus is on the following properties: Takara Printing, Bishop Estate – Club Cleopatra, Iwilei Station - HECO, General Services Administration (GSA) – Halekauwila St. by Mililani St., and Howard Hughes.

o Mitigation efforts: HART obtained FTA’s concurrence on Takara Printing’s parcel counteroffer. An official letter was provided to the owner on June 26, 2020, with anticipated access by the end of July, pending escrow and Possession and Use Agreement (PUA) completion. Cost to Cure (C2C) CROE agreement for Club Cleopatra came through from HART Corporation Counsel (COR), however the property owner was firm that no electrical work is permitted until the agreement is finalized; estimated to be December 2020, the timing of which should not affect the current CCUR schedule. GSA provided some movement to allow landscaping work to occur simultaneously as CCUR work, pending Royal obtaining a performance bond required for the landscaping. HCC acquisition pushed to Q3 2020, pending HCC providing HART feedback on the current CROE. A decision has been made to move forward with a HART CROE, rather than extending the Royal CROE, as a general HART CROE will mitigate future issues of transferring a CROE from one contractor to another (i.e., CCUR to CCUR II or the P3). Regular meetings are being held between HART and HCC to resolve the CROE details and to execute the new agreement. Hawaiian Electric Phase II Environmental remediation in the Iwilei Makai yard is complete, allowing Nan yard access on June 27, 2020. Iwilei Mauka yard is still on schedule to be completed Q3 2020.

o HECO Agreements: The Nov. 25, 2013 agreement with HECO allows HECO to complete the electrical design up to 2 years after receiving the final infrastructure design. A general agreement was in place, as of Q4 2019, to expedite electrical design times to meet schedule needs.

o Mitigation efforts: HART and HECO meet bi-weekly or more frequently as required, to review schedule assumptions based on the expedited schedule durations incorporated and requirements to maintain and improve the schedule based on the 2019 general agreement. Regular, informal communications occur between CEI and HECO on a daily basis to facilitate design and construction resolutions.

o Long lead Material Procurement: Estimates for the duration of long lead materials have been adjusted in the schedule based on information provided by HECO for electrical equipment to be purchased under the CCUR contract. These corrected durations have contributed to the critical paths associated with CCUR Area Target Finish dates. The long lead procurement cycle is driving the longest path completion of Area 1A.

o Mitigation efforts: HECO provided HART additional suppliers who met their pole requirements. Rohn provided pricing and riser pole calculations, which were submitted to HECO on June 16, 2020. Rohn’s pricing is $800,000 less and the lead time would be reduced by 18-weeks, compared to Valmont. A decision regarding Nan changing vendors was made based on HECO’s validation that Rohn’s proposal will meet the pre-requisite submittal requirements.

o Geotechnical Engineer's Recommendation: Cost impacts to the contract will occur for 2’ over excavation of trenches in areas where soft lagoonal soils or groundwater are encountered and the installation of a Mirafi wrapped rock stabilization layer is required. This will need to be monitored closely by CEI.

o Mitigation efforts: CEI confirmed HECO’s inquiry that the geotechnical engineer's recommendations are applicable to both duct lines and MH's for City Center alignment where conditions warrant. A geotechnical engineer was consulted to discuss mitigation measures for soft soil areas. AECOM has revised the trench restoration details to clarify where the crushed rock stabilization will be required based on various soil and ground water conditions. HART provided HECO with the final geotechnical engineer’s recommendations on June 10, 2020. Additional jet grouting may be considered to limit areas requiring overexcavation and stabilization to mitigate high shoring and dewatering costs associated with the extra depth.

Page 69: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

69 | P a g e

KEY MILESTONES:

Construction Status1

NTP Target Finish2 Installed Complete3

Area 1A: Dillingham: Middle to Mokauea 20-Sep-19 24-Nov-21 5.0%

Area 1B: Dillingham: Mokauea to Waiakamilo 20-Sep-19 25-Feb-23 1.1%

Area 1C: Dillingham: Waiakamilo to Ka‘aahi 01-Feb-20 30-Jan-23 0.8%

Area 2: Ka‘aahi Street 02-Feb-19 14-Apr-21 33.4%

Area 3: Nimitz Highway 20-Sep-19 27-Sept-21 11.9%

Area 4: Halekauwila Street 24-Jan-20 19-Jul-22 0.5%

Area 5: Queen Street 01-Oct-18 01-Jul-21 2.4%

Area 6: Kona Street 01-Mar-19 17-Sept-21 23.1%

1 Based on 6/26/2020 data date. Multiple Design Packages are incorporated into each area. 2 Based on double shifts, 6 days per week, 10 hours per shift. 3 The percentages shown are based on installed work values against the current allocated amount. The contracted amount does not incorporate the full scope of the work. In May 2020, HART presented an Estimated Cost at Completion to the HART Board for all the work required prior to the P3 contractor commencing their work. HART Project Controls and CEI are now working to incorporate a quantity-based assessment that is being imported into the oversight schedule; the resulting percentages will be presented with the July update. __________________________________________________________________________________________________________________________________________________________

QUALITY MANAGEMENT: No major quality issues identified this period.

CCUR NCR Log (Issued by Nan)

Total NCRs Issued to Date Closed Open

8 7 1

Page 70: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

70 | P a g e

4.6 Professional Services A. Program Management Contractor Contract

CPP No.: MM-902 Contractor: HDR Engineering, Inc. Contract Start Date: January 1, 2017 Contract Completion Date: December 31, 2022 Description of Work: Oversee the successful design and construction of the full Honolulu Rail Transit Project (HRTP), which includes providing personnel with relevant transit design, construction and operations experience and leadership in the various areas, including construction management, design management, project controls, procurement and contracts, right of way, public and business outreach, safety and security, quality assurance, environmental planning, and federal programmatic compliance.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $332,229

DBE % Attained: 0.52%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $0

None N/A ---

Cumulative Current Report $0

*Monthly actuals are based on Pay App Verification values and are reconciled with the city’s C2HERPS system instead of CMS.

Jan

-17

Mar

-17

May

-17

Jul-

17

Sep

-17

No

v-1

7

Jan

-18

Mar

-18

May

-18

Jul-

18

Sep

-18

No

v-1

8

Jan

-19

Mar

-19

May

-19

Jul-

19

Sep

-19

No

v-1

9

Jan

-20

Mar

-20

May

-20

Jul-

20

Sep

-20

No

v-2

0

Jan

-21

Mar

-21

May

-21

Jul-

21

Sep

-21

No

v-2

1

Jan

-22

Mar

-22

May

-22

Jul-

22

Sep

-22

No

v-2

2

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 63.0 %

06/2020

Original Contract: $63,522,953 Incurred-to-Date: $39,755,919

Current Contract Value¹: $63,522,953 Incurred in June: $1,151,546

1Current Contract Value = Original contract value + executed Change Orders

Page 71: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

71 | P a g e

WORK PROGRESS: Activities this Month:

21 HDR staff contracted through HART. Hired three (3) additional senior staff members to

support HART’s Procurement Department with the CCUR RFP.

Terminated three Public Involvement (PI) subcontracts, as the PI services were transferred to HART staff.

Look Ahead: Continue to support the design and

construction of the HRTP, including assessing management needs in Project Controls.

KEY ISSUES:

Based on the average monthly expenditure rate, the current contract total will be exhausted by June 2021.

Subcontractor charges paid to date (from beginning of contract) is $5,667,627.96.

Page 72: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

72 | P a g e

B. Construction Engineering and Inspection (CEI) West CPP No.: MM-290 Contractor: PGH Wong Engineering, Inc. Contract Start Date: January 9, 2014 Contract Completion Date: December 31, 2020 Description of Work: Provides construction, engineering, and inspection services for construction contract compliance, construction scheduling, construction cost estimating, support, on-site field oversight, project controls and related construction support for the west section of the project.

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $12,156,277

DBE % Attained: 13.05%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $38,900,000

None N/A ---

Cumulative Current Report $38,900,000

* Monthly actuals are based on Pay App Verification values and are reconciled with the city’s C2HERPS system instead of CMS.

Jan

-14

Feb

-14

Mar

-14

Ap

r-1

4

May

-14

Jun

-14

Jul-

14

Au

g-1

4

Sep

-14

Oct

-14

No

v-1

4

Dec

-14

Jan

-15

Feb

-15

Mar

-15

Ap

r-1

5

May

-15

Jun

-15

Jul-

15

Au

g-1

5

Sep

-15

Oct

-15

No

v-1

5

Dec

-15

Jan

-16

Feb

-16

Mar

-16

Ap

r-1

6

May

-16

Jun

-16

Jul-

16

Au

g-1

6

Sep

-16

Oct

-16

No

v-1

6

Dec

-16

Jan

-17

Feb

-17

Mar

-17

Ap

r-1

7

May

-17

Jun

-17

Jul-

17

Au

g-1

7

Sep

-17

Oct

-17

No

v-1

7

Dec

-17

Jan

-18

Feb

-18

Mar

-18

Ap

r-1

8

May

-18

Jun

-18

Jul-

18

Au

g-1

8

Sep

-18

Oct

-18

No

v-1

8

Dec

-18

Jan

-19

Feb

-19

Mar

-19

Ap

r-1

9

May

-19

Jun

-19

Jul-

19

Au

g-1

9

Sep

-19

Oct

-19

No

v-1

9

Dec

-19

Jan

-20

Feb

-20

Mar

-20

Ap

r-2

0

May

-20

Jun

-20

Jul-

20

Au

g-2

0

Sep

-20

Oct

-20

No

v-2

0

Dec

-20

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 96.1%

06/2020

Original Contract: $54,232,480 Incurred-to-Date: $89,449,893

Current Contract Value¹: $93,132,480 Incurred in June: $993,335

1Current Contract Value = Original contract value + executed Change Orders

Page 73: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

73 | P a g e

WORK PROGRESS: Activities this Month: Resident Engineers (REs) provided the weekly project status and

issues briefings at the weekly HART Project Managers (PM) meetings.

RE’s managed assigned projects as the HART on-site field representatives for CEI, managing contract correspondence and contract change administrative processes, issuing Field Change Notices (FCNs) when required, and overseeing work.

Continued monitoring fabrication of Hālawa (Aloha Stadium) Station canopy supports.

Completed installation of the WTC station canopy fabric. Updated Monthly Progress Report Dashboards for all stations. Work-off of backlogged claims and changes progressed. Continued implementation of contract closeout processes for

WOSG and FHSG in anticipation of completion by the end of 3rd quarter 2020.

Look Ahead: Turning over infrastructure to allow

Core Systems to continue their installation.

Continue to monitor and track station canopy fabrication and installation activities to complete canopies at KHSG.

Oversee construction of assigned projects.

Closeout the UH West O‘ahu Park and Ride & UHWO Campus Road “B” (UHPRB) contract.

Continue closeout processes for WOSG, FHSG and KHR contracts.

Closeout MSF, KHG and WOFH contracts.

Change Orders Processed

CONTRACT FOM NSM SON CCO

UHPRB 0 0 1 0

WOSG 1 2 1 0

FHSG 0 0 0 0

KHSG 1 1 1 1

KHR 0 0 0 0

_______________________________________________________________________________________________________

KEY ISSUES:

The COVID-19 pandemic has continued to impact delivery of the contracted station works; mitigation for which is not yet defined; however, construction activities are continuing to proceed within constraints at impacted pace.

Completing Core Systems access requirements and balance of structures conduit for CSC follow on work.

Continuation and completion of canopy installations.

Continue working-off of backlog of outstanding claims/change issues.

Page 74: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

74 | P a g e

C. Construction Engineering and Inspection (CEI) East CPP No.: MM-596 Contractor: Stantec Consulting Services Inc. Contract Start Date: September 14, 2015 Contract Completion Date: December 31, 2021 Description of Work: Provides construction, engineering, and inspection services for construction contract compliance, construction scheduling, construction cost estimating, support, on-site field oversight, project controls and related construction support for the east section of the project.

_______________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $23,655,901

DBE % Attained: 23.18%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $47,000,000

None N/A ---

Cumulative Current Report $47,000,000

* Monthly actuals are based on Pay App Verification values and are reconciled with the city’s C2HERPS system instead of CMS.

Sep

-15

No

v-1

5

Jan

-16

Mar

-16

May

-16

Jul-

16

Sep

-16

No

v-1

6

Jan

-17

Mar

-17

May

-17

Jul-

17

Sep

-17

No

v-1

7

Jan

-18

Mar

-18

May

-18

Jul-

18

Sep

-18

No

v-1

8

Jan

-19

Mar

-19

May

-19

Jul-

19

Sep

-19

No

v-1

9

Jan

-20

Mar

-20

May

-20

Jul-

20

Sep

-20

No

v-2

0

Jan

-21

Mar

-21

May

-21

Jul-

21

Sep

-21

No

v-2

1

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 69.0%

06/2020

Original Contract: $55,036,130 Incurred-to-Date: $70,438,852

Current Contract Value¹: $102,036,130 Incurred in June: $2,163,931

1Current Contract Value = Original contract value + executed Change Orders

Page 75: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

75 | P a g e

WORK PROGRESS: Activities this Month: Current Stantec East CEI support for the HRTP is at

approximately 69% of total contract value. Performed CEI services for the AGS DB, On-Call III, On-Call

IV, CCGS DB/P3, and CCUR projects throughout the east section project limits.

Implemented COVID-19 safe work practices in the field and at all project office locations.

AGS DB overall construction progress is at 71.3% - Guideway progress is at approximately 69%, and Stations are at approximately 13%.

Precast Yard activities ongoing: 2,658/2,708 segments completed (98%).

Span erection progress for 3 gantries (Reach B-502, C-544 & E-606): 122/210 spans completed (58%).

Plinth rebar installation for Track 2 continues between Span 430-432 and Span 426-428 on Track 1 for AGS DB.

Worked with HECO on CCUR to identify a second supplier for the HECO poles that could save as much as 18 weeks on the overall procurement schedule.

Provided detailed schedules relating to multiple scenarios for the CCUR construction activity required in support of the P3 access dates.

Provided CEO consultant evaluation summary of the Stantec contract for construction progress of ongoing projects along the East Section.

Identified a Public Involvement (PI) manager to replace the manager who left the project – candidate has been approved and started on the project in June 2020.

Look Ahead: Working with HART to monitor construction

progress in support of the current substantial completion dates for ongoing AGS DB and CCUR projects.

Continuing to monitor staff resources and overall East CEI II project budget with additional HART scope requests.

Continue to work with HART in support of construction completion to support the P3 planned activities.

Supporting HART with the potential addition of a second contractor for CCUR to include the review of phasing, CEI II staffing, and potential schedule improvements to support the P3 planned activities. Working with the HART PM to update the organizational structure to meet planned construction activities.

Stantec submitted a contract amendment request to HART in June 2020, in response to requests from HART for increased construction support on various contracts through December 2021. This amendment is in review by HART. The contract amendment will need to be issued by March 2021, which is the projected date for the full expenditure of the current CEI II contract funding.

_______________________________________________________________________________________________________

KEY ISSUES:

No issues.

Page 76: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

76 | P a g e

D. General Engineering Consultant CPP No.: MM-913 Contractor: CH2M Hill, Inc. Contract Start Date: December 5, 2013 Contract Completion Date: July 4, 2021 Description of Work: Task 01 – Scheduling and Estimating Support: Task Order 01 provides staff augmentation to support scheduling and cost estimating services through the design and construction phase of the Project.

Task 02 – Interface Management and Coordination: Provide oversight of technical coordination and Configuration Management.

Task 03 – Environmental and Planning: Provide environmental and planning support to ensure compliance with appropriate decision documents for the Project; integration with other applicable state or city entities for systems, station, land use, and operation planning.

Task 04 – Design Management Services: Engineering and architectural design management services for the duration of the project.

Task 05 – Program Management and Deliverables: Program Management services throughout the entire duration of the Project to include, but not limited to the Work Breakdown Structure, Budget Staffing Plan, Monthly Progress and Status Reports, and Contract Administration.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Task Description Original Value Current Value Incurred-to-Date

1 Scheduling and Estimating Support $13,187,310 $22,556,723 $20,012,698

2 Interface Management and Coordination $5,644,829 $4,097,085 $3,599,200

3 Environmental and Planning $6,537,705 $20,303,965 $12,867,198

4 Design Management Services $16,986,250 $34,866,501 $30,217,921

5 Program Management and Deliverables $2,434,232 $1,565,057 $1,366,010

OD Other Direct Expenses $1,352,951 $1,339,444 $1,038,120

Total $46,143,277 $84,728,775 $69,101,146

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $8,300,160

DBE % Attained: 9.80%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $38,585,498

None N/A ---

Cumulative Current Report $38,585,498

Original Contract: $46,143,277 Incurred-to-Date: $69,101,146

Current Contract Value¹: $84,728,775 Incurred in June: $2,757,150

1Current Contract Value = Original contract value + executed Change Orders

Page 77: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

77 | P a g e

* Monthly actuals are based on Pay App Verification values and are reconciled with the city’s C2HERPS system instead of CMS.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

WORK PROGRESS: Activities this Month: Look Ahead: Task 01: Produced May schedule updates for PMOC meetings. Outlined schedule

updates and progress. Maintained HART’s Master Project Integrated Schedule (MPIS).

Operational Readiness – Segment 1 Turnover date is March 4, 2021. Operational Readiness – Segment 3 Turnover date is March 16, 2026.

Provided review and analysis of STG’s May 2020 progress schedule. Reviewed Elevators & Escalators schedule for coordination of installation

activities in the station contracts. Continued supporting Design and Construction with City Center Utility and

Guideway/Station coordination of activity predecessors. Began developing an interface schedule between AGS and the CSC

schedules. Provided Independent Cost Estimate (ICE) Cost to Complete for the

following: o CCUR Community Antenna Television (CATV) Installation by OTWC o CCUR Task Order 28 o CCUR Task Order 32 o CCUR Design Services During Construction (DSDC) Rough Order of

Magnitude (ROM) o UH West O‘ahu Entrance Building ICE Rev 3 o Farrington Highway and Pupukahi Street ICE

Produced Monthly Internal Schedule Progress Report. The report outlines progress on all ongoing projects.

Provided administrative support for Rapid Transit Stabilization Agreement (RTSA) activities.

Reviewed CMS payment documentation to reconcile actual invoices and payments to cost coding worksheets in Project Controls in preparation for data migration into Unifier.

Reviewed all Detail Forecast Worksheets for month-end reporting, updated variance report for the forecast sheets, and made notes as required. Completed monthly EAC requirements.

Continued reviewing request for payment for all Professional Services and Construction contracts – ensured proper coding.

Reviewed contingency for all Contract Packaging Plan’s (CPPs) project-wide.

Task 01: On-going support of ICE development or reviews of cost

estimates prepared by the CEI team for independent quality assessments. The following are projected ICE’s: o Update quantity takeoffs and Costs for CCUR

Wet/Dry Utility Task Orders o East Kapolei Park & Ride and Entrance Building o Update the CCGS & P3 ICE o ICE for Requests for Change from Contractor

(RFCC’s) and Requests for Change by HART (RFCR’s) o FOM/Negotiation Strategy Memo (NSM) Review

and Approval Continue updates of Monthly Schedule reports and

analysis. Continue providing administrative support for RTSA

activities. Incorporate updates from the Accepted and Accepted as

Noted contractor’s progress schedules. Continue developing the interface schedule between the

AGS and CSC projects. Continue to implement the Oracle Unifier system on

parts of the Business Systems, Scheduling and Cost Team Integration.

Staffing plan review for the entire project until RSD – all potential areas will be reviewed that will interface with P3 partners and will also include mitigation review should alternatives be required.

Continue updating executive summary EAC that highlights significant changes in the EAC for construction, professional services, design, management, and other contracts as required.

Dec

-13

Jan

-14

Feb

-14

Mar

-14

Ap

r-1

4M

ay-1

4Ju

n-1

4Ju

l-1

4A

ug-

14

Sep

-14

Oct

-14

No

v-1

4D

ec-1

4Ja

n-1

5Fe

b-1

5M

ar-1

5A

pr-

15

May

-15

Jun

-15

Jul-

15

Au

g-1

5Se

p-1

5O

ct-1

5N

ov-

15

Dec

-15

Jan

-16

Feb

-16

Mar

-16

Ap

r-1

6M

ay-1

6Ju

n-1

6Ju

l-1

6A

ug-

16

Sep

-16

Oct

-16

No

v-1

6D

ec-1

6Ja

n-1

7Fe

b-1

7M

ar-1

7A

pr-

17

May

-17

Jun

-17

Jul-

17

Au

g-1

7Se

p-1

7O

ct-1

7N

ov-

17

Dec

-17

Jan

-18

Feb

-18

Mar

-18

Ap

r-1

8M

ay-1

8Ju

n-1

8Ju

l-1

8A

ug-

18

Sep

-18

Oct

-18

No

v-1

8D

ec-1

8Ja

n-1

9Fe

b-1

9M

ar-1

9A

pr-

19

May

-19

Jun

-19

Jul-

19

Au

g-1

9Se

p-1

9O

ct-1

9N

ov-

19

Dec

-19

Jan

-20

Feb

-20

Mar

-20

Ap

r-2

0M

ay-2

0Ju

n-2

0Ju

l-2

0A

ug-

20

Sep

-20

Oct

-20

No

v-2

0D

ec-2

0Ja

n-2

1Fe

b-2

1M

ar-2

1A

pr-

21

May

-21

Jun

-21

Jul-

21

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 81.6%

06/2020

Page 78: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

78 | P a g e

Activities this Month (continued): Started quarterly review of all CPPs coding sheets versus baseline

allocations to ensure line items are being tracked and charged off properly.

