Top Banner
/ŶǀĞƐƚŽƌ ƉƌĞƐĞŶƚĂƚŝŽŶ Ɖƌŝů ϮϬϭϭ
28

Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Mar 19, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Investor presentation 

April 2011

Page 2: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 2 

Important notices 

Disclaimer Forward looking statements This presentation  includes forward‐looking statements. Although Leighton Holdings Limited (the Company) believes the expectations expressed  in such forward‐looking statements are based on reasonable assumptions,  these statements are not guarantees or predictions of future performance, and involve both known and unknown risks, uncertainties and other factors, many of which are beyond the Company’s control. As a result, actual results or developments may differ materially from those expressed in the statements contained in this presentation.   Investors are cautioned  that statements contained  in this presentation are not guarantees or projections of future performance and actual results or developments may differ materially from those projected in forward‐looking statements. 

Reliance on third party information The information and views expressed  in this presentation were prepared by the Company on a confidential basis. They may contain information that has been derived from publicly available sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness  or reliability of the information. No responsibility, warranty or liability is accepted by the Company, its officers, employees,  agents or contractors for any errors, misstatements in or omissions from this presentation. 

Not investment advice This presentation  is not intended and should not be considered  to be the giving of investment advice by the Company or any of its shareholders, directors, officers, agents, employees  or advisers. The information provided in this presentation has been prepared without taking into account the recipient’s  investment objectives, financial circumstances or particular needs. Each party to whom this presentation is made available must make its own independent assessment of the Company after making such investigations and taking such advice as may be deemed necessary. 

No offer of securities Nothing in this presentation should be construed as either an offer to sell or a solicitation of an offer to buy or sell Company securities in any jurisdiction. 

US Securities Act This presentation does not constitute an offer to sell, or a solicitation of an offer to buy, any securities in the United States. This presentation may not be distributed or released in the United States. The offer and sale securities referenced herein have not been, and will not be, registered under the U.S. Securities Act of 1933 (the “Securities Act”) or the securities laws of any state or other jurisdiction of the United States and such securities may not be offered or sold, directly or indirectly, in the United States absent registration except in a transaction exempt from, or not subject to, the registration requirements of the Securities Act and any other applicable securities laws. 

Non‐GAAP Measures You should be aware that certain financial data included  in this presentation are “non‐GAAP financial measures” under Regulation G under the United States Securities Exchange Act of 1934, including “EBITDA”. The disclosure of such non‐GAAP financial measures in the manner included in this presentation would not be permissible in a registration statement under the Securities Act. These non‐GAAP financial measures do not have a standardised meaning prescribed by AIFRS and, therefore, may not be comparable to similarly titled measures presented by other entities, nor should they be construed as an alternative to other financial measures determined  in accordance with AIFRS. Although the Company believes these non‐GAAP financial measures provide useful information to users in measuring the financial performance and condition of our business for the reasons set out in this presentation, you are cautioned not to place undue reliance on any non‐ GAAP financial measures and ratios included in this presentation. 

No liability To the maximum extent permitted by law, neither the Company nor its related bodies corporate, directors, employees or agents, nor any other person, accepts any liability, including without limitation any liability arising from fault or negligence, for any direct, indirect or consequential  loss arising from the use of this presentation or its contents or otherwise arising in connection with it.

Page 3: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 3 

Agenda 

Introduction 

Airport Link Project 

Victorian Desalination Project 

Habtoor Leighton Group 

Business outlook 

Summary

Page 4: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Overview 

Major review of business 

Revised FY11 forecast due to: 

—  Airport Link Project (‘APL’) 

—  Victorian Desalination Project (‘VDP’) 

—  Habtoor Leighton Group (‘HLG’) 

$757m capital raising 

Outlook remains very positive 

$46bn of work in hand 

Expect NPAT of $600‐650m for FY12 

Introduction 

4

Page 5: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Reconciliation of FY11 statutory forecasts 

Pre‐tax ($m) 

NPAT ($m) 

Cash impact 

FY11  FY12  FY13 

Feb 2011 guidance  480 

Airport Link  (470)  (329)  (708)  (94) 

Victorian Desalination  (282)  (197)  (282) 

HLG equity impairment  (200)  (200) 

HLG earnings reduction  (120)  (120) 

Other  (76)  (61)  50 

Tax impact  211  40 

Total  (1,148)  (907)  50  (779)  (54) 

April 2011 guidance  (427) 

Reconciliation of FY11 statutory forecasts 

Introduction 

5

Page 6: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 6 

Recapitalisation of balance sheet 

Covenant headroom maintained 

Improves gearing 

Supports credit rating metrics 

No final FY11 dividend 

Supports pursuit of growth opportunities 

Expect to resume dividend in FY12 

Balance sheet and credit rating Introduction

Page 7: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Indicative Project Cost Schedule 

Why have issues emerged so quickly? 

