Top Banner
1 Stormwater Pond Sediment Loading and Accumulation Analysis Michael A. Gregory Abstract The permanent pool in stormwater detention facilities is designed for water quality treatment by providing an appropriate stor- age volume for the settling of the suspended solids and particulate matter that are carried in stormwater runoff. The facility may include additional storage components designed to provide erosion and flood control, but it is the layout and configuration of the permanent pool volume that typically dictates the overall pond footprint size. Sizing of the permanent pool volume is often based on local regulatory requirements that dictate a prescribed total suspended solids (TSS) removal rate, expressed as a percentage removal on an average annual basis. The volume requirement is typically given as a function of the imperviousness and area of the tributary catchment. It is presumed that a pond that meets or exceeds the required volume will achieve its TSS removal target. The actual treatment efficiency of the pond is a function of catchment hydrology (of which imperviousness is just one of many variables), control structure hydraulics, and the particle size distribution of TSS in stormwater runoff. After the pond has been constructed it is also important for the owner or operator of the pond to understand the sediment loading and accumulation char- acteristics, given the high cost of sediment removal. Presumptive design criteria used to size the permanent pool of stormwater ponds do not account for these site specific characteristics. To overcome the limitations inherent in presumptive design criteria, a modeling and design methodology using SWMM5 was developed to estimate the sediment loading and accumulation rate for a facility in Ontario, Canada. Keywords: stormwater detention facilities, total suspended solids (TSS), particle size distribution, treatment efficiency. 1 Background In November, 2011 the City of Hamilton, Ontario retained AECOM to provide consulting engineering services related to the design, permitting and construction of the Twenty Road regional storm- water management facility. This facility is located on city owned property, a 2.2 ha (5.4 acre) parcel southeast of the intersection of Twenty Road and the future Dartnall Road extension, designed to service 36 ha (89 acre) of future development on primarily com- mercial and industrial lands. The stormwater servicing design includes infrastructure for collecting and managing stormwater to minimize flooding and erosion hazards, as well as to maximize water quality treatment and environmental benefits in the downstream receiving water- courses of Hannon Creek, which ultimately discharges into Lake Ontario. Figure 1 shows the layout and configuration for the pond design. There are two piped inlets discharging to the forebay that will serve future developments to the east and west. A deflec- tion berm was designed to improve the settling and dispersion of the particulate pollutants that remain in the stormwater runoff after treatment in the forebay (by increasing the hydraulic residence time from the forebay to the outlet). The permanent pool elevation in both the forebay and main cell of the pond are shown in light grey in the figure. Two rip-rap lined channels direct major system overflows into the pond from the east and west, bypassing the forebay. The figure also shows the maintenance access route (dark gray) and planting shelf around the pond perimeter, as well as the sediment decant and drying area along the south edge of the property. The primary outfall discharges into a receiving watercourse located northwest of the pond, and a secondary pond outfall discharges to the northeast for the purpose of providing supplementary inflows for a relocated watercourse (in order to maintain the exist- ing flow regime) as part of the site development in the adjacent property to the east. The analysis and design efforts undertaken during this project were subject to stringent deadlines. Fieldwork and model setup began in December 2011, and the final design and permit- ting was completed in June 2012. This project required ongoing design coordination with others on adjacent properties, includ- ing roadway extensions, watercourse relocations and significant site development of an industrial property to be serviced by the pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving watercourses throughout the study area. Construction began in Gregory, M. 2014. "Stormwater Pond Sediment Loading and Accumulation Analysis." Journal of Water Management Modeling C378. doi: 10.14796/JWMM.C378. © CHI 2014 www.chijournal.org ISSN: 2292-6062
10

Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

Oct 17, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

1

Stormwater Pond Sediment Loading and Accumulation Analysis

Michael A. Gregory

Abstract

The permanent pool in stormwater detention facilities is designed for water quality treatment by providing an appropriate stor-

age volume for the settling of the suspended solids and particulate matter that are carried in stormwater runoff. The facility may

include additional storage components designed to provide erosion and flood control, but it is the layout and configuration of the

permanent pool volume that typically dictates the overall pond footprint size. Sizing of the permanent pool volume is often based

on local regulatory requirements that dictate a prescribed total suspended solids (TSS) removal rate, expressed as a percentage

removal on an average annual basis. The volume requirement is typically given as a function of the imperviousness and area of

the tributary catchment. It is presumed that a pond that meets or exceeds the required volume will achieve its TSS removal target.

The actual treatment efficiency of the pond is a function of catchment hydrology (of which imperviousness is just one of many

variables), control structure hydraulics, and the particle size distribution of TSS in stormwater runoff. After the pond has been

constructed it is also important for the owner or operator of the pond to understand the sediment loading and accumulation char-

acteristics, given the high cost of sediment removal. Presumptive design criteria used to size the permanent pool of stormwater

ponds do not account for these site specific characteristics. To overcome the limitations inherent in presumptive design criteria, a

modeling and design methodology using SWMM5 was developed to estimate the sediment loading and accumulation rate for a

facility in Ontario, Canada.

Keywords: stormwater detention facilities, total suspended solids (TSS), particle size distribution, treatment efficiency.

