© 2011 Autodesk iPads® and BIM in Construction: What Is the ROI? – A Case Study Will Senner, Assistant Project Manager, Skanska USA Building Josh Kanner, Cofounder, VP Marketing & BD, Vela Systems
51

iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Sep 01, 2018

Download

Documents

dinhphuc
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

© 2011 Autodesk

iPads® and BIM in Construction: What Isthe ROI? – A Case Study

Will Senner, Assistant Project Manager, Skanska USA BuildingJosh Kanner, Cofounder, VP Marketing & BD, Vela Systems

Page 2: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

© 2011 Autodesk

Agenda

Introduction (Josh – 5 min.)

Case Study and ROI framework (Will – 35 min.)

What’s Next? Field BIM – Interactive (Josh – 5 min.)

Q+A (both – 15 min.)

Page 3: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

© 2011 Autodesk

Class Summary

Results of iPads, BIM, and field software on the Hunt Libraryproject, Raleigh, NC.

Focus is on quality assurance, commissioning of systemsand equipment, punch listing, and material tracking of curtainwall.

An ROI framework developed as a part of graduate-levelresearch at North Carolina State University will also bepresented.

Page 4: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

© 2011 Autodesk

Learning Objectives

At the end of this class, you will be able to:

Understand specific applications of BIM, iPads and field managementsoftware for potential use on your projects

Leverage an ROI framework for translating both soft and hard benefits oftechnology into dollar terms

Avoid common stumbling blocks when implementing technologies ofthese types on a project

Page 5: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –
Page 6: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

NC State Centennial Campus

Page 7: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

NC State Centennial Campus

Page 8: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

NC State Centennial Campus

Page 9: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Technology Overview− BIM in Estimating & Preconstruction

− Visualization & Smart Boards

− Logistics Planning & 4D Scheduling

− Field Mobility & Mobile Electronic Resource Stations

− Material Tracking

− MEP Coordination & As-Built BIM Handover

ROI / Cost-Benefit Research− Research Methodology/Approach

− Direct & Indirect Costs

− Benefits

− Efficiency Gains & Rework Reductions

− ROI Calculations

Page 10: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Estimating & Preconstruction

Page 11: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Quantification using BIM

Page 12: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Visualization & Smart Boards

Uses:

• Constructability review during designphases producing electronic reviewcomments

• Shop drawing review and teamcoordination meetings

Benefits:

• Improved understanding of difficultproject conditions

• Increased ability to convey design intentto subcontractors

• Ability to engage and collaborate withremotely located team members

Page 13: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Vela Systems Overview

Page 14: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Vela Systems Overview

Page 15: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Quality Control & Safety – Field Mobility

Page 16: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Quality Control –Mobile Electronic Resource Stations

Page 17: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Exterior Envelope

Page 18: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Material Tracking for Unitized Curtainwall

Page 19: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

0

5

10

15

20

25

30

35

40

45

50

16-Feb 26-Feb 8-Mar 18-Mar 28-Mar 7-Apr 17-Apr 27-Apr 7-May 17-May 27-May

Nu

mb

er

of

Un

its

Fabrication and Installation Production

Fabrication

Installation

Material Tracking for Unitized Curtainwall

Page 20: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Quality Control –Verification of Door Frame Installation

Page 21: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

MEP Systems & Technology Strategies

Page 22: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

MEP Systems

Page 23: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Innovation Grant Research Project:ROI of Innovation

Identify KeyFeatures ofTechnology

Implementation

Quantify Benefits& Evaluate ROI

DevelopRecommendations for

FutureImplementations

− Abstract: Innovative Technologies increase the effectiveness of operations & field personnel.

Page 24: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Research Assumptions

Assumptions

• Construction Manager at Risk delivery model

• 100% of project “savings” (General Conditions,Contingency, etc) returned to the owner at the endof the project

• 2 year schedule, $100M overall project cost

• No self-perform work by the CM

• Limited sample size due to “emerging” technologies

Page 25: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Research Framework

Calculate Return on Investment

“Owner” ROI “Project” ROI

Translate Benefits to Real Dollars

Determine Typical Rework CostsRework Avoided by Increasing Efficiency of CM

Staff

Determine Benefits

Observe Changes in Durations of Weekly Activities Use data to determine efficiency gains

Determine Total Implementation Costs

Direct Costs Indirect Costs

Page 26: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Direct Costs Summary –Field Mobility & Related Infrastructure

SINGLE PURCHASE(CAN BE REUSED)

AVOIDABLE COST(TRIAL AND ERROR)

RECURRING PURCHASE(PER PROJECT)

TOTALMARKET COST

(RETAIL)

$ 57,487.54 $ 2,270.00 $ 30,720.00 $ 90,477.54

SinglePurchase:

63.5%

AvoidableCost: 2.5%

RecurringPurchase:

34.0%

Breakdown of Costs

Page 27: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Indirect Costs

− 16 hour initial set up: uploading of electronic documents, development of location hierarchy, templates, etc

0

2

4

6

8

10

12

14

16

UPLOADING CONTRACT

DOCUMENTS/PLANS

ELECTRONIC MARK-UPS TRAINING

Ho

urs

Pe

rW

ee

k

Weekly Implementation Costs

Page 28: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Benefits

How are wereally usingthe tools?