EDD files were reviewed for capital reallocations between CPPs – no major shifts were found.

Look Ahead (continued):

Task 02:

Configuration Management (CFM) and Closeout activities performed: o Had over 40 meetings, informal discussions or e-mail exchanges with

various HART personnel to discuss: assessment of HRH’s compliance with their Configuration Management plans; and documentation and activities remaining for the closeout of the West Side Stations Groups (WSSG) contracts with special emphasis on Safety and Security items, Environmental submittals and permits, operation and maintenance manuals, training sessions, and status of lists of spare parts.

o Review of submittal logs for the WSSG contracts and tabulation of the status of select submittals (O&M manuals, training sessions, etc.) required for closeout.

o Prepared a comprehensive summary of the status of various aspects of the WSSG closeout activities for HART Core Systems.

Task 02:

CFM and WSSG Closeout tasks to be worked on are: o Review of HRH’s written response to the HART

letter regarding “Verification of Configuration Management Activities.”

o Continue expediting activities for closeout for the WSSG contracts and continue tracking status.

o Continue coordination with HART Environmental and Safety and Security Divisions to ascertain the status of closeout activities for WSSG contracts.

o Address review comments on draft of Revision 5 of the Configuration Management Plan.

o Schedule, organize and chair weekly WSSG Elevated Issues meetings and Configuration Control Committee meetings.

Task 03: Permits – assisted in obtaining a two-year extension of the U.S. Coast

Guard advanced approval authorization for 8 stream/waterway crossing. Submitted the application to extend the WOFH community noise permit to the Department of Health. Preparing the closeout form and supporting documentation for the Moanalua Stream Channel Alteration Permit (SCAP).

Environmental Analyses and Documentation – assisted in obtaining FTA approval for the post-Record of Decision (ROD) document for the Ho‘opili temporary park-and-ride facility and reconfigured permanent UHWO park-and-ride facility.

Programmatic Agreement (PA) Compliance – subcontractor Honua Consulting finalized the Interpretive Plan pursuant to PA Stipulation VII.A.

On-Call Support for Right of Way, Utilities, Environmental Planning – assisting with the assessment of the impending expiration of the Hawai‘i Department of Transportation Incidental Take License related to the endangered plant species Abutilon Menziesii and implications for HART’s Certificate of Inclusion.

Task 03: Permits – complete and submit SCAP for changes in pier

locations in Kalihi Stream. Environmental Analyses & Documentation – prepare

post-ROD evaluation for the East Kapolei park-and-ride facility.

PA Compliance – subcontractors Mason Architects and Minatoishi Architects will prepare for and assist with the presentation of National/Hawai‘i Register nominations of six historic properties adversely affected by the Project, per PA Stipulation VI.C. Prepare revised work plan for the Park Improvement Plan which is required by PA Stipulation VIII.D.

On-Call Support for Right of Way, Utilities, Environmental Planning – complete mapping of geospatial information for right-of-way acquired after the Record of Decision was issued. Prepare documentation of ridership projections and study methodology for the Before-and-After Study.

Task 04: Coordinated a field investigation at Leeward Community College parking

lot, which involved drilling and sampling of 8 borings to depths of 40 to 60 feet below the ground surface, and installation of groundwater monitoring and slope movement instrumentation. Recommendations for pavement repair to be developed in coordination with a subconsultant and HART construction staff.

Created a scope of work and figures to address erosion at guideway columns along Kaloi Channel. Repair work will involve extending drainage pipes from the base of the guideway columns to near the invert of the Channel.

Completed the design to add guardrail to the Pearl City Stream Bridge. Addressed HDOT comments on design drawings and calculations.

Reviewed 4 design submittals, 31 NCRs, 13 Field Design Changes, and 8 Notice of Design Changes for the Airport Guideway and Stations contract. Attended Task Force Meetings, presubmittal workshops and comment resolution meetings.

Continued to provide track engineering support to the Core Systems group to adjust track related issues identified by HRH.

Task 04: Assist in evaluating City Center P3 proposals. Continue to provide engineering support to CCUR to

evaluate possible guideway configuration changes to minimize utility relocation costs.

Continue to provide technical support to the CEI team overseeing the Airport Guideway and Stations contract.

Continue participation in third-party coordination meetings (technical meetings and management meetings) for various contracts. Third parties include HECO, HDOT, Department of Health (DOH), Airport, Navy and UH West O‘ahu.

Continue to provide construction support for the Kamehameha Highway Resurfacing project.

Page 79: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

79 | P a g e

Activities this Month (continued): Task 05: Monitored contract labor and sub-consultant expenditures. Updated Monthly Estimate at Completion (EAC). Participated in preparation of monthly reports. Reviewed performance of all tasks based on attachments to invoice. Received chart describing contract cost trends. Discussed flexibility and potential shifting of resources.

Look Ahead (continued): Task 05: Review five tasks versus the cost and schedule. Continue to monitor contract labor and sub-consultant

expenditures. Update Monthly EAC. Participate in preparation of monthly reports.

________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES: Task 01:

No current contractual issues. Task 02:

No current contractual issues. Task 03:

No current contractual issues. Task 04:

No current contractual issues. Task 05:

Contract extends through to July 4, 2021.

There is one option year remaining on the contract.

Page 80: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

80 | P a g e

E. Core Systems Support CPP No.: MM-962 Contractor: Lea+Elliott, Inc. Contract Start Date: February 11, 2014 Contract Completion Date: September 10, 2022

Description of Work: Provide design and construction management oversight for the Core System Design-Build-Operate-Maintain (CSDBOM) Contract, to include system commissioning, passenger services start-up, and pre-revenue operations and maintenance activities.

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

COST INFORMATION:

Disadvantaged Business Enterprise (DBE) Participation

Actual DBE Participation: $1,738,588

DBE % Attained: 2.24%

Contract Changes in June

Change No. Description Amount ($)

Cumulative Previously Reported $33,784,957

None N/A ---

Cumulative Current Report $33,784,957

* Monthly actuals are based on Pay App Verification values and are reconciled with the city’s C2HERPS system instead of CMS.

WORK PROGRESS: Activities this Month:

Project Management: o Eight (8) letters were received from HRH and reviewed. Four (4) letters were finalized

and issued by the Core Systems Oversight Consultant (CSOC). o Six (6) RFIs were received and three (3) RFIs were responded to this period. o The CSOC received 102 submittals and completed 105 submittal reviews during this

period.

Look Ahead:

Continue to monitor, observe, witness, and report on the Core Systems Contractor’s daily activities on-site and at the factories.

Feb

-14

Ap

r-1

4

Jun

-14

Au

g-1

4

Oct

-14

Dec

-14

Feb

-15

Ap

r-1

5

Jun

-15

Au

g-1

5

Oct

-15

Dec

-15

Feb

-16

Ap

r-1

6

Jun

-16

Au

g-1

6

Oct

-16

Dec

-16

Feb

-17

Ap

r-1

7

Jun

-17

Au

g-1

7

Oct

-17

Dec

-17

Feb

-18

Ap

r-1

8

Jun

-18

Au

g-1

8

Oct

-18

Dec

-18

Feb

-19

Ap

r-1

9

Jun

-19

Au

g-1

9

Oct

-19

Dec

-19

Feb

-20

Ap

r-2

0

Jun

-20

Au

g-2

0

Oct

-20

Dec

-20

Feb

-21

Ap

r-2

1

Jun

-21

Au

g-2

1

Oct

-21

Dec

-21

Feb

-22

Ap

r-2

2

Jun

-22

Au

g-2

2

Actual $ Per Month Forecast $ Per Month Actual % Forecast %

Actual 63.7%

06/2020

Original Contract: $43,988,989 Incurred-to-Date: $49,564,600

Current Contract Value¹: $77,773,946 Incurred in June: $2,206,222

1Current Contract Value = Original contract value + executed Change Orders

Page 81: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

81 | P a g e

Activities this Month (continued): o Received 1 Maintenance of Traffic (MOT) submittal and returned 1. o Developed Rough Order of Magnitude (ROM) for the proposed new entrance building at

UHWO. o Drafted Finding of Merit/No Merit (FOM) for Issue 236 Revised Date for I/O#1. o Reviewed and validated HRH’s Request for Payment #102 for work reported by HRH

during May 2020. Interface Management:

o Continued to support HART with the migration to Unifier with the Request for Interface Data (RFID) process.

o Prepared proposal for station turnover process. o Supported HART with switches guardrail flangeway dimensions issue; all switches have

been adjusted with the exception of 6 on the mainline and 1 in the yard. o Continued work on the station turnover process.

Manufacturing Oversight and Factory Inspection: o Continued oversight of Trains #15 through #18 assembly activities. o Completed shipping inspection of Train #7.

Installation Oversight: o Continued oversight for Comms installation at EKP, UHWO, HOP, WLO, WTC, LCC, PHL

and PLR. o Continued oversight of BLS installation at stations. o Continued oversight of FDAS installation at UHWO. o Continued oversight of SCADA installation at LCC, EKP and UHWO. o Completed oversight of PSGS tower installation at PLR and PHL. o Continued oversight of PSGS electrical installation at PLR. o Continued oversight of junction box (JB) and conduits remediation at ALS.

System Acceptance, Testing, and Commissioning: o Witnessing of the following testing activities:

Train #8 onboard ATC and COMM acceptance test Train #9 onboard ATC and COMM acceptance test Train #13 static and dynamic acceptance test Train #14 delivery and static acceptance test Onboard ATC Vehicle Test Procedure (VTP)/Central Test Procedure (CTP) testing

in the functional section extended to ALS Initial 3rd rail energization using PLR TPSS PLR TPSS to OCC testing MSF TEL testing (E-911 calls) MSF CCTV testing MSF Wireless Communication System (WCS) testing MSF PIS testing MSF SLAN/Communications Transmission System (CTS) testing ATC wayside phase 3 testing in different locations (LCC, PHL, PLR) HOP SLAN/CTS/CCTV/PIS Site Acceptance Test (SAT) testing LCC SLAN/CTS/CCTV SAT testing SLAN/CTS testing at WLO, WTC, WLO TPSS, HOP TPSS, WTC TPSS and LCC Gap

Breaker Station (GBS) WTC FDAS testing SCADA testing in HOP, UHWO, WLO, WTC and LCC Follow up on MDS coverage testing with Train #8 from HOP to LCC

Other Assignments: o Provided Data Room Update #12 for the P3. o Supported HART with responses to P3 RFIs and P3 Procurement activities. o Continued to manage the Traction Power Backup Generator (TPBG) Contract which

includes review of submittals, respond to RFIs, interface with necessary stakeholders, and conduct monthly progress meeting.

o Continued to manage HART’s Oversight Procedure (OP) 54 database for all stakeholders.

Look Ahead (continued): Continue to assist HART

with the resolution of change and claim issues.

Continue to assist HART with the Track Allocation Procedure.

Continue to support HART to address outstanding issues related to construction access at stations.

Continue to support HART to meet MSF Operational schedule objective and Interim Opening activities.

Continue to support HART to prepare the functional section to start integration testing on the mainline.

Support HART on P3 activities, as required.

Continue to support HART with HECO issues, including work on power quality and mitigation analysis.

Review final design, O&M, plans, and test procedures/report submittals.

Finalize passenger vehicle (PV) design solution to add car shell ventilation holes.

Finalize PV design solution to add four additional CCTV cameras.

Continue to mobilize personnel to support additional tasks added to the CSOC’s scope.

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

KEY ISSUES: o No issues.

Page 82: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

82 | P a g e

4.7 Contract Status by Contract Packaging Plan (CPP) Number

Contract Summary by CPP

(data as of Jun 30, 2020) A B C = A + B D E = D / C

CPP # CPP Title

Original Contract

Value

Change

Orders

Current Contract

Value Incurred % Exp.

Award

Date

Original

Completion

Date

Revised

Completion

Date

DB-120 West Oahu/Farrington Hwy Guideway 482,430,201 185,351,685 667,781,886 667,781,886 100% Nov-2009 Oct-2013 Dec-2018

DB-122 Westside Bird Control 0 0 0 0 0% TBD TBD TBD

DB-172 DR Horton Parking / Interim PnR Ho'opili 0 0 0 0 0% TBD TBD TBD

DB-200 Maintenance & Storage Facility 195,258,000 86,517,032 281,775,032 281,775,032 100% Jun-2011 Dec-2014 Jul-2016

DB-275 Pearl Highlands Garage, Bus Terminal, H2 Ramp 0 0 0 0 0% TBD TBD TBD

DB-320 Kamehameha Hwy Guideway 372,150,000 31,405,774 403,555,774 403,555,774 100% Jun-2011 Oct-2014 Dec-2018

DB-450 Airport Section Guideway/Stations 874,750,000 11,762,752 886,512,752 622,970,587 70% Sep-2016 May-2021 May-2021

DB-550 City Center Guideway and Station (CCGS) 100,000 134,000 234,000 206,546 88% Jan-2018 Nov-2024 Nov-2024

DBB-121 WOFM Median Landscaping 0 0 0 0 0% TBD TBD TBD

DBB-171 West Oahu Station Group 56,088,470 32,026,202 88,114,672 82,722,876 94% Jul-2015 Mar-2018 Mar-2019

DBB-271 Farrington Highway Station Group 78,999,000 39,290,879 118,289,879 92,755,232 78% Jun-2015 Jan-2018 Jan-2019

DBB-272 Waipahu Makai Entrance 0 0 0 0 0% TBD TBD TBD

DBB-371 Kamehameha Hwy Station Group 115,805,845 15,310,476 131,116,321 121,218,853 93% Jan-2016 May-2019 May-2019

DBB-385 Ramp H2R2 5,203,646 332,250 5,535,896 5,535,896 100% May-2015 Oct-2016 Nov-2017

DBB-505 Airport Section Utilities Construction 27,993,290 726,200 28,719,489 28,719,489 100% Jun-2014 Feb-2016 Oct-2016

DBB-511 City Center Utilities Relocation Construction 400,000,000 0 400,000,000 32,800,101 8% May-2018 May-2020 May-2022

DBB-525 Airport Section Guideway 7-Pier 3,973,000 54,843 4,027,843 4,027,843 100% Sep-2014 Feb-2015 Apr-2015

DBB-551 Advanced Guideway Foundations in Kaka'ako 0 0 0 0 0% TBD TBD TBD

DBB-600 Park-and-ride Lots Construction 0 0 0 0 0% TBD TBD TBD

DBB-602 UHWO Temp PnR and Campus Rd B 11,589,300 1,607,232 13,196,532 12,908,138 98% Dec-2017 Jul-2019 Jul-2019

DBB-701 Kamehameha Highway Resurfacing 25,989,989 2,455,926 28,445,915 27,703,164 97% Jul-2018 Sep-2019 Sep-2019

DBB-921 WiFi Passenger Vehicles 0 0 0 0 0% TBD TBD TBD

DBOM-920 Core Systems Design Build O/M 573,782,793 209,736,373 783,519,166 432,745,999 55% Nov-2011 Mar-2019 Jan-2025

FD-140 West Oahu Station Group 7,789,000 6,442,995 14,231,995 13,610,465 96% Jun-2012 Nov-2016 May-2020

FD-145 Dillingham / Kaka'ako (Eastside) SG FD 0 0 0 0 0% TBD TBD TBD

FD-240 Farrington Highway Stations Group 9,300,696 7,697,120 16,997,816 16,450,443 97% Jan-2011 Nov-2016 Mar-2020

FD-340 Kamehameha Hwy Station Group 8,702,592 5,034,135 13,736,727 13,201,352 96% Nov-2012 Jun-2017 Nov-2019

FD-430 Airport Sect. Guideway/Util 38,840,960 4,111,440 42,952,400 42,371,374 99% Dec-2011 Aug-2013 Jun-2017

FD-440 Airport Station Group 10,177,365 (117,545) 10,059,820 10,059,820 100% Nov-2012 Jan-2014 Jul-2015

FD-530 City Center Guideway/Util 43,948,220 14,550,073 58,498,293 57,489,264 98% Jul-2012 Mar-2014 Jul-2020

FD-550 Dillingham and Kaka'ako Station Group 18,321,918 (6,020,837) 12,301,081 12,341,565 100% Aug-2013 Sep-2014 Aug-2016

FD-600 KHG 138kV Underground Design 0 0 0 0 0% TBD TBD TBD

FD-700 Design Services for 138kV Util. Reloc. at KHG 8,766,327 0 8,766,327 4,305,543 49% Aug-2018 Nov-2021 Nov-2021

FD-701 KH Civil Design 60,000 0 60,000 60,000 100% Jan-2018 Jan-2019 Jan-2019

MI-900 Fare Collection DFI 15,464,198 444,026 15,908,224 7,570,108 48% Mar-2016 Jan-2029 Jan-2029

MI-930 Elevators & Escalators Install/Maint 50,982,714 4,879,726 55,862,440 28,141,001 50% Jul-2013 May-2018 May-2021

MI-940 Core Systems Backup Generators 8,965,000 0 8,965,000 537,500 6% Dec-2019 Apr-2021 Jan-2021

MI-950 Volt Ampere Reactive Equipment 0 0 0 0 0% TBD TBD TBD

MM-945 On-Call Construction I 1,000,000 1,000,000 2,000,000 1,999,983 100% Aug-2014 Jul-2019 Dec-2016

MM-947 On-Call Construction II 7,500,000 0 7,500,000 7,495,772 100% May-2015 May-2020 May-2020

MM-948 On-Call Construction III 20,000,000 6,000,000 26,000,000 25,665,343 99% May-2016 May-2023 May-2023

MM-949 On-Call Construction IV 46,000,000 7,000,000 53,000,000 38,728,685 73% Jan-2018 Nov-2024 Nov-2024

Page 83: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

83 | P a g e

Contract Summary by CPP

(data as of Jun 30, 2020) A B C = A + B D E = D / C

CPP # CPP Title

Original Contract

Value

Change

Orders

Current Contract

Value Incurred % Exp.

