0 Getting What you Paid for: Acquisition Risk Analysis James Taylor Omnia Paratus Corporation Used with Permission
0
Getting What you Paid for:Acquisition Risk Analysis
James TaylorOmnia Paratus
CorporationUsed with Permission
1
Omnia Paratus Corporation
Lamborghini Reventon
$1.6M
Kia Rio
$12,145
2
Omnia Paratus Corporation
A recent poll showed that 68% of companies experienced financial losses directly related to Supply Chain disruptions
Most of the financial impacts were related to supplier performance that did not meet demand requirements, and delayed, damaged or misdirected shipments.
The majority of companies polled are in the early stages or have yet to think about integrating Risk Management into their Supply Chain
Supplier related risks are most often identified after contract award is a program issue, not a risk:– Supplier shipment delay – Supplier capacity exceeded– Unable to meet technical requirements – 1st Article or Flight Test failures– Parts damaged during shipment or rejected during quality inspection
Schedule delays caused by supplier performance can have an equal or greater financial impact to a program’s bottom line, but are often overshadowed budget impacts due to supplier cost overruns
3
Omnia Paratus Corporation
Procurement analysis exists in varying degrees, although the most commonly used practice is Best Value Analysis (BVA)
Incumbent Supplier w/ Existing Capabilities
New Supplier
Score based on savings to program
~$300K
Technical Score based on:- New Capability to Supplier- Technical deviations req’d based on proposal- 1st Article & Flight Req’d based on Customer reqt’s
BVA considers not only cost, but other quantifiable and non-quantifiable factors supporting an investment decision– Utilizes weighting scales for analyzing “True” program value of supplier bids– Can include, but is not limited to, performance, producibility, reliability, maintainability, and
supportability enhancements– Intended to select the source offering the greatest overall benefit in response to the requirement
4
Omnia Paratus Corporation
While a BVA attempts to provide insight to the least risky procurement, it does not specifically address or integrate impacts of risk
Technical Deviations required by Supplier
Design changes resulting from Technical deviations resulted in cost growth to original purchase order
Program Award fee lost resulting in Supplier delays cause IMS milestones to be missed
Orders placed were against original design and fulfilled by Incumbent suppler
Impact from production delays of 4 weeks
Fees required to get Incumbent supplier operations back up and minimize delay of deliveries to Customer
$390K overrun was a direct loss of company profit
Performing a sample analysis of a new supplier shows the potential risks that may be incurred when basing decisions on costs alone– Technical requirements outside current capabilities– Schedule impact due from potential delay of 1st Article Testing or Flight Test Requirements– Cost growth due to technical deviation’s required– Impact to Operations due to late supplier deliveries
5
Omnia Paratus Corporation
Despite the value-add it offers to improving the acquisition process, risk management is seldom considered or implemented
Risk Management Is Not Difficult, Is Well Documented, and Training Materials Are Readily Available. So Why Is It “Hard”? – Seldom seems urgent It’s a “lower right quadrant” activity It’s often overcome by events It’s someone else’s job
– Requires careful thought People think it’s “easy” because it’s not difficult Fail to distinguish between perception and reality Skip the analysis and solve the wrong problem Determining what can be controlled, influenced, or changed
– Team participation Part of the culture Common understanding Training, support, and reinforcement
Risk Management
Low High
Low
H
igh
Importance
Urg
ency
6
Omnia Paratus Corporation
Risks that impact large scale programs often directly originate from supplier performance throughout all phases of a program
The main challenges that confront these programs include:– Program Requirements – Technical requirements can have a tendency to increase unknown
potential for inhibiting program success or realization of full award fee are often over looked while developing scope of work and supplier selection process.
– Source Selection Analysis - A review of industry standard Best Value Analysis or Lowest Cost Alternative approach reveals gaps in several areas of Procurement Analysis skewing the perception of results derived, inherently selecting a supplier who may not adequately meet program requirements.
– Risk Identification – Most risks identified often have root causes stemming from supplier performance and/or capabilities, these risks tend to be identified after procurement award.
– Risk Impact Analysis – Procurement analysis does not provide insight into the potential cost and schedule impacts associated with selecting a supplier, impacts that could affect the success or ability of program operations, award fee and sustaining customer contracts.
– Mitigation Analysis – Developing a mitigation plan after a problem has occurred limits a program’s mitigation options resulting in exuberant mitigation costs that extend beyond program office and/or client budget.