Time Original Cost  D&C Revenue 

Original Profit 

Current time 

Original budget completion 

Contractual completion 

Introduction 

7

Page 8: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Indicative Project Cost Schedule 

Why have issues emerged so quickly? 

Time Original Cost  Revised Cost Draft  D&C Revenue 

Revised Draft Profit 

Current time 

Original budget completion 

Contractual completion 

Introduction 

8

Page 9: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Indicative Project Cost Schedule 

Why have issues emerged so quickly? 

Time Original Cost  Revised Cost Draft  Revised Cost Confirmed  D&C Revenue 

Revised confirmed loss 

Current time 

Original budget completion 

Contractual completion 

Introduction 

New design introduced

Page 10: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 10 

Currently ~70% complete overall 

TBM tunnel ~60% complete 

Airport flyer completed 9 months ahead of schedule 

Civil design 99% complete 

Program targets completion 30 June 2012 

— Commissioning targeted to commence mid April 2012 

— Accelerated hours to meet target 

Project status 

Project status Airport Link

Page 11: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Key project challenges 

Issue  Impact/description 

1.  Access and approvals Authority approvals and access issues (including Clem7 interface) have significantly delayed the project These delays have added substantially to the forecast final cost 

2.  Ground conditions Some areas more difficult and variable than anticipated Has impacted tunnelling performance and productivity 

3.  Weather 

Unprecedented wet weather conditions, particularly from October through January (Brisbane flooding), has severely hampered progress Impacted time and costs to complete 

4.  Design Completion of design has taken much longer than expected Actual design hours more than double tendered allowance 

5.  Materials 

Construction complexity has resulted in material quantities significantly exceeding tender expectations 133k tonnes of reinforcing steel v 86k tendered, 945k m 3 of concrete v 820k m 3 tendered 

Airport Link 

11

Page 12: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Airport Link 

Project cost review and financial impact 

Further access and approval delays 

Commissioning process 

Weather (although less so as mainly underground) 

Ability to successfully conclude claims 

Retention of key staff 

Remaining risks 

— Very thorough bottom up analysis 1  — Realistic cost assessment 4 

— Greater cost visibility, now 70% complete 

2  — Tunnelling close to completion 5 

— Design 99% complete 3  — Time and cost contingency reset 6 

12

Page 13: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Delivering the project 

Strategy  Impact/description 

1.  Drive to completion  Support construction activities to achieve earliest possible completion 

2.  Handover arrangements Work integrally with BrisConnections, Government authorities and Brisbane City Council on handover arrangements to minimise impacts to road opening 

3.  Insurance  Progress policy claims wherever appropriate 

4.  Cost recoveries  Identify and pursue entitlements for compensation where we have incurred additional cost and time overruns 

Airport Link 

13

Page 14: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 14 

Project status The project incorporates 4 components, 3 of which are progressing profitably 

However, the reverse osmosis plant which is the largest component is facing challenges 

Victorian Desalination Project 

Thiess share  Thiess value  Profitable 

Marine  97%  100%  $272m 

Tunnels  90%  100%  $150m 

Pipeline to dams  74%  32.5%  $155m 

Plant  40%  65%  $1.9bn

Page 15: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Key project challenges 

Issue  Impact/description 

1.  Weather Has impacted the ability to construct the reverse osmosis building Lost 33% of available time causing lower productivity on site Flooding of pipeline 

2.  Labour Labour productivity on the project significantly less than budgeted Significant planning issues due to complexity 

3.  Design Design costs increased from $141m in tender to $200m Inconsistency and errors between tender and final design 

4.  Materials Final design has increased materials quantities from tender level: structural steel by 226%, bored piles by 226%, bulk earthworks by 149%, rebar by 181% , cables by 131% and pumps by 128% 

Victorian Desalination Project 

15

15

Page 16: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Delivering the project 

Issue  Impact/description 

1.  Timeframe  Final project commissioning and handover is targeted for June 2012 with acceleration 

2.  Weather Allowances made for further bad weather but expect improvement in productivity and increased production with night shift operation and roofed structure 