Award

Date

Original

Completion

Date

Revised

Completion

Date

MM-290 Construction Engrg & Insp CEI West 54,232,480 38,900,000 93,132,480 89,449,893 96% Jan-2014 Jan-2020 Dec-2020

MM-595 Construction Engrg & Insp CEI East I 63,083,417 (50,377,317) 12,706,100 12,711,366 100% Jan-2014 Jan-2019 Jan-2016

MM-596 Construction Engrg & Insp CEI East II 55,036,130 47,000,000 102,036,130 70,438,852 69% Sep-2015 Dec-2019 Dec-2021

MM-901 Program Mgt Support Conslt II 33,376,897 16,359,765 49,736,662 49,736,662 100% Feb-2012 Mar-2015 Mar-2017

MM-902 Program Mgt Support Conslt III 63,522,953 0 63,522,953 39,755,919 63% Jan-2017 Dec-2022 Dec-2022

MM-905 MM-905 Gen Engrg Conslt EIS/PE 0 75,995,982 75,995,982 75,995,982 100% Aug-2007 Feb-2010 Feb-2011

MM-910 MM-910 Gen Engrg Conslt FD-Construct 150,226,265 0 150,226,265 150,226,265 100% Jun-2011 Dec-2014 Dec-2014

MM-913 MM-913 Gen Engrg Recompete 46,143,277 38,585,498 84,728,775 69,101,146 82% Dec-2013 Apr-2019 Jul-2021

MM-915 HDOT Traffic Mgmt. Consult. 1,600,000 5,010,000 6,610,000 6,373,913 96% Jun-2012 Jun-2017 Jun-2019

MM-920 HDOT Coordination Conslt WOFH 3,000,000 6,500,000 9,500,000 9,483,733 100% Jun-2011 Jun-2016 Dec-2018

MM-921 HDOT Coordination Conslt KHG 16,138,390 (1,400,000) 14,738,390 8,072,380 55% Jun-2012 Feb-2025 Feb-2025

MM-922 HDOT Coordination Conslt. East 17,560,000 (7,631,360) 9,928,640 6,016,859 61% Jun-2012 Dec-2024 Dec-2024

MM-925 HDOT - WOFH/KHG Imprv Agreements 550,000 2,865,633 3,415,633 2,761,830 81% Oct-2010 Oct-2019 Oct-2019

MM-930 HDOT State SOA Manager & Consultant 1,272,400 583,142 1,855,542 990,437 53% Feb-2012 Aug-2017 Aug-2017

MM-940 Kako'o Consultant I 1,000,000 (3,106) 996,894 531,609 53% Mar-2012 Mar-2022 Mar-2022

MM-941 Kako'o Consultant II 200,000 400,000 600,000 391,667 65% Dec-2015 Jan-2018 Jan-2020

MM-946 On-Call Hazmat Assessment Consultant 12,006,227 2,075,000 14,081,227 7,724,232 55% Feb-2018 Feb-2023 Feb-2023

MM-950 OCIP Consultant I 1,250,000 0 1,250,000 1,250,000 100% May-2012 Jun-2017 May-2017

MM-951 Owner-Controlled Insurance Program 41,000,000 8,640,674 49,640,674 43,621,335 88% Apr-2014 Apr-2020 Mar-2019

MM-953 OCIP Consultant II 415,000 405,000 820,000 415,000 51% May-2017 May-2020 May-2020

MM-960 Archeological & Cultural Monitoring 2,489,748 0 2,489,748 2,935,019 118% Jan-2014 Jan-2019 Jan-2019

MM-962 Core Systems Support 43,988,989 33,784,957 77,773,946 49,564,600 64% Feb-2014 Sep-2019 Sep-2022

MM-964 Safety and Security Consultant 21,699,279 5,549,188 27,248,468 16,363,933 60% Apr-2014 Jan-2017 Jan-2019

MM-970 Fare Collection Consultant 1,178,300 640,620 1,818,920 989,464 54% Sep-2015 Dec-2019 Dec-2019

MM-975 LEED Commissioning Services for MSF 278,630 7,845 286,475 286,475 100% Oct-2010 Jan-2016 Aug-2017

PA-102 Programmatic Agreement HPC 667,275 (175,947) 491,329 274,585 56% Jul-2013 Jan-2019 Jan-2019

ART ART Contracts 2,139,500 10,000 2,149,500 807,550 38% Jan-2016 Jul-2019 Jul-2019

MM-935 Real Estate Consultant 3,000,000 5,077,665 8,077,665 7,504,910 93% Mar-2012 Mar-2017 Mar-2017

MM-936 Real Estate Consultant II 8,190,000 0 8,190,000 6,756,819 83% Sep-2016 Sep-2020 Sep-2020

MM-937 Real Estate Consultant - Maps/Surv. 2,998,000 1,130,000 4,128,000 3,086,075 75% May-2014 May-2017 May-2019

MM-981 Complex Real Property Nego. Lit. Sup 600,000 (21) 599,979 602,241 100% Sep-2016 Sep-2018 Sep-2018

MM-982 On Call Appraiser 4,000,000 0 4,000,000 654,996 16% Jun-2016 Dec-2022 Dec-2022

MM-983 Land Court Petition Services 1,200,000 0 1,200,000 102,337 9% Oct-2016 Oct-2019 Oct-2019

MM-985 On Call Appraisers II 1,261,308 0 1,261,308 354,144 28% Apr-2017 Apr-2022 Apr-2022

MM-986 Real Estate Legal Services 5,800,000 6,000,000 11,800,000 4,498,167 38% Oct-2017 Dec-2022 Dec-2022

MM-990 Design Review Consultant 4,027,781 0 4,027,781 471,099 12% Mar-2018 Dec-2024 Dec-2024

MM-991 P3 Financial Legal Services 4,282,333 6,709,384 10,991,717 8,661,498 79% Oct-2018 TBD TBD

UTIL Utility Contracts and Agreements 144,141,812 52,132,834 196,274,646 78,136,178 40% Dec-2009 Dec-2018 Jun-2018

HART-201 HART Expenses & ODCs 38,985,433 0 38,985,433 30,945,820 79% N/A N/A N/A

HART-202 Precast Yard Agreement 32,254,379 16,101,392 48,355,771 8,485,945 18% N/A N/A N/A

4,404,728,727 978,609,586 5,383,338,313 3,963,986,566

Source: HART CMS. Note: Incurred amounts for Non-Contractual Expenses (i.e. ROW transactions, debt financing costs, and City/HART contract packages) are tracked in the below table and are also included in the total incurred amount in Appendix A. 2

Non-Contractual Expenses

(data as of Jun 30, 2020)

CPP # CPP Title

Current Contract

Value Incurred

ROW Real Estate Docs/ 3P Agreements 201,003,514

CCH-100 HART/CITY CCH

14,925,228

CCH-101 HART/ City Dept of BFS 0

CCH-102 HART/ City DDC Land Division

173,182

CCH-107 HART/ City Corporation Counsel (COR) 3,088,688

CCH-108 HART / Board of Water Supply (BWS)

928,325

HART-200 HART - Labor 83,166,048

HART-201 HART Expenses & ODCs

38,893,409

OTHER Debt Financing Costs 44,189,360

TOTAL 386,367,753

Source: HART CMS.

Page 84: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

84 | P a g e

5 OVERALL PROJECT-WIDE ACTIVITIES

5.1 Overall Key Issues

Overview

Experienced Personnel: HRH is addressing the need for qualified personnel, including personnel in management, testing, commissioning, construction, quality and safety certification. HRH recently brought in a number of subcontractors to help support the team. This has been impacted by COVID-19 and is being addressed as we start to stabilize.

O&M Training: HRH commenced formal training classes on April 6, on schedule. HRH has developed an increased number of virtual training options. HRH has rescheduled training to align with hiring for the commencement of Trial Running in November.

HRH’s development of the Maintenance Management Information System (MMIS) (Maximo) is critical for Interim Opening. MMIS implementation has started, development of module 2 is in progress to finalize the system design, and the plan for data transfer has been completed. HRH has decided to change suppliers for the Developer Contract, but they are still targeting September for the MMIS to go live.

System Service Availability (SSA) Calculation Program: HRH must develop a computer program to automatically calculate the SSA for use in determining monthly Operations and Maintenance (O&M) invoices. The program must be accepted by the City. HRH is preparing to start a working group with City stakeholders to develop the business rules that will govern SSA calculation. The first draft of these rules is under HART review.

Trial Run Plan: HRH has begun development of plans for the trial run period. Stakeholder meetings were held to secure buy in. Detailed plans are being written to describe how system demonstration, pre-revenue O&M readiness testing, and the full-scale emergency drill will be scheduled, resourced, conducted, and evaluated.

Automated Yard Operation: Closure of open issues of the DBOM Core Systems contract are needed, particularly the communications system and the integration with the vehicles and automated train control systems. HART is working with HRH to address the Operations Control Center’s (OCC’s) outstanding issues that are necessary for the start of Functional Track testing.

Functional Track Integration Testing: Completion of all equipment installation and testing in the Functional Section is underway prior to system integration testing. Remaining critical subsystems are Communications and SCADA. Realignment of critical goals have been made to meet the revised Interim Opening #1 date. The revised goals and schedule may have to be reassessed when taking into consideration future issues related to COVID-19.

AGS integrated schedule: The latest draft of the schedule shows a delay of turnover dates to the Core Systems Contractor. This would impact Interim Opening #2. Core Systems is working with the Stantec RE and HRH construction team to try and mitigate as much as possible.

Procurement of materials by HRH has been delayed and caused schedule slippage. HRH management has added on-site procurement personnel and obtained additional support from headquarters. This issue is further amplified due to additional design changes and COVID-19, but HRH is progressing.

Canopy arms are installed at all stations with the exception of Hālawa (Aloha Stadium) Station. Completion of the final canopy arm design and shop drawing development/approval for Hālawa (Aloha Stadium) Station has continued to delay the completion and shipping of the canopy arms. They are scheduled to start installation in July 2020. Canopy fabric is installed at Kualaka‘i (East Kapolei), Keone‘ae (University of Hawai‘i West O‘ahu), Honouliuli (Ho‘opili), Pouhala (Waipahu Transit Center), Hālaulani (Leeward Community College) and Hō‘ae‘ae (West Loch). Fabric is installed at Kalauao (Pearlridge), with the exception of the center panels; installation will be completed after correction of a roofing conflict. Waiawa (Pearl Highlands) is scheduled for July 2020 and Hālawa (Aloha Stadium) fabric is scheduled to start in September 2020. Coordinating canopy arm and fabric installation with Core Systems to lessen the impact on train testing.

HART is dependent on the electrical design prepared by HECO for the electrical power line relocation work that must be performed by HART’s CCUR contractor. As HART’s civil design becomes available, HECO begins their electrical design. HART is continuing to meet at all levels within HECO to coordinate the required designs for the CCUR contract.

The ability to meet the required CCUR construction access dates as put forth in the P3/DB solicitation is critical. HART is in the process of finalizing a solicitation package to bring on board additional contractors to facilitate construction, as this would provide additional resources and means and methods to prosecute the work.

Page 85: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

85 | P a g e

5.2 Permits Permits Submitted and In-Progress HART submitted the University of Hawai‘i Park and Ride stockpiling permit. HART submitted a trenching permit for City Center Utility Relocation (Task Order 14). HART received the extension of the advanced approval that authorizes construction of the project over eight

streams under U.S. Coast Guard jurisdiction. HART submitted the Community Noise Permit for the West O‘ahu Farrington Highway section.

Look Ahead HART will be submitting permit applications for utility relocations across the Kapālama Canal.

5.3 Hawai'i Department of Transportation (HDOT) Agreements Activities this Month HDOT Attorney General is currently reviewing the WOFH Master Agreement and Joint Use and Occupancy

Agreement (JUOA) Amendment 1 draft amendments. The latest update from HDOT is that completion of their review and comments is expected in July 2020.

Ongoing tracking of the progress of the projects for the Highway Improvement Agreement. Coordinating documentation of the highway improvement projects with HDOT and Federal Highway Administration (FHWA) for reimbursement. Reimbursement for approximately $20 million of completed highway improvement work is being pursued for the current federal fiscal year. FHWA is reviewing files for compliance on the solicitation of items that require a waiver to disburse funding for the Highway Improvements. For the Kuala left-turn Highway Improvement project, HART is in the process of determining which contract the work is to be performed. Pupukahi right-turn and traffic signal cost estimate approvals are being coordinated with HDOT, FHWA and on-call.

DTS comments on the Draft WOFH Utility Abandonment agreement is currently being reviewed and addressed. Record drawings/as-builts need to be provided for WOFH Utilities for Exhibit A of the agreement.

Look Ahead Route externally for execution of the West O‘ahu Farrington Highway Master Agreement and Joint Use and

Occupancy Agreement Amendment 1. Route to BFS, followed by final legal review, estimated fourth quarter 2020. Presentation to the Board and City Council to follow, estimated fourth quarter 2020.

The West O‘ahu Farrington Highway Joint Use and Occupancy Agreement Amendment 2 is being prepared and includes maintenance agreements related to guideway permanent Best Management Practice’s (BMPs) and traffic signal mounts on the pedestrian bridge at the UHWO Station. WOFH Permanent BMP report acceptance by HDOT is expected in July 2020. Waiawa Stream Operations and Maintenance Manual to be drafted by HART. Expected completion of reports is July 2020. Recommendations to be added to the JUOA Amendment 2.

Comment resolution and resubmittal of the Draft Utility Abandonment agreement to DTS is expected to be completed in July 2020. Upon HART/DTS concurrence, external routing to HDOT is expected in the third quarter of 2020.

Page 86: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

86 | P a g e

5.4 Utility Agreements

Utility Agreements Status Matrix

Utility Owner Status WOFH KHG Airport City Center

ESA UCA ESA UCA UCA COMBINED ESA UCA

AT&T (Corporation)

Executed 05/11/11 12/20/11 5/18/12

Including with ESA

Not Required

12/26/13 05/03/17 NTP 05/12/11 12/21/11

Amd 01 07/01/11 HRS Ch. 104 11/22/16

AT&T Corp. (Public Sector)

Executed 12/26/13 08/27/18 12/26/13

NTP

Chevron

Executed 12/04/09

11/04/11

NTP 12/22/09 11/15/11

Amd 01 07/01/11

Hawaiian Telcom

Executed 05/20/10 11/17/14 05/10/12 12/31/14 05/28/15 09/27/13 04/06/17

NTP 06/14/10 11/18/14

Amd 01 07/01/11 04/13/15 05/11/17 11/19/18 09/20/19

Amd 02 05/10/12

HECO

Design

Services Construction

Services Design

Services Construction

Services Design

Services Construction

Services Design

Services Construction

Services

Executed 11/20/13 11/29/13 11/20/13 11/29/13 11/20/13

11/25/13

NTP 11/20/13 11/29/13 11/20/13 11/29/13 11/20/13 11/25/13

Executed 05/16/18

Change Order 01

06/30/17 11/13/19 02/22/18

Working on

Change Order 01

Change Order 02

02/22/18 11/13/19

Mem

ora

nd

um

s o

f

Un

der

stan

din

g

08/07/14 – Construction Drawings

05/01/15 – Access

05/15/15 – Derrick Truck

06/23/15 – Master Agreement

06/09/15 – MSF Advanced Construction

09/16/15 – Right of Entry

10/12/15 – Clearance (West) 11/10/15 – Dillingham Blvd Materials

07/13/16 – KHG Vertical Clearance

Power Quality MOU (Working on MOU)

08/16/18 - Airport Clearance Agreement

05/15/19 – Vehicle Storage MOU

08/13/19 - Airport Energization MOU

Charter Communications/Oceanic Time Warner Cable

Executed 12/08/09 12/21/11 01/09/12 06/02/14 12/19/14

04/03/13 9/22/16

NTP 12/22/09 04/04/13 9/30/16

Amd 01 07/01/11 02/27/14 HRS Ch. 104 07/06/18 Finalizing

agreement documents

Amd 02 10/07/13 HRS Ch. 104

Pacific Lightnet/ Wavecom

Executed 04/28/10 03/12/12 02/15/12

NTP 04/29/10 03/13/12 02/16/12

Amd 01 07/01/11 HRS Ch. 104

Page 87: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

87 | P a g e

Utility Agreements Status Matrix

Utility Owner Status WOFH KHG Airport City Center

ESA UCA ESA UCA UCA COMBINED ESA UCA

Sandwich Isle Communications

Executed 05/20/10 04/20/12

NTP 06/08/10

Amd 01 07/01/11

Hawai'i GAS

Executed 12/18/09 06/30/11 06/01/12 04/14/14

08/19/14 09/27/13

05/08/15

NTP 12/22/09 07/12/11 08/20/14 05/11/15

Amd 01 07/01/11 10/17/14 08/28/14 08/31/17 10/24/17

Amd 02 05/09/16 10/23/15 11/03/19

Received CC final

drawings. Working on

AMD 02

Amd 03 HRS Ch. 104

Level 3/TW Telecom

Executed 12/02/09

02/14/12 Oceanic to relocate for TW Telecom

10/11/12 Oceanic to relocate for TW Telecom NTP 12/22/09 02/16/12

Amd 01 07/01/11

Tesoro

Executed

02/15/12 09/12/13

08/27/13

NTP 02/16/12 09/03/13

Amd 01 09/12/14

Amd 02 05/13/15

Amd 03 HRS Ch. 104

Legend = Action this month COR = Corporation Counsel UCA = Utility Construction Agreement

= Not applicable ESA = Engineering Services Agreement

UFRCRA = Combined Engineering and Construction Utility Agreement

Overall Key Issues No key issues to report this month.

HECO

Ka‘aahi Substation near MSF area o Supplemental Agreement (SA) –HART received a letter from HECO dated June 19, 2020, stating that based

on HART’s latest load forecast of Jan. 15, 2020, the service date remains unchanged and that it will not start construction until HART executes the SA. HECO needs 10 consecutive months to construct the substation. Also, City DTS is now agreeable to co-signing a SA with HART and HECO; HART is awaiting final comments from City DTS.

o Post-Record of Decision (ROD) Environmental Determination – HART received a letter from the Federal Transit Administration dated May 29, 2020, stating that HECO’s proposed 58-foot antenna pole (in lieu of the extension of fiber optic cable) in the substation will not cause significant environmental impacts and that the preparation of a Supplementary Environmental Impact Statement (EIS) is not necessary.

Mitigation of Horizontal Working Clearance Requirements o KHG 138kV Relocation project: Refer to the Design Services for 138kV Utilities Relocation at KHG contract

page in Section 4.3 for the latest updates. o Specialized Vehicle Storage Yard at MSF: The security fencing is now targeted to be complete by the end of

July 2020. In the meantime, HECO has stored two of its older vehicles at the MSF while storing its new specialized vehicles at its own yard.

Page 88: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

88 | P a g e

5.5 Right-of-Way Key Issues ROW is engaging with property owners along the City Center Guideway and Stations (CCGS) Section to acquire the requisite property rights, via Right of Entry and Possession and Use Agreements (ROE/PUA) for Land Court properties pending final Grant of Easement or Deed. When acquisition by purchase is not reasonably available, ROW uses eminent domain to acquire the requisite property interests. HART’s counsel prosecutes its eminent domain actions and the respective motions for immediate possession of the property so that the construction access may be obtained. Current eminent domain actions:

o West O‘ahu/Farrington: Parcel Identification Number (PID) 102 R. Lee: HART has possession of the property, while the

Lees remediate contamination on the parcel. The judge overseeing this case has been serving as a mediator and facilitator, assisting the property owner in completing its obligations under the settlement. The judge holds biweekly status conferences with the parties and has engaged the Hawai‘i Department of Health (HDOH) in facilitating the completion of the remediation of the property. The HDOH has issued one “no further action” letter and there now remain three sections of the property to remediate.

o Airport: HART has possession of the subject property in the four cases filed with the court. For

PID 318 Masters, the parties are closing on a settlement. PID 306 SCI and PID 319 SCI were consolidated and mediation is ongoing; trial is postponed to after Aug. 31, 2020.

o City Center: Eight cases are filed with the court and are active (PID 400 Blood Bank, PID 472A Desky, PID 439

Yamauchi, PID 485 Scott Shoe, Howard Hughes various parcels, PID 433 HECO Iwilei, PID 502 Yung Soon Tajima Trust, PID 503 JY Trading Co.). HART filed its eminent domain action and motion for order putting HART in possession of PID 433 HECO Iwilei. HECO filed a challenge to HART’s Order of Possession of the property for the HECO Dillingham Avenue property. HART performed a Phase II environmental survey on this property and will also have one done on the HECO downtown property on Ala Moana Boulevard. PID 439 Yamauchi executed a settlement agreement and counsel will formally dismiss this case once the Land Court process is completed. Possession has been granted for PID 400 Blood Bank, PID 472A Desky, PID 485 Scott Shoe, Howard Hughes various parcels, and PID 503 JY Trading Co. HART began processing approvals to file eminent domain action for PID 474 Ka’a Limited Partnership.

During the month of May 2019, the FTA conducted a review of the relocation program and the FTA issued a report on Sept. 23, 2019 regarding its findings. The report details measures that must be taken to bring the closed relocation files into compliance, including interviewing the relocated parties. The FTA approved HART’s plan to bring the files into compliance, which was transmitted on Oct. 31, 2019. HART contracted with a team that met with the FTA in January 2020 to discuss the implementation of the plan. The corrective action plan team is auditing files and prepared initial contact to displaced parties in June 2020. The team provides regular reports on progress to HART and the FTA.

Regular meetings between the CCUR team, Project Controls and ROW to track progress, identify opportunities, foresee obstacles to access for critically needed parcels, and budget are ongoing. Revisions in designs made necessary by guideway and utility redesigns will require revised and new acquisitions along Dillingham and Halekauwila Street, including acquisitions currently in negotiation.

The FTA agreed to the proposed multi-agency approach to the acquisition and tenant relocations for PID 493 Watumull which is the site for the Ala Moana Station. HART has partnered with the City and County of Honolulu’s DTS, Department of Design and Construction (DDC), and BFS to facilitate. The owner recently transmitted a counter-offer for the City’s consideration. Relocation assistance work is underway.

Page 89: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

89 | P a g e

HART recently entered into agreements with Latter Day Saints (LDS), Otani and General Growth Properties (GGP) Ala Moana to obtain necessary property rights; the properties are currently in escrow.

Relocation assistance is being provided to the tenant and PID 404 Takara. HART and the owner are working to finalize an agreement.

ROW continues to monitor negotiations between Design and Construction and HECO regarding issues involving

clearance requirements due to maintenance equipment staging needs for 138kV poles and lines located next to the HART guideway system. These discussions will identify additional acquisitions of non-asset easements on behalf of HECO or other utility agencies and/or companies.

Negotiations are continuing with UH, including securing a construction ROE Agreement with the Honolulu

Community College.

