Page 1: jica present

29th JULY 20131/30

Page 2: jica present

Houses to be relocatedThe consultant has cooperated with RID to relocate local houses that affect the construction.

The client (RID) had already completed the compensation for the relocation to the affected people.

Most of houses had already been relocated except SRT’s house (in process of compensation) and nursery

2/30

Page 3: jica present

KRA MANG SITE

4

3

1

2

3/30

Page 4: jica present

KRA MANG SITE

RELOCATED HOUSE No.1 (FINISH)4/30

Page 5: jica present

KRA MANG SITE

RELOCATED HOUSE No.2 (FINISH)5/30

Page 6: jica present

KRA MANG SITE

HOUSE No.3 (NURSERY HOUSE)6/30

Page 7: jica present

KRA MANG SITE

HOUSE No.4 (SRT’S HOUSE)7/30

Page 8: jica present

HAN TRA SITE

8/30

96

8

7

5

Page 9: jica present

HAN TRA SITE

HOUSE No.5 (FINISH)9/30

(land owner relocated voluntarily without the compensation)

Page 10: jica present

HAN TRA SITE

RELOCATED HOUSE No.6 (FINISH)10/30

Page 11: jica present

HAN TRA SITE

RELOCATED HOUSE No.7 AND 8 (FINISH)11/30

Page 12: jica present

HAN TRA SITE

SMALL ARBORE No.912/30

Page 13: jica present

RELOCATION FOR WATER SUPPLY LINE

The consultant found that the existing water supply line was obstruction for the construction.

The consultant has cooperated with RID and Thetsaban Pranakorn Sri Ayutthaya Water to relocate the water supply system.

The relocation for water supply is in progress.

13/30

Page 14: jica present

KRA MANG SITE

cutting pipe line relocated pipe line existing pipe line

14/30

Tunnel

(PVC) (PVC) (PVC)

Page 15: jica present

Change to HDPE pipe

HAN TRA SITE

15/30

cutting pipe line relocated pipe line existing pipe line

HDPE pipe line iron pipe line

Page 16: jica present

SITE WORK

ABANDONED PIPE LINE (FINISH)16/30

Page 17: jica present

SITE WORK

RELOCATED PIPE LINE (FINISH)17/30

Page 18: jica present

RELOCATION FOR ELECTRIC OVERHEAD LINE

The consultant found that the existing electric overhead line was the obstruction for the construction.

The consultant has cooperated with RID, contractor and PEA for the relocation of electric overhead lines.

PEA plans to commence the relocation work once the contractor constructs temporary access road.

18/30

Page 19: jica present

KRA MANG SITE

RELOCATED FOR ELECTRIC OVERHEAD LINE 19/30

Page 20: jica present

HAN TRA SITE

RELOCATION FOR ELECTRIC OVERHEAD LINE

20/30

abadoned overhead line propose overhead

line existing overhead line

New Line

Page 21: jica present

DETAILS OF EXISTING ELETRIC OVERHEAD LINE

21/30

Type A Type B

Page 22: jica present

SITE WORK

EXISTING ELETRIC OVERHEAD LINE22/30

Page 23: jica present

TEMPORARY RELOCATION FOR SRT’S OVERHEAD SIGNAL LINEAt Kra Mang site, the consultant found that the existing SRT overhead line was the obstruction for the construction.

The consultant has cooperated with RID and SRT for the relocation of SRT’s overhead signal line.

The relocation of SRT overhead signal line is in progress.

23/30

Page 24: jica present

KRA MANG SITE

TEMPORARY RELOCATION FOR SRT SIGNAL LINE

24/30

existing cable line

relocation line

existing cable line

cutting line

Page 25: jica present

SIGNAL LINE SYSTEM

DETAILS OF SIGNAL LINE TO UNDERGROUND

25/30

Page 26: jica present

SITE WORK

26/30

Page 27: jica present

SITE WORK

27/30

Page 28: jica present

SITE WORK

28/33

Page 29: jica present

SUMMARY OF RELOCATION WORKS(UPDATE 16th JULY 2013)

29/30

1 KRAMANG SITE STATUS NOTE

1.1

Houses to be relocated

1.1.1House No.1 Finish

Owner has received compensation and relocated

1.1.2House No.2 Finish

Owner has received compensation and relocated

1.1.3House No.3 On Hold

Owner has received compensation, but requestedaddition compensation

1.1.4House No.4

In Progres

sNot yet start relocation works,

internal process by SRT.

In

Page 30: jica present

30/30

2 Han Tra SITE STATUS NOTE

2.1Houses to be

relocated

2.1.1 House No.5 Finish

Owner has relocated voluntarily without compensation

2.1.2 House No.6 Finish

Owner has received compensation and relocated

2.1.3 House No.7 Finish

Owner has received compensation and relocated

2.1.4 House No.8 Finish

Owner has received compensation and relocated

2.1.5 Small Arbor No.9

Not Yet Start

Owner has received compensation and plan to start relocation

Water Supply In

ProgresIn process of compensation

SUMMARY OF RELOCATION WORKS(UPDATE 16th JULY 2013)