Top Banner
Iron Horse Trail Dublin Boulevard Overcrossing Community Meeting 6:00-7:30 PM December 3, 2018
15

Iron Horse Trail Dublin Boulevard Overcrossing

May 08, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Iron Horse Trail Dublin Boulevard Overcrossing

Iron Horse Trail

Dublin Boulevard

Overcrossing

Community Meeting

6:00-7:30 PM

December 3, 2018

Page 2: Iron Horse Trail Dublin Boulevard Overcrossing

• Sign-in (6:00-6:10)

• Presentation (6:10-6:30)

1. Welcome

2. Project Background

3. Project Details

4. Project Schedule

5. Next Steps

• Open House (6:30-7:30)

Page 3: Iron Horse Trail Dublin Boulevard Overcrossing

• Iron Horse Trail Feasibility Study

• Alameda CTC funded the Study

• City of Dublin supported Alameda CTC

consultant on preparing and finalizing the Study

• Study was coordinated with Scarlett Drive

Extension and the Community Park projects

which are both being constructed by The

Boulevard developer

Page 4: Iron Horse Trail Dublin Boulevard Overcrossing
Page 5: Iron Horse Trail Dublin Boulevard Overcrossing

Key Recommendations:

• Striping, signing, traffic signal improvements at Dougherty Road crossing (completed)

• Bicycle facilities through BART station to close gap in trail (in design)

• Bicycle/pedestrian bridge over Dublin Boulevard (in design)

Page 6: Iron Horse Trail Dublin Boulevard Overcrossing
Page 7: Iron Horse Trail Dublin Boulevard Overcrossing
Page 8: Iron Horse Trail Dublin Boulevard Overcrossing
Page 9: Iron Horse Trail Dublin Boulevard Overcrossing
Page 10: Iron Horse Trail Dublin Boulevard Overcrossing
Page 11: Iron Horse Trail Dublin Boulevard Overcrossing
Page 12: Iron Horse Trail Dublin Boulevard Overcrossing
Page 13: Iron Horse Trail Dublin Boulevard Overcrossing
Page 14: Iron Horse Trail Dublin Boulevard Overcrossing

• Finalize design – Fall 2019

• Future Phases – Funding Dependent

Page 15: Iron Horse Trail Dublin Boulevard Overcrossing

• Refine design elements such as bridge aesthetics, lighting, etc.

• Hold a Public Meeting

• Refine bridge interface to park and roadway

• Finalize construction documents