What’schanged from

before?

What value arewe really

adding to theproject/owner?

To otherparties?

How do wetranslate that“value” to real

dollars?

Page 29: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Benefits - Step 1:

How are we operating nowand actually using thesetools day to day?

Page 30: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Distribution of Weekly Management Time

ManagementSector

ColorDesignation

Reaction

Assessment

Planning

Administration

ActivityAvg. DurationPrevious (Hrs.)

Avg. DurationNew (Hrs.)

Coordinate with PMs of Trades for the weeks activities-Reaction 2.30 2.50

Follow up statuses of past week's issues-Reaction 2.30 1.40

Monitor productivity of installation/construction-Reaction 2.00 1.60

Verify last week's issues have been corrected/addressed-Reaction 1.20 1.20

Conduct Meetings with Sub and A/E on rolling punchlist issues-Reaction 2.40 1.80

Document/Photograph unresolved issues and their location 2.00 1.10

Email/Phone other trades about coordination issues/construction sequence-Reaction 2.80 2.40

React to any issues/discrepancies which have arisen in the field 3.80 3.00

Follow up statuses of past week's issues-Assessment 2.60 1.00

Monitor productivity of installation/construction-Assessment 3.20 2.80

Verify last week's issues have been corrected/addressed-Assessment 2.00 2.20

Conduct Meetings with Sub and A/E on rolling punchlist issues-Assessment 2.60 1.80

Go to field to verify progress and quality 4.20 4.40

Assess productivity of past week/month 2.20 1.40

Walking with Owner/Commissioning Agent 2.75 2.50

CM Team Meeting 1.60 1.60

OAC Meeting 1.60 1.60

Review Plans/Specs/Shop Drawings/Submittals 5.60 5.60

Coordinate with PMs of Trades for the week's activities-Planning 3.20 3.50

Email/Phone fabrication shop to verify sequence and number of units 1.38 1.13

Determine what productivity for following week must be to stay on schedule 1.60 1.60Email/Phone other trades about coordination issues/construction sequence-Planning 1.60 1.60

Plan for next week's construction/installation 2.80 4.00

Pay Apps 1.80 1.80

Update information in the BIM to serve as electronic deliverable to Owner 2.50 1.00

Total Weekly Hours: 62.03 54.53

Page 31: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Benefits - Step 2:

What’s changed from theold way?

Page 32: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Efficiency Gains

− 62 hrs/wk to 54.5 hrs/wk on average

− 16.7% of time savings is returned to the project resulting in an increase in value-added planning

Reaction:18.80 Hrs.

(30%)

Assessment:19.55 Hrs.

(32%)

Planning:19.38 Hrs.

(31%)

Admin.:4.30 Hrs. (7%)

Previous

Reaction:15.00 Hrs.

(27%)

Assessment:16.10 Hrs.

(30%)

Planning:20.63 Hrs.

(38%)

Admin.: 2.80Hrs. (5%)

New

Page 33: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Efficiency Gains

− Equivalent to an additional 5.6%-11.3% of additional field supervision (50hrs/wk) [Avg.= 8.5%] excluding punch list operations

− With punch list efficiency: 8.2%-13.8% [Avg.=11.0%]

* “Earned” Hours are defined as time spent on planning and assessment activities

Metric: Previous (Baseline) New

“Earned” Hours * 38.93 40.43

Actual Hours 38.93 36.23

Efficiency 1.000 1.116

Metric: Time Savings

Increase in “Value Added” Planning 1.5 hours/week

Travel Efficiency 1.33 - 4.17 hours/week

Punch list Efficiency 2.0 hours/day during punch list operations

Page 34: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Benefits - Step 3:

What part(s) of this changereally result in added valueto the project/owner?To other parties?

Page 35: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Root Causes of Rework

HumanResourceCapability

UnclearInstructions to

Workers

InadequateSupervision &Job Planning

ExcessiveOvertime

Insufficient SkillLevels

Engineering &Reviews

Late DesignChanges

Poor DocumentControl

Scope Changes

Errors andOmissions

Leadership AndCommunications

IneffectiveManagement ofProject Team

Lack ofOperations (EndUser) Persons

Buy-in

Lack of Safetyand QA/QCcommitment

PoorCommunications

ConstructionPlanning &Scheduling

ConstructabilityProblems

Late DesignerInput

UnrealisticSchedules

InsufficientTurnover &

CommissioningResourcing

Material &Equipment

Supply

UntimelyDeliveries

Prefab. & Constr.Not to Project

Req.

Non-compliancewith

Specification

Materials not inRight Place

when Needed

Page 36: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Root Causes of Rework

HumanResourceCapability

UnclearInstructions to

Workers

InadequateSupervision &Job Planning

ExcessiveOvertime

Insufficient SkillLevels

Engineering &Reviews

Late DesignChanges

Poor DocumentControl

Scope Changes

Errors andOmissions

Leadership AndCommunications

IneffectiveManagement ofProject Team

Lack ofOperations (EndUser) Persons

Buy-in

Lack of Safetyand QA/QCcommitment

PoorCommunications

ConstructionPlanning &Scheduling

ConstructabilityProblems

Late DesignerInput

UnrealisticSchedules

InsufficientTurnover &

CommissioningResourcing

Material &Equipment

Supply

UntimelyDeliveries

Prefab. & Constr.Not to Project

Req.

