# Activity ID Activity Name Original Duration Start Finish 1 ISBL ISBL 1674h 01-Jan-15 12:00 AM 11-Mar-15 06:00 PM 2 FURNACE FURNACE 1135h 01-Jan-15 06:00 AM 17-Feb-15 01:00 PM 3 R15E-151-007 R15E-151-007 RC2-32-151-PV-0013-CV-OVERHAUL & SERVICING 1135h 01-Jan-15 06:00 AM 17-Feb-15 01:00 PM 4 PRE-SHUTD PRE-SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 5 II100630 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 6 II100635 Remove Insulation 2h 01-Jan-15 07:00 AM 01-Jan-15 09:00 AM 7 SHUTDOWN SHUTDOWN 31h 16-Feb-15 06:00 AM 17-Feb-15 01:00 PM 8 II100640 Verify LT&T and Obtain permit 1h 16-Feb-15 06:00 AM 16-Feb-15 07:00 AM 9 II100645 Disconnect Signals / Connections for CV 1h 16-Feb-15 07:00 AM 16-Feb-15 08:00 AM 10 II100650 Removal of CV & Install Blinds 4h 16-Feb-15 08:00 AM 16-Feb-15 12:00 PM 11 II100655 Trans port CV to Work Shop 1h 16-Feb-15 12:00 PM 16-Feb-15 01:00 PM 12 II100660 Overhaul / Service CV 12h 16-Feb-15 01:00 PM 17-Feb-15 01:00 AM 13 II100665 Test Valve (Refer Documentation) 2h 17-Feb-15 01:00 AM 17-Feb-15 03:00 AM 14 II100670 Trans port CV to Unit / Remove Blinds 1h 17-Feb-15 03:00 AM 17-Feb-15 04:00 AM 15 II100675 Install CV 6h 17-Feb-15 04:00 AM 17-Feb-15 10:00 AM 16 II100680 Loop Check & Stroke test 2h 17-Feb-15 10:00 AM 17-Feb-15 12:00 PM 17 II100685 Inspection by RLOC 1h 17-Feb-15 12:00 PM 17-Feb-15 01:00 PM 18 POST SHUT POST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 19 II100690 Reinsulate CV 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 20 II100695 House keeping & Close PTW 1h 01-Jan-15 07:00 AM 01-Jan-15 08:00 AM 21 R15E-999-001 R15E-999-001 RC2-32-999-10-BD-002-INST-VERIFY AND ARREST LEAK 19h 13-Feb-15 02:00 PM 14-Feb-15 09:00 AM 22 SHUTDOWN SHUTDOWN 19h 13-Feb-15 02:00 PM 14-Feb-15 09:00 AM 23 II110545 Review JSA 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM 24 II110550 Verify LT&T and Obtain permit 2h 13-Feb-15 03:00 PM 13-Feb-15 05:00 PM 25 II110555 Disconnect signals / connections 3h 13-Feb-15 05:00 PM 13-Feb-15 08:00 PM 26 II110560 Verify Leaking area and Arrest the Leak 6h 13-Feb-15 08:00 PM 14-Feb-15 02:00 AM 27 II110565 Reconnect the signals / connections 4h 14-Feb-15 02:00 AM 14-Feb-15 06:00 AM 28 II110570 Offer for Inspection 2h 14-Feb-15 06:00 AM 14-Feb-15 08:00 AM 29 II110575 House keeping & Close PTW 1h 14-Feb-15 08:00 AM 14-Feb-15 09:00 AM 30 VHP VHP 1668h 01-Jan-15 06:00 AM 11-Mar-15 06:00 PM 31 R15E-002-004 R15E-002-004 RC2-31-002-PV-0001-CV-OVERHAUL & SERVICING 992h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 32 PRE-SHUTD PRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 33 II100000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 34 II100005 Errect Scaffolding / Remove Insulation 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM 35 SHUTDOWN SHUTDOWN 43h 09-Feb-15 07:00 PM 11-Feb-15 02:00 PM 36 II100010 Verify LT&T and Obtain permit 1h 09-Feb-15 07:00 PM 09-Feb-15 08:00 PM 37 II100015 Disconnect Signals / Connections for CV 1h 09-Feb-15 08:00 PM 09-Feb-15 09:00 PM 38 II100020 Removal of CV & Install Blinds 10h 09-Feb-15 09:00 PM 10-Feb-15 07:00 AM 39 II100025 Trans port CV to Work Shop 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM 40 II100030 Overhaul / Service CV 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM 41 II100035 Test Valve (Refer Documentation) 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM 42 II100040 Trans port CV to Unit / Remove Blinds 1h 10-Feb-15 10:00 PM 10-Feb-15 11:00 PM 43 II100045 Install CV 12h 10-Feb-15 11:00 PM 11-Feb-15 11:00 AM 44 II100050 Loop Check & Stroke test 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM 45 II100055 Inspection by RLOC 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM 46 POST SHUT POST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 47 II100060 Reinsulate CV / Removal of Scafflods 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 48 II100065 House keeping & Close PTW 1h 01-Jan-15 09:00 AM 01-Jan-15 10:00 AM 49 R15E-002-005 R15E-002-005 RC2-31-002-PV-0003-CV-OVERHAUL & SERVICING 992h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 50 PRE-SHUTD PRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 51 II100070 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 52 II100075 Errect Scaffolding / Remove Insulation 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM 53 SHUTDOWN SHUTDOWN 43h 09-Feb-15 07:00 PM 11-Feb-15 02:00 PM 54 II100080 Verify LT&T and Obtain permit 1h 09-Feb-15 07:00 PM 09-Feb-15 08:00 PM 55 II100085 Disconnect Signals / Connections for CV 1h 09-Feb-15 08:00 PM 09-Feb-15 09:00 PM 56 II100090 Removal of CV & Install Blinds 10h 09-Feb-15 09:00 PM 10-Feb-15 07:00 AM 57 II100095 Trans port CV to Work Shop 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM 58 II100100 Overhaul / Service CV 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM 59 II100105 Test Valve (Refer Documentation) 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM 60 II100110 Trans port CV to Unit / Remove Blinds 1h 10-Feb-15 10:00 PM 10-Feb-15 11:00 PM 61 II100115 Install CV 12h 10-Feb-15 11:00 PM 11-Feb-15 11:00 AM 62 II100120 Loop Check & Stroke test 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM at Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W hr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 1 of 128 TASK filters: FILTERS, FILTERS_1. © Oracle Corporation
128
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  1. 1. # Activity ID Activity Name Original Duration Start Finish 1 ISBLISBL 1674h 01-Jan-15 12:00 AM 11-Mar-15 06:00 PM 2 FURNACEFURNACE 1135h 01-Jan-15 06:00 AM 17-Feb-15 01:00 PM 3 R15E-151-007 RC2-32-151-PV-0013-CV-OVERHAUL & SERVICINGR15E-151-007 RC2-32-151-PV-0013-CV-OVERHAUL & SERVICING 1135h 01-Jan-15 06:00 AM 17-Feb-15 01:00 PM 4 PRE-SHUTDOWNPRE-SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 5 II100630 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 6 II100635 Remove Insulation 2h 01-Jan-15 07:00 AM 01-Jan-15 09:00 AM 7 SHUTDOWNSHUTDOWN 31h 16-Feb-15 06:00 AM 17-Feb-15 01:00 PM 8 II100640 Verify LT&T and Obtain permit 1h 16-Feb-15 06:00 AM 16-Feb-15 07:00 AM 9 II100645 Disconnect Signals / Connections for CV 1h 16-Feb-15 07:00 AM 16-Feb-15 08:00 AM 10 II100650 Removal of CV & Install Blinds 4h 16-Feb-15 08:00 AM 16-Feb-15 12:00 PM 11 II100655 Transport CV to Work Shop 1h 16-Feb-15 12:00 PM 16-Feb-15 01:00 PM 12 II100660 Overhaul / Service CV 12h 16-Feb-15 01:00 PM 17-Feb-15 01:00 AM 13 II100665 Test Valve (Refer Documentation) 2h 17-Feb-15 01:00 AM 17-Feb-15 03:00 AM 14 II100670 Transport CV to Unit / Remove Blinds 1h 17-Feb-15 03:00 AM 17-Feb-15 04:00 AM 15 II100675 Install CV 6h 17-Feb-15 04:00 AM 17-Feb-15 10:00 AM 16 II100680 Loop Check & Stroke test 2h 17-Feb-15 10:00 AM 17-Feb-15 12:00 PM 17 II100685 Inspection by RLOC 1h 17-Feb-15 12:00 PM 17-Feb-15 01:00 PM 18 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 19 II100690 Reinsulate CV 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 20 II100695 House keeping & Close PTW 1h 01-Jan-15 07:00 AM 01-Jan-15 08:00 AM 21 R15E-999-001 RC2-32-999-10-BD-002-INST-VERIFY AND ARREST LEAKR15E-999-001 RC2-32-999-10-BD-002-INST-VERIFY AND ARREST LEAK 19h 13-Feb-15 02:00 PM 14-Feb-15 09:00 AM 22 SHUTDOWNSHUTDOWN 19h 13-Feb-15 02:00 PM 14-Feb-15 09:00 AM 23 II110545 Review JSA 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM 24 II110550 Verify LT&T and Obtain permit 2h 13-Feb-15 03:00 PM 13-Feb-15 05:00 PM 25 II110555 Disconnect signals / connections 3h 13-Feb-15 05:00 PM 13-Feb-15 08:00 PM 26 II110560 Verify Leaking area and Arrest the Leak 6h 13-Feb-15 08:00 PM 14-Feb-15 02:00 AM 27 II110565 Reconnect the signals / connections 4h 14-Feb-15 02:00 AM 14-Feb-15 06:00 AM 28 II110570 Offer for Inspection 2h 14-Feb-15 06:00 AM 14-Feb-15 08:00 AM 29 II110575 House keeping & Close PTW 1h 14-Feb-15 08:00 AM 14-Feb-15 09:00 AM 30 VHPVHP 1668h 01-Jan-15 06:00 AM 11-Mar-15 06:00 PM 31 R15E-002-004 RC2-31-002-PV-0001-CV-OVERHAUL & SERVICINGR15E-002-004 RC2-31-002-PV-0001-CV-OVERHAUL & SERVICING 992h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 32 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 33 II100000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 34 II100005 Errect Scaffolding / Remove Insulation 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM 35 SHUTDOWNSHUTDOWN 43h 09-Feb-15 07:00 PM 11-Feb-15 02:00 PM 36 II100010 Verify LT&T and Obtain permit 1h 09-Feb-15 07:00 PM 09-Feb-15 08:00 PM 37 II100015 Disconnect Signals / Connections for CV 1h 09-Feb-15 08:00 PM 09-Feb-15 09:00 PM 38 II100020 Removal of CV & Install Blinds 10h 09-Feb-15 09:00 PM 10-Feb-15 07:00 AM 39 II100025 Transport CV to Work Shop 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM 40 II100030 Overhaul / Service CV 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM 41 II100035 Test Valve (Refer Documentation) 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM 42 II100040 Transport CV to Unit / Remove Blinds 1h 10-Feb-15 10:00 PM 10-Feb-15 11:00 PM 43 II100045 Install CV 12h 10-Feb-15 11:00 PM 11-Feb-15 11:00 AM 44 II100050 Loop Check & Stroke test 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM 45 II100055 Inspection by RLOC 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM 46 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 47 II100060 Reinsulate CV / Removal of Scafflods 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 48 II100065 House keeping & Close PTW 1h 01-Jan-15 09:00 AM 01-Jan-15 10:00 AM 49 R15E-002-005 RC2-31-002-PV-0003-CV-OVERHAUL & SERVICINGR15E-002-005 RC2-31-002-PV-0003-CV-OVERHAUL & SERVICING 992h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 50 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 51 II100070 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 52 II100075 Errect Scaffolding / Remove Insulation 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM 53 SHUTDOWNSHUTDOWN 43h 09-Feb-15 07:00 PM 11-Feb-15 02:00 PM 54 II100080 Verify LT&T and Obtain permit 1h 09-Feb-15 07:00 PM 09-Feb-15 08:00 PM 55 II100085 Disconnect Signals / Connections for CV 1h 09-Feb-15 08:00 PM 09-Feb-15 09:00 PM 56 II100090 Removal of CV & Install Blinds 10h 09-Feb-15 09:00 PM 10-Feb-15 07:00 AM 57 II100095 Transport CV to Work Shop 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM 58 II100100 Overhaul / Service CV 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM 59 II100105 Test Valve (Refer Documentation) 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM 60 II100110 Transport CV to Unit / Remove Blinds 1h 10-Feb-15 10:00 PM 10-Feb-15 11:00 PM 61 II100115 Install CV 12h 10-Feb-15 11:00 PM 11-Feb-15 11:00 AM 62 II100120 Loop Check & Stroke test 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 1 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  2. 