# Activity ID Activity Name Original Duration Start Finish 1 ISBL ISBL 1674h 01-Jan-15 12:00 AM 11-Mar-15 06:00 PM 2 FURNACE FURNACE 1135h 01-Jan-15 06:00 AM 17-Feb-15 01:00 PM 3 R15E-151-007 R15E-151-007 RC2-32-151-PV-0013-CV-OVERHAUL & SERVICING 1135h 01-Jan-15 06:00 AM 17-Feb-15 01:00 PM 4 PRE-SHUTD PRE-SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 5 II100630 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 6 II100635 Remove Insulation 2h 01-Jan-15 07:00 AM 01-Jan-15 09:00 AM 7 SHUTDOWN SHUTDOWN 31h 16-Feb-15 06:00 AM 17-Feb-15 01:00 PM 8 II100640 Verify LT&T and Obtain permit 1h 16-Feb-15 06:00 AM 16-Feb-15 07:00 AM 9 II100645 Disconnect Signals / Connections for CV 1h 16-Feb-15 07:00 AM 16-Feb-15 08:00 AM 10 II100650 Removal of CV & Install Blinds 4h 16-Feb-15 08:00 AM 16-Feb-15 12:00 PM 11 II100655 Trans port CV to Work Shop 1h 16-Feb-15 12:00 PM 16-Feb-15 01:00 PM 12 II100660 Overhaul / Service CV 12h 16-Feb-15 01:00 PM 17-Feb-15 01:00 AM 13 II100665 Test Valve (Refer Documentation) 2h 17-Feb-15 01:00 AM 17-Feb-15 03:00 AM 14 II100670 Trans port CV to Unit / Remove Blinds 1h 17-Feb-15 03:00 AM 17-Feb-15 04:00 AM 15 II100675 Install CV 6h 17-Feb-15 04:00 AM 17-Feb-15 10:00 AM 16 II100680 Loop Check & Stroke test 2h 17-Feb-15 10:00 AM 17-Feb-15 12:00 PM 17 II100685 Inspection by RLOC 1h 17-Feb-15 12:00 PM 17-Feb-15 01:00 PM 18 POST SHUT POST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 19 II100690 Reinsulate CV 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 20 II100695 House keeping & Close PTW 1h 01-Jan-15 07:00 AM 01-Jan-15 08:00 AM 21 R15E-999-001 R15E-999-001 RC2-32-999-10-BD-002-INST-VERIFY AND ARREST LEAK 19h 13-Feb-15 02:00 PM 14-Feb-15 09:00 AM 22 SHUTDOWN SHUTDOWN 19h 13-Feb-15 02:00 PM 14-Feb-15 09:00 AM 23 II110545 Review JSA 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM 24 II110550 Verify LT&T and Obtain permit 2h 13-Feb-15 03:00 PM 13-Feb-15 05:00 PM 25 II110555 Disconnect signals / connections 3h 13-Feb-15 05:00 PM 13-Feb-15 08:00 PM 26 II110560 Verify Leaking area and Arrest the Leak 6h 13-Feb-15 08:00 PM 14-Feb-15 02:00 AM 27 II110565 Reconnect the signals / connections 4h 14-Feb-15 02:00 AM 14-Feb-15 06:00 AM 28 II110570 Offer for Inspection 2h 14-Feb-15 06:00 AM 14-Feb-15 08:00 AM 29 II110575 House keeping & Close PTW 1h 14-Feb-15 08:00 AM 14-Feb-15 09:00 AM 30 VHP VHP 1668h 01-Jan-15 06:00 AM 11-Mar-15 06:00 PM 31 R15E-002-004 R15E-002-004 RC2-31-002-PV-0001-CV-OVERHAUL & SERVICING 992h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 32 PRE-SHUTD PRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 33 II100000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 34 II100005 Errect Scaffolding / Remove Insulation 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM 35 SHUTDOWN SHUTDOWN 43h 09-Feb-15 07:00 PM 11-Feb-15 02:00 PM 36 II100010 Verify LT&T and Obtain permit 1h 09-Feb-15 07:00 PM 09-Feb-15 08:00 PM 37 II100015 Disconnect Signals / Connections for CV 1h 09-Feb-15 08:00 PM 09-Feb-15 09:00 PM 38 II100020 Removal of CV & Install Blinds 10h 09-Feb-15 09:00 PM 10-Feb-15 07:00 AM 39 II100025 Trans port CV to Work Shop 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM 40 II100030 Overhaul / Service CV 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM 41 II100035 Test Valve (Refer Documentation) 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM 42 II100040 Trans port CV to Unit / Remove Blinds 1h 10-Feb-15 10:00 PM 10-Feb-15 11:00 PM 43 II100045 Install CV 12h 10-Feb-15 11:00 PM 11-Feb-15 11:00 AM 44 II100050 Loop Check & Stroke test 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM 45 II100055 Inspection by RLOC 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM 46 POST SHUT POST SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM 47 II100060 Reinsulate CV / Removal of Scafflods 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM 48 II100065 House keeping & Close PTW 1h 01-Jan-15 09:00 AM 01-Jan-15 10:00 AM 49 R15E-002-005 R15E-002-005 RC2-31-002-PV-0003-CV-OVERHAUL & SERVICING 992h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 50 PRE-SHUTD PRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM 51 II100070 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 52 II100075 Errect Scaffolding / Remove Insulation 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM 53 SHUTDOWN SHUTDOWN 43h 09-Feb-15 07:00 PM 11-Feb-15 02:00 PM 54 II100080 Verify LT&T and Obtain permit 1h 09-Feb-15 07:00 PM 09-Feb-15 08:00 PM 55 II100085 Disconnect Signals / Connections for CV 1h 09-Feb-15 08:00 PM 09-Feb-15 09:00 PM 56 II100090 Removal of CV & Install Blinds 10h 09-Feb-15 09:00 PM 10-Feb-15 07:00 AM 57 II100095 Trans port CV to Work Shop 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM 58 II100100 Overhaul / Service CV 12h 10-Feb-15 08:00 AM 10-Feb-15 08:00 PM 59 II100105 Test Valve (Refer Documentation) 2h 10-Feb-15 08:00 PM 10-Feb-15 10:00 PM 60 II100110 Trans port CV to Unit / Remove Blinds 1h 10-Feb-15 10:00 PM 10-Feb-15 11:00 PM 61 II100115 Install CV 12h 10-Feb-15 11:00 PM 11-Feb-15 11:00 AM 62 II100120 Loop Check & Stroke test 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM at Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W hr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 30-Nov-14 08:44 AM Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Page 1 of 128 TASK filters: FILTERS, FILTERS_1. © Oracle Corporation