Acquisitions Figure 7. Right-of-Way Status for the Parcels

Relocations Figure 8. Relocation Status for the Occupants

Page 90: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

90 | P a g e

Non-Right of Way Figure 9. Temporary Construction Easements and Utility

Status of Inter-Governmental Agreements Figure 10. Inter-Governmental Agreement Status The status of agreements between HART and other government entities. Objectives are:

1) Obtain Construction Right of Entry, Executive Orders, Set Asides, Jurisdiction Transfers, Joint Use Agreements, licenses, easements, Memorandum of Understanding (MOUs), Memorandum of Agreement (MOAs), etc. with impacted government agencies. Government agencies HART is working with include: Federal (GSA, Navy, USPS, Office of Interior), State (HDOT-Highways & Air, DLNR, DAGS, HCDA, DOE, Aloha Stadium, UH), and County Agencies (DTS, DPP, DFM, BFS, DDC, Parks, DLM, ENV). Some government agencies may choose to issue the final documents after construction is substantially underway or near completion.

2) To help negotiate and/or obtain Rights of Entry for certain other construction-related activities as requested by Design and Construction. Such agreements may include: geotechnical borings, soil testing, environmental surveys, bus stop agreements, construction lay down surveys, and other construction-related needs. There may be other Rights of Entry and Agreements which may not involve ROW acquisition or relocation. ROW will assist other HART departments, should requests be authorized and funded.

3) Agreements to be executed are in white. Executed agreements are in grey at the end of the table, and while these parcels may be accessible at this time for construction, further documentation may also be required to complete the acquisition.

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

STATE AGREEMENTS

UH – University of Hawai‘i, West O‘ahu (UHWO-125)

Construction Right of Entry and Occupancy & Use Agreement for East Kapolei Park & Ride

TBD/ Estimate

2021

WOFH Yes Interim park and ride (300 spaces) completed.

3rd Amendment to CROE has been fully executed. It allows for

installation of electrical connections from Road B to station area and

subsequently into interim parking.

Page 91: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

91 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

UH – Urban Gardens (201A) Conveyance to HDOT (H) – Dept. of Transportation Highways

September 2020

KHG Yes

2nd Amendment to HART ROE fully executed. Based on final Phase II

results, HDOT has issued concurrence letter. Construction is

nearing completion. Quitclaim deed under review by HDOT-Highways.

Subdivision map completed.

UH – Honolulu Community College (HCC) (424A)

Construction Right of Entry for guideway & station

September 2020

City Center No Pending design finalization. Working with UH regarding ROE Agreement.

Third round of comments on Draft of CROE Agreement under review by

UH. A portion of planned demolition and preliminary construction

activities completed under letter agreement with Royal Construction.

DLNR – Dept of Land & Natural Resources (124)

Kapolei Easement Agreement for overhead guideway and for park and ride facility

September 2020

WOFH

Yes In process. DPP approved subdivision application for guideway easement footprint. Transmitted to DLNR for

land court submittal. Discussions are ongoing regarding language

permitting guideway easement. Request to expand Park and Ride

CROE (executed in 2013) from 5 to 11 acres was approved by the Board

of Land and Natural Resources (BLNR) at its May 8, 2020 Board Meeting. A Right of Entry will be

issued for 11 acres.

DLNR/C&C Wastewater Div (437B)

Easement Agreement December 2020

City Center Yes Waiting for the easement map to be finalized by DLNR.

DOE - Waipahu H.S. (118) Permanent Easement (State owned portion)

July 2020

WOFH Yes

In process. Construction is not impacted as the ROE for right to access and construct is executed.

With DOE for review. Working with DLNR for permanent rights.

DOE – Waipahu H.S. (117) Permanent Easement (City portion)

December 2020

WOFH Yes Construction is not impacted as the Master/ Construction Agreement is

executed. Still waiting for DOE to sign off on Right of Entry extension for

HECO and HART that was submitted in March 2020. It is still with the

attorney general for review. The city owned portion of Waipahu H.S. is being transferred to the State of Hawai‘i. Revised easement map

being provided by RM Towill. HART will submit to DOE and the State to finalize the easement map so the

subdivision process can commence.

Page 92: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

92 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

Aloha Stadium / Dept. of Accounting & General Services (DAGS) (207A to C)

Easement Agreement September 2020

KHG Yes In process. Creating maps that separate the parking area from the station and guideway easements.

2016 MOU being revised and updated to reflect the evolving

nature of the agreement between HART and Stadium Authority prior to permanent easements being put in

place. DTS will be involved. Final revised easement map submitted to DLNR, DAGS and Stadium Authority for approval. BWS easement will be

considered at 7/24 BLNR Board meeting.

Aloha Stadium/ DAGS (207B)

Ground Lease Agreement for bus interface and shared parking area

July 2020

KHG Yes In process. Agreement format may impact map approvals from Stadium

Authority, DAGS and DLNR. Construction is not impacted as the

ROE for right to access and construct is executed. Parking area rights will

be granted via long term lease. Relocation of parking spaces will be

addressed to accommodate TOD development at the Stadium.

HDOT(H) – Dept. of Transportation Highways (100,100-A, 304, 400-A, 400-B)

Master Agreement Amendment

July 2020

WOFH Yes Construction is not impacted as the Joint Use & Occupancy (JU&O)

Agreement for right to access and construct is executed.

HDOT(H) and (A) – Dept of Transportation Highways & Airports (100,100-A, 301, 304, 304, 400-A, 400-B)

Master Agreement for KHG, Airport and City Center Amendment

July 2020

KHG, Airport,

City Center

Yes for KHG & Airport

Construction is not impacted as the JU&O for right to access and

construct for City Center will be executed when the Notice to

Proceed (NTP) is issued.

HDOT(H) (100,100-A, 304, 400-A, 400-B)

JU&O Sub-agreement July 2020

WOFH Yes In process. Construction is not impacted as the JU&O for right to access and construct is executed.

HDOT(H) (100,100-A, 304, 400-A, 400-B)

JU&O Sub-agreement July 2020

City Center In process. Construction is not impacted as the JU&O will be executed when NTP is issued.

HCDA -HI Community Development Authority (444A, 450,463BE-5-B, 475)

Construction ROE, License Agreement, & Final Disposition

August 2020

City Center Coordination is ongoing. ROE for Royal Contracting pre-construction

activities extended. Final disposition pending revised design.

DAGS (441-A) Construction Right of Entry July 2020

City Center A street is being designed substantially within the footprint of

Easement U as requested by DAGS as a precondition to ROE. The street will be provided as in-kind consideration

for a staging yard for the 3rd party contractor. Survey for staging area

being conducted and street concept plan undergoing refinement. Utility

work descoped; will now be performed by the P3 contractor.

Page 93: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

93 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

DAGS (441-A) Guideway and Utility Easement Agreement

August 2020

City Center Design plans for the Kaaahi Street extension are still being refined and

vetted with the City.

DAGS (443-A) Utility, (Communications & Electrical) Agreement

September 2020

City Center No On-going negotiations with DAGS to secure right of entry. Letter requesting issuance of ROE

submitted to DLNR/DAGS on June 22, 2020.

DAGS (443-B) Guideway and TCE Agreement

December 2020

City Center No On-going negotiations with DAGS to secure right of entry. Agreement

being negotiated for loss of parking revenue during construction of

column in parking area.

Kalihi Kai Elementary (501) Right of Entry from DOE/DLNR

October 2020

City Center Communications with DOE is ongoing regarding “in kind”

consideration in the form of air conditioning equipment. DOE wants

this decided prior to issuance of ROE.

Kalihi Kai Elementary (501) Easement Agreement March 2021

City Center On hold pending design finalization. Once ROE is in place, subdivision

map to be completed and submitted to DPP. Notice of Intent to Acquire

containing enlarged electrical footprint for electrical easement and a new column easement was sent in

late May 2020.

State of Hawaii - DOT (504) Easement Agreement Pending City Center HECO amending easement design and under review.

FEDERAL AGREEMENTS

USPS (301) Permanent Easement 2021 Airport Via GOE Construction is not impacted. Grant of Easements were recorded in

Regular System to facilitate entry onto property for construction even though the property is registered in Land Court. Now petitions for Land Court designation of easements are

being developed for submittal to Land Court.

U.S. Gov't/General Services Administration (GSA)/Federal Courthouse (443C)

Master Agreement, Security & Landscape License Agreement, Utility License Agreement, Guideway License Agreement

September 2020

City Center Master Agreement fully executed on 8/13/19.

Design changes finalized and signed

maps, which reflect relocation of guideway supports onto GSA

property, were shared with GSA. Negotiations to amend Master

Agreement are ongoing. Appraisal underway to revalue the guideway

easement; expected by late July 2020.

GSA Federal Courthouse Quitclaim Easement Documents for Utility and Guideway Easements

2020 City Center Under development.

CITY AGREEMENTS

Page 94: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

94 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

BFS – Dept. of Budget & Fiscal Svcs (204A)

Intra-Agency coordination which may take the form of a ROE, letter agreement, or license (Continental Investment)

2020 KHG Via intra-agency

coordination

In process.

DFM (423A) Work Permit (Kapalama Stream for Street, Bridge, and Guideway Improvements)

2020 City Center DFM/DLM granted entry.

DFM (423A) Easement Agreement for Utilities

2020 City Center Utility agreements on hold pending design finalization.

The property work access was granted in late March by DFM.

DTS – Dept. of Transportation Svcs (322)

Intra-Agency coordination which may take the form of a ROE, letter agreement, or license (Middle Street Station)

2020 Airport Via intra agency

coordination

In process.

OTHER AGREEMENTS

D.R. Horton (101B) MOU Construction Right of Entry Amendment – D.R. Horton & HART Easement Agreement – D.R. Horton & HECO

July 2020

WOFH Yes MOU draft circulating for comments. PH I environmental survey

completed. D.R. Horton (DRH) counsel and COR counsel speaking

directly to address remaining issues on license agreement.

Negotiations finalized regarding the License Agreement to cover

increases in park and ride construction costs, GET tax on

license and property taxes. Signature version of License Agreement being

prepared.

D.R. Horton Final Easement Agreement September 2020

WOFH Yes Construction is not impacted. D.R. Horton is completing further

subdivision of the property. Maps will be updated with new Tax Map

Key prior to submittal of application to DPP.

EXECUTED AGREEMENTS

CITY AGREEMENTS

BFS (205A) Jurisdictional transfer from DFM to HART of Kamehameha Hwy/Makalapa Manor

Airport Yes Jurisdictional Transfer from BFS Letter dated 8/26/11.

DPR - Dept. of Parks & Recreation (119)

Construction consent to construct for MSF drainage

WOFH Yes

BFS / DFM (Dept. of Facility & Maintenance) (437C)

Jurisdictional Transfer (Awa Triangle, N. Nimitz & Awa St.)

City Center Jurisdictional transfer completed July 9, 2018.

STATE AGREEMENTS

Page 95: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

95 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

DLNR/C&C Wastewater Div (437B)

Construction Right of Entry

City Center Yes Construction ROE obtained from

DLNR 10/21/17. Subdivision submitted with DPP 1/1/18.

UH – University of Hawai‘i Master Agreement is not needed as the ROE for right to access and construct will be executed separately by each campus.

WOFH, KHG, City

Center

Will be executed by each campus

Construction is not impacted as the ROE for right to access and construct

will be executed by each campus.

UH Pre-Construction Right of Entry and Amendment

WOFH, KHG, City

Center

Yes

UH - West O‘ahu (UHWO) (125)

Construction Right of Entry for Station, Temporary Park & Ride, and Amendment for Construction of Road B

WOFH Yes

UH - Leeward Community College (LCC) (122)

Construction Right of Entry for Guideway

WOFH Yes

UH – LCC (122) Construction Right of Entry for Station

WOFH Yes

UH - Urban Gardens (201A)

Construction Right of Entry KHG Yes

DLNR – Dept. of Land and Natural Resources (124)

Kapolei Construction Right of Entry for overhead guideway and for park and ride facility

WOFH Yes CROE has been granted once a year by letter. Working on permanent

Easement with DLNR. Currently with DPP for subdivision.

DLNR (320) Keehi Lagoon Construction Right of Entry

Airport Yes

DOE – Dept. of Education Waipahu H.S. (117, 118)

Master/Construction Agreement

WOFH Yes

DOE/DLNR for Waipahu H.S. (118)

Construction Right of Entry WOFH Yes Executed by DLNR with DOE concurrence.

Aloha Stadium / Dept of Accounting & General Services (DAGS) (207)

MOU for guideway & station KHG Yes

Aloha Stadium/DAGS Construction Right of Entry for guideway

KHG Yes

Aloha Stadium/DAGS Construction Right of Entry for station park and ride

KHG Yes

HDOT(H) – Dept. of Transportation Highways (100)

Master Agreement for HDOT Highways for WOFH

WOFH Yes

HDOT(H) and (A) – Dept. of Transportation Highways & Airports

Master Agreement for HDOT Highways and Airports, for KHG, Airport and City Center Sections

KHG, Airport,

City Center

Yes except for City Center

whose JU&O will be

executed when the NTP

is issued

HDOT(H) JU&O Sub-agreement WOFH Yes

HDOT(H) JU&O Sub-agreement KHG Yes

Page 96: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

96 | P a g e

Inter-Governmental Agreements

Agency

Pending Agreements (Executed Agreements

are shaded grey)

Target

Section

Construction Right of Entry

(CROE) Obtained

Notes/Remarks

HDOT(H) JU&O Sub-agreement Airport Yes

HDOT (A) - Dept. of Transportation Airports

Airport Special Provisions for Right of Entry

Airport Yes

HDOT(A) JU&O Sub-agreement for Airport Division parcels

Airport Yes

HDOT(A) (301A) Easement document for Airport Division parcel (Main guideway easement)

Airport Yes Ongoing intra-agency coordination. Construction is not impacted as the Special Provisions and the JU&O for

right to access and construct is executed.

DHHL - Dept. of Hawaiian Home Lands (Exchange w/ Varona Village) (115A)

MOA, License/ROE from DHHL, City Council Resolution

WOFH, MSF Yes DLNR approves withdraw from GEO 571 7/14/17. DFM accepts road

widening and now City jurisdiction.

OCCC - Dept. of Public Safety, Oahu Community Correctional Center (400A)

MOU

City Center Yes

OCCC/DLNR Construction Right of Entry

City Center Yes

DLNR/OCCC Letter of Responsibility from City-DFM/Road

City Center Yes

HCDA -HI Community Development Authority (444A, 450, 463B, E-5-B, 475)

Pre-construction Right of Entry

City Center Yes, effective upon request

Verbal approval granted by the HCDA Board in 6/2016.

FEDERAL AGREEMENTS

U.S. Navy (116A) Grant of Easements for Maintenance & Storage Facility (MSF)/Rail Operations Center (ROC) offsite drainage and sewer easements

WOFH Yes Per Letter #N62478-12-RP00011 dated 6/28/12 confirming easement

from Navy.

U.S. Navy (300) Licenses/Construction Right of Entry

WOFH, KHG,

Airport

Yes 6/22/15 – 5 Yrs. License ends in 2020. All utility work needs to be

completed by then.

U.S. Navy Easement Agreements WOFH, KHG,

Airport

Yes Grant of Easement executed. Grant of Easement 8/22/16.

U.S. Navy Pearl Harbor Station Acquisition of Fee Transfer

Airport Yes Quitclaim deed executed 2/25/16.

U.S. Post Office (USPS) (301)

Honolulu Processing Center acquisition

Airport Yes Acquisition completed in regular system. Need to process through Land Court to complete process.

Funds already paid. USPS Land Court share to complete process is in

escrow.

OTHER AGREEMENTS

D.R. Horton Construction Right of Entry - D.R. Horton & HECO

WOFH Yes Executed 5/11/2018.

Page 97: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

97 | P a g e

6 MANAGEMENT AND ADMINISTRATIVE UPDATES

6.1 Safety and Security (S&S) Key Milestone Progress HART Safety works with the Core Systems Oversight Consultant (CSOC) to oversee HRH preparation for MSF

Attended Operations in the yard and the Functional Track Section. o Expected completion of HRH requirements for the Attended Operations Milestone is August 2020.

HART Safety conducts monthly certification meetings with each station group project team to close out safety and security critical Open Items in preparation for substantial completion.

HART Safety is working with Project Controls to ensure Safety and Security Certification Milestones and related activities are identified and updated on the Master Project Schedule.

The Construction Safety and Security Plan is under revision; estimated acceptance is July 2020. Key Issues Scheduled certification milestones for Segment 1 may be delayed due to the following open requirements:

MSF Attended Operations Milestone (Hold Point) o HRH to complete open items in regard to ATC, COMM, SIT and SCADA.

Specification Testing Conformance Checklists (STCC) Open Items (58)

ATC – 3 Open out of 21

Communications – 35 Open out of 38

System Integration & Testing – 9 Open out of 22

SCADA – 6 Open out of 14 o HRH to complete 8 open items in regard to Operational Readiness. o HRH to complete 13 STCC open items for PVs fleet design verification and individual certifications. o HART Safety is following up with CSOC and HRH for MSF Systems Certification (4 STCC Open Items)

Inspection and Test Procedures for MSF Yard Communication Inspection and Test Report for MSF Yard Communication On-site Inspection and Test Report for MSF Yard Uninterruptible Power Supply (UPS) Panel Distribution Unit Low Voltage (LV) Schematic Drawing for MSF Yard Control Bungalow

(YCB) UPS o Maintenance of Way (MOW) vehicles certification – pending approved STCC documentation for the

Multiple Purpose Vehicle (MPV) acceptance. HART Safety and CSOC are following up with HRH to close the following STCC open item (1):

HNL-23015 Accepted as Noted –Resubmit (ANR): O&M Manual

HART Safety witnessed the final acceptance test and is awaiting HRH’s submittal of the updated O&M Manual.

System Integration Testing Milestone (Hold Point) o HART Safety is working with CSOC to identify the pre-requisite requirements needed for the System

Integration Testing Hold Point for the following procedures HNL-12428 IST Procedure – Single Tracking Mode HNL-12434 IST Procedure – Operation under Headway Regulation HNL-12435 IST Procedure – Operation under Schedule Regulation

Page 98: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

98 | P a g e

6.1.1 Project Overall Certification Status

Project Overall Certification Status - Progress Total Items

Total Verified 1/1/20

Total Verified 6/30/20 Total Remaining

Δ YTD

% Complete

% Remaining

Segment 1 Revenue Service 25,283 20,095 22,638 2,645 2,543 90% 10%

Segment 2 Revenue Service 9,849 4,951 5,240 4,609 289 53% 47%

Segment 3 Revenue Service 7,652 4 4 7,648 0 0% 100%

Final Overall 42,784 25,050 27,882 14,902 2,832 65% 35%

6.1.2 Segment 1 Revenue Service Date Certification Status

Segment 1 Certification Status - Progress Anticipated Completion

Total Items

Total Verified 1/1/20

Total Verified 6/30/20

Total Remaining

Δ YTD

% Complete

% Remaining

MSF (Civil & Systems) AUG 2020 740 725 734 6 9 99% 1%

Guideway (Civil & Systems) CLOSED 7,368 7,368 7,368 0 - 100% 0%

Stations & Parking (Civil & Systems) SEPT 2020 7,330 6,884 7,185 145 301 98% 2%

Passenger Vehicle (PT 8-14) and Fleet Requirements

NOV 2020 1,603 519 1,203 400 684 75% 25%

MOW Vehicles JUL 2020 458 454 457 1 3 99% 1%

Traction Electrification System (TES) AUG 2020 301 204 218 83 14 72% 28%

Automatic Train Control (ATC) AUG 2020 346 301 314 32 13 91% 9%

Supervisory Control and Data Acquisition (SCADA)

AUG 2020 84 56 56 28 0 67% 33%

Communication SEPT 2020 983 676 685 298 9 70% 30%

System Integration Testing (SIT) NOV 2020 138 71 71 67 0 51% 49%

Platform Screen Gate System (PSGS) JUL 2020 96 66 71 25 5 74% 26%

Elevators / Escalators AUG 2020 508 295 295 213 0 58% 42%

Fare Collection System NOV 2020 78 28 28 50 0 36% 64%

Arts in Transit NOV 2020 168 14 14 154 0 8% 92%

Operational Readiness NOV 2020 736 123 223 513 100 30% 70%

Risk Management NOV 2020 4,346 2,311 3,716 630 1,405 86% 14%

25,283 20,095 22,638 2,645 2,543

Page 99: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

99 | P a g e

6.1.3 Segment 2 Revenue Service Date Certification Status

Segment 2 Certification Status - Progress Total Items Total Verified

1/1/20 Total Verified

6/30/20 Total

Remaining Δ YTD % Complete

Guideway (Civil & Systems) 3,041 1624 1,802 1,239 178 59%

Stations & Parking (Civil & Systems) 1,998 1525 1,600 398 75 80%

Passenger Vehicles (1-7 & 15-20) 2,138 676 707 1,431 31 33%

Traction Electrification System (TES) 54 4 4 50 0 7%

Automatic Train Control (ATC) 29 12 12 17 0 41%

Supervisory Control and Data Acquisition (SCADA) 47 8 8 39 0 17%

Communication 32 0 0 32 0 0%

Platform Screen Gate System (PSGS) 8 0 0 8 0 0%

System Integration Testing (SIT) 44 0 0 44 0 0%

Elevators / Escalators 33 0 0 33 0 0%

Fare Collection System 50 0 0 50 0 0%

Arts in Transit 63 0 0 63 0 0%

Operational Readiness 555 0 0 555 0 0%

Risk Management 1,757 1,102 1,107 650 5 63%

9,849 4,951 5,240 4,609 289

6.1.4 Segment 3 Revenue Service Date Certification Status

Segment 3 Certification Status - Progress Total Items Total Verified

1/1/20 Total Verified

6/30/20 Total

Remaining Δ YTD % Complete

Guideway (Civil & Systems) 1,772 0 0 1,772 0 0%

Stations & Parking (Civil & Systems) 4,908 0 0 4,908 0 0%

Traction Electrification System (TES) 39 0 4 35 4 10%

Automatic Train Control (ATC) 29 0 0 29 0 0%

Supervisory Control and Data Acquisition (SCADA) 47 0 0 47 0 0%

Communication 47 0 0 47 0 0%

Passenger Screen Gate System (PSGS) 16 0 0 16 0 0%

System Integration Testing (SIT) 44 0 0 44 0 0%

Elevators / Escalators 33 0 0 33 0 0%

Fare Collection System 50 0 0 50 0 0%

Arts in Transit 112 0 0 112 0 0%

Operational Readiness 555 0 0 555 0 0%

Risk Management 0 0 0 0 0 0%

7,652 0 4 7,648 4

6.1.5 Construction Safety and Security: Safety and Security Incidents Incidents for June 1-30, 2020:

Recordable Safety Incidents (medical treatment and/or lost time only): o AGS: An employee was struck in the face by a winch cable that broke under stress. This cable is one of the

two cables that hold the snatch box in place. First aid was administered, and then the employee was taken to Kaiser Permanente where they received stitches to the face.

o CCUR: A belt system was started when an employee who had his right hand on the engine, had the tips and middle ring finger of his hand smashed and fractured.

