Jack Creek Park Capital Improvement Project Public Information Meeting October 2, 2017 Consultants & Designers, Inc. “Integrating Engineering and Environment” 7455 New Ridge Road, Suite T Phone: (410) 694-9401 Hanover, Maryland 21076 Fax: (410) 694-9405 1
25

Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

May 05, 2018

Download

Documents

lengoc
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Jack Creek Park Capital Improvement Project

Public Information Meeting

October 2, 2017

Consultants & Designers, Inc.“Integrating Engineering and Environment”

7455 New Ridge Road, Suite T Phone: (410) 694-9401Hanover, Maryland 21076 Fax: (410) 694-9405

1

Page 2: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Introduction Office of County Executive Steven R. Schuh

• Michelle Corkadel, Constituent Services Officer

Anne Arundel County Department of Public Works• Masoud Ghatineh, P.E., Project Manager

Design Consultant – BayLand Consultants & Designers, Inc.• Sepehr Baharlou, P.E., Project Manager

Meeting Purpose• Increase Community Awareness of the Project• Provide Project Overview and Status Update• Respond to Questions

2

Page 3: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Project Goals Protect park from shoreline erosion

Enhance water quality of the Chesapeake Bay

Address County MS4/TMDL permit requirements

Improve public access to the waterway

Support recreational boating dredging program

3

Page 4: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Project Overview Shoreline Protection

• Living shoreline

Waterway Access• Soft (natural) canoe/kayak launch

Dredged Material Placement• Place dry material from Idlewilde DMP Site

4

Page 5: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Jack Creek Park

58 acres

5

Page 6: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection 1994 Aerial Photo

6

Page 7: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection 2014 Aerial Photo

7

Page 8: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection 2014 VS 1994 Aerial Photo

• 6 acres lost due to erosion

8

Page 9: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection Existing shoreline conditions

9

Bay Front Jack Creek

Along the Point

Page 10: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection Living Shorelines

• Controls shoreline erosion• Provides a productive, natural shoreline• Strategic placement of plants, stone, sand fill and other

structural and organic materials• Implemented through a variety of shoreline protection

methods

10

Page 11: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection Stone structures provide erosion protection Sand fill provides planting terrace Marsh plantings provide flood protection and habitat

enhancement

11

Page 12: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Shoreline Protection Protects 1,488 LF of

shoreline Restores 58,811 SF of

tidal marsh

12Preliminary Concept Plan

Page 13: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Waterway Access Access Road

13

Parking Launch Area

Preliminary Concept Plan

Page 14: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Waterway Access Launch Area

• Soft (natural) canoe/kayak launch• Natural shoreline

14

Page 15: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Waterway Access Access shoreline through existing trail Provide ADA compliant surface Incorporate launch area into living shoreline design

15

Page 16: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Waterway Access Parking

• 20 car parking spots (no trailers)• Permeable grass paving

16

Page 17: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Waterway Access Access Road

• Follow existing gravel road• Gravel surface to the parking area• Trail to water will be permeable gravel (ADA compliant)• Controlled access (gate) will remain

17

Page 18: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Dredged Material Placement Place dry material from Idlewilde DMP Site

18

Page 19: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Dredged Material Placement Idlewilde DMP Site primarily used for South County

recreational dredging projects such as:• Parish Creek (Federal and County channels)• Rockhold Creek Jetty • Broadwater Creek• Church Creek• West River, etc…

All materials are tested before dredging• Metals• Pesticides & PCBs• Priority pollutants volatiles & semi-volatiles• Total of 149 parameters

19

Page 20: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Dredged Material Placement Jack Creek Park placement area

20

Page 21: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Dredged Material Placement Place dry material from Idlewilde DMP Site

• 14,000 cubic yards• 3-acre area• Amend soil with lime and fertilizer• Cover with 6 inches of topsoil• Shape to form natural land features• Re-seed with meadow mix

Create small wetlands (rain garden) Restore to existing use and vegetative cover

21

Page 22: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Dredged Material Placement Truck Route

• Idlewilde Road to Snug Harbor Road – ½ mile

22

Page 23: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Dredged Material Placement Example

23

During Placement After

Page 24: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Schedule

Project has been split into two phases

Phase 1: Dredged Material Placement• Under construction – to be completed in 2 months

Phase 2: Living Shoreline & Waterway Access• Design completed• Federal, State and County permitting underway• To be constructed in 12 to 18 months

24

Page 25: Jack Creek Park Capital Improvement Project - … · Jack Creek Park Capital Improvement Project ... 20 car parking spots ... Jack Creek Park placement area. 20.

Discussion

25