1 BackgroundIn November, 2011 the City of Hamilton, Ontario retained AECOM to provide consulting engineering services related to the design, permitting and construction of the Twenty Road regional storm-water management facility. This facility is located on city owned property, a 2.2 ha (5.4 acre) parcel southeast of the intersection of Twenty Road and the future Dartnall Road extension, designed to service 36 ha (89 acre) of future development on primarily com-mercial and industrial lands.

The stormwater servicing design includes infrastructure for collecting and managing stormwater to minimize flooding and erosion hazards, as well as to maximize water quality treatment and environmental benefits in the downstream receiving water-courses of Hannon Creek, which ultimately discharges into Lake Ontario.

Figure 1 shows the layout and configuration for the pond design. There are two piped inlets discharging to the forebay that will serve future developments to the east and west. A deflec-tion berm was designed to improve the settling and dispersion of the particulate pollutants that remain in the stormwater runoff after treatment in the forebay (by increasing the hydraulic residence time from the forebay to the outlet). The permanent

pool elevation in both the forebay and main cell of the pond are shown in light grey in the figure.

Two rip-rap lined channels direct major system overflows into the pond from the east and west, bypassing the forebay. The figure also shows the maintenance access route (dark gray) and planting shelf around the pond perimeter, as well as the sediment decant and drying area along the south edge of the property. The primary outfall discharges into a receiving watercourse located northwest of the pond, and a secondary pond outfall discharges to the northeast for the purpose of providing supplementary inflows for a relocated watercourse (in order to maintain the exist-ing flow regime) as part of the site development in the adjacent property to the east.

The analysis and design efforts undertaken during this project were subject to stringent deadlines. Fieldwork and model setup began in December 2011, and the final design and permit-ting was completed in June 2012. This project required ongoing design coordination with others on adjacent properties, includ-ing roadway extensions, watercourse relocations and significant site development of an industrial property to be serviced by the pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving watercourses throughout the study area. Construction began in

Gregory, M. 2014. "Stormwater Pond Sediment Loading and Accumulation Analysis." Journal of Water Management Modeling C378. doi: 10.14796/JWMM.C378.© CHI 2014 www.chijournal.org ISSN: 2292-6062

Page 2: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

2

Figure 1 Plan view of stormwater detention facility design (not to scale).

October 2012 and was completed in early 2013. Figure 2 shows a photo of the pond in January 2013 (looking southeast).

Figure 2 Stormwater detention facility during construction (photo courtesy of the City of Hamilton).

2 Model Development (Event Based Simulation)

The latest version of SWMM5 (build 5.0.022, released April 2011) was used to simulate the stormwater runoff response under existing and proposed land use conditions, and to analyze and optimize the pond design.

2.1 Hydrologic ModelStormwater facilities were designed using a traditional event based hydrology approach, which is most appropriate for flood control where the design objective is to collect and dispose of runoff in a manner that protects public safety and minimizes property damage during extreme events. The sizing of the major and minor collection system, pond control structures and outlet works adheres to the local municipal and provincial design stan-dards, which quantify criteria for a range of defined design storm events that include:

Page 3: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

3

· baseflow event featuring 15 mm rainfall over 24 h duration, which corresponds to a 1 month return period;

· water quality control volume event featuring 25 mm rainfall over 24 h duration, which corresponds to a 3 month return period;

· 2 y return period 24 h duration event with 53.1 mm rain;

· 5 y 24 h event with 71.8 mm rain; · 10 y 24 h event with 84.2 mm rain; · 25 y 24 h event with 99.8 mm rain; · 100 y 24 h event with 122.9 mm rain; and · the regional storm event, Hurricane Hazel, repre-

sented by a rainfall depth of 285 mm over a 48 h period. This event features 212 mm of rainfall over a 12 h period, preceded by 73 mm rainfall over a period of 36 h.

The hydrologic model was developed using lumped par-ameters in which average representative values were determined for each hydrologic unit (or subcatchment) tributary to the pro-posed pond. Overland flow parameters describe the slope and length characteristics of shallow surface runoff. Representative overland flow paths were identified for each hydrologic unit. The overland flow path slope was taken as the grade difference of the land surface along the overland flow path. Overland flow path lengths were divided into the subcatchment area to give a characteristic width of overland flow, which is a SWMM5 input parameter.

Surface cover parameters describe the imperviousness, roughness and depression storage characteristics. Various surface cover types were defined in order to reflect the unique hydrologic properties within each subcatchment. These were selected in consideration of the TSS buildup and washoff characteristics that also vary by surface cover type, as discussed below for water quality. The surface cover types include:

· Forest: forest or meadow, heavy vegetation with high transpiration rates and a deep root zone;

· Grass: grass or turf, light vegetation, cultivated or landscaped areas with a shallow root zone;

· Farm: cultivated agricultural fields; · Bare: unvegetated soil, loose granular materials, or

legacy compacted fill; · GrnRoof: building structures with vegetated roof; · RegRoof: building structures with regular rooftop

construction and materials; · PrmPave: permeable paved surfaces with underdrain

system; · ImpPave: regular impermeable paved surfaces (road-

ways, parking, driveways); · Gravel: gravel and compacted granular in traffic

areas; · Wetland: hydrologic parameters reflect an area that

is roughly half open water and half heavily vege-tated; and

· Water: open water surface, including detention facilities.