2. # Activity ID Activity Name Original Duration Start Finish 63 II100125 Inspection by RLOC 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM 64 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 65 II100130 Reinsulate CV / Removal of Scafflods 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 66 II100135 House keeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 67 R15E-108-003 RC2-32-108-36-H-108-VALVE REPLACEMENTR15E-108-003 RC2-32-108-36-H-108-VALVE REPLACEMENT 1023h 01-Jan-15 06:00 AM 12-Feb-15 09:00 PM 68 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 06:00 AM 01-Jan-15 04:00 PM 69 IM104760 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 70 IM104765 Shift valve to job location 1h 01-Jan-15 07:00 AM 01-Jan-15 08:00 AM 71 IM104770 Erect Scaffolding 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM 72 IM104775 Removal of Insulations. 4h 01-Jan-15 12:00 PM 01-Jan-15 04:00 PM 73 SHUTDOWNSHUTDOWN 111h 08-Feb-15 06:00 AM 12-Feb-15 09:00 PM 74 IM104780 Verify LT&T and Obtain PTW 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM 75 IM104785 Blinding as per blindlist (Refer ISBL Steam System LT&T 1) 0h 08-Feb-15 08:00 AM 08-Feb-15 08:00 AM 76 IM104790 Cut, remove valve & Fitup new valve 30h 08-Feb-15 08:00 AM 09-Feb-15 02:00 PM 77 IM104795 Carrout welding 24h 09-Feb-15 02:00 PM 10-Feb-15 02:00 PM 78 IM104800 NDT on weld joints (As per RAT sheet) 24h 10-Feb-15 02:00 PM 11-Feb-15 02:00 PM 79 IM104805 Carryout repair on weld, if any 10h 11-Feb-15 02:00 PM 12-Feb-15 12:00 AM 80 IM104810 Hydrotesting on weld joints 16h 12-Feb-15 12:00 AM 12-Feb-15 04:00 PM 81 IM104815 Painting on weld joints 4h 12-Feb-15 04:00 PM 12-Feb-15 08:00 PM 82 IM104820 Carryout De-Blinding (Refer ISBL Steam System LT&T 1) 0h 12-Feb-15 08:00 PM 12-Feb-15 08:00 PM 83 IM104825 Shift the removed valve for servicing 1h 12-Feb-15 08:00 PM 12-Feb-15 09:00 PM 84 POST SHUTDOWNPOST SHUTDOWN 11h 01-Jan-15 06:00 AM 01-Jan-15 05:00 PM 85 IM104830 Fix back insulation 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 86 IM104835 Remove scaffolding 4h 01-Jan-15 10:00 AM 01-Jan-15 02:00 PM 87 IM104840 Housekeeping and close PTW 2h 01-Jan-15 02:00 PM 01-Jan-15 04:00 PM 88 IM104845 Q.C. Documents Submission 1h 01-Jan-15 04:00 PM 01-Jan-15 05:00 PM 89 R15E-310-029 RC2-32-310-41-E-316-EXCH-INTER & EXTERNAL INSPR15E-310-029 RC2-32-310-41-E-316-EXCH-INTER & EXTERNAL INSP 1200h 01-Jan-15 06:00 AM 20-Feb-15 06:00 AM 90 PRE-SHUTDOWNPRE-SHUTDOWN 25h 01-Jan-15 06:00 AM 03-Jan-15 07:00 AM 91 IM110995 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 92 IM111000 Shift blinds to blinding location 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM 93 IM111005 Erect Scaffolding 15h 01-Jan-15 12:00 PM 02-Jan-15 03:00 PM 94 IM111010 Tarpaulins, barrication, sand bags setup 4h 02-Jan-15 03:00 PM 03-Jan-15 07:00 AM 95 SHUTDOWNSHUTDOWN 288h 08-Feb-15 06:00 AM 20-Feb-15 06:00 AM 96 IM111015 Purging, Flushing & Gas test, LEL checking 6h 08-Feb-15 06:00 AM 08-Feb-15 12:00 PM 97 IM111020 Verify LT&T and Obtain PTW 2h 08-Feb-15 12:00 PM 08-Feb-15 02:00 PM 98 IM111025 Drop spools & blind as per blindlist 24h 08-Feb-15 02:00 PM 09-Feb-15 02:00 PM 99 IM111030 Remove end covers 15h 09-Feb-15 02:00 PM 10-Feb-15 05:00 AM 100 IM111035 Carryout prelim. inspn. & Offer for AFI 3h 10-Feb-15 05:00 AM 10-Feb-15 08:00 AM 101 IM111040 100% hydrojetting of tube internals 90h 10-Feb-15 08:00 AM 14-Feb-15 02:00 AM 102 IM111045 Hydrojetting of tubesheet & channel covers 5h 14-Feb-15 02:00 AM 14-Feb-15 07:00 AM 103 IM111050 Carryout detailed inspn. 3h 14-Feb-15 07:00 AM 14-Feb-15 10:00 AM 104 IM111055 ECT on 347 tubes (Confirm via IRIS) 60h 14-Feb-15 10:00 AM 16-Feb-15 10:00 PM 105 IM111060 Boroscopic test & thickness monitoring 3h 16-Feb-15 10:00 PM 17-Feb-15 01:00 AM 106 IM111065 NDT of welds 3h 17-Feb-15 01:00 AM 17-Feb-15 04:00 AM 107 IM111070 Hydrostatic test on shell & tube side 12h 17-Feb-15 04:00 AM 17-Feb-15 04:00 PM 108 IM111075 Repairs & retest as per inspn. report 20h 17-Feb-15 04:00 PM 18-Feb-15 12:00 PM 109 IM111080 Final Inspection 2h 18-Feb-15 12:00 PM 18-Feb-15 02:00 PM 110 IM111085 Reinstall end covers 15h 18-Feb-15 02:00 PM 19-Feb-15 05:00 AM 111 IM111090 Reinstall spools & Deblinding 25h 19-Feb-15 05:00 AM 20-Feb-15 06:00 AM 112 POST SHUTDOWNPOST SHUTDOWN 14h 01-Jan-15 06:00 AM 02-Jan-15 08:00 AM 113 IM111095 Remove scaffolding 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 114 IM111100 Housekeeping & close PTW 2h 02-Jan-15 06:00 AM 02-Jan-15 08:00 AM 115 R15E-310-043 RC2-32-310-84-ST-301-VALVE REPLACEMENTR15E-310-043 RC2-32-310-84-ST-301-VALVE REPLACEMENT 1668h 01-Jan-15 06:00 AM 11-Mar-15 06:00 PM 116 PRE-SHUTDOWNPRE-SHUTDOWN 840h 01-Jan-15 06:00 AM 11-Mar-15 06:00 PM 117 IM105750 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 118 IM105755 Prefab. valve lifting structure as per dwg. 72h 01-Jan-15 08:00 AM 07-Jan-15 08:00 AM 119 IM105760 Inspection of lifting structure 12h 07-Jan-15 08:00 AM 08-Jan-15 08:00 AM 120 IM105765 Painting of lifting structure 24h 08-Jan-15 08:00 AM 10-Jan-15 08:00 AM 121 IM105770 Prefab. steam blow piping as per dwg. 144h 10-Jan-15 08:00 AM 22-Jan-15 08:00 AM 122 IM105775 Inspection of weld joints 24h 22-Jan-15 08:00 AM 24-Jan-15 08:00 AM 123 IM105780 Shift all prefab. items to job location 6h 24-Jan-15 08:00 AM 24-Jan-15 02:00 PM 124 IM105785 Shift new valve to job area 4h 24-Jan-15 02:00 PM 24-Jan-15 06:00 PM 125 IM105790 Shift blinds to blinding location 24h 25-Jan-15 06:00 AM 26-Jan-15 06:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 2 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  3. 3. # Activity ID Activity Name Original Duration Start Finish 126 IM105795 Erect scaffolding, wherever reqd. 60h 27-Jan-15 06:00 AM 31-Jan-15 06:00 PM 127 IM105800 Removal of Insulations, wherever reqd. 12h 01-Feb-15 06:00 AM 01-Feb-15 06:00 PM 128 IM105805 Fix the valve lifting structure as per dwg. 24h 02-Feb-15 06:00 AM 03-Feb-15 06:00 PM 129 IM105810 Load testing of lifting structure 12h 04-Feb-15 06:00 AM 04-Feb-15 06:00 PM 130 IM105815 Open the grating at job area 4h 05-Feb-15 06:00 AM 05-Feb-15 10:00 AM 131 IM105870 Erect scaffolding to drop ESV's 6h 11-Mar-15 10:00 AM 11-Mar-15 04:00 PM 132 IM105875 Remove insulation from ESV's 2h 11-Mar-15 04:00 PM 11-Mar-15 06:00 PM 133 SHUTDOWNSHUTDOWN 397h 08-Feb-15 12:00 AM 24-Feb-15 01:00 PM 134 IM105820 Verify LT&T and Obtain PTW 2h 08-Feb-15 12:00 AM 08-Feb-15 02:00 AM 135 IM105825 Blinding as per blindlist. (ISBL Steam System LT&T 1) 24h 08-Feb-15 02:00 AM 09-Feb-15 02:00 AM 136 IM105830 Crane mobilization at job area 4h 09-Feb-15 02:00 AM 09-Feb-15 06:00 AM 137 IM105835 Unbolt & drop yoke and bonnet 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM 138 IM105840 Remove stem & wedge 4h 09-Feb-15 10:00 AM 09-Feb-15 02:00 PM 139 IM105845 Initial visual inspn. of valve internals 1h 09-Feb-15 02:00 PM 09-Feb-15 03:00 PM 140 IM105850 In-situ repair with new spares 120h 09-Feb-15 03:00 PM 14-Feb-15 03:00 PM 141 IM105855 Final inspection of valve 2h 14-Feb-15 03:00 PM 14-Feb-15 05:00 PM 142 IM105860 Box-up stem & wedge 8h 14-Feb-15 05:00 PM 15-Feb-15 01:00 AM 143 IM105865 Box-up bonnet & yoke with gearbox 8h 15-Feb-15 01:00 AM 15-Feb-15 09:00 AM 144 IM105880 Remove elect. connections from ESV's 1h 08-Feb-15 02:00 AM 08-Feb-15 03:00 AM 145 IM105885 Drop ESV-1934 & ESV-1935 6h 08-Feb-15 03:00 AM 08-Feb-15 09:00 AM 146 IM105890 Fix the steam blow piping as per dwg. 10h 21-Feb-15 11:00 PM 22-Feb-15 09:00 AM 147 IM105895 Cut, remove & drop the valve 24h 09-Feb-15 03:00 PM 10-Feb-15 03:00 PM 148 IM105900 Edge prep. & Fit up new valve 24h 10-Feb-15 03:00 PM 11-Feb-15 03:00 PM 149 IM105905 Carryout preheating & welding 96h 11-Feb-15 03:00 PM 15-Feb-15 03:00 PM 150 IM105910 PWHT on weld joints 20h 15-Feb-15 03:00 PM 16-Feb-15 11:00 AM 151 IM105915 RT on weld joints 28h 16-Feb-15 11:00 AM 17-Feb-15 03:00 PM 152 IM105920 Carryout repair on weld, if any 20h 17-Feb-15 03:00 PM 18-Feb-15 11:00 AM 153 IM105925 PWHT on weld joints after repair 20h 18-Feb-15 11:00 AM 19-Feb-15 07:00 AM 154 IM105930 RT on weld joints after repair 28h 19-Feb-15 07:00 AM 20-Feb-15 11:00 AM 155 IM105935 Hydrotesting on weld joints 36h 20-Feb-15 11:00 AM 21-Feb-15 11:00 PM 156 IM105940 Carryout Steam blow-out 24h 22-Feb-15 09:00 AM 23-Feb-15 09:00 AM 157 IM105945 Remove steam blow-out piping 4h 23-Feb-15 09:00 AM 23-Feb-15 01:00 PM 158 IM105950 Fix back ESV-1934 & ESV-1935 6h 23-Feb-15 01:00 PM 23-Feb-15 07:00 PM 159 IM105955 Provide elect. connections to ESV's 1h 23-Feb-15 07:00 PM 23-Feb-15 08:00 PM 160 IM105960 Fix back insulation for ESV's 1h 23-Feb-15 08:00 PM 23-Feb-15 09:00 PM 161 IM105965 Remove scaffolding from ESV's 1h 23-Feb-15 09:00 PM 23-Feb-15 10:00 PM 162 IM105970 Carryout De-Blinding (ISBL Steam System LT&T 1) 24h 23-Feb-15 01:00 PM 24-Feb-15 01:00 PM 163 IM105975 Painting on weld joints 1h 21-Feb-15 11:00 PM 22-Feb-15 12:00 AM 164 POST SHUTDOWNPOST SHUTDOWN 49h 01-Jan-15 06:00 AM 05-Jan-15 07:00 AM 165 IM105980 Fix back the insulation 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 166 IM105985 Refix grating on job area 1h 01-Jan-15 02:00 PM 01-Jan-15 03:00 PM 167 IM105990 Remove scaffolding 36h 01-Jan-15 03:00 PM 04-Jan-15 03:00 PM 168 IM105995 Housekeeping and close PTW 3h 04-Jan-15 03:00 PM 04-Jan-15 06:00 PM 169 IM106000 Q.C. Documents Submission 1h 05-Jan-15 06:00 AM 05-Jan-15 07:00 AM 170 R15E-310-044 RC2-32-310-84-ST-301-CGC TURBINE MINOR OHR15E-310-044 RC2-32-310-84-ST-301-CGC TURBINE MINOR OH 1188h 01-Jan-15 06:00 AM 19-Feb-15 06:00 PM 171 PRE-SHUTDOWNPRE-SHUTDOWN 44h 01-Jan-15 06:00 AM 04-Jan-15 02:00 PM 172 IM117625 Conduct JSA, Rigging plan study 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 173 IM117630 Erect scaffold for blinding 8h 01-Jan-15 02:00 PM 02-Jan-15 10:00 AM 174 IM117635 Erect scaffold for work platform 8h 02-Jan-15 10:00 AM 02-Jan-15 06:00 PM 175 IM117640 Remove insulation, wherever reqd. 8h 03-Jan-15 06:00 AM 03-Jan-15 02:00 PM 176 IM117645 Shift blinds, tools & tackles to job site 12h 03-Jan-15 02:00 PM 04-Jan-15 02:00 PM 177 SHUTDOWNSHUTDOWN 276h 08-Feb-15 06:00 AM 19-Feb-15 06:00 PM 178 IM117650 Verify LT&T and Obtain PTW 4h 08-Feb-15 06:00 AM 08-Feb-15 10:00 AM 179 IM117655 Blinding as per blindlist 24h 08-Feb-15 10:00 AM 09-Feb-15 10:00 AM 180 IM117660 Remove necessary pipes & inst. lines 12h 09-Feb-15 10:00 AM 09-Feb-15 10:00 PM 181 IM117665 Remove NDE brg. housing top cover 4h 09-Feb-15 10:00 PM 10-Feb-15 02:00 AM 182 IM117670 Remove NDE brg. housing 4h 10-Feb-15 02:00 AM 10-Feb-15 06:00 AM 183 IM117675 Inspect NDE journal & thrust brg. 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM 184 IM117680 Fix back NDE brg. housing 4h 10-Feb-15 10:00 AM 10-Feb-15 02:00 PM 185 IM117685 Remove DE brg. housing 4h 10-Feb-15 02:00 PM 10-Feb-15 06:00 PM 186 IM117690 Inspect DE journal & thrust brg. 4h 10-Feb-15 06:00 PM 10-Feb-15 10:00 PM 187 IM117695 Fix back DE brg. housing 4h 10-Feb-15 10:00 PM 11-Feb-15 02:00 AM 188 IM117700 Inspect seal rings 8h 11-Feb-15 02:00 AM 11-Feb-15 10:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 3 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  4. 