Top Banner
Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By Belal Almassri
16

Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Feb 23, 2016

Download

Documents

johnna

Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri. Chapter 7 Coordinate geometry and traverse surveying – Part 2. Resection Traverse Surveying Definitions Types, Utilizations and advantages Computations and correction errors Examples. A. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Islamic University of GazaCivil Engineering Department

Surveying IIECIV 2332

ByBelal Almassri

Page 2: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Chapter 7 Coordinate geometry and traverse surveying – Part 2 -Resection -Traverse Surveying Definitions-Types, Utilizations and advantages-Computations and correction errors-Examples

Page 3: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

6. ResectionAs in the following figure, the

horizontal position of a new point like P can be Determined by measuring the horizontal angles to three points of known coordinates like: A & B & CA

P

CB

NM

c bӨ

RФβ

Page 4: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Let J = β + Ф then J = 360º – ( M+ N+ R )

1- compute & & b & c & R from the known coordinates of points: A , B ,C . (R= - )

2- compute J = 360º – ( M+ N+ R )3- compute H = b sin M / c sin N4- compute Ф ( tan Ф = sin J / (H + cos J ))5- compute Ө = 180º - N – Ф6- compute = + Ө 7- compute AP = b sin Ф / sin N8- compute Xp & YpXp = XA + AP sinYp = YA + AP cos

AB AC

AP AC

AP

AP

Procedure:

AB AC

Page 5: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Example 7.6:

Page 6: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri
Page 7: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Traverse SurveyingDefinitions:- Traverse is one of the most commonly

used methods for determining the relative positions of a number of survey points.

- Traverse is a method in the field of surveying to establish control networks. It is also used in geodetic work. Traverse networks involved placing the survey stations along a line or path of travel, and then using the previously surveyed points as a base for observing the next point.

Page 8: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Utilizations:- property survey to establish

boundaries.- Location and construction layout

surveys for highways, railways and other works.

- Helps the surveys for photogrammetric mapping.

Types of Traverse: a- Closed Traverse b- Open

Traverse

Page 9: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Advantages:- Less organization needed.- Few observations needed.- More accurate than other methods.- Suits different types of utilizations

Open Vs Closed:- Closed traverse is useful in marking the

boundaries of wood or lakes .- Open traverse is utilised in plotting a

strip of land which can then be used to plan a route in road construction.

Page 10: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Choice of traverse stations: 1. As close as possible to the

survey details.2. Traverse shortest line should be

greater than 1/3 of the longest line (preferred to be equal).

3. Traverse stations should be selected in firm ground.

4. From one station we can see the back sight and the foresight.

Page 11: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Underground . . . .

Page 12: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Computations and correction of errorsA- Determine the Azimuth of each line: 1- When ( α1 + Ө ) > 180º α2 = Ө - ( 180º – α1) = Ө + α1 - 180º

2- When ( α1 + Ө ) < 180º α2 = Ө + 180º + α1 = Ө + α1 + 180º

Page 13: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

B- Checks and correction of errors : X last point – X first point = ∑ ∆ X all lines Y last point – Y first point = ∑ ∆ y all lines

In order to meet the previous two conditions, the following corrections are performed:1- Angle correction:a- Closed loop traverse: For a closed traverse of n sides, - sum of true internal angles = (n – 2 ) × 180 º - error = sum of measured angles – ((n – 2 ) × 180 º) - correction per angle = - error / no of internal angles

Page 14: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

b- connecting traverse: If the azimuth of the last line in the traverse is known, then the error- εα = αc (calculated azimuth) - αn (known azimuth) - correction / angle = - εα / n the corrected azimuth - αi = α’i ( initially computed azimuth)– i (εα / n) 2- Position correction: IF the calculated and known coordinates of last point are: ( X c , Y c ) & ( X n , Y n )respectively, then :- Closure error in x-direction(ε x ) = X c – X n- Closure error in y-direction(ε y ) = Y c – Y n- Closure error in the position of the last points = √ ε x² + ε y ²

Page 15: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Compass ( Bowditch ) Rule : used for position correction as follow:

Correction to departure of side ij( ∆x) = -(length of side ij / total length of traverse)(ε x )

Correction to departure of side ij( ∆y) = -(length of side ij / total length of traverse)(ε y )

Correction can be done directly to coordinates:Cxi = - (Li / D) (ε x ) & Cyi = - (Li / D) (ε y ) Where: Li=the cumulative traverse distance up to station i

&D=total length of the traverseThe corrected coordinates of station i ( x'i , y'i ) are: X'i =

Xi + Cxi & Y'i = Yi + Cyi Allowable error in Traverse surveying

Page 16: Islamic University of Gaza Civil Engineering Department Surveying II ECIV 2332 By B elal A lmassri

Azimuth and bearing

North to east or west / South to east or west