3.  Labour Extending 4‐on/4‐off roster to accelerate program Working night shift for additional production 

Victorian Desalination Project 

Risks 

Failure to achieve improved productivity —  Further costs and risk to timeline 

Extreme weather Timely completion of final design tasks 

16

Page 17: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Habtoor Leighton Group 

Investment overview 

Investment in HLG($m) 31 December 2010 

$299m reduction in book value due to operating losses, FX and $100m impairment 

impairment reflected lack of new work and losses on pre‐acquisition projects 

1144 

845 

525 

320 

299 

Jun‐10  Impairment  Dec‐10  Impairment  Apr‐11 

Book value  Impairment 

Operating loss  FX Impact 

17 

Note:   Leighton has provided $289m of shareholder loans to HLG and pledged cash as security against a AED500m bank loan facility 

Current valuation 

Further $320 million reduction in book value 

—  $200m Leighton corporate impairment 

—  $120m operating loss reflects Leighton’s share of HLG result 

—  Underlying business operating profitably, result impacted by provisioning 

Request for further AED1bn in funding 

17

Page 18: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Habtoor Leighton Group 

The new HLG business is performing 

Contract  Value to LHL ($m)  % Complete  Profitable 

Dubai Pearl, Dubai  1084  2 

Al Shaqab, Qatar  340  93 

City Centre expansion, Qatar  275  89 

KPIZ Industrial Zone, Abu Dhabi  264  9 

Al Bustan Mixed Use, Abu Dhabi  218  67 

Zayed University  183  76 

Ritz‐Carlton, Abu Dhabi  175  71 

Al Ghurair City expansion, Dubai  158  81 

JAFZA Convention Centre  158  83 

P9 Development  150  85 

Top Ten Contracts by Value to HLG 

18

Page 19: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 19 

Repositioning Habtoor Leighton Group 

Increase diversification of business 

Geographic diversification 

—  Increasing focus outside UAE (Dubai and Abu Dhabi) and Qatar 

—  Saudi Arabia, Kuwait, Iraq are key growth markets 

Sector diversification 

—  Increased focus on infrastructure 

—  Opportunities in oil & gas 

Business improvement and efficiency 

—  Reduced workforce numbers but increased productivity 

—  Improved worker accommodation and morale 

—  Introduce Leighton management systems and processes 

—  Greater accountability for performance 

—  More selective with clients 

Key business improvement initiatives 

Habtoor Leighton Group 

Zayed University, Abu Dhabi

Page 20: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Habtoor Leighton Group 

Market conditions looking positive in the longer term 

Market conditions 

Recent new work includes 

—  AED2.2bn JV to build the Al Mafraq Hospital in Abu Dhabi 

—  AED400m Abu Dhabi Islamic Bank’s new headquarters in Abu Dhabi 

Short term outlook remains challenging 

Gulf Cooperative Council (GCC) economies expected to grow at average 5% p.a. from 2011 to 2015 

Award to Qatar of the 2022 FIFA World Cup will stimulate development in the medium to longer term 

Longer term outlook for Middle East region is positive 

Approx US$1.1tn worth of projects to be awarded in region over next 5‐10 years 

Upcoming projects by Geography (~US$1 trillion)* —next 5 years 

KSA 32% 

Levant + Libya 16% 

UAE 15% 

Iraq 15% 

Qatar 8% 

Bahrain 4% 

Oman 4% 

Kuwait 6% 

* Includes all projects yet to be awarded 

20

Page 21: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Habtoor Leighton Group 

Identified regional opportunities 

Saudi Arabia  AEDm 

Ministry of Interior hospitals program 

10,000 

Water Projects  3,000 

Jeddah Airport Hangers  2,000 

Ma’adanMine  2,000 

Kuwait  AEDm 

Sabah Al Salam University  1,500 

Kuwait Airport Runway  1,385 

KOC Small Boat Harbour  750 

Oman  AEDm 

Sohar Airport Terminal  3,000 

Ras Al Hadd Airport  2,000 

Oman Convention Centre  2,000 

Bidbid Sur Road  1,400 

Qatar  AEDm 

Lusail Expressway  3,300 

Doha Metro  2,000 

Musheireb Phase 2  1,500 

Northgate Mall  1,200 

Qatar Education City  500 

21 

UAE  AEDm 

Midfield Terminal  10,000 

Union Railway  4,000 

Louvre Abu Dhabi Museum  2,000 

Sweihan airside works  400

Page 22: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Major projects worth more than $1bn 