4. # Activity ID Activity Name Original Duration Start Finish 189 IM117705 Remove ESV 8h 11-Feb-15 10:00 AM 11-Feb-15 06:00 PM 190 IM117710 Remove & Inspect ESV strainer 6h 11-Feb-15 06:00 PM 12-Feb-15 12:00 AM 191 IM117715 Fix back ESV strainer 4h 12-Feb-15 12:00 AM 12-Feb-15 04:00 AM 192 IM117720 Reinstall ESV 8h 12-Feb-15 04:00 AM 12-Feb-15 12:00 PM 193 IM117725 Check bypass & b.fly valves 6h 12-Feb-15 12:00 PM 12-Feb-15 06:00 PM 194 IM117730 Replace parts of valves, if reqd. 6h 12-Feb-15 06:00 PM 13-Feb-15 12:00 AM 195 IM117735 Check & Inspect extraction, bleed S/O valves 12h 13-Feb-15 12:00 AM 13-Feb-15 12:00 PM 196 IM117740 Clean & Inspect Double servo cyl. 12h 13-Feb-15 12:00 PM 14-Feb-15 12:00 AM 197 IM117745 Clean & Inspect the Pilot valves 12h 14-Feb-15 12:00 AM 14-Feb-15 12:00 PM 198 IM117750 Clean & Inspect the Operating cyl. 12h 14-Feb-15 12:00 PM 15-Feb-15 12:00 AM 199 IM117755 Clean & Inspect pinion/wheel gear brg. 12h 15-Feb-15 12:00 AM 15-Feb-15 12:00 PM 200 IM117760 Clean & Inspect governing valve links, bushes 12h 15-Feb-15 12:00 PM 16-Feb-15 12:00 AM 201 IM117765 Recharge nitrogen for accumulator 12h 16-Feb-15 12:00 AM 16-Feb-15 12:00 PM 202 IM117770 Fix back auxiliary pipings 24h 16-Feb-15 12:00 PM 17-Feb-15 12:00 PM 203 IM117775 Fix back instrument connections 6h 17-Feb-15 12:00 PM 17-Feb-15 06:00 PM 204 IM117780 Fix back turbine insulation 24h 17-Feb-15 06:00 PM 18-Feb-15 06:00 PM 205 IM117785 Carryout De-Blinding 24h 18-Feb-15 06:00 PM 19-Feb-15 06:00 PM 206 POST SHUTDOWNPOST SHUTDOWN 44h 01-Jan-15 06:00 AM 04-Jan-15 02:00 PM 207 IM117790 Fix back insulation 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 208 IM117795 Remove scaffolding 12h 01-Jan-15 02:00 PM 02-Jan-15 02:00 PM 209 IM117800 Housekeeping & Close PTW 24h 02-Jan-15 02:00 PM 04-Jan-15 02:00 PM 210 R15E-310-045 RC2-32-310-84-ST-301-ATTEND CGC ST FLANGE LEAKR15E-310-045 RC2-32-310-84-ST-301-ATTEND CGC ST FLANGE LEAK 540h 01-Jan-15 06:00 AM 14-Feb-15 06:00 PM 211 PRE-SHUTDOWNPRE-SHUTDOWN 14h 01-Jan-15 06:00 AM 02-Jan-15 08:00 AM 212 IM117840 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 213 IM117845 Erect scaffolding, wherever reqd. 8h 01-Jan-15 08:00 AM 01-Jan-15 04:00 PM 214 IM117850 Remove insulation, wherever reqd. 4h 01-Jan-15 04:00 PM 02-Jan-15 08:00 AM 215 SHUTDOWNSHUTDOWN 26h 12-Feb-15 04:00 PM 14-Feb-15 06:00 PM 216 IM117855 Verify LT&T and Obtain PTW 2h 12-Feb-15 04:00 PM 12-Feb-15 06:00 PM 217 IM117860 Open flanges & Clean flange faces 12h 13-Feb-15 06:00 AM 13-Feb-15 06:00 PM 218 IM117865 Repair / Renew gaskets & Boxup flanges 12h 14-Feb-15 06:00 AM 14-Feb-15 06:00 PM 219 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 06:00 AM 01-Jan-15 04:00 PM 220 IM117870 Fix back insulation 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 221 IM117875 Remove scaffolding 4h 01-Jan-15 10:00 AM 01-Jan-15 02:00 PM 222 IM117880 Housekeeping & Close PTW 2h 01-Jan-15 02:00 PM 01-Jan-15 04:00 PM 223 R15E-310-047 RC2-32-310-93-V-0050B-VALVE REPLACEMENTR15E-310-047 RC2-32-310-93-V-0050B-VALVE REPLACEMENT 468h 01-Jan-15 06:00 AM 09-Feb-15 06:00 AM 224 PRE-SHUTDOWNPRE-SHUTDOWN 13h 01-Jan-15 06:00 AM 02-Jan-15 07:00 AM 225 IM106005 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 226 IM106010 Hydrotest new valve & Shift to job area 6h 01-Jan-15 07:00 AM 01-Jan-15 01:00 PM 227 IM106015 Erect scaffolding 4h 01-Jan-15 01:00 PM 01-Jan-15 05:00 PM 228 IM106020 Removal of Insulations. 2h 01-Jan-15 05:00 PM 02-Jan-15 07:00 AM 229 SHUTDOWNSHUTDOWN 12h 08-Feb-15 06:00 AM 09-Feb-15 06:00 AM 230 IM106025 Verify LT&T and Obtain PTW 3h 08-Feb-15 06:00 AM 08-Feb-15 09:00 AM 231 IM106030 Blinding as per blindlist (Refer ISBL Steam System LT&T 1) 0h 08-Feb-15 09:00 AM 08-Feb-15 09:00 AM 232 IM106035 Unbolt & drop the valve 4h 08-Feb-15 09:00 AM 08-Feb-15 01:00 PM 233 IM106040 Fix the new valve 4h 08-Feb-15 01:00 PM 08-Feb-15 05:00 PM 234 IM106045 Shift the removed valve for servicing 1h 08-Feb-15 05:00 PM 08-Feb-15 06:00 PM 235 IM106050 Carryout De-Blinding (Refer ISBL Steam System LT&T 1) 0h 09-Feb-15 06:00 AM 09-Feb-15 06:00 AM 236 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 237 IM106055 Fix back the insulation 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 238 IM106060 Remove scaffolding 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 239 IM106065 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 240 R15E-310-050 RC2-32-310-93-V-1712-CALIBRATIONR15E-310-050 RC2-32-310-93-V-1712-CALIBRATION 958h 01-Jan-15 06:00 AM 10-Feb-15 04:00 AM 241 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 06:00 AM 01-Jan-15 01:00 PM 242 IM118270 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 243 IM118275 Erect Scaffolding & load brg. 6h 01-Jan-15 07:00 AM 01-Jan-15 01:00 PM 244 SHUTDOWNSHUTDOWN 46h 08-Feb-15 06:00 AM 10-Feb-15 04:00 AM 245 IM118280 Verify LT&T and Obtain PTW 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM 246 IM118285 Remove PRV & Provide end blind 8h 08-Feb-15 08:00 AM 08-Feb-15 04:00 PM 247 IM118290 Send PRV for repair & calibration 2h 08-Feb-15 04:00 PM 08-Feb-15 06:00 PM 248 IM118295 Repair & Calibrate PRV 24h 08-Feb-15 06:00 PM 09-Feb-15 06:00 PM 249 IM118300 Receive & Shift PRV back to site 2h 09-Feb-15 06:00 PM 09-Feb-15 08:00 PM 250 IM118305 Remove end blind, Install back PRV 8h 09-Feb-15 08:00 PM 10-Feb-15 04:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 4 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  5. 5. # Activity ID Activity Name Original Duration Start Finish 251 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 06:00 AM 01-Jan-15 12:00 PM 252 IM118310 Remove scaffolding 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 253 IM118315 Housekeeping & Close PTW 1h 01-Jan-15 11:00 AM 01-Jan-15 12:00 PM 254 R15E-310-051 RC2-32-310-93-V-1713-CALIBRATIONR15E-310-051 RC2-32-310-93-V-1713-CALIBRATION 958h 01-Jan-15 06:00 AM 10-Feb-15 04:00 AM 255 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 256 IM118320 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 257 IM118325 Erect Scaffolding & load brg. 6h 01-Jan-15 08:00 AM 01-Jan-15 02:00 PM 258 SHUTDOWNSHUTDOWN 46h 08-Feb-15 06:00 AM 10-Feb-15 04:00 AM 259 IM118330 Verify LT&T and Obtain PTW 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM 260 IM118335 Remove PRV & Provide end blind 8h 08-Feb-15 08:00 AM 08-Feb-15 04:00 PM 261 IM118340 Send PRV for repair & calibration 2h 08-Feb-15 04:00 PM 08-Feb-15 06:00 PM 262 IM118345 Repair & Calibrate PRV 24h 08-Feb-15 06:00 PM 09-Feb-15 06:00 PM 263 IM118350 Receive & Shift PRV back to site 2h 09-Feb-15 06:00 PM 09-Feb-15 08:00 PM 264 IM118355 Remove end blind, Install back PRV 8h 09-Feb-15 08:00 PM 10-Feb-15 04:00 AM 265 POST SHUTDOWNPOST SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 266 IM118360 Remove scaffolding 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 267 IM118365 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 268 R15E-310-074 RC2-32-310-LT-1710A-INST-INSPECTION AND CLEANINGR15E-310-074 RC2-32-310-LT-1710A-INST-INSPECTION AND CLEANING 20h 20-Feb-15 04:00 PM 21-Feb-15 12:00 PM 269 SHUTDOWNSHUTDOWN 20h 20-Feb-15 04:00 PM 21-Feb-15 12:00 PM 270 II108525 Review JSA 1h 20-Feb-15 04:00 PM 20-Feb-15 05:00 PM 271 II108530 Verify LT&T and Obtain permit 2h 20-Feb-15 05:00 PM 20-Feb-15 07:00 PM 272 II108535 Disconnect Conn. / Power Supply 24V DC 2h 20-Feb-15 07:00 PM 20-Feb-15 09:00 PM 273 II108540 Remove the LT 2h 20-Feb-15 09:00 PM 20-Feb-15 11:00 PM 274 II108545 Cleaning of LT Diaphragm Flanges 3h 20-Feb-15 11:00 PM 21-Feb-15 02:00 AM 275 II108550 Calibrate the LT 2h 21-Feb-15 02:00 AM 21-Feb-15 04:00 AM 276 II108555 Fix back the LT 2h 21-Feb-15 04:00 AM 21-Feb-15 06:00 AM 277 II108560 Re Connect Conn. / Power Supply 24V DC 2h 21-Feb-15 06:00 AM 21-Feb-15 08:00 AM 278 II108565 Perform Function Test 2h 21-Feb-15 08:00 AM 21-Feb-15 10:00 AM 279 II108570 Inspection by RLOC 1h 21-Feb-15 10:00 AM 21-Feb-15 11:00 AM 280 II108575 House keeping & Close PTW 1h 21-Feb-15 11:00 AM 21-Feb-15 12:00 PM 281 R15E-310-075 RC2-32-310-LT-1710B-INST-INSPECTION AND CLEANINGR15E-310-075 RC2-32-310-LT-1710B-INST-INSPECTION AND CLEANING 20h 15-Feb-15 05:00 AM 16-Feb-15 01:00 AM 282 SHUTDOWNSHUTDOWN 20h 15-Feb-15 05:00 AM 16-Feb-15 01:00 AM 283 II108580 Review JSA 1h 15-Feb-15 05:00 AM 15-Feb-15 06:00 AM 284 II108585 Verify LT&T and Obtain permit 2h 15-Feb-15 06:00 AM 15-Feb-15 08:00 AM 285 II108590 Disconnect Conn. / Power Supply 24V DC 2h 15-Feb-15 08:00 AM 15-Feb-15 10:00 AM 286 II108595 Remove the LT 2h 15-Feb-15 10:00 AM 15-Feb-15 12:00 PM 287 II108600 Cleaning of LT Diaphragm Flanges 3h 15-Feb-15 12:00 PM 15-Feb-15 03:00 PM 288 II108605 Calibrate the LT 2h 15-Feb-15 03:00 PM 15-Feb-15 05:00 PM 289 II108610 Fix back the LT 2h 15-Feb-15 05:00 PM 15-Feb-15 07:00 PM 290 II108615 Re Connect Conn. / Power Supply 24V DC 2h 15-Feb-15 07:00 PM 15-Feb-15 09:00 PM 291 II108620 Perform Function Test 2h 15-Feb-15 09:00 PM 15-Feb-15 11:00 PM 292 II108625 Inspection by RLOC 1h 15-Feb-15 11:00 PM 16-Feb-15 12:00 AM 293 II108630 House keeping & Close PTW 1h 16-Feb-15 12:00 AM 16-Feb-15 01:00 AM 294 R15E-310-076 RC2-32-310-LT-1729A-INST-INSPECTION AND CLEANINGR15E-310-076 RC2-32-310-LT-1729A-INST-INSPECTION AND CLEANING 20h 16-Feb-15 01:00 AM 16-Feb-15 09:00 PM 295 SHUTDOWNSHUTDOWN 20h 16-Feb-15 01:00 AM 16-Feb-15 09:00 PM 296 II108635 Review JSA 1h 16-Feb-15 01:00 AM 16-Feb-15 02:00 AM 297 II108640 Verify LT&T and Obtain permit 2h 16-Feb-15 02:00 AM 16-Feb-15 04:00 AM 298 II108645 Disconnect Conn. / Power Supply 24V DC 2h 16-Feb-15 04:00 AM 16-Feb-15 06:00 AM 299 II108650 Remove the LT 2h 16-Feb-15 06:00 AM 16-Feb-15 08:00 AM 300 II108655 Cleaning of LT Diaphragm Flanges 3h 16-Feb-15 08:00 AM 16-Feb-15 11:00 AM 301 II108660 Calibrate the LT 2h 16-Feb-15 11:00 AM 16-Feb-15 01:00 PM 302 II108665 Fix back the LT 2h 16-Feb-15 01:00 PM 16-Feb-15 03:00 PM 303 II108670 Re Connect Conn. / Power Supply 24V DC 2h 16-Feb-15 03:00 PM 16-Feb-15 05:00 PM 304 II108675 Perform Function Test 2h 16-Feb-15 05:00 PM 16-Feb-15 07:00 PM 305 II108680 Inspection by RLOC 1h 16-Feb-15 07:00 PM 16-Feb-15 08:00 PM 306 II108685 House keeping & Close PTW 1h 16-Feb-15 08:00 PM 16-Feb-15 09:00 PM 307 R15E-310-077 RC2-32-310-LT-1729B-INST-INSPECTION AND CLEANINGR15E-310-077 RC2-32-310-LT-1729B-INST-INSPECTION AND CLEANING 20h 16-Feb-15 09:00 PM 17-Feb-15 05:00 PM 308 SHUTDOWNSHUTDOWN 20h 16-Feb-15 09:00 PM 17-Feb-15 05:00 PM 309 II108690 Review JSA 1h 16-Feb-15 09:00 PM 16-Feb-15 10:00 PM 310 II108695 Verify LT&T and Obtain permit 2h 16-Feb-15 10:00 PM 17-Feb-15 12:00 AM 311 II108700 Disconnect Conn. / Power Supply 24V DC 2h 17-Feb-15 12:00 AM 17-Feb-15 02:00 AM 312 II108705 Remove the LT 2h 17-Feb-15 02:00 AM 17-Feb-15 04:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 5 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  6. 