Surface cover types were interpreted using aerial pho-tography of the site. Characteristic hydrologic properties were assigned to each surface cover type as shown in Table 1, based on literature values (e.g. Bedient and Huber 1992; Chow et al. 1988) and adapted for use in many watershed master planning and de-sign studies throughout North America.

Table 1 Summary of hydrologic properties (by surface cover type).

Manning's "n" Dep. Storage (mm) % % Imperv.Surface Cover Imperv- Pervious Imperv- Pervious Imperv- Subarea % Without

Type ious ious ious Routing Routed StorageForest 0.030 0.400 10.0 15.0 1 Pervious 100 10Grass 0.025 0.250 5.0 10.0 2.5 Pervious 75 10Farm 0.025 0.350 5.0 10.0 5 Pervious 75 10Bare 0.020 0.150 5.0 7.5 5 Pervious 50 10

GrnRoof 0.025 0.300 17.5 20.0 25 Pervious 25 15RegRoof 0.015 0.150 2.5 5.0 95 Pervious 10 25PrmPave 0.020 0.200 12.5 15.0 50 Pervious 25 15ImpPave 0.015 0.150 2.5 5.0 95 Pervious 10 20

Gravel 0.025 0.200 5.0 7.5 90 Pervious 25 20Wetland 0.015 0.350 0.0 15.0 50 Pervious 50 10Water 0.015 0.015 0.0 0.0 100 Pervious 0 0

For each surface cover type, the following hydrologic par-ameters are given:

· overland flow roughness factors, expressed as Man-ning’s n value, for both impervious and pervious fractions;

· initial abstractions (i.e. depression storage losses) for both impervious and pervious fractions;

· percentage of impervious cover, including any land surface that has been compacted or is covered with a layer of material such that it substantially reduces or prevents the infiltration of stormwater runoff into the ground;

· subarea routing is a SWMM5 simulation param-eter that designates the internal routing of runoff between pervious and impervious areas (in this case, Pervious was selected to indicate a portion of runoff from impervious areas can be discharged onto pervious areas);

· percent routed indicates the portion of runoff that is routed between subareas (e.g. 100% indicates that all of the impervious area in the subcatchment is routed onto pervious surfaces); and

· the final column indicates the fraction of impervious area that has no depression storage.

Table 2 shows the distribution of surface cover within each hydrologic unit, expressed as a percentage of the total subcatch-ment area, under proposed conditions. When these proportions are cross-multiplied by the global parameters in Table 1, the re-sulting area-weighted surface cover parameters are calculated for each hydrologic unit. The bottom row shows the area-weighted average values throughout the study area. Note that only the hydrologic units named with the prefixes “Pr_” or “ML_” are tribu-tary to the stormwater pond.

Page 4: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

4

Table 2 Distribution of surface cover types (by hydrologic unit).

Hydrologic Percent By Surface Cover TypeUnit Name Forest Grass Farm RegRoof ImpPave Gravel Wetland Water Total

Ex_10 15.6% 55.0% 13.3% 3.1% 10.1% 0.8% 2.2% 100.0%Ex_12m 5.2% 82.8% 0.4% 11.2% 0.4% 100.0%

Ex_13 8.6% 88.5% 2.9% 100.0%Ex_14 20.2% 79.8% 100.0%

Ex_15m 76.0% 24.0% 100.0%Ex_16 9.3% 83.5% 7.2% 100.0%

Ex_16Am 75.2% 24.8% 100.0%Ex_16Bm 1.6% 94.1% 4.3% 100.0%

Pr_1 11.0% 37.0% 47.0% 5.0% 100.0%Pr_2 11.0% 37.0% 47.0% 5.0% 100.0%Pr_3 12.0% 31.0% 42.0% 15.0% 100.0%Pr_4 23.0% 20.0% 36.0% 21.0% 100.0%

ML_1 32.9% 45.7% 21.4% 100.0%ML_2 49.2% 0.0% 50.8% 100.0%ML_3 20.5% 57.8% 21.7% 100.0%ML_4 20.4% 72.6% 7.0% 100.0%ML_5 0.0% 86.6% 13.4% 100.0%ML_6 27.0% 52.0% 21.0% 100.0%ML_7 14.3% 7.2% 78.5% 100.0%ML_8 16.6% 46.4% 37.0% 100.0%ML_9 100.0% 0.0% 0.0% 100.0%

ML_10 100.0% 0.0% 0.0% 100.0%ML_11 100.0% 0.0% 0.0% 100.0%ML_12 100.0% 0.0% 0.0% 100.0%

aHC0011 92.3% 7.7% 100.0%aHC0011a3 7.3% 3.8% 73.8% 2.4% 1.4% 11.3% 100.0%

Area-wtd Avg: 3.2% 12.4% 39.8% 18.3% 22.1% 1.4% 0.9% 2.0% 100.0%

Infiltration parameters were determined for the Green–Ampt method in SWMM5 based on soil texture properties, including:

· capillary tension, a measure of how tightly water is held within the soil pore space;

· saturated hydraulic conductivity, a measure of how quickly the water can be drained vertically; and

· porosity (or initial soilwater deficit), the volumetric fraction of water within the soil pore space under initially dry conditions.

