INVESTIGATION ON PERFORMANCE RELIABILITY
IMPROVEMENT BY OPTIMIZING MAINTENANCE
PRACTICES THROUGH FAILURE ANALYSIS IN
CONTINUOUS PROCESS INDUSTRY
A Thesis submitted to Gujarat Technological University
for the Award of
Doctor of Philosophy
in
Mechanical Engineering
by
Pancholi Nilesh Hasamukhlal
129990919010
under supervision of
Dr. Mangal G. Bhatt
GUJARAT TECHNOLOGICAL UNIVERSITY
AHMEDABAD
September 2019
ii
© Pancholi Nilesh Hasamukhlal
iii
DECLARATION
I declare that the thesis entitled “Investigation on Performance Reliability Improvement
by Optimizing Maintenance Practices through Failure Analysis in Continuous
Process Industry” submitted by me for the degree of Doctor of Philosophy
is the record of research work carried out by me during the period from October 2012 to
November 2017 under the supervision of Dr. Mangal G. Bhatt, Principal, Shantilal
Shah Engineering College, Bhavnagar and this has not formed the basis for the award
of any degree, diploma, associate ship, fellowship, titles in this or any other University or
other institution of higher learning.
I further declare that the material obtained from other sources has been duly acknowledged
in the thesis. I shall be solely responsible for any plagiarism or other irregularities, if
noticed in the thesis.
Signature of the Research Scholar: ………………………… Date:
Name of Research Scholar: Pancholi Nilesh Hasamukhlal
Place: Ahmedabad
iv
CERTIFICATE
I certify that the work incorporated in the “Investigation on Performance Reliability
Improvement by Optimizing Maintenance Practices through Failure Analysis in
Continuous Process Industry” submitted by Shri Pancholi Nilesh
Hasamukhlal was carried out by the candidate under my supervision/guidance. To
the best of my knowledge: (i) the candidate has not submitted the same research work
to any other institution for any degree/diploma, Associate ship, Fellowship or other
similar titles (ii) the thesis submitted is a record of original research work done by the
Research Scholar during the period of study under my supervision, and (iii) the thesis
represents independent research work on the part of the Research Scholar.
Signature of Supervisor: ……………………………… Date:
Name of Supervisor: Dr. Mangal G. Bhatt
Place: Ahmedabad
v
Course-work Completion Certificate
This is to certify that Mr. Pancholi Nilesh Hasamukhlal, enrolment no. 129990919010 is a PhD
scholar enrolled for PhD program in the branch Mechanical Engineering of Gujarat
Technological University, Ahmedabad.
(Please tick the relevant option(s))
He/She has been exempted from the course-work (successfully completed during M.Phil
Course)
He/She has been exempted from Research Methodology Course only (successfully
completed during M.Phil Course)
He/She has successfully completed the PhD course work for the partial requirement for the
award of PhD Degree. His/ Her performance in the course work is as follows-
Grade Obtained in Research Methodology Grade Obtained in Self Study Course (Core Subject)
(PH001) (PH002)
AB AB
Supervisor’s Sign
(Dr. Mangal G. Bhatt)
vi
Originality Report Certificate
It is certified that PhD Thesis titled “Investigation on Performance Reliability
Improvement by Optimizing Maintenance Practices through Failure Analysis in
Continuous Process Industry” by Mr. Pancholi Nilesh Hasamukhlal has been examined
by us. We undertake the following:
a. Thesis has significant new work / knowledge as compared already published or are under
consideration to be published elsewhere. No sentence, equation, diagram, table,
paragraph or section has been copied verbatim from previous work unless it is placed
under quotation marks and duly referenced.
b. The work presented is original and own work of the author (i.e. there is no plagiarism).
No ideas, processes, results or words of others have been presented as Author own work.
c. There is no fabrication of data or results which have been compiled / analysed.
d. There is no falsification by manipulating research materials, equipment or processes, or
changing or omitting data or results such that the research is not accurately represented in
the research record.
e. The thesis has been checked using Turnitin Plagiarism (copy of originality report
attached) and found within limits as per GTU Plagiarism Policy and instructions issued
from time to time (i.e. permitted similarity index <=10%).
Signature of the Research Scholar: …………………………… Date:
Name of Research Scholar: Pancholi Nilesh Hasamukhlal
Place: Ahmedabad
Signature of Supervisor: ……………………………… Date:
Name of Supervisor: Dr. Mangal G. Bhatt
Place: Ahmedabad
vii
Turnitin Originality Report
viii
PhD THESIS Non-Exclusive License to
GUJARAT TECHNOLOGICAL UNIVERSITY
In consideration of being a PhD Research Scholar at GTU and in the interests of the
facilitation of research at GTU and elsewhere, I, Pancholi
Nilesh Hasamukhlal, having Enrollment No. 129990919010 hereby grant a non-exclusive,
royalty free and perpetual license to GTU on the following terms:
a) GTU is permitted to archive, reproduce and distribute my thesis, in whole or in part,
and/or my abstract, in whole or in part ( referred to collectively as the “Work”)
anywhere in the world, for non-commercial purposes, in all forms of media;
b) GTU is permitted to authorize, sub-lease, sub-contract or procure any of the acts
mentioned in paragraph (a);
c) GTU is authorized to submit the Work at any National / International Library, under
the authority of their “Thesis Non-Exclusive License”;
d) The Universal Copyright Notice (©) shall appear on all copies made under the
authority of this license;
e) I undertake to submit my thesis, through my University, to any Library and Archives.
Any abstract submitted with the thesis will be considered to form part of the thesis.
f) I represent that my thesis is my original work, does not infringe any rights of others,
including privacy rights, and that I have the right to make the grant conferred by this
non-exclusive license.
g) If third party copyrighted material was included in my thesis for which, under the
terms of the Copyright Act, written permission from the copyright owners is required,
I have obtained such permission from the copyright owners to do the acts mentioned
in paragraph (a) above for the full term of copyright protection.
h) I retain copyright ownership and moral rights in my thesis, and may deal with the
copyright in my thesis, in any way consistent with rights granted by me to my
University in this non-exclusive license.
i) I further promise to inform any person to whom I may hereafter assign or license my
copyright in my thesis of the rights granted by me to my University in this non-
exclusive license.
ix
j) I am aware of and agree to accept the conditions and regulations of PhD including all
policy matters related to authorship and plagiarism.
Signature of the Research Scholar: ……………………….
Name of Research Scholar: Pancholi Nilesh Hasamukhlal
Date: Place: Ahmedabad
Signature of the Supervisor: ……………………….
Name of the Supervisor: Dr. Mangal G. Bhatt
Date: Place: Ahmedabad
Seal:
x
Thesis Approval Form
The viva-voce of the PhD Thesis submitted by Shri Pancholi
Nilesh Hasamukhlal, Enrollment No. 129990919010 entitled “Investigation on
Performance Reliability Improvement by Optimizing Maintenance Practices through
Failure Analysis in Continuous Process Industry” was conducted on
…………………….………… (day and date) at Gujarat Technological University.
(Please tick any one of the following option)
The performance of the candidate was satisfactory. We recommend that he/she be
awarded the PhD degree.
Any further modifications in research work recommended by the panel after 3
months from the date of first viva-voce upon request of the Supervisor or request of
Independent Research Scholar after which viva-voce can be re-conducted by the
same panel again.
(briefly specify the modifications suggested by the panel)
The performance of the candidate was unsatisfactory. We recommend that he/she
should not be awarded the PhD degree.
(The panel must give justifications for rejecting the research work)
----------------------------------------------------- -----------------------------------------------------
Name and Signature of Supervisor with Seal 1) (External Examiner 1) Name and Signature
------------------------------------------------------- -------------------------------------------------------
2) (External Examiner 2) Name and Signature 3) (External Examiner 3) Name and Signature
xi
Abstract
There are certain possibilities of the performance reliability improvement through
maintenance optimization of various systems or components of major process industries
that run on continuous basis. Looking to the past business volume of 6.5 lac metric tons
for aluminium wire and expected compound annual growth rate of 13.5 % during
2014-19 due to Government of India’s power for all drive, an aluminium wire
processing plant forms a noticeable sector of continuous process industry. The
maintenance time is about 20 to 25 % of the total time which leads to reliability losses.
Moreover, poor maintenance seems the prime reason of low productivity and profit. Such
facts and challenges of keeping the system in ready-state motivate a definite maintenance
plan to be modeled based on a live failure analysis to be executed during shutdown or
scheduled period. The purpose of this research study is to investigate the extent at
which the reliability of an aluminium wire rolling mill can be improved by
ameliorating current control and maintenance practices.
The deliverables are achieved by collecting the historical failure data i.e. downtime
and failure frequencies; from April 2013 to March 2014 at Sampat aluminium private
limited. Reliability modeling is done in a view to understand the failure pattern behaviour
of the rolling machine. The critical components like; bearings, gears and machining shafts
are discriminated based on these data and their functional failures, failure causes, effects
and repercussions of failures with existing control and maintenance practices has been
modeled based on live shop-floor study. Scores are assigned on 1 to 10 levels by analyzing
attributes effects from lowest to highest concern respectively for every modes of failure
through realistic brain-storming among maintenance team by incorporating some advanced
attributes like; maintainability, economic safety, economic cost and spares with basic
criteria in this study. The risk priority number (RPN) and maintainability criticality indices
(MCIs) are narrated by these score values through traditional as well as MCDM based
failure analysis models like; TOPSIS, COPRAS-G and PSI.
The primary findings of this research work are to propose improvements in the
maintenance plan of critical components like bearings, gears and shafts of an
aluminium wire rolling mill which are commonly representing the most critical
components in a large range of industrial processes. The common modes of failure (C5,
xii
C3, C4, C10, and C14) having large is covered with condition-based monitoring or
predictive type of approaches, modes of failure (C13, C7, C8, and C1) having medium
is covered with preventive measures where it is assumed that avoidance of failure is
better than restore and modes of failure (C2, C11, C12, C6, and C9) having small is
covered by remedial or corrective actions when breakdown prompts. Originality mainly
consists in the contemporary application of non-identical MCDM methods.
The PhD thesis will be helpful in explicating the drawbacks of maintaining matters of the
foremost processing plants and prescribed yield outputs where MCDM approaches are
advantageous.
xiii
Dedicated to
My Wife (Unnati)
and
My Daughter (Dhanvee)
xiv
Acknowledgement
I am deeply indebted to my supervisor Dr. Mangal. G. Bhatt, Principal, Shantilal Shah
Engineering College, Bhavnagar whose invaluable guidance and constant encouragement
at all stages of the research work provided me with valuable insight without which this
research work would not have been possible. He gave me complete freedom to finish the
work at my own without compromising the standards.
I am thankful to Doctoral Progress Committee members Dr. Kalpesh D. Maniya, C. K.
Pithawala College of Engineering and Technology, Surat and Dr. Harshit K. Dave, S. V.
National Institute of Technology, Surat. Their valuable advices and moral support during
earnest reviews provide me proper direction throughout the research work.
I am especially grateful to Mr. Samyak Deora, Director, Deora Group for permitting me to
do research work at his esteemed industry. I am also thankful to Mr. Shrikant Patel,
Executive Director, Sampat Aluminium Pvt. Ltd., Ahmedabad and his team of maintenance
personnel, managers, and shop floor executives for giving their kind and valuable technical
support in fulfillment of requirements directly or indirectly during this study.
I acknowledge Honorable Vice Chancellor Dr. Navin Sheth, Dr. N. M. Bhatt and Dr. Rajul
Gajjar, Deans (Ph. D.), Shri J. C. Lilani, Registrar and staff members of Ph. D. section for
their kind support. I am also thankful to Dr. S. B. Sharma, former outstanding scientist and
Dy. Director, Antenna system area, SAC, ISRO, Ahmedabad for motivating to dream about
Ph. D. course by igniting research attitude in me and Late Prof. C. C. Rajyaguru, Director
(Academics), Dr. K. M. Srivastav, Ex. Professor, Indus Institute of Technology and
Engineering, Ahmedabad for providing me path to fulfill such dream.
Last but not least, I would like to express my gratitude to all nears and dears who helped
me in the course of my journey to complete this work with their good wishes.
Pancholi Nilesh Hasamukhlal Date:
xv
Table of Contents
List of Abbreviations .......................................................................................................... xix
List of Symbols ................................................................................................................... xxi
List of Figures ................................................................................................................... xxiv
List of Tables ..................................................................................................................... xxv
CHAPTER 1 ......................................................................................................................... 1
Introduction and Literature Review .................................................................................. 1
1.1 Broad Area of Research ................................................................................................... 1
1.2 Overview and Significance of Study ............................................................................... 1
1.3 Brief Overview about Reliability ..................................................................................... 2
1.3.1 Reliability Concept ....................................................................................................... 2
1.3.2 Significance of Mortality (Bath-tub) Curve .................................................................. 3
1.3.3 System Reliability Models ............................................................................................ 4
1.3.3.1 Series networks .......................................................................................................... 4
1.3.3.2 Parallel networks ........................................................................................................ 5
1.3.3.3 Redundant Reliability Model ..................................................................................... 5
1.3.3.4 The x – out of – m structure ....................................................................................... 6
1.3.3.5 System with mixed mode failure ............................................................................... 6
1.3.4 Reliability Analysis through Failure Distribution Function ......................................... 7
1.4 Brief Overview about Maintenance ................................................................................. 7
1.4.1 Maintenance Philosophy ............................................................................................... 8
1.4.2 Systematic step-by-step method for planning maintenance program ......................... 10
1.5 Brief Overview about Failure Mode Effect and Criticality Analysis (FMECA) ........... 11
1.5.1 Concept ....................................................................................................................... 11
1.5.2 Types of FMEA/FMECA ........................................................................................... 12
1.6 Brief Overview about Multi-criteria Decision-making (MCDM) ................................. 12
1.6.1 Overview and Importance of MCDM Approaches ..................................................... 12
1.6.2 Multi-criteria Decision-making Process ..................................................................... 14
1.6.3 Multi-criteria Approaches ........................................................................................... 14
1.7 Historical Background of Reliability Analysis Issues ................................................... 15
1.8 Comprehensive Literatures Review related to Maintenance Planning .......................... 16
1.9 Literatures Review on Multi-criteria Decision-making (MCDM) based FMECA ........ 18
xvi
1.10 Motivation of Research ................................................................................................ 20
1.10.1 Outcome of Literature Review and Research Gap ................................................... 20
1.10.2 Definition of the Problem ......................................................................................... 20
1.11 Objective and the Scope of Work ................................................................................ 22
1.12 Research Approaches ................................................................................................... 24
1.13 Original contribution by the thesis ............................................................................... 26
1.14 Organization of Thesis ................................................................................................. 26
1.15 Summary ...................................................................................................................... 28
CHAPTER 2 ....................................................................................................................... 29
Data Collection, Reliability Modeling and Identification of Critical Components ..... 29
2.1 Overview of Identified Process Industry (Rolling Mill) ................................................ 29
2.1.1 Introduction and Background ..................................................................................... 29
2.1.2 Rolling Process ........................................................................................................... 30
2.1.3 Rolling Mill Components ........................................................................................... 30
2.1.4 Rolling Mill Properzi Process ..................................................................................... 32
2.1.5 Rolling Machine Sub-Components ............................................................................. 32
2.2 Major Reliability and Maintenance Issues during Preliminary Studies and Learnings
from them ............................................................................................................................. 34
2.3 Failure Data Collection and Analysis ............................................................................ 35
2.4 Reliability Modelling ..................................................................................................... 40
2.5 Discrimination of Critical Components of Rolling Mill ................................................ 45
2.6 Summary ........................................................................................................................ 48
CHAPTER 3 ....................................................................................................................... 49
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional
Approach ............................................................................................................................ 49
3.1 Failure Pattern Study of Critical Components through Failure Mode and Effect
Analysis (FMEA) ................................................................................................................. 49
3.1.1 Overview ..................................................................................................................... 49
3.1.2 FMEA for discriminated Critical Components ........................................................... 50
3.2 Selection of Criteria for Criticality Assessment ............................................................ 53
3.2.1 Traditional Criteria...................................................................................................... 53
3.2.2 Advanced Criteria ....................................................................................................... 53
3.3 Score Assignment Methodology .................................................................................... 54
3.3.1 Score Assignment for Traditional Approach .............................................................. 54
xvii
3.3.2 Score Assignment for MCDM based Failure Analysis Models.................................. 56
3.4 Traditional Failure Analysis Approach .......................................................................... 58
3.4.1 Overview ..................................................................................................................... 58
3.4.2 Criticality Assessment based on Risk Priority Number (RPN) .................................. 59
3.4.3 Maintenance Planning Through Traditional FMECA ................................................ 61
3.4.4 Drawbacks of Traditional FMECA ............................................................................. 62
3.5 Summary ........................................................................................................................ 63
CHAPTER 4 ....................................................................................................................... 64
Multi-criteria Decision-making based Failure Analysis Models ................................... 64
4.1 Overview ........................................................................................................................ 64
4.2 TOPSIS based Failure Mode Effect and Criticality Analysis ........................................ 65
4.2.1 TOPSIS Methodology ................................................................................................. 65
4.2.2 Maintenance Planning through TOPSIS FMECA ...................................................... 71
4.3 COPRAS-G based Failure Mode Effect and Criticality Analysis ................................. 73
4.3.1 COPRAS-G Methodology .......................................................................................... 73
4.3.3 Significance of COPRAS-G ....................................................................................... 79
4.3.4 Maintenance Planning through COPRAS-G FMECA ................................................ 79
4.4 PSI based Failure Mode Effect and Criticality Analysis ............................................... 81
4.4.1 PSI Methodology ........................................................................................................ 81
4.4.2 Significance of PSI ..................................................................................................... 86
4.4.3 Maintenance Planning through PSI FMECA .............................................................. 86
4.5 Summary ........................................................................................................................ 88
CHAPTER 5 ....................................................................................................................... 89
Results and Discussion ....................................................................................................... 89
5.1 General Overview .......................................................................................................... 89
5.2 Results of Discrimination Process through Shop-floor Statistics .................................. 90
5.3 Results of Traditional FMECA Model .......................................................................... 92
5.4 Results of MCDM based FMECA ................................................................................. 93
5.5 Suggested Remedies ...................................................................................................... 95
5.6 Summary ........................................................................................................................ 96
CHAPTER 6 ....................................................................................................................... 99
Conclusion and Future Scope ........................................................................................... 99
6.1 General Overview .......................................................................................................... 99
xviii
6.2 Major Concluding Remarks ......................................................................................... 100
6.3 Recommendations for Future Scope of Work ............................................................. 101
6.4 Limitations of Proposed Research Work ..................................................................... 102
6.5 Summary ...................................................................................................................... 102
References .......................................................................................................................... 103
List of Publications ............................................................................................................ 112
xix
List of Abbreviations
AHP: Analytical Hierarchy Process
ANP: Analytical Network Process
BCR: Benefit-to-Cost Ratio
CAGR: Compound Annual Growth Rate
CMMS: Computerized Maintenance Management Systems
COPRAS-G: Grey-Complex Proportional Risk Assessment
DTMM: Delay Time Maintenance Model
ELECTRE: Elimination and Choice Translating Reality
FAHP: Fuzzy Analytic Hierarchy Process
FMEA: Failure Mode Effect Analysis
FMECA: Failure Mode Effect and Criticality Analysis
GA: Genetic Algorithm
GP: Goal Programming
HGA: Hybrid Genetic Algorithm
JIT: Just-in Time
LEPs: Large Engineering Plants
LOLP: Loss of Load Probability
MACBETH: Measuring Attractiveness by a Categorical Based Evaluation
Technique
MAVT: Multi-Attribute Value Theory
MCDM: Multi Criteria Decision Making
MCI: Maintainability Criticality Index
MDT: Mean Down Time
MSF: Modeling System Failure
MTBF: Mean Time between Failure
MTTF: Mean Time to Failure
MTTR: Mean Time to Repair
OJT: On the Job Training
PM: Preventive Maintenance
PROMETHEE: Preference Ranking Organization Method for Enrichment
Evaluation
PSI: Preference Selection Index
xx
QBD: Quasi-Birth–Death
RDCIS: Research & Development Centre for Iron and Steel
RNN: Recurrent Neural Network
RPN: Risk Priority Number
RRE: Reusable Rocket Engine
SA: Simulated Annealing
SAIL: Steel Authority of India Ltd.
TOPSIS: Technique for Order Preference by Similarity to Ideal Solution
TPM: Total Productive Maintenance
TQM: Total Quality Management
WSM: Weighted Sum Model
xxi
List of Symbols
Scores for probability of occurrence (P) for i
th alternative and j
th criteria in
traditional FMECA
: Operational availability
: Inherent availability
Scores for degree of detectability (D) for ith
alternative and jth
criteria in
traditional FMECA
C1: Improper lubrication & defective sealing
C2: Higher speed than specified
C3: Design defects, bearing dimension not as per specification
C4: Foreign matters/particles
C5: Sudden impact on the rolls
C6: Loss of power
C7: Inadequate lubrication - dirt, viscosity issues
C8: Improper meshing, case depth & high residual stresses
C9: Overheating at gear mesh
C10: Excessive overload & cyclic stresses
C11: High contact stresses due to rolling & sliding action of mesh
C12: Vibratory dynamic load from bearing
C13: Uneven bearing load
C14: Reverse & repeated cyclic loading
Degree of unity in percentage (%) contribution for ith
failure cause
Scores for degree of severity (S) for ith
alternative and jth
criteria in
traditional FMECA
D: Degree of detectability
: Distance between positive ideal solutions in TOPSIS
: Distance between negative ideal solutions in TOPSIS
Deviation in preference value in PSI jth
criteria in PSI
: Downtime
EC: Economic cost
ES: Economic safety
: Entropy of jth
criteria in TOPSIS
xxii
: Hazard rate
M: Degree of maintainability
Maximum value of relative weight of Maintainability criticality index
among all alternatives
: Maintainability criticality index for COPRAS-G
: Maintainability criticality index for PSI
: Maintainability criticality index for TOPSIS
: Mean Downtime
: Mean time between failures
: Mean time between maintenance,
: Mean time to repair
: Frequency of failure
Score for normalized decision matrix – X in PSI
Overall preference value for jth
criteria in PSI
P: Probability of chances of failure
Weighted mean normalized sums of beneficial criteria
Preference variation value for jth
criteria in PSI
Weighted mean normalized sums of non-beneficial criteria
Score for normalized decision matrix – X in TOPSIS
S: Degree of severity
: Positive ideal solution in TOPSIS
Negative ideal solution in TOPSIS
SP: Spare parts
: Total time
: Uptime
Score for decision matrix – X in TOPSIS
Maximum score value of each alternative
Minimum score value of each alternative
; : Lower and upper score value of decision matrix – X in grey interval in
COPRAS-G
Lower and upper score value of normalized decision matrix – X1 in grey
interval in COPRAS-G
xxiii
: Lower and upper score value of weighted normalized decision matrix –
X2 in grey interval in COPRAS-G
: Weight of jth
criteria in TOPSIS
xxiv
List of Figures
Figure
No. Title
Page
No.
1.1 Bathtub curve (Ebling Charles, 2016) 03
1.2 Effect of planned maintenance on failure rate (Moubray
John, 1997) 04
1.3 Series network 05
1.4 Parallel network 05
1.5 Redundant reliability model 06
2.1 Rolling mill plant layout 30
2.2 Rolling mill components with their functional details 31
2.3 Actual image of rolling machine (Fifteen stands) 31
2.4 Rolling mill process flow (Properzi) 32
2.5 Hazard rate curve for rolling mill 44
2.6 Availability curve for rolling mill 45
2.7 Criticality curve for reliability parameters (rolling
machine components) 46
2.8 Criticality curve based on losses in production volume
and cost 46
3.1 Some photographs of the observations made at shop-
floor study 51
3.2 General flow process of traditional FMECA 58
4.1 Flow Diagram of MCDM based FMECA process 65
5.1 Pie chart presentation for % failure contributions of
components 90
5.2 RPN for each failure cause based on traditional FMECA 93
5.3 MCI for each failure cause based on MCDM based
FMECA 94
xxv
List of Tables
Table
No. Title
Page
No.