7
Omnia Paratus Corporation
Request for ProposalDevelopment Proposal Evaluation Contract Award
Integrating Risk Management directly into the acquisition analysis process is seamless and beneficial
Develop and issue RFPs based on a standard format; collect vendor proposals
Des
crip
tion
Evaluate proposals using a clear and structured evaluation mechanism and methodology
Activ
ities
Assess program requirements Assess supplier capabilities Assessment methodology &
criteria development Define risk parameters
RFP responses collection Technical and contractual /
procedural evaluation Risk identification Risk ratings defined
Supplier proposal risk analysis Identify potential mitigation plans Assess mitigation posture Integration of risk impact into
program budget and schedule
Out
com
e Detailed functional and technical requirements
Evaluation methodology Scoring model for RFP evaluation Vendor bidders list RFP document Risk rating scales & categories
Technical, contractual / procedural and commercial evaluation of proposals
List of potential risks and risk ratings within individual proposals
Pre-Mitigation Analysis Post-Mitigation Analysis and
Effectiveness Program level risk adjusted
cost and schedule analysis Supplier selection Contract Award
Analyze potential risk impact and mitigation posture relating to supplier proposal’s
Assess program requirements, supplier capabilities and evaluation criteria to establish RFP
Provide insight into where supplier risks affect the program and uncover their true impacts.
Compare supplier risk profile at proposal evaluation completion to determine outstanding risk exposure.
8
Omnia Paratus Corporation
Acquisition Risk Analysis follows a typical Risk Management process and can be tailored to program specific needs
Risk Identificat
ion
Sets risk parameters for effective risk analysis
Examines risks to determine impacts by
and across alternatives
Identifies risks that may impact cost,
schedule, or performance
Develops measures for keeping risk at
acceptable levels
Uses results of risk analysis in assessing
alternatives
Risk Planning
• Collecting SME input, best practices, metrics, etc., to identify possible risks
• Documenting risk data into a central repository
1 Risk Identification
• Creating standard risk terms and definitions
• Developing processes, criteria, and scoring approach for risk
Risk Analysis
• Conduct probabilistic assessments of risk impacts
Risk Mitigation
• Identifying, evaluating, and selecting strategies to reduce risk
• Developing an actionable risk mitigation plan, with sound rationale (if applicable)
Applying Risk Results
• Using cumulative risk scores as a vehicle for ranking alternatives
2 3 4 5
9
Omnia Paratus Corporation
Building qualitative definitions for risk ratings enables an objective, not subjective quantification of proposal risks The first step in Risk Planning involves defining standard risk terminology using many different resources, but
should be robust and accurate enough to reflect the program’s overall risk tolerance
Developing a robust, well-defined risk analysis process will produce results that reflect program needs; effectively communicates these needs across stakeholders; reduce personal bias in determining relative risk importance; and uncover potential impacts of great importance to the program
Risk criteria is not normative, and are based on available resources, time constraints, and amount/type of information solicited in generating the criteria
Performance Metrics
The analyst needs to ensure that the units of measure for risk impact reflect program needs. Critical program drivers might include life-cycle costs or metrics reliability (e.g., Mean Time Between Failure).
Order of MagnitudeIf impact thresholds are expressed in percentages (for example) the analyst needs to review those figures within the context of the overall anticipated program cost—e.g., 10% of $5 million program is substantially different than 10% of a $5 billion program.
Level of ImpactThe analyst needs to ensure that there is an adequate number of thresholds for evaluating the risk impact. The more levels of consequence that are utilized, the greater the insight into the need for increased data fidelity/quantity of data the analyst would need to consider.
Qualitative vs. Quantitative
Qualitative data is represented by probability values ranging from “Very Unlikely” to “Very Likely” , using stakeholder input to assess and weigh the importance of benefits, cost, and risk in relationship to the total analysis or evaluation of benefit, risk, and cost factors that cannot be quantified.
Quantitative data is represented by consequence values using linear numerical probabilities (e.g., 0.1, 0.3, 0.5, 0.7, and 0.9), nonlinear numerical probabilities (e.g., 0.05, 0.1, 0.2, 0.4, 0.8), cost estimates, metrics, ranges, or percentages.