Soil texture was based on the geotechnical investiga-tions undertaken as part of the adjacent site development, which included >30 boreholes across the site and two within the proposed location for the stormwater detention facility. These in-vestigations indicated that surficial soils are consistently silty clay throughout the site.

2.2 Hydraulic ModelThe hydraulic model was developed using available field survey and topographical data to characterize the conveyance and routing of stormwater throughout the existing drainage network. The drainage network was represented by a link–node system of conduits (culverts, pipes, open watercourses and road overflows) and junctions (storage areas, connecting nodes and outfalls). The model includes a representation of the collection system tribu-tary to the proposed pond, significant storage features within the subject site, the pond and its related control structures, and the connection of the pond outfalls to the downstream receiving watercourses.

A fixed tailwater elevation was assigned to the outfall as the boundary condition that varied for each design storm event. For non-outfall junctions, these values were projected horizontal-ly through the system to determine the corresponding initial flow depth. The initial flow depth for junctions tributary to the pond were based on the normal pool elevation (210.50 m).

The storage volume in the forebay and main cell of the proposed pond was combined and represented as a single stor-age unit in SWMM5. Surface flooding in the upstream collection system was noted for the larger design storm events. As a result, surface storage was added to the locations of inundation and connecting conduits were added to route major system surface flows into the pond.

3 Stormwater Management Servicing De-sign

The design criteria used to size the proposed pond and corres-ponding control structures was based on achieving the following:

· consistency with design standards (City of Hamilton 2007);

· water quality treatment: enhanced level of protec-tion as designated by the provincial guidelines (Ontario Ministry of the Environment 2003);

· water quantity control: post-development peak flow rates discharged from the stormwater facility do not exceed pre-development rates for the 2 y through 100 y return period design storm events and the regional storm event must be safely conveyed to the receiving watercourse; and

· erosion hazard mitigation: erosion protection meas-ures at the primary and secondary outfalls, which includes rock and stone treatments sized to provide resistive forces in excess of the tractive forces re-sulting from 100 y return period flows.

Detention facility volume components and control struc-ture features can be classified by various pond storage compon-ents as described below.

3.1 Permanent PoolThe permanent pool was sized to provide an appropriate water quality treatment volume based on provincial requirements that achieve an enhanced protection level, which is presumed to provide 80% suspended solids removal rate on an average annual basis. The required water quality treatment volume varies by the imperviousness of the tributary area. A portion of the permanent pool volume is included in the forebay at the south end of the facility, which receives minor flows from the two pond inlets and is shaped to enhance initial settling of suspended solids.

A permanent pool elevation of 210.50 m will be maintained by the invert elevation of a reverse sloped bottom-draw. This elevation is coincident with the gate valve used to control the extended detention volume. The permanent pool has a maximum depth of 2.00 m, with a pond bottom elevation of 208.50 m.

Design details include:

· permanent pool elevation: 210.50 m; · surface area (at permanent pool elevation, forebay

plus main cell): 6 600 m2;

Page 5: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

5

· required permanent pool volume: 7 000 m3 (195 m3/ha, for 76% imperviousness of the tributary area to the pond); and

· available permanent pool volume: 8 200 m3, which exceeds the required volume (note this assumes the maximum permanent pool depth of 2 m throughout the main cell).

It is not recommended that the pond footprint be reduced to match the required permanent pool volume as the additional storage volume above the permanent pool is critical to achieving the pre-development peak flows for the larger design storm events.

3.2 Extended DetentionThe volume component above the permanent pool is referred to in this paper as extended detention, which has multiple func-tions in controlling downstream flows from the higher frequency (smaller volume) rainfall events. This component has also been referred to as live storage, suggesting its role in water quantity control (i.e. typically for rainfall events with a return period of ≤5 y) However, extended detention also provides additional water quality treatment and streambank erosion protection.

Runoff in this component is controlled by means of a gate valve. The sizing of an equivalent orifice diameter for the valve was optimized to achieve the 2 y through 100 y pre-develop-ment discharge, and to ensure that runoff from the water quality event will not be completely discharged in <24 h. The top of the extended detention volume is indicated by the quality overflow elevation of 212.40 m, which is controlled by the lowest grate ele-vation of a ditch inlet catchbasin. The quality overflow elevation is coincident with the 10 y design high water level. This provides an extra level of erosion protection should the secondary outfall controls be inoperable due to clogging by debris, for example.

Design details include:

· water quality gate valve setting (equivalent orifice diameter): 225 mm (crest elevation at 210.50 m);

· quality overflow elevation: 212.40 m (1.90 m above permanent pool); and

· available extended detention volume: 17 800 m3, or approximately 495 m3/ha.

3.3 Flood ControlIn this paper, flood control storage refers to the volume compon-ent above the extended detention storage and serves to mitigate water quantity impacts downstream of the facility for the lower frequency (larger volume) rainfall events. While some water quantity control is provided in the extended detention compon-ent below, the primary function of this upper component is flood control.

Runoff in this component will be controlled by means of the water quantity orifice plate attached to the outlet pipe. The top of the flood control volume is marked by the top of the embankment and is controlled by an emergency spillway crest that is set 0.3 m below the top of berm (i.e. emergency overflow

elevation of 213.22 m, which is ≥0.1 m above the 100 y design high water level, according to the city standard).