1.1 Comparisons of few researchers’ considerations with
presented study
21
2.1 Format for master list of machineries/component 36
2.2 Format for breakdown maintenance records 37
2.3 Format for preventive maintenance check list 37
2.4 Part-wise failure data of rolling machine (Duration: April
- 2013 to March - 2014)
39
2.5 Month-wise summary of failure data of rolling mill –
reliability modeling (Duration: April -2013 to March -
2014)
42
3.1 FMEA of derived vital parts 52
3.2 Scores for probability of occurrence (P) 55
3.3 Scores for degree of detectability (D) 55
3.4 Scores for degree of severity (S) 55
35 Scores for degree of maintainability (M) 57
3.6 Scores for spare parts (SP) 57
3.7 Scores for economic safety (ES) 57
3.8 Scores for economic cost (EC) 58
3.9 Decision matrix – X for traditional FMECA 60
3.10 Risk priority number (RPN) for traditional FMECA 60
3.11 RPN based FMEA with existing practices and proposed
improvements in maintenance plan
61
4.1 Decision matrix – X for TOPSIS 67
4.2 Normalization of decision matrix – X for TOPSIS 68
4.3 Distances between positive and negative ideal solution 70
4.4 Maintainability criticality index and criticality
rank for TOPSIS
71
xxvi
4.5 based FMEA with existing practices and
proposed improvements in maintenance plan
72
4.6 Decision matrix – X for COPRAS-G 75
4.7 Normalized decision matrix – for COPRAS-G 76
4.8 Weighted normalized decision matrix – for
COPRAS-G
77
4.9 Maintainability criticality index and (%)
contribution for COPRAS-G
79
4.10 based FMEA with existing practices and
proposed improvements in maintenance plan
80
4.11 Decision matrix – X for PSI 82
4.12 Normalized decision matrix – for PSI 84
4.13 Multiplication matrix of and 85
4.14 Maintainability criticality index and rank for PSI 85
4.15 based FMEA with existing practices and
proposed improvements in maintenance plan
87
5.1 Outcome of shop-floor data regarding performance of
rolling machine parts
92
5.2 Outcome (RPN) of traditional FMECA and suggestions 93
5.3 Outcome ( ) of MCDM FMECAs and suggestions 94
5.4 Maintenance optimization action plan 97
1
CHAPTER 1
Introduction and Literature Review
1.1 Broad Area of Research
The present research study is focusing on the area of reliability engineering, maintenance
management and failure pattern of the process industries influencing their performance.
Moreover, the research work also discusses the multi-criteria decision making methods to
enhance failure models. The area as reliability engineering deals with the methods of
reducing the failure frequencies by identifying and rectifying the causes of failures. The
accountability of maintenance management is to ensure efficient functioning of the
processing units or their systems and components with optimized capacity. The failure
pattern study helps to understand the failure causes, effects and their consequences. The
study is exploring the scope of failure mode and effect analysis and its modification as a
promising tool for targeting reliability problems. The area of multi-criteria decision
making encompasses the instinctive assessment of various criteria with interdependency.
Such tools are reasonably new in the failure analysis problems associated with processing
units to effectively make decisions. The presented study is smoothly integrating all such
areas in consideration of research objectives.
1.2 Overview and Significance of Study
The reliability subject is essential for maintenance personnel like; service managers and
plant technocrats alike, for keeping the components in a ready state. The reliability
engineering helps to identify the fault-diagnosis of component or system, compare
Introduction and Literature Review
2
several consequences of failure in a view to plan and maintain them effectively. It is
imperative to mix regular and planned maintenance retaining the reliability and
availability of components. A proper reliability analysis will help the plant managers
enhancing system’s working and maintaining task as well. The conditions of operation
and repair strategies of the processing unit are crucial in maintaining the operating
systems with the highest uptime. This is achieved only through the performance
evaluation and analysis of critical components of the process industry. Moreover,
maintenance planning and optimization are complex and stochastic, which require multi-
criteria approaches for enhancing mean time between failure (MTBF), mean time to
repair (MTTR) as well as other reliability parameters. The issues or drawbacks of
maintaining non-performing things of the processing unit are covered under the proposed
study. The system performance can be measured in reliability and analyzed in real
working conditions to optimize maintenance activities of concern aluminium rolling mill.
1.3 Brief Overview about Reliability
1.3.1 Reliability Concept
Reliability is defined as the probability that the part, sub-system or unit will perform its
required job adequately for given period of time under specified design life
(Balagurusamy, 1984). This parameter is important as the repairs should always be
considered in a determination of reliability for the repairable system. Reliability is a time-
dependent property which can be predicted at any time during the process but can be
evaluated after an elapsed time. The unreliability is defined as the probability that the
part, sub-system or unit will not perform its desired function for given orders within
specified design life.
Important features of reliability are;
Reliability works on the concept of probability and its value ranging between 0
and 1.
Use of well-established and simple design leads high reliability of the
components.
Redundancy increases high risk of failure and leads to lower the reliability.
1.3 Brief Overview about Reliability
Poor shop-floor activities, complexities in system, poor maintenance practices,
lack of skill and human errors increases unreliability.
Assessing system reliability by finding faults at each subsystem and their
contribution in overall unreliability is essential for performance reliability
improvement.
Efficient reliability analysis should be supported with good mathematical
reliability models.
Reliability can be enhanced by using high-rated component with design
improvement, simplicity and better maintenance practices.
1.3.2 Significance of Mortality (Bath-tub) Curve
The mortality curve is representing the failure rate of the components in three different
zones. The components are experiencing single or any combinations of zone during a
lifetime as shown in Fig. 1.1. According to the shape of curve, it is also called the bath-
tub curve (Mishra and Pathak, 2012).
FIGURE 1.1 Bathtub curve (Ebling Charles, 2016)
In the first stage, the rate of failure suddenly decreased from large initial failure due to
machining or commissioning errors which is called burn-in zone. Once the machine
components pass this stage, it is entering into the long-life zone without hurdles.
However, the scheduled maintenance may send such components back into the burn-in
zone as shown in Fig. 1.2. For example; if similar bearings groups are imposed planned
maintenance, they may suffer burn-in period. The proper maintenance strategies on
Introduction and Literature Review
4
showing signs of imminent failure are good to increase the design life of such
components.
The second stage of bath-tub curve is constant failure rate region and third and final stage
experienced the sudden rise of the failure rate due to parts or components wear-out. The
bath-tub curve is very useful in understanding failure-form of major industrial processes.
The simple as well as the complex system is following such failure pattern which helps to
understand failure pattern of the components or system to enhance reliability.
The planned maintenance increases the maintenance task due to an increased failure rate
as the parts or components are experiencing infant mortality after maintenance. If the
parts or components are allowed to run till failure by incorporating proper condition-
based techniques, the average life of the components are extended.
FIGURE 1.2 Effect of planned maintenance on failure rate (Moubray John, 1997)
1.3.3 System Reliability Models
The important system reliability models with their configurations are discussed as under
(Balagurusamy, 1984):
1.3.3.1 Series networks
In the series model, the components are in a series manner and the system is said to be
successful only when all its components are successful. Consider reliability model in
which n components with reliabilities , …., are connected in series. The
reliability of the complete system would be;
1.3 Brief Overview about Reliability
……. (1.1)
FIGURE 1.3 Series network
In this configuration, the failure of any one component affects the system in shut down.
An alternate exponential formula for calculating the reliability of a series network is
given as;
(1.2)
Where = the total parts working in series manner
1.3.3.2 Parallel networks
In this configuration, it is possible for the system to be partially operative even if some of
its components are in non-working condition. Considering the configuration of n
components having reliabilities , …., which are connected in parallel. The
reliability of the system can be derived from the following equation;
(1.3)
Where; =
FIGURE 1.4 Parallel networks
1.3.3.3 Redundant Reliability Model
If the system contains both series and parallel components to obtain higher reliability,
then the reliability of it is calculated similarly as discussed in parallel and series
Introduction and Literature Review
6
arrangements. The analysis of a system is done by combining all components into
equivalents serially. Following configuration helps to analyze the system effectively.
FIGURE 1.5 Redundant reliability models
1.3.3.4 The x – out of – m structure
This type of configuration is another important practical system in which spare
components are paralleled to reduce downtime. The binomial distribution is good to
determine reliability of the systems with identical and statically independent components.
According to the binomial theorem, the probability of x out of m components is evaluated
with the help of following expression;
(1.4)
Where;
p = the probability of components in working condition
( ) (1.5)
So, system reliability is the addition of binomial probabilities as follows;
R = ∑ (1.6)
1.3.3.5 System with mixed mode failure
For the component having double failures, reliability is expressed as;
(1.7)
Where; and are failure probabilities due to short mode and open mode respectively.
1.4 Brief Overview about Maintenance
1.3.4 Reliability Analysis through Failure Distribution Function
As demonstrated by Balagurusamy (1984), it is necessary for reliability failure data
which are collected from either experiment or field observations to have their appropriate
distribution due to random in nature. Sometimes it is difficult to gather sufficient data for
accurate analysis. Understanding the pattern such data can be possible through some
failure distributions as listed below through which proper reliability analysis can be done:
Binomial
Exponential
Gamma-Poison
Normal and logarithmic-normal
Weibull type
Normal and exponential distributions are good, however, Weibull distribution is an
important distribution used in the analysis of reliability of the system. By properly
selecting the parameters the curve obtained can be represented with field observations.
1.4 Brief Overview about Maintenance
Since last decade, the maintenance has changed than any other management philosophy
because of increasing diversification of engineering resources including automation.
These assets should be maintained throughout their lifespan. Moreover, more complex
designs need to explore the scope of optimal ideas of up keeping resources. Maintenance
process is reacted and influenced for creating awareness about equipment failure
concerning quality, safety, environment, and increasing pressure to achieve high-
performance reliability with little or no cost.
Maintenance is the process of optimizing the available resources such as; manpower,
materials, machinery, tools and testing equipment within the asset in a view to achieve
objectives and goals of an organization (Khanna, 2010). Pintelon and Gelders (1992)
defined the maintenance activity as the process to restore as well as to keep the
equipment in a designated working environment.
Introduction and Literature Review
8
The goal of any organization is profit making by performing tasks as cost-effective as
possible. The primary objectives of maintenance management as discussed by Van Raijn
(1987) for industries are:
(i) to maximize the volume and capacity with consideration of reliability and
availability of the component,
(ii) to optimize safety and environmental ease
1.4.1 Maintenance Philosophy
As discussed by Khanna (2010), the maintenance philosophy is to optimize productivity
and plant availability with minimum consistent maintenance team and safety. The right
mixing of the following strategies is effective to obtain such philosophy.
(i) Breakdown Maintenance: In this process, a machine is allowed to run until it fails.
Several machines are maintained in this way without financial justification. It
leads loss of reliability due to the excessive delay in the production.
(ii) Scheduled Maintenance: It is the regular time-interval procedure so that sudden
failures can be prevented. The inspection, repair and overhaul, lubrication etc. are
covered under this strategy.
(iii)Preventive Maintenance: In this type of maintenance plan, each critical machine is
shut down after a specified period of time and replacement or repair of worn-out
parts is carried out based on the inspection. It works on the principle of prevention
is better than cure. The life of the components can be improved with additional
safety and low cost. However, it cannot guard against deterioration between
overhauls.
(iv) Total Productive Maintenance (TPM): It is fundamentally the management tool in
which all employees of the organization are involved for maintenance
improvement task. It works on a Japanese concept where; total quality
management (TQM) and just in time (JIT) concepts are applied over equipment
maintenance area.
(v) Predictive Maintenance: In predictive maintenance, the condition of machine
components are regularly measured and recorded. The fundamental difference
between preventive maintenance and predictive maintenance is that first type is
done immediately upon the progress of pre-determined period. Whereas in
1.4 Brief Overview about Maintenance
predictive maintenance inspection or condition monitoring is done at pre-decided
regular intervals to decide maintenance. This type of maintenance strategy is used
to overcome the limitations of previously discussed maintenance types.
(vi) Reliability – Centered Maintenance (RCM): Moubrey (1997) discussed the role of
reliability modelling focusing the maintenance activities in a manner to retain
reliability of the components or system. The process of RCM employs FMEA to
understand the plan of maintenance of components effectively.
There are several maintenance strategies as discussed above which can be implemented
in any manufacturing or processing plant. The manufacturing or process equipment is
complex in nature and needs skilled personnel which lead increasing the maintenance
costs (Albert and Tsang, 1995). The decision-making approach helps to decide better
tools in various processing units including rolling mill. Fulop (2005) recommended the
usefulness of the decision-making process in identifying maintenance approaches which
satisfy the objectives of process industry in terms of profit. Some efforts were made to
bring such models to different aspects of maintenance management in the past. However,
it is a new and broad tool which exhibits the scope for modelling maintenance
management activities in many process industries.
In the large process industry, the aim of the production department is to manufacture a
planned output over definite time based on sales demand. The system or sub-system of it
may be in one of the following conditions;
In production process
No need for production
Under scheduled maintenance
Under corrective maintenance due to unexpected failure
Non-operational due to a shortage of maintenance resources
The maintenance optimization model should be presented by considering the parameters
affecting the availability and condition of the plant to gather. So, the function of the
maintenance team is to repair, replace, correct or modify the system or component of the
processing plant to make it operational with optimum performance reliability.
The important engineered maintenance strategies are discussed as under in a view to
improving component reliability. (Khanna, 2010).
Introduction and Literature Review
10
(i) Planned-maintenance: In this strategy, the major maintenance task is split into the
minor scheduling-based task by integrating activities pre-planned.
(ii) Emergency Maintenance: It works on two approaches; in the first approach,
exigencies are handled with routine scheduling thereafter pending issues are covered
with contractual or ad-hoc workers or by providing overtime to regular workers. It is
proved strategy for processing units to allow about 15% of emergencies. The second
approach includes; estimation of an amount of emergency maintenance and
assignment of a work order to skilled and dedicated workers.
(iii)Reliability Improvement: The reliability improvement approach offers a sound
alternative for improving the maintenance task in which critical and major
equipment’s historical records are observed to monitor MTBF behaviour.
(iv) Equipment Management Program: It deals with generating TPM plan to almost all
parts of an instrument in the view to provide the satisfactory improvement in
maintenance performances.
(v) Cost Reduction: This approach works on the principle of reducing costs with
alternative materials, methods of service and overhaul, tooling and equipment,
scheduling and time standards.
(vi) Training and Employee Motivation: The art of optimum performance is always skill-
based which required an on-the-job-training (OJT) program to ensure that person
should have enough skills with high motivation.
1.4.2 Systematic step-by-step method for planning maintenance program
The systematic step-by-step process of the planning a maintenance program as suggested
by Khanna (2010) is as under:
(i) Determine the critical plant units by dividing the plant into units considering the
nature of the plant process. Then, failure analysis and estimation of the loss of the
production and availabilities should be done.
(ii) Classify the plant into constituent items. The classification is complex for the units
having high criticalities.
(iii) Decide the appropriate process to each item or component and assign them a rank
based on the cost and safety viewpoint.
(iv) Establish a plan for the identified critical components based on the type and
complexity of the plants.
1.5 Brief Overview about Failure Mode Effect and Criticality Analysis (FMECA)
(v) Establish the on-line and off-line maintenance schedule, corrective or preventive
maintenance, condition-based maintenance, shutdown etc. Unexpected failures
should be planned under spare management.
1.5 Brief Overview about Failure Mode Effect and Criticality Analysis
(FMECA)
1.5.1 Concept
The FMEA is the structured process of identifying, analyzing and documentation of
possible issues of component or system (Mcdermott et al., 2009). The failure
consequences on performance are reviewed and appropriate remedial measures are
imposed to eliminate or control them. It includes criticality analysis called; FMECA
which is an important reliability approach for avoiding costs experienced from product
failure.
FMECA is useful in following important activities;
Overall design process
Concept development phase to reduce the cost of design changes
Testing
Design modifications etc.
Other tools like; brainstorming; verification, fault tree analysis, data and record keeping,
material selection and procurement etc. are considered together with FMECA in order to
gain advantages.
FMECA is a most common tool for the planning the maintenance activities of the process
industries through reliability analysis among various tools. FMECA mainly consist of
two different approaches; (i) failure-mode and analysis of its effect and (ii) criticality
analysis. The FMEA is the technological tool for explaining, recognizing or removing
issues of the design process (Omdahl, 1988). It is one of the earliest preventive measures
which are reducing system or design failures (Kececioglu, 2002).
In FMECA, RPN is calculated with a multiplication of the scores of criteria like;
probability of chances of failure (P), detectability (D), and severity of the effect (S). It
helps to identify defects or failures happen in processing or element through structured
Introduction and Literature Review
12
conceptualized discussion among experts (Vandenbrande, 1998). Dhillon (1985) and
O’Conner (2002) defined FMECA as a committed tool to evaluate the system reliability
with a review of possible failures modes with their consequences. It also provides the
organized way to determine criticalities considering risks as the final point in failure
study problem (Holmberg, 1991).
1.5.2 Types of FMEA/FMECA
There are three common types of FMEA as discussed below (Mcdermott et al., 2009) :
(i) System or concept FMEA: It is focusing system related deficiencies by
integrating the concept of system or sub-system in early stages. It provides
effective coordination between a system and surrounding considering single
failures.
(ii) Design FMEA: It is focusing component related design deficiencies by
involving adjacent components ensuring reliable performance for useful life.
This type of FMEA is normally implemented at a component, sub-system or
system level.
(iii) Process FMEA: It is focusing on process related deficiencies by incorporating
manufacturing and assembly operations, inward, storage and dispatch of
components or spares, conveying and maintenance processes. It ensures the
product should be manufactured to design specifications with minimum
downtime.
1.6 Brief Overview about Multi-criteria Decision-making (MCDM)
1.6.1 Overview and Importance of MCDM Approaches
Due to rapid technological and economic growth from the past few decades, the process
industries are facing complex problems in taking decisions. MCDM is very useful in
taking a decision where several alternatives are possible. It is very common practice to
select the most preferable alternatives through several mathematical models which are
developed recently. The MCDM tools are attracting academicians, practitioners etc. to
make convenient decision-making during conflicting situations of various criteria jointly.
International society on multiple-criteria decision-making defined the MCDM as the
1.6 Brief Overview about Multi-criteria Decision-making (MCDM)
process of consolidating disputed and numerous criteria together by the ways of
decisions.
The MCDM approaches started during early 1971. The growth of MCDM approaches is
due to pressing need of considering several criteria to the reliability problems of major
industrial processes including rolling process. It helps maintenance practitioners’ to
enhance the decision-making with recent advancements in optimization methods. Many
research articles and studies reflected the effect of MCDM paradigm on business,
engineering, and science where experts of various branches are assembled (Wiecek et al.,
2008).
Eshlaghy and Homayonfar (2011) considered three hundred eighty-six research papers
about the applications of MCDM approaches in various areas to know the facts about
state of art of work in MCDM domain. The results show the various categories as
follows: energy affairs twenty papers (about 5%), transportation and logistics matters
seventy eight papers (about 20%), strategic planning forty three papers (about 11%),
business and financial management fifty papers (about 13%), manufacturing and
assembly consideration thirty five papers (about 9%), environment affairs thirty four
papers (about 9%), water management twenty two papers (about 6%), agricultural and
forest area twelve papers (about 3%), project management thirty eight papers (about
10%), social welfare eleven papers (about 3%) and military domain eight papers (about
2%) and other general topics like; general science, sports etc. thirty five papers (about
9%).
There is very little application of MCDM approaches in processing plants to improve the
performance in different aspects including maintenance optimization. The major
industrial processing units are facing crucial problems of loss of reliability due to
components failures and breakdowns. All such plant’s performance depends on various
parameters or criteria. It seems very difficult to establish interdependence among all
criteria through traditional approaches. The requirement leads MCDM tool as a better
alternative for handling the problems associated with components failures and planning
effective maintenance plan among decision-makers.
Introduction and Literature Review
14
1.6.2 Multi-criteria Decision-making Process
Janssen (2001) and Macharis et al. (2004) explained that MCDM is an explicit and
structured way to gain reasonable outcome by enhancing objectives satisfactorily. Roy
(1996) proposed a MCDM based solution in conflicting conditions as follows:
(i) Define the set of actions; say set S and the group of criteria; say group C
(ii) Decide best actions subset of in accordance to group C
(iii) Sorting of set S into subsets with their features
(iv) Assign rank to the activities of set S on basis of good to bad
(v) Discuss bad effects in a structured manner in a view to evaluate them effectively
The decision-making process flows step-by-step, however in case of addition of new
data; the process is repeated from any desired step. Yoe (2002) explained the MCDM
process as given below:
(i) Define the MCDM problem and its objectives.
(ii) List and explain alternatives to satisfy objectives.
(iii) Interpret criteria evaluators for the fulfillment of various options.
(iv) Collect data to determine the criteria.
(v) Build the decision-matrix for alternatives versus criteria.
(vi) Obtain unbiased weights for each criterion.
(vii) Assign ranking to alternatives and present the results to concern team.
(viii) Decide to recommendations of concern team group to obtain results.
1.6.3 Multi-criteria Approaches
Roy (1996) categorized the MCDM approaches into the following groups according to
their similarities, one multi-attribute concept; second out-ranking approaches; and third
interactive tools as under:
(i) Unique criterion method: It involves combining many perspectives into the
definite function to be optimized. For example; TOPSIS approach.
(ii) Out-ranking method: It involves the growth of an out-ranking relationship with
choice of decision-makers, to facilitate decision-maker solving problems. For
example; ELECTRE approach.
1.7 Historical Background of Reliability Analysis Issues
(iii) Interactive local judgment method: This method is based on trial-error relation
who provides alternative calculations with successive compromising solutions,
in a view to have additional knowledge to the choice of decision-taker (Vincke,
1992).
Some important MCDM approaches are listed as under:
AHP; Analytical hierarchy process
ELECTRE; called elimination and choice translating reality
GP or goal programming
COPRAS-G; Grey-complex proportional risk assessment
MACBATH means; measuring attractiveness by a categorical-based evaluation
technique
MAVT i.e. multi-attribute value theory
PROMETHEE or preference ranking organization method for enrichment
evaluation
PSI; Preference selection index approach
TOPSIS called; a technique for order preference by similarity to ideal solution
WSM i.e. weighted sum model
Many MCDM methods (e.g. TOPSIS, COPRAS-G) use the weight criteria in deciding
criticalities. These weights are keys to evaluate the overall preferences of alternatives.
MCDM methods utilize the different weights due to different groupings. It is very
essential for a decision-maker to correctly apply weights to alternatives for satisfactory
results.
1.7 Historical Background of Reliability Analysis Issues
From last five decades, reliability engineering is considered an important branch of
science. A study of reliability engineering helps in understanding the difficulties
associated with repairable systems. Development of reliability engineering is due to
quality control and its need. American Society for Mechanical Engineers (ASME) in
association with Bell laboratories was using statistical quality control during early the
1920s. Thereafter mathematical consideration of reliability was used in military
technology during the Second World War in 1939. Weibull studied fatigue life in
Introduction and Literature Review
16
materials and proposed failure distribution function to fit data and observations especially
for reliability analysis.
The reliability analysis issues were discussed almost half-century back. These issues are
considered as useful in the field of reliability modelling, risk analysis and maintenance
planning. Barlow and Proschan (1965) proposed some mathematical practices in
maintenance activities. Jensen (1995), Dekker (1996) and Pham and Wang (1996)
discussed the maintenance models and their classification. Sikorska (2008) presented the
scope to improve the quality of failure histories stored in computerized maintenance
management systems (CMMS).
1.8 Comprehensive Literatures Review related to Maintenance Planning
Ashayeri et al. (1996) proposed mixed-integer linear programming based modification in
preventive maintenance schedule and production order of processing plant. Knapp (1998)
proposed a model to distribute maintenance personnel in proper quantity and quality at
proper workplace and time by precisely indicating the role of employees to improve
performance reliability in processing units. Santos et al. (1999) suggested the need of
efficient management system for the process industries which covers major factors to
reduce operating costs. They prepared the genetic algorithm for production sections of
kraft pulp and paper industry to introduce forced shutdowns. Parida et al. (2000)
explained the joint efforts of SAIL and Rourkela steel plant, and research and
development centre for iron and steel (RDCIS) to implement total productive
maintenance (TPM). They recommended vibration monitoring and analysis to do such
task effectively. Marseguerra et al. (2002) proposed a multi-objective genetic algorithm
(GA) to optimize profit and availability for determining the optimal degradation level.