Page 100: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

100 | P a g e

Security Incidents (arrests and/or thefts only): o None.

Page 101: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

101 | P a g e

6.2 Quality Management Key Issues

HART NCR Log

Total NCRs Issued To Date Closed Open

101 (Audits) 97 4

3 (Construction) 2 1 Note: HART Issued NCRs for Construction are shown on each respective contract.

Resolution of major NCRs that need to be addressed and corrected to prevent recurrence, and to mitigate impact on the overall progress of the project. The major NCRs are described below: o Cracks in Canopy Structural Steel Members. Cracks on the Canopy Structural Steel members were found in the

WOSG and FHSG station groups. HART is in the process of finding the “root cause” of the defects, the disposition, and appropriate corrective action to prevent recurrence. All lower portions of the canopy arms (grade 100 steel) will be replaced at WOSG, FHSG and KHSG. The canopies at WOSG and FHSG are corrected. Please see Section 5.1 Overall Key Issues, for the latest status on the KHSG canopies.

o Train #12. End Car 1 of Train #12 was damaged (about 2.0 ft. long x ¾ in. wide x ¼ in. deep gouge on the left side, which did not penetrate the aluminum extrusion skin, and about ½ in. diameter penetration in the first set of the Door Panel on the right side of End Car 1) during transit from Pittsburg, CA to Honolulu, HI. HRI determined that cosmetic repairs will be required. A qualified and certified surface finisher repair crew is scheduled to be in Honolulu to fix the damage using an approved repair procedure once it is available.

Audit Look Ahead Prepared and issued (Revision 5) the Project Combined Management Systems Audit Schedule for 2020 to HART and all

contractors, consultants and suppliers. Planning for the audits to be performed in July and August 2020: Audit No. 20-003 AGS (Casting Facility) Combined QA,

Buy America (BA) and Environmental Compliance (EC) Audit of STG, Audit No. 20-004 Core System Support Consultant (CSSC) QA Audit of Lea + Elliott (L+E), Audit No. 20-005 CCUR Combined QA, BA and EC Audit of Nan Inc., Audit No. 20-006 On-Call (Project Wide) of Royal Contracting, and Audit No. 20-007 GEC 3 QA Audit of Jacobs. Due to the COVID-19 pandemic, all audits scheduled for April to June 2020 were postponed until July and August 2020.

Issued Closeout Letter on Audit No. 20-001 AGS (Construction) Combined QA, BA and EC Audit of STG held on Feb. 27-28, 2020. The Audit Team found eight (8) Positive Findings (5-QA/3-EC), seven (7) Observations (4-QA/3-EC), and five (5) EC Suggestions. Currently reviewing response from STG.

Issued Audit Report on Audit No. 20-016 Internal QA Audit of HART 5.CA-11 Contract Changes Procedure. The Audit Team found three (3) Positive Findings, three (3) Observations and two (2) Suggestions. Issued follow-up email to close the audit.

Issued Audit Report on Audit No. 19-019 HART Combined QA, S&S and EC Internal Audit of HART on Jan. 17, 2020. The Audit Team found: three (3) Positives, three (3) NCRs, nine (9) Observations, and three (3) Suggestions on QA; two (2) Observations, and two (2) Suggestions on S&S; and one (1) Positive on EC. Issued follow-up emails to close the audit.

Issued Audit Report on Audit No. 20-002 AGS (Surveying) QA Audit of STG held on March 5, 2020. The Audit found two (2) NCRs. One of the NCR’s was closed in April 2020.

Oversight and Monitoring Attended and participated in Pre-activity meetings, Inspections and Testing on the project

o KHSG: Best Management Practice (BMP)/Environmental Inspection. o AGS: BMP/Environmental Inspections. o CCUR: BMP/Environmental Inspection.

Prepared and issued Project NCRs Trend Analysis from July 2019 to June 2020 (Revision 53). The trend for this month: Trains: went up 22 from 29 to 51; Core System: no change (zero); Fixed Facilities: went up 10 from 12 to 22. See the next page for the Project NCRs Trend Analysis, and the following are detailed analysis of NCRs for the Trains and Fixed Facilities. o Trains: In June 2020, 51 NCRs were issued. 29 NCRs are from Honolulu: 10-Train #13, 9-Train #14, 3-Train #8, 7-

various trains during receipt inspection of new trains and dynamic testing; 22 NCRs in Pittsburg, CA: related to receipt inspection of components, cables found to be short and have to be rerouted, exterior paint scratches that happened during handling ,and other minor defects found on the two (2) trains (8 cars) being assembled in the plant with the goal of delivering one (1) train per month to Honolulu.

o AGS: In June, 22 NCRs were issued: the activities and production on the project (Superstructure, Substructures, Casting Facility and four (4) Stations) is in full blast and the number of NCRs issued is normal for that magnitude. The monthly average of NCRs for Fixed Facilities is 22.

Page 102: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

102 | P a g e

Page 103: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

103 | P a g e

6.3 Buy America Compliance (49 CFR 661 and 49 CFR 663) Overview and Key Issues

HRH continues to execute the corrective action plan to meet the PV Buy America requirements. The implementation of all required corrective action identified in the Post-Delivery Report has not yet been completed on all previously delivered Trains #1 through #6. Train #1 has been returned to Pittsburg, CA for retrofit and Train #2 will return to Pittsburg, CA within the coming months. Trains #3 through #6 require various retrofit that are planned to be conducted off-site, but on-island. The CSC will continue to monitor the update of the monthly Buy America compliance report as the retrofit status progresses to demonstrate compliance with the Corrective Action Plan. HRH has been notified that HART plans to complete the Post-Delivery Buy America audit on the Interim Opening (I/O) #1 fleet now that all seven (7) Interim Opening #1 fleet trains have been received in Honolulu. A significant component of the remaining Post-Delivery Audit effort is a follow-up “Supplier Audit” of Hitachi’s interior lining supplier to verify domestic content based on the implemented Corrective Action Plan. However, Hitachi has indicated that the Hayward, CA based supplier was impacted by the COVID-19 shutdown and is not yet prepared to support the conclusion of the Post-Delivery Audit. Hitachi has been tasked to coordinate with this supplier and identify the earliest possible date for the Raul V. Bravo + Associates, Inc. (RVB+A) auditors to conduct the audit and complete the Hitachi component of Post-Delivery Audit and issue the complete report. There will also be a final Buy America (BA) audit once the full fleet is delivered and tested prior to full system opening.

Train # Anticipated Date for BA Compliance

Open Issues

1 TBD Carshell structural retrofit, fire resistivity retrofit, and BA retrofit.

2 TBD Carshell structural retrofit, fire resistivity retrofit, and BA retrofit.

3 TBD Interior panels in M-Cars requires replacement for BA compliance.

4 TBD Requires M-car interior panel and Auxiliary Power Supply (APS) retrofit in accordance with BA Corrective Action Plan.

5 Completed Requires fire resistivity retrofit.

6 Completed Requires fire resistivity retrofit.

7 Completed No issue and in transit to Honolulu. Delivery to MSF is planned for July.

8 (I/O Fleet) Completed No issue and delivered to MSF on March 27, 2020.

9 (I/O Fleet) Completed No issue and delivered to MSF on Feb. 14, 2020.

10 (I/O Fleet) Completed No issue and delivered to MSF on Dec. 9, 2019.

11 (I/O Fleet) Completed No issue and delivered to MSF on Jan. 9, 2020.

12 (I/O Fleet) Completed No issue and delivered to MSF on Oct. 26, 2019.

13 (I/O Fleet) Completed No issue and delivered to MSF on May 8, 2020.

14 (I/O Fleet) Completed No issue and delivered to MSF by June 1, 2020.

15 December 2020 Manufacturing activities ongoing.

16 December 2020 Manufacturing activities ongoing.

17 December 2020 Manufacturing activities ongoing.

18 December 2020 Manufacturing activities ongoing.

19 TBD Manufacturing activities ongoing.

20 TBD Manufacturing activities ongoing.

6.4 Disadvantaged Business Enterprise (DBE) Activities this Month

$151,980,785 = total dollar participation for all DBEs on all HART contracts from 9/24/07 to 6/30/20 o 18.85% = DBE utilization on total disbursed FTA funds received to date ($151,980,785 divided by

$806,258,734) o 8.62% = DBE utilization to date on total Project FTA funds ($151,980,785 divided by $1,763,903,901) o 9.81% = DBE utilization to date on 5309 Project FTA funds ($151,980,785 divided by $1,550,000,000)

Page 104: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

104 | P a g e

6.5 Art-in-Transit (AIT) Program The Honolulu Rail Transit Project's December 2012 FFGA grant (Sitework and Special Conditions) includes a public art program. In addition, the Revised Ordinances of Honolulu (ROH) Section 3-2.7, "Art in City Buildings," provides for the inclusion of art in city-owned buildings frequented by the public. For the rail project, the AIT staff negotiates and manages contracts for the west-side stations and AGS. AIT contracts are managed in five NTP phases:

NTP1 - Conceptual design NTP2 - Design development, final design, and construction documents NTP3 - Mobilization NTP4 - Fabrication, transportation, and installation NTP5 - Final acceptance

Conceptual and final designs are presented to the Mayor's Commission on Culture and the Arts for review and comment. The Transit Art Committee (TAC) evaluates and makes the final recommendation and approval.

Station / Facility Name Artist Name NTP Phase Comments

East Kapolei Station Robert Flint NTP4

Artist and team Safety certified. Contractor changes to art wall completed. Artist scheduled to travel to Honolulu to confirm final dimensions and finishes in mid-July to commence fabrication of ceramic mural.

University of Hawai‘i West O‘ahu Station

Satoru Abe NTP3

Artistʻs team visited station to confirm inner dimensions of architectural fence for fabrication. Assisting the artist with Design Criteria Conformance Checklists (DCCC) submittal documents. Artistʻs team is working on Material Safety Data Sheet (MSDS) information for Safety.

Ho‘opili Station Karen Lucas NTP3

Assisted artist in verification of dimensions and confirmed directional placement of artworks for the best visual sightline. Fabricator is exploring another technology to interpret artistʻs designs on to custom colored glass tesserae to accurately replicate the fine details of the original pastel drawings.

West Loch Station Hans Ladislaus NTP3

Conducted in-depth technical research to assist artist on fabrication questions and options. Working with the artist on required technical documentation and MSDS information for Safety & Security Design Criteria Conformance Checklist review. Artist is working on scaled depth and texture studies to prepare maquette. Installation of barrier flashing on TCCR artwall is needed for art installation.

Waipahu Transit Center Station

John Koga NTP1 The TAC reviewed conceptual design submittal #5; revisions recommended.

Rail Operations Center – Operations & Servicing Building

Shigeru Miyamoto

NTP3

Working with the artist on required technical documentation and MSDS information for Safety & Security Design Criteria Conformance Checklist review. The artist needs to submit color samples during NTP3 and NTP4.

Leeward Community College

Donald Lipski NTP4 Fabrication continues in Florida, with casting of the sculptural elements and piercing of the star patterns on each unit.

Page 105: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

105 | P a g e

Station / Facility Name Artist Name NTP Phase Comments

Pearlridge Station Robert Kushner NTP4

Artistʻs fabricator completed production of the (makai entrance artwork) first of two 7’x 20’ glass and stone mosaic murals. Received digital images of work, second mural started. Awaiting the station contractor’s implementation of changes to paving area to integrate artwork for the installation.

Aloha Stadium Station Jay Wilson NTP1 Revising conceptual design.

Pearl Harbor Naval Base Station

Carol Bennett NTP2

Artist is working on glass samples to test colors and techniques that will be utilized to create desired textures and areas of opacity versus transparency. First sample images received.

Honolulu International Airport Station

Mamoru Sato NTP1

Artist submitted revised conceptual designs for the Mauka and Makai artworks. Mayor's Commission on Culture and the Arts review is scheduled for mid-July via an online meeting platform. Design work is pending refinement of mullion system used for artwork installation.

Lagoon Drive Station Carol Yotsuda NTP1 Revising conceptual design.

6.6 Planning and Environment Activities this Month

Environmental Compliance o Environmental Due Diligence: HART continued remediation of the Iwilei Station location. Remediation of

the Lee Property, near Pearl Highlands Transit Center, is continuing. o Environmental Review Documentation: On June 24, HART received a formal concurrence determination

from the FTA on the post-ROD environmental re-evaluation of the addition of an interim park-and-ride facility at the Ho‘opili station and the reconfiguration of the permanent park-and-ride facility at the University of Hawai‘i West O‘ahu station.

Project Mitigation Commitments o Historic Resource Documentation: The pre-draft Historic American Buildings Survey (HABS) documentation

for Chinatown and the pre-draft of the Chinatown Historic District National Register (NR) Update are still under review. Final comments of the draft of the Historic Context Studies were received by HART in May and have been reviewed by staff before transmittal to the contractor (HHM). Work was completed on the Historic Preservation Certification Application (HPCA) Part II for the Wo Fat Chop Sui House. Revisions to the draft nominations for Waimalu Stream, Kalauao Springs and Kalauao Stream Bridges were completed and transmitted for public hearing for the July 31, 2020 Hawai‘i Historic Places Review Board (HHPRB) meeting, along with the Oahu Railway & Land Co. (OR&L) Property, Wood Tenements, and True Kamani Tree Row. Draft nominations submitted for the Sept. 18, 2020 HHPRB meeting included: Aloha Tower, Dillingham Transportation Building, HDOT Harbors Division, Kapālama Canal Bridge, Aloha Chapel at Pearl Harbor, and Six Quonset Huts. Comments on the site forms for the Multiple Property Documentation (MPD) were transmitted to Fung Associates.

o Cultural Landscape Reports: Staff completed final review of the comment review matrices for the Cultural Landscape Report (CLR) reports for Mother Waldron Park and Playground, Walker Park, and Irwin Memorial Park. These comment responses will be posted on the HART website in July 2020.

o Historic Preservation Fund: Staff continued planning efforts for the public meetings for round 2 of the Historic Preservation Fund, including potential topics and speakers. This effort is on hold pending the resumption of public meetings.

Page 106: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

106 | P a g e

o Interpretive and Educational Materials: Staff are reviewing comments on the prototype Stipulation VII educational materials and are working to finalize the comment response matrix. Planning has started the next phase of the consultation process for Stipulation VII. Processes are being developed to engage the broader community while complying with social distancing guidelines. On June 16, HART convened a virtual consultation meeting with staff of the Office of Hawaiian Affairs. This meeting was attended by 12 participants. A broader list for community engagement has been developed that will focus on having four meetings in each section of the alignment, with the first tentatively scheduled for July 29.

o Section 106 Programmatic Agreement: The June PA report is included in the Semi-Annual report and is in draft form and being routed for edits.

o Other Mitigation: Planning staff have reviewed the required Noise and Vibration Management Plan for the Airport Guideway and Stations contractor. This is a regular 6 month update as required by the PA.

Sustainable Mobility o Youth Community Change: SuMoLab continued working with Hawai‘i Youth Climate Coalition,

HawaiiKidsCAN and the Sierra Club on developing a platform for youth-driven community change. This month, the youth focused on connecting with advocates for social justice, developing a process for interviewing them, and learning their histories.

o Malama ʻAina Rides Partnerships: SuMoLab continued conversations around a malama ʻaina partnership with Mālama Pu‘uloa by visiting Kapapapuhi Point Park in West Loch over one of the weekends. This city-owned park is on the Pu‘uloa (Pearl Harbor) shoreline and an active site for shoreline restoration and clearing Mangrove. It is also a short distance from the Hō‘ae‘ae rail station and with improved bike connectivity, could be a site for malama ‘aina work that is easily accessible through clean transportation (rail + bike). Kalihi Valley Instructional Bike Exchange (KVIBE) and Mālama Pu‘uloa are looking into a vision where KVIBE youth can someday ride to the rail, and then connect with youth and ʻaina in other communities at places like Kapapapuhi Point Park.

o Community Placemaking: SuMoLab has been developing a partnership with Hawaii Bicycling League and 808 Urban to develop a mural near Lehua Elementary in Pearl City. 808 Urbanʻs process of engaging with youth in the histories of place compliments the projectʻs work to promote sustainable mobility, while connecting people to history and place through transportation.

o Station-Community Integration: SuMoLab has also been participating in the Active Transportation and Food Access Committee (ATFAC) convened by the Department of Health on developing concepts for providing fresh produce at rail stations. The idea was inspired by Marta Market (https://www.itsmarta.com/marta-market.aspx) and is building on a grant concept developed for a Local Food Local Places program.

o ACT2 Livable Communities: Interest areas that emerged in April and May through ACT2’s focus on livable communities, continued into June. One of the most notable is the coalition building around Zero Waste O‘ahu — making connections between construction waste (with participation from Re-use Hawai‘i), eWaste, food waste, plastic waste, and more.

Planning o Oahu Metropolitan Planning Organization (OahuMPO): Staff continued to participate on the OahuMPO

Technical Advisory Committee (TAC) Board. The June 12 TAC meeting discussed the temporary Accelerated Transportation Improvement Program (TIP) Amendment Policy only for projects using stimulus funds or federal redistribution funds. The committee also reviewed congestion pricing examples from London and Stockholm.

Look Ahead

Preparation of Post-ROD and other environmental documentation: o Intelligent Transportation Systems (ITS): SHPD continues to review documentation for an amendment of the

Project Area of Potential Effect (APE) to cover ITS work. o East Kapolei Park-and-Ride Lot: Staff continue to coordinate with the University of Hawai‘i regarding the

location and configuration of the 900-stall park-and-ride lot at the Kualaka‘i (East Kapolei) Station. o City Center/Pearl Highlands: Any project final design refinements or new right-of-way takes will be assessed

and submitted to the FTA, as appropriate.

Page 107: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

107 | P a g e

o Kamehameha 138kV Relocation: Overhead 138kV lines are to be relocated between the Waiau Power Plant and Aloha Stadium in order to provide the required working clearances around the guideway. Analysis is pending development of the preliminary design drawings.

o Right-of-Way and APE Updates: Staff will be documenting project design changes and adjustments to right-of-way acquisitions to date.

6.7 Risk Management Following is a progress report highlighting top risks and mitigation efforts from the June 2020 monthly risk update.