The sizing of the quantity orifice was optimized to achieve the 100 y pre-development discharge and to ensure that the 100 y high water level in the pond remains ≥0.1 m below the emergency overflow elevation. The spillway was designed to provide flood control conveyance for the regional storm event, within acceptable depth and velocity limits. That is, spillway flows for this extreme event do not exceed a depth of 0.25 m or a vel-ocity of 2.0 m/s.

Design details include:

· water quantity orifice diameter: 300 mm; · primary outfall pipe diameter: 750 mm; · quantity overflow elevation: 213.22 m; · top of embankment elevation: 213.52 m (3.02 m

above permanent pool); · available flood control volume (at the overflow ele-

vation): 10 300 m3, or approximately 287 m3/ha; and · reserve flood control volume (to top of embank-

ment): 4 200 m3.The emergency spillway was designed to convey excess

runoff from the regional storm event through the roadside ditch along the eastern right-of-way of Dartnall Road. The emergency spillway includes an overflow channel with characteristics that were represented as follows:

· length: 10 m (across the access road); · height: 0.3 m (to the top of the berm); · bottom width: 10 m (crest elevation corresponds to

the quantity overflow elevation of 213.22 m); and · sideslopes: 10:1.

3.4 Secondary OutfallThe control structures described above discharge to the primary outfall (west tributary) and were sized to provide water qual-ity and quantity objectives for future development that will be serviced by the pond. A secondary outfall discharges to the east tributary and was sized to achieve the supplementary inflows specified for the receiving watercourse, using two orifices to limit flows through the outfall pipe. This tributary also receives treated stormwater from the portion of the adjacent development site that is not serviced by the Twenty Road pond. Details for this outfall include:

· secondary outfall pipe diameter: 525 mm; · water quantity orifice 1 diameter: 140 mm (crest

elevation at 211.50 m); and · water quantity orifice 2 diameter: 450 mm (crest

elevation at 212.38 m).

4 Model Development (Continuous Simu-lation)

The previous sections summarize the modeling methodology and design approach to meet local standards involving event based

Page 6: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

6

simulation. This section describes how the model was adapted for continuous simulation.

4.1 Model Applications Using Continuous Simu-lation

Continuous hydrologic simulation requires long term meteoro-logical input that encompasses a range of historical rainfall events as well as the dry weather periods in between, not just selected design storms that characterize extreme events. It can comple-ment the sizing of stormwater infrastructure by addressing the full range of runoff response characteristics, from the common rainfall events that are commensurate with the day-to-day stormwater facility operations, as well as chemical and biological functions and physical processes in the receiving waters, to the extreme events embodied in current drainage design and flood-plain management practices.

Among the many benefits of continuous simulation, it is possible to evaluate the hydraulic performance of existing stormwater systems under a broad range of flow regimes, rather than just snapshots of performance indicators for selected design storm events. Only long term (multi-year) continuous simulation can achieve design objectives that involve:

· maintaining baseflows in receiving watercourses; · maintaining appropriate water level fluctuations in

wetlands; · groundwater recharge and discharge and water sup-

ply and wellhead protection; and · natural habitat impacts.For this project, continuous simulation was used in order to

meet specific requirements of the permitting agencies, including:

1. Erosion threshold analysis: Erosion hazard impacts to the downstream watercourses can be addressed by performing a flow frequency analysis of peak velocity results, and comparing these to the critical erosive velocity thresholds that were defined as part of the geomorphology assessment for this project. Sustained flows that exceed the defined thresholds would require watercourse improvements to protect against erosion. Velocity frequency curves derived from continuous simulation were used to optimize the stormwater detention facility design to achieve the defined erosion thresholds. Results confirmed that the extended detention storage volume was sufficient to reduce the peak velocities discharged;

2. Vegetation selection: A pond drawdown analysis was conducted to determine the time to release the flood control and extended detention volume com-ponents of the pond. In addition, a depth duration analysis was performed using continuous simulation to facilitate vegetation selection for the landscap-ing plan. Figure 3 shows the total time duration that pond stages are exceeded. For example, vegeta-tion planted along the water’s edge (water level

210.50 m) can expect an inundation depth of 50 cm (water level 211.00 m) 3% of the time. This informa-tion assisted the landscape architect’s selection as the analysis accounts for the delayed drawdown times following real storm events, rather than the peak pond depths during design storm events which cannot be correlated to biological activity;

3. Future development source controls: Onsite storm-water retention facilities would likely be required for future development upstream of the pond. These may include infiltration trenches or galleries, bioretention cells, green roofs or cisterns for irriga-tion, and equipment and vehicle washing or other non-potable uses. Water balance controls are implicit in low impact development (LID) design, which is intended to manage runoff volumes in an attempt to maintain predevelopment hydrologic conditions. One advantage of continuous simulation is that it better expresses the proportion of hydrologic com-ponents, compared to design storm events where water balance proportions are necessarily biased to-ward rare events (Gregory and Arseneau 2012); and

4. Sediment loading and accumulation analysis: This is described in detail in Section 5.

Figure 3 Depth duration analysis of pond water levels.