Chen et al. (2004) discussed the optimization of fed-batch bio-reactor with recurrent
neural network (RNN) and genetic algorithm (GA) jointly to obtain optimal feed rate.
Sortrakul et al. (2005) suggested an approach for integrating production timings and
precautionary maintenance management through heuristic based GA tool and show its
effectiveness numerically through various problems. Abdullah et al. (2006) described the
genetic algorithms (GA) based solutions to the problems of multiple objectives with
diverse fitness functions. Eti et al. (2006) discussed the need of condition monitoring in
PM through FMECA, root-cause analysis, fault-tree analysis etc. Ghosh and Roy (2006)
1.8 Comprehensive Literatures Review related to Maintenance Planning
discussed the benefit-to-cost ratio (BCR) based methodology to optimize the preventive
maintenance of processing units whose failure distribution function is either exponential
or Weibull. Nastac and Thatte (2006) described the potential fault locations based on
software tool and genetic algorithm and presented the results achieved from this tool.
Andrawus et al. (2007) highlighted two approaches; modelling system failure (MSF) and
delay time maintenance model (DTMM) to the windmill for maintenance planning. They
highlighted the relevance and applicability of these techniques for optimizing the
maintenance of wind turbines. Mohanta et al. (2007) used a genetic algorithm (GA) and
simulated annealing (SA) with stochastic reliability as an objective function to evaluate
the loss of load probability (LOLP) for maintenance of components of captive power
plant like; boilers, turbines and generators. Nguyen and Bagajewicz (2008) suggested
preventive maintenance optimization with the help of GA and Monte Carlo simulation
techniques to evaluate the cost and economic loss. Sikorska (2008) explored the scope of
quality improvement of historical records of failures, which are stored in computerized
maintenance management systems (CMMS) through cost evaluation algorithm.
Mahadevan et al. (2010) discussed the maintenance planning problems for a process
industry to decide substitution or repairing the subsystems with the use of a hybrid
genetic algorithm (HGA). Nguyen and Bagajewicz (2010) proposed the optimal
preventive maintenance to processing plants through the genetic algorithm to equipment
and labour allocation task. Sanjeev Kumar (2010) developed the optimized models in
terms of availability for units of fertilizer processing unit considering steady-state
behaviour. Verma et al. (2010) recommended three-pronged strategies to establish e-
maintenance for large engineering plants (LEPs) and derived the scope of their results as
inputs to upgrade the condition monitoring methods. Moghaddass et al. (2011) addressed
x - out-of - m configuration to dissimilar units for efficient assessment of the availability
of systems in order to get steady state solutions through a non-homogeneous process
called QBD i.e. quasi-birth death process. The correctness and efficiency of proposed
methods were demonstrated with the help of analogue Monte Carlo simulation in their
study. Mehdi et al. (2011) focused to get the optimal balance between costs and benefits
of maintenance with its execution time on the existing maintenance optimization models.
Braaskma et al. (2012) presented the application of FMEA for industrial practices and
summarized descriptions and assumptions of FMEA into six postulates which helps
maintenance practitioners to access their potentials for implementing FMEA. Godwin et
al. (2012) discussed the critical failures of various subsystems like; impact crusher, air
Introduction and Literature Review
18
slide, conveyor and separator system, elevator and gear assembly etc. of the raw mill in a
view to developing the cost-effective maintenance plan through analytical hierarchy
process (AHP) and goal programming (GP). Zhixian and Guobin (2012) developed the
genetic algorithm based optimization model for aircraft maintenance to minimize the
cost. Lynch et al. (2013) described the effect of maintenance plan on the performance of
an industrial system by considering preventive maintenance optimization through a
genetic algorithm. Chen et al. (2013) modeled genetic algorithm based PM i.e. preventive
maintenance scheduling with the concept of life-age for RRE i.e. reusable rocket engine.
1.9 Literatures Review on Multi-criteria Decision-making (MCDM)
based FMECA
By reviewing and analyzing literature, it is found that various researchers enhanced
FMECA through MCDM approaches to overcome the drawbacks of many processing
plants. Hwang and Yoon (1981) proposed MCDM significance by considering disputed
and diverse criteria on educational or corporate affairs. Gilchrist (1993) suggested an
expected cost model with economic considerations through modifying FMECA;
Bevilacqua et al. (2000) incorporated operating state as new criteria for power processing
unit to enhance FMECA; Braglia (2000) integrated financial affairs in traditional
FMECA to analyze reliability and failure mode. Xu et al. (2002) evaluated an automobile
engine to alter FMEA through fuzzy logic. Braglia et al. (2003) suggested modifications
in conventional US MIL-STD-1629A approach using fuzzy TOPSIS to domestic
appliance producing industry of Italy. Sahoo et al. (2004) explained the FMECA is
essential for any maintenance plan and help to improve system reliability by reducing
overall maintenance cost. Sachdeva et al. (2009) approached paper processing unit with
MCDM based TOPSIS to re-order priority of causes of failure. Gargama and Chaturvedi
(2011) discussed risk factors in fuzzy linguistic variables to induce fuzzy rank priority
number. Maniya and Bhatt (2011) approached the problem of facility layout design
selection criteria through PSI based MCDM approach. Zammori and Gabbrielli (2011)
enhanced FMECA jointly with multi-criteria analytical network process (ANP) by
dividing fundamental criteria into sub-criteria to determine RPN. Liao et al. (2012)
illustrated preference orders of possible modes of failure through clouding FMECA for
1.9 Literatures Review on Multi-criteria Decision-making (MCDM) based FMECA
electrical transformers quantitatively. Feili et al. (2013) proposed FMEA approach to
comprehend the primary issues of units of geothermal power processing plant failures.
Adhikary and Bose (2014) discussed MCDM based COPRAS-G approach to thermal
power unit fueled through coal considering personnel’s features and working condition as
extra criteria. Fragassa et al. (2014) discussed FTA and RDA blended FMECA to
numerous diesel-suction systems with consideration of optimizing manufacturing
processing elements covering metal wire processing. Liu et al. (2015) highlighted the
joint use of fuzzy AHP and entropy method in fuzzy VIKOR for assigning weights to risk
factor for avoiding uncertainty and vagueness due to individual perception and
experience. Mobin et al. (2015) integrated the fuzzy AHP and COPRAS-G to assign
prime concern to suppliers of the household device producing company of Iran. Zhang
(2015) proposed fuzzy TOPSIS with unbiased weights for determining closeness-
coefficient for various causes of failure so that score calculation errors can be controlled.
Chanamool and Naenna (2016) incorporated fuzzy FMEA to the trauma center of a
hospital for planning and assessment of working failures of it. Fragassa and Ippoliti
(2016) discussed the use of FMECA in the complex situation of continuous production
and end with a list of modifications to be used for improving the plant design in the way
to reduce the maintenance task. Mittal et al. (2016) assigned ranks to severe issues of
plywood processing plant with the help of MCDM based fuzzy TOPSIS in order to refine
them effectively. Rathi et al. (2016) described MCDM based fuzzy VIKOR to look after
problems and their scenario of Indian automobile domain and strengthen the performance
of six-sigma. Rastegari et al. (2017) proposed monitoring the condition of vibrations for
spindles of gear-box producing enterprise situated in Sweden to establish a proper
maintenance plan. Farley and Miller of Innoval technology Ltd. presented three parts on
maintaining rolling mill performance. In the first part, they identified some factors
responsible for unhealthy rolling mill performance over time. In the second part, they
discussed the overall equipment efficiency (OEE) based approaches to improve rolling
mill performance and in third part they explained guidelines to avoid an initial decrease
in performance of new mill through good design, training and technical support.
Introduction and Literature Review
20
1.10 Motivation of Research
The study is proposed in the field of reliability-centered maintenance based issues in
processing plant as its research interests are an excellent match for my academic
background. Competitive global market demands high reliability with optimized
maintenance. The motivational factors like; research gap and expected business growth of
an aluminium wire are discussed in following sections and then problem is defined.
1.10.1 Outcome of Literature Review and Research Gap
Literature reviews state that failure mode effect and criticality analysis (FMECA) is an
accepted tool for enhancing maintenance practices in the processing unit. Moreover, it
helps to identify defects or failures happen in processing or element through structured
conceptualized discussion among experts (Vandenbrande, 1998). Dhillon (1985) and
O’Conner (2002) defined FMECA as a committed tool to evaluate the system reliability
with a review of possible failures modes with their consequences.
Literature review seems certain possibilities of the performance reliability improvement
through maintenance optimization of systems or components of major process industries
that run on continuous basis. The challenges of keeping the system in ready-state
necessitate a definite maintenance plan to be modeled based on a live failure analysis to
be executed during shutdown or scheduled period. Table 1.1 shows comparisons of some
researchers’ contributions with presented work to exhibit motivation of research study.
Moreover, the exploration about literature shows that former researchers did not reflect a
case for three MCDM approaches simultaneously applied to any process industry. There
is a huge scope of improvement in reliability by optimizing maintenance practices
through MCDM based failure analysis models in processing plants and advocate a need
to address such interesting issues in form of the research study.
1.10.2 Definition of the Problem
Many researchers have presented modified FMECA approaches to various industries, but
quality research is lacking in aluminium wire rolling mill which forms a noticeable sector
of the process industry. Looking to the past business volume of aluminium wire about
6,50,000 metric tons during 2015 in India, an aluminium wire processing mill is consider
important for the study. (The sixty eighth report of IEEMA, 2014-15).
1.10 Motivation of Research
TABLE 1.1 Comparisons of few researchers’ considerations with presented study
Braglia et
al. (2003)
Sachdeva
et al. (2009)
Feili et.al
(2013)
Adhikari
and Bose
(2014)
Mittal et al.
(2016)
Presented study
Focused
Processing
Plant
Italian
domestic-
appliance
manufacturer
Paper
processing
unit
Geothermal
Plant
Coal-fired
steam power
plant
Plywood
processing
unit
Aluminium wire processing unit
Approaches Fuzzy
TOPSIS
TOPSIS Standard
FMECA
COPRAS-G Fussy
TOPSIS
(i) Traditional FMECA with basic criteria
(ii) TOPSIS with an assignment of scores in
crisp value with weighted attributes
(iii) COPRAS-G to express the criteria
values in intervals to avoid practical
difficulties and variations of maintenance
personnel
(iv) PSI by statistics instead of weight
assignments.
Consideration
of Criteria
Only three
basic criteria
Basic criteria
with
maintainability,
economic
safety and cost
consideration
Only three
basic criteria
Some
process
criteria with
basic criteria
Criteria like;
cost, safety,
maintenance,
environment
and
automation
Basic criteria with maintainability, economic
safety and cost consideration
Significance Limited to
three basic
criteria with
TOPSIS
Limited to
TOPSIS
Limited to
traditional
FMCEA
with basic
criteria
Limited to
COPRAS-G
Limited to
TOPSIS
RPN based criticalities with weighed
attributes; in exact value (TOPSIS) as well as
in upper and lower limits (COPRAS-G) and
PSI without calculating any weights
Introduction and Literature Review
22
Moreover, due to a proposal of expanding electrical wire network, industry requirements,
infrastructure planning and Indian Government’s project about electrical power to every
corner of the country, it is expecting the growth of aluminium wire market about 13.5%
CAGR i.e. compound annual growth rate during 2014-2019. In Gujarat, a network of
transmission lines is expected to rise at 7.8% CAGR during the financial year 2014-
2018 and Government of Gujarat will be investing around US$ 4500 million in
transmission and distribution till year 2020 (BIG 2020 report, volume 1-2009).
During the detailed study of the performance of the identified processing plant, it is
observed that maintenance time is about 20 to 25 % of the total time which leads to
reliability losses. The yearly loss of production and profit is about 3000 tons and INR 45
crores respectively. The average usage of aluminium wire rolling mill in India is
approximately 75 - 80 %. After studying the facts related to this plant, it is found that
poor maintenance is the prime reason of low productivity and profit. Hence, it is required
to upgrade existing maintenance so that the highest utilization of resources is obtained by
incorporating small cost or without any additional cost.
In the present research study, it is investigated the scope of optimizing the maintenance
practices through actual failure analysis by applying traditional and three distinct MCDM
based FMECA approaches as under:
(i) TOPSIS i.e. technique for order preference by similarity to ideal solution where;
weighted scores are considered in the crisp value
(ii) COPRAS-G i.e. grey-complex proportional assessment where; weighted scores
are in grey range rather than in crisp value and;
(iii) PSI i.e. preference selection index where; subjective weight consideration not
required
1.11 Objective and the Scope of Work
The prime objective of the study is to investigate the scope of reliability improvement
and discuss non-identical failure analysis models for evaluating criticalities of various
failure causes of critical components of an aluminium wire rolling mill. It advances
refinement of planning the maintenance by modifying FMECA through MCDM
approaches of an identified processing unit. The results are helpful in prioritizing the
1.11 Objective and the Scope of Work
maintenance actions to the process industry of same or of different kinds in accordance
with failure analysis.
The objectives of the research explored are listed under:
(i) To study reliability and maintenance issues faced by the aluminium wire rolling
mill and deriving the scope of optimizing maintenance activities.
(ii) To collect and analyze the historical data associated with failures including
calculation of major reliability parameters for components of identified
aluminium wire rolling mill.
(iii) To identify the vital or critical parts of concern rolling mill with the help of
reliability parameters like; failure frequencies, downtime and loss of production
on volume and cost consideration.
(iv) To study failure pattern of the critical components, select various criteria or
attributes and assigning the scores to each failure cause for every criteria based
on real shop-floor condition in order to evaluate criticality level of these failure
causes.
(v) To optimize maintenance activities of the critical components through traditional
as well as MCDM based failure analysis models based on comparison of
criticalities achieved from them. Furthermore, suggestions regarding the remedial
measures for optimal performance of rolling mill based on findings.
The scope of the proposed research work is summarized as below:
(i) Understanding the current scenario about the working of an aluminium wire
rolling mill plant and to acquire relevant information about reliability and
maintenance issues. Study existing maintenance practices and its limitations,
deriving scope of improvements.
(ii) Collection of historical failure data of major components of concern rolling mill.
(The data may be used for comparison and investigation of future failures with
the highest probability of occurrence). Failure data analysis as well as reliability
parameter calculation to generate necessary inputs.
(iii) Identification of critical components of the rolling mill on reliability parameters
like; downtime, failure frequencies, production loss on volume and cost basic.
Introduction and Literature Review
24
(iv) Interpretation of the failure modes, causes, effects and consequences of failure
pattern and problems faced in present maintenance practices.
(v) Traditional and MCDM based different failure models for prioritizing
maintenance activities.
(vi) Comparison of results of different failure models. Suggested improvement and
recommendations for a future scope.
1.12 Research Approaches
In the present research study, following approaches are applied to fulfil the objectives:
Objective (i): To study reliability and maintenance issues faced by the aluminium wire
rolling mill and deriving the scope of optimizing maintenance activities.
This objective is achieved by obtaining permission from Sampat aluminium private
limited (Deora group) situated at Rakanpur GIDC near Ahmedabad to do the research
work. The on-site study about basic components, product details, plant layout, reliability
and maintenance issues etc. of concern rolling mill is made. During preliminary study, it
is found that average maintenance cost or loss of reliability is about 20 to 25 % of total
production time with existing maintenance practices are either breakdown or planned
shutdown. The study seems fair verdict on a need of the scope of improvement in the
existing maintenance practices.
Objective (ii): To collect and analyze the historical data associated with failures
including calculation of major reliability parameters for components of identified
aluminium wire rolling mill.
This objective is achieved with suggesting some formats to gather the maintenance data.
Substantial failure data like; downtime and frequency of failures are collected for thirty-
one components of aluminium rolling machine for a period of one year (April, 2013 to
March, 2014) for further failure analysis.
Objective (iii): To identify the vital or critical parts of concern rolling mill with the help
of reliability parameters like; failure frequencies, downtime and loss of production on
volume and cost consideration.
1.12 Research Approaches
For fulfilling this objective, the comprehensive reliability failure data are scrutinized for
identifying the major vital components with the help of reliability parameters like; failure
frequencies, downtime, loss of production on volume and cost basis etc. for all components
of each stand of a rolling machine. The critical components identified for extended
failure analysis are; ball and tapered roller bearings of designation 6213, 32308, 30310,
32222, power transmission gears of bevel type with spigot and tapered shape and
primary and secondary machining shafts.
Objective (iv): To study failure pattern of critical components, select various criteria or
attributes and assigning the scores to each failure cause for every criteria based on real
shop-floor condition in order to evaluate criticality level of these failure causes.
This objective is achieved by studying failure modes, causes, effects, and consequences
of failure pattern with the present maintenance practices of identified critical components
of the aluminium wire processing mill such as; bearings, gears, shafts. The potential
FMEA development, criteria selection and score assignment is done by methods of a
question-based survey with maintenance team including managers, engineers, shop-floor
technicians and machine operators etc. The scores are assigned to various criteria on 1 to
10 point scales from minimal to greatest influence for each failure cause.
Objective (v): To optimize maintenance activities of the critical components through
traditional as well as MCDM based failure analysis models based on comparison of
criticalities achieved from them. Furthermore, suggestions regarding the remedial
measures for optimal performance of rolling mill based on findings.
This objective is achieved by incorporating traditional FMECA to calculate risk priority
number (RPN). Then, maintainability criticality indices are calculated by three
non-identical MCDM approaches; TOPSIS in crisp value, COPRAS-G in grey number
range and PSI without subjective weight consideration for each failure cause in a view to
sequence maintenance activities. The remedial measures are suggested for smooth or
optimal functioning of concern rolling mill.
Introduction and Literature Review
26
1.13 Original contribution by the thesis
In the present research study, three distinct MCDM based failure analysis models are
deployed as a modified FMECA for providing the satisfactory alternatives to
maintenance practitioner for better maintenance strategies. The research will make the
following original contributions:
(i) The actual historical failure data like; runtime, uptime, frequency of failures,
average repair or replace time are collected for the duration of a year (April’ 2013
to March’ 2014) for indicated aluminium wire rolling mill.
(ii) Reliability terms such as; MTTR, MTBF, MDT, hazard rate, availability are
determined based on realistic historical failure data to generate necessary inputs
for further failure analysis.
(iii)The failure modes with their causes and effects, failure patterns with the
problems faced in present maintenance practices are studied. The potential
FMEA for major critical elements is deduced. Moreover, the assignment of
scores to each failure cause for every diversified criterion is done based on real
shop-floor condition in order to evaluate criticality ranks through different failure
analysis approaches.
(iv) The results of criticality are evaluated and compared with discrete failure analysis
approaches.
(v) A contribution is proposed through the failure analysis approaches in showing
case-study for the maintenance plan preparation to rolling mill processing plant
entirely in a research study.
(vi) Originality mainly consists of the contemporary application of three non-identical
MCDM based methods (TOPSIS, COPRAS-G and PSI). The results are helpful
in explicating the pitfalls of maintenance for foremost processing plants and
prescribed yield outputs.
1.14 Organization of Thesis
The thesis is split into six units in order to organize the research work effectively.
Chapter 1 discusses the broad area of research, an overview of the study and its
significance. It reviews the literature related to reliability, maintenance, FMECA and
1.14 Organization of Thesis
MCDM with historical background. It shows the comprehensive literature reviews about
maintenance optimization through different tools. Moreover, it discusses the reviews of
past research study on improvements or modifications of FMECA through MCDM
approaches. General aspects of reliability and maintenance are also addressed in this
chapter. It defines the research gap and problem statement about an investigation of the
scope of reliability improvement by maintenance optimization through MCDM based
FMECA approaches to aluminium wire rolling mill. It states the objectives and scope of
present research work and original contributions.
Chapter 2 presents an introduction and overview of the identified process industry with
plant layout, process flow, major components etc. It also shows the substantial historical
failure data for the duration of April 2013 to March 2014 at Sampat Heavy Engineering
Ltd., Ahmedabad, India. The reliability modelling and process of discrimination of the
critical parts are presented based on the failure data and shop-floor condition in this
chapter.
Chapter 3 discusses the FMEA derived through failure modes, causes, effects and the
failure pattern consequence and problems faced in the present maintenance practices of
indicated critical components. It also discusses the procedure of selection of criteria and
score assignment methodology to every failure cause traditional as well as MCDM based
failure analysis models. Moreover, it discusses the traditional failure models and
evaluation of RPN through it with maintenance planning.
Chapter 4 presents MCDM based failure analysis models with an addition of some more
advanced criteria. It also describes methods to evaluate MCI for each failure mode of
targeted critical components through three different MCDM failure analysis models
called; TOPSIS, COPRAS-G, and PSI for optimizing current maintenance strategies of
the critical components of the targeted unit.
Chapter 5 discusses the out-trend of literature, the results of discrimination process
through shop-floor data for critical components and criticality indices obtained through
traditional and various MCDM based FMECA approaches as discussed in chapter 4. The
comparison of results is displayed in form of tables, figures etc. for effective
understanding. Based on achieved RPN and MCI, remedial measures are suggested and
priority plan of existing maintenance activities is discussed in the chapter.
Introduction and Literature Review
28
Chapter 6 concludes the present research study and the scope of future work
recommendations.
1.15 Summary
This chapter discusses the broad area of research, an overview of the study and its
significance. It reviews the literature related to reliability, maintenance, FMECA and
MCDM with historical background. It shows the comprehensive literature reviews about
maintenance optimization through different tools. Moreover, it discusses the reviews of
past research study on improvements or modifications of FMECA through MCDM
approaches. General aspects of reliability and maintenance are also addressed in this
chapter. It defines the research gap and problem statement about an investigation of the
scope of reliability improvement by maintenance optimization through MCDM based
FMECA approaches to aluminium wire rolling mill. It states the objectives and scope of
present research work and original contributions.
The next chapter presents an introduction and overview of the identified process industry
with plant layout, process flow, major components etc. It also shows the substantial
historical failure data for the duration of April 2013 to March 2014 at Sampat Heavy
Engineering Ltd., Ahmedabad, India. The reliability modelling and process of
discrimination of the critical parts are presented based on the failure data and shop-floor
condition in this chapter.
29
CHAPTER 2
Data Collection, Reliability Modeling and
Identification of Critical Components
2.1 Overview of Identified Process Industry (Rolling Mill)
2.1.1 Introduction and Background
Deora Group's Sampat aluminium rolling mill is well known for electrical conductor
(EC) grade aluminium transmission wire products of International designation 1350 at
national and international level. It deals the non-ferrous market with cost-effective and
product integrity features in products like; shots, ingots, notch bars, flip-coiled and EC
grade aluminium wires. The constant casting and hot rolling based Properzi process are
used to manufacture aluminium wires in various diameters. Such products have multiple
usages in the area of electrical as well as mechanical engineering including electricity
supply, transformers production etc. The targeted rolling mill is primarily supplying
good conductivity non-ferrous overhead cores to Australia so that requirements of steel
cores are minimized to a major extent.
The detailed layout of the aluminium wire rolling mill plant is given in Fig. 2.1. It mainly
consists of the furnace, caster wheel and rolling machine. The functional details of these
components are discussed in Section 2.1.3. The rolled wire is wound around the spool to
the desired size.
Data Collection, Reliability Modeling and Identification of Critical Components
30
FIGURE 2.1 Rolling mill plant layout
2.1.2 Rolling Process
The rolling is a manufacturing process in which untreated metal block is feed between
couples of rollers to form desired sizes. The process is termed as hot or cold rolling
based on the temperature of raw aluminium. The hot rolling and cold rolling are the
forming methods in which processing temperature is more and less than recrystallization
temperature respectively. The hot and cold rolling produces more output than any other
hot or cold working processes respectively.
2.1.3 Rolling Mill Components
The research study is concentrating the problems of loss of reliability as well as improper
maintenance of a specific aluminium wire rolling mill plant situated in Gujarat, India.
Fig. 2.2 demonstrates the actual view of the rolling mill components and there role to
convert raw aluminium into aluminium wire through molten state. The functional details
of these parts are discussed as follows:
(i) Furnaces: It is used to convert aluminium raw into melting state of
temperature about 800 0C. The identified mill is having oil-fired furnaces of
twelve ton and fifteen-ton capacity to meet demands.
(ii) Caster Wheel: The caster wheel of diameter 1.4 m helps to pass melted
aluminium from furnace to rolling machine for further forming operations.