6. # Activity ID Activity Name Original Duration Start Finish 313 II108710 Cleaning of LT Diaphragm Flanges 3h 17-Feb-15 04:00 AM 17-Feb-15 07:00 AM 314 II108715 Calibrate the LT 2h 17-Feb-15 07:00 AM 17-Feb-15 09:00 AM 315 II108720 Fix back the LT 2h 17-Feb-15 09:00 AM 17-Feb-15 11:00 AM 316 II108725 Re Connect Conn. / Power Supply 24V DC 2h 17-Feb-15 11:00 AM 17-Feb-15 01:00 PM 317 II108730 Perform Function Test 2h 17-Feb-15 01:00 PM 17-Feb-15 03:00 PM 318 II108735 Inspection by RLOC 1h 17-Feb-15 03:00 PM 17-Feb-15 04:00 PM 319 II108740 House keeping & Close PTW 1h 17-Feb-15 04:00 PM 17-Feb-15 05:00 PM 320 R15E-310-078 RC2-32-310-LT-1729C-INST-INSPECTION AND CLEANINGR15E-310-078 RC2-32-310-LT-1729C-INST-INSPECTION AND CLEANING 20h 17-Feb-15 05:00 PM 18-Feb-15 01:00 PM 321 SHUTDOWNSHUTDOWN 20h 17-Feb-15 05:00 PM 18-Feb-15 01:00 PM 322 II108745 Review JSA 1h 17-Feb-15 05:00 PM 17-Feb-15 06:00 PM 323 II108750 Verify LT&T and Obtain permit 2h 17-Feb-15 06:00 PM 17-Feb-15 08:00 PM 324 II108755 Disconnect Conn. / Power Supply 24V DC 2h 17-Feb-15 08:00 PM 17-Feb-15 10:00 PM 325 II108760 Remove the LT 2h 17-Feb-15 10:00 PM 18-Feb-15 12:00 AM 326 II108765 Cleaning of LT Diaphragm Flanges 3h 18-Feb-15 12:00 AM 18-Feb-15 03:00 AM 327 II108770 Calibrate the LT 2h 18-Feb-15 03:00 AM 18-Feb-15 05:00 AM 328 II108775 Fix back the LT 2h 18-Feb-15 05:00 AM 18-Feb-15 07:00 AM 329 II108780 Re Connect Conn. / Power Supply 24V DC 2h 18-Feb-15 07:00 AM 18-Feb-15 09:00 AM 330 II108785 Perform Function Test 2h 18-Feb-15 09:00 AM 18-Feb-15 11:00 AM 331 II108790 Inspection by RLOC 1h 18-Feb-15 11:00 AM 18-Feb-15 12:00 PM 332 II108795 House keeping & Close PTW 1h 18-Feb-15 12:00 PM 18-Feb-15 01:00 PM 333 R15E-310-122 RC2-32-310-93-V-0050 - PRV REPLACEMENTR15E-310-122 RC2-32-310-93-V-0050 - PRV REPLACEMENT 524h 01-Jan-15 06:00 AM 13-Feb-15 02:00 PM 334 PRE-SHUTDOWNPRE-SHUTDOWN 46h 01-Jan-15 06:00 AM 04-Jan-15 04:00 PM 335 IM109075 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 336 IM109080 Hydrotest new valves & Shift to job area 24h 01-Jan-15 08:00 AM 03-Jan-15 08:00 AM 337 IM109085 Erect Scaffolding 12h 03-Jan-15 08:00 AM 04-Jan-15 08:00 AM 338 IM109090 Removal of Insulations. 8h 04-Jan-15 08:00 AM 04-Jan-15 04:00 PM 339 SHUTDOWNSHUTDOWN 58h 08-Feb-15 04:00 PM 13-Feb-15 02:00 PM 340 IM109095 Verify LT&T & Obtain PTW 4h 08-Feb-15 04:00 PM 09-Feb-15 08:00 AM 341 IM109100 Blinding as per blindlist. 0h 09-Feb-15 08:00 AM 09-Feb-15 08:00 AM 342 IM109105 Unbolt & drop the valves 24h 09-Feb-15 08:00 AM 11-Feb-15 08:00 AM 343 IM109110 Fix the new valves 24h 11-Feb-15 08:00 AM 13-Feb-15 08:00 AM 344 IM109115 Shift the removed valves for servicing 6h 13-Feb-15 08:00 AM 13-Feb-15 02:00 PM 345 IM109120 Carryout De-Blinding 0h 13-Feb-15 02:00 PM 13-Feb-15 02:00 PM 346 POST SHUTDOWNPOST SHUTDOWN 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 347 IM109125 Remove scaffolding 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 348 IM109130 Fix back insulation 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 349 IM109135 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 350 DRYERSDRYERS 1398h 01-Jan-15 06:00 AM 28-Feb-15 12:00 PM 351 R15E-320-001 RC2-32-320-25-D-301A-MIDEA REPLACEMENTR15E-320-001 RC2-32-320-25-D-301A-MIDEA REPLACEMENT 1184h 01-Jan-15 06:00 AM 19-Feb-15 02:00 PM 352 PRE-SHUTDOWNPRE-SHUTDOWN 74h 01-Jan-15 06:00 AM 07-Jan-15 08:00 AM 353 IM101095 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 354 IM101100 Erect Scaffolding 24h 01-Jan-15 08:00 AM 03-Jan-15 08:00 AM 355 IM101105 Remove Insulation 48h 03-Jan-15 08:00 AM 07-Jan-15 08:00 AM 356 SHUTDOWNSHUTDOWN 296h 07-Feb-15 06:00 AM 19-Feb-15 02:00 PM 357 IM101110 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 358 IM101115 Mechanical Isolation & Blinding 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM 359 IM101120 Manway Opening 6h 07-Feb-15 06:00 PM 08-Feb-15 12:00 AM 360 IM101125 Removal of Dessicants as per Approved Method of Statement 60h 08-Feb-15 12:00 AM 10-Feb-15 12:00 PM 361 IM101130 Loading the Dessicants as per Approved Method of Statement 60h 10-Feb-15 12:00 PM 13-Feb-15 12:00 AM 362 IM101135 Top Manway Box-up 6h 13-Feb-15 12:00 AM 13-Feb-15 06:00 AM 363 IM101140 De-Blinding 8h 13-Feb-15 06:00 AM 13-Feb-15 02:00 PM 364 IM101145 Reinstall insulations 144h 13-Feb-15 02:00 PM 19-Feb-15 02:00 PM 365 POST SHUTDOWNPOST SHUTDOWN 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 366 IM101150 Remove Scaffolding 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 367 IM101155 Carry out House keeping 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 368 IM101160 Close Work permit 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 369 R15E-320-002 RC2-32-320-25-D-301A-TSA PAINTINGR15E-320-002 RC2-32-320-25-D-301A-TSA PAINTING 1134h 01-Jan-15 06:00 AM 17-Feb-15 12:00 PM 370 PRE-SHUTDOWNPRE-SHUTDOWN 32h 01-Jan-15 06:00 AM 03-Jan-15 02:00 PM 371 IM101165 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 372 IM101170 Erect Scaffolding for Piping - TSAPainting 12h 01-Jan-15 08:00 AM 02-Jan-15 08:00 AM 373 IM101175 Remove Insulation for Piping TSA Painting 18h 02-Jan-15 08:00 AM 03-Jan-15 02:00 PM 374 SHUTDOWNSHUTDOWN 246h 07-Feb-15 06:00 AM 17-Feb-15 12:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 6 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  7. 7. # Activity ID Activity Name Original Duration Start Finish 375 IM101180 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 376 IM101185 Obtain Confined space permit 2h 07-Feb-15 10:00 AM 07-Feb-15 12:00 PM 377 IM101190 Removal of Screen Mesh,Hold down & Support Grids 12h 07-Feb-15 12:00 PM 08-Feb-15 12:00 AM 378 IM101195 Erect Internal Scaffolding 8h 08-Feb-15 12:00 AM 08-Feb-15 08:00 AM 379 IM101200 Preliminary Inspection 6h 08-Feb-15 08:00 AM 08-Feb-15 02:00 PM 380 IM101205 Cleaning & Repair & Installation of Meshes and Grids 30h 08-Feb-15 02:00 PM 09-Feb-15 08:00 PM 381 IM101210 Remove Internal Scaffolding 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM 382 IM101215 Final Inspection 6h 10-Feb-15 12:00 AM 10-Feb-15 06:00 AM 383 IM101220 Side Manway Box-up 6h 10-Feb-15 06:00 AM 10-Feb-15 12:00 PM 384 IM101225 TSA Painting on Equipment and Regeneraton Looping Piping 168h 10-Feb-15 12:00 PM 17-Feb-15 12:00 PM 385 POST SHUTDOWNPOST SHUTDOWN 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 386 IM101230 Reinstall insulations 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 387 IM101235 Remove Scaffolding 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 388 IM101240 Carry out House keeping 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 389 IM101245 Close Work permit 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 390 R15E-320-003 RC2-32-320-25-D-301B-MIDEA REPLACEMENTR15E-320-003 RC2-32-320-25-D-301B-MIDEA REPLACEMENT 1184h 01-Jan-15 06:00 AM 19-Feb-15 02:00 PM 391 PRE-SHUTDOWNPRE-SHUTDOWN 74h 01-Jan-15 06:00 AM 07-Jan-15 08:00 AM 392 IM101250 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 393 IM101255 Erect Scaffolding 24h 01-Jan-15 08:00 AM 03-Jan-15 08:00 AM 394 IM101260 Remove Insulation 48h 03-Jan-15 08:00 AM 07-Jan-15 08:00 AM 395 SHUTDOWNSHUTDOWN 296h 07-Feb-15 06:00 AM 19-Feb-15 02:00 PM 396 IM101265 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 397 IM101270 Mechanical Isolation & Blinding 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM 398 IM101275 Manway Opening 6h 07-Feb-15 06:00 PM 08-Feb-15 12:00 AM 399 IM101280 Removal of Dessicants as per Approved Method of Statement 60h 08-Feb-15 12:00 AM 10-Feb-15 12:00 PM 400 IM101285 Loading the Dessicants as per Approved Method of Statement 60h 10-Feb-15 12:00 PM 13-Feb-15 12:00 AM 401 IM101290 Top Manway Box-up 6h 13-Feb-15 12:00 AM 13-Feb-15 06:00 AM 402 IM101295 De-Blinding 8h 13-Feb-15 06:00 AM 13-Feb-15 02:00 PM 403 IM101300 Reinstall insulations 144h 13-Feb-15 02:00 PM 19-Feb-15 02:00 PM 404 POST SHUTDOWNPOST SHUTDOWN 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 405 IM101305 Remove Scaffolding 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 406 IM101310 Carry out House keeping 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 407 IM101315 Close Work permit 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 408 R15E-320-004 RC2-32-320-25-D-301B-TSA PAINTINGR15E-320-004 RC2-32-320-25-D-301B-TSA PAINTING 1134h 01-Jan-15 06:00 AM 17-Feb-15 12:00 PM 409 PRE-SHUTDOWNPRE-SHUTDOWN 32h 01-Jan-15 06:00 AM 03-Jan-15 02:00 PM 410 IM101320 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 411 IM101325 Erect Scaffolding for Piping - TSAPainting 12h 01-Jan-15 08:00 AM 02-Jan-15 08:00 AM 412 IM101330 Remove Insulation for Piping TSA Painting 18h 02-Jan-15 08:00 AM 03-Jan-15 02:00 PM 413 SHUTDOWNSHUTDOWN 246h 07-Feb-15 06:00 AM 17-Feb-15 12:00 PM 414 IM101335 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 415 IM101340 Obtain Confined space permit 2h 07-Feb-15 10:00 AM 07-Feb-15 12:00 PM 416 IM101345 Removal of Screen Mesh,Hold down & Support Grids 12h 07-Feb-15 12:00 PM 08-Feb-15 12:00 AM 417 IM101350 Erect Internal Scaffolding 8h 08-Feb-15 12:00 AM 08-Feb-15 08:00 AM 418 IM101355 Preliminary Inspection 6h 08-Feb-15 08:00 AM 08-Feb-15 02:00 PM 419 IM101360 Cleaning & Repair & Installation of Meshes and Grids 30h 08-Feb-15 02:00 PM 09-Feb-15 08:00 PM 420 IM101365 Remove Internal Scaffolding 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM 421 IM101370 Final Inspection 6h 10-Feb-15 12:00 AM 10-Feb-15 06:00 AM 422 IM101375 Side Manway Box-up 6h 10-Feb-15 06:00 AM 10-Feb-15 12:00 PM 423 IM101380 TSA Painting on Equipment and Regeneraton Looping Piping 168h 10-Feb-15 12:00 PM 17-Feb-15 12:00 PM 424 POST SHUTDOWNPOST SHUTDOWN 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 425 IM101385 Reinstall insulations 18h 01-Jan-15 06:00 AM 02-Jan-15 12:00 PM 426 IM101390 Remove Scaffolding 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 427 IM101395 Carry out House keeping 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 428 IM101400 Close Work permit 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 429 R15E-320-005 RC2-32-320-35-F-312-INTER INSP & CLEANINGR15E-320-005 RC2-32-320-35-F-312-INTER INSP & CLEANING 702h 01-Jan-15 06:00 AM 28-Feb-15 12:00 PM 430 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 06:00 AM 01-Jan-15 04:00 PM 431 IM115525 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 432 IM115530 Erect scaffolding, wherever reqd. 8h 01-Jan-15 08:00 AM 01-Jan-15 04:00 PM 433 SHUTDOWNSHUTDOWN 64h 23-Feb-15 08:00 AM 28-Feb-15 12:00 PM 434 IM115535 Verify LT&T and Obtain PTW 2h 23-Feb-15 08:00 AM 23-Feb-15 10:00 AM 435 IM115540 Drop top spool & blind as per blindlist 8h 23-Feb-15 10:00 AM 23-Feb-15 06:00 PM 436 IM115545 Open top dish head & manhole 8h 24-Feb-15 06:00 AM 24-Feb-15 02:00 PM 437 IM115550 Obtain CSE permit 2h 24-Feb-15 02:00 PM 24-Feb-15 04:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 7 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  8. 