4.2 Model Adjustments for Continuous Simula-tion

In addition to the design storm events listed in Section 2.1, long-term rainfall records were applied. Local archival tipping bucket gauge data (with at least a 5 min resolution) were not available for use in this study. Long term tipping bucket rainfall data were available from the Elora Research Station, operated by the Univer-sity of Guelph, located approximately 50 km (30 miles) from the project site. A total of 22 y tipping bucket data (1 min resolution) was acquired from the Elora station, representing the period of record from 1989 through 2010. This rain gauge is not operated

Page 7: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

7

during the winter months and therefore only data from April through October was used as input for continuous simulation. Consequently, snowmelt was not considered in the analysis.

The rainfall records used for continuous simulation in this study include:

· 1989–2010: the complete Elora period of record dataset; and

· average year: a composite dataset developed from the Elora dataset comprising selected data over the rainfall season (April through October); repre-sentative months were selected based on the total monthly rainfall in any given year that was closest to the long term station average at the Hamilton airport.

Table 3 compares these rainfall records with the Environ-ment Canada reported climate normals for the most recent me-teorological epoch (1971–2000) at the airport. These values are for rainfall only, and do not include snowfall equivalent amounts in the late spring and early fall months. The first row shows the 22 y Elora station average monthly totals from the composite average year Elora record, along with the dataset year that was used (in parentheses). The second row lists the corresponding airport monthly totals, followed by the difference between the average year and the local rainfall monthly totals. Overall, the designated average year data used in this study is within 1% of the total amount representing the airport rainfall year.

Table 3 Rainfall record comparison

Rainfall Record Apr May Jun Jul Aug Sep Oct Total69.6 74.2 84.2 90.4 81.0 81.4 70.8 551.6

(1995) (1994) (2002) (1996) (2005) (1992) (1993)Hamilton Airport

1971-2000 (Climate Normals)69.6 75.0 83.9 86.5 80.6 82.1 71.6 549.3

Difference 0% -1% 0% 5% 0% -1% -1% 0%

Elora Research Station"Average Year"

Evaporation during the intense short duration design storm events is negligible and is typically ignored in the sizing of stormwater management infrastructure and facilities. For continuous simulation however, evaporation is a significant hydrologic variable and cannot be ignored. Evaporation from all storage junctions including the pond was also simulated in the model.

In this study, evaporation data were input into the hydro-logic model as a daily abstraction rate for each calendar month in the continuous simulation runs, including the following values during the simulation period:

· April: 1.1 mm/d; · May: 2.0 mm/d; · June: 4.9 mm/d; · July: 5.2 mm/d; · August: 4.9 mm/d; · September: 3.3 mm/d; and · October: 2.3 mm/d.These values represent a total potential evaporation of

725 mm over the rainfall year (April through October). The total

potential evaporation for all months in the calendar year matches the annual lake evaporation rate of 813 mm for Lake Ontario at Toronto.

Seasonal fluctuations in groundwater levels can also af-fect the performance of stormwater management facilities. The geotechnical investigations undertaken as part of the adjacent site development indicated that seasonal fluctuations of ground-water levels would not impact the performance of the pond. Consequently, groundwater impacts were not considered as part of the continuous simulation analysis.

5 Sediment Loading and AccumulationThe permanent pool was sized to provide an appropriate water quality treatment volume based on provincial requirements that achieve an enhanced level of protection presumed to provide an 80% suspended solids removal rate on an average annual basis. After the model was adapted for continuous simulation, it was applied to confirm the long term suspended solids removal efficiency would be achieved and also to estimate sediment load-ing and accumulation volumes for the city’s future pond cleanout operations. A monitoring program to collect water quality data and determine the actual removal efficiency has not yet been conducted.

5.1 Model MethodologyThe water quality module of SWMM5 was used to simulate the generation of TSS loadings from each subcatchment tributary to the pond, including pollutant buildup during dry weather periods and washoff during rainfall events. The pollutographs were subse-quently routed through the collection system and the deposition of particulate solids in the pond was simulated.

The process for simulating TSS loading into the collection system first required the categorization of surface cover types to generate the pollutant loads. Next, the appropriate param-eters were assigned to the buildup and washoff functions that determine the pollutant loadings from each surface cover type. The only source of TSS represented in the model is from surface washoff. That is, contributions from rainfall, groundwater or other sources were not considered.

In SWMM5, particulate settling can be represented by a characteristic settling velocity distribution. No local stormwater settling velocity measurements were available and so empirical data from other regions were used from the Nationwide Urban Runoff Program (NURP, referenced in USEPA 1983). Six mass frac-tions were used to characterize the particle size distribution of the stormwater washoff load and these are shown in Table 4. For each mass fraction, the equivalent particle diameter range and mean are shown along with the average particle density and dry bulk density.

Page 8: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

8

Table 4 Suspended solids characteristics.

Mass Equiv. Diameter (µm) Density Bulk DensityFraction Range Mean (kg/m3) Dry (kg/m3)

0-20% <3 1.5 2,200 20020-30% 3-5 4 2,425 40030-40% 5-7 6 2,425 40040-60% 7-17 12 2,575 1,20060-80% 17-35 26 2,650 1,800

80-100% >35 103 2,650 1,800

5.2 Buildup and Washoff CharacteristicsThe parameters describing the buildup and washoff of TSS are shown in Table 5. Suspended solids loadings for each subcatch-ment were determined using the same surface cover types that were defined for the hydrology model described in Section 2.1. The buildup of TSS that accumulates within each land use category was represented using the power function option in SWMM5. With this function, the pollutant buildup is expressed by a rate that increases proportionally by the number of preced-ing dry weather days until a maximum accumulation mass is achieved.