This component works on the principle of constant casting with the use of
water as quenching media. The unprocessed molten metal is coming from a
furnace and transferred to the rolling machine through caster wheel by
converting molten state into a solid form at recrystallize temperature through
water quenching.
(iii) Rolling Machine: It is the primary functional part of processing mill where
reliability and maintenance issues are on high-priority. The research is
2.1 Overview of Identified Process Industry (Rolling Mill)
31
targeting the rolling machine for further failure study. The diameter of
unprocessed metal coming from caster wheel is decreased from 40 mm to 6
mm through 15 successive stands in a series network. Fig. 2.3 illustrates the
actual image of a rolling machine (fifteen stands) for conceptualize the real
view of a plant.
FIGURE 2.2 Rolling mill components with their functional details
FIGURE 2.3 Actual image of rolling machine (Fifteen stands)
Data Collection, Reliability Modeling and Identification of Critical Components
32
2.1.4 Rolling Mill Properzi Process
The production of aluminium metal rod is possible through the properzi process as
shown in block diagram Fig 2.4. The properzi process is defined as the continuous
casting based rolling process of producing aluminium wire in long length directly
through the molten state. The step by step process of producing aluminium through the
Properzi Process is as under.
(i) Aluminium Ingot (billet) is fed into the furnace and melted at about 750-800 C.
(ii) The liquid aluminium is then fed to the aluminium caster i.e. casting wheel. Water is
used for cooling the hot aluminium to convert it into the soft solid bar of 40 mm
diameter.
(iii) The soft solid bar is then converted into 6 mm diameter rod through the series
rolling process by fifteen stands with a decrease of the diameter of wire by about 15-
20 % at each stand.
(iv) The coils of about 2-2.5 tons are wound.
FIGURE 2.4 Rolling mill process flow (Properzi)
2.1.5 Rolling Machine Sub-Components
The research is targeting the rolling machine for failure study where; successive series of
15 stands suffer pivotal problems of maintenance. Each stand consisting of thirty-one
sub-components as listed below:
1. Primary shaft
2. Secondary shaft
3. Bearing secondary housing
4. Primary bevel gear spigot end
5. Primary bevel gear taper end
6. Secondary bevel gear ring
7. Pin for entry guide roller
Melting of Aluminium ingots in furnace
Input
Semi solid cast bar through water
sprinking
Caster
Diameter reduction
through 15 stands in
series
Rolling Machine
Coiling of rod Output Dispatch
2.1 Overview of Identified Process Industry (Rolling Mill)
33
8. Main chuck nut for primary shaft
9. Spline side chuck nut
10. Chuck nut for bearing
11. Bottom nut for secondary shaft
12. Shear pin for drive assembly
13. Top nut for secondary shaft
14. Lock nut bearing side
15. Cylinder pin for primary assembly
16. Special bolt for secondary
17. Spacer for outer
18. Spacer for inner
19. Secondary block housing
20. Bearing housing 110ɸ for primary
21. Bearing housing 120ɸ for primary
22. Bearing tapered roller with designation 32308
23. Bearing tapered roller with designation 30310
24. Bearing radial ball bearing with designation 6213
25. Bearing tapered roller with designation 32222
26. Oil ring with designation 701010 changed with ball bearings
27. Oil ring with designation 608010 changed with roller bearings
28. Oil ring with designation 629010 changed with roller bearings
29. Coiler bolt
30. Casting bolt
31. Coupler bolt
The primary and secondary bevel gearing arrangement provides the proper feed with
forward motion and punch pressing force in a view to reduce diameter to desired level
for the processing aluminium bar. These gears are mounted in association with primary
and secondary shafts respectively. The tapered ball and roller type bearings facilitate the
rotary motion and support the dynamic loading. The other sub-components are integral
and essential parts of these three components in order to maintain smooth functioning of
them.
Data Collection, Reliability Modeling and Identification of Critical Components
34
2.2 Major Reliability and Maintenance Issues during Preliminary
Studies and Learning from them
The following issues were observed during the preliminary study which affects reliability
and needs attention to enhance maintenance plan. The other specific observations are
made during detailed shop-floor study and failure analysis models have been discussed.
(i) Excessive vibration: Rolling mill is experiencing excessive machine vibration from a
super calendar stack specifically at higher speeds. The excessive vibration leads to
create severe damage to the rolls and keep the mill away from running to its
designated speed till replacement. The mill is experiencing such problems from
several years and the root cause is unknown to date. Following general causes are
observed to such problems:
High vibration at a lower part of the stack
Jammed/barred/broken rolls (Age-related issue)
Flat spots on the rolls
Failed bearings due to thrust load
(ii) Critical equipment failures: Rolling mill is experiencing frequent, unexpected and
sudden failures of critical equipment, which leads to loss of reliability. This
phenomenon may occur due to;
Lack of proper reactive maintenance.
Production below capacity.
Higher waste rate.
(iii) Poor operations and its management: The challenging issues addressing this
problem are;
Lack of an effective reliability program.
High downtime due to preventable unplanned breakdown.
High replacement rate of spare parts.
2.3 Failure Data Collection and Analysis
35
2.3 Failure Data Collection and Analysis
In reliability problem, the information or data on which a conclusion is derived must be
the result of some observation. During the failure study of rolling machine, the data
collection is considered the random experiment, which is the result of a repeatedly
performed experiment or observation under similar conditions with the different
performance at each level (Balagurusamy, 1984).
The random experiment has the following characteristics:
- It has a well-defined set of rules.
- It is repetitive in nature.
- The result of each performance cannot be uniquely predicted.
Examples of the random experiment are;
(i) Computing the number of defective parts in a batch through random
selection.
(ii) Measuring the lifespan of definite bulbs through random selection from the
lot.
(iii) Observing the diameter of a circular bar produced by turning process.
(iv) Recording the run time of car before the failure of the brakes.
(v) Deciding the age of individual persons in a community etc.
The above points are contemplated during failure data collection process. The main
objectives of the data collection are to monitor the performance of process plant and to
identify the actual condition of it which helps in deciding an appropriate course of action
to improve the reliability and maintenance issues.
The reliability engineering is associated with the problems of evaluating risks and
consequences. Reliability theory basically depends on probability theory for its
application. Balagurusamy (1984) suggested some points for addressing any reliability
problem as under:
(i) Understanding the physical problems associated with the real situations under
consideration.
Data Collection, Reliability Modeling and Identification of Critical Components
36
(ii) Presenting the physical problems into mathematical form and application of
suitable methods to solve them.
(iii) Converting the mathematical outcome into a statement of real situations and its
implementation.
Looking to above points addressed for any reliability problems, it is necessary that the
system performance should be quantitative or in measurable terms of statistics. Hence, it
is necessary to collect certain data like; non-operational or downtime, frequency of
failures etc. associated directly with the system failures. The evaluation of reliability
parameters as discussed in this Section is helpful to interpreting the failure pattern
behaviour of the components of specific rolling mill. The recording of data and
evaluation process of concern parameters; i.e. reliability modeling is discussed in Section
2.4.
Based on observations during a preliminary study of plant condition and existing
maintenance system, the maintenance department of the plant is recommended and
consulted to record failure data in specific required format as displayed in Table 2.1 to
2.3 for effective data recording and management.
Table 2.1 is helpful to list the machineries with their technical specification and history
cards. Table 2.2 is facilitating the records of breakdown faults of any components/sub-
components with their timing of occurrence, existing control and maintenance practices
followed and downtime. Table 2.3 is providing preventive maintenance schedule
checklist on daily basis for each month to be followed. These templates are
recommended as a part of precise and organized data collection process to
comprehended neat failure pattern study.
TABLE 2.1 Format for master list of machineries/component
Sr.
No.
Name of
Machinery
/Component
I.D.
No Model Type
Manufacturer
Name
Year /
Month of
Installation
Capacity Other
Detail
2.3 Failure Data Collection and Analysis
37
TABLE 2.2 Format for breakdown maintenance records
Month :
_________________
S
No
.
Date
Machine
/Component /
Part Details
Fault/
Breakdown
Detail
Reported
time
Root
cause
analysis
Disposal/
Immediate
action taken
corrective
action
Break down
close date &
time
breakdown
hours Remarks
TABLE 2.3 Format for preventive maintenance check list
MONTH Machine Name Frequency
Parameter /
Check Point
/ To do
Point
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Data Collection, Reliability Modeling and Identification of Critical Components
38
The data collection process involves the prior discernment of the parameters like;
runtime, downtime, uptime and frequency of failures. These primary parameters are
directly associated with shop-floor conditions. The measure of these parameters
quantifies the performance of the plant. Hence, it is required to record and determine
these parameters. The concept of these reliability parameters and their sample
calculation is illustrated as follows. Moreover, the obtained values are recorded in Table
2.4.
Runtime ( ):
The runtime is the total assumed running time of the plant for a specific period of time.
Here, in this study, the duration of a year of 365 days (April 2013 to March 2014) is
selected for data collection with considering one day as shutdown per month.
So, total working days are; ( )
Downtime ( ):
The downtime is the total non-working time of the plant due to repair or replaces during
failures. In this study, it is directly recorded and listed in Table 2.4.
Uptime ( ):
The uptime is the difference between running time and downtime. It is calculated from
downtime as shown.
Frequency of Failure ( ):
It is a number of breakdowns or failures noted during the specified service period of the
plant. It is recorded part-wise for the entire study period.
Production loss in terms of volume and cost:
The loss of production is the actual loss suffered due to failures under downtime. The
sample calculation for loss of production in terms of volume is derived by considering
the plant capacity as 1.5 ton per hour.
For example; the production loss in volume (ton) for primary shaft is;
And the production loss in terms of cost is derived by considering the cost of finished
aluminium wire as Rs. 140 per kilogram (Kg)
So, the production loss in cost (Rs.) for the primary shaft is;
( )
2.3 Failure Data Collection and Analysis
39
TABLE 2.4 Part-wise failure data for aluminium rolling machine (April - 2013 to March - 2014)
Part
No.
Part
Name
Run
time
(Hrs.)
Up
time
(Hrs.)
TOTAL
Down
time
(hrs.)
Failure
frequencies
(n)
Production
Loss
(Tons)
Profit Loss
(Rs. in
Crores)
1 Primary Shaft 8472 8388 84 21 126 1.76
2 Secondary Shaft 8472 8432 40 20 60 0.84
3 Bearing Secondary Housing 8472 8448 24 12 36 0.50
4 Primary Bevel gear Spigot end 8472 8394 78 23 117 1.64
5 Primary Bevel gear Taper end 8472 8400 72 18 108 1.51
6 Secondary Bevel gear Ring 8472 8418 54 27 81 1.13
7 Pin for Entry Guide Roller 8472 8447 25 154 38 0.53
8 Main Chuck Nut for primary
shaft 8472 8446 26 13 39 0.55
9 Spline Side Chuck Nut 8472 8452 20 10 30 0.42
10 Chuck Nut for BRG 8472 8448 24 12 36 0.50
11 Bottom Nut for secondary
shaft 8472 8444 28 14 42 0.59
12 Shear Pin for Drive Assembly 8472 8472 0 0 0 0.00
13 Top Nut for secondary shaft 8472 8469 3 36 4 0.06
14 Lock Nut Bearing side 8472 8461 11 11 17 0.23
15 Cylinder Pin for Primary
Assembly 8472 8412 60 15 90 1.26
16 Special Bolt for Secondary 8472 8472 0 0 0 0.00
17 Spacer for Outer 8472 8472 0 0 0 0.00
18 Spacer for Inner 8472 8472 0 0 0 0.00
19 Secondary Block Housing 8472 8472 0 0 0 0.00
20 Bearing Housing 110ɸ for
Primary 8472 8456 16 8 24 0.34
21 Bearing Housing 120ɸ for
Primary 8472 8448 24 12 36 0.50
22 Bearing No. 32308 8472 8136 336 168 504 7.06
23 Bearing No. 30310 8472 8140 332 166 498 6.97
24 Bearing No. 6213 8472 8136 336 168 504 7.06
25 Bearing No. 32222 8472 8000 472 118 708 9.91
26 Oil ring with designation
701010 8472 8472 0 0 0 0.00
27 Oil ring with designation
608010 8472 8472 0 0 0 0.00
28 Oil ring with designation
629010 8472 8472 0 0 0 0.00
29 Coiler Bolt 8472 8472 0 18 0 0.00
30 Casting Bolt 8472 8436 36 12 54 0.76
31 Coupler Bolt 8472 8456 16 8 24 0.34
Data Collection, Reliability Modeling and Identification of Critical Components
40
Table 2.4 shows the thirty-one sub-components of a rolling machine with their historical
failure data. The plant has been monitored for a period from April 2013 to March 2014 to
record these data which are used to identify the critical components in the next section.
2.4 Reliability Modelling
Reliability modelling helps to understand and quantify the plant performance in terms of
design life. The reliability modelling is performed on substantial shop-floor failure data.
The brief overview about reliability parameters and their significance in this study is
presented as below:
The MTBF (Mean Time between Failures) is the expected time between failures of a
repairable system. The MTTF (Mean Time to Failure) is the expected time to failure of
the non-repairable system. The lower and upper confidence levels for these parameters
can be calculated by dividing total operational time with frequency of failures. The
fundamental difference between these parameters is that MTBF and MTTR is
specifically important to observe the performance of repairable and non-repairable
system or component respectively. Mathematically, it is expressed as;
(2.1)
For MTTR n is assumed as unity considering replacement after every instant of failures.
The failure or hazard rate is the probability of system failure within time t and t + 1 unit,
given that the system is continuously operational until time t. This system parameter can
be calculated for specific points in time. The components having constant hazard rate are
not replaced at specific failure instant, then total failure time is included in operational
time to evaluate MTTR. Mathematically, it is expressed as;
=
(2.2)
The MDT (Mean Downtime) is the average non-working time of the components of
plant due to repair or replacement. Mathematically, it is expressed as;
(2.3)
2.4 Reliability Modelling
41
The MTTR (Mean Time to Repair) is average repair time of the components of the plant.
It is generally considered as 30 % of mean downtime. Mathematically, it is expressed as;
(2.4)
MTBM (Mean Time between Maintenance) is the average time to retain the components
into operable state through service overhaul or repair between failures of the
components. Mathematically, it is expressed as;
(
) (2.5)
The operational availability is the probability that a system or component is in an
operable state at a specified time. Logistic delay times and administrative downtime for
maintenance are included in the calculation of operational availability. Operational
availability can be calculated by taking a ratio of MTBF over the sum of MTBF and
MDT for specific points in time with lower and upper confidence levels. Inherent
availability is the instantaneous availability in which delay or downtime is not included.
It can be calculated by taking a ratio of MTBF over the sum of MTBF and MTTR. The
evaluation of these parameters helps deciding the criteria responsible for administrative
or logistic delay in failure analysis models. Mathematically, they are expressed as;
( ) (2.6)
( ) (2.7)
In all equations from 2.1 to 2.7; is Mean-time between failure, is a frequency of
failure, is hazard rate, is Uptime, is Mean downtime, is Downtime,
is Mean-time to repair, is Mean-time between maintenance, is Total
time, is Operational availability, is Inherent availability
Table 2.5 shows the month wise summary of major reliability parameters evaluated from
failure data with the help of above discussed mathematical equations (Mishra and Pathak
(2012). The sample calculation of reliability parameters for the month of April 2013 is
also illustrated as under:
Data Collection, Reliability Modeling and Identification of Critical Components
42
Sample Calculation:
=
(
)
(
) = 7.38
( )
( )
= 0.78 (78 %)
( )
( )
= 0.92 (92 %)
2.4 Reliability Modelling
43
TABLE 2.5 Month-wise summary of failure data of rolling mill – reliability modelling (Duration: April -2013 to March - 2014)
Sr.
No. Month-Year
Total Run
Time (Hrs.)
[1 day
shutdown]
Total
Uptime
(Hrs.)
Total
Down Time
(hrs.)
Freq. of Failure
(n)
MTBF
(HRS.)
HAZARD RATE
(HRS.)
MDT
(HRS.)
OPERATION AVAILABILITY
(Aop)
MTTR
(HRS.)
MTBM
(HRS.)
INHERENT AVAILABILITY
(Ain)
1 Apr-13 696 546 150 74 7.38 0.14 2.03 0.78 0.61 7.38 0.92
2 May13 720 549 171 86 6.38 0.16 1.99 0.76 0.60 6.38 0.91
3 Jun-13 696 543 153 83 6.54 0.15 1.85 0.78 0.55 6.54 0.92
4 Jul-13 720 558 162 88 6.34 0.16 1.84 0.77 0.55 6.34 0.92
5 Aug-13 720 535 185 94 5.69 0.18 1.97 0.74 0.59 5.69 0.91
6 Sep-13 696 513 183 95 5.40 0.19 1.93 0.74 0.58 5.40 0.90
7 Oct-13 720 540 180 86 6.28 0.16 2.09 0.75 0.63 6.28 0.91
8 Nov-13 696 551 145 80 6.88 0.15 1.82 0.79 0.54 6.88 0.93
9 Dec-13 720 551 169 83 6.63 0.15 2.04 0.76 0.61 6.63 0.92
10 Jan-14 720 527 193 96 5.49 0.18 2.01 0.73 0.60 5.49 0.90
11 Feb-14 648 458 190 94 4.87 0.21 2.02 0.71 0.61 4.87 0.89
12 Mar-14 720 488 233 113 4.31 0.23 2.06 0.68 0.62 4.31 0.87
Data Collection, Reliability Modeling and Identification of Critical Components
44
From the reliability modeling, the hazard rate (bathtub) curve and availability curve are
presented as Fig. 2.5 and Fig. 2.6 respectively in a view to understand the failure pattern
behaviour of the components of rolling machine. The hazard rate function is also called
the failure rate function and often used in reliability. It gives an instantaneous failure rate
at time t and used to predict the behaviour of the failure of components. The bathtub
curve is the simplified form of hazard rate function based upon linear and constant
failure rates which represents failure rate component-wise over time.
The lifespan of a rolling machine is assumed long but its failure-free performance mainly
depends on lifetime span of rotating components like; bearings whose lifespan is
expected about million rotations. The obtained curves show the segmental lifetime span
and availability of rolling mill as continuous replacement of components like; bearings
are common practice. Thus, the obtained curve shows a cyclic pattern throughout
lifetime span of rolling mill.
The inherent or operational availability curve shows the probability that the rolling
machine is in the operable state during the specific month. The administrative downtime
is considered in operational availability.
FIGURE 2.5 Hazard rate curve for rolling mill
0.00
0.05
0.10
0.15
0.20
0.25
Haz
ard
Rat
e
Apr-13
May-13
Jun-13
Jul-13
Aug-13
Sep-13
Oct-13
Nov-13
Dec-13
Jan-14
Feb-14
Mar-14
Hazard Rate 0.14 0.16 0.15 0.16 0.18 0.19 0.16 0.15 0.15 0.18 0.21 0.23
Hazard Rate (Bath Tub) Curve
2.5 Discrimination of Critical Components of Rolling Mill
45
FIGURE 2.6 Availability curve for rolling mill
The significance of both the curves is to illustrate the short-term and long-term failure
pattern of the components. The actual time period for failure distribution is widely
ranging considering various failure causes of the components or sub-system. Sometimes
infant mortality may retain till many years and sometime wear-out failure may happen
within a few months. The presentation of such curves helps to conceptualize the overall
failure pattern of the system or plant at instantaneous time span so that appropriate
actions can be accelerated.
2.5 Discrimination of Critical Components of Rolling Mill
The substantial historical failure data such as downtime, failure frequencies etc. as
displayed in Table 2.4 are used to identifying vital components. The frequency of
failures represents the total instant of failures of each part of all fifteen stands as a whole.
The downtime represents the average non-working time after every failure. For example;
primary shafts from any stand failed twenty-one times as a whole during the period of
study. Also, each primary shaft failure needs four hours (recorded based on shop-floor
practices for each component) to restore and/or replacement with total eighty-four hours
downtime. Fig. 2.7 shows graphical presentation of the criticalities through important
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
Ava
ilab
iliti
es
Apr-13
May-13
Jun-13
Jul-13
Aug-13
Sep-13
Oct-13
Nov-13
Dec-13
Jan-14
Feb-14
Mar-14
Operational Availability 0.78 0.76 0.78 0.77 0.74 0.74 0.75 0.79 0.76 0.73 0.71 0.68
Inherent Availability 0.92 0.91 0.92 0.92 0.91 0.90 0.91 0.93 0.92 0.90 0.89 0.87
Availability Curve
Data Collection, Reliability Modeling and Identification of Critical Components
46
reliability parameters as discussed. Fig. 2.8 shows graphical presentation of the criticality
analysis based on loss of production in terms of volume and cost.
FIGURE 2.7 Criticality curve for reliability parameters (rolling machine components)
FIGURE 2.8 Criticality curve based on losses in production volume and cost
(Part-wise)
0
50
100
150
200
250
300
350
400
450
500
Cri
tica
lity
Val
ue
Rolling Mill Components
Total DownTime (Hrs)
Frequency ofFailures
0
200
400
600
800
1000
1200
Pri
mar
y Sh
aft
Brg
Sec
on
dar
y H
ou
sin
g
Pri
mar
y B
evel
ge
ar…
Pin
fo
r En
try
Gu
ide
…
Splin
e S
ide
Ch
uck
Nu
t
Bo
tto
m N
ut
for…
Top
Nu
t fo
r…
Cyl
ind
er P
in f
or…
Spac
er
for
Ou
ter
Seco
nd
ary
Blo
ck…
Brg
Ho
usi
ng
12
0ɸ
fo
r …
Be
arin
g N
o. 3
03
10
Be
arin
g N
o. 3
22
22
Oil
Seal
. 60
80
10
…
Co
iler
Bo
lt
Cri
tica
lity
Val
ue
Rolling Mill Components
Losses inProduction(Tonnes)Losses inProduction(Cost)
2.5 Discrimination of Critical Components of Rolling Mill
47
The vital parts or components by explicating shop-floor data are as follows:
1. Bearings: The rolling machine consists of two types of bearings; ball bearings
(No. 6213) and taper roller bearings (No. 32308, 30310, 32222). The bearings
are used to impart motion and support dynamic loads. These are rotating
machining elements and found most critical with about 70 % failure
contributions. It is observed 100 % replacement of failed or time-worn bearings
with obscene practice of mountings which leads much failure rate.
2. Gears: The rolling machine is having bevel gearing like; the primary bevel gears
of spigot end, primary bevel gear of tapered end and secondary bevel gear – ring
type. These gears are used to transmit power and feed motion to unprocessed
aluminium rod. The gears are contributing 4 % which is comparatively low
against bearings (70%) but their role in association with bearings leads them a
second most vital part in a rolling machine.
3. Shafts: In rolling machine, the primary and secondary machining shafts are fitted
for power transmission with bearings and gears. Their failure contributions are
about 4% but seem critical due to their functional link with bearings and gears.
The appropriate functioning of above parts provides a proper feed to the aluminium wire
for size reduction at every stage of a stand. These parts are working in conjunction with
each other at high speed with dynamic loads due to which they are considered the most
vital parts of an aluminium rolling machine.
The other remaining parts or components are contributing about 22 % loss due to their
failures. It is noted that all other parts are not having a significant effect on overall
performance of a rolling machine and they are replaced under the standard replacement
of three identified vital parts; bearings, gears and shafts. These critical components
(bearings, gears, and shafts) are usual components to nearly all processing units.
Hence, it is decided to have modified failure mode effect and criticality (FMECA)
analysis of such components through different MCDM methods to prioritize
maintenance practices to enhance overall reliability of the plant.
Data Collection, Reliability Modeling and Identification of Critical Components
48
2.6 Summary
This chapter presents an introduction and overview of the identified process industry
with plant layout, process flow, major components etc. It also shows the substantial
historical failure data recorded for the duration of April 2013 to March 2014 at Sampat
Heavy Engineering Ltd., Ahmedabad, India. The reliability modelling and process of
discrimination of the critical parts are presented based on the failure data and shop-floor
condition in this chapter.
The next chapter discusses the FMEA derived through failure modes, causes, effects and
the failure pattern consequence and problems faced in the present maintenance practices
of indicated critical components. It also discusses the procedure of selection of criteria
and score assignment methodology to every failure cause traditional as well as MCDM
based failure analysis models. Moreover, it discusses the traditional failure models and
evaluation of RPN through it with maintenance planning.
