Clean Fuels Project Diesel Hydrotreating Unit Scoping Study Lauren Brickner Chi Lo Pamela Morse Jacobs Engineering Liaisons: Daniel LaRiviere Gary Gough
Clean Fuels Project Diesel Hydrotreating Unit
Scoping Study
Lauren Brickner Chi Lo
Pamela Morse
Jacobs Engineering Liaisons: Daniel LaRiviere
Gary Gough
Project Description and Scope
l New regulations require highway diesel to have below 15 ppm of sulfur (reduced from 500 ppm)
l Benefit of producing ultra low sulfur diesel (ULSD) is about $0.10/gal
l Evaluate ability of existing equipment to adapt to modified process to produce ULSD
l Economic feasibility of producing ULSD
Design: Material & Energy Balances
Reactor
QuenchTreat
87 mol% H23,500 scf/bbl
H2 consumed = 6,022,500 SCFD
ΔHrxn = 29,408 Btu/bbl
Recycle86.12 mol% H2
Hydrogen Plant99.9 mol% H2
Reformer81.53 mol% H2FRH
90 mol% H2
Oil Feed
Qquench
Qin
Qout Mole BalanceFRH = Freformer + FHplantnRH*FRH = nreformer*Freformer + nHplant*FHplant
FRH + Frecycle = FTreatnRH*FRH + nrecycle*Frecycle = nTreat*FTreat
Energy BalanceQin + Qquench + ΔHrxn = Qout
Qquench 1579 lbmol/hr
Design: Heaters
Heater
HPHSReactor
Oil Feed Hydrogen
Feed
Feed/Effluent Exchangers
Heater
HPHS
Reactor
Oil Feed
Hydrogen Feed
Feed/Effluent Exchangers
Current Configuration
Proposed Configuration
Design: Water Injections System
ProcessStream
Fan Cooler
Water Injection
Design Considerations: 1. 25% of injected water remain in the liquid phase
downstream of the injection point. 2. Concentration of ammonia bisulfide in the HPHS
sour water be maintained at or below 4 wt%
Design: Compressors/Pumps
Recycle Hydrogen
Plant and Reformer
Given From HYSYS TM
Capacity (ACFM) Efficiency Capacity (ACFM) Horsepower
Stage 1 GC1 1111:= E1 .903:= C1 877.2:= H1 610.5hp⋅:=
Stage 2 GC2 488.5:= E2 .928:= C2 469.4:= H2 820.1hp⋅:=
Stage 3 GC3 231.7:= E3 .914:= C3 204:= H3 565.6hp⋅:=
Stage 4 GC4 562.8:= E4 .76:= C4 452.3:= H4 395.5hp⋅:=
P-101 Pump Curves
2000
2500
3000
3500
4000
4500
5000
5500
0 100 200 300 400 500 600
Flow (GPM)
TDH
(ft)
9.35" 9.88"
Design: Separators and Fractionator
Specifications Naphtha Kerosene Diesel (ULSD)Distillation Sim Dist. D-86 D-8610%, °F - 401 max -90%, °F - 550 max 640 maxEnd Point, °F 400 max 572 max -
Product Specifications
Design Goals: 1. Ensure products are
separated to desired specifications
2. Ensure adequate vapor/liquid disengagement
3. Ensure adequate surge capacity
Design Conclusions / Recommendations
1. New Feed Tank § To ensure constant feed flow § Be a holding tank for catalyst change out and shutdowns
2. New Feed Pump § Flow = 590 GPM § Total dynamic head (TDH) = 4142 ft § Max impeller diameter TDH = 3200 ft
3. Heat Exchangers § Replace reactor feed/effluent exchangers § Add heat exchanger to feed
4. Compressor § Required hp = 2378 (motors rated at 4000 hp) § Adequate capacity § No changes to be made
Design Conclusions / Recommendations
5. Water Injection System § 8330 lb/hr water required to remove ammonia bisulfide
6. High Pressure Hot Separator § Adequate vapor/liquid disengagement § Surge capacity too small § Will not replace – install safety devices to prevent overflow
7. Fractionating Tower § Produces adequate product specifications § Replace trays to prevent weeping
8. Piping § Sized to fit constraints of: maximum velocity, slug flow, ΔP/100 ft
Economics – Equipment Bare Module Costs
Total bare module cost ~ $5 million
Equipment Costs
Instruments7%
Piping7%
Reactor & Fractionator
Internals50%
Equipment36%
Total Variable Costs
Catalyst4%
Heating Fuel Oil 71%
Electricity11%
Steam2%
Hydrogen10%
Water2%
Economics – Annual Costs & Product Selling Prices
Annual Cost Breakdown Variable Costs: $14.7 Million Crude Oil Cost: $365 Million
Operating Costs: $541 Million
Product Selling Prices ULSD: $1.93 / GAL
Naphtha: $1.53 / GAL Kerosene: $1.94 / GAL
Economics: Cash Flow Analysis
Ultra Low Sulfur Diesel Process Cash FlowSelling Price = 1.93
-$20,000
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
$160,000
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Years
Cas
h Fl
ow ($
k)
l IRR = 141.7% l NPV = $913M (at the beginning
of each period) l ROI = 56.5% l PBP = 1.8 years
Comments and Future Recommendations
l Liaison/Student Communication l Project description and equipment
documentation l Time constraints l Project scope