Moorhouse Lane Solar Array The story of a community energy project
Aug 18, 2015
Moorhouse Lane Solar Array
The story of a community energy project
Moorhouse Solar Array
7200 x 255W BenQ panels = 1,836 kWp
Annual yield 960 kW/kWp = 1.76MWh
Total cost £2.012M
Annual income = £187,500
11 acres Grade 3 agricultural land
Timeline to Moorhouse solar array (1)2010
Community energy
workshop withThe Converging
World
2009Transition Portishead
set up
April 2011Low Carbon
Gordanoestablished
Nov 2011First 6
community roof
schemes abandoned
Mar 2012£100,000
LEAFfunding
2012Partnership
formedwith BWCE
Timeline to Moorhouse solar array (2)
Nov 2013NS planners
reject300kW project(Green Belt)
2013BWCE support
300kW solar project
Jan 2014BWCE offer
LCGMoorhouse
Project
May 2014Moorhouse receives planning consent
Jun 2014£2.2M
communityShare offer
for Moorhouse
Sep 2014£2.2M raised
Sep 2014Solarsense
awardedcontract
April 2015Moorhouse
fully operational
Moorhouse share offerWho invested(1)?
71%
29%
Moorhouse share offerWho invested(2)?
29%30%
26%
13%
Moorhouse share offerWho invested (3)?
Moorhouse share offerHow did the money come in?
25% wk6
50% wk10
75% wk11
100% wk12
EIS Approved
wk5 £600,000 Underwriting
Facilitywk8
Share offer
Extendedwk8
388 Members
£5,700Average
investment
Ham Lane share offer
25% wk4
50% wk5
75% wk7
100% wk7
EIS Approved
wk3 175 investors85 new members£5,600 average
investment
The Moorhouse project (1)Jul 2013
1st Planning application
by ORTA solarwithdrawn
Jan 2014BWCE agree
Heads of Termswith ORTA
Jan 2014BWCE offer project
To LCG
May 2014Planning consent
Granted –BWCE purchase
Scheme from ORTA
29 Nov 20132nd Planning application
by ORTA solar
Jun 2014LCG launches
share offer for £2.2MWith BWCE support
Jul 2014Solarsense chosen
as contractor
SEP 2014Share offer successful
LCG puchases scheme
from BWCE
Oct 2014EPC contract agreed
with Solarsense
The Moorhouse project (2)
Oct 2014Delays due to
Pipeline crossing,Unexploded bomb
survey
Dec 2014Solarmax inverter
manufacturer ceasesTrading - 8 week
delayFIT deadline missed
Apr 2015Site fully operational
Mar 2015G59 test complete-
Site connected to grid
Nov 2014Site works start
Feb 2015New Lti Inverters
on site
May 2015Mayor of Bristol
George FergusonLaunches solar array
July 2015Final performance
testing
Moorhouse today
860,000 kWh
450 tonnes
£130,000
Generation
Carbon saved
Income