49
CHAPTER 3
Failure Pattern Study, Criteria Selection, Score
Assignment and Traditional Approach
3.1 Failure Pattern Study of Critical Components through Failure
Mode and Effect Analysis (FMEA)
3.1.1 Overview
Failure Pattern study involves analyzing functional failures, failure causes, effects and
repercussions of failures with existing control and maintenance practices. Failure Mode
Effect Analysis (FMEA) is commonly used tool for planning such activities of
processing plants through reliability analysis. The FMEA is technological tool to explain,
explore and reduce possible issues associated with parts or components of the
manufacturing unit (Braaksma et al., 2013)
The FMEA consists of following step by step procedure:
(i) Deciding the key process inputs
(ii) Identifying the potential failure modes to each process inputs
(iii) Finding the reasons for each potential failure modes
(iv) Discussing the effects of every reasons/causes
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
50
The primary elements of FMEA are;
(i) Failure mode: It is the way by which the system or component fails to
perform as designated.
(ii) Effect: It is the impact incorporated due to failure mode; and
(iii) Cause: It is the reason due to which the system or component bring about
failure mode.
It is very interesting to know about the relationship between these elements. There is a
chance of single cause with multiple effects or a combination of causes with a single
effect. To understand FMEA properly, it is required to have an idea about types of
different failure modes. The potential failure modes are; complete or partial failures,
intermittent failures, over-time failure, incorrect or premature operation, and failure due
to non-functioning of parts prematurely or up to design life. It is necessary to
contemplate that a part may have single or combinational failures.
3.1.2 FMEA for discriminated Critical Components
The shop-floor activities and live failure pattern including; visual inspection of failed
parts – its condition, wear, tear, processing temperature, misalignment, noise etc. of
critical components as discriminated in Chapter 2 is closely studied and observed in a
view to understanding;
(i) important process inputs;
(ii) potential failure modes; i.e., how process inputs failed
(iii) failure causes; i.e., why process inputs failed
(iv) failure effects; i.e., how the impact affected due to failure (external or
internal)?
It provides the concept about current control practices and problems faced during routine
activities. The behaviour of the failure pattern was illustrated by the observations of
definitely failed components. Fig. 3.1 shows some photographs of actual shop-floor
conditions and observations made for such components.
From this comprehensive study, the FMEA of vital components of aluminium wire
rolling mill is modeled. Table 3.1 highlights the FMEA of derived vital components.
3.1 Failure Pattern Study of Critical Components through Failure Mode and Effect Analysis (FMEA)
51
FIGURE 3.1 Some photographs of the oobservations made at shop-floor study
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
52
TABLE 3.1 FMEA of derived vital parts
Important
Process
Input
Potential
Failure
Mode
Possible Causes Potential Effects
Notation What is
process
input?
How
Process
inputs fail?
Why important
input failed?
How the impact affected
due to failure (customer
or internal)?
Rolling Mill
Bearing
Failure
Bearing
high
temperature
Improper
lubrication &
defective sealing
Bearing gets
jammed/Bearing housing
jammed
C1
Bearing
corrosion
Higher speed than
specified
Increase in vibration &
noise C2
Bearing
fatigue
Design defects,
Bearing dimension
not as per
specification
Life reduction C3
Roller balls
wear- out
Foreign
matters/particles Sudden rise in thrust C4
Bearing
misalignme
nt &
improper
mounting
Sudden impact on
the rolls
Shaft damage due to
impact on other parts C5
Electrical
damage Power loss Process interruption C6
Rolling Mill
Gearing
Failure
Gear teeth
wear-out
Inadequate
lubrication - dirt,
viscosity issues
Rough operation and
considerable noise C7
Gear teeth
surface
fatigue
(Pitting)
Improper meshing,
case depth and
high residual
stresses
Gear life reduction C8
Gear teeth
scoring
Overheating at
gear mesh
Interference and backlash
phenomenon C9
Gear teeth
fracture
Excessive overload
and cyclic stresses
Sudden stoppage of
process plant C10
Gear teeth
surface
cold/plastic
flow
Large contact
stresses due to
rolling and sliding
meshing
Slippage and power loss C11
Rolling Mill
Shaft
(Primary &
Secondary)
Failure
Shaft
fretting
Vibratory dynamic
load from bearing Leads to sudden failure C12
Shaft
misalignme
nt
Uneven bearing
load Vibration & fatigue C13
Shaft
fracture
(Fatigue)
Reverse and
repeated cyclic
loading
Sudden stoppage of
process C14
3.2 Selection of Criteria for Criticality Assessment
53
Their failures are considered as key process inputs to deduce the FMEA. C1 to C14
represents the different potential failure modes/causes.
3.2 Selection of Criteria for Criticality Assessment
The selection of criteria or attributes needs instinctive decisions and constructive
thoughts for explicit determination of criticality of various failure modes. In this research
study, three basic as well as four advanced criteria are proposed in order to have better
criticality assessment, which are as follows:
3.2.1 Traditional Criteria
(1) Probability of chances of failure (P): This criterion represents the possibilities of
failure happens during runtime. The frequency of failures is having major impact
on criticality level so, this criterion is important in the study.
(2) Degree of detectability (D): This criterion highlights at what level maintenance
person can identify failures through visual looking or observing conditions of
elements. The lower score assumes easily detectable.
(3) Degree of severity (S): This criterion explains the impact of severity on working
of parts or components. The large value is assigned to high downtime and repairs
or replaces time.
The above criteria are incorporated in finding criticalities through traditional approach.
3.2.2 Advanced Criteria
(1) Maintainability (M): The term severity is replaced with the maintainability (M)
criteria which define the difficulty level of doing service, repairing or exchange.
The lower score value states less difficulty in maintaining components.
(2) Spare Parts (SP): Looking to the difference obtained between operational and
inherent availability during reliability modeling, spare part (SP) criterion
selected. This criterion interprets the level of reserve stocks of spare parts
available during sudden failures. The larger score value represents non-
availability of spares.
(3) Economic Safety (ES): This criterion is claiming the safety measures of resources
of the unit. The lower score refers to a safer environment.
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
54
(4) Economic Cost (EC): This criterion considers the various costs associated with
processing, spares, machinery, manpower etc. It states that large score value
refers more costly things.
The multi-criteria decision-making based failure analysis models are incorporated with
above four advanced criteria together with the probability of chances of failure (P) and
degree of detectability (D) looking to their impact on criticality assessment.
3.3 Score Assignment Methodology
3.3.1 Score Assignment for Traditional Approach
Traditional failure analysis needs score ranking for every mode of failure with different
criteria. Here, every failure modes of targeted vital parts are assessed with basic criteria
like; probability of chances of failure (P), degree of detectability (D) and degree of
severity (S).
The independent scores for each failure cause are decided with following consideration;
(i) past records of failures; that provides a detailed outline about failure consequence of
parts or component extracted and,
(ii) through questioning; to shop-floor technicians, plant engineers, service managers
etc.
These scores are assigned on 1 to 10 levels by considering criteria effects from lowest to
highest concern respectively. These values are chosen based on realistic shop-floor
condition.
With the help of the following tables; the scores are assigned to each failure cause for
every process input during FMEA. Table 3.2 shows the score for probability of failure
from no occurrence to high occurrence. Table 3.3 presents the score of this criterion from
immediate to impossible detectability of problems. Table 3.4 highlights the score of
severity from high service duration affected to almost nil.
3.3 Score Assignment Methodology
55
TABLE 3.2 Scores for probability of occurrence (P)
Occurrence Criteria Score
Never More than three year 1
Very infrequent Once every 2-3 year 2
Infrequent Once every 1-2 year 3
Very less Once every 11-12 month 4
Less Once every 9-10 month 5
Medium Once every 7-8 month 6
Medium High Once every 5-6 month 7
High Once every 3-4 month 8
Too High Once every 1-2 month 9
Utmost High Less than 1 month 10
TABLE 3.3 Scores for degree of detectability (D)
Detection
Chances Non-detection level (%) Score
Instant < 10 1
Best 10 to 20 2
Better 21 to 30 3
Good 31 to 40 4
Easy 41 to 50 5
Periodic 51 to 60 6
Overdue 61 to 70 7
Hard 71 to 80 8
Very Hard 81 to 90 9
Impossible 91 to 100 10
TABLE 3.4 Scores for degree of severity (S)
Severity
impact Affected duration Score
Never < 30 min. 1
Very infrequent 1 hour 2
Infrequent 2 hour 3
Very less 3 hour 4
Less 4 hour 5
Medium 5 hour 6
Medium High 6 hour 7
High 7 hour 8
Too High 8 hour 9
Utmost High >8 hour 10
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
56
3.3.2 Score Assignment for MCDM based Failure Analysis Models
Multi-criteria based failure analysis needs accurate score ranking to each failure mode
with different criteria. The work emphasizes the score assigned to the failure causes (C1-
C14) of derived vital components on six different criteria P, D, M, SP, ES and ED as
discussed in Section 3.2.
The process of selection of score value is the perception of maintenance personnel
depending upon their experience and expertise. It is challenging to represent shop-floor
activities and past performance records in number. To accurately model such task special
care should be taken on certain aspects such as; manufacturing environment, processing
terms, the skill level of manpower etc.
These scores are given a number on 1 to 10 levels by considering attributes effects from
lowest to highest concern respectively. These scores are chosen based on realistic shop-
floor condition and questionnaires to maintenance personnel as discussed in earlier
section.
The probability of chances of failure (P) and degree of detectability (D) is kept same as
per traditional failure analysis model. Table 3.2 and 3.3 are used to model score for these
criteria. Table 3.5 shows the score of maintainability (M) criterion from extremely high
to almost nil maintainability of parts. Table 3.6 presents the score of spare parts (SP)
criterion from easy availability to impossible to procure with an urgent need of spare
parts. Table 3.7 proposed the score of economic safety (ES) criterion from extremely
less safe to the extremely safer working atmosphere. Table 3.8 represented the score of
economic cost (EC) criterion from extremely less costly to extremely more costly
resources.
The scores are in exact value for TOPSIS and PSI approach and in number range (lower
and upper limit) for COPRAS-G approach to compensate practical limitations and
variations of the maintenance personnel in a decision of scores.
3.3 Score Assignment Methodology
57
TABLE 3.5 Scores for maintainability (M)
Chances of
detection Maintainability level (%) Score
Utmost High < 10 1
Too High 10 to 20 2
High 21 to 30 3
Medium High 31 to 40 4
Medium 41 to 50 5
Less 51 to 60 6
Very Less 61 to 70 7
Infrequent 71 to 80 8
Very infrequent 81 to 90 9
Never 91 to 100 10
TABLE 3.6 Scores for spare parts (SP)
Criteria of procurement and need Score
Easily procured and desirable 1
Easily procured and essential 2
Easily procured and too essential 3
Difficult to procure but desirable 4
Difficult to procure but essential 5
Difficult to procure but too essential 6
Rarely available and desirable 7
Rarely available and essential 8
Rarely available and very essential 9
Impossible to avail and acute 10
TABLE 3.7 Scores for economic safety (ES)
Criteria for economic safety Score
Extremely less 1
Very less 2
Less 3
Fair 4
Average 5
Medium 6
Medium high 7
High 8
Too high 9
Utmost high 10
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
58
TABLE 3.8 Scores for economic cost (EC)
Criteria for economic cost Score
Extremely less 1
Very less 2
Less 3
Fair 4
Average 5
Medium 6
Medium high 7
High 8
Too high 9
Utmost high 10
3.4 Traditional Failure Analysis Approach
3.4.1 Overview
The traditional failure analysis model is incorporated with criticality analysis in FMEA,
which is termed as failure mode effect and criticality (FMECA). Fig. 3.2 highlights the
general flow diagram of traditional FMECA; in which parts or components are reviewed
initially thereafter scores are allotted with brainstorming approaches to evaluate risk
priority number (RPN) for effective prioritization process.
FIGURE 3.2 General flow process of traditional FMECA
FMECA is composed of three steps: (i) analysis of failure modes and their effects with
consequences (ii) assignment of scores to each failure cause and (iii) criticality analysis.
In criticality analysis; the risk is quantified with RPN, which is determined through
multiplication of scores of basic criteria such as; probability of chances of failure (P),
degree of severity (S), and degree of detectability (D).
3.4 Traditional Failure Analysis Approach
59
The step-by-step FMECA method for planning maintenance activities as suggested by
Mcdermott et al. (2009) is as under:
(i) Review of the process, system or component.
(ii) Brainstorming the modes of possible failure and gist their effects for further
analysis
(iii)Give a score to each cause of the failure based on its occurrence, severity and
detection criteria
(iv) Determine the RPN by multiplying the score of each criterion of failure mode
(v) Arrange the failure modes to their rank value order to prioritize the maintenance
action and implementation.
3.4.2 Criticality Assessment based on Risk Priority Number (RPN)
During the initial stage of interpretation of criticalities, it is necessary to establish the
decision-matrix by giving score-number to modes of failure (C1 to C14) for fundamental
criteria (P, D and S) as per method described in Section 3.2.1. Table 3.9 is representing
score assignment in form of decision-matrix for determining RPN through multiplication
of score-number as expressed below;
(3.1)
Where; i = 1, 2… n (choices) and j = 1, 2… m (attributes)
For example; RPN for failure cause C1 is;
and Table 3.10 displays the RPN obtained through traditional FMECA.
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
60
TABLE 3.9 Decision matrix – X for traditional FMECA
P D S
Poss
ible
cau
ses
of
Fai
lure
Pro
bab
ilit
y o
f
Chan
ce o
f fa
ilure
Deg
ree
of
Det
ecta
bil
ity
Deg
ree
of
Sev
erit
y
C1 5 8 7
C2 3 6 4
C3 9 7 10
C4 8 6 7
C5 5 5 8
C6 2 1 7
C7 5 2 5
C8 8 5 8
C9 7 6 4
C10 8 6 8
C11 5 3 5
C12 5 6 5
C13 7 7 8
C14 7 4 8
TABLE 3.10 Risk priority number (RPN) for traditional FMECA
Notation Possible or potential causes of failure Rank
C1 Improper lubrication & defective sealing 280 7
C2 Higher speed than specified 72 12
C3 Design defects, Bearing dimension not as
per specification 630 1
C4 Foreign matters/particles 336 4
C5 Sudden impact on the rolls 320 5
C6 Power loss 14 14
C7 Inadequate lubrication - dirt, viscosity
issues 50 13
C8 Improper meshing, case depth and high
residual stresses 320 6
C9 Overheating at gear mesh 168 9
C10 Excessive overload and cyclic stresses 384 3
C11 High contact stresses due to rolling and
sliding action of mesh 75 11
C12 Vibratory dynamic load from bearing 150 10
C13 Uneven bearing load 392 2
C14 Reverse and repeated cyclic loading 224 8
3.4 Traditional Failure Analysis Approach
61
3.4.3 Maintenance Planning Through Traditional FMECA
By analyzing current maintenance practices with an outcome of RPN, modified and
constructive maintenance practices are proposed as per Table 3.11. The classification of
various failure modes is done through RPN value. The failure modes are considered most
vital having 500 or more RPN value and recommended predictive or condition-based
approaches. The failure modes having RPN value between 250 and 500 are considered
critical and recommended preventive strategies during a shutdown. The failure modes
having RPN value below 250 are termed as normal failures and proposed corrective
actions when prompted breakdown.
TABLE 3.11 RPN based FMEA with existing practices and proposed improvements in
maintenance plan
Particulars
Current
Controls
Su
gg
este
d I
mpro
vem
ent
in
Mai
nte
nan
ce P
lan
No
tati
on
Key
Process
Input
Potential
Failure Mode
Potential
Causes
Potential
Failure Effects
What is
process
input?
How Process
inputs fail?
Why
important
input failed?
How the
impact
affected due to
failure
(customer or
internal)?
What are the
existing
practices
through
which
failure mode
controlled?
Rolling
Mill
Bearing
Failure
Bearing high
temperature
Improper
lubrication &
defective
sealing
Bearing gets
jammed/Beari
ng housing
jammed
Lubricating
the parts
when
occurred
Preventive
Maintenance C1
Bearing
corrosion
Higher speed
than specified
Increase in
vibration &
noise
Proper
coolant
Corrective
Maintenance C2
Bearing
fatigue
Defects in
design,
Bearing
dimension
not as per
specification
Life reduction Bearing
replacement
Predictive
Maintenance C3
Roller balls
wear- out
Foreign
matters/partic
les
Sudden rise in
thrust
Regular
cleaning of
parts
Preventive
Maintenance C4
Bearing
misalignment
& improper
mounting
Sudden
impact on the
rolls
Shaft damage
due to impact
on other parts
Routine
check up
Preventive
Maintenance C5
Failure Pattern Study, Criteria Selection, Score Assignment and Traditional Approach
62
Electrical
damage Power loss
Process
interruption
Electrical
wiring check
up
Corrective
Maintenance C6
Rolling
Mill
Gearing
Failure
Gear teeth
wear-out
Inadequate
lubrication –
Dirt, viscosity
issues
Rough
operation &
considerable
noise
Routine
check-up of
lubrication
Corrective
Maintenance C7
Gear teeth
surface
fatigue
(Pitting)
Improper
meshing, case
depth & high
residual
stresses
Gear life
reduction
Preventive
maintenance
Preventive
Maintenance C8
Gear teeth
scoring
Overheating
at gear mesh
Interference &
backlash
phenomenon
Lubricating
when
needed
Corrective
Maintenance C9
Gear teeth
fracture
Excessive
overload &
cyclic
stresses
Sudden
stoppage of
process plant
Break down
maintenance
Preventive
Maintenance C10
Gear teeth
surface
cold/plastic
flow
Large contact
stresses due
to rolling and
sliding
meshing
Slippage &
power loss
Gear replace
when
needed
Corrective
Maintenance C11
Rolling
Mill Shaft
(Primary &
Secondary)
Failure
Shaft fretting
Vibratory
dynamic load
from bearing
Leads to
sudden failure
Break down
maintenance
Corrective
Maintenance C12
Shaft
misalignment
Uneven
bearing load
Vibration &
fatigue
Preventive
maintenance
Preventive
Maintenance C13
Shaft fracture
(Fatigue)
Reverse &
repeated
cyclic loading
Sudden
stoppage of
process
Preventive
maintenance
Preventive
Maintenance C14
3.4.4 Drawbacks of Traditional FMECA
Some drawbacks of traditional FMECA are notes as under;
(i) The traditional FMECA is only working on specific fundamental criteria.
(ii) The same weightage is given to all criteria
(iii) Pertinence or inter-connection between criteria is not considered during the
assignment of scores and;
(iv) Minor changes in scores lead to discrepancy in RPN due to a multiplication of
mathematics. As RPN is the multiplication of score of three basic criteria, the
little changes of assignment of score due to personal perspective leads large
variations.
3.5 Summary
63
The above drawbacks of this failure analysis model can be resolved using MCDM based
failure models.
3.5 Summary
This chapter discusses the FMEA derived through failure modes, causes, effects and the
failure pattern consequence and problems faced in the present maintenance practices of
indicated critical components. It also discusses the procedure of selection of criteria and
score assignment methodology to every failure cause for traditional as well as MCDM
based failure analysis models. Moreover, it discusses the traditional failure models and
evaluation of RPN through it with maintenance planning.
The next chapter presents MCDM based failure analysis models with an addition of
some more advanced criteria. It also describes methods to evaluate MCI for each failure
mode of targeted critical components through three different MCDM failure analysis
models called; TOPSIS, COPRAS-G, and PSI for optimizing current maintenance
strategies of them.
64
CHAPTER 4
Multi-criteria Decision-making based Failure
Analysis Models
4.1 Overview
The MCDM approach is very easy to use with covering more criteria. It compares the
alternatives relatively on weights which helps the decision-making process effective.
This chapter describes a method for evaluating i.e. maintainability criticality index
of all causes of failures C1 to C14 as suggested through three different MCDM failure
analysis models, first based on TOPSIS, second based on COPRAS-G and third based on
PSI in a view to optimize existing maintenance plan of critical components of aluminium
wire rolling mill.
Fig. 4.1 shows the general flow diagram of MCDM based FMECA process incorporated
in this study which shows the assignment of scores to designated failure causes for three
distinct failure models in a view to enhance priority by determining
4.2 TOPSIS based Failure Mode Effect and Criticality Analysis
65
FIGURE 4.1 Flow Diagram of MCDM based FMECA process
4.2 TOPSIS based Failure Mode Effect and Criticality Analysis
4.2.1 TOPSIS Methodology
TOPSIS stands for a technique for order preference by similarity to an ideal solution in
which, Euclidean distance is calculated from a classical point. It works on a multi-criteria
concept where attributes are scored in exact number and weights are considered to decide
preference level. The crisp version of TOPSIS was presented by Hwang and Yoon in
1981.
Multi-criteria Decision-making based Failure Analysis Models
66
The evaluation of of listed failure causes of vital or critical components of the
aluminium wire processing unit as discussed previously is done by the TOPSIS method
as recommended by Sachdeva et al. (2009).
The step-by-step process is described as under:
Step – 1: Preparing a decision matrix by tabulating causes of failure and designated
criteria into rows and columns correspondingly.
The said decision matrix is deduced for a set of beneficial attributes (P, D, M, SP, ES,
EC) against a set of fourteen causes of failure (C1 to C14) as per the description of
Section 3.3.2.
Step – 2: Development of decision matrix – by assigning score value in an exact
number
(4.1)
Where; i = 1, 2… n (choices) and j = 1, 2… m (attributes)
Table 4.1 displays decision matrix – which is developed by proper assignment of score
value to matrix cell through the methods described in Section 3.3.2.
Step – 3: Normalizing a decision matrix – .
The process of normalization of decision matrix is explained by Deng et al. (2000).
Moreover, Salabun (2013) proposed a method for calculation of the normalized value of
score for straight beneficial attributes as follows:
∑
(4.2)
The normalized matrix is presented in Table 4.2.
4.2 TOPSIS based Failure Mode Effect and Criticality Analysis
67
TABLE 4.1 Decision matrix – X for TOPSIS
P D M SP ES EC
Pote
nti
al F
ailu
re C
ause
s
Pro
bab
ilit
y o
f ch
ance
of
fail
ure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic s
afet
y
Eco
nom
ic c
ost
C1 9 8 1 3 3 3
C2 8 6 2 2 4 3
C3 10 7 6 3 10 9
C4 9 6 5 3 7 5
C5 10 5 6 5 9 10
C6 9 1 1 3 5 2
C7 7 3 5 3 7 4
C8 8 5 5 3 5 5
C9 5 4 2 3 3 3
C10 9 2 6 4 7 7
C11 3 6 3 3 3 3
C12 5 5 4 3 3 3
C13 8 5 5 3 6 6
C14 9 2 6 4 6 7
for profit criteria:
=
(
) (4.3)
=
(4.4)
Multi-criteria Decision-making based Failure Analysis Models
68
Step – 5: Determining all weighted attributes.
With the help of Shannon’s entropy concept, weights of all criteria are calculated by first
evaluating entropy of jth
criteria as per the following expression,
= -
∑
(4.5)
TABLE 4.2 Normalization of decision matrix – X for TOPSIS
P D M SP ES EC
Pote
nti
al F
ailu
re
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f fa
ilure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic s
afet
y
Eco
nom
ic c
ost
C1 0.0826 0.1231 0.0175 0.0667 0.0385 0.0429
C2 0.0734 0.0923 0.0351 0.0444 0.0513 0.0429
C3 0.0917 0.1077 0.1053 0.0667 0.1282 0.1286
C4 0.0826 0.0923 0.0877 0.0667 0.0897 0.0714
C5 0.0917 0.0769 0.1053 0.1111 0.1154 0.1429
C6 0.0826 0.0154 0.0175 0.0667 0.0641 0.0286
C7 0.0642 0.0462 0.0877 0.0667 0.0897 0.0571
C8 0.0734 0.0769 0.0877 0.0667 0.0641 0.0714
C9 0.0459 0.0615 0.0351 0.0667 0.0385 0.0429
C10 0.0826 0.0308 0.1053 0.0889 0.0897 0.1000
C11 0.0275 0.0923 0.0526 0.0667 0.0385 0.0429
C12 0.0459 0.0769 0.0702 0.0667 0.0385 0.0429
C13 0.0734 0.0769 0.0877 0.0667 0.0769 0.0857
C14 0.0826 0.0308 0.1053 0.0889 0.0769 0.1000
4.2 TOPSIS based Failure Mode Effect and Criticality Analysis
69
Later on, weights are determined for jth
criteria through following expression;
= –
∑ –
(4.6)
Step – 6: Determining the distance between a positive ideal solution and negative ideal
solution
respectively.