6.7.1 Top Risk Summary

Top Cost Risks

Core Systems: Delay to CSC due to AGS station delays

AGS Time Impact Analysis (TIA) for HECO Zone 8 Delay

Core Systems: Additional work until assigned to P3

CCUR: Insufficient performance by utility owners

Environmental for CCGS (risk sharing)

CCUR: Delay in agency permitting

CCUR Field changes resulting from HECO requirements

ROW: Mauka entrance to Kuloloia Station (at Downtown)

CCUR: Misidentified and unidentified utilities

P3 for CCGS: Affordability Cap being exceeded

P3 for CCGS: Revocation of Noise Variance

ROW: Cost and Time Impacts for Numerous Small Property Acquisitions for Straddle Bent Foundations

P3 and CCUR interface impacts

Core Systems, incomplete interface details

ROW: Makai entrance to Kuloloia Station (at Downtown)

P3 for CCGS: CCUR Access Dates if not met

Fare Collection Systems: delay if station electrical systems not ready (applies to interim RSD)

P3 for CCGS: Unanticipated Archaeological Finds

Utilities: HECO Substation at MSF

See additional low risks highlighted in green in the table below

Watch List Risks

Coronavirus Concerns. Risk impacts began to be reported in the March 2020 report including the procurement extension due to COVID-19 impacts on the PLO’s ability to price the work. The Risk Manager has continued to status this risk topic with project teams and HART management in ongoing monthly risk updates considering potential impacts to project schedules; availability of labor, equipment and materials; contingency; project funding.

Opportunities for Cost Savings

P3 competitiveness, innovation for CCGS

CCUR II competitiveness

Top Schedule Risks: Critical or Near Critical Path

CCUR: Delay in agency permitting

AGS TIA for HECO Zone 8 Delay

Core Systems: Delay to CSC due to AGS station delays

CCUR: Insufficient performance by utility owners

P3 for CCGS: Affordability Cap being exceeded (time to resolve)

Utilities: HECO Substation at MSF

CCUR: Misidentified and unidentified utilities

CCUR Field changes resulting from HECO requirements

Core Systems, incomplete interface details

Environmental for CCGS (risk sharing)

Possible Revocation of Noise Variance

P3 and CCUR interface impacts

CCUR Access Dates if not met for P3

ROW – numerous small property acquisitions for straddle bent foundations (currently not critical, but could become critical if delays occur)

P3 for CCGS: Unanticipated Archaeological Finds

Opportunities for Maintaining Schedule

Aggressive CEI oversight of CCUR with fully qualified field staff

Procurement of CCUR II contract

ROW to maintain schedule for new acquisitions based on final CCGS alignment, through appropriate staff and consultant support

Fill vacant staff positions with existing staff and consultant support

Page 108: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

108 | P a g e

6.7.2 Top Risk Threats and Mitigations

Risk ID Risk Description Risk Threat Score

Risk Mitigation

DBOM920 PRO 80.03_10

Schedule and cost impacts due to AGS guideway and stations delays affecting the Core Systems Contractor (CSC). (New risk as of end of May 2020.)

15 HART Core Systems team is reviewing the merits of this issue expressed by the CSC, including concurrent delay due to time required for CSC’s design affecting the AGS schedule.

DB450 SIT 40.02_11

AGS: HECO Zone 8 Delay. 15 HART is evaluating the TIA for concurrent delays.

DBOM920 SYS 50.01_12

Core Systems: Risk of additional work by Core Systems Contractor following recent settlement, until assigned to P3.

12 1. HART is troubleshooting systems interface issues with West stations work to avoid further cost due to changed conditions. 2. Plan for 2-phase testing at platforms has allowed more time for canopy arm installation, followed by Core Systems devices and testing.

DBB511 SIT 40.02_01

Insufficient construction performance by utility owners.

12 HART is coordinating with utility companies, including HTI and AT&T, to ensure sufficient resources to meet HART’s schedule for utility relocations along the corridor. This risk was updated in May and June 2020.

P3-DB550 SIT 40.03_03 (schedule) and 40.03_02 (cost)

P3 for CCGS and PH: Environmental Cleanup, Cost and Schedule Impacts to HART (2 separate risks, but combined here for scoring). The Risk Management System (RMS) adjusted the cost portion of this risk slightly downward based on the expectation that CCUR work will uncover most, if not all, pockets of contamination. There is a risk sharing arrangement in the P3 RFP for environmental cleanup responsibilities.

12 1. Although HART would be responsible for the cost and schedule impact for cleanup of undisclosed contamination, the P3 would be responsible for the schedule risk associated with the cleanup of disclosed contamination. Some cleanup activities could be non-critical path delays depending upon where they occur in the project. 2. HART will handle the cleanup with on-call contractors familiar with this work and who can execute the work most efficiently.

DBB511 SIT 40.08_01

CCUR: Delay in obtaining City Agency Permitting had been forecast and continues to result in delays to critical utility relocation work.

12 HART continues to coordinate with City permitting agencies to provide any further design information that is needed, and to reduce the timeframes for review and permitting of utility relocation work.

DBB511 SIT 40.02_24

CCUR: Field changes resulting from HECO requirements.

12 HART is continuing to coordinate with HECO to identify all appropriate requirements are fully planned, such as epoxy coated manholes, and increased conduit diameters for cabling.

ROW 60.01_17

ROW: Parcel Scope changes for Mauka Entrance to Kuloloia Station (at Downtown)

12 HART and DTS are evaluating the preferred Mauka station entrance location for the Kuloloia Station (at Downtown). The preferred location is within the courtyard of the existing Pacific Guardian Center (PGC). Initial discussions with the Property Manager have taken place.

DBB511 SIT 40.02_07

CCUR: Scope and schedule of construction could be impacted by the discovery of misidentified and unidentified utilities

10 HART will pay for differences in quantities of utility relocations based on as-bid unit rates.

P3-DB550 PRO 80.01_07

P3 for CCGS and PH: Risk of Affordability Cap being exceeded for the capital construction and/or the future O&M. Note: This risk was part of a risk grouping that has now resulted in a delay to RSD within the risk forecast, since the Procurement Delay risk has been inactivated.

10 1. The Affordability Cap for Capital as well as O&M were provided to the P3 PLO(s) on 26JUL2019 in order to allow HART sufficient time to respond in case concerns are expressed by the PLO(s). 2. HART’s ICE estimate was reviewed and received concurrence from E&Y and from HART’s Project Execution Consultant.

P3-DB550 SIT 40.04_09

P3 for CCGS and PH: Revocation of Noise Variance which allows night and weekend work. This could have a cost and schedule impact to the CCGS project.

9 HART will pursue greater involvement with the community to inform them of construction activities and be more responsive to their concerns. HART can mitigate by compensating the contractor to utilize noise mitigation strategies and by maintaining open communication with DOH who controls the noise variance.

Page 109: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

109 | P a g e

Risk ID Risk Description Risk Threat Score

Risk Mitigation

ROW 60.01_19

ROW: Cost and time impacts for numerous small property acquisitions necessary for foundations to support straddle bents along Dillingham Blvd and elsewhere.

9 HART is awaiting confirmation of required properties for straddle bent foundations and Temporary Construction Easements (TCE’s). Specific property identification is dependent on final designs. Management has begun meetings with affected property owners to advise of the need for straddle bent foundations at specific locations and to attempt to minimize the impacts to the property owners and to seek their cooperation with HART's plan.

P3-DB550 SYS 50.03_01

P3 for CCGS and PH: Interface impacts between CCGS and other contracts including CCUR and Core Systems Contractor.

9 HART is working to make sure CCUR work is completed as expeditiously as possible, and that achievable access dates to the P3 (area by area in the CCGS corridor) have been included in the P3 RFP.

DBOM920 SYS 50.01_01

Core Systems: Incomplete Interface Details (Stations & Guideway).

9 Final interface details continue to be worked out as West Stations progress much closer to final completion. HART and CSC are doing additional pre-final inspections for west stations to ensure compliance.

ROW 60.01_10

ROW: HECO Kuloloia Station (at Downtown) Makai Parcel Scope Changes. Late agreement with HECO for Kuloloia Station (at Downtown) Makai parcel, currently an old power plant, could impact DB contract requirements.

9 Get agreement with HECO and perform early subsurface investigations. Include report in bid documents.

P3-DB550 SIT 40.05_02

P3 for CCGS and PH: Potential for CCUR work to extend beyond Access Dates committed to the P3 for CCGS. If committed access dates are not met, then the P3's start of work in those areas could potentially be delayed, placing HART at risk of having to compensate the P3 for owner-caused delay.

9 The P3 Procurement Documents include a list of Access Dates that HART is committing to meet. This risk pertains to HART's guarantee to the P3 that CCUR work will be completed by certain committed dates area by area through the CCGS project.

MI900 SYS 50.06_11

Fare Collection: Rail Station installation of Fare Systems equipment could be delayed if Stations’ electrical systems are not ready in time for Revenue Service.

9 Coordinate with station contractors to develop and share station as-builts with the Fare System Vendor. Coordinate schedules as well to allow sufficient time for testing and installation at each of the stations.

P3-DB550 GUI 10.04_01

P3 for CCGS and PH: Discovery of unanticipated archaeological findings could result in added cost and schedule impact to HART.

8 The HART Procurement and technical team for the P3 has been working on an appropriate level of risk for the P3 to undertake in dealing appropriately with archaeological finds. HART will be responsible for finds that cause undue cost and schedule delay.

UTIL68 SYS 50.03_01

Private Utilities: HECO Substation needed on land from UH adjacent to MSF, for reliable power for train operations.

8 HECO has stated that the electrical grid system requires a new substation adjacent to the MSF. HECO has approval from PUC to install the substation on the site. Because HART currently has all interim opening trains on-site and in testing at the MSF, there is no anticipated need for the substation to start interim service. HART will continue to work with HECO and monitor loads to install the substation before full revenue service.

DBOM920 SIT 40.05_01

Core Systems: Operating Noise Exceeds Environmental Impact Statement (EIS) Defined Limits.

6 Tangent track noise test compliant with Technical Provision (TP) requirements. Noise testing in curves still required. Evaluation against EIS noise levels outstanding. Mitigation may require installation of track lubricators along the alignment, implementation of a rail engineer grinding program, and/or noise absorption panels.

DBB271 STA 20.01_26

FHSGC: Plan B Canopy Redesign Delay Claim.

6 The risk needs to remain active within the Risk Register until the claim is negotiated and fully resolved. This risk was not part of the FHSG Consolidated Resolution that was approved by the HART Board on May 28, 2020.

DBB371 STA 20.02_05

KHSGC: HART Open Changes. 6 HART is continuing to negotiate with the contractor for a fair settlement of all remaining issues through final closeout of the project.

DBB600 SUP 30.01_01

Park-and-Ride Lots: Contingency for Park-and-Ride Lots construction.

6 HART is holding a contingency value until the final park-and-ride locations are determined, designs are complete, and construction is underway.

Page 110: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

110 | P a g e

Risk ID Risk Description Risk Threat Score

Risk Mitigation

MI900 SYS 50.06_20

Fare Systems Vendor could experience additional costs.

6 Negotiate change orders with the proper contractor and/or award a separate contract as needed for Fare Systems requirements. These requirements pertain to startup and rollout costs that are not included in the scopes of work for the Fare Systems Contractor or Technical Consultant.

UTIL68 SIT 40.02_08

Private Utilities: Construction sequencing for City Center creates additional work for utility companies.

6 HART is working with utility companies to understand the requirement for additional inspectors as the sequence of the CCUR work becomes more apparent through schedule coordination with the contractors involved.

UTIL68 SIT 40.02_09

HECO KHG 138 kV Relocation to provide adequate separation from guideway.

6 HART will coordinate with the design firm (RM Towill) to guide the scope to remain within reasonable limits, while meeting all necessary HECO requirements. A potholing program is underway to determine the locations of existing utilities along the route, and the reasonableness of undergrounding the 138kV along the highway. The project is in the concept design phase.

MI930 STA 20.07_03

Elevators/Escalators: Increase in Elevator and Escalator Quantity Requirements

6 The final number of additional escalators on all east stations have been determined to be two for AGS, and 11 additional for CCGS. Still need to negotiate a favorable resolution with E&E contractor for CCGS. This risk will be revisited after award of the City Center DB contract.

DBB371 STA 20.02_22

KHSGC: Potential Electrical and Structural Canopy Design Issues.

4 HART is continuing to negotiate with the contractor for a fair settlement of all remaining issues through final closeout of the project.

ROW 60.01_18

ROW: Net cost to HART for Land Trade for Rail Operations Center.

4 HART is working with the City on this land exchange. The City needs to approve this exchange once it is worked out by the Dept. of Hawaiian Homelands (DHHL).

DB450 SIT 40.02_04

AGS: Conflict Resolution – Costs for Utility Relocations.

4 HART is coordinating with the contractor and utility agencies to mitigate any utility delay risks that could result in cost or schedule impact to the project.

Risk Scoring for Risk Threats The following risk scoring table (used in the calculation of the risk threat scores shown above) is in accordance with FTA guidelines for summarizing the overall severity of project risks. HART has adjusted the cost and schedule ranges shown below in order to scale to the HART Project size.

Risk Scoring for Risk Threats

Impact Scores Legend

Low 1

Medium 2

High 3

(P) Probability <10% >10% <50% >50%

(C) Cost Impact <$10 M >$10 M <$50 M >$50 M

(S) Schedule Impact <1 month >1 month <4 months >4 months

Rating <6 7 - 12 13 - 18

Score = (Cost + Schedule) * Probability

Risks are assessed based on the probability of occurrence, potential (and most likely) cost impact, and potential (and most likely) schedule delay. The total score is arrived at by adding the cost and schedule impact scores, multiplied by the probability score. For example:

40% Probability = 2; A $60 million Cost Impact = 3; A five month Schedule Impact = 3 Resulting Score = 3 + 3 = 6 x 2 = 12; a Medium Risk.

Page 111: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

111 | P a g e

6.7.3 Top Risk Opportunities

Risk ID Risk Description Risk Opportunity Score

Risk Mitigation

P3-550 SIT 40.05_01

P3 for CCGS: Opportunities for P3 innovation through Alternative Technical Concepts (ATC’s).

15 1. HART plans to evaluate and approve ATC’s that are beneficial to the Project. 2. There were ATC’s that were received for previous HART projects, so there is precedence for this possible savings.

275 PRO 80.01_01

P3-PHPTR: Opportunity for P3 to present a modest cost reduction for construction of the Pearl Highlands Garage and Transit Center.

9 HART has been working to make the RFP as performance-based as possible so that it allows creativity from the P3 team(s).

DB511 SIT 40.08_16

CCUR: Opportunity for CCUR II to reduce base cost.

6 New Opportunity Risk created to capture the likelihood of benefit from the CCUR II Contract over the current CCUR Contract.

P3-DB550 PRO 80.01_02

P3 for CCGS: Opportunity for P3 to present a modest cost reduction for construction of City Center Guideway and Stations, and remaining Core Systems work.

6 HART has been working to make the RFP as performance-based as possible so that it allows creativity from the P3 team(s).

Risk Scoring for Risk Opportunities

Risk Scoring for Risk Opportunities

Impact Scores Legend

Low 1

Medium 2

High 3

(P) Probability <10% >10% <50% >50%

(C) Cost Impact <$10 M >$10 M <$50 M >$50 M

(S) Schedule Impact <1 month >1 month <4 months >4 months

Rating <6 7 - 12 13 - 18

Score = (Cost + Schedule) * Probability

Similar to the legend for scoring of Risk Threats, Risk Opportunities are assessed based on the probability of occurrence, potential (and most likely) cost impact, and potential (and most likely) schedule delay. The total score is arrived at by adding the cost and schedule impact scores, multiplied by the probability score. The scoring calculation for Risk Opportunities is the same as for Risk Threats; however, in the Opportunities scoring table above, high opportunity scores are colored green (versus red), low opportunity scores are colored blue (versus green), and medium opportunity scores are still colored yellow. 6.7.4. Recent Risk Updates

The most recent risk update occurred in June 2020, the results of which are discussed herein. These results have been summarized in the FTA Quarterly meeting including the PMOC on July 8 and July 9, 2020. The P65 results now place the projected forecast at $8.277 billion, which is $112 million above HART’s budget goal of $8.165 billion. The current P65 result at $8.277 billion is $22 million below the overall budget goal of $8.299 billion as recommended by PMOC and FTA from HART’s Revised Recovery Plan. The June 2020 Risk update was facilitated by the Risk Manager. This involved virtual meetings with project team members instead of face to face meetings because of current travel restrictions as a result of COVID-19. At the Risk update meetings, the teams reviewed each risk, discussed their validity and if any adjustments are needed to the post-responses, discussed if any new risks are necessary, and explored ongoing risk mitigation efforts.

The most significant risk adjustments in the June 2020 risk update included: 1. Based on recommendations from the CCUR team, the Risk Manager added $240 million to the base cost

for CCUR, bringing the overall base cost to $640 million from the previous $400 million. This is a conservative approach as forecasted by the Risk Manager. The $240 million adjustment is undergoing internal review by HART and has not yet been officially reflected in Project Controls’ base cost.

Page 112: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

112 | P a g e

2. CCUR team introduced an opportunity risk of ($33.3 million) due to presumed competitiveness from the planned CCUR II procurement.

3. CCUR team reduced risks by $77.5 million due to the risks now being included in the base cost increase. 4. Risk Manager removed extended overhead calculations occurring within the Risk Model on the CCUR

contract due to it being a task order contract. The approximate reduction from this action was $10 million.

5. Core Systems added a new risk of delay alleged by the Core Systems Contractor due to delay of several months of the AGS stations, affecting Core Systems work. Risk Expected Value is $13.8 million.

6. Other base cost adjustments included incorporation of the Consolidated Resolution for FHSG into base cost, and thus retired from the risk forecast for FHSG.

7. The base project completion date, without schedule contingency, was January 2026 in the June 2020 Risk update, which remained the same from the May 2020 Risk update. From that base date of January 2026, the Risk Model forecasts 10.9 months of schedule delay to the P65 date of December 2026.

Pending Risk Adjustments in July 2020:

1. HART overhead costs are being reviewed and may be adjusted in future months to be at the level anticipated to be needed for proper oversight of the P3’s CCGS and PHPTR work, which is the final major HART project leading to full RSD by end of year 2026. A revised HART overhead forecast could affect the cost forecast in the risk model, such as reducing the forecast if a smaller contingent of staff is needed once the west contracts are closed out, and later when the AGS contract is closed out.

Several significant adjustments in the prior May 2020 Risk Refresh included:

1. Inactivated a major ROW Risk for the Kaka‘ako area because its value is now reflected in the base budget for ROW.

2. Inactivated bid uncertainty and escalation calculations related to the Affordability Cap within the Risk Model (not the affordability cap risk itself) for the P3. The risk system normally halts the bid uncertainty and escalation calculations on projects that have bid, since those variables are reflected in the bid price. Since the P3 proposals are within 2 months of being received, and the Affordability Cap must hold, the Risk Manager determined in our monthly risk review with senior HART management that it is appropriate at this time to halt the referenced calculations which was adding a high degree of reserve on top of the base contract values for the P3 being held in the Risk Model. The Risk Manager clarified to HART management that if the Affordability Cap is exceeded by the P3 PLO’s proposals, then HART would consider the options of available contingency to cover the difference, or would consider scope reductions in order to keep the P3’s costs in line with the Affordability Cap.

3. P3 for CCGS and PH: Risk of Affordability Cap being exceeded for the capital construction and/or the future O&M, which represents a potential time delay should there be an affordability cap issue after proposals are received from the PLO’s in July 2020. This risk has not changed, but it now takes precedence because it is part of a risk grouping that has now resulted in a delay to RSD within the risk forecast, since the Procurement Delay risk has been inactivated.

4. The base project completion date, without schedule contingency, shifted to January 2026 in the May 2020 Risk Refresh, compared to June 2025 from the April 2020 risk update. This represents a shift of 7 months in the base completion schedule for CCGS. From that base date of January 2026, the Risk Model had forecast 10.5 months of schedule delay to the P65 date of December 2026.

Page 113: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

113 | P a g e

6.7.5. Cost and Schedule Probability Curves from June 2020 Risk Update Figure 11. Cost Probability Curve, June 2020 Risk Data

The update shown in Figure 11, at $8.277 billion, resulted in a $95.3 million increase to the P65 risk expected value when comparing the June 2020 update (shown above) to the May 2020 update (shown in the prior report). This increase is due to the following adjustments:

Base Cost: +$248.3M (due to updated CCUR base cost estimate increase of $240M, plus $8.3M of misc. CPP adjustments)

Core Systems Risks: +$13.8M (new risk re: alleged AGS delays)

CCGS Risks: +1.7M (misc. adjustments, pending July bids)

UHPRB Risks: +$0.1M

CCUR Risks: ($110.8M) (Opportunity Risk of -$33.3M, and Risk reductions of -$77.5M now in Base)

FHSGC Risks: ($19.7M) (executed Consolidated Resolution change order)

ROW Risks: ($11.9M) (misc. adjustments)

AGS Risks: ($5.3M) (misc. adjustments)

KHSG, WOSG Services During Construction (SDC) ($5.1M) (design SDC)

WOSG Risks: ($0.4M) (closing out)

Risk Model Changes: (approx. $10M) (overheads on CCUR within Risk Model not needed), and another ($5.4M) in miscellaneous Risk Model changes

Total P65 Change, May to June: +$95.3M The P65 for the overall HART project is now $8.277 billion, which is $112 million above HART’s budget goal of $8.165 billion. The current P65 result at $8.277 billion is $22 million below the overall budget goal of $8.299 billion as recommended by PMOC and FTA from HART’s Revised Recovery Plan.