Considerations for Defining Risk Criteria
10
Omnia Paratus Corporation
A Supplier Management Maturity module is used to determine if supplier capabilities comply with program requirements
Framework used to assess each IPTs risk management maturity in terms of People, Process, Technology, and Governance
The optimal goal of the risk enhancement effort is to select supplier cable of bidding based on their “Best in Class” maturity
Regular training conducted to enhance skills and capabilities Dedicated organizational resources All staff is informed and capable of applying mid- to advanced concepts
Applied use of specific processes/tools
Dedicated team resources In-house core experts, formally
trained in basic skills
Dedicated resources do not exist
Limited to individuals who may have had little or no formal training
Minimal understanding or experience in applying basic concepts and principles
Minimal understanding of principles or language
Integral to informed decision-making by upper management
Active use encouraged and rewarded Part of the organizational philosophy to
achieving program success Top-down commitment by leadership
• Accepted as a program management function
Benefits recognized and expected Upper management requires
tracking and reporting Focus on mitigation effectiveness
versus reporting and status tracking
Upper management encourages, but does not require use
Application varied through out program
• Process may be viewed as additional overhead with variable benefits
• Minimal awareness Minimal upper management
involvement Tendency to continue with
existing processes even in the face of potential failure
Dedicated resources do not exist
State-of-the-art tools and methodologies
Distributed data environment that provides access to all program resources
Standardized and automated reporting capabilities
• Integrated set of tools and methodologies
Centralized data environment managed by dedicated team resources
• Customizable solutions tailored to program
• Few repeatable technological solutions in place
• No structured application Management and tracking tools
not in use Analysis not performed
Qualitative/quantitative analysis methodologies employed with emphasis on valid and reliable data sources Metrics used and reported, with consistent feedback for improvement External stakeholders actively participate in process Integration into organizational processes and decision-making
Formal processes integrated into different areas of the program
Active allocation and management of budgets
Metrics collected Key internal stakeholders actively
participate in process
Common processes defined and formally documented
Process effectiveness limited to a dedicated team
Qualitative analysis based on ill-defined rating system
Established decision-body forum
Inconsistent application of concepts or principles
Formal risk decision-making body does not exist
Risk reporting and/or metrics is minimal or does not exist
Formal, documented process does not exist
4 – Best in Class3 – High Performance2 – Functional1 – Minimal Capability
Peop
lePr
oces
sTe
chno
logy
Gov
erna
nce
NOTIONAL
People Process Tech Gov’t Metrics Quality Capacity Average Rating
3 4 4 1 2 2 1 2.42
2 3 - 3 3 1 1 1.85Supplier B
3 3 4 2 3 3 2 2.85Supplier C
3 3 4 4 3 3 2 3.14Supplier D
Supplier A
Supplier’s will be scored based on the maturity model to establish a list of qualified suppliers for proposal solicitation
NOTIONAL
11
Omnia Paratus Corporation
Once proposals have been received a technical evaluation should be conducted for clarifications prior to identifying supplier risks
Proposal Clarification Items
Topic
General
Area
Staffing
Questions
Is the team available as indicated in the Proposal? Additionally, a further elaboration on local staff/ qualifications is
required
Ref.
P. 60
Approach
A further elaboration on the timeline is required, especially on the 9 days timeframe proposed for defining the architecture and standards
A show-case of the deliverables must be provided How realistic are the assumptions on available data and
Organization staff?
P. 46
Assumptions What is the impact on costs and timeline of a provision of a documentation in other languages?
P. 18
Phase 0: Kick-Off
Phase 1: Baseline
Phase 2: Best Practice Review
Alignment
Tools
Approach
How will Bidder ensure the alignment of the PM tools to the Organization’s PMO?
How will the automatic “systems” feed work (XML). Is it a requirement?
How will any incompatibilities of import functions affect the suggested timeline?
What if the Organization wants to use other EA tools, like ARIS? Further elaboration on “GEAS” layers required. A mapping to the
Organization framework layers is needed as well Explanation of the rationale for selecting Singapore, Australia and
Canada Is the access to those countries only via databases/benchmarks or
“real” contact?
P. 34
P. 36-38
P. 43
Phase 3: Definition of Architecture &
StandardsImperatives
No reference given, on how the Organization’s imperatives will be ensure – therefore, a further elaboration on the approach is required
P. 45
Answer Given Issue Resolved
All questions to a Bidder should be compiled and sent in a formal email / fax
All Bidders should be given ample and the same amount of time to respond to clarifications requested
12
Omnia Paratus Corporation
The next step to the risk assessment process is to identify risks that may impact a program’s cost, schedule, or technical performance……
Risk Identificat
ion
The risk analysis focuses on risks that affect each supplier’s ability to ensure program success (i.e., ongoing, uninterrupted support to the operational forces).
