Page 1: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

CONSTRUCTION UPDATE – January 2015Dr. Prem Reddy Health & Science

Page 2: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal decking installed at digital

nurses lab

Page 3: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal Decking being set

Page 4: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal roof deck installed

At science labs

Page 5: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Perimeter walls being framed in medical supplies & equipment

Page 6: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Boring for columns

for shade structure

Page 7: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal deck installed at restrooms.

Page 8: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Perimeter wall framing and structural steel set in faculty office area.

Page 9: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Perimeter wall framing in nursing fundamentals lab.

Also overhead piping installed.

Page 10: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal decking, perimeter wall framing in nursing

fundamentals and corridor 127

Page 11: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Plywood covers holes bored for shade

structure posts in new courtyard area

Page 12: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Steel set in admin & workroom areas.

Page 13: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal Decking installed at faculty offices

Page 14: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal Decking at nursing fundamentals lab.

Overhead piping installed.

Page 15: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Rear view of rotunda.

Page 16: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Looking towards faculty offices from corridor 127

Page 17: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Overhead piping, perimeter framing, and metal decking installed at beds &

equipment

Page 18: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Interior view of main entrance

Page 19: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Perimeter framing at workroom and admin areas

Page 20: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

More perimeter framing at anatomy labs.

Page 21: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Preparation for footings at new trash enclosure

Page 22: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

New doorway cut into existing science bldg.

(Temporary Door)

Page 23: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Metal decking installed at anatomy labs

Page 24: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

SIM Lab area perimeter wall framing installed. Decking in process of

install.

Page 25: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Perimeter wall framing and metal decking installed at

deans office / meeting rooms

Page 26: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Holes bored for covered walkway

pilasters.

Page 27: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Framing for walls along corridor 127

Page 28: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Progress on metal decking at nursing fundamentals

Page 29: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Top view of metal decking installation

Page 30: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Another top view of metal decking. Looking towards the second floor

mezzanine and rotunda

Page 31: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Stored duct waiting for install is covered to

prevent dirt and debris from accumulating inside.

Page 32: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Stored duct waiting for install is covered to

prevent dirt and debris from accumulating inside.

Page 33: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Duct being installed in chemistry lab

Page 34: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Decking installed over corridor 127

Page 35: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Installing in wall conduits for power and piping for

roof drains.

Electrical room 132

Page 36: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Rebar laid out on metal decking in mezzanine for

concrete topping and equipment pad.

Page 37: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Looking down into courtyard area

Page 38: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Opening for duct from HVAC unit in mezzanine.

Page 39: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Signed steel beam set into place

Page 40: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Temporary jacks set in place in preparation of

concrete being poured on deck above

Page 41: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Concrete being poured on mezzanine deck

Page 42: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Footing poured for trash enclosure

Page 43: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Interior walls being framed for faculty offices

Page 44: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Framing of interior walls in the admin, workroom,

deans office areas

Page 45: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Concrete poured out for revolving door at main

entry

Page 46: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Mezzanine concrete and equipment pad- North

side

Page 47: January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Mezzanine concrete and equipment pad- South

side