Top Banner
June 16, 2015 SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota [email protected] 1
24

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

Jan 18, 2018

Download

Documents

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test I&T Plans Philosophy –Requirements are verified as early as possible at a low level Verifies subsystems, Retires risk –Requirements are verified at the highest level of assembly possible Often involves verifying a requirement at several levels –Maintain flexibility in test sequencing to maintain schedule Tests on ETU/EM ✔ –Substantial environmental test program on EM hardware –FIELDS EM units have been assembled, integrated and tested –Includes TV Tests on Flight Units –Full environmental test program on Flight units Typical Test Levels: –Subassembly (circuit board): functional –Component (e.g. V1, MAG, SCM, MEP): functional, mass properties, vibration, TV, deployments, magnetics –Instrument: functional, calibration, interface, EMC, TV 3
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 1SPP/FIELDS SOC CDR: Integration & Test

SPP/FIELDSIntegration and Test

SOC Critical Design Review

Keith GoetzUniversity of Minnesota

[email protected]

Page 2: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 2SPP/FIELDS SOC CDR: Integration & Test

FIELDS Block Diagram

Page 3: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 3SPP/FIELDS SOC CDR: Integration & Test

I&T Plans

• Philosophy– Requirements are verified as early as possible at a low level

• Verifies subsystems, Retires risk– Requirements are verified at the highest level of assembly possible

• Often involves verifying a requirement at several levels– Maintain flexibility in test sequencing to maintain schedule

• Tests on ETU/EM ✔– Substantial environmental test program on EM hardware– FIELDS EM units have been assembled, integrated and tested– Includes TV

• Tests on Flight Units– Full environmental test program on Flight units

• Typical Test Levels:– Subassembly (circuit board): functional– Component (e.g. V1, MAG, SCM, MEP): functional, mass properties,

vibration, TV, deployments, magnetics– Instrument: functional, calibration, interface, EMC, TV

Page 4: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 4SPP/FIELDS SOC CDR: Integration & Test

Planned ETU I&T Flow

Page 5: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 5SPP/FIELDS SOC CDR: Integration & Test

Planned FM I&T Flow

Page 6: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 6SPP/FIELDS SOC CDR: Integration & Test

Procedures

• Each test will be documented by a Test Procedure– Test procedure shall identify IRD requirements to be verified by the test– Test procedure shall include pass/fail criteria– System Engineer, QA, Subsystem lead to sign off on procedure before use– System Engineer, QA to sign off on completed as-run procedure– QA to ensure Red-lines to be transferred into procedure before next use

• Each completed test to be documented by a Test Report– ETU and subassembly test reports may be a combination of the as-run

procedure and lab notebook– System Engineer to sign off on test reports, and determine if test adequately

verifies associated requirements• Discrepancies found during tests to be documented in a Problem

Failure Report (PFR)– Starting with first functional tests at FM subassembly level– Includes any problem (including software) not immediately identified as a test

setup or operator problem which cannot stress the flight article– QA will track PFRs to closure with concurrence of the Failure Review Board

(includes APL)

Page 7: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 7SPP/FIELDS SOC CDR: Integration & Test

Calibrations

• Co-I hardware institutions will deliver fully calibrated sub-assemblies

• Once FIELDS instrument is fully integrated– Several verification cals in ambient and at temperature– Timing– SWEAP

• Antennas – as mechanical elements – can be tested separately

Page 8: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 8SPP/FIELDS SOC CDR: Integration & Test

Interfaces

• Interface tests verify interfaces meet requirements from ICD and/or specifications.

• FIELDS ETU well tested with APL S/C mini emulators• FIELDS FM to be tested with APL S/C full emulators• FIELDS TDS ETU/FM to be tested with SWEAP (at UCB)• At other times (prior to Observatory I&T) interfaces simulated with

GSE – Board, Component level tests performed with

• Board Interface Simulation GSE– Instrument-level tests performed with:

• APL-provided spacecraft emulators• Command and Telemetry GSE software• Stimulation GSE or internal test signal• SWEAP simulator (FIG)• Deployment actuator simulators

– GSE functionality, design described in GSE section

Page 9: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 9SPP/FIELDS SOC CDR: Integration & Test

Mechanical Testing

• Antenna mechanisms can be tested independently of electronics• Full functional testing• Vibration• TV• Where appropriate, testing will include whips

• FIELDS Contamination Control Plan documents how FIELDS will meet Project contamination control requirements

Page 10: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 10SPP/FIELDS SOC CDR: Integration & Test

Thermal Testing

• Tests per SPP Environmental Spec– 1 survival and 6 operational thermal vacuum cycles– Temperature ranges detailed in thermal presentation

• Per FIELDS V&V and T&C plan– V1-V4 PAs in one range– V5 PA in one range– MAG sensors (at GSFC)– SCM assembly (at LPC2E)– MEP is the simplest

• Includes all sensors– Antenna mechanisms

• Proposed Thermal Balance test using ETU FIELDS boom and ETU sensors – fall 2015

Page 11: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 11SPP/FIELDS SOC CDR: Integration & Test

