Issues and challenges: sourcing sustainable products & technologies Gary Wilburn DESIGN ZERO DRIVE Sustainable Construction Network
Jan 27, 2015
Issues and challenges: sourcing sustainable products & technologies
Gary Wilburn
DESIGN ZERO DRIVE
SustainableConstructionNetwork
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 1
Issues and challenges� It is not only building skills and alternative solutions that are the challenge� Avoiding Greenwash!: can only be understood with knowledge� Human behavior, habits and methodologies need to change, this need
not cost money but takes commitment� Embrace the principles of continuous improvement, do not accept convention� Involution: combining innovation and evolution� Proving low energy building performance: Building physics and dynamic modeling
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 2
There are opportunities in ALL sectors and not always new-buildHousing retro-fit challenge (Source BERR 2008)
� 80%+ of housing stock in the UK in 2050 already exists� 500,000 houses to be transformed per year at approx £20,000 - 30,000 house for 40 years� 200,000 construction jobs required to support the task� The largest ever UK Engineering Project
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 3
Sustainable communities: how many opportunities do we want?
There are examples around the world (even in the UK), get out and see them!
Community-scale wind turbine
Maintained ‘eco-system’
Green roofingFuel-cell bus Waste-to-energy plant
Refurbishment existing dwellings
Combined heat and power plant
Solar shading
Rainwater harvesting
Ground-source heating
High-speed broadband
Sustainable drainage system Car re-charging
Community recyclingZero-carbon dwellings
District heating networkSmart metering
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 4
Sourcing sustainable products & technologies
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 5
DESIGN ZERO DRIVE
Building Materials Showroom Austria
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 6
DESIGN ZERO DRIVE
Building Materials Showroom Austria
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 7
Case studies: Designing to a higher level
GW-SCN (Draft 2) pres. 15/2/10 09:52 Page 8
DESIGN ZERO DRIVE
Passivhaus School Austria
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 9
Hammarby ‘cradle to cradle’ strategy
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 10
DESIGN ZERO DRIVE
Hammarby Sjöstad Stockholm
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 11
DESIGN ZERO DRIVE
Hammarby Sjöstad Stockholm
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 12
DESIGN ZERO DRIVE
Hammarby Sjöstad Stockholm
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 13
DESIGN ZERO DRIVE
Hammarby Sjöstad Stockholm
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 14
DESIGN ZERO DRIVE
Hammarby Sjöstad Stockholm
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 15
Passivhaus Construction� Use of bioregionally sourced materials� Manufactured, high quality solution� Off-site modular format� Maximising insulation, minimising energy use� Known technology and construction details
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 16
DESIGN ZERO DRIVE
Ludesch Community Building Austria
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 17
DESIGN ZERO DRIVE
Wolfort Housing Austria
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 18
Paultons ParkNew low carbon attraction building
Wildflower roof
Naturally ventilated indoor play area
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 19
DESIGN ZERO DRIVE
Paultons Park - Indoor play area
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 20
B&Kcolumn
B&Kcolumn
B&Kcolumn
B&Kcolumn
B&Kcolumn
B&Kcolumn
B&Kcolumn
B&Kcolumn
B&Kcolumn
90
15.8115.79
15.7115.72
5.27
15.37
15.4215
.43
15
15.89
16.00
15.85
15.74
15.67
15.60
15.52
15.51
15.63
15.73
15.66
15.55
15.59
15.63
15.54
15.53
15.51
15.40
15.80
15.71
15.91
DESIGN ZERO DRIVE
Paultons Park - Technical specifications
WM5 WM6 WM7
WG6
1800 1800 1800 EqualEqual
900 1800 900
252100
1
6 =
boa
rds
2575
Boa
rds
@ 1
25 c
\cs
Timber panels central on window opening
WEST ELEVATION
mez
zani
ne fl
oor
c/l w
indo
w
c/l w
indo
w
c/l w
indo
w
18001800 1800 1800Equal Equal
252100
1
6 =
boa
rds
2575
Boa
rds
@ 1
25 c
\cs
WG5
Timber panels central on window opening
NORTH WEST ELEVATION
Section through south facing eaves(Wall construction not shown for clarity)
Grass & wildflower turf on membrane
Shallow profile roof cladding panels
Kingspan Topspan composite panels
200
circa 900
wall thickness
straight ro
of
curve
d roof
Steel column
Structural supportif required
Structural support@ each gridline(7.1m)
Gutter profile
PPC pressed metal profileflashing to conceal gutter& support beam
Rwp
curved beam
Section through north facing eaves(Wall construction not shown for clarity)
Grass & wildflower turf on membrane
Shallow profile roof cladding panels
Kingspan Topspan composite panels
Steel column
Structural supportif required
Gutter profile
PPC pressed metal profileflashing to conceal gutter& support beam
Rwp
curv
ed b
eam
200
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 21
DESIGN ZERO DRIVE
Paultons Park - Current site images
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 22
Visitor CentreTaking full advantage of a 54 acre site, HPW created the concept and developed the Visitor Centre to act as a hub for access to:- 26 acre Country park- 6 permanent mazes- Countryside interpretation exhibition- Retail offer
A purpose built 4,500 sq.ft. timber framed and clad building. In its countryside setting the centre nestles beneath established trees and oversails two lakes to form a gateway to the visitor attractions and complementary retail operations.
