Top Banner
Trabajo Rustico Concrete Structure (bus stop) Repairs 4900 Block Broadway & Patterson Presented By: Jason Lutz Community Development Services Director City Council Meeting Agenda Item # 11 July 25, 2016
14

Item #11 ppt bus stop

Apr 06, 2017

Download

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Item #11   ppt bus stop

Trabajo Rustico Concrete Structure (bus stop)

Repairs4900 Block Broadway & Patterson

Presented By: Jason LutzCommunity Development Services Director

City Council MeetingAgenda Item # 11

July 25, 2016

Page 2: Item #11   ppt bus stop

SUMMARY Overview of repair costs for the historic

bus stop structure.

Page 3: Item #11   ppt bus stop

3

BACKGROUND

Built by Dionicio Rodriguez around 1927 Three large trunks with branches

supporting its papapa roof Style of art is French faux bois (false

wood) Placed on the National Register of

Historic Places in 2004

Page 4: Item #11   ppt bus stop

4

Page 5: Item #11   ppt bus stop

5

CONDITION OF THE BUS STOP

Overall in good condition concerningfoundation and structural rebar.

Roof has lost its original finishing due tothe elements.

The structure has lost 70% of its originalcoloration

Page 6: Item #11   ppt bus stop

6

CONDITION OF THE BUS STOP Water seeping through the roof has caused

efflorescence to appear on the structure. Efflorescence is when a substance changes

to powder due to water and crystallizes onthe adjacent surface.

When efflorescence takes hold, the structuralintegrity of a structure is at great risk.

Page 7: Item #11   ppt bus stop

7

EFFLORESCENCE

Page 8: Item #11   ppt bus stop

8

CONDITION

Page 9: Item #11   ppt bus stop

9

REPAIRS & RESTORATION PROCESS

The efflorescence can be stopped toprevent any future damage as part of therestoration process.

Repairs will be made by Rene Romero

Page 10: Item #11   ppt bus stop

10

REPAIRS & RESTORATION PROCESS

Structural Repairs Repair/replace missing or damaged

rebar Replace visible texture which is

missing or faded Re-attach broken/cracked pieces

Page 11: Item #11   ppt bus stop

11

REPAIRS & RESTORATION PROCESS

Restoration Process called “resanado” (to restore) Cover all cracks Restain using the original mineral

salts to bring back the original colors

Page 12: Item #11   ppt bus stop

12

REPAIRS & RESTORATION PROCESS

Process Will take approximately 1 month to

complete 10 years of protection Traffic control plans will need to be

developed to TxDOT standards

Page 13: Item #11   ppt bus stop

13

FISCAL IMPACT

Restoration Process (1 month) = $46,700

Engineering Costs (Traffic Control Plan &TxDOT permitting) = $2,752

Road Closure Costs (Traffic control,barrels, attenuator crash truck rental) =10,168.50

Total Costs = $59,620.50

Page 14: Item #11   ppt bus stop

QUESTIONS?