8. # Activity ID Activity Name Original Duration Start Finish 438 IM115555 Clean, Inspect & Repair as per ERG 12h 24-Feb-15 04:00 PM 25-Feb-15 04:00 PM 439 IM115560 Replace all filter cadridges 12h 25-Feb-15 04:00 PM 26-Feb-15 04:00 PM 440 IM115565 Fix back top dish head & manhole 12h 26-Feb-15 04:00 PM 27-Feb-15 04:00 PM 441 IM115570 De-Blind & Fix back top spool 8h 27-Feb-15 04:00 PM 28-Feb-15 12:00 PM 442 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 443 IM115575 Remove scaffolding 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 444 IM115580 Housekeeping & close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 445 R15E-320-016 RC2-32-320-41-E-307-EXCH-INTER & EXTERNAL INSPR15E-320-016 RC2-32-320-41-E-307-EXCH-INTER & EXTERNAL INSP 1288h 01-Jan-15 06:00 AM 23-Feb-15 10:00 PM 446 PRE-SHUTDOWNPRE-SHUTDOWN 24h 01-Jan-15 06:00 AM 02-Jan-15 06:00 PM 447 IM111465 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 448 IM111470 Shift blinds to blinding location 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM 449 IM111475 Erect Scaffolding 6h 01-Jan-15 10:00 AM 01-Jan-15 04:00 PM 450 IM111480 Removal of insulation 8h 01-Jan-15 04:00 PM 02-Jan-15 12:00 PM 451 IM111485 Purging, Flushing & Gas test, LEL checking 6h 02-Jan-15 12:00 PM 02-Jan-15 06:00 PM 452 SHUTDOWNSHUTDOWN 136h 18-Feb-15 06:00 AM 23-Feb-15 10:00 PM 453 IM111490 Verify LT&T and Obtain PTW 2h 18-Feb-15 06:00 AM 18-Feb-15 08:00 AM 454 IM111495 Drop spools & blind as per blindlist 8h 18-Feb-15 08:00 AM 18-Feb-15 04:00 PM 455 IM111500 Remove channel head 5h 18-Feb-15 04:00 PM 18-Feb-15 09:00 PM 456 IM111505 Carryout prelim. inspn. & Offer for AFI 2h 18-Feb-15 09:00 PM 18-Feb-15 11:00 PM 457 IM111510 Pull out the tube bundle 5h 18-Feb-15 11:00 PM 19-Feb-15 04:00 AM 458 IM111515 Perform AFI on tube bundle, shell & channel head 2h 19-Feb-15 04:00 AM 19-Feb-15 06:00 AM 459 IM111520 Shift tube bundle to jetting area 2h 19-Feb-15 06:00 AM 19-Feb-15 08:00 AM 460 IM111525 100% hydrojetting of tube external & internal 10h 19-Feb-15 08:00 AM 19-Feb-15 06:00 PM 461 IM111530 Hydrojetting of shell & channel covers 4h 19-Feb-15 06:00 PM 19-Feb-15 10:00 PM 462 IM111535 Perform detailed inspn. 3h 19-Feb-15 10:00 PM 20-Feb-15 01:00 AM 463 IM111540 RFECT inspn. on 178U tubes (Confirm via IRIS) 33h 20-Feb-15 01:00 AM 21-Feb-15 10:00 AM 464 IM111545 NDT of welds & thickness monitoring 6h 21-Feb-15 10:00 AM 21-Feb-15 04:00 PM 465 IM111550 Shift back tube bundle to site 3h 21-Feb-15 04:00 PM 21-Feb-15 07:00 PM 466 IM111555 Reinstall tube bundle 4h 21-Feb-15 07:00 PM 21-Feb-15 11:00 PM 467 IM111560 Hydrotest the exchanger 10h 21-Feb-15 11:00 PM 22-Feb-15 09:00 AM 468 IM111565 Repairs & retest as per inspn. report 20h 22-Feb-15 09:00 AM 23-Feb-15 05:00 AM 469 IM111570 Final Inspection 2h 23-Feb-15 05:00 AM 23-Feb-15 07:00 AM 470 IM111575 Reinstall channel head 5h 23-Feb-15 07:00 AM 23-Feb-15 12:00 PM 471 IM111580 Reinstall spools & Deblinding 10h 23-Feb-15 12:00 PM 23-Feb-15 10:00 PM 472 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 473 IM111585 Fix back insulation 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 474 IM111590 Remove scaffolding 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 475 IM111595 Housekeeping & close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 476 R15E-320-018 RC2-32-320-41-E-308-EXCH-INTER & EXTERNAL INSPR15E-320-018 RC2-32-320-41-E-308-EXCH-INTER & EXTERNAL INSP 1363h 01-Jan-15 06:00 AM 27-Feb-15 01:00 AM 477 PRE-SHUTDOWNPRE-SHUTDOWN 16h 01-Jan-15 06:00 AM 02-Jan-15 10:00 AM 478 IM112730 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 479 IM112735 Shift blinds to blinding location 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM 480 IM112740 Erect Scaffolding 4h 01-Jan-15 10:00 AM 01-Jan-15 02:00 PM 481 IM112745 Removal of insulation 2h 01-Jan-15 02:00 PM 01-Jan-15 04:00 PM 482 IM112750 Purging, Flushing & Gas test, LEL checking 6h 01-Jan-15 04:00 PM 02-Jan-15 10:00 AM 483 SHUTDOWNSHUTDOWN 139h 21-Feb-15 06:00 AM 27-Feb-15 01:00 AM 484 IM112755 Verify LT&T and Obtain PTW 2h 21-Feb-15 06:00 AM 21-Feb-15 08:00 AM 485 IM112760 Drop spools & blind as per blindlist 12h 21-Feb-15 08:00 AM 21-Feb-15 08:00 PM 486 IM112765 Remove channel head 5h 21-Feb-15 08:00 PM 22-Feb-15 01:00 AM 487 IM112770 Carryout prelim. inspn. & Offer for AFI 2h 22-Feb-15 01:00 AM 22-Feb-15 03:00 AM 488 IM112775 Pull out the tube bundle 5h 22-Feb-15 03:00 AM 22-Feb-15 08:00 AM 489 IM112780 Perform AFI on tube bundle & shell 2h 22-Feb-15 08:00 AM 22-Feb-15 10:00 AM 490 IM112785 Shift tube bundle to jetting area 2h 22-Feb-15 10:00 AM 22-Feb-15 12:00 PM 491 IM112790 100% hydrojetting of tube external & internal 12h 22-Feb-15 12:00 PM 23-Feb-15 12:00 AM 492 IM112795 Hydrojetting of shell & channel head 4h 23-Feb-15 12:00 AM 23-Feb-15 04:00 AM 493 IM112800 Perform detailed inspn. 3h 23-Feb-15 04:00 AM 23-Feb-15 07:00 AM 494 IM112805 RFECT inspn. on 256U tubes (Confirm via IRIS) 32h 23-Feb-15 07:00 AM 24-Feb-15 03:00 PM 495 IM112810 NDT of welds, visual insp. & thickness monitoring 6h 24-Feb-15 03:00 PM 24-Feb-15 09:00 PM 496 IM112815 Shift back tube bundle to site 2h 24-Feb-15 09:00 PM 24-Feb-15 11:00 PM 497 IM112820 Reinstall tube bundle 5h 24-Feb-15 11:00 PM 25-Feb-15 04:00 AM 498 IM112825 Hydrotest on shell & tube side 8h 25-Feb-15 04:00 AM 25-Feb-15 12:00 PM 499 IM112830 Repairs & retest as per inspn. Report 20h 25-Feb-15 12:00 PM 26-Feb-15 08:00 AM 500 IM112835 Final Inspection 2h 26-Feb-15 08:00 AM 26-Feb-15 10:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 8 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  9. 9. # Activity ID Activity Name Original Duration Start Finish 501 IM112840 Reinstall channel head 5h 26-Feb-15 10:00 AM 26-Feb-15 03:00 PM 502 IM112845 Reinstall spools & Deblinding 10h 26-Feb-15 03:00 PM 27-Feb-15 01:00 AM 503 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 504 IM112850 Fix back insulation 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 505 IM112855 Remove scaffolding 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 506 IM112860 Housekeeping & close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 507 CGCCGC 1567h 01-Jan-15 06:00 AM 07-Mar-15 01:00 PM 508 R15E-420-003 RC2-32-420-43-AT-0059 - POWER SUPPLY CHECKINGR15E-420-003 RC2-32-420-43-AT-0059 - POWER SUPPLY CHECKING 592h 01-Jan-15 06:00 AM 19-Feb-15 10:00 AM 509 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 510 IE100355 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 511 SHUTDOWNSHUTDOWN 4h 19-Feb-15 06:00 AM 19-Feb-15 10:00 AM 512 IE100360 Verify LT&T and Obtain permit 1h 19-Feb-15 06:00 AM 19-Feb-15 07:00 AM 513 IE100365 Remove CB of EL-4722Aand Install new CB 2h 19-Feb-15 07:00 AM 19-Feb-15 09:00 AM 514 IE100370 Do function test and witnes the Job 1h 19-Feb-15 09:00 AM 19-Feb-15 10:00 AM 515 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 516 IE100375 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 517 R15E-520-021 RC2-32-520-43-L-0070 - CHANGE OF HEATER PHINOLIC TAGSR15E-520-021 RC2-32-520-43-L-0070 - CHANGE OF HEATER PHINOLIC TAGS 690h 01-Jan-15 06:00 AM 27-Feb-15 12:00 PM 518 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 519 IE100380 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 520 SHUTDOWNSHUTDOWN 4h 27-Feb-15 08:00 AM 27-Feb-15 12:00 PM 521 IE100385 Verify LT&T and Obtain permit 1h 27-Feb-15 08:00 AM 27-Feb-15 09:00 AM 522 IE100390 Check the Loop for the Each Tags 1h 27-Feb-15 09:00 AM 27-Feb-15 10:00 AM 523 IE100395 Identify and Place the Appropriate tags in the Position 1h 27-Feb-15 10:00 AM 27-Feb-15 11:00 AM 524 IE100400 Witness the Job 1h 27-Feb-15 11:00 AM 27-Feb-15 12:00 PM 525 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 526 IE100405 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 527 R15E-520-022 RC2-32-520-43-L-0080 - CHANGE OF HEATER PHINOLIC TAGSR15E-520-022 RC2-32-520-43-L-0080 - CHANGE OF HEATER PHINOLIC TAGS 694h 01-Jan-15 06:00 AM 27-Feb-15 04:00 PM 528 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 529 IE100410 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 530 SHUTDOWNSHUTDOWN 4h 27-Feb-15 12:00 PM 27-Feb-15 04:00 PM 531 IE100415 Verify LT&T and Obtain permit 1h 27-Feb-15 12:00 PM 27-Feb-15 01:00 PM 532 IE100420 Check the Loop for the Each Tags 1h 27-Feb-15 01:00 PM 27-Feb-15 02:00 PM 533 IE100425 Identify and Place the Appropriate tags in the Position 1h 27-Feb-15 02:00 PM 27-Feb-15 03:00 PM 534 IE100430 Witness the Job 1h 27-Feb-15 03:00 PM 27-Feb-15 04:00 PM 535 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 536 IE100435 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 537 R15E-610-009 RC2-32-610-43-P-0001 - REMOVAL OF OLD ELECT CABLE HEATERR15E-610-009 RC2-32-610-43-P-0001 - REMOVAL OF OLD ELECT CABLE HEATER 698h 01-Jan-15 06:00 AM 28-Feb-15 08:00 AM 538 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 539 IE100500 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 540 SHUTDOWNSHUTDOWN 4h 27-Feb-15 04:00 PM 28-Feb-15 08:00 AM 541 IE100505 Verify LT&T and Obtain permit 1h 27-Feb-15 04:00 PM 27-Feb-15 05:00 PM 542 IE100510 Remove old Electrical Cable for 610-PDI-0001 3h 27-Feb-15 05:00 PM 28-Feb-15 08:00 AM 543 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 544 IE100515 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 545 R15E-710-003 RC2-32-710-30-H-710 - SD MAINT OF MCC MODULER15E-710-003 RC2-32-710-30-H-710 - SD MAINT OF MCC MODULE 504h 01-Jan-15 06:00 AM 11-Feb-15 06:00 PM 546 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 547 IE100520 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 548 SHUTDOWNSHUTDOWN 4h 11-Feb-15 02:00 PM 11-Feb-15 06:00 PM 549 IE100525 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM 550 IE100530 Do Insp. & Maint. as per Checklist 3h 11-Feb-15 03:00 PM 11-Feb-15 06:00 PM 551 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 552 IE100535 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 553 R15E-710-004 RC2-32-710-30-H-710 - SD MAINT OF H-710R15E-710-004 RC2-32-710-30-H-710 - SD MAINT OF H-710 512h 01-Jan-15 06:00 AM 12-Feb-15 02:00 PM 554 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 555 IE100540 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 556 SHUTDOWNSHUTDOWN 4h 12-Feb-15 10:00 AM 12-Feb-15 02:00 PM 557 IE100545 Verify LT&T and Obtain permit 1h 12-Feb-15 10:00 AM 12-Feb-15 11:00 AM 558 IE100550 Do Insp. & Maint. as per Checklist 3h 12-Feb-15 11:00 AM 12-Feb-15 02:00 PM 559 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 560 IE100555 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 561 R15E-999-002 RC2-32-999-29-EL-4760 - SD MAINT OF EL-4760R15E-999-002 RC2-32-999-29-EL-4760 - SD MAINT OF EL-4760 448h 01-Jan-15 06:00 AM 07-Feb-15 10:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 9 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  10. 