Page 114: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

114 | P a g e

Figure 12. Schedule Probability Curve, June 2020 Risk Data

The schedule update shown in Figure 12 remained unchanged when comparing the June 2020 update (December 2026 shown above) to the May 2020 update. The P65 for the overall HART project is now December 2026, which is 9 months beyond HART’s current stated schedule goal of March 2026 for operational readiness, and 3 months beyond the PMOC recommended target date of September 2026 for meeting final revenue service.

6.7.6. Ongoing Risk Mitigation Efforts The P65 schedule extension to December 2026 from the June 2020, May 2020 and April 2020 risk updates (formerly October 2026 from the March 2020 risk update, August 2026 from the February 2020 risk update, and July 2026 from the January 2020 and December 2019 risk updates) is a significant concern to HART. The project delivery timeframe for CCGS to still accomplish the full RSD by March 2026 (formerly a goal of December 2025) had been a significant HART goal, which is now overshadowed by the expanding threat of the COVID-19 pandemic on not only the HART Project, but on the state of Hawai‘i, as well as nearly all populations and countries around the world. Nevertheless, HART will maintain particular focus on the following risk areas in order to complete the Project as expeditiously as possible given the ongoing project risks:

1. Expedite the ROW acquisition schedule for necessary acquisitions to accommodate utility relocations (CCUR) and necessary space for straddle bent foundations along the CCGS route. Ensure qualified ROW staff are in place and necessary support is received from HART’s Real Estate Consultant. All necessary ROW must be acquired in time for P3 Access Dates to be met.

2. Expedite the City Center Utilities Relocations and Road work (CCUR) in time to meet area by area Access Dates being committed to the P3 PLO’s in the procurement documents. This can be accomplished by securing all third party agreements and permits in advance, and maintaining the right level of qualified CEI staff for design oversight and field construction oversight. Ensure that the CCUR contractor is executing the work as proactively as possible with qualified construction staff, equipment selections, and effective maintenance-of-traffic planning. HART is preparing a procurement for a second CCUR contractor to expedite the work. The base estimate update for CCUR has been reviewed in March, April, May and June 2020, the results of which have now been incorporated into the June 2020 risk update. The CCUR team has incorporated numerous risk reductions due to base cost increase for CCUR as reported herein.

Page 115: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

115 | P a g e

3. Ensure that the approach to dealing with both identified and unidentified environmental contamination, and/or archaeological finds, are agreed with DOH and other oversight agencies in advance, in order to deal with the impacts encountered during construction appropriately and as expeditiously as possible. HART will need to set aside adequate contingency to pay for this cleanup work due to the risk transfers from the P3 to HART, which HART believes can be effectively managed by HART’s on-call environmental cleanup contractors.

4. Ensure all necessary procurement procedures are being followed correctly. Minimize the possibility of a protest over procedural issues related to this important procurement. A time extension to the P3 procurement was recently granted due to the COVID-19 concerns, which was a reasonable response by HART to the PLO(s) request for more time given the difficult current circumstance of pricing the work until the virus threat has passed.

5. Ensure final completion and closeout of the west station projects by late-2020, in order to obtain Interim Revenue Service as soon as is reasonable in the first quarter of 2021 (given the COVID-19 concerns), and to have this west section fully functional and ready for turnover to the P3 at the appropriate date to be clarified in the P3 RFP.

As reflected above, the current schedule risk forecast identifies potential concerns with risks in the categories of agency permitting, interface between contractors, construction performance by utility contractors, procurement and right-of-way. The schedule risk forecast suggests if ongoing mitigation efforts related to these risks fail, or if problems related to the COVID-19 pandemic worsen, the delay consequences could be severe.

6.8 Construction Claims Pursuant to FTA Circular 4220.1F, HART is obligated to notify the FTA and PMOC about third-party claims and litigation with which it is involved. HART considers a “claim” to arise when a third-party contractor submits a request for a final written decision by the Contracting Officer. Pursuant to Hawai‘i Revised Statutes Section 103D-711 and Hawai‘i Administrative Rules Section 3-126-28, the Contracting Officer’s decision is deemed final and the basis on which the aggrieved party can initiate an action in Circuit Court within six (6) months of receipt of the Contracting Officer’s decision.

There are currently no open claims.

6.9 Community Outreach Overview

Since the inception of HART, the outreach team has participated in: o 1,517 Public Presentations and Events

The HART Public Involvement (PI) team participated in a total of 5 events and presentations in June 2020. Due to the COVID-19 pandemic, many public events and meetings – which HART was supposed to present or participate as part of its public outreach activities – were cancelled or postponed.

A project-wide virtual construction update/community meeting was held on June 30, 2020 from 1:30 p.m. – 2:30 p.m., where members of the public were invited online via YouTube and Facebook to take part in a comprehensive project update from West to East. HART’s construction contractors provided updates on construction and progress – including reports from WOSG/Nan, Inc., FHSG/Hawaiian Dredging Construction Company, KHSG/Nan, Inc., AGS/Shimmick, Traylor & Granite, Core Systems/Hitachi Rail, and CCUR/Nan, Inc. An audience Q/A session was also presented. The meeting recorded a high of 95 attendees online. HART PI is looking to have these meetings presented monthly until normal in-person community meetings can resume in the future.

Community outreach events in June included virtual Project Update presentations with the West Oahu Rotary Club and the Office of Hawaiian Affairs. A HART All-Staff Meeting was also presented with a PI progress presentation to internal audiences.

Page 116: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

116 | P a g e

HART Public Involvement continued with its new “Rail Facts LIVE” monthly online show utilizing Facebook LIVE. This month’s edition focused on a virtual tour of UH West O‘ahu Station, a highlight of its Art-in-Transit program and cultural design elements, and a virtual audience Q/A session.

HART Public Involvement completed four more installments of its “Rail Construction Traffic Update in Sixty Seconds” weekly video updates for its website, social media and eBlast platforms.

o 895 Neighborhood Board Meetings Most of the neighborhood boards started to resume regular meetings in virtual/online formats, due

to the COVID-19 pandemic. In person meetings are still TBD. Community Input HART's public outreach team responded to 59 public inquiries and comments via the 24-hour project hotline (28

inquiries) and project email ([email protected] with 31 inquiries), during the month of June 2020. Inquiries were generally related to general construction issues in the field and CCUR activities.

6.10 Staffing Overview

Organization: The latest organizational chart is dated Jan. 29, 2020. Please see Appendix D. Project Staffing:

o Target (Allocated) City Positions: 135 Full-Time Equivalent (FTE) City Staff. Does not include Project Management Support consultants below.

o Filled City Positions: 116 Employees: (103) Personal Services Contract [PSC] Employees, (1) Civil Service, (5) Appointees, (4) 89-day contract, (3) Interns

Vacancy Rate 2020

January February March April May June

11.8% 13.3% 13.3% 11.8% 10.3% 11.03%

July August September October November December

- - - - - -

o Project Management Support Consultant (HDR) Staff Total: 18 HDR employees embedded in the HART

organization directly participating in the management of the project, 2 HDR employees working for the State Historic Preservation Division (SHPD) providing support services, and 1 HDR employee assisting HART on a part-time basis with risk modeling (statistical analysis and risk report production).

Positions Filled in June:

o Electrical Engineer I (Core Systems) o Electrical Engineer I (Readiness & Activation)

Projected Position Fills: o Systems Analyst (Readiness & Activation)- July o Contract Management Assistant (Lead) - July o Right of Way Acquisition & Relocation Manager- August o Planner III (Hazmat Planner) – July o Planner IV (Transportation Planner) – July o Construction Claims Manager – August o Fixed Asset Specialist –July o Records Management Analyst II – July o Procurement & Specifications Specialist – August o Business Systems Analyst – July

June Departures: o Administrative Specialist I (Readiness & Activation) o Information Specialist II o Contract Management Assistant o Records Management Analyst II

Page 117: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

117 | P a g e

Projected Departures: o N/A

Figure 13. Staffing Activities

Staffing Activities

Title Group

New/Existing HART

Position (City or PMC)

Position Status* Start Month

P3 , Core Systems, and Readiness and Activation

Electrical Engineer I Core Systems Existing (City) Filled - PSC June

Electrical Engineer I Readiness and Activation New (City) Filled - PSC June

Systems Analyst Readiness and Activation New (City) Selected – PSC July

Design & Construction

Program Manager Production East Area Construction Existing (City) Recruiting - PSC

Assistant Area Manager East Area Construction Existing (City) Recruiting - PSC

Transportation Planner Third Party and Traffic Engineering

New (City) Recruiting - PSC

Transit Property Acquisition & Relocation

Right of Way Acquisition & Relocation Manager

Transit Property Acquisition & Relocation

Existing (City) Selected - PSC August

Planning

Planner (Land Use) Planning Existing (City) Recruiting – PSC

Planner III (Hazmat Planner) Planning Existing (City) Selected - PSC July

Planner IV (Transportation Planner) Planning Existing (City) Selected - PSC July

Budget & Finance

Financial Services Manager Budget & Finance Existing (City) Recruiting - PSC

Financial Analyst/Management Analyst

Budget & Finance Existing (City) Recruiting - PSC

Financial/Management Analyst (Financing)

Budget & Finance Existing (City) Recruiting - PSC

OCIP/Risk Compliance Budget & Finance Existing (City) Recruiting - PSC

Project Controls

Financial Analyst Project Controls Existing (City) Recruiting – PSC

Scheduler I –III Project Controls Existing (City) Recruiting – PSC

Business Systems Analyst Project Controls Existing (City) Selected – PSC July

Records Management Analyst II Project Controls Existing (City) Selected – PSC July

Procurement, Contracts & Construction Claims

Director Procurement, Contracts, and Construction Claims

Procurement, Contracts and Construction Claims

Existing (City) Recruiting – PSC

Procurement & Specifications Specialist

Procurement & Consultant Contracts

Existing (City) Selected - PSC August

Procurement & Specifications Specialist

Procurement & Consultant Contracts

Existing (City) Recruiting - PSC

Construction Claims Manager Construction Claims Existing (City) Selected - PSC August

Lead Contract Management Assistant

Contract Administration Existing (City) Selected – PSC July

Administrative Services

Human Resources Specialist V Administrative Services Existing (City) Recruiting - PSC

Asset Management

Fixed Asset Specialist Executive Management New (City) Selected – PSC July

*Personal Services Contracts are limited to one year per the Revised Charter of the City and County of Honolulu, Sec. 6-1103(g).

Page 118: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

118 | P a g e

6.11 HART Baseline Plans and Procedures Status List The status of the Baseline Plans and Procedures is shown below (NOTE: changes, if any, are in bold font):

Owner Plan/Procedure Revision Level Date Approved Status

Project Management (Sam Carnaggio)

Project Management Plan (PMP)

8.G April 21, 2020 Approved/Baselined

Safety and Security (Ralph McKinney)

Construction Safety and Security Plan (CSSP)

5.0 March 5, 2019 Approved/Baselined

Safety and Security Certification Plan (SSCP)

8.0 March 6, 2020 Approved/Baselined

Safety and Security Management Plan (SSMP)

9.0 March 6, 2020 Approved/Baselined

Sensitive Safety Information Plan

1.0 December 13, 2017 Approved/Baselined

Preliminary Hazard Analysis (PHA)

4.0 July 3, 2019 Approved/Baselined

Threat and Vulnerability Assessment (TVA)

2.0 January 12, 2018 Approved/Baselined

Incident Investigation Procedure

0.0 February 28, 2019 Approved/Baselined

Quality Assurance (Alberto Bonifacio)

1.PP-02, Project Procedure and Plan Revision and Control Procedure

4.0 February 22, 2019 Approved/Baselined

1.PP-03, Standard Terms, Definitions, and Acronyms Procedure

4.0 April 21, 2020 Approved/Baselined

3.PM-05, Meeting Minutes Procedure

4.0 January 28, 2019 Approved/Baselined

6.CM-01, Submittal Processing Procedure

4.0 January 28, 2019 Approved/Baselined

Quality Management Plan (QMP)

5.0 May 19, 2020 Approved/Baselined

Procurement, Contracts, and Construction

2.PA-09, Procurement Standards of Conduct Procedure

2.0 March 6, 2019 Approved/Baselined

Claims (David Ha)

2.PA-10, Procurement Methods Procedure

1.0 February 13, 2019 Approved/Baselined

2.PA-11, Procurement Full and Open Competition Procedure

1.0 February 13, 2019 Approved/Baselined

2.PA-12, Procurement Federal Compliance Procedure

1.0 March 5, 2019 Approved/Baselined

2.PA-13, Procurement Protests Procedure

2.0 February 13, 2019 Approved/Baselined

Page 119: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

119 | P a g e

Owner Plan/Procedure Revision Level Date Approved Status

2.PA-14, Procurement Record-keeping Procedure

1.0 April 2, 2019 Approved/Baselined

2.PA-15, Stipend Payment Procedure

1.0 February 11, 2019 Approved/Baselined

2.PA-16 Executive Decision Document (EDD) Procedure

0.0 January 24, 2019 Approved/Baselined

5.CA-06, Project Closeout Procedure

3.0 April 23, 2019 Approved/Baselined

5.CA-11, Contract Changes Procedure

6.0 May 26, 2020 Approved/Baselined

5.CA-12 Professional Services and Utility Engineering Services Agreement Contract Closeout Procedure

0.0 November 4, 2019 Approved/Baselined

Buy America Plan (BAP) 4.0 May 7, 2020 Approved/Baselined

HART Procurement Manual

1.0 April 25, 2019 Approved/Baselined

(David Uchiyama) 5.CA-13 Consultant Performance Milestone Evaluation Procedure

0.0 February 24, 2020 Approved/Baselined

5.CA-14 Consultant Performance Evaluation Procedure

0.0 February 24, 2020 Approved/Baselined

Project Controls (Nate Meddings)

2.PA-04, Project-wide Document Control and Project Library Procedure

4.0 November 25, 2019 Approved/Baselined

3.PM-01, Contract Management System Procedure

3.0 March 13, 2019 Approved/Baselined

4.PC-03, Project Progress Report Procedure

3.0 March 19, 2019 Approved/Baselined

4.PC-04, Project Scheduling Procedure

4.0 August 15, 2018 Approved/Baselined

4.PC-06, Cost Estimating Procedure

3.0 December 13, 2017 Approved/Baselined

4.PC-07, Cost Control Procedure

3.0 March 25, 2019 Approved/Baselined

4.PC-09, Contingency Management Procedure

2.0 March 5, 2019 Approved/Baselined

Contract Packaging Plan (CPP)

7.0 May 27, 2020 Approved/Baselined

Budget and Finance (Ruth Lohr)

5.CA-03, Contractor Payment Application Procedure

3.0 March 22, 2019 Approved/Baselined

5.CA-10, Consultant Invoice Payment Procedure

2.0 May 2, 2020 Approved/Baselined

Page 120: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

120 | P a g e

Owner Plan/Procedure Revision Level Date Approved Status

7.GA-04, Petty Cash Procedure

3.0 January 9, 2019 Approved/Baselined

7.GA-06, Travel Procedure

3.0 March 29, 2019 Approved/Baselined

Project Financial Plan (PFP): Revised Recovery Plan

1.0 November 19, 2018 Approved/Baselined

Planning and Permitting (Ryan Tam)

6.CM-08, Environmental Procedure

1.0 April 1, 2019 Approved/Baselined

Before-and-After Study Plan

1.0 March 25, 2019 Approved/Baselined

Bus Fleet Management Plan (BFMP)

5.0 April 15, 2019 Approved/Baselined

Mitigation Monitoring Plan (MMP)

4.0 June 29, 2020 Approved/Baselined

Right-of-Way (Dylan Jones)

Real Estate Acquisition Management Plan (RAMP)

7.0 January 23, 2019 Approved/Baselined

Public Information (Joyce Oliveira)

2.PA-06, Community Relations and Media Contacts Procedure

3.0 March 6, 2019 Approved/Baselined

3.PM-04, Public Involvement Communications Procedure

3.0 March 6, 2019 Approved/Baselined

Public Involvement Plan (PIP)

2.0 March 4, 2019 Approved/Baselined

Design and Construction (Frank Kosich)

6.CM-02, Request for Information (RFI) Processing Procedure

3.0 March 15, 2019 Approved/Baselined

CADD Procedures 2.0 March 19, 2019 Approved/Baselined

Configuration Management Plan (CFMP)

4.0 March 27, 2019 Approved/Baselined

Construction Management Plan (CMP)

5.0 June 16, 2020 Approved/Baselined

Operation and Maintenance (Robert Good/DTS)

Interface Management Plan (IMP)

5.0 May 5, 2020 Approved/Baselined

System Integration and Test Plan (SITP)

3.0 May 26, 2020 Approved/Baselined

Rail Fleet Management Plan (RFMP)

2.0 March 28, 2019 Approved/Baselined

Operation and Management Plan (OMP)

2.0 March 28, 2019 Approved/Baselined

Rail Activation Plan 3.0 May 18, 2020 Approved/Baselined

2. PA-17 DTS – HART Communication Procedure

0.0 July 15, 2019 Approved/Baselined

Page 121: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

121 | P a g e

Owner Plan/Procedure Revision Level Date Approved Status

Administrative Services (Dexter Suzuki)

1.PP-05, Identification Badge Procedure

3.0 January 24, 2019 Approved/Baselined

2.PA-03, Email Management Procedure

3.0 January 31, 2019 Approved/Baselined

2.PA-07, Training Procedure

3.0 January 31, 2019 Approved/Baselined

Staffing and Succession Plan

6.0 March 20, 2019 Approved/Baselined

Risk Management (Paul Johnson)

4.PC-08, Risk Management Procedure

3.0 March 8, 2019 Approved/Baselined

Risk and Contingency Management Plan (RCMP)

4.0 June 9, 2020 Approved/Baselined

6.12 Readiness and Activation

Overview of Key Responsibilities Oversight of the Core System Contractor’s Operations and Maintenance (O&M) development and mobilization. Review and support of HART project activities with an emphasis on O&M impact assessment. Collaborating with DTS to ensure readiness for O&M responsibilities.

Ongoing Activities

Supporting P3 procurement process. Key HRH Mobilization Activities

o Document Development Health, Safety, Quality and Environment (HSQE) documents have been formally submitted and

are under review with stakeholders. Completed internal Rule Book presentation – focus on integrated management system solution

using tablets. HRH is finalizing the Rule Book in combination with the Infrastructure Access Procedure and Railway Worker Protection Manual for formal submission.

HRH continues to develop the Trial Run Program Plan including: trial run resource loaded schedule, test cases, system demonstration, emergency drill, and transition from Test & Commissioning (T&C) to O&M. Held a Trial Run presentation for internal stakeholder comment and feedback.

o O&M Training started April 6. 8,200 hours of training for O&M staff through the end of June. Readiness and Activation (R&A) team is auditing select HRH training classes and course material. HRH continues to administer training via Instructor Led Course (in accordance with social

distancing measures) and online. o HRH continues to actively recruit key positions and experienced rail transit personnel.

HRH Head of O&M – Americas continues to support the mobilization effort. 120 of 178 O&M employees have accepted offers. Mass recruitment efforts continue, while the hiring ramp-up schedule is under review.

o Maintenance Activities Asset Management and Maintenance Management Plans officially submitted for review. Maintenance document suite drafted and under review.

All Maintenance Service Plans (MSP’s) have been formally submitted Continued oversight and auditing of the HRH maintenance program, KPIs, spares/consumables

and special tools.

Page 122: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

122 | P a g e

o Ongoing COVID-19 program impact assessment. DTS and project stakeholder coordination

o Facilitate Interim Opening Task Force Meeting with DTS, BFS and City Stakeholders. o Supporting document reviews per HART Charter Amendment 4 MOU procedure.