Non-compliancewith

Specification

Materials not inRight Place

when Needed

Page 37: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Breakdown of Rework Causes

*(COAA study of over 100 constr. Projects)

Engineering &Reviews55.41%

HumanResourceCapability

18.28%

Material &Equipment

Supply 23.46%

Leadership &Communication

0.38%

Const. Planning& Scheduling

2.47%

Construction Owners Association of Alberta

DocumentControl

40%

Quality &Managerial

60%

Skanska Specific

Page 38: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Benefits - Step 4:

How do we translate that“value” into real dollars?

Page 39: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Mobile Technology Research Conclusions

− Estimated 5% of overall project cost spent on rework− $5M Total on a $100M project

− 50% Trade Costs

− 50% Project Costs/Contingency

90%

10%

Document Control Rework:

Trade Costs

Project Costs/ Contingency

23%

77%

Quality / ManagerialRework:

Page 40: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

0

10

20

30

40

50

60

70

80

90

100

0 100 200 300 400 500 600 700 800

%o

fR

ew

ork

Avo

ided

Additional Hours Spent (weekly)

Opportunity to Avoid Reworkthrough Additional Planning & Supervision

Page 41: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Mobile Technology Research Conclusions

− 1/3 of all rework could be avoided with an additional 50 hours/week of field supervision & planning− 90% avoided quality control items

− 10% avoided document control items

Potential Savings fromAdditional 50 hours of Field Supervision

Trade Cost Savings $500 K

Project Cost / Contingency Savings $1.17 M

Total Savings $1.67 M

Page 42: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Mobile Technology Research Conclusions

− Mobile Technology (excluding MERS) allows CM employees to be 8.5% more efficient on average

− Equates to $142K in avoided total rework− $99.5K in avoided project costs

− Hypothesis: In the long term, reductions in trade cost rework will reduce bids, translating into further ownersavings.

Return on Investment Summary

Project Costs Only 17%

Overall Costs 67%

Page 43: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Research Framework Review

Time Savings and Efficiency Gains

Decreased Weekly HoursWorked

Increased “Value Added”Planning

Reduced Rework

Contingency /Owner Savings

SubcontractorSavings

Page 44: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Mobile Technology Research Conclusions

− Mobile Electronic Resource Station Benefits: − 45% reduction in “Document Control” related rework (approx.

18% of all rework)

− Positive ROI for projects valued over $7.5M

Realized Savings from Mobile Electronic Resource Station

Trade Cost Savings $810 K

Project Cost / Contingency Savings $ 90 K

Overall Savings $900 K

Return on Investment Summary

Project Costs Only 1540%

Overall Costs 16300%

Page 45: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

− Direct Costs:

− Indirect Costs:

2 hrs/week of ongoing team training

BIM – Implementation Costs

Investment

Smartboard

Performance Laptop Premium

BIM Suite of Software (unlimited users)

Free BIM Viewer

Misc. Training

TOTAL Direct Costs $17,500

Page 46: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

BIM – Realized Benefits

− Pre-Construction Benefits:− 3-4 Days saved through model quantity verification

− Clash Detection & Coordination Benefits− 33% reduction in MEP coordination time

− $90K in overall avoided rework

BIM Coordination Savings from Avoided Rework

Trade Cost Savings $40 K

Project Cost / Contingency Savings $50 K

Total Rework Savings $90 K

Page 47: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

BIM – Return on Investment

Return on Investment Summary

Project Costs Only 186%

Overall Costs 414%

− Not inclusive of additional benefits resulting from additional time which is no longer spent supervisingrework

Page 48: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Return on Investment Summary

ROI

Project Total

Mobile Technology 17% 67%

Mobile Electronic ResourceStation

1540% 16300%

BIM 186% 414%

Overall TechnologyImplementation

122% 948%

Page 49: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

ROI Projections for Future Projects

0%

200%

400%

600%

800%

1000%

1200%

1400%

Retu

rno

nIn

vestm

en

t

Total Project Cost

OverallImplementation -Project Benefits

OverallImplementation -Total Benefits

Page 50: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

Questions

Will Senner

Assistant Project Manager

[email protected]

919-291-1425

Page 51: iPads® and BIM in Construction: What Is the ROI? - …aucache.autodesk.com/au2011/sessions/4674/class_presentations/v1... · iPads® and BIM in Construction: What Is the ROI? –

© 2011 Autodesk

Autodesk, AutoCAD* [*if/when mentioned in the pertinent material, followed by an alphabetical list of all other trademarks mentioned in the material] are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the USA and/or other countries. All other brand names, product names, or trademarks belong to their respective holders. Autodeskreserves the right to alter product and services offerings, and specifications and pricing at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. © 2011 Autodesk, Inc. All rights reserved.