10. # Activity ID Activity Name Original Duration Start Finish 562 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 563 IE100920 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 564 SHUTDOWNSHUTDOWN 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 565 IE100925 Verify LT&T and Obtain permit 1h 07-Feb-15 06:00 AM 07-Feb-15 07:00 AM 566 IE100930 Do Insp. & Maint. as per Checklist 3h 07-Feb-15 07:00 AM 07-Feb-15 10:00 AM 567 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 568 IE100935 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 569 R15E-999-003 RC2-32-999-29-EL-4761 - SD MAINT OF EL-4761R15E-999-003 RC2-32-999-29-EL-4761 - SD MAINT OF EL-4761 462h 01-Jan-15 06:00 AM 08-Feb-15 12:00 PM 570 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 571 IE100940 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 572 SHUTDOWNSHUTDOWN 6h 08-Feb-15 06:00 AM 08-Feb-15 12:00 PM 573 IE100945 Verify LT&T and Obtain permit 1h 08-Feb-15 06:00 AM 08-Feb-15 07:00 AM 574 IE100950 Do Insp. & Maint. as per Checklist 5h 08-Feb-15 07:00 AM 08-Feb-15 12:00 PM 575 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 576 IE100955 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 577 R15E-999-004 RC2-32-999-29-EL-4762 - SD MAINT OF EL-4762R15E-999-004 RC2-32-999-29-EL-4762 - SD MAINT OF EL-4762 522h 01-Jan-15 06:00 AM 13-Feb-15 12:00 PM 578 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 579 IE100960 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 580 SHUTDOWNSHUTDOWN 6h 13-Feb-15 06:00 AM 13-Feb-15 12:00 PM 581 IE100965 Verify LT&T and Obtain permit 1h 13-Feb-15 06:00 AM 13-Feb-15 07:00 AM 582 IE100970 Do Insp. & Maint. as per Checklist 5h 13-Feb-15 07:00 AM 13-Feb-15 12:00 PM 583 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 584 IE100975 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 585 R15E-999-005 RC2-32-999-29-EL-4760 - SD MAINT OF PANEL EL-4760R15E-999-005 RC2-32-999-29-EL-4760 - SD MAINT OF PANEL EL-4760 456h 01-Jan-15 06:00 AM 07-Feb-15 06:00 PM 586 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 587 IE100980 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 588 SHUTDOWNSHUTDOWN 6h 07-Feb-15 12:00 PM 07-Feb-15 06:00 PM 589 IE100985 Verify LT&T and Obtain permit 1h 07-Feb-15 12:00 PM 07-Feb-15 01:00 PM 590 IE100990 Do Insp. & Maint. as per Checklist 5h 07-Feb-15 01:00 PM 07-Feb-15 06:00 PM 591 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 592 IE100995 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 593 R15E-999-006 RC2-32-999-29-EL-4761 - SD MAINT OF PANEL EL-4761R15E-999-006 RC2-32-999-29-EL-4761 - SD MAINT OF PANEL EL-4761 468h 01-Jan-15 06:00 AM 08-Feb-15 06:00 PM 594 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 595 IE101000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 596 SHUTDOWNSHUTDOWN 6h 08-Feb-15 12:00 PM 08-Feb-15 06:00 PM 597 IE101005 Verify LT&T and Obtain permit 1h 08-Feb-15 12:00 PM 08-Feb-15 01:00 PM 598 IE101010 Do Insp. & Maint. as per Checklist 5h 08-Feb-15 01:00 PM 08-Feb-15 06:00 PM 599 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 600 IE101015 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 601 R15E-999-007 RC2-32-999-29-EL-4762 - SD MAINT OF PANEL EL-4762R15E-999-007 RC2-32-999-29-EL-4762 - SD MAINT OF PANEL EL-4762 528h 01-Jan-15 06:00 AM 13-Feb-15 06:00 PM 602 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 603 IE101020 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 604 SHUTDOWNSHUTDOWN 6h 13-Feb-15 12:00 PM 13-Feb-15 06:00 PM 605 IE101025 Verify LT&T and Obtain permit 1h 13-Feb-15 12:00 PM 13-Feb-15 01:00 PM 606 IE101030 Do Insp. & Maint. as per Checklist 5h 13-Feb-15 01:00 PM 13-Feb-15 06:00 PM 607 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 608 IE101035 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 609 R15E-005-001 RC2-32-005-29-EL-4709-MAINT OF CONVENIENCE PNLR15E-005-001 RC2-32-005-29-EL-4709-MAINT OF CONVENIENCE PNL 652h 01-Jan-15 06:00 AM 24-Feb-15 10:00 AM 610 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 611 IE100000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 612 SHUTDOWNSHUTDOWN 8h 23-Feb-15 02:00 PM 24-Feb-15 10:00 AM 613 IE100005 Verify LT&T and Obtain permit 1h 23-Feb-15 02:00 PM 23-Feb-15 03:00 PM 614 IE100010 Do Insp. & Maint. as per Checklist 7h 23-Feb-15 03:00 PM 24-Feb-15 10:00 AM 615 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 616 IE100015 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 617 R15E-005-002 RC2-32-005-29-EL-4712-MAINT OF CONVENIENCE PNLR15E-005-002 RC2-32-005-29-EL-4712-MAINT OF CONVENIENCE PNL 676h 01-Jan-15 06:00 AM 26-Feb-15 10:00 AM 618 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 619 IE100020 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 620 SHUTDOWNSHUTDOWN 8h 25-Feb-15 02:00 PM 26-Feb-15 10:00 AM 621 IE100025 Verify LT&T and Obtain permit 1h 25-Feb-15 02:00 PM 25-Feb-15 03:00 PM 622 IE100030 Do Insp. & Maint. as per Checklist 7h 25-Feb-15 03:00 PM 26-Feb-15 10:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 10 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  11. 11. # Activity ID Activity Name Original Duration Start Finish 623 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 624 IE100035 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 625 R15E-005-003 RC2-32-005-29-EL-4715-MAINT OF CONVENIENCE PNLR15E-005-003 RC2-32-005-29-EL-4715-MAINT OF CONVENIENCE PNL 656h 01-Jan-15 06:00 AM 24-Feb-15 02:00 PM 626 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 627 IE100040 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 628 SHUTDOWNSHUTDOWN 8h 24-Feb-15 06:00 AM 24-Feb-15 02:00 PM 629 IE100045 Verify LT&T and Obtain permit 1h 24-Feb-15 06:00 AM 24-Feb-15 07:00 AM 630 IE100050 Do Insp. & Maint. as per Checklist 7h 24-Feb-15 07:00 AM 24-Feb-15 02:00 PM 631 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 632 IE100055 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 633 R15E-005-004 RC2-32-005-29-EL-4718-MAINT OF CONVENIENCE PNLR15E-005-004 RC2-32-005-29-EL-4718-MAINT OF CONVENIENCE PNL 664h 01-Jan-15 06:00 AM 25-Feb-15 10:00 AM 634 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 635 IE100060 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 636 SHUTDOWNSHUTDOWN 8h 24-Feb-15 02:00 PM 25-Feb-15 10:00 AM 637 IE100065 Verify LT&T and Obtain permit 1h 24-Feb-15 02:00 PM 24-Feb-15 03:00 PM 638 IE100070 Do Insp. & Maint. as per Checklist 7h 24-Feb-15 03:00 PM 25-Feb-15 10:00 AM 639 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 640 IE100075 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 641 R15E-005-005 RC2-32-005-29-EL-4721-MAINT OF CONVENIENCE PNLR15E-005-005 RC2-32-005-29-EL-4721-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 642 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 643 IE100080 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 644 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 645 IE100085 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 646 IE100090 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 647 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 648 IE100095 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 649 R15E-005-006 RC2-32-005-29-EL-4724-MAINT OF CONVENIENCE PNLR15E-005-006 RC2-32-005-29-EL-4724-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 650 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 651 IE100100 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 652 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 653 IE100105 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 654 IE100110 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 655 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 656 IE100115 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 657 R15E-005-007 RC2-32-005-29-EL-4725-A-MAINT OF CONVENIENCE PNLR15E-005-007 RC2-32-005-29-EL-4725-A-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 658 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 659 IE100120 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 660 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 661 IE100125 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 662 IE100130 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 663 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 664 IE100135 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 665 R15E-005-008 RC2-32-005-29-EL-4727-MAINT OF CONVENIENCE PNLR15E-005-008 RC2-32-005-29-EL-4727-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 666 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 667 IE100140 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 668 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 669 IE100145 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 670 IE100150 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 671 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 672 IE100155 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 673 R15E-005-009 RC2-32-005-29-EL-4728-A-MAINT OF CONVENIENCE PNLR15E-005-009 RC2-32-005-29-EL-4728-A-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 674 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 675 IE100160 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 676 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 677 IE100165 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 678 IE100170 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 679 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 680 IE100175 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 681 R15E-005-010 RC2-32-005-29-EL-4730-MAINT OF CONVENIENCE PNLR15E-005-010 RC2-32-005-29-EL-4730-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 682 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 11 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  12. 12. # Activity ID Activity Name Original Duration Start Finish 683 IE100180 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 684 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 685 IE100185 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 686 IE100190 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 687 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 688 IE100195 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 689 R15E-005-011 RC2-32-005-29-EL-4733-MAINT OF CONVENIENCE PNLR15E-005-011 RC2-32-005-29-EL-4733-MAINT OF CONVENIENCE PNL 644h 01-Jan-15 06:00 AM 23-Feb-15 02:00 PM 690 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 691 IE100200 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 692 SHUTDOWNSHUTDOWN 8h 23-Feb-15 06:00 AM 23-Feb-15 02:00 PM 693 IE100205 Verify LT&T and Obtain permit 1h 23-Feb-15 06:00 AM 23-Feb-15 07:00 AM 694 IE100210 Do Insp. & Maint. as per Checklist 7h 23-Feb-15 07:00 AM 23-Feb-15 02:00 PM 695 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 696 IE100215 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 697 R15E-005-012 RC2-32-005-29-EL-4734-A-MAINT OF CONVENIENCE PNLR15E-005-012 RC2-32-005-29-EL-4734-A-MAINT OF CONVENIENCE PNL 668h 01-Jan-15 06:00 AM 25-Feb-15 02:00 PM 698 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 699 IE100220 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 700 SHUTDOWNSHUTDOWN 8h 25-Feb-15 06:00 AM 25-Feb-15 02:00 PM 701 IE100225 Verify LT&T and Obtain permit 1h 25-Feb-15 06:00 AM 25-Feb-15 07:00 AM 702 IE100230 Do Insp. & Maint. as per Checklist 7h 25-Feb-15 07:00 AM 25-Feb-15 02:00 PM 703 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 704 IE100235 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 705 