June 16, 2015 SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota [email protected] 1
Jan 18, 2018
June 16, 2015 1SPP/FIELDS SOC CDR: Integration & Test
SPP/FIELDSIntegration and Test
SOC Critical Design Review
Keith GoetzUniversity of Minnesota
June 16, 2015 2SPP/FIELDS SOC CDR: Integration & Test
FIELDS Block Diagram
June 16, 2015 3SPP/FIELDS SOC CDR: Integration & Test
I&T Plans
• Philosophy– Requirements are verified as early as possible at a low level
• Verifies subsystems, Retires risk– Requirements are verified at the highest level of assembly possible
• Often involves verifying a requirement at several levels– Maintain flexibility in test sequencing to maintain schedule
• Tests on ETU/EM ✔– Substantial environmental test program on EM hardware– FIELDS EM units have been assembled, integrated and tested– Includes TV
• Tests on Flight Units– Full environmental test program on Flight units
• Typical Test Levels:– Subassembly (circuit board): functional– Component (e.g. V1, MAG, SCM, MEP): functional, mass properties,
vibration, TV, deployments, magnetics– Instrument: functional, calibration, interface, EMC, TV
June 16, 2015 4SPP/FIELDS SOC CDR: Integration & Test
Planned ETU I&T Flow
June 16, 2015 5SPP/FIELDS SOC CDR: Integration & Test
Planned FM I&T Flow
June 16, 2015 6SPP/FIELDS SOC CDR: Integration & Test
Procedures
• Each test will be documented by a Test Procedure– Test procedure shall identify IRD requirements to be verified by the test– Test procedure shall include pass/fail criteria– System Engineer, QA, Subsystem lead to sign off on procedure before use– System Engineer, QA to sign off on completed as-run procedure– QA to ensure Red-lines to be transferred into procedure before next use
• Each completed test to be documented by a Test Report– ETU and subassembly test reports may be a combination of the as-run
procedure and lab notebook– System Engineer to sign off on test reports, and determine if test adequately
verifies associated requirements• Discrepancies found during tests to be documented in a Problem
Failure Report (PFR)– Starting with first functional tests at FM subassembly level– Includes any problem (including software) not immediately identified as a test
setup or operator problem which cannot stress the flight article– QA will track PFRs to closure with concurrence of the Failure Review Board
(includes APL)
June 16, 2015 7SPP/FIELDS SOC CDR: Integration & Test
Calibrations
• Co-I hardware institutions will deliver fully calibrated sub-assemblies
• Once FIELDS instrument is fully integrated– Several verification cals in ambient and at temperature– Timing– SWEAP
• Antennas – as mechanical elements – can be tested separately
June 16, 2015 8SPP/FIELDS SOC CDR: Integration & Test
Interfaces
• Interface tests verify interfaces meet requirements from ICD and/or specifications.
• FIELDS ETU well tested with APL S/C mini emulators• FIELDS FM to be tested with APL S/C full emulators• FIELDS TDS ETU/FM to be tested with SWEAP (at UCB)• At other times (prior to Observatory I&T) interfaces simulated with
GSE – Board, Component level tests performed with
• Board Interface Simulation GSE– Instrument-level tests performed with:
• APL-provided spacecraft emulators• Command and Telemetry GSE software• Stimulation GSE or internal test signal• SWEAP simulator (FIG)• Deployment actuator simulators
– GSE functionality, design described in GSE section
June 16, 2015 9SPP/FIELDS SOC CDR: Integration & Test
Mechanical Testing
• Antenna mechanisms can be tested independently of electronics• Full functional testing• Vibration• TV• Where appropriate, testing will include whips
• FIELDS Contamination Control Plan documents how FIELDS will meet Project contamination control requirements
June 16, 2015 10SPP/FIELDS SOC CDR: Integration & Test
Thermal Testing
• Tests per SPP Environmental Spec– 1 survival and 6 operational thermal vacuum cycles– Temperature ranges detailed in thermal presentation
• Per FIELDS V&V and T&C plan– V1-V4 PAs in one range– V5 PA in one range– MAG sensors (at GSFC)– SCM assembly (at LPC2E)– MEP is the simplest
• Includes all sensors– Antenna mechanisms
• Proposed Thermal Balance test using ETU FIELDS boom and ETU sensors – fall 2015
June 16, 2015 11SPP/FIELDS SOC CDR: Integration & Test
EMC Tests
• Tests per EMECP
• Electro-Static Discharge Test (EM only)• DC Magnetics (sniff test)• Surface Charging / Electrostatic Cleanliness• Ground Bonding and Isolation• Turn On/Off Transients• CE, CS, RE, RS Tests as detailed in EMECP