Although identification of risk relies on the skill, experience, and insight of subject matter experts and risk personnel, the methods and tools for initiating the identification of risk may vary
As such utilizing risk categories such as these bolsters risk identification…
“Common” Risks
Scope of Work
Testing & Integration
Material Availability
Suppler Metrics Schedule Budget Constraints
Qualification Requirements
Supplier Capabilities
Performance Metrics
Resources
Lessons Learned
ManagementComponents Program Requirements
Sensitivity Analysis
13
Omnia Paratus Corporation
Technical
…each risk is then reviewed against a set of Program-specific impact definitions, with the highest rating used to determine overall risk severity
Cost ( % over of cost target) Supplier Delivery Schedule
Existing technology does not exists
Existing technology exists, but has not been proven
Supplier has never built component before, Flight Test required
Supplier has never built component before, 1st article required
Supplier has never built component before
Supplier built similar component, Flight Test required
Supplier has built a component similar in nature, 1st article required
Supplier has built identical component for other Programs
Supplier has previously built component
Incumbent supplier
Level
Disastrous
Severe
Critical
Substantial
Significant
High
Moderate
Medium
Low
Minimal
Technical = High 3 Schedule = Critical 1 Cost = High 2
Consequence Rating = Critical
> 6.00%
5.01 – 6.00%
4.01 – 5.00%
3.01 – 4.00%
2.01 – 3.00%
1.01 – 2.00%
.76 – 1.00%
.51 - .75%
.26 - .50%
< .25%
>5 month slip in MRP requirements
4-5 month slip in MRP requirements
3-4 month slip in MRP requirements
2-3 month slip in MRP requirements
1-2 month slip in MRP requirements
< 1 month slip in MRP requirements
Risk erodes 100% of schedule margin
Risk erodes 51 – 75% of schedule margin
Risk erodes 26 – 50% of schedule margin
Risk erodes < 25% of schedule margin
14
Omnia Paratus Corporation
Risk #
WBS Impact
IMS Task ID Risk Description Risk
RatingCost Impact
($K's)
Schedule Impact (Days)
1 1.2.1.353
Lack of supplier staff to support delivery requirements
3 8 31.00$7,500 88
2 2.3.1.6 71 CCB is a development item 5 9 71.25 $8,500 118
3 4.3.5.1.1101
Supplier X's On Time Delivery rating subpar
2 10 28.50$9,500 150
4 6.3.3.788,97
Requirements of flux capacitor increase the need for Supplier X System Test & Eval staff and resources
4 6 32.25$5,500 52
5 1.3.1.570
Lack of technical capability in power generation / storage hardware may cost / schedule over runs
1 3 3.30$2,500 18
6 1.3.1.21.3.3.15 67,97
Tooling re-use approach may not be compatible with new technology
4 10 71.25$9,500 150
Prob. Conseq.
Risks are then integrated into the suppliers proposal to determine impacts of risks based on the risk ratings identified The risk database transposes risk rating into cost and schedule impacts in quantifiable dollar and
days
WBS and IMS task are later used to integrate supplier risk adjusted proposal into the Program’s Budget and IMS
15
Omnia Paratus Corporation
Monte Carlo Analysis is used in calculating risks associated with supplier cost impacts to program budget….This chart example utilized Crystal
Ball to perform Monte Carlo, multiple types of software exists and can be used for this analysis
Pick a Confidence Level based on program maturity and requirements
This example highlights the 75th
Percentile– 75% of costs are below the line,
25% of costs are above– The 75% CL is $49,448
16
Omnia Paratus Corporation
….as well as supplier risks that have the potential for disrupting a program’s Operations schedule.
The analysis example utilized SCRAM to run the schedule risks analysis
Confidence Level (CL) picked for cost is also used for schedule to determine how risk may impact a supplier’s delivery schedule
17
Omnia Paratus Corporation
Schedule & Cost Risk Assessment Module (SCRAM) is a MS Project add-in and FREE for use on NASA projects.