The expressions as listed below are used to determine the distance from ideal value;
√∑
(4.7)
√∑
(4.8)
Table 4.3 represents the value of
for each failure cause.
Step – 7: Determining criticality index for TOPSIS;
The same is determined as per the following expression;
=
(4.9)
Table 4.4 shows the obtained value of and its criticality rank.
Multi-criteria Decision-making based Failure Analysis Models
70
TABLE 4.3 Distances between positive and negative ideal solution
P D M SP ES EC
Pote
nti
al
Fai
lure
Cau
ses
Pote
nti
al
Fai
lure
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f
fail
ure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic
safe
ty
C1 0.0005 0.0170 0.0000 0.0634 0.0418 0.0000 0.0111 0.0028 0.0444 0.0000 0.0545 0.0011
C2 0.0019 0.0118 0.0052 0.0323 0.0268 0.0017 0.0251 0.0000 0.0327 0.0009 0.0545 0.0011
C3 0.0000 0.0231 0.0013 0.0466 0.0000 0.0418 0.0111 0.0028 0.0000 0.0444 0.0011 0.0545
C4 0.0005 0.0170 0.0052 0.0323 0.0017 0.0268 0.0111 0.0028 0.0082 0.0145 0.0278 0.0100
C5 0.0000 0.0231 0.0117 0.0207 0.0000 0.0418 0.0000 0.0251 0.0009 0.0326 0.0000 0.0711
C6 0.0005 0.0170 0.0635 0.0000 0.0418 0.0000 0.0111 0.0028 0.0227 0.0036 0.0712 0.0000
C7 0.0042 0.0076 0.0324 0.0052 0.0017 0.0268 0.0111 0.0028 0.0082 0.0145 0.0401 0.0044
C8 0.0019 0.0118 0.0117 0.0207 0.0017 0.0268 0.0111 0.0028 0.0227 0.0036 0.0278 0.0100
C9 0.0118 0.0019 0.0207 0.0116 0.0268 0.0017 0.0111 0.0028 0.0444 0.0000 0.0545 0.0011
C10 0.0005 0.0170 0.0466 0.0013 0.0000 0.0418 0.0028 0.0112 0.0082 0.0145 0.0100 0.0278
C11 0.0231 0.0000 0.0052 0.0323 0.0151 0.0067 0.0111 0.0028 0.0444 0.0000 0.0545 0.0011
C12 0.0118 0.0019 0.0117 0.0207 0.0067 0.0151 0.0111 0.0028 0.0444 0.0000 0.0545 0.0011
C13 0.0019 0.0118 0.0117 0.0207 0.0017 0.0268 0.0111 0.0028 0.0145 0.0081 0.0178 0.0178
C14 0.0005 0.0170 0.0466 0.0013 0.0000 0.0418 0.0028 0.0112 0.0145 0.0081 0.0100 0.0278
4.2 TOPSIS based Failure Mode Effect and Criticality Analysis
71
TABLE 4.4 Maintainability criticality index and criticality rank for TOPSIS
Notation Potential Failure Causes Rank
C1 Improper lubrication & defective sealing 0.4265 9
C2 Higher speed than specified 0.3640 10
C3 Design defects, bearing dimension not as
per specification 0.7986 2
C4 Foreign matters/particles 0.5794 3
C5 Sudden impact on the rolls 0.8051 1
C6 Power loss 0.2499 14
C7 Inadequate lubrication - dirt, viscosity
issues 0.4419 8
C8 Improper meshing, case depth and high
residual stresses 0.4981 7
C9 Overheating at gear mesh 0.2515 13
C10 Excessive overload and cyclic stresses 0.5636 4
C11 Large contact stresses due to rolling and
sliding meshing 0.3460 12
C12 Vibratory dynamic load from bearing 0.3525 11
C13 Uneven bearing load 0.5505 5
C14 Reverse and repeated cyclic loading 0.5455 6
4.2.2 Maintenance Planning through TOPSIS FMECA
It is noted from the Table 4.4 that failure-cause sudden impact on roll (C5) looks the vital
or most-critical and power loss (C6) looks minimal critical. Table 4.5 shows the failure
mode effect analysis with current control practices and suggested maintenance plan
based on their criticalities. It is recommended updating existing maintenance practices as
listed in Table 4.5 that causes of failure (C5, C3, C4, C10, and C13) with high
is covered with condition monitoring based predictive strategy, causes of failure (C14,
C8, C7, C1, C2) with medium is covered with preventive approaches which
are targeted during plant shutdown and causes of failure (C12, C11, C9, C6) with small
is approached remedial measures when prompted.
Multi-criteria Decision-making based Failure Analysis Models
72
TABLE 4.5 based FMEA with existing practices and proposed improvements
in maintenance plan
Particulars
Current
Controls
Su
gg
este
d I
mpro
vem
ent
in
Mai
nte
nan
ce P
lan
No
tati
on
Key
Process
Input
Potential
Failure Mode
Potential
Causes
Potential
Failure Effects
What is
process
input?
How Process
inputs fail?
Why
important
input failed?
How the
impact
affected due to
failure
(customer or
internal)?
What are the
existing
practices
through
which
failure mode
controlled?
Rolling
Mill
Bearing
Failure
Bearing high
temperature
Improper
lubrication &
defective
sealing
Bearing gets
jammed/Beari
ng housing
jammed
Lubricating
the parts
when
occurred
Preventive
Maintenance C1
Bearing
corrosion
Higher speed
than specified
Increase in
vibration &
noise
Proper
coolant
Preventive
Maintenance C2
Bearing
fatigue
Design
defects,
Bearing
dimension
not as per
specification
Life reduction Bearing
replacement
Predictive
Maintenance C3
Roller balls
wear- out
Foreign
matters/partic
les
Sudden rise in
thrust
Regular
cleaning of
parts
Predictive
Maintenance C4
Bearing
misalignment
& improper
mounting
Sudden
impact on the
rolls
Shaft damage
& Impact
damage on
other parts
Routine
check up
Predictive
Maintenance C5
Electrical
damage
Loss of
power
Operation
interrupted
Electrical
wiring check
up
Corrective
Maintenance C6
Rolling
Mill
Gearing
Failure
Gear teeth
wear-out
Inadequate
lubrication –
Dirt, viscosity
issues
Rough
operation &
considerable
noise
Routine
check-up of
lubrication
Preventive
Maintenance C7
Gear teeth
surface
fatigue
(Pitting)
Lack of
proper
meshing of
case depth &
high residual
stresses
Gear life
reduction
Preventive
maintenance
Preventive
Maintenance C8
Gear teeth
scoring
Overheating
at gear mesh
Interference &
backlash
phenomenon
Lubricating
when
needed
Corrective
Maintenance C9
Gear teeth
fracture
Excessive
overload &
cyclic
stresses
Sudden
stoppage of
process plant
Break down
maintenance
Predictive
Maintenance C10
4.3 COPRAS-G based Failure Mode Effect and Criticality Analysis
73
Gear teeth
surface
cold/plastic
flow
Large contact
stresses due
to rolling and
sliding
meshing
Slippage &
power loss
Gear replace
when
needed
Corrective
Maintenance C11
Rolling
Mill Shaft
(Primary &
Secondary)
Failure
Shaft fretting
Vibratory
dynamic load
from bearing
Leads to
sudden failure
Break down
maintenance
Corrective
Maintenance C12
Shaft
misalignment
Uneven
bearing load
Vibration &
fatigue
Preventive
maintenance
Predictive
Maintenance C13
Shaft fracture
(Fatigue)
Reverse and
repeated
cyclic loading
Process
suddenly
stopped
Preventive
maintenance
Preventive
Maintenance C14
4.3 COPRAS-G based Failure Mode Effect and Criticality Analysis
4.3.1 COPRAS-G Methodology
COPRAS-G stands for grey-complex proportional risk assessment which works on grey
number concept. As discussed by Zavadskas et al. (2008, 2009), the data facts are
grouped into three numbers called; black, white and grey. The black number has no
higher as well as lower ranges. A white number is an exact number which means, the
upper and lower values are the same. Whereas the grey number has dissimilar values
with both above and below ranges so, it falls within an interval called the grey range
(Maity et al., 2012). This concept of the grey range was deduced from grey theory, which
helps in dealing uncertainty of real environment (Deng 1989, Chang et al. 1999 and Lin
et al. 2008).
The evaluation of of listed failure causes of vital or critical components of an
aluminium wire processing unit is based on following procedure (Zavadskas et al., 2008,
2009 and Maity et al., 2012):
Step – 1: Preparing a decision matrix by tabulating causes of failure and designated
criteria in to rows and columns correspondingly.
The decision matrix is deduced for a set of beneficial attributes (P, D, M, SP, ES, EC)
against a set of fourteen causes of failure (C1 to C14) as per description of Section 3.3.2.
Step – 2: Development of decision matrix – by assigning scores value in upper and
lower grey range as under.
Multi-criteria Decision-making based Failure Analysis Models
74
= ] = [
] (4.10)
Where; and represents low and high scores in grey-range respectively.
i = 1, 2… m representing causes of failure
j = 1, 2… n representing profit criteria
The decision matrix – as shown in Table 4.6 is developed by proper assignment of
score values in a range to matrix cell through the methods described in Section 3.3.2.
Step – 3: Normalizing decision matrix- .
Table 4.7 shows the normalized matrix- which derived from expression as under;
=
∑ ∑
(4.11)
=
∑ ∑
(4.12)
= [
] (4.13)
The primary objectives of the normalizing process to organize the data with acceptable
logic and dependencies with less redundancy.
Step – 4: Determining weighted attributes.
With the help of Shannon’s entropy concept, weights of all criteria are calculated by first
evaluating entropy for both range and of jth
criteria as per the following
expression,
= -
∑
(4.14)
= -
∑
(4.15)
Thereafter weights are calculated similarly as follows;
4.3 COPRAS-G based Failure Mode Effect and Criticality Analysis
75
= –
∑ –
(4.16)
= –
∑ –
(4.17)
TABLE 4.6 Decision matrix – X for COPRAS-G
P D M SP ES EC
Pote
nti
al F
ailu
re
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f fa
ilure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic s
afet
y
Eco
nom
ic c
ost
C1 8 9 7 8 1 2 2 3 3 4 3 4
C2 8 9 5 6 1 2 2 3 3 4 4 5
C3 9 10 7 8 6 8 3 5 9 10 9 10
C4 7 9 6 7 4 5 3 5 7 8 5 6
C5 8 10 5 6 6 7 5 7 9 10 9 10
C6 7 9 1 2 1 2 3 4 5 6 2 3
C7 7 8 2 3 5 6 3 4 7 8 4 5
C8 8 9 4 5 5 6 3 4 4 5 5 6
C9 4 5 3 4 2 3 2 3 2 3 3 4
C10 9 10 2 4 6 7 3 4 7 8 7 8
C11 3 4 6 7 3 4 3 4 2 3 3 4
C12 5 6 4 5 3 5 3 4 3 4 3 4
C13 8 9 4 5 5 6 4 5 4 5 5 6
C14 9 10 2 3 6 7 3 4 5 6 6 7
Step – 5: Evaluation of weighted normalized matrix-
This matrix- is generated based on the following equations as displayed in Table 4.8.
= (4.18)
= (4.19)
= [
] (4.20)
Multi-criteria Decision-making based Failure Analysis Models
76
TABLE 4.7 Normalized Decision Matrix – X1 for COPRAS-G
P D M SP ES EC P
ote
nti
al F
ailu
re
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f
fail
ure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic s
afet
y
Eco
nom
ic c
ost
C1 0.0737 0.0829 0.1069 0.1221 0.0161 0.0323 0.0396 0.0594 0.0390 0.0519 0.0400 0.0533
C2 0.0737 0.0829 0.0763 0.0916 0.0161 0.0323 0.0396 0.0594 0.0390 0.0519 0.0533 0.0667
C3 0.0829 0.0922 0.1069 0.1221 0.0968 0.1290 0.0594 0.0990 0.1169 0.1299 0.1200 0.1333
C4 0.0645 0.0829 0.0916 0.1069 0.0645 0.0806 0.0594 0.0990 0.0909 0.1039 0.0667 0.0800
C5 0.0737 0.0922 0.0763 0.0916 0.0968 0.1129 0.0990 0.1386 0.1169 0.1299 0.1200 0.1333
C6 0.0645 0.0829 0.0153 0.0305 0.0161 0.0323 0.0594 0.0792 0.0649 0.0779 0.0267 0.0400
C7 0.0645 0.0737 0.0305 0.0458 0.0806 0.0968 0.0594 0.0792 0.0909 0.1039 0.0533 0.0667
C8 0.0737 0.0829 0.0611 0.0763 0.0806 0.0968 0.0594 0.0792 0.0519 0.0649 0.0667 0.0800
C9 0.0369 0.0461 0.0458 0.0611 0.0323 0.0484 0.0396 0.0594 0.0260 0.0390 0.0400 0.0533
C10 0.0829 0.0922 0.0305 0.0611 0.0968 0.1129 0.0594 0.0792 0.0909 0.1039 0.0933 0.1067
C11 0.0276 0.0369 0.0916 0.1069 0.0484 0.0645 0.0594 0.0792 0.0260 0.0390 0.0400 0.0533
C12 0.0461 0.0553 0.0611 0.0763 0.0484 0.0806 0.0594 0.0792 0.0390 0.0519 0.0400 0.0533
C13 0.0737 0.0829 0.0611 0.0763 0.0806 0.0968 0.0792 0.0990 0.0519 0.0649 0.0667 0.0800
C14 0.0829 0.0922 0.0305 0.0458 0.0968 0.1129 0.0594 0.0792 0.0649 0.0779 0.0800 0.0933
4.3 COPRAS-G based Failure Mode Effect and Criticality Analysis
77
TABLE 4.8 Weighted normalized decision matrix – X2 for COPRAS-G
P D M SP ES EC P
ote
nti
al
Fai
lure
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f
fail
ure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic
safe
ty
Eco
nom
ic c
ost
C1 0.0217 0.0235 0.0178 0.0195 0.0014 0.0032 0.0027 0.0058 0.0081 0.0100 0.0071 0.0090
C2 0.0217 0.0235 0.0127 0.0146 0.0014 0.0032 0.0027 0.0058 0.0081 0.0100 0.0095 0.0112
C3 0.0244 0.0261 0.0178 0.0195 0.0083 0.0127 0.0040 0.0096 0.0243 0.0250 0.0213 0.0225
C4 0.0190 0.0235 0.0153 0.0171 0.0056 0.0080 0.0040 0.0096 0.0189 0.0200 0.0119 0.0135
C5 0.0217 0.0261 0.0127 0.0146 0.0083 0.0111 0.0066 0.0135 0.0243 0.0250 0.0213 0.0225
C6 0.0190 0.0235 0.0025 0.0049 0.0014 0.0032 0.0040 0.0077 0.0135 0.0150 0.0047 0.0067
C7 0.0190 0.0209 0.0051 0.0073 0.0069 0.0096 0.0040 0.0077 0.0189 0.0200 0.0095 0.0112
C8 0.0217 0.0235 0.0102 0.0122 0.0069 0.0096 0.0040 0.0077 0.0108 0.0125 0.0119 0.0135
C9 0.0109 0.0131 0.0076 0.0098 0.0028 0.0048 0.0027 0.0058 0.0054 0.0075 0.0071 0.0090
C10 0.0244 0.0261 0.0051 0.0098 0.0083 0.0111 0.0040 0.0077 0.0189 0.0200 0.0166 0.0180
C11 0.0081 0.0104 0.0153 0.0171 0.0042 0.0064 0.0040 0.0077 0.0054 0.0075 0.0071 0.0090
C12 0.0136 0.0157 0.0102 0.0122 0.0042 0.0080 0.0040 0.0077 0.0081 0.0100 0.0071 0.0090
C13 0.0217 0.0235 0.0102 0.0122 0.0069 0.0096 0.0053 0.0096 0.0108 0.0125 0.0119 0.0135
C14 0.0244 0.0261 0.0051 0.0073 0.0083 0.0111 0.0040 0.0077 0.0135 0.0150 0.0142 0.0157
Multi-criteria Decision-making based Failure Analysis Models
78
Step – 6: Calculation of weighted-mean normalized additions of profit criteria whose
higher value is preferred and non-beneficial criteria , whose smaller value is
preferred.
They are calculated as follow;
= -
∑
(4.21)
= -
∑
(4.22)
where; i = 1,2,….,m (total criteria)
It is assumed that profit attributes are k then (m - k) is non-profit attributes. It is common
practice to keep profit attributes at the beginning followed by non-profit attributes.
Step – 7: Measure the relative weight of for available choices
It is deduced with following expressions;
= ∑
∑
(4.23)
= ∑
∑
(4.24)
Where; represents the least additions of weighted-mean normalized values for
unfavourable attributes ,
The mode of failures are prioritized with arranging results of in ascending
manner i.e. the higher value of is given top priority over others.
Step – 8: Determining the (%) contribution for ith
causes of failure;
The percentage contribution is determined to present unity as per following expression
and ranks are decided with ;
4.3 COPRAS-G based Failure Mode Effect and Criticality Analysis
79
=
(4.25)
Table 4.9 highlighted the achieved results of , (%) contribution and rank
order.
TABLE 4.9 Maintainability criticality index and (%) contribution for
COPRAS-G
Notation Potential Failure Causes (%) Rank
C1 Improper lubrication & defective sealing 0.1297 60 9
C2 Higher speed than specified 0.1244 58 10
C3 Design defects, bearing dimension not as
per specification 0.2156 100 1
C4 Foreign matters/particles 0.1662 77 4
C5 Sudden impact on the rolls 0.2079 96 2
C6 Loss of power 0.1062 49 12
C7 Inadequate lubrication - girt, viscosity
issues 0.1401 65 8
C8 Improper meshing, case depth & high
residual stresses 0.1444 67 7
C9 Overheating at gear mesh 0.0863 40 14
C10 Excessive overload and cyclic stresses 0.1700 79 3
C11 Large contact stresses due to rolling and
sliding meshing 0.1022 47 13
C12 Vibratory dynamic load from bearing 0.1096 51 11
C13 Uneven bearing load 0.1477 68 6
C14 Reverse and repeated cyclic loading 0.1526 71 5
4.3.3 Significance of COPRAS-G
It is very difficult for maintenance personnel to assign the score consistently at various
stages of assessment of criticalities. Thus, an exact interpretation of causes of failure
looks practically difficult. This challenge may be handled by incorporating score-values
into interval called a grey number rather than an exact and specific value of TOPSIS.
The primary objective of this approach is to present score-values in range.
4.3.4 Maintenance Planning through COPRAS-G FMECA
The results of Table 4.9 highlight that failure cause; design defects and lack of
specification in bearing dimensions (C3) looks vital or most-critical and overheating at
gear mesh (C9) looks less important. Table 4.10 shows the failure mode effect analysis
with current control practices and suggested maintenance plan based on criticalities. It is
Multi-criteria Decision-making based Failure Analysis Models
80
recommended to update the current control practices as listed in Table 4.10. It highlights
that causes of failure (C3, C5, C10, C4, and C14) with large may be covered
with condition monitoring or predictive type of approaches, causes of failure (C13, C8,
C7, C1, and C2) with medium is covered with preventive measures during
shut down and failure causes (C12, C6, C11, and C9) with small value of is
covered by remedial or corrective actions when breakdown prompts.
TABLE 4.10 based FMEA with existing practices and proposed
improvements in maintenance plan
Particulars
Current
Controls
Su
gg
este
d I
mpro
vem
ent
in
Mai
nte
nan
ce P
lan
No
tati
on
Key
Process
Input
Potential
Failure Mode
Potential
Causes
Potential
Failure Effects
What is
process
input?
How Process
inputs fail?
Why
important
input failed?
How the
impact
affected due to
failure
(customer or
internal)?
What are the
existing
practices
through
which
failure mode
controlled?
Rolling
Mill
Bearing
Failure
Bearing high
temperature
Improper
lubrication &
defective
sealing
Bearing gets
jammed/Beari
ng housing
jammed
Lubricating
the parts
when
occurred
Preventive
Maintenance C1
Bearing
corrosion
Higher speed
than specified
Increase in
vibration &
noise
Proper
coolant
Preventive
Maintenance C2
Bearing
fatigue
Design
defects,
bearing
dimension
not as per
specification
Life reduction Bearing
replacement
Predictive
Maintenance C3
Roller balls
wear- out
Foreign
matters/partic
les
Sudden rise in
thrust
Regular
cleaning of
parts
Predictive
Maintenance C4
Bearing
misalignment
& improper
mounting
Sudden
impact on the
rolls
Shaft damage
& Impact
damage on
other parts
Routine
check up
Predictive
Maintenance C5
Electrical
damage Power loss
Process
interruption
Electrical
wiring check
up
Corrective
Maintenance C6
Rolling
Mill
Gearing
Failure
Gear teeth
wear-out
Inadequate
lubrication –
Dirt, viscosity
issues
Rough
operation &
considerable
noise
Routine
check-up of
lubrication
Preventive
Maintenance C7
4.4 PSI based Failure Mode Effect and Criticality Analysis
81
Gear teeth
surface
fatigue
(Pitting)
Improper
meshing, case
depth & high
residual
stresses
Gear life
reduction
Preventive
maintenance
Preventive
Maintenance C8
Gear teeth
scoring
Overheating
at gear mesh
Interference &
backlash
phenomenon
Lubricating
when
needed
Corrective
Maintenance C9
Gear teeth
fracture
Excessive
overload &
cyclic
stresses
Sudden
stoppage of
process plant
Break down
maintenance
Predictive
Maintenance C10
Gear teeth
surface
cold/plastic
flow
Large contact
stresses due
to rolling and
sliding
meshing
Slippage &
power loss
Gear replace
when
needed
Corrective
Maintenance C11
Rolling
Mill Shaft
(Primary &
Secondary)
Failure
Shaft fretting
Vibratory
dynamic load
from bearing
Leads to
sudden failure
Break down
maintenance
Corrective
Maintenance C12
Shaft
misalignment
Uneven
bearing load
Vibration &
fatigue
Preventive
maintenance
Preventive
Maintenance C13
Shaft fracture
(Fatigue)
Reverse and
repeated
cyclic loading
Process
suddenly
stopped
Preventive
maintenance
Predictive
Maintenance C14
4.4 PSI based Failure Mode Effect and Criticality Analysis
4.4.1 PSI Methodology
Maniya and Bhatt (2011) discussed PSI approach. This method is very useful for
incompatible situations to take an effective decision. It is multi-criteria based crisp
approach which works on the principle of statistical tabulation without consideration of
weights to decide preferences.
The evaluation of of listed modes of failure of vital or critical parts of the
aluminium wire processing unit as discussed previously is done by the PSI method as
recommended by Maniya and Bhatt (2011).
The step-by-step process is described as under:
Step – 1: Preparing a decision matrix by arranging designated criteria and failure
causes into columns and rows correspondingly.
Multi-criteria Decision-making based Failure Analysis Models
82
The said decision matrix is deduced for a set of beneficial attributes (P, D, M, SP, ES,
EC) against a set of fourteen failure causes (C1 to C14) as per description stated in
Section 3.2.2.
Step – 2: Development of decision matrix – by assigning score value in exact number
= = [
] (4.26)
Where; represents fixed scores.
i = 1, 2… m representing causes of failure
j = 1, 2… n representing profit criteria
The decision matrix – as displayed in Table 4.11 is developed by proper assignment of
score value to matrix cell through the methods described in Section 3.3.2.
TABLE 4.11 Decision matrix – X for PSI
P D M SP ES EC
Pote
nti
al
Fai
lure
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f
fail
ure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic
safe
ty
Eco
nom
ic c
ost
C1 9 8 1 3 3 3
C2 8 6 2 2 4 3
C3 10 7 6 3 10 9
C4 9 6 5 3 7 5
C5 10 5 6 5 9 10
C6 9 1 1 3 5 2
C7 7 3 5 3 7 4
C8 8 5 5 3 5 5
C9 5 4 2 3 3 3
C10 9 2 6 4 7 7
C11 3 6 3 3 3 3
C12 5 5 4 3 3 3
C13 8 5 5 3 6 6
C14 9 2 6 4 6 7
4.4 PSI based Failure Mode Effect and Criticality Analysis
83
Step – 3: Normalizing decision matrix -
Considering likelihood level of attributes, normalizing of score-values is done with the
help of expressions as described under and the same is presented in Table 4.12.
