Jeff Vinklarek, P.E. Yoakum District
Jeff Vinklarek, P.E. Yoakum District
• Area Offices submit project list
• District Office rides the roadways and uses PMIS & surface age maps to develop the plan
• District Staff, Area Engineers, & Maint. Supervisors review and verify the plan
Function of –Distress –Ride Quality
Type of Work Lane-Miles Added Service Life
Cost per Lane-Mile
Cost
Rehab 110 10 $220,000 $24 million
Overlays 90 10 $120,000 $11 million
Micro Seal 65 8 $32,000 $2 million
Seal Coat 500 7 $16,000 $8 million
Sum $45 million
FY12 Plan Lane-mile years = 6,020
YKM District Lane-miles = 8,140
Type of Work Lane-Miles
Added Service Life
Lane-Mile Years
Cost
Rehab (-23) 87 10 870 $19 million
Overlays (-10) 80 10 800 $9.5 million
Micro Seal (+40) 105 8 840 $3.5 million
Seal Coat (+300) 800 7 5,600 $13 million
Sum 8,110 $45 million
YKM District Lane-Miles 8,140
Definition: Original Construction to End of Service Life (Rehab) YKM Lane-miles = 8,140 Lane-miles of Rehab in Plan = 110
Rehab: YKM Lane-miles / 50 years 8,140/50 = 160 Overlays: YKM Lane-miles over 10,000 ADT 10 year cycle Micro Seal: YKM Lane-miles 7,000 < ADT <10,000 8 year cycle Seal Coat: YKM Lane-miles ADT < 7,000 7 year cycle
Lane-Miles
Added Service Life per Mile
Lane-Mile Years
Cost per Lane-Mile Cost
Rehab 160 10 1,600 $220,000 $35 million
Overlays 150 10 1,500 $120,000 $18 million
Micro Seal 70 8 560 $32,000 $2.5 million
Seal Coat 640 7 4,480 $16,000 $10 million
Total Amount of Lane-Mile Years = 8,140
Yoakum District Lane-Miles = 8,140
Total Cost = $65.5 million
Pavement Life Cycle = 50.875