– ETU will only do CE measurements on the bench ✔
June 16, 2015 12SPP/FIELDS SOC CDR: Integration & Test
S/C-level I&T
• FIELDS and APL have had discussions w/r/t S/C level I&T
• FIELDS integration will involve a number of hardware elements (~20)
• FIELDS magnetic sensors will have protective enclosures• FIELDS will have external stimulus to support CPT functional testing
• Antennas will not be deployed at Spacecraft level– Too hard to implement off-loading GSE at spacecraft level– First motion without whips
• Actuator simulators will be provided to perform simulated boom deployments– Simulators contain flight-like resetable actuators (or equivalent loads)– Simulators attach to S/C deployment harnessing– Simulators can be used at spacecraft-level TV
June 16, 2015 13SPP/FIELDS SOC CDR: Integration & Test
FIELDS Flight Configuration
June 16, 2015 14SPP/FIELDS SOC CDR: Integration & Test
FIELDS Bench Testing Configuration
June 16, 2015 15SPP/FIELDS SOC CDR: Integration & Test
FIELDS CPT Configuration
June 16, 2015 16SPP/FIELDS SOC CDR: Integration & Test
FIELDS Flight Configuration
SOC
June 16, 2015 17SPP/FIELDS SOC CDR: Integration & Test
GSE Evolution
• SOC development will flow naturally from GSE• GSE and GSEOS are fully functional with FIELDS EM
– FIELDS1 and FIELDS2 EMs• GSE and GSEOS will continue with FM development
– At all hardware institutions• UCB, UMN, LASP, GSFC
– Used for all commanding• FIELDS1/FIELDS2
– Used for acquiring all telemetry• FIELDS1/FIELDS2
– Will move with us to APL for S/C level I&T• GSE and GSEOS will evolve into components of SOC
after launch– Used to build, test and send command loads– Used to operate EM test-beds at UCB and UMN
June 16, 2015 18SPP/FIELDS SOC CDR: Integration & Test
Commissioning - 1
• FIELDS has a number of critical steps in the commissioning period
• Deployment of the magnetometer boom (day ~3)– Turn on and check out FIELDS MEP– Turn on and check out FIELDS MAGs
• Command for high rate MAG data– Turn on and check out FIELDS SCM
• Command for SCM configuration– Gather background data - stowed– Deploy MAG Boom– Gather background data - deployed
June 16, 2015 19SPP/FIELDS SOC CDR: Integration & Test
Commissioning - 2
• Deployment of the V1234 Antennas (day ~30)– Turn on and check out FIELDS MEP
• Command for data acquisition– Deploy Antennas
• Deploy V1– Gather background data - stowed– Deploy V1– Gather background data – deployed
• Deploy V2– Gather background data - stowed– Deploy V2– Gather background data - deployed
• Deploy V3– Gather background data - stowed– Deploy V3– Gather background data - deployed
• Deploy V4– Gather background data - stowed– Deploy V4– Gather background data – deployed
– Survey deployed antenna beam patterns
June 16, 2015 20SPP/FIELDS SOC CDR: Integration & Test
Commissioning - 3
• Observe Probable Interference from TWTA (day ~30)– Start TWTA X-band contact– Turn on FIELDS MEP
• Command for data acquisition– Turn off TWTA– Send FIELDS science data to spacecraft SSR– Turn on TWTA by timed command– Playback recorded data
– Repeat
June 16, 2015 21SPP/FIELDS SOC CDR: Integration & Test
Commissioning - 4
• Observe Interactions with Other SPP Instrument (day ~40)– Start TWTA X-band contact– Turn on FIELDS MEP
• Command for data acquisition– Turn on SWEAP
• Test inter-instrument interface• Run in noisy mode
– Turn on EPI (2)• Run in noisy mode
– Turn on WISPR• Run in noisy mode
– Repeat in reverse order looking for interference
June 16, 2015 22SPP/FIELDS SOC CDR: Integration & Test
Commissioning - 5
• Observe Interactions with SPP Spacecraft (day TBD)– Start TWTA X-band contact– Turn on FIELDS MEP
• Command for data acquisition– Turn on other instruments as desired
– Run reaction wheel speed program– Run SA flap and feather– Run HGA motion survey
– Repeat - looking for interference
June 16, 2015 23SPP/FIELDS SOC CDR: Integration & Test
Commissioning - 6
• Observe SPP Spacecraft Attitudes (day TBD)– Start TWTA X-band contact– Turn on FIELDS MEP
• Command for data acquisition– Turn on other instruments as desired
– Run some rolls – fast– Run some slews
• Run a roll while slewed
– Repeat
June 16, 2015 24SPP/FIELDS SOC CDR: Integration & Test
Conclusion
• Instrument I&T plans are in good shape– Previous experience helps
• Spacecraft I&T plans are getting started– Previous experience helps here too
• FIELDS SOC is ready to move forward