Considering likelihood more for profit attributes;
=
(4.27)
Considering likelihood less for profit attributes;
=
(4.28)
where; and are the higher and lower score-value possible causes of failure
correspondingly;
Then;
Normalized decision matrix is as follows;
= [
] (4.29)
Step – 4: Determine deviation in preference
The deviation in preference is determined with an expression as under;
= ∑ ] (4.30)
where; =
∑
(4.31)
Step – 5: Determine deviation of parameter
The deviation in parameter is determined with an expression as under;
= (4.32)
Multi-criteria Decision-making based Failure Analysis Models
84
TABLE 4.12 Normalized decision-matrix – for PSI
P D M SP ES EC
Pote
nti
al F
ailu
re
Cau
ses
Pro
bab
ilit
y o
f
chan
ce o
f fa
ilure
Deg
ree
of
Det
ecta
bil
ity
Mai
nta
inab
ilit
y
Spar
e par
ts
Eco
nom
ic s
afet
y
Eco
nom
ic c
ost
C1 0.900 1.000 0.167 0.600 0.300 0.300
C2 0.800 0.750 0.333 0.400 0.400 0.300
C3 1.000 0.875 1.000 0.600 1.000 0.900
C4 0.900 0.750 0.833 0.600 0.700 0.500
C5 1.000 0.625 1.000 1.000 0.900 1.000
C6 0.900 0.125 0.167 0.600 0.500 0.200
C7 0.700 0.375 0.833 0.600 0.700 0.400
C8 0.800 0.625 0.833 0.600 0.500 0.500
C9 0.500 0.500 0.333 0.600 0.300 0.300
C10 0.900 0.250 1.000 0.800 0.700 0.700
C11 0.300 0.750 0.500 0.600 0.300 0.300
C12 0.500 0.625 0.667 0.600 0.300 0.300
C13 0.800 0.625 0.833 0.600 0.600 0.600
C14 0.900 0.250 1.000 0.800 0.600 0.700
Step – 6: Determine overall preference parameter
The is evaluated as per expression;
=
∑
(4.33)
Table 4.13 highlights the matrix of a product of and values.
Step – 7: Determine of each alternative.
The for all attributes are counted by expression;
= ∑ (4.34)
The preference of criticalities is arranged in an ascending manner of results of .
The higher should be considered the most pressing matter. Table 4.14 highlights
and rank preferences which may be helpful in recommending remedial measures.
4.4 PSI based Failure Mode Effect and Criticality Analysis
85
TABLE 4.13 Multiplication matrix of and
C D M SP ES EC
Pote
nti
al
Fai
lure
Cau
ses
Pro
bab
ilit
y
of
chan
ce
of
fail
ure
Deg
ree
of
Det
ecta
bil
it
y
Mai
nta
inab
i
lity
Spar
e par
ts
Eco
nom
ic
safe
ty
Eco
nom
ic
cost
C1 0.2500 0.1071 -0.0320 0.2845 0.0621 0.0381
C2 0.2220 0.0804 -0.0643 0.1897 0.0828 0.0381
C3 0.2775 0.0938 -0.1930 0.2845 0.2071 0.1144
C4 0.2497 0.0804 -0.1608 0.2845 0.1450 0.0636
C5 0.2775 0.0670 -0.1930 0.4741 0.1864 0.1272
C6 0.2497 0.0134 -0.0322 0.2845 0.1035 0.0254
C7 0.1942 0.0402 -0.1608 0.2845 0.1450 0.0509
C8 0.2220 0.0670 -0.1608 0.2845 0.1035 0.0636
C9 0.1387 0.0536 -0.0643 0.2845 0.0621 0.0381
C10 0.2497 0.0268 -0.1930 0.3793 0.1450 0.0890
C11 0.0832 0.0804 -0.0965 0.2845 0.0621 0.0381
C12 0.1387 0.0670 -0.1287 0.2845 0.0621 0.0381
C13 0.2220 0.0670 -0.1608 0.2845 0.1243 0.0763
C14 0.2497 0.0268 -0.1930 0.3793 0.1243 0.0890
TABLE 4.14 Maintainability criticality index and rank for PSI
Notation Potential Failure Causes Rank
C1 Improper lubrication & defective sealing 0.7095 3
C2 Higher speed than specified 0.5486 11
C3 Design defects, bearing dimension not as
per specification 0.7842 2
C4 Foreign matters/particles 0.6623 6
C5 Sudden impact on the rolls 0.9391 1
C6 Loss of power 0.6444 7
C7 Inadequate lubrication - dirt, viscosity
issues 0.5539 10
C8 Improper meshing, case depth & high
residual stresses 0.5797 9
C9 Overheating at gear mesh 0.5127 12
C10 Excessive overload & cyclic stresses 0.6968 4
C11 Large contact stresses due to rolling and
sliding meshing 0.4519 14
C12 Vibratory dynamic load from bearing 0.4618 13
C13 Uneven bearing load 0.6131 8
C14 Reverse and repeated cyclic loading 0.6761 5
Multi-criteria Decision-making based Failure Analysis Models
86
4.4.2 Significance of PSI
In PSI approach, the predilections of attributes or criteria are determined through the
statistical way. Moreover, the normalized numbers are not converted into weights as per
TOPSIS and COPRAS-G, which make this process more convenient. This method is best
suitable for incompatible situations where conclusions cannot be derived at common
points.
4.4.3 Maintenance Planning through PSI FMECA
Table 4.14 displays the outcomes in form of which are achieved from MCDM
assisted PSI approach as described in Section 4.4.1. The interpretation of these results
gives views about predilections of causes of failures. It conveys that failure cause C5;
sudden impact on the rolls due to bearing misalignment and improper mounting is vital
whereas cause of failure C11; large contact stresses due to rolling and sliding meshing is
minimal in terms of criticality.
This table also shows the failure mode effect analysis with current control practices and
suggested maintenance plan based on their criticalities. It is recommended to update the
current control practices as listed in Table 4.15 that modes of failure C5, C3, C1, C10,
and C14 having large is covered with condition-based monitoring or predictive
type of approaches, modes of failure C4, C6, C13, C8, and C7 having medium is
covered with preventive strategies on principle of prevention is good before collapsible
failures and modes of failure C2, C9, C12, and C11 having low is covered with
remedial actions when prompted.
4.4 PSI based Failure Mode Effect and Criticality Analysis
87
TABLE 4.15 based FMEA with existing practices and proposed improvements in
maintenance plan
Particulars
Current
Controls
Su
gg
este
d I
mpro
vem
ent
in
Mai
nte
nan
ce P
lan
No
tati
on
Key
Process
Input
Potential
Failure Mode
Potential
Causes
Potential
Failure Effects
What is
process
input?
How Process
inputs fail?
Why
important
input failed?
How the
impact
affected due to
failure
(customer or
internal)?
What are the
existing
practices
through
which
failure mode
controlled?
Rolling
Mill
Bearing
Failure
Bearing high
temperature
Improper
lubrication &
defective
sealing
Bearing gets
jammed/Beari
ng housing
jammed
Lubricating
the parts
when
occurred
Predictive
Maintenance C1
Bearing
corrosion
Higher speed
than specified
Increase in
vibration &
noise
Proper
coolant
Corrective
Maintenance C2
Bearing
fatigue
Design
defects,
Bearing
dimension
not as per
specification
Life reduction Bearing
replacement
Predictive
Maintenance C3
Roller balls
wear- out
Foreign
matters/partic
les
Sudden rise in
thrust
Regular
cleaning of
parts
Preventive
Maintenance C4
Bearing
misalignment
& improper
mounting
Sudden
impact on the
rolls
Shaft damage
& Impact
damage on
other parts
Routine
check up
Predictive
Maintenance C5
Electrical
damage Power loss
Process
interruption
Electrical
wiring check
up
Preventive
Maintenance C6
Rolling
Mill
Gearing
Failure
Gear teeth
wear-out
Inadequate
lubrication –
dirt, viscosity
issues
Rough
operation &
considerable
noise
Routine
check-up of
lubrication
Preventive
Maintenance C7
Gear teeth
surface
fatigue
(Pitting)
Improper
meshing, case
depth & high
residual
stresses
Gear life
reduction
Preventive
maintenance
Preventive
Maintenance C8
Gear teeth
scoring
Overheating
at gear mesh
Interference &
backlash
phenomenon
Lubricating
when
needed
Corrective
Maintenance C9
Gear teeth
fracture
Excessive
overload &
cyclic
stresses
Sudden
stoppage of
process plant
Break down
maintenance
Predictive
Maintenance C10
Multi-criteria Decision-making based Failure Analysis Models
88
Gear teeth
surface
cold/plastic
flow
Large contact
stresses due
to rolling and
sliding
meshing
Slippage &
power loss
Gear replace
when
needed
Corrective
Maintenance C11
Rolling
Mill Shaft
(Primary &
Secondary)
Failure
Shaft fretting
Vibratory
dynamic load
from bearing
Leads to
sudden failure
Break down
maintenance
Corrective
Maintenance C12
Shaft
misalignment
Uneven
bearing load
Vibration &
fatigue
Preventive
maintenance
Preventive
Maintenance C13
Shaft fracture
(Fatigue)
Reverse and
repeated
cyclic loading
Process
stopped
suddenly
Preventive
maintenance
Predictive
Maintenance C14
4.5 Summary
This chapter presents MCDM based failure analysis models with an addition of some
more advanced criteria. It also describes methods to evaluate MCI for each failure mode
of targeted critical components through three different MCDM failure analysis models
called; TOPSIS, COPRAS-G, and PSI for optimizing current maintenance strategies.
The next chapter discusses the out-trend of literature, the results of discrimination
process through shop-floor data for critical components and criticality indices obtained
through traditional and various MCDM based FMECA approaches as discussed in this
chapter. The comparison of results is displayed in form of tables, figures etc. for
effective understanding. Based on achieved RPN and MCI, remedial measures are
suggested and priority plan of existing maintenance activities is discussed in the chapter.
89
CHAPTER 5
Results and Discussion
5.1 General Overview
This chapter describes the results or outcome achieved in previous chapters; i.e. out-
trends of literature review, outcome of the discrimination process for components
through shop-floor data and results obtained through traditional and MCDM based
failure analysis models. The traditional, as well as multi-criteria decision-making based
FMECA approaches are applied to critical components in a view to investigating the
scope of improving reliability by optimizing existing maintenance practices.
The epilogue of such models and their impact on planning the maintenance activities are
discussed. Remedial measures are also discussed based on the observations and outcome
of study. Tables and figures are constructed to show the results and their comparisons in
a most effective manner possible.
The upshot of literature review mentioned the challenges to keep the performance
reliability of major industrial processes by incorporating suitable maintenance strategies.
It highlights the failure analysis as better tool to reach to the root cause of failures.
Furthermore, there were modifications observed in FMECA to enhance the maintenance
plan by some researchers for various processing units. The outcome of the literature
review clears a scope in contemporary application of non-identical MCDM approaches
to the maintenance prioritization problems. The aluminium wire rolling mill appears to
Results and Discussion
90
be one of the important segments of processing units due to the expansion of
electrification in India. The strong exigency of disproportionate multi-criteria FMCEA
approaches simultaneously at a time to an aluminium wire rolling mill is advocated and
discussed.
5.2 Results of Discrimination Process through Shop-floor Statistics
In chapter 2, the critical components of aluminium wire rolling mill are differentiated by
explicating the historical failure data and real shop-floor practices. The past records
regarding non-performance or failures of parts or components associated with an
aluminium processing machine are gathered as well as disseminated based on downtime,
frequency of failures and loss of production in terms of volume (tons) and cost. The
failure pattern behaviour of these components is understood with modelling of reliability
terms in this study. The identification of critical components is done based on actual
shop-floor condition and historical records. Fig. 5.1 shows the results of failure records
in form of % failure contributions of each part through pie chart for better understanding.
FIGURE 5.1: Pie chart presentation for % failure contributions of components
5.2 Results of Discrimination Process through Shop-floor Statistics
91
The interpretation of data extracted major critical components as;
(i) Bearings
(ii) Gears
(iii) Shafts
The total downtime recorded is 2117 hours during the study period of a year for rolling
machine. Out of which 1476 hours are only due to bearings failures. Moreover, it is
noted that the bearings failed 620 times of total 1072 failure frequencies. It seems that
the bearings are most critical with about 70 % failure contributions. It is observed that
the gear’s overall percentage failure contribution is 4 % having 204 hours downtime of
total 1476 hours. The gears failed 68 times of total 1072 failure frequencies. The failure
contributions of shafting are about 4% with 124 hours downtime of total 1476 hours with
bearings and gears. They failed 41 times of total 1072 failure frequencies.
The above parts are essential and responsible for a proper feed of the aluminium wire for
size reduction at every stage of a stand. These parts are interdependently working with
high speed and experiencing various forces. This phenomenon leads them the most vital
parts of an aluminium rolling machine. Moreover, these critical components (bearings,
gears, and shafts) are usual components to nearly all processing units.
The other remaining parts or components are contributing about 22 % loss due to their
failures with 313 hours downtime of total 1476 hours. They failed together for 343 times.
It is noted that all such parts are not having a significant effect on overall performance of
a rolling machine. Also, it is observed that many such parts are replaced under the
standard replacement of three identified vital parts; bearings, gears and shafts.
Table 5.1 represents outcome of the process of shop-floor data collection during April
2013 to March 2014 regarding the performance of three discriminated vital parts over
other components of a rolling machine.
Results and Discussion
92
Table 5.1: Outcome of shop-floor data regarding performance of rolling machine parts
Sr.
No. Particulars Downtime (Hours)
Frequency of
failures (n)
1 Bearings (Critical part-1) 1476 620
2 Gears (Critical part-2) 204 68
3 Shafts (Critical part-3) 124 41
4 All remaining parts other than
critical 1, 2, and 3 313 343
Rolling mill as a whole unit
(All parts-Total) 2117 1072
5.3 Results of Traditional FMECA Model
In traditional FMECA, RPN of every failure mode is calculated for specific critical
components by multiplying scores of three basic criteria. The score are modeled for each
criterion for every failure mode is on a scale of 1 to 10 based on actual perspective of the
maintenance personnel and shop-floor conditions.
The classification of various failure modes is done through obtained RPN value in most
critical, critical and normal. The failure modes are scrutinized as most critical for RPN
value 500 or higher and need predictive or condition-based maintenance. The failure
modes are scrutinized as critical for RPN value ranging between 250 and 500 and
proposed preventive type of strategies. Whereas failure modes with RPN value below
250 are termed as normal failures and proposed cured when failed concept of corrective
strategies.
Table 5.2 shows the categorization of different failure causes based on their criticalities
evaluated through RPN. The failure mode bearing fatigue (C3) is the most critical failure
mode under study. The failure modes C1, C4, C5, C8, C10, C13 are found critical and
C2, C6, C7, C9, C11, C12, C14 are found normal.
5.4 Results of MCDM based FMECA
93
TABLE 5.2 Outcome (RPN) of traditional FMECA and suggestions
RPN Value Failure Causes Criticality
Level
Suggested
Maintenance
Plan
More than 500 C3 Most critical Predictive
Between 250 to 500 C13, C10, C4, C5, C8, C1 Critical Preventive
Less than 250 C14, C9, C12, C11, C2, C7, C6 Normal Corrective
The Fig. 5.2 shows the graphical representation of RPN for each failure cause based on
the traditional FMECA approach.
FIGURE 5.2 RPN for each failure cause based on traditional FMECA
5.4 Results of MCDM based FMECA
The for various modes of failure of targeted vital parts are determined based on
three non-identical MCDM failure analysis models called; TOPSIS, COPRAS-G, and
PSI as discussed in Chapter 4. The six criteria; P, D, M, SP, ES and EC as described in
Section 3.3.2 are assigned scores based on actual shop-floor practices in order to find
MCIs. The outcome of the study categorized the failure causes in most critical, critical
and normal failures for a high, moderate and low value of MCIs respectively. The
appropriate maintenance action has been suggested which is discussed in Section 5.5.
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14
RPN 280 72 630 336 320 14 50 320 168 384 75 150 392 224
0
100
200
300
400
500
600
700
RP
N
Traditional FMECA
RPN
Results and Discussion
94
Table 5.3 shows the categorization of different failure causes based on their criticalities
evaluated through MCDM approaches. Moreover, Fig. 5.3 shows the graphical
representation of MCIs for each failure cause based on different MCDM FMECA
approaches.
TABLE 5.3 Outcome (MCI) of MCDM FMECAs and suggestions
FIGURE 5.3 MCI for each failure cause based on MCDM based FMECA
Particulars Failure Causes
Met
hod
s
TOPSIS C5, C3, C4, C10,
C14
C13, C8, C7, C1,
C12
C2, C11, C9, C6
COPRAS-G C3, C5, C10, C4,
C14
C13, C8, C7, C1,
C2
C12, C6, C11, C9
PSI C5, C3, C1, C10,
C14
C4, C6, C13, C8,
C7
C2, C9, C12, C11
MCI Value Impact High Moderate Low
Criticality Level Most Critical Critical Normal
Suggested Plan Predictive
(Condition-based)
Preventive Corrective
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14
TOPSIS FMECA 0.4265 0.3640 0.7986 0.5794 0.8051 0.2499 0.4419 0.4981 0.2515 0.5636 0.3460 0.3525 0.5505 0.5455
COPRAS FMECA 0.1297 0.1244 0.2156 0.1662 0.2079 0.1062 0.1401 0.1444 0.0863 0.1700 0.1022 0.1096 0.1477 0.1526
PSI FMECA 0.7095 0.5486 0.7842 0.6623 0.9391 0.6444 0.5539 0.5797 0.5127 0.6968 0.4519 0.4618 0.6131 0.6761
0.0000
0.1000
0.2000
0.3000
0.4000
0.5000
0.6000
0.7000
0.8000
0.9000
1.0000
MC
I
MCDM Based FMECA
TOPSIS FMECACOPRAS FMECAPSI FMECA
5.5 Suggested Remedies
95
5.5 Suggested Remedies
During the failure pattern study, it is observed that almost 70 % downtime is due to
bearing failure and replacement practice is 100 %. The bearing is rotational machining
member under dynamic loading. The primary reason for high failure rate is the use of
non-standardize bearings. Moreover, it is noticed poor shop-floor management, lack of
proper documentation and monitoring regarding failure rate, inadequate or traditional
maintenance practice like; mounting and misalignment issues, lubrication issues etc.
Also, the gears and shafting functions are dependent on bearing performance. Such
issues make the bearings vital part of major industrial processing units like; aluminium
rolling mill.
It is suggested to select standardize bearing with appropriate specifications and mount
them properly during every replacement. This will help to avoid bearing misalignment
(C5) and minimizing reverse and repeated cyclic loading thus shaft fatigue (C14) and
gear tooth fracture (C10) can be controlled.
An appropriate condition monitoring methods are suggested to record the condition of
bearing damage and shaft damage which will help to prevent sudden breakdown and
starting thrust on these components. Also, it is suggested checking the condition of
lubricants and replacing them whenever necessary rather than routine clean up. So that,
failure causes such as; sudden impact on the rolls (C5), design defects with bearing
dimension/specification (C3), foreign matters/particles (C4), excessive overload & cyclic
stresses (C10) and reverse & repeated cyclic loading (C14) can be covered and
controlled under recommendations.
Table 5.4 shows the maintenance action plan based on a comparison of results obtained
through traditional as well as MCDM based FMECA (TOPSIS/COPRAS-G/PSI)
approaches respectively. The suggestions in the revision of the current control practices
are derived based on the concurrent effect of these results and same is displayed in Table
5.4. The common modes of failure C5, C3, C4, C10, and C14 having large is
covered with condition-based monitoring or predictive type of approaches, modes of
failure (C13, C7, C8, and C1) having medium is covered with preventive measures
where it is assumed that avoidance of failure is better than restore and modes of failure
Results and Discussion
96
(C2, C11, C12, C6, and C9) having small is covered by remedial or corrective
actions when breakdown prompts.
5.6 Summary
This chapter discusses the out-trend of literature, the results of discrimination process
through shop-floor data for critical components and criticality indices obtained through
traditional and various MCDM based FMECA approaches as discussed in chapter 3. The
comparison of results is displayed in form of tables, figures etc. for effective
understanding. Based on achieved RPN and MCI, remedial measures are suggested and
priority plan of existing maintenance activities is discussed in the chapter.
The next chapter includes the conclusions of a present research study and the scope of
future work recommendations.
5.6 Summary
97
TABLE 5.4 Maintenance optimization action plan
Key
Pro
cess
Inp
ut
Po
ten
tia
l
Ca
use
s
Cu
rren
t
Co
ntr
ols
No
tati
on
RPN Maintainability
Criticality Index Rank
Su
gg
esti
on
Tra
dit
ion
al
TO
PS
IS
CO
PR
AS
-G
PS
I
Tra
dit
ion
al
TO
PS
IS
CO
PR
AS
-G
PS
I
Bearing
Failure
Improper
lubrication &
defective
sealing
Lubricating
the parts
when
occurred
C1 280 0.4265 0.1297 0.7094 7 9 9 3 Preventive
Maintenance
Higher speed
than specified
Proper
coolant C2 72 0.3640 0.1244 0.5486 12 10 10 11
Corrective
Maintenance
Design defects,
Bearing
dimension, not
as per
specification
Bearing
replacement
C3 630 0.7986 0.2156 0.7842 1 2 1 2 Predictive
Maintenance
Foreign
matters/particles
Regular
cleaning of
parts
C4 336 0.5794 0.1662 0.6622 4 3 4 6 Predictive
Maintenance
Sudden impact
on the rolls
Routine
check up C5 320 0.8051 0.2079 0.9391 5 1 2 1
Predictive
Maintenance
Power loss
Electrical
wiring
check up
C6 14 0.2499 0.1062 0.6444 14 14 12 7 Corrective
Maintenance
Rolling
Mill
Gearing
Failure
Inadequate
lubrication -
dirt, viscosity
issues
Routine
check-up of
lubrication
C7 50 0.4419 0.1401 0.5538 13 8 8 10 Preventive
Maintenance
Improper
meshing, case
depth & high
residual stresses
Preventive
maintenance C8 320 0.4981 0.1444 0.5797 6 7 7 9
Preventive
Maintenance
Overheating at
gear mesh
Lubricating
when
needed
C9 168 0.2515 0.0863 0.5127 9 13 14 12
Corrective
Maintenance
Excessive
overload
& cyclic
stresses
Break down
maintenance C10 384 0.5636 0.1700 0.6967 3 4 3 4
Predictive
Maintenance
Large contact
stresses due to
rolling and
sliding meshing
Gear
replace
when
needed
C11 75 0.3460 0.1022 0.4518 11 12 13 14 Corrective
Maintenance
Rolling
Mill Shaft
(Primary
&
Secondary)
Failure
Vibratory
dynamic load
from bearing
Break down
maintenance C12 150 0.3525 0.1096 0.4617 10 11 11 13
Corrective
Maintenance
Uneven bearing
load
Preventive
maintenance C13 392 0.5505 0.1477 0.6131 2 5 6 8
Preventive
Maintenance
Results and Discussion
98
Reverse and
repeated cyclic
loading
Preventive
maintenance C14 224 0.5455 0.1526 0.6760 8 6 5 5
Predictive
Maintenance
99
CHAPTER 6
Conclusion and Future Scope
6.1 General Overview
In this thesis, the research study has been carried out to investigate the scope of
reliability improvement by optimizing the maintenance practices through actual failure
analysis with the help of traditional as well as multi-criteria FMECA approaches. In this
study, three distinct MCDM approaches namely; TOPSIS, COPRAS-G, and PSI are
discussed. The essences or criteria employed in this study are; probability of chances of
failure, degree of detectability and degree of severity for traditional approach. Moreover
along with probability of chances of failure and degree of detectability; some advanced
criteria like; maintainability, spare parts, economic cost, economic safety are selected
based on the outcome of shop-floor analysis and reliability modeling for MCDM based
failure analysis models.