R15E-005-014 RC2-32-005-29-EL-4739-MAINT OF CONVENIENCE PNLR15E-005-014 RC2-32-005-29-EL-4739-MAINT OF CONVENIENCE PNL 676h 01-Jan-15 06:00 AM 26-Feb-15 10:00 AM 706 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 707 IE100260 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 708 SHUTDOWNSHUTDOWN 8h 25-Feb-15 02:00 PM 26-Feb-15 10:00 AM 709 IE100265 Verify LT&T and Obtain permit 1h 25-Feb-15 02:00 PM 25-Feb-15 03:00 PM 710 IE100270 Do Insp. & Maint. as per Checklist 7h 25-Feb-15 03:00 PM 26-Feb-15 10:00 AM 711 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 712 IE100275 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 713 R15E-005-015 RC2-32-005-29-EL-4742-MAINT OF CONVENIENCE PNLR15E-005-015 RC2-32-005-29-EL-4742-MAINT OF CONVENIENCE PNL 680h 01-Jan-15 06:00 AM 26-Feb-15 02:00 PM 714 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 715 IE100280 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 716 SHUTDOWNSHUTDOWN 8h 26-Feb-15 06:00 AM 26-Feb-15 02:00 PM 717 IE100285 Verify LT&T and Obtain permit 1h 26-Feb-15 06:00 AM 26-Feb-15 07:00 AM 718 IE100290 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 07:00 AM 26-Feb-15 02:00 PM 719 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 720 IE100295 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 721 R15E-005-016 RC2-32-005-29-EL-4745-MAINT OF CONVENIENCE PNLR15E-005-016 RC2-32-005-29-EL-4745-MAINT OF CONVENIENCE PNL 688h 01-Jan-15 06:00 AM 27-Feb-15 10:00 AM 722 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 723 IE100300 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 724 SHUTDOWNSHUTDOWN 8h 26-Feb-15 02:00 PM 27-Feb-15 10:00 AM 725 IE100305 Verify LT&T and Obtain permit 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM 726 IE100310 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 03:00 PM 27-Feb-15 10:00 AM 727 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 728 IE100315 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 729 R15E-310-007 RC2-32-310-16-C-301-INST-LT REPLACEMENTR15E-310-007 RC2-32-310-16-C-301-INST-LT REPLACEMENT 60h 07-Feb-15 06:00 AM 09-Feb-15 06:00 PM 730 SHUTDOWNSHUTDOWN 60h 07-Feb-15 06:00 AM 09-Feb-15 06:00 PM 731 II108310 Review JSA 1h 07-Feb-15 06:00 AM 07-Feb-15 07:00 AM 732 II108315 Verify LT&T and Obtain permit 2h 07-Feb-15 07:00 AM 07-Feb-15 09:00 AM 733 II108320 Disconnect connections 6h 07-Feb-15 09:00 AM 07-Feb-15 03:00 PM 734 II108325 Remove the existing stanchions & LT 6h 07-Feb-15 03:00 PM 07-Feb-15 09:00 PM 735 II108330 Replace Isolation valve, DP Capillary LT 30h 07-Feb-15 09:00 PM 09-Feb-15 03:00 AM 736 II108335 Re-connect & check reading 12h 09-Feb-15 03:00 AM 09-Feb-15 03:00 PM 737 II108340 Inspection by RLOC 2h 09-Feb-15 03:00 PM 09-Feb-15 05:00 PM 738 II108345 House keeping & Close PTW 1h 09-Feb-15 05:00 PM 09-Feb-15 06:00 PM 739 R15E-310-010 RC2-32-310-16-C-302A-N2 BOOSTER COMP-A MAJOR OHR15E-310-010 RC2-32-310-16-C-302A-N2 BOOSTER COMP-A MAJOR OH 456h 01-Jan-15 06:00 AM 07-Feb-15 06:00 PM 740 PRE-SHUTDOWNPRE-SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 741 IM115875 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 742 IM115880 Shift blinds to blinding location 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM 743 SHUTDOWNSHUTDOWN 48h 04-Feb-15 06:00 AM 07-Feb-15 06:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 12 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  13. 13. # Activity ID Activity Name Original Duration Start Finish 744 IM115885 Verify LT&T and Obtain PTW 2h 04-Feb-15 06:00 AM 04-Feb-15 08:00 AM 745 IM115890 Blinding as per blindlist 2h 04-Feb-15 08:00 AM 04-Feb-15 10:00 AM 746 IM115895 Remove necessary pipes & inst. lines 2h 04-Feb-15 10:00 AM 04-Feb-15 12:00 PM 747 IM115900 Remove foundation bolt & lift the skit 4h 04-Feb-15 12:00 PM 04-Feb-15 04:00 PM 748 IM115905 Shift the skit to workshop 1h 04-Feb-15 04:00 PM 04-Feb-15 05:00 PM 749 IM115910 Disassemble the drive unit 2h 04-Feb-15 05:00 PM 05-Feb-15 07:00 AM 750 IM115915 Disassemble the valve/piston assembly 2h 05-Feb-15 07:00 AM 05-Feb-15 09:00 AM 751 IM115920 Disassemble crankcase assembly 2h 05-Feb-15 09:00 AM 05-Feb-15 11:00 AM 752 IM115925 Clean & Inspect all parts 2h 05-Feb-15 11:00 AM 05-Feb-15 01:00 PM 753 IM115930 Repair or Replace, if reqd. 2h 05-Feb-15 01:00 PM 05-Feb-15 03:00 PM 754 IM115935 Assemble crankcase assembly 2h 05-Feb-15 03:00 PM 05-Feb-15 05:00 PM 755 IM115940 Assemble the valve/piston assembly 2h 05-Feb-15 05:00 PM 06-Feb-15 07:00 AM 756 IM115945 Assemble the drive unit 2h 06-Feb-15 07:00 AM 06-Feb-15 09:00 AM 757 IM115950 Shift the skit to job site 1h 06-Feb-15 09:00 AM 06-Feb-15 10:00 AM 758 IM115955 Fix back the skit 4h 06-Feb-15 10:00 AM 06-Feb-15 02:00 PM 759 IM115960 Clean & Check cooler/ NRV/ relief valve 4h 06-Feb-15 02:00 PM 06-Feb-15 06:00 PM 760 IM115965 Fix back all pipes & inst. lines 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM 761 IM115970 Carrryout De-Blinding 2h 07-Feb-15 08:00 AM 07-Feb-15 10:00 AM 762 IM115975 Performance check for compressor 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM 763 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 764 IM115980 Housekeeping & close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 765 R15E-310-011 RC2-32-310-16-CC-301A-CGC LP COMP MAJOR OHR15E-310-011 RC2-32-310-16-CC-301A-CGC LP COMP MAJOR OH 1416h 01-Jan-15 06:00 AM 01-Mar-15 06:00 AM 766 PRE-SHUTDOWNPRE-SHUTDOWN 60h 01-Jan-15 06:00 AM 05-Jan-15 06:00 PM 767 IM116995 Conduct JSA, Rigging plan study 10h 01-Jan-15 06:00 AM 01-Jan-15 04:00 PM 768 IM117000 Erect scaffold for work platform 12h 01-Jan-15 04:00 PM 02-Jan-15 04:00 PM 769 IM117005 Remove insulation, wherever reqd. 8h 02-Jan-15 04:00 PM 03-Jan-15 12:00 PM 770 IM117010 Shift tools & tackles to job site 12h 03-Jan-15 12:00 PM 04-Jan-15 12:00 PM 771 IM117015 Shift & Unload rotor canister to site 12h 04-Jan-15 12:00 PM 05-Jan-15 12:00 PM 772 IM117020 Provide necessary lighting 6h 05-Jan-15 12:00 PM 05-Jan-15 06:00 PM 773 SHUTDOWNSHUTDOWN 528h 07-Feb-15 06:00 AM 01-Mar-15 06:00 AM 774 IM117025 Verify LT&T and Obtain PTW 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 775 IM117030 Blinding as per blindlist (R15E-310-119) 0h 07-Feb-15 10:00 AM 07-Feb-15 10:00 AM 776 IM117035 Remove necessary pipes & inst. lines 24h 07-Feb-15 10:00 AM 08-Feb-15 10:00 AM 777 IM117040 Remove coupling guard - LP to HP 4h 08-Feb-15 10:00 AM 08-Feb-15 02:00 PM 778 IM117045 Check & Record LP to HP alignment 4h 08-Feb-15 02:00 PM 08-Feb-15 06:00 PM 779 IM117050 Remove coupling spacer - LP to HP 4h 08-Feb-15 06:00 PM 08-Feb-15 10:00 PM 780 IM117055 Record measurements on LP-NDE & DE 4h 08-Feb-15 10:00 PM 09-Feb-15 02:00 AM 781 IM117060 Open DE bearing top half housing 4h 09-Feb-15 02:00 AM 09-Feb-15 06:00 AM 782 IM117065 Measure & record the clearance 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM 783 IM117070 Remove journal brg. @ DE & Install shipping brg. 4h 09-Feb-15 10:00 AM 09-Feb-15 02:00 PM 784 IM117075 Lock rotor & Remove coupling hub @ LP-NDE 4h 09-Feb-15 02:00 PM 09-Feb-15 06:00 PM 785 IM117080 Open NDE bearing top half housing 4h 09-Feb-15 06:00 PM 09-Feb-15 10:00 PM 786 IM117085 Measure & record the clearance 4h 09-Feb-15 10:00 PM 10-Feb-15 02:00 AM 787 IM117090 Remove journal brg. @ NDE & Install shipping brg. 4h 10-Feb-15 02:00 AM 10-Feb-15 06:00 AM 788 IM117095 Remove coupling hub at LP-NDE 4h 10-Feb-15 06:00 AM 10-Feb-15 10:00 AM 789 IM117100 Remove lock nut & thrust disk 4h 10-Feb-15 10:00 AM 10-Feb-15 02:00 PM 790 IM117105 Disassemble LP-NDE Dry gas seal/Sealing system from housing 4h 10-Feb-15 02:00 PM 10-Feb-15 06:00 PM 791 IM117110 Install LP-NDE rotor seal support unit 4h 10-Feb-15 06:00 PM 10-Feb-15 10:00 PM 792 IM117115 Disassemble LP-DE Dry gas seal/Sealing system from housing 4h 10-Feb-15 10:00 PM 11-Feb-15 02:00 AM 793 IM117120 Install LP-DE rotor seal support unit 4h 11-Feb-15 02:00 AM 11-Feb-15 06:00 AM 794 IM117125 Remove injection nozzles 8h 11-Feb-15 06:00 AM 11-Feb-15 02:00 PM 795 IM117130 Remove all LP casing bolts 18h 11-Feb-15 02:00 PM 12-Feb-15 08:00 AM 796 IM117135 Remove & Shift upper casing 8h 12-Feb-15 08:00 AM 12-Feb-15 04:00 PM 797 IM117140 Remove LP casing top inserts 12h 12-Feb-15 04:00 PM 13-Feb-15 04:00 AM 798 IM117145 Remove rotor & Place on support stand 8h 13-Feb-15 04:00 AM 13-Feb-15 12:00 PM 799 IM117150 Remove casing inserts from lower casing 12h 13-Feb-15 12:00 PM 14-Feb-15 12:00 AM 800 IM117155 Shift casing inserts to blasting area 24h 14-Feb-15 12:00 AM 15-Feb-15 12:00 AM 801 IM117160 Glass bead blasting of casing inserts 48h 15-Feb-15 12:00 AM 17-Feb-15 12:00 AM 802 IM117165 Cleaning of casing & rotor 48h 17-Feb-15 12:00 AM 19-Feb-15 12:00 AM 803 IM117170 Cleaning of suction lines & injn. nozzle 8h 19-Feb-15 12:00 AM 19-Feb-15 08:00 AM 804 IM117175 Inspect lower, upper casing & acce. 24h 19-Feb-15 08:00 AM 20-Feb-15 08:00 AM 805 IM117180 Inspect all casing bolts 24h 20-Feb-15 08:00 AM 21-Feb-15 08:00 AM 806 IM117185 Shift casing inserts to job site 24h 21-Feb-15 08:00 AM 22-Feb-15 08:00 AM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 13 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  14. 14. # Activity ID Activity Name Original Duration Start Finish 807 IM117190 Install casing inserts into lower casing 8h 22-Feb-15 08:00 AM 22-Feb-15 04:00 PM 808 IM117195 Lift rotor & Position in to the compressor casing 8h 22-Feb-15 04:00 PM 23-Feb-15 12:00 AM 809 IM117200 Record the neccessary clearances 8h 23-Feb-15 12:00 AM 23-Feb-15 08:00 AM 810 IM117205 Install casing inserts into upper casing 8h 23-Feb-15 08:00 AM 23-Feb-15 04:00 PM 811 IM117210 Lift & Install upper casing 12h 23-Feb-15 04:00 PM 24-Feb-15 04:00 AM 812 IM117215 Tight casing bolts as per procedure 12h 24-Feb-15 04:00 AM 24-Feb-15 04:00 PM 813 IM117220 Measure & record rotor free float 4h 24-Feb-15 04:00 PM 24-Feb-15 08:00 PM 814 IM117225 Install all injection nozzle 8h 24-Feb-15 08:00 PM 25-Feb-15 04:00 AM 815 IM117230 Install LP-NDE Dry gas seal/Sealing system 8h 25-Feb-15 04:00 AM 25-Feb-15 12:00 PM 816 IM117235 Assemble NDE thrust disk & lock the disk 8h 25-Feb-15 12:00 PM 25-Feb-15 08:00 PM 817 IM117240 Assemble thrust brg. case with thrust pads 4h 25-Feb-15 08:00 PM 26-Feb-15 12:00 AM 818 IM117245 Install NDE coupling hub & Provide lock nut 4h 26-Feb-15 12:00 AM 26-Feb-15 04:00 AM 819 IM117250 Install DE Dry gas seal/Sealing system 8h 26-Feb-15 04:00 AM 26-Feb-15 12:00 PM 820 IM117255 Install DE coupling hub & Provide lock nut 4h 26-Feb-15 12:00 PM 26-Feb-15 04:00 PM 821 IM117260 Remove shipping brg. @ DE & Install journal brgs. 8h 26-Feb-15 04:00 PM 27-Feb-15 12:00 AM 822 IM117265 Remove shipping brg. @ NDE & Install journal/thrust brgs. 8h 27-Feb-15 12:00 AM 27-Feb-15 08:00 AM 823 IM117270 Record the neccessary clearances 4h 27-Feb-15 08:00 AM 27-Feb-15 12:00 PM 824 IM117275 Install DE/NDE bearing housing top half 6h 27-Feb-15 12:00 PM 27-Feb-15 06:00 PM 825 IM117280 Install coupling spacer 4h 27-Feb-15 06:00 PM 27-Feb-15 10:00 PM 826 IM117285 Perform alignment on MP-LP by Laser/Dial 12h 27-Feb-15 10:00 PM 28-Feb-15 10:00 AM 827 IM117290 Install back MP-LP lower/upper half of coupling guard 4h 28-Feb-15 10:00 AM 28-Feb-15 02:00 PM 828 IM117295 Fix back instrument connections 8h 28-Feb-15 02:00 PM 28-Feb-15 10:00 PM 829 IM117300 Fix back auxiliary pipings 8h 28-Feb-15 10:00 PM 01-Mar-15 06:00 AM 830 IM117305 Carryout De-Blinding (R15E-310-119) 0h 01-Mar-15 06:00 AM 01-Mar-15 06:00 AM 831 POST SHUTDOWNPOST SHUTDOWN 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 832 IM117310 Fix back insulation 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 833 IM117315 Remove scaffolding 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 834 IM117320 Rotor preservation & Send for refub. 