Input parameters for the power buildup function include:

· maximum buildup rate, expressed as a limiting mass per unit subcatchment area;

· buildup rate constant, expressed as a mass per unit area per day input for each size fraction; and

· power constant used to characterize the time expo-nent in the buildup equation.

Table 5 Buildup and washoff parameters for total suspended solids.

Water Quality Surface Cover CategoryParameter Forest Grass Farm Bare GrnRoof RegRoof PrmPave ImpPave Gravel Wetland Water

Street Sweeping No No No No No No No No No No NoBuildup Function Power Power Power Power Power Power Power Power Power Power PowerNormalized By Area Area Area Area Area Area Area Area Area Area AreaMax. Buildup (kg/ha) 1200 600 4800 6000 600 1200 4800 4800 5400 400 0Power Rate Constant

TSS_1 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42TSS_2 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21TSS_3 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21TSS_4 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42TSS_5 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42TSS_6 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42

Power Constant 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5EMC (mg/L) 200 100 500 600 100 200 500 500 550 75 0

The buildup of accumulated TSS becomes available for washoff into the collection system. Washoff of TSS was repre-sented using the Event Mean Concentration (EMC) option in SWMM5. With this option, the pollutant washoff is expressed as a constant washoff pollutant concentration in mass per liter. During wet weather events, these concentrations are sustained until the accumulated buildup mass is depleted at which time washoff ceases. The washoff EMC rates were defined individually by surface cover type and shown in the final row of Table 5. No lo-cal TSS measurements were available to calibrate the buildup and washoff functions; therefore parameters were estimated from the range of values reported in the literature.

5.3 Particulate SettlingTo represent the deposition of particulates in the pond, a treat-ment expression based on settling velocity was developed for each mass fraction of TSS. The treatment expression defines the rate of particulate settling as a function of time and depth of water in the pond. The mass of TSS that settles out is removed from the water column.

Table 6 shows the settling velocities for each size fraction along with the corresponding treatment expressions reported in the NURP study (USEPA 1983) and subsequently adapted for use in detention facility sizing (USEPA 1985). The treatment expres-sions are input directly into SWMM5, using the variables as shown (C = concentration; Depth = settling depth; and DT = computa-tional timestep). The residual TSS concentration in the pond was assumed to be zero for all size fractions.

Table 6 Particulate settling velocities and treatment expressions.

Size % Finer Mass Average Velocity Treatment ExpressionFraction Than Fraction (m/s) (ft/hr)

TSS_1 20% 20% 0.0000025 0.03 C = TSS_1 * EXP(-0.00000254/DEPTH*DT)TSS_2 30% 10% 0.0000130 0.15 C = TSS_2 * EXP(-0.00001300/DEPTH*DT)TSS_3 40% 10% 0.0000254 0.30 C = TSS_3 * EXP(-0.00002540/DEPTH*DT)TSS_4 60% 20% 0.0001270 1.50 C = TSS_4 * EXP(-0.00012700/DEPTH*DT)TSS_5 80% 20% 0.0005927 7.00 C = TSS_5 * EXP(-0.00059267/DEPTH*DT)TSS_6 100% 20% 0.0055033 65.00 C = TSS_6 * EXP(-0.00550333/DEPTH*DT)

5.4 Model Results and DiscussionThe model was applied to the average year rainfall described in Section 4.2, which is representative of the local average annual conditions. Figure 4 shows the simulated TSS concentrations for the smallest and largest size fractions (TSS_1 and TSS_6 respect-ively) within the water column of the pond. The differences in particulate removal rates are evident by comparing the two pollutographs, with the lighter particles remaining in the water column for a longer duration after each rainfall event (smallest size fraction) and the heavier particles settling out quickly (largest size fraction).

Figure 4 Average year TSS concentration in pond.

Page 9: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

9

Results of the sediment loading and accumulation analy-sis are presented in Table 7. The sediment characteristics of the particulate mass fractions are shown at the top of the table. The first two rows show the surface washoff loading into the pond along with the TSS load that is discharged from the pond for an average rainfall year (i.e. April through October). The resulting removal efficiencies are shown in the third row, which highlights the preferential transport of smaller particles (i.e. lower removal efficiency for the smallest size fraction) and the preferential set-tling of larger particles (i.e. nearly 100% efficiency for the largest size fraction). The total TSS washoff loading rate is approximately 920 kg/ha/y (~820 lb/acre/y), which is at the upper end of the range reported in the literature for highly urbanized areas (Harper 1994; SWFWMD 1989).

Table 7 Sediment loading and accumulation results.