Total contract value 1  Type of project  Location 

Airport Link  $4.2bn  Design and construct  Queensland 

Senakin & Satui Coal Mines  $3.9bn  Contract mining  Indonesia 

Area C Iron Ore Mine  $3.6bn  Contract mining  Western Australia 

Mt Owen Coal Mine  $3.4bn  Contract mining  New South Wales 

Sangatta Coal Mine  $2.6bn  Contract mining  Indonesia 

Victorian Desalination Project  $2.5bn  Design and construct  Victoria 

Burton Coal Mine  $2.2bn  Contract mining  Queensland 

Wahana Coal Mine  $2.2bn  Contract mining  Indonesia 

Yandi Iron Ore Mine  $2.1bn  Contract mining  Western Australia 

Metro Trains  $1.2bn  Operation & maintenance  Victoria 

Dubai Pearl  $1.1bn  Design and construct  Dubai 

UHG Coal Mine  $1.0bn  Contract mining  Mongolia 

MSJ Coal Mine  $1.0bn  Contract mining  Indonesia 

Note: 1:‐ For long term contracts extending beyond five years, the total contract value shown includes the value of work completed to date plus five years worth of work in hand. 

Business outlook 

22

Page 23: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Group risk profile 

Construction contracts >$500m 

Total Work in Hand ($46bn) 

Note: All figures as of 31 Dec 2010 

Contract 

Dubai Pearl 

Barrow Island (civil) 

Barrow Island (jetty) 

Hunter Expressway 

Royal North Shore Hospital 

Iraq—offshore oil pipeline 

M80 Ring Road 

Barrow Island (site prep) 

Leppington rail line 

Ballina Bypass 

PPP  Structure 

D&C 

Alliance 

D&C 

Alliance 

D&C 

D&C 

Alliance 

D&C 

D&C 

Alliance 

Size 

$1bn 

$814m 

$768m 

$757m 

$729m 

$733m 

$558m 

$541m 

$530m 

$527m 

Complete 

2% 

1% 

11% 

5% 

38% 

16% 

18% 

25% 

0% 

83% 

Profitable 

Contract mining/ services/ development contracts 

Construction contracts <$500m 

Construction contracts >$500m 

Airport Link/ VDP 

57% 

23% 

15% 

6% ‐ 2 contracts 

Outside of the two large PPP projects, Leighton has a well diversified and performing portfolio 

Business outlook 

23

Page 24: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Business outlook 

Portfolio effect of diverse work load spreads risk 

Diversification by activity  Diversification by geography (work in hand) 

Record $46bn of work in hand 

31% 

3% 

36% 

2% 3%  2% 

3% 

6% 

14% 

Aust ‐ infrastructure 

Aust ‐ resources 

Aust ‐ property 

Indonesia 

Middle East 

India 

Hong Kong/Macau 

Mongolia 

Other 

Australia = 70% RoW = 30% 

Construction 

Contract mining 

Services 

43% of work in hand 

Half of construction is fixed price‐ fixed time 

Shares some or all risks with client on balance 

42% of work in hand 

Different and lower risk profile 

Longer term contracts 

13% of work in hand 

Lower risk profile 

24

Page 25: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 25 

Lessons learnt Business outlook 

Increased focus on: 

—  Tender accuracy and risk identification 

—  Adequate time allowances 

—  Adequate pricing of risk 

—  Project delivery and risk management 

—  Client cooperation and issues that could impact performance 

Senior manager to oversee APL and VDP

Page 26: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 26 

Positive outlook across major markets 

Infrastructure market to remain strong 

Good contract mining outlook 

LNG and coal seam gas to drive construction work 

Good opportunities in Asia 

Record $46bn of work in hand 

Diversification strategy remains sound 

Business outlook

Page 27: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Summary 

Addressing issues —  Airport Link —  Victorian Desalination Project —  Habtoor Leighton Group 

Undertaking review of major projects 

Recapitalisation underway 

No final FY11 dividend 

Position for growth, outlook remains very positive 

Expect NPAT of between $600‐650m in FY12 

27

Page 28: Investor presentations3-us-west-2.amazonaws.com/brr-streamguys/files/LEI/LEI20110211downgrade.pdfAlthough Leighton Holdings Limited (the Company) believes the expectation s expressed

Leighton Holdings Limited 

Investor presentation 

April 2011