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 23
Window detail E32-01/1
Wall detail E32-01/2Wall section E32-01/3
Wall section E32-01/4
Window head toE32-01/3
Silicone pointing
75 x 50 vertical counter batten set to take external boarding
External timber boarding returned atwindow reveal. Outside of boarding toline up with outside face of glazing bead.Shape at base to cill
Integrated timber cill
Internal board to returnat window reveal
Soffit over dotted
Timber soffit above shown
Width of windows: 1200; 915
Silicone bead to perimeter of boardingwhere in contact with window frame.Colour : best match for stain colour
2510
150
10
300
glul
am
150
9mm Sterling Board to take curve of wall,fixed with cups & screws in pattern,finish to match boards.
Vapour barrier with sealed taped joints
Insulation
Breathable sarking felt
Treated 50 x 50 sw counterbattens screw fixed
Treated sw battens (provisional 50x32)screw fixed
125x25 vertical sw boarding
All 100x100 RHS post to be INSULATEDwith injected foam
Vertical softwood mullions100mm deep, width to suit span
10mm shadow gap between boards.Face of mullion painted black
9mm Sterling Board to take curve of wall,fixed with cups & screws in pattern,finish to match boards.
Vapour barrier with sealed taped joints
Insulation
Breathable sarking felt
Treated sw counterbattens (provisional 50 x 50)screw fixed
Treated sw battens (provisional 50x32)screw fixed
125x25 vertical sw boarding
300
Circular timber casing to metal post
Circular galvanised collar
250
Curved galvanised edge beam
Glulam beam tapered at perimeter
Curved galvanised edge beam oncurved timber fascia
220
50
4241
NT
S
2750
1491
NT
S
Insulation to both sidesof ring beam
Roof membrane18mm Sterling board102 x 50 battens11mm Sterling board Drainage to be
determined
Floor construction:75mm floor finish (varies in type) on 150 conc slab (by engineer)Insulation Damp proof membrane Sand blindingDOT type 1
450
Foundations by structural engineer
Damp proof membrane behind steel
400
72.925 provisional
73.47573.475Timber decking by Dobbies
Timber double glazed windows
125 x 25 timber external vertical boarding
Boarding to window reveal trimmed towindow cill and sealed with polysulphidestrip
For description see detail E32-01/4
1205
1210
10m
m g
ap
1205
Curved timber sole plate& cladding rails
Curved 200 x 100 galvanisedangle
Sizes & spacings of treatedsw battens by structuralengineer
Coursing block to act as shutter
All window / door posts to be INSULATED with injected foam
Dpm to edge of concrete
1200 or 915 between posts
150
7552
5
73.475
7515
0
External timber boarding returned atwindow reveal. Outside of boarding toline up with outside face of glazing bead.Shape at base to cill
Timber double glazed windows
76.225
Curved timber cladding railsbetween window posts
Internal board to returnat window reveal
40
76.265
15 a
ir ga
p 10
360
glul
am
Curved galvanised edge beam oncurved timber fascia
Curved galvanised infil panel betweenglulam beams. 15mm air gap at top edge
Vapour barrier18mm Sterling board102 x 50 battens11mm Sterling board
Drainage to bedetermined
50
Silicone pointing to window head
T & G boarding to soffit of external roof
235
2750
72.72572.725
76.225
stee
l
Depth of steel by Fordingbridge
5 to
lera
nce
Decking support provisional Decking support provisional
75.910
2512
00
2400 x 1200 boards laidlandscape
10m
m g
ap
300 glulam
75 x 25 timber battens
12mm gap
Soffit board shaped to curve(width varies)
Roof finish build up to detail
5 to
lera
nce
Detail as right
Roof finish build up to detail
50
External soffit level
Approximate existing ground level
Plan @ entrance
15072.925
400
over
all
750
Landing 1 in 60 fall
Ramp
73.475
Treated timber retaining wall
4241
Outer skin:Vertical timber boards 25mm thick on50 x 32 horizontal treated sw battens on50 x 50 vertical treated sw counter battens onbreathable sarking felt on100 x 50 vertical sw battens Inner skin:9mm Sterlingboards on vapour barrieron 25 x 75 sw battens
Outer skin:Curved cladding as specified on50 x 25 vertical treated sw counter battens onbreathable sarking felt on50 x 50 vertical sw battens fixed to100 deep curved sheeting rails @ 1000 c/cs
Insulation:100 rockwool quilt between cladding railsJablite board between 50 x 50 vertical sw battens
Curved flashing to top of boards
Curved flashing to top of cladding
Edge steel by Fordingbridge.Painted finish
Glulam beams chamferred
Curved edge trim to roofto detail
Sterling board internal finish
Exposed radial glulam beams