Event/Particle Characteristic TSS Loading and Accumulation by Particle SizeMass Fraction (% Finer Than): 0-20% 20-30% 30-40% 40-60% 60-80% 80-100%

Equivalent Particle Size: <3 µm 3-5 µm 5-7 µm 7-17 µm 17-35 >35 µmMean Equivalent Diameter: 1.5 µm 4 µm 6 µm 12 µm 26 µm 103 µm

Equiv. Particle Density (kg/m3): 2,200 2,425 2,425 2,575 2,650 2,650Equiv. Dry Bulk Density (kg/m3): 200 400 400 1,200 1,800 1,800

Surface Washoff Load (kg) 6,765 3,011 3,011 6,765 6,765 6,765 33,083Pond Discharge Load (kg) 2,535 510 374 350 69 5 3,844

Removal Efficiency 62.5% 83.1% 87.6% 94.8% 99.0% 99.9% 88.4%Load Remaining in Pond (kg) 4,230 2,501 2,637 6,415 6,696 6,760 29,239Volume Remaining in Pond (m3) 21.1 6.3 6.6 5.3 3.7 3.8 46.8

Total TSS

Loading

Overall, the pond removal efficiency is 88% on an average annual basis, which achieves the presumptive design criteria for an enhanced level of water quality protection. The last two rows show the TSS loads and corresponding volumes (based on dry bulk density) that remain in the pond at the end of the rainfall year.

The average sediment volume is 47 m3, which corresponds to an accumulation rate of 1.3 m3/ha/y (~18.7 ft3/acre/y) for the non-winter period of April through October. Note that SWMM5 does not reduce the available storage volume in the pond by the amount of accumulated sediment. In this case, the sediment volume amounts to less than 1% of the permanent pool volume, which is considered negligible.

Snowmelt and hydrologic conditions during winter months were not included in this analysis. In addition to the washoff loads generated by land surfaces, winter road operations may introduce additional TSS loading for the winter months of Nov-ember through March. As a conservative estimate, the computed accumulation rate for the non-winter period was assumed also for the winter months, giving an estimated annual sediment ac-cumulation rate of 2.6 m3/ha/y (37.4 ft3/acre/y). The estimated sediment accumulation volume over a 10 y period is 940 m3, which can be accommodated within the available sediment de-cant volume of 1 230 m3.

6 ConclusionsThe sizing of stormwater management facilities across North America largely relies on event based hydrologic modeling meth-ods, which continue to be prescribed in local stormwater design guidelines. However, event based methods cannot be used to suf-

ficiently assess the water quality treatment performance of such facilities. In lieu of monitoring, only continuous simulation can be used to assess the long term average annual TSS removal from a stormwater detention facility.

To overcome the limitations inherent in presumptive design criteria, a modeling methodology was developed that improves the current state-of-the-practice design methods. This method was applied to a recently permitted and constructed pond in Ontario. A key feature of this method involves repre-senting the catchment hydrology based on source area delinea-tions that distinguish specific surface cover types to characterize the generation of TSS loads across a range of urban land uses.

The water quality module of SWMM5 was used to simulate the generation of TSS loadings from all source areas tributary to the pond, including pollutant buildup during dry weather periods and washoff during rainfall events for a representative average year of rainfall. The pollutographs were subsequently routed through the collection system and the deposition of particulate solids in the pond was simulated. The TSS removal efficiency and annual sediment accumulation rates were then estimated.

ReferencesBedient, P. B. and W. C. Huber. 1992. Hydrology and Floodplain

Analysis, 2nd ed. Lebanon, IN: Addison-Wesley. ISBN 0-201-51711-6.

Chow, V. T., D. R. Maidment and L. W. Mays. 1988. Applied Hydrol-ogy. New York: McGraw-Hill. ISBN 0-07-010810-2.

City of Hamilton. 2007. Criteria and Guidelines for Stormwater Infra-structure Design. Burlington, Ontario: Philips Engineering Ltd.

Environment Canada. 2008. Canadian Climate Normals 1971–2000. Ottawa: Environment Canada National Climate Data and Information Archive. http://climate.weather.gc.ca/index_e.html.

Gregory, M. and D. Arseneau. 2012. "Design, Construction and Hydraulic Performance Assessment of an Infiltration Gallery." Journal of Water Management Modeling R245-10. doi: 10.14796/JWMM.R245-10.

Harper, H. H. 1994. Stormwater Loading Rate Parameters for Central and South Florida. Orlando, FL: Environmental Research & Design Inc. (ERD).

Ontario Ministry of the Environment. 2003. Stormwater Manage-ment Planning and Design Manual. Toronto: Queen’s Printer for Ontario. ISBN 0-7794-2969-9.

SWFWMD (Southwest Florida Water Management District). 1989. Estimation of Loading Rate Parameters for the Tampa Bay Watershed. Brooksville, FL: Southwest Florida Water Man-agement District.

USEPA. 1983. Results of the Nationwide Urban Runoff Program: Vol-ume 1—Final Report. Washington, DC: U.S. Environmental

Page 10: Journal of Water Management Modeling - Stormwater Pond ...pond. The modeling efforts developed as part of this study served as the basis for gauging the cumulative impacts on receiving

10

Protection Agency, Water Planning Division. Publication 832-R-83-112.

USEPA. 1985. Methodology for Analysis of Detention Basins for Control of Urban Runoff Quality. Washington, DC: U.S. En-vironmental Protection Agency, Water Planning Division. Publication 440-5-87-001.

USEPA. 2010. Storm Water Management Model User’s Manual, Ver-sion 5.0. Washington, DC: U.S. Environmental Protection Agency. Publication 600-R-05-040.

Michael A. Gregory AECOM, Kitchener, Ontario.