SCRAM’s capabilities compare with that of Pertmaster, @Risk and Risk++
Extremely user friendly and reliable
Customizable aspects not available with other tools
Compatible will all MS Office Products
18
Omnia Paratus Corporation
Once Monte Carlo simulations are complete and confidence levels selected, supplier bids can be compared based on potential risk impacts
Proposed $ 494,958 $ 465,135 $ 514,453
10% $ 507,645 $ 512,622 $ 547,565
20% $ 509,542 $ 523,002 $ 555,345
30% $ 510,834 $ 530,892 $ 561,676
40% $ 512,016 $ 537,855 $ 567,689
50% $ 513,090 $ 544,29 $ 573,385
60% $ 514,241 $ 551,640 $ 579,471
70% $ 517,449 $ 552,673 $ 585,912
80% $ 520,923 $ 565,114 $ 594,321
90% $ 523,007 $ 582,310 $ 607,304
100% $ 629,484 $ 589,685 $ 711,107
Supplier A Supplier B Supplier C
$700,000,000$600,000,000$500,000,000
Confidence Level ChosenSupplier B
Supplier A
Supplier C
19
Omnia Paratus Corporation
$497,042 $482,331 $427,436
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
$350,000
$400,000
$450,000
$500,000
$550,000
$600,000
$650,000
Supplier A Risk Adjusted Bid Supplier B Risk Adjusted Bid Supplier C Risk Adjusted Bid
Side-by-side risk exposure calculations provides leadership with comparative insights into supplier potential costs impacts
Prog
ram
Cos
t (in
thou
sand
s)
$39,100
Supplier Initial Cost
Risk Exposure
All costs reported at the 90% confidence interval.
Analysis will lead to a cumulative assessment of the total risk exposure and the potential impact to program
budget.
Component budget $500K
Potential Risk Impact $25K
Potential Risk Impact $99K
Potential Risk Impact $179K
20
Omnia Paratus Corporation
0
1
2
3
4
5
6
7
8
6/2/10 6/6/10 6/10/10 6/14/10 6/18/10 6/22/10
Material Resource Planning requirement for this component is 04/25/2010
Risk adjusted delivery schedules are then compared to determine the potential risk impact to program’s operations
Supplier’s Initial ProposalSupplier A B C
Proposed Schedule 04/18/2010 04/04/2010 04/21/2010
Risk Adjusted Schedule 05/13/2010 07/18/2012 08/21/2012
0
1
2
3
4
5
6
7
8
9
5/3/10 5/7/10 5/11/10 5/15/10
0
0.5
1
.5
2
.5
3
.5
4
4.5
7/7/10 7/11/10 7/15/10 7/19/10 7/23/10 7/27/10 7/31/10 8/4/10 8/8/10
Illustrative IllustrativeIllustrative
Supplier A Supplier B Supplier C
21
Omnia Paratus Corporation
The risk-adjusted cost and schedule results are then compared for awarding contracts on a risk averse path
Initial review of Supplier bids would indicate “C” as the supplier of choice
Based on Supplier B & C delivery metrics and potential risk, schedule impact could result in more than a 3 months past MRP requirements
Based on supplier C’s lack of technical capabilities and schedule risk to operations, risk impact could equate to ~$100K over component budget
Based on risk adjusted Cost & Schedule proposal analysis supplier “A” should receive program consensus for contract award based on least amount of risk exposure to the program
Supplier’s Risk Adjusted ProposalSupplier A B C
Risk Adjusted Cost $ 523,007 $ 582,310 $ 607,304
Risk Adjusted Schedule 05/13/2010 07/18/2012 08/21/2012
Supplier’s Initial Proposal
Supplier A B C
Proposed Cost $ 497,042 $ 482,331 $ 427,436
Proposed Schedule 04/18/2010 04/04/2010 04/21/2010
22
Omnia Paratus Corporation
Given these potential benefits, a few key considerations are worth noting
In order to have a successful portfolio risk management process, it’s important that the constituent components of the program have sufficiently mature supply chain management and risk management processes.
Integration of acquisition risk analysis into a program’s budget and schedule is necessary to capture the magnitude of potential program risk impact by a single supplier
Identifying risks within a proposal enables forward looking program management that can be streamlined into existing risk database’s for future risk management planning and mitigation.
Qualitative risk analysis provides enhanced proposal evidentiary support and solid justification for awarding contracts
The success of a supply chain risk management program requires the consistent and active support of program leadership in order to be successful.
23
Omnia Paratus Corporation
For more information on how acquisition risk analysis can be applied to your specific challenges, please:
Contact:
James TaylorHuntsville, [email protected]