Umbrella support by Fordingbridge
Floor: (To Wedgewoods specification)175 powerfloated concrete floor onKingspan insulation board ondpm on sand blinding on 150 mintype 1
200 x 100 curved steelangle by Fordingbridge
2750
Decking provisional
Insulation & ceiling boards continues
Air curtain over doorfixed through boardingonto timber bearers
25
Vertical timber boardingabove door to u/side ofglulam beams
2790
str
uctu
ral
2445
ope
ning
130
External boarding to soffits and reveals to line up with outside face of window bead 12
0
10mm drainage gapbetween sarking felt and timber soffit
Insulation to provide U=<0.25
Roof finish to design
General roof make up:Green roof on waterproof membrane oninsulation on vapour barrier on18mm sterlingboard decking on timber joists onglulam beams
55
Fordingbridge curved anglecovered with floor mat
Door frame over showndotted
Internal boarding above doorto be set in by 55mm to coverdoor frame at head
Back corner of door frame seton back corner of steel post
Aluminium threshold fixed toperimeter angle
Edge of perimeter angle
750
1650
Internal boarding above all 1750 doorsset out as plan (right) to cover door head
1100
bottom panel to reception buildingwindows to be obscure glazed to hpw specification
ring beam dotted to illustrate door frame
hd
100
1200
700
Bulkhead over@ 2100
Bulkhead over@ 2100
Suspended ceiling over
Bulkhead over@ 2100
Bulkhead over@ 2445
Bulkhead over@ 2100
Line of wall over
See studio arc dwg110-BA01C for settingout
1445
aav & sp
gully gully
aav & sp
1440
4900
svp
W19
1000 clear
1000 clear
100
500
1200 clear
70
equal
equal70
equal
equal
4275
70.0
1
70.01
70
3 @ 750 c/cs = 2250
2180
1250
cle
ar
1000
115
900
300
1500
70
1230
103090
0
900
1000
1240
300
790
100
7055
115
70
250
70
1825
70
1200 clear
1200
clea
r
70
50
1500 clear
equal
equal
70
50
100
2218
183570
49570
equa
leq
ual
fan
C
1475
Window detailE32-01/1
Wall detailE32-01/2
Wall section
E32-01/3
Wall section
E32-01/4
DX2
DX1
DX3
DX4
DX5
W1 W2
W3
W4
W5
W6
W7
W8
W9W10
W11
W12
W13
W14
W15
W16
W17
W18
D1
D2D3
D4D5
Building section
E22-01/2
Building section
E2 2-01/1
Building section
E22-01/1
Building section
E22-01/2
Wall section
E32-01/4
D8
1030
radial partition
W20
W21
ss sink in 1500 base
wp & aavD9
125900
2999
.99
70
wp & aavgully
ic
1294
490
70
115070
355
90070
D7
70
re
D6 zone 5
zone 4
zone 3
zone 2
zone 1
Retail
female toilets
male toilets
lobby 1
lobby 2
corridor
disabled toilet
classroomwc
wc
wc
3 N
o w
hbs
& v
anito
ry to
p
3 N
o w
hbs
& v
anito
ry to
p
Cubiclesto detail
2 No urinals
Cubicleto detail
Beam over@ low level
hd
hd
1500 clear
staff room
office
1200
1200
mat
2650
750
900
70
equal
equal
600
equa
l
equa
l
Steel beam over (by structural engineer) to provide top restraint to timber posts
Type 3 window1200 x 2450Located centrallybetween glulam beams
Type 3 window1200 x 2450Located centrallybetween glulam beams
DESIGN ZERO DRIVE
Atherstone Visitors Centre - Concept and construction details
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 24
DESIGN ZERO DRIVE
Atherstone Visitors Centre - Site images
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 25
Bicester AvenueAward-winning flagship for Wyevale group (formerly Blooms)
Attention to detail and application of sustainability on a large commercial scheme
FSC Timber cladding, low energy lighting, under-floor heating, porous surfacing, rainwater harvesting and SUDS scheme
Locally sourced materials and waste management procedures adopted throughout the build process
WinnerStore Design of the Year
WinnerRetail Destination of the Year
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 26
DESIGN ZERO DRIVE
Bicester Avenue - Mall entrance
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 27
DESIGN ZERO DRIVE
Wyevale - Main retail atrium
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 28
Marwell Zoo Kangaroo and Emu houseAll material found/reclaimed on site
As zero carbon as you can get?
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 29
Rooflights Laminated glazing Proposed aviaryTimber Cladding RenderProfile metal sheet roof cladding
Profile metal sheet roof claddingTimber Cladding Render
Timber sections in mesh frame Rooflights
1800mm staggered timber post fence for kangaroo enclosure
1400mm staggered timber post fence for emu enclosure
DESIGN ZERO DRIVE
Marwell Zoo - Kangaroo and Emu House
GW-SCN (Draft 2) pres. 15/2/10 09:53 Page 30
Thank you... any questions?DESIGN ZERO DRIVE
SustainableConstructionNetwork
GW-SCN (Draft 2) pres. 15/2/10 09:54 Page 31