DTS Management Capacity and Capability Plan and Operations and Maintenance plan review and comment.

o Facilitating negotiations for Amendment 1 and 2 to the HDOT West O‘ahu Farrington Highway Master Agreement, and Joint Use and Occupancy Agreement.

o Jointly developing Grand Opening and Public Awareness and Safety Outreach plans with DTS. o HDOT comments on the Transit Agency Rail Safety Plan were received and incorporated. System Security

Plan submitted to HDOT. HRH continues to revise and re-submit supporting documentation. o Supporting fixed facility contractor O&M training development and documentation. o Supporting City Stakeholder participation in station walkthroughs for handover from fixed facility

contractors to the Core Systems Contractor. Supporting HART Safety revisions of Operational Readiness Conformance Checklist (ORCC) and Trial Run

Conformance Checklist to correspond with the HRH Mobilization Program. Onboarded R&A system analyst and mechanical engineer. Fare Systems (see Fare Systems section of report).

Look Ahead

Continued development of a COVID-19 Mitigation Plan for HRH Hiring and Training.

Oversight Procedure (OP) 54 part 2 and part 3 with HDOT/Project Management Oversight (PMO).

Page 123: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

123 | P a g e

APPENDICES

Page 124: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Ho

no

lulu

Rai

l Tra

nsi

t P

roje

ct M

on

thly

Pro

gre

ss R

ep

ort

Ju

ne

20

20

12

4 |

Pa

ge

A

pp

en

dix

A.

Pro

ject

Co

sts

by

SCC

– L

eve

l 2 (d

ata

as o

f Ju

ne

30

, 20

20

)

Co

st r

epo

rts

are

run

fro

m t

he

HA

RT

Co

ntr

act

Man

agem

ent

Syst

em

(C

MS)

SCC

De

scri

pti

on

Bas

e C

ost

Co

nti

nge

ncy

Tota

lB

ase

Co

stC

on

tin

gen

cyTo

tal

Incu

rre

d

10

GU

IDEW

AY

& T

RA

CK

ELE

MEN

TS1

,38

5,6

13

,35

0

22

2,8

68

,32

5

1

,60

8,4

81

,67

5

1,4

73

,02

1,4

40

1

35

,46

0,2

36

1,6

08

,48

1,6

76

9

40

,64

5,5

43

10

.02

Gu

idew

ay:

At-

gra

de

sem

i-ex

clu

sive

17

,37

8

-

1

7,3

78

17

,37

8

-

1

7,3

78

17

,37

8

1

0.0

4G

uid

ewa

y: A

eria

l st

ruct

ure

1,2

43

,17

0,3

39

2

14

,66

8,3

25

1,4

57

,83

8,6

64

1

,33

0,5

78

,42

9

12

7,2

60

,23

6

1

,45

7,8

38

,66

5

85

2,4

27

,72

0

1

0.0

5G

uid

ewa

y: B

uil

t-u

p f

ill

-

-

-

-

-

-

5,0

54

,74

4

1

0.0

6G

uid

ewa

y: U

nd

ergr

ou

nd

Cu

t &

Cvr

-

-

-

-

-

-

(1,2

28

,00

0)

1

0.0

8G

uid

ewa

y: R

eta

ined

cu

t o

r fi

ll1

42

,42

5,6

33

8,2

00

,00

0

1

50

,62

5,6

33

14

2,4

25

,63

3

8

,20

0,0

00

15

0,6

25

,63

3

-

1

0.0

9Tr

ack

: Dir

ect

fixa

tio

n-

-

-

-

-

-

8

0,4

48

,45

2

10

.11

Tra

ck: B

all

ast

ed-

-

-

-

-

-

2

,39

4,3

73

10

.12

Tra

ck: S

pec

ial

(sw

itch

es, t

urn

ou

ts)

-

-

-

-

-

-

1,5

30

,87

6

2

0ST

ATI

ON

S, S

TOP

S, T

ERM

INA

LS, I

NTE

RM

OD

A7

40

,27

8,8

79

91

,42

3,1

95

8

31

,70

2,0

74

81

2,1

91

,12

9

2

0,4

19

,81

8

83

2,6

10

,94

7

2

72

,68

9,1

24

20

.01

At-

gra

de

sta

tio

n, s

top

, sh

elte

r, m

all

, ter

min

al,

pla

tfo

rm4

,95

6,1

81

8,5

05

,32

5

1

3,4

61

,50

6

4,9

56

,18

1

8

,50

5,3

25

13

,46

1,5

06

1

1,4

20

,22

7

20

.02

Aer

ial

sta

tio

n, s

top

, sh

elte

r, m

all

, ter

min

al,

pla

tfo

rm5

48

,21

9,0

08

54

,49

6,4

53

6

02

,71

5,4

61

62

7,9

11

,85

7

(2

4,2

87

,52

3)

60

3,6

24

,33

4

2

43

,75

6,3

68

20

.04

Oth

er s

tati

on

s, l

an

din

gs, t

erm

ina

l-

-

-

-

-

-

-

2

0.0

6A

uto

mo

bil

e p

ark

ing

mu

lti-

sto

ry s

tru

ctu

re1

21

,60

9,4

73

26

,63

2,4

75

1

48

,24

1,9

48

12

1,6

09

,47

3

2

6,6

32

,47

5

14

8,2

41

,94

8

-

2

0.0

7El

eva

tors

, esc

ala

tors

65

,49

4,2

17

1

,78

8,9

42

67

,28

3,1

59

5

7,7

13

,61

8

9,5

69

,54

1

6

7,2

83

,15

9

17

,51

2,5

30

3

0SU

PP

OR

T FA

CIL

ITIE

S: Y

AR

DS,

SH

OP

S, A

DM

IN. B

LDG

S1

00

,80

6,8

54

-

10

0,8

06

,85

4

9

9,8

06

,85

4

1,0

00

,00

0

1

00

,80

6,8

54

12

2,2

67

,69

2

3

0.0

1A

dm

inis

tra

tio

n B

uil

din

g: O

ffic

e, S

ale

s-

-

-

-

-

-

2

31

,25

0

30

.02

Ligh

t M

ain

ten

an

ce F

aci

lity

3

,05

7,2

40

-

3,0

57

,24

0

3

,05

7,2

40

-

3,0

57

,24

0

7

,58

2,7

04

30

.03

Hea

vy M

ain

ten

an

ce F

aci

lity

64

,47

9,5

56

-

6

4,4

79

,55

6

63

,47

9,5

56

1

,00

0,0

00

64

,47

9,5

56

4

6,2

95

,36

6

30

.04

Sto

rage

or

Ma

inte

na

nce

of

Wa

y B

uil

din

g8

,61

9,2

30

-

8,6

19

,23

0

8

,61

9,2

30

-

8,6

19

,23

0

8

,89

2,7

39

30

.05

Yard

an

d Y

ard

Tra

ck2

4,6

50

,82

8

-

24

,65

0,8

28

2

4,6

50

,82

8

-

24

,65

0,8

28

5

9,2

65

,63

3

40

SITE

WO

RK

& S

PEC

IAL

CO

ND

ITIO

NS

2,3

15

,29

4,4

90

2

30

,44

2,9

32

2,5

45

,73

7,4

22

2

,43

7,0

64

,35

1

10

2,7

51

,42

9

2

,53

9,8

15

,78

0

1,0

79

,64

1,8

55

4

0.0

1D

emo

liti

on

, Cle

ari

ng,

Ea

rth

wo

rk3

3,4

46

,02

9

1,0

38

,00

0

3

4,4

84

,02

9

33

,44

6,0

29

1

,03

8,0

00

34

,48

4,0

29

5

,00

0,1

12

40

.02

Site

Uti

liti

es, U

tili

ty R

elo

cati

on

78

4,9

93

,47

4

9

7,1

26

,87

4

88

2,1

20

,34

8

1

,01

4,4

34

,88

4

(13

9,3

21

,17

8)

87

5,1

13

,70

6

2

31

,13

1,3

79

40

.03

Ha

z. M

at’

l, c

on

tam

’d s

oil

rem

ova

l/m

itig

ati

on

, gro

un

d w

ate

r tr

eatm

ents

33

,82

9,6

83

5

15

,00

0

34

,34

4,6

83

3

3,8

29

,68

3

51

5,0

00

3

4,3

44

,68

3

21

,82

3,8

78

4

0.0

4En

viro

nm

enta

l m

itig

ati

on

, e.g

. wet

lan

ds,

his

tori

c/a

rch

eolo

gic,

pa

rks

5,5

18

,86

4

-

5

,51

8,8

64

6,8

87

,36

4

(1

,36

8,5

00

)

5,5

18

,86

4

1

5,5

24

,74

3

40

.05

Site

str

uct

ure

s in

clu

din

g re

tain

ing

wa

lls,

so

un

d w

all

s2

1,7

64

,98

5

6,8

84

,51

1

2

8,6

49

,49

6

21

,76

4,9

85

6

,88

4,5

11

28

,64

9,4

96

1

3,1

25

,04

2

40

.06

Ped

estr

ian

/ b

ike

acc

ess

an

d a

cco

mm

od

ati

on

, la

nd

sca

pin

g1

4,7

44

,27

6

50

0,0

00

1

5,2

44

,27

6

14

,74

4,2

76

5

00

,00

0

15

,24

4,2

76

2

,48

2,1

94

40

.07

Au

tom

ob

ile,

bu

s, v

an

acc

essw

ays

in

clu

din

g ro

ad

s, p

ark

ing

lots

26

4,5

80

,52

4

2

9,2

37

,56

8

29

3,8

18

,09

2

2

81

,24

2,8

24

12

,57

5,2

68

2

93

,81

8,0

92

98

,42

4,6

57

4

0.0

8Te

mp

ora

ry F

aci

liti

es a

nd

oth

er i

nd

irec

t co

sts

du

rin

g co

nst

ruct

ion

1,1

56

,41

6,6

55

9

5,1

40

,97

9

1,2

51

,55

7,6

34

1

,03

0,7

14

,30

6

22

1,9

28

,32

8

1

,25

2,6

42

,63

4

69

2,1

29

,84

9

5

0SY

STEM

S3

13

,98

3,9

39

16

,03

3,6

68

3

30

,01

7,6

07

32

8,3

22

,83

3

6

,14

7,5

42

33

4,4

70

,37

5

1

66

,44

3,5

76

50

.01

Tra

in c

on

tro

l a

nd

sig

na

ls1

57

,07

7,7

32

7,7

56

,52

2

1

64

,83

4,2

54

17

0,5

38

,35

1

(1

,25

1,3

29

)

16

9,2

87

,02

2

7

2,4

59

,34

7

50

.02

Tra

ffic

sig

na

ls a

nd

cro

ssin

g p

rote

ctio

n3

,17

2,1

31

59

8,7

25

3

,77

0,8

56

3,1

72

,13

1

5

98

,72

5

3,7

70

,85

6

9

8,0

00

50

.03

Tra

ctio

n p

ow

er s

up

ply

: su

bst

ati

on

s 3

2,3

96

,80

8

-

32

,39

6,8

08

3

2,3

96

,80

8

-

32

,39

6,8

08

5

,24

0,1

30

50

.04

Tra

ctio

n p

ow

er d

istr

ibu

tio

n: c

ate

na

ry a

nd

th

ird

ra

il3

7,1

20

,97

7

-

37

,12

0,9

77

3

7,1

20

,97

7

-

37

,12

0,9

77

4

2,9

52

,90

8

50

.05

Co

mm

un

ica

tio

ns

65

,39

0,7

42

-

6

5,3

90

,74

2

65

,39

0,7

42

-

6

5,3

90

,74

2

35

,33

7,0

27

5

0.0

6Fa

re c

oll

ecti

on

sys

tem

an

d e

qu

ipm

ent

15

,01

5,2

06

7

,67

8,4

21

22

,69

3,6

27

1

5,8

93

,48

1

6,8

00

,14

6

2

2,6

93

,62

7

6,9

81

,96

7

5

0.0

7C

entr

al

Co

ntr

ol

3,8

10

,34

3

-

3

,81

0,3

43

3,8

10

,34

3

-

3

,81

0,3

43

3,3

74

,19

7

C

on

stru

ctio

n S

ub

tota

l (1

0 –

50

)4

,85

5,9

77

,51

2

56

0,7

68

,12

0

5

,41

6,7

45

,63

2

5,1

50

,40

6,6

07

2

65

,77

9,0

25

5,4

16

,18

5,6

32

2

,58

1,6

87

,79

1

Re

cove

ry P

lan

Bu

dge

tEs

tim

ate

At

Co

mp

leti

on

Page 125: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Ho

no

lulu

Rai

l Tra

nsi

t P

roje

ct M

on

thly

Pro

gre

ss R

ep

ort

Ju

ne

20

20

12

5 |

Pa

ge

SCC

De

scri

pti

on

Bas

e C

ost

Co

nti

nge

ncy

Tota

lB

ase

Co

stC

on

tin

gen

cyTo

tal

Incu

rre

d

60

RO

W, L

AN

D, E

XIS

TIN

G IM

PR

OV

EMEN

TS2

54

,83

5,5

74

10

6,7

89

,89

0

3

61

,62

5,4

64

38

5,0

41

,20

7

(2

3,4

15

,74

3)

36

1,6

25

,46

4

2

21

,92

2,7

07

60

.01

Pu

rch

ase

or

lea

se o

f re

al

esta

te

17

1,4

00

,00

0

1

01

,50

0,0

00

27

2,9

00

,00

0

3

01

,60

5,6

33

(28

,70

5,6

33

)

2

72

,90

0,0

00

22

1,6

44

,90

7

6

0.0

2R

elo

cati

on

of

exis

tin

g h

ou

seh

old

s a

nd

bu

sin

esse

s8

3,4

35

,57

4

5,2

89

,89

0

8

8,7

25

,46

4

83

,43

5,5

74

5

,28

9,8

90

88

,72

5,4

64

2

77

,80

0

70

VEH

ICLE

S2

11

,38

9,9

52

-

21

1,3

89

,95

2

2

11

,38

9,9

52

-

21

1,3

89

,95

2

1

37

,98

5,2

62

70

.01

Ligh

t R

ail

19

0,3

83

,69

4

-

1

90

,38

3,6

94

19

0,3

83

,69

4

-

1

90

,38

3,6

94

12

5,3

18

,57

0

7

0.0

2H

eavy

Ra

il-

-

-

-

-

-

-

7

0.0

5O

ther

12

8,7

00

-

1

28

,70

0

12

8,7

00

-

1

28

,70

0

49

3,7

00

7

0.0

6N

on

-rev

enu

e ve

hic

les

14

,37

1,3

44

-

1

4,3

71

,34

4

14

,37

1,3

44

-

1

4,3

71

,34

4

12

,17

2,9

92

7

0.0

7Sp

are

pa

rts

6,5

06

,21

4

-

6

,50

6,2

14

6,5

06

,21

4

-

6

,50

6,2

14

-

80

PR

OFE

SSIO

NA

L SE

RV

ICES

1,9

89

,87

0,7

25

9

7,6

30

,13

9

2,0

87

,50

0,8

64

2

,01

4,2

95

,72

5

73

,76

5,1

39

2

,08

8,0

60

,86

4

1,3

64

,56

9,1

99

8

0.0

1P

reli

min

ary

En

gin

eeri

ng

54

,75

3,8

40

-

5

4,7

53

,84

0

54

,75

3,8

40

-

5

4,7

53

,84

0

18

0,7

05

,91

6

8

0.0

2Fi

na

l D

esig

n5

84

,14

9,8

99

31

,51

2,6

97

6

15

,66

2,5

96

59

4,6

74

,89

9

2

0,9

87

,69

7

61

5,6

62

,59

6

3

69

,92

8,3

72

80

.03

Pro

ject

Ma

na

gem

ent

for

Des

ign

an

d C

on

stru

ctio

n6

68

,55

7,9

25

29

,85

1,8

33

6

98

,40

9,7

58

66

8,5

57

,92

5

2

9,8

51

,83

3

69

8,4

09

,75

8

5

01

,51

1,9

96

80

.04

Co

nst

ruct

ion

Ad

min

istr

ati

on

& M

an

age

men

t 2

78

,64

0,4

20

28

,22

0,0

08

3

06

,86

0,4

28

29

2,5

40

,42

0

1

4,3

20

,00

8

30

6,8

60

,42

8

2

25

,98

5,3

06

80

.05

Pro

fess

ion

al

Lia

bil

ity

an

d o

ther

No

n-C

on

stru

ctio

n I

nsu

ran

ce

99

,34

0,0

00

4

,00

0,0

00

10

3,3

40

,00

0

9

9,3

40

,00

0

4,0

00

,00

0

1

03

,34

0,0

00

45

,98

6,8

35

8

0.0

6Le

gal;

Per

mit

s; R

evie

w F

ees

by

oth

er a

gen

cies

, cit

ies,

etc

.9

9,9

28

,69

8

3,7

68

,43

9

1

03

,69

7,1

37

99

,92

8,6

98

3

,76

8,4

39

10

3,6

97

,13

7

3

4,1

70

,25

1

80

.07

Surv

eys,

Tes

tin

g, I

nve

stig

ati

on

, In

spec

tio

n1

41

,68

6,6

22

27

7,1

62

1

41

,96

3,7

84

14

1,6

86

,62

2

2

77

,16

2

14

1,9

63

,78

4

4

,16

4,1

19

80

.08

Sta

rt u

p6

2,8

13

,32

1

-

62

,81

3,3

21

6

2,8

13

,32

1

56

0,0

00

6

3,3

73

,32

1

2,1

16

,40

4

9

0Su

bto

tal (

10

– 8

0)

7,3

12

,07

3,7

63

7

65

,18

8,1

49

8,0

77

,26

1,9

12

7

,76

1,1

33

,49

1

31

6,1

28

,42

1

8

,07

7,2

61

,91

2

4,3

06

,16

4,9

59

U

NA

LLO

CA

TED

CO

NTI

NG

ENC

Y-

2

21

,73

8,0

87

22

1,7

38

,08

7

-

8

7,7

92

,27

9

87

,79

2,2

79

1

00

Sub

tota

l (1

0 –

90

)7

,31

2,0

73

,76

3

98

6,9

26

,23

6

8

,29

8,9

99

,99

9

7,7

61

,13

3,4

91

4

03

,92

0,7

00

8,1

65

,05

4,1

91

4

,30

6,1

64

,95

9

FIN

AN

CE

CH

AR

GES

60

9,0

00

,00

0

-

6

09

,00

0,0

00

54

7,0

00

,00

0

-

5

47

,00

0,0

00

44

,18

9,3

60

To

tal P

roje

ct C

ost

(1

0 –

10

0)

7,9

21

,07

3,7

63

9

86

,92

6,2

36

8,9

07

,99

9,9

99

8

,30

8,1

33

,49

1

40

3,9

20

,70

0

8

,71

2,0

54

,19

1

4,3

50

,35

4,3

19

Tota

l FFG

A P

roje

ct C

ost

(1

0 –

10

0)

7,9

21

,07

3,7

63

9

86

,92

6,2

36

8,9

07

,99

9,9

99

8

,30

8,1

33

,49

1

40

3,9

20

,70

0

8

,71

2,0

54

,19

1

4,3

50

,35

4,3

19

Esti

mat

e A

t C

om

ple

tio

nR

eco

very

Pla

n B

ud

get

Page 126: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

126 | P a g e

Appendix B. Core Accountability Items Including Major Issues

Core Accountability Items Including Major Issues – June 2020 Note that HART’s Recovery Plan, with revised budget and RSD, was approved by the FTA on Sept. 5, 2019; however, HART intends to continue to manage the project to its current EAC of September 2026.

Project Status: ($ are in millions) Original Budget

at FFGA HART

Current EAC Recovery Plan

Cost Base Cost w/o Contingency

$4,305 $7,761 $7,312

Contingency

Allocated $542 $316 $765

Unallocated Contingency $102 $88 $222

FFGA Finance Charges

$173 $547 $609

Post RSD Finance Charges

$42 $293 $231

Total Project Costs

$5,164 $9,005 $9,139

Schedule Revenue Service Date (RSD) January 31, 2020 September 2026 September 2026

Project Status: ($ are in millions) Amount ($) Percent

(as % of total)

Planned Value to Date $3,121 63.0%

Earned Value to Date $2,912 58.8%

Actual cost* $4,350 56.1%

Contracts

Total Contracts Awarded to Date $5,393 69.5%

Total Construction Contracts Awarded** (Construction Contracts Only)

$2,948 67.8%

Physical Construction Work Completed*** (Amount of Construction Actually Completed)

$2,214 50.9%

Date of Next Quarterly Meeting TBD

*Percentage calculated by taking Actual Cost divided by Base Cost w/o Contingency **Percentage calculated by taking Construction Contracts Only divided by Actual Cost ***Percentage calculated by taking Physical Construction Work divided by Actual Cost

Page 127: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

127 | P a g e

Appendix C. Construction Progress Interim Opening

Page 128: June 2020 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-24008/June … · Transit Administration (FTA), in the interest of information exchange. The United

Honolulu Rail Transit Project Monthly Progress Report June 2020

128 | P a g e

Appendix D. Project Organization Chart