EMC Tests

• Tests per EMECP

• Electro-Static Discharge Test (EM only)• DC Magnetics (sniff test)• Surface Charging / Electrostatic Cleanliness• Ground Bonding and Isolation• Turn On/Off Transients• CE, CS, RE, RS Tests as detailed in EMECP

– ETU will only do CE measurements on the bench ✔

Page 12: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 12SPP/FIELDS SOC CDR: Integration & Test

S/C-level I&T

• FIELDS and APL have had discussions w/r/t S/C level I&T

• FIELDS integration will involve a number of hardware elements (~20)

• FIELDS magnetic sensors will have protective enclosures• FIELDS will have external stimulus to support CPT functional testing

• Antennas will not be deployed at Spacecraft level– Too hard to implement off-loading GSE at spacecraft level– First motion without whips

• Actuator simulators will be provided to perform simulated boom deployments– Simulators contain flight-like resetable actuators (or equivalent loads)– Simulators attach to S/C deployment harnessing– Simulators can be used at spacecraft-level TV

Page 13: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 13SPP/FIELDS SOC CDR: Integration & Test

FIELDS Flight Configuration

Page 14: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 14SPP/FIELDS SOC CDR: Integration & Test

FIELDS Bench Testing Configuration

Page 15: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 15SPP/FIELDS SOC CDR: Integration & Test

FIELDS CPT Configuration

Page 16: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 16SPP/FIELDS SOC CDR: Integration & Test

FIELDS Flight Configuration

SOC

Page 17: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 17SPP/FIELDS SOC CDR: Integration & Test

GSE Evolution

• SOC development will flow naturally from GSE• GSE and GSEOS are fully functional with FIELDS EM

– FIELDS1 and FIELDS2 EMs• GSE and GSEOS will continue with FM development

– At all hardware institutions• UCB, UMN, LASP, GSFC

– Used for all commanding• FIELDS1/FIELDS2

– Used for acquiring all telemetry• FIELDS1/FIELDS2

– Will move with us to APL for S/C level I&T• GSE and GSEOS will evolve into components of SOC

after launch– Used to build, test and send command loads– Used to operate EM test-beds at UCB and UMN

Page 18: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 18SPP/FIELDS SOC CDR: Integration & Test

Commissioning - 1

• FIELDS has a number of critical steps in the commissioning period

• Deployment of the magnetometer boom (day ~3)– Turn on and check out FIELDS MEP– Turn on and check out FIELDS MAGs

• Command for high rate MAG data– Turn on and check out FIELDS SCM

• Command for SCM configuration– Gather background data - stowed– Deploy MAG Boom– Gather background data - deployed

Page 19: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 19SPP/FIELDS SOC CDR: Integration & Test

Commissioning - 2

• Deployment of the V1234 Antennas (day ~30)– Turn on and check out FIELDS MEP

• Command for data acquisition– Deploy Antennas

• Deploy V1– Gather background data - stowed– Deploy V1– Gather background data – deployed

• Deploy V2– Gather background data - stowed– Deploy V2– Gather background data - deployed

• Deploy V3– Gather background data - stowed– Deploy V3– Gather background data - deployed

• Deploy V4– Gather background data - stowed– Deploy V4– Gather background data – deployed

– Survey deployed antenna beam patterns

Page 20: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 20SPP/FIELDS SOC CDR: Integration & Test

Commissioning - 3

• Observe Probable Interference from TWTA (day ~30)– Start TWTA X-band contact– Turn on FIELDS MEP

• Command for data acquisition– Turn off TWTA– Send FIELDS science data to spacecraft SSR– Turn on TWTA by timed command– Playback recorded data

– Repeat

Page 21: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 21SPP/FIELDS SOC CDR: Integration & Test

Commissioning - 4

• Observe Interactions with Other SPP Instrument (day ~40)– Start TWTA X-band contact– Turn on FIELDS MEP

• Command for data acquisition– Turn on SWEAP

• Test inter-instrument interface• Run in noisy mode

– Turn on EPI (2)• Run in noisy mode

– Turn on WISPR• Run in noisy mode

– Repeat in reverse order looking for interference

Page 22: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 22SPP/FIELDS SOC CDR: Integration & Test

Commissioning - 5

• Observe Interactions with SPP Spacecraft (day TBD)– Start TWTA X-band contact– Turn on FIELDS MEP

• Command for data acquisition– Turn on other instruments as desired

– Run reaction wheel speed program– Run SA flap and feather– Run HGA motion survey

– Repeat - looking for interference

Page 23: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 23SPP/FIELDS SOC CDR: Integration & Test

Commissioning - 6

• Observe SPP Spacecraft Attitudes (day TBD)– Start TWTA X-band contact– Turn on FIELDS MEP

• Command for data acquisition– Turn on other instruments as desired

– Run some rolls – fast– Run some slews

• Run a roll while slewed

– Repeat

Page 24: June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

June 16, 2015 24SPP/FIELDS SOC CDR: Integration & Test

Conclusion

• Instrument I&T plans are in good shape– Previous experience helps

• Spacecraft I&T plans are getting started– Previous experience helps here too

• FIELDS SOC is ready to move forward