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 835 IM117325 Housekeeping & Close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 836 R15E-310-012 RC2-32-310-16-CC-301C-CGC HP COMP MAJOR OHR15E-310-012 RC2-32-310-16-CC-301C-CGC HP COMP MAJOR OH 1424h 01-Jan-15 06:00 AM 01-Mar-15 02:00 PM 837 PRE-SHUTDOWNPRE-SHUTDOWN 60h 01-Jan-15 06:00 AM 05-Jan-15 06:00 PM 838 IM117330 Conduct JSA, Rigging plan study 10h 01-Jan-15 06:00 AM 01-Jan-15 04:00 PM 839 IM117335 Erect scaffold for work platform 12h 01-Jan-15 04:00 PM 02-Jan-15 04:00 PM 840 IM117340 Remove insulation, wherever reqd. 8h 02-Jan-15 04:00 PM 03-Jan-15 12:00 PM 841 IM117345 Shift tools & tackles to job site 12h 03-Jan-15 12:00 PM 04-Jan-15 12:00 PM 842 IM117350 Shift & Unload rotor canister to site 12h 04-Jan-15 12:00 PM 05-Jan-15 12:00 PM 843 IM117355 Provide necessary lighting 6h 05-Jan-15 12:00 PM 05-Jan-15 06:00 PM 844 SHUTDOWNSHUTDOWN 536h 07-Feb-15 06:00 AM 01-Mar-15 02:00 PM 845 IM117360 Verify LT&T and Obtain PTW 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 846 IM117365 Blinding as per blindlist (R15E-310-119) 0h 07-Feb-15 10:00 AM 07-Feb-15 10:00 AM 847 IM117370 Remove necessary pipes & inst. lines 10h 07-Feb-15 10:00 AM 07-Feb-15 08:00 PM 848 IM117375 Open DE bearing top half housing 8h 07-Feb-15 08:00 PM 08-Feb-15 04:00 AM 849 IM117380 Remove journal brg. @ DE & Install shipping brg. 8h 08-Feb-15 04:00 AM 08-Feb-15 12:00 PM 850 IM117385 Open NDE bearing top half housing 8h 08-Feb-15 12:00 PM 08-Feb-15 08:00 PM 851 IM117390 Remove journal brg. @ NDE & Install shipping brg. 4h 08-Feb-15 08:00 PM 09-Feb-15 12:00 AM 852 IM117395 Measure & record the clearance 8h 09-Feb-15 12:00 AM 09-Feb-15 08:00 AM 853 IM117400 Remove lock nut & thrust disk 4h 09-Feb-15 08:00 AM 09-Feb-15 12:00 PM 854 IM117405 Disassemble HP-NDE Dry gas seal/Sealing system from housing 4h 09-Feb-15 12:00 PM 09-Feb-15 04:00 PM 855 IM117410 Install HP-NDE rotor seal support unit 4h 09-Feb-15 04:00 PM 09-Feb-15 08:00 PM 856 IM117415 Remove coupling hub at HP-DE 4h 09-Feb-15 08:00 PM 10-Feb-15 12:00 AM 857 IM117420 Disassemble HP-DE Dry gas seal/Sealing system from housing 4h 10-Feb-15 12:00 AM 10-Feb-15 04:00 AM 858 IM117425 Install HP-DE rotor seal support unit 4h 10-Feb-15 04:00 AM 10-Feb-15 08:00 AM 859 IM117430 Remove injection nozzles 10h 10-Feb-15 08:00 AM 10-Feb-15 06:00 PM 860 IM117435 Remove HP casing bolts 12h 10-Feb-15 06:00 PM 11-Feb-15 06:00 AM 861 IM117440 Install bundle pulling arrangement 12h 11-Feb-15 06:00 AM 11-Feb-15 06:00 PM 862 IM117445 Pullout Bundle 12h 11-Feb-15 06:00 PM 12-Feb-15 06:00 AM 863 IM117450 Dismantle bundle 18h 12-Feb-15 06:00 AM 13-Feb-15 12:00 AM 864 IM117455 Remove rotor & Place on support stand 6h 13-Feb-15 12:00 AM 13-Feb-15 06:00 AM 865 IM117460 Shift casing inserts to blasting area 24h 13-Feb-15 06:00 AM 14-Feb-15 06:00 AM 866 IM117465 Glass bead blasting of casing inserts 48h 14-Feb-15 06:00 AM 16-Feb-15 06:00 AM 867 IM117470 Shift casing inserts to job site 24h 16-Feb-15 06:00 AM 17-Feb-15 06:00 AM 868 IM117475 Clean HP parts & casing 48h 17-Feb-15 06:00 AM 19-Feb-15 06:00 AM 869 IM117480 Cleaning of suction lines & injn. nozzle 8h 19-Feb-15 06:00 AM 19-Feb-15 02:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 14 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  15. 15. # Activity ID Activity Name Original Duration Start Finish 870 IM117485 Assemble bundle with new rotor 36h 19-Feb-15 02:00 PM 21-Feb-15 02:00 AM 871 IM117490 Inspect HP Casing & accessories 24h 21-Feb-15 02:00 AM 22-Feb-15 02:00 AM 872 IM117495 Inspect all casing bolts 24h 22-Feb-15 02:00 AM 23-Feb-15 02:00 AM 873 IM117500 Insert HP barrel into compressor casing 24h 23-Feb-15 02:00 AM 24-Feb-15 02:00 AM 874 IM117505 Record the neccessary clearances 4h 24-Feb-15 02:00 AM 24-Feb-15 06:00 AM 875 IM117510 Install casing cover 8h 24-Feb-15 06:00 AM 24-Feb-15 02:00 PM 876 IM117515 Tight casing bolts as per procedure 8h 24-Feb-15 02:00 PM 24-Feb-15 10:00 PM 877 IM117520 Measure & record rotor free float 4h 24-Feb-15 10:00 PM 25-Feb-15 02:00 AM 878 IM117525 Install all injection nozzle 8h 25-Feb-15 02:00 AM 25-Feb-15 10:00 AM 879 IM117530 Install NDE Dry gas seal/Sealing system 8h 25-Feb-15 10:00 AM 25-Feb-15 06:00 PM 880 IM117535 Assemble NDE thrust disk & lock the disk 4h 25-Feb-15 06:00 PM 25-Feb-15 10:00 PM 881 IM117540 Remove shipping brg. @ NDE & Install journal brgs. 8h 25-Feb-15 10:00 PM 26-Feb-15 06:00 AM 882 IM117545 Install DE Dry gas seal/Sealing system 8h 26-Feb-15 06:00 AM 26-Feb-15 02:00 PM 883 IM117550 Install DE coupling hub & Provide lock nut 8h 26-Feb-15 02:00 PM 26-Feb-15 10:00 PM 884 IM117555 Remove shipping brg. @ DE & Install journal brgs. 8h 26-Feb-15 10:00 PM 27-Feb-15 06:00 AM 885 IM117560 Record the neccessary clearances 4h 27-Feb-15 06:00 AM 27-Feb-15 10:00 AM 886 IM117565 Install DE/NDE bearing housing top half 8h 27-Feb-15 10:00 AM 27-Feb-15 06:00 PM 887 IM117570 Install coupling spacer 4h 27-Feb-15 06:00 PM 27-Feb-15 10:00 PM 888 IM117575 Perform alignment on LP-HP by Laser/Dial 12h 27-Feb-15 10:00 PM 28-Feb-15 10:00 AM 889 IM117580 Install back LP-HP lower/upper half of coupling guard 4h 28-Feb-15 10:00 AM 28-Feb-15 02:00 PM 890 IM117585 Replace seal gas filter elements 4h 28-Feb-15 02:00 PM 28-Feb-15 06:00 PM 891 IM117590 Fix back instrument connections 8h 28-Feb-15 06:00 PM 01-Mar-15 02:00 AM 892 IM117595 Fix back auxiliary pipings 12h 01-Mar-15 02:00 AM 01-Mar-15 02:00 PM 893 IM117600 Carryout De-Blinding (R15E-310-119) 0h 01-Mar-15 02:00 PM 01-Mar-15 02:00 PM 894 POST SHUTDOWNPOST SHUTDOWN 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 895 IM117605 Fix back insulation 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 896 IM117610 Remove scaffolding 12h 01-Jan-15 06:00 AM 01-Jan-15 06:00 PM 897 IM117615 Rotor preservation & Send for refub. 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 898 IM117620 Housekeeping & Close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 899 R15E-310-013 RC2-32-310-35-F-301-INTER INSP & CLEANINGR15E-310-013 RC2-32-310-35-F-301-INTER INSP & CLEANING 924h 01-Jan-15 06:00 AM 08-Feb-15 06:00 PM 900 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 901 IM115225 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 902 IM115230 Erect scaffolding 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM 903 IM115235 Removal of insulation 2h 01-Jan-15 12:00 PM 01-Jan-15 02:00 PM 904 SHUTDOWNSHUTDOWN 36h 07-Feb-15 06:00 AM 08-Feb-15 06:00 PM 905 IM115240 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM 906 IM115245 Drop spool with strainer & Fix end blind 10h 07-Feb-15 08:00 AM 07-Feb-15 06:00 PM 907 IM115250 Shift strainer to cleaning area 1h 07-Feb-15 06:00 PM 07-Feb-15 07:00 PM 908 IM115255 Clean, Inspect & Repair as per ERG 12h 07-Feb-15 07:00 PM 08-Feb-15 07:00 AM 909 IM115260 Shift strainer to job site 1h 08-Feb-15 07:00 AM 08-Feb-15 08:00 AM 910 IM115265 Drop end blind & Fix strainer with spool 10h 08-Feb-15 08:00 AM 08-Feb-15 06:00 PM 911 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 912 IM115270 Fix back insulation 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 913 IM115275 Remove scaffolding 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 914 IM115280 Housekeeping & close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 915 R15E-310-014 RC2-32-310-35-F-308-INTER INSP & CLEANINGR15E-310-014 RC2-32-310-35-F-308-INTER INSP & CLEANING 924h 01-Jan-15 06:00 AM 08-Feb-15 06:00 PM 916 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM 917 IM115285 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 918 IM115290 Erect scaffolding 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM 919 IM115295 Removal of insulation 2h 01-Jan-15 12:00 PM 01-Jan-15 02:00 PM 920 SHUTDOWNSHUTDOWN 36h 07-Feb-15 06:00 AM 08-Feb-15 06:00 PM 921 IM115300 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM 922 IM115305 Drop spool with strainer & Fix end blind 10h 07-Feb-15 08:00 AM 07-Feb-15 06:00 PM 923 IM115310 Shift strainer to cleaning area 1h 07-Feb-15 06:00 PM 07-Feb-15 07:00 PM 924 IM115315 Clean, Inspect & Repair as per ERG 12h 07-Feb-15 07:00 PM 08-Feb-15 07:00 AM 925 IM115320 Shift strainer to job site 1h 08-Feb-15 07:00 AM 08-Feb-15 08:00 AM 926 IM115325 Drop end blind & Fix strainer with spool 10h 08-Feb-15 08:00 AM 08-Feb-15 06:00 PM 927 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 928 IM115330 Fix back insulation 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 929 IM115335 Remove scaffolding 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 930 IM115340 Housekeeping & close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 931 R15E-310-015 RC2-32-310-35-F-309-INTER INSP & CLEANINGR15E-310-015 RC2-32-310-35-F-309-INTER INSP & CLEANING 924h 01-Jan-15 06:00 AM 08-Feb-15 06:00 PM 932 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 15 of 128 TASK filters: FILTERS, FILTERS_1. Oracle Corporation
  16. 16. # Activity ID Activity Name Original Duration Start Finish 933 IM115345 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 934 IM115350 Erect scaffolding 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM 935 IM115355 Removal of insulation 2h 01-Jan-15 12:00 PM 01-Jan-15 02:00 PM 936 SHUTDOWNSHUTDOWN 36h 07-Feb-15 06:00 AM 08-Feb-15 06:00 PM 937 IM115360 Verify LT&T and Obtain PTW 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM 938 IM115365 Drop spool with strainer & Fix end blind 10h 07-Feb-15 08:00 AM 07-Feb-15 06:00 PM 939 IM115370 Shift strainer to cleaning area 1h 07-Feb-15 06:00 PM 07-Feb-15 07:00 PM 940 IM115375 Clean, Inspect & Repair as per ERG 12h 07-Feb-15 07:00 PM 08-Feb-15 07:00 AM 941 IM115380 Shift strainer to job site 1h 08-Feb-15 07:00 AM 08-Feb-15 08:00 AM 942 IM115385 Drop end blind & Fix strainer with spool 10h 08-Feb-15 08:00 AM 08-Feb-15 06:00 PM 943 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 944 IM115390 Fix back insulation 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 945 IM115395 Remove scaffolding 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 946 IM115400 Housekeeping & close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 947 R15E-310-016 RC2-32-310-35-F-310-INTER INSP & CLEANINGR15E-310-016 RC2-32-310-35-F-310-INTER INSP & CLEANING 924h 01-Jan-15