The failure analysis models are applied to the identified vital components i.e.; bearings,
gears and machining shafts. The identification of critical components is done and FMEA
is deduced with real shop-floor practices. In order to obtain quantitative results,
criticality analysis is governed by assigning the scores to each failure causes of these
components. To do such task effectively, the plant has been monitored for a period from
April 2013 to March 2014 to record the historical failure data in the specific format as
suggested. Moreover, reliability modelling is done with the help of these data to
understand the behaviour of the failure pattern of the rolling mill.
Conclusion and Future Scope
100
To compensate the disadvantages or limitations of traditional failure analysis models,
MCDM based FMECA approaches are discussed. It is concluded from the outcome of all
failure analysis models that failure causes C3, C5, C10 and C14 have prescribed crucial
and advised intensive technical measures. These results are helpful in prioritizing
maintenance activities of process industry of same or of different kinds in accordance
with failure analysis.
6.2 Major Concluding Remarks
Lack of proper maintenance planning without absolute failure analysis is the main reason
of loss of reliability and poor productivity in process industries. In such condition, it is
necessary to optimize current control and maintenance practices. In this research work,
the novelty is primarily abiding by the demonstration of a case study of aluminium wire
rolling mill plant with contemporary application of three non-identical MCDM based
failure analysis models. The cardinal parts discussed here are usually revealing the large-
scale industrial processes along with metal rolling. Thus, the results and
recommendations are useful in explicating the drawbacks of the extant maintenance plan
and revise the same to comparable processing units.
Following conclusions are drawn from presented research work:
(i) The notable past failure statistics (downtime, frequency of failures, loss of
production in terms of tons and cost) of an aluminium wire rolling mill are
recorded with the help of templates suggested in Table 2.1, 2.2 and 2.3 for April
2013 to March 2014. These data are analysed based on reliability to extract an
explicative components i.e.; bearings, gears and machining shafts.
(ii) The study is concentrating prospective modes of various failures of imperative
parts such as; ball or roller type bearings, gears for shorter distance power
transmission and machining shafts of wire rolling process unit. These machining
parts are usually characterized in almost all manufacturing or processing units.
(iii) In traditional FMECA, usually three basic criteria as mentioned in chapter 3 are
considered. In MCDM based FMECA, the severity is replaced with maintainability
to impart value to the maintenance as a measurable term. Furthermore, the
economic safety, economic cost and spares are enumerated. To quantify the effect
6.3 Recommendations for Future Scope of Work
101
of these criteria statically, each criterion is scored on a scale of 1 to 10 based on
perspective of real shop floor context and its footprint on the diverse failure modes.
(iv) Maintenance planning is proposed in RPN for traditional FMECA and to overcome
the drawback of it, maintainability criticality indices are evaluated by three distinct
multi-criteria decision-making approaches; TOPSIS in crisp value, COPRAS-G in
grey number range and PSI where subjective weight consideration not required for
calculating .
(v) The results are helpful in prioritizing maintenance activities of a process industry of
alike or of dissimilar kinds in accordance with the failure analysis. The outcome of
the research in form of the maintenance prioritization will assist in indicating the
procedure for maintaining other non-performing issues of related industrial process
optimally to improve the plant to certain extent.
(vi) The proposed study is a demanding and collaborative type which assists in
comprehension of parts or components’ design life and connected defects. This
will lead to boost new technologies efficiently and to gain the operational
advantage.
6.3 Recommendations for Future Scope of Work
The research work presented can further be extended as under:
(i) Similar work can be extended to other related or different kinds of process industries
like; chemical or fertilizer unit, clothing or sugar mill, petroleum refineries etc. in a
view to deciding suitable maintenance strategy with other multi-criteria based
approaches such as; qualitative flexible multi-criteria (QUALIFLEX), heuristic tools
etc.
(ii) In this research, six criteria are considered during modelling of scores to each failure
cause for further failure analysis. However, there is a scope to incorporate some
more attributes such as; the skill of person, process environment, atmospheric
degradation etc. based on a need of industry.
(iii) Failure analysis approaches can be developed for various process industries
considering contemporaneous failures among various systems.
Conclusion and Future Scope
102
6.4 Limitations of Proposed Research Work
The proposed research study has some limitations as under:
(i) Failure pattern of various kinds of ball and roller bearings are considered identical
and subsequently, failure analysis models have been proposed.
(ii) Reliability parameters like; future forward time and backward time are not
considered during reliability modelling. This may be helpful specifically when it is
difficult to detect failure time.
(iii) The proposed failure models are not showing failures occurred with design
acceptance for parts having an excessive rate of failure and it is out of the scope of
this study.
(iv) The metallurgical aspect of raw aluminium is important for the quality of final
products. It is not the part of a proposed research study.
6.5 Summary
This chapter includes the conclusions of a present research study and the scope of future
work recommendation
103
References
1. Abbas Toloie Eshlaghy and Mahdi Homayonfar, (2011), “MCDM methodologies
and applications: A literature review from 1999 to 2009”, Research Journal of
International studies, vol. 21, Accessed from:
https://www.researchgate.net/publication/259933820
2. Adhikary D. D., Bose G. K., Bose D., and Mitra S., (2014), “Multi-criteria
FMECA for coal-fired thermal power plants using COPRAS-G,” International
Journal of Quality & Reliability Management, vol. 31, no. 5, pp. 601–614, ISSN:
0265-671X.
3. Albert H.C. Tsang, (1995), "Condition‐based maintenance: tools and decision
making", Journal of Quality in Maintenance Engineering, Vol. 1 Issue:
3, pp.3-17, https://doi.org/10.1108/13552519510096350.
4. Andrawus, J. A., Watson, J. and Kishk, M., (2007), “Wind turbine maintenance
optimization: principles of quantitative maintenance optimization”, Wind
Engineering, vol. 31 (2), pp. 101-110, ISSN: 0309-524X.
5. Ashayeri J., Teelen A., and W. Selenj W., (1996), “A production and
maintenance planning model for process industry”, International Journal for
Production Research, Issue 12, vol. 34, pp. 3311-3326, ISSN: 0020-7543.
6. DuyQuang Nguyen and Miguel Bagajewicz, (2008), “Optimization of preventive
maintenance scheduling in processing plants”, 18th European Symposium on
Computer aided Process Engineering, Elsevier, Volume 25, pp. 319–324.
7. Bevilacqua M., Braglia M., and Gabbrielli R., (2000), “Monte Carlo simulation
approach for a modified FMECA in a power plant,” Quality and Reliability
Engineering International, vol. 16, no. 4, pp. 313–324, ISSN: 1099-1638.
8. Braaksma, A., Klingenberg W., and Veldman J. (2013), “Failure mode and effect
analysis in asset maintenance: a multiple case study in the process industry”,
International Journal of Production Research, Issue 4, vol. 51, pp. 1–17, ISSN:
0020-7543.
9. Braglia M, Frosolini M., Montanari R. (2003), “Fuzzy TOPSIS approach for
failure mode, effect and criticality analysis”, Quality and Reliability Engineering
International, vol. 19, pp. 425-443, ISSN: 1099-1638.
104
10. Braglia M., (2000), “MAFMA: multi-attribute failure mode analysis,”
International Journal of Quality & Reliability Management, vol. 17, no. 9, pp.
1017–1033, ISSN: 0265-671X.
11. Braglia M., Frosolini M., and Montanari R., (2003), “Fuzzy TOPSIS approach
for failure mode, effects and criticality analysis” Quality and Reliability
Engineering International, vol. 19, no. 5, pp. 425–443, ISSN: 1099-1638.
12. Braglia M., Frosolini M., and Montanari R., (2003), “Fuzzy criticality assessment
model for failure modes and effects analysis,” International Journal of Quality &
Reliability Management, vol. 20, no. 4, pp. 503–524, ISSN: 0265-671X.
13. Chanamool N., T. Naenna, (2016), “Fuzzy FMEA application to improve the
decision-making process in an emergency department,” Applied Soft Computing,
vol. 43, pp. 441–453, ISSN: 1568-4946.
14. Chang C. L., Wei C. C., and Lee Y. H., (1999), “Failure mode and effects
analysis using fuzzy method and grey theory,” Kybernetes, vol. 28, no. 9, pp.
1072–1080.
15. Chen, LeiZhi, Sing Kiong Nguang, Xiao Dong Chen, and Xue Mei Li. (2004),
“Modeling and optimization of fed-batch fermentation processes using dynamic
neural networks and genetic algorithms” Biochemical Engineering Journal vol.
22, Issue 1, pp. 51–61. doi:10.1016/j.bej.2004.07.012, ISSN: 1369-703X.
16. Chen, Tao, Jiawen Li, Ping Jin, and Guobiao Cai., (2013), “Reusable rocket
engine preventive maintenance scheduling using genetic algorithm”, Reliability
Engineering & System Safety, vol. 114, pp. 52–60, ISSN: 0951-8320.
17. Dekker, (1996), “Applications of maintenance optimization models: a review and
analysis”, Reliability Engineering & System Safety vol. 51, no. 3, pp. 229–240,
ISSN: 0951-8320.
18. Deng J. L., (1989), “Introduction to grey system theory”, The Journal of Grey
Theory, vol. 1, no. 1, pp. 1–24.
19. Eti, M.C., S.O.T. Ogaji, and S.D. Probert, (2006), “Development and
implementation of preventive-maintenance practices in Nigerian industries”,
Applied Energy, vol. 83, no. 10, pp. 1163–1179, ISSN: 0306-2619.
20. Feili H. R., Akar N., Lotfizadeh H., Bairampour M., Nasiri S., (2013), “Risk
analysis of geothermal power plants using failure modes and effects analysis
(FMEA) technique”, Journal of energy conservation and management, Vol. 72,
pp.69-76, ISSN: 0196-8904.
105
21. Fragassa C, Ippoliti M., (2016), “Failure mode effects and criticality analysis
(FMECA) as a quality tool to plan improvements in ultrasonic mould cleaning
systems”, International Journal for Quality Research, vol. 10, Issue 4, 2016, pp.
847-870, ISSN: 1800-6450.
22. Fragassa C, Pavlovic A., Massimo S., (2014), “Using a total quality strategy in a
new practical approach for improving the product reliability in automotive
industry”, International Journal for Quality Research, vol. 8(3), pp. 297-310,
ISSN 1800-6450.
23. Fulop J., (2005), “Introduction to decision making methods,” BDEI Workshop,
pp. 1–15.
24. Gargama H., and Chaturvedi S. K., (2011), “Criticality assessment models for
failure mode effects and criticality analysis using fuzzy logic”, IEEE
Transactions on Reliability, vol. 60, no. 1, pp. 102–110, ISSN: 0018-9529.
25. Ghosh Devarun, Roy Sandip, (2009), “Maintenance optimization using
probabilistic cost-benefit analysis”, Journal of Loss Prevention in Process
Industry, Elsevier, vol. 22, pp. 403-407, ISSN: 0950-4230.
26. Gilchrist, W. (1993), “Modeling failure modes and effects analysis'',
International Journal of Quality & Reliability Management, vol. 10, No. 5, pp.
16-23, ISSN: 0265-671X.
27. Godwin Barnabas, Maran M, Nixon G S and I Ambrose, (2012), “Maintenance
cost optimization in process industry”, International Journal of Mechanical
Engineering and Robotics Research, Vol.1, No.3, pp. 81-90, ISSN 2278 – 0149.
28. Hwang C. L., Yoon K., (1981), “Multiple attribute decision making: methods and
applications”, Volume 186 of Lecture Notes in Economics and Mathematical
Systems, Springer, New York, USA.
29. Janssen R., (2001), “On the use of multi-criteria analysis in environmental impact
assessment in The Netherlands”, Journal of multi-criteria decision analysis, vol.
10, Issue 2, pp. 101-109, ISSN: 1099-1360.
30. Jensen (1995), “Stochastic models of reliability and maintenance: an overview”,
Proceedings of the NATO Advanced Study Institute on Current Issues and
Challenges in the Reliability and Maintenance of Complex Systems, Kemer-
Antalya, Turkey, June 12–22, pp. 3–36.
106
31. Knapp Gerald M., and Milind Mahajan, (1998), “Optimization of maintenance
organization and manpower in process industries” Journal of Quality in
Maintenance Engineering, vol. 4, no. 3, pp. 168–183, ISSN: 1355-2511.
32. Konak Abdullah, David W. Coit, and Alice E. Smith, (2006), “Multi-objective
optimization using genetic algorithms: a tutorial”, Reliability Engineering &
System Safety, vol. 91, no. 9, pp. 992–1007, ISSN: 0951-8320.
33. Liao R, Bian J., Yang L., Grzybowski S., (2012), “Cloud model-based failure
mode and effects analysis for prioritization of failures of power transformer in
risk assessment”, International transactions on electrical energy systems, vol. 23,
pp. 1172–1190, ISSN: 2050-7038.
34. Lin Y. H., Lee P. C., and Ting H. I., (2008), “Dynamic multi-attribute decision-
making model with grey number evaluations”, Expert Systems with Applications,
vol. 35, no. 4, pp. 1638–1644, ISSN: 0957-4174.
35. Liu H. C., You J. X., You X. Y., and Shan M. M., (2015), “A novel approach for
failure mode and effects analysis using combination weighting and fuzzy VIKOR
method”, Applied Soft Computing, vol. 28, pp. 579–588, ISSN: 1568-4946.
36. Lynch, P., K. Adendorff, V. S. S. Yadavalli, and O. Adetunji, (2013), “Optimal
spares and preventive maintenance frequencies for constrained industrial
systems”, Computers & Industrial Engineering, vol. 65, no. 3, pp. 378–387,
ISSN: 0360-8352.
37. Macharis C., Springael J., Brucker K, D., Verbeke A., (2004), “PROMETHEE
and AHP: The design of operational synergies in multi criteria analysis:
strengthening PROMETHEE with ideas of AHP”, European Journal of
Operational Research, vol. 153, pp. 307-317, ISSN: 0377-2217.
38. Mahadevan M.L, Poorana Kumar S, and Vinodh R., (2010), “Preventive
Maintenance Optimization of Critical Equipment in Process Plant Using
Heuristic Algorithms”, Proceedings of the 2010 International Conference on
Industrial Engineering and Operations Management, Dhaka, Bangladesh,
January 9 – 10.
39. Maity S. R., Chatterjee P., and Chakraborty S., (2012), “Cutting tool material
selection using grey complex proportional assessment method”, Materials and
Design, vol. 36, pp. 372–378, ISSN: 0264-1275.
107
40. Maniya K. D., Bhatt M. G., (2011), “A selection of material using a novel type
decision making method: preference selection method”, Materials and Design,
Vol. 31, pp. 1785-1789, ISSN: 0264-1275.
41. Marseguerra, Marzio, Enrico Zio, and Luca Podofillini, (2002), “Condition-based
maintenance optimization by means of genetic algorithms and Monte Carlo
simulation”, Reliability Engineering & System Safety, vol. 77, no. 2, pp. 151–165,
ISSN: 0951-8320.
42. Mehdi Vasili, Tang Sai Hong, Napsiah Ismail, Mohammadreza vasili, (2011),
“Maintenance optimization models: a review and analysis”, Proceedings of the
2011 International Conference on Industrial Engineering and Operations
Management, pp. 1131-1138, Kuala Lumpur, Malaysia, January 22-24.
43. Mittal K., Tiwary P. C., Khanduja D, Kaushik P., (2016), “Application of Fuzzy
TOPSIS MADM approach in ranking & underlining the problems of plywood
industry in India”, Journal of Cogent Engineering, vol. 3, Issue 1, ISSN: 2331-
1916.
44. Mobin M., Roshani A., Saeedpoor M., & Mozaffari M. M. (2015), “Integrating
FAHP with COPRAS-G method for supplier selection (case study: An Iranian
manufacturing company)”, Proceedings of the International Annual Conference
of the American Society for Engineering Management, American Society for
Engineering Management (ASEM).
45. Moghaddass R., M. J. Zuo and Jian Qu, (2011), “Reliability and availability
analysis of a repairable -out-of- System with repairmen subject to shut-off rules”,
IEEE Transactions on Reliability, vol. 60, no. 3, pp. 658–666. ISSN: 0018-9526.
46. Mohanta Dusmanta Kumar, Pradip Kumar Sadhu, and R. Chakrabarti, (2007),
“Deterministic and stochastic approach for safety and reliability optimization of
captive power plant maintenance scheduling using GA/SA-based hybrid
techniques: a comparison of results”, Reliability Engineering & System Safety,
vol. 92, no. 2, pp. 187–199, ISSN: 0951-8320.
47. Nastac, L., and A.A. Thatte., (2006), “A heuristic approach for predicting fault
locations in distribution power systems”, Power Symposium, NAPS 2006, North
American, doi:10.1109/NAPS.2006.360136.
48. Parida S., N.R.Kotu, M. M. Prasad, (2000), “Development and implementation of
reliability centered maintenance using vibration analysis: experiences at Rourkela
108
steel plant”, 15th
World Conference on Non-destructive Testing, Rome, Italy, 15-
21 October.
49. Pham, Wang (1996), “Imperfect maintenance”, European Journal of Operational
Research, vol. 94, pp. 425–438, ISSN: 0377-2217.
50. Pintelon L. M. and Gelders L. F., (1992), “Maintenance management decision
making”, European Journal of Operational Research, vol. 58, Issue 3, pp. 301-
317, ISSN: 0377-2217.
51. Rastegari A., Archenti A., Mobin M., (2017), “Condition-based maintenance of
machine tools: Vibration monitoring of spindle units”, IEEE Reliability and
Maintainability Symposium (RAMS), pp. 1-8, Florida (FL), USA.
52. Rathi R., Khanduja D., Sharma S. K., (2016), “A fuzzy-MADM based approach
for prioritizing six sigma projects in the Indian auto sector”, International
Journal of Management Science and Engineering Management, Page 1-8,
http://dx.doi.org/10.1080/17509653.2016.1154486.
53. Sachdeva A., Kumar D., and Kumar P., (2009), “Multi-factor failure mode
criticality analysis using TOPSIS”, Journal of Industrial Engineering,
International, vol. 5, no. 8, pp. 1–9, ISSN: 1735-5702.
54. Sahoo T., Sarkar P. K., and Sarkar A. K., (2014), “Maintenance optimization for
critical equipment in process industry based on FMECA method”, International
Journal of Engineering and Innovative Technology, vol. 3, no. 10, pp. 107–112,
ISSN: 2277-3754.
55. Salabun W., (2013), “The mean error estimation of TOPSIS method using a
fuzzy reference models”, Journal of Theoretical and Applied Computer Science,
vol. 7, Issue 3, pp. 40–50, ISSN: 2299-2634.
56. Santos, Amancio, and Antonio Dourado, (1999), “Global optimization of energy
and production in process industries: a genetic algorithm application”, Control
Engineering Practices, vol. 7, issue 4, pp. 549-554, ISSN: 0967-0661.
57. Sikorska J., (2008), “Identifying failure modes retrospectively using RCM data”,
ICOM Asset Management Conference, Fremantle, May 26-29.
58. Son, Young Kap, (2011), “Reliability prediction of engineering systems with
competing failure modes due to component degradation”, Journal of Mechanical
Science and Technology, vol. 25, no. 7, pp. 1717–1725, ISSN: 1738-494X.
59. Sortrakul, N., H. L. Nachtmann, and C. R. Cassady, (2005), “Genetic algorithms
for integrated preventive maintenance planning and production scheduling for a
109
single machine”, Computers in Industry, vol. 56, no. 2, pp. 161–168, ISSN: 0166-
3615.
60. Vandenbrande W. W., (1998), “How to use FMEA to reduce the size of your
quality toolbox”, Quality progress, vol. 31, Issue 11, pp. 97-100, ISSN: 0033-
524X.
61. Verma Ajit Kumar, A. Srividya, and P. G. Ramesh, (2010), “A systemic
approach to integrated E-maintenance of large engineering plants”, International
Journal of Automation and Computing, vol. 7, no. 2, pp. 173–179, ISSN: 1476-
8186.
62. Van Rjin C., (1987), “A system engineering approach for reliability, availability
and maintainability”, Conference on foundation of computer aided operations,
Salt Lake city, UT, July 5-10.
63. Wiecek M, M., Ehrgott M., Fadel G., Figueira J. R., (2008), “Multiple criteria
decision making for engineering”, Omega, The International Journal of
Management Science, vol. 36, pp. 337-339, ISSN: 0305-0483.
64. Xu K., Tang L. C., Xie Ho S. L., and Zhu M. L., (2002), “Fuzzy assessment of
FMEA for engine systems,” Reliability Engineering & System Safety, vol. 75, no.
1, pp. 17–29, ISSN: 0951-8320.
65. Yang Zhixian, and Guobin Yang, (2012), “Optimization of aircraft maintenance
plan based on genetic algorithm”, Physics Procedia, pp. 580–586,
doi:10.1016/j.phpro.2012.05.107.
66. Zammori F., Gabbrielli R., (2011), “ANN/RPN: a multi criteria evaluation of the
risk priority number”, Journal of quality and reliability engineering.
International, vol. 28, pp. 85–104, ISSN: 1099-1638.
67. Zavadskas E. K., Kaklauskas A., Turskis J., and Tamosaitiene J., (2008),
“Selection of the effective dwelling house walls by applying attributes values
determined at intervals”, Journal of Civil Engineering and Management, vol. 14,
no. 2, pp. 85–93, ISSN: 1392-3730.
68. Zavadskas E. K., Kaklauskas A., Turskis J., and Tamosaitiene J., (2009), “Multi-
attribute decision-making model by applying grey numbers,” Informatica, IOS
press, Amsterdam, vol. 20, no. 2, pp. 305–320.
110
69. Zhang F., (2015), “Failure modes and effects analysis based on fuzzy TOPSIS”,
Proceedings of the IEEE International Conference on Grey System and
Intelligent Services (GSIS), pp. 588–593, Leicester, UK.
Books:
1. Balagurusamy E., (1984), “Reliability Engineering”, Tata McGraw Hill, New
Delhi, ISBN-13: 978-0-07-048339-2.
2. Barlow and Proschan (1965), “Mathematical Theory of Reliability”, Wiley &
Sons, New York, Republication in 1996 by Society for Industrial and Applied
Mathematics, ISBN: 978-0-898713-69-5.
3. Dhillon B. S. (1985), “Quality Control, Reliability, and Engineering Design”,
Marcel Dekker, New York, ISBN: 0-8247-7278-4.
4. Ebeling Charles (2016), “An Introduction to Reliability and Maintainability
Engineering”, 19e reprint, McGraw Hill Education (India) Private Limited,
ISBN-13: 978-0-07-042138-2.
5. Hoang Pham (2003), “Handbook of Reliability Engineering”, Springer, ISBN:
978-1-85233-453-6.
6. Holmberg K., Folkeson A. (1991), “Operation reliability and systematic
maintenance”, Elsevier science publishers’ ltd., London, ISBN: 1-85166-612-5.
7. Kececioglu D. (2002), “Reliability Engineering Handbook”, vol. 1, DEStech
publication, ISBN: 1-932078-00-2.
8. Khanna O.P., (2010), “Industrial Engineering and Management”, Dhanpat rai &
sons, ISBN-13: 978-818992835.
9. Kumar Sanjeev, (2009), “Performance analysis and optimization of some
operating systems of a fertilizer plant”, NIT, Kurukshetra, Ph. D. thesis, 2009.
10. Mcdermott R. R., Mikulak R. J. (2009), Beauregard M. R., “Basics of FMEA”,
2nd
Edition, CRC press (Taylor and Francis Group), New york, ISBN: 13: 978-1-
56327-377-3.
11. Mishra R C & Pathak K (2012), “Maintenance Engineering and Management”,
Prentice Hall of India Pvt. Ltd., New Delhi, 2012, ISBN: 978-81-203-4573-7.
12. Moubray J. (1997), “Reliability-centered Maintenance”, 2nd edition, Industrial
Press Inc., ISBN: 0-8311-3078-4.
13. Omdahl T. P. (1988), “Reliability, Availability and Maintainability Dictionary”,
Milwaukee, ASQC Quality Press, ISBN: 0-873-890450.
111
14. O’Connor P. (2002), “Practical Reliability Engineering, John Wiley, England,
ISBN 13: 978-0-470-84462-5.
15. Roy B. (1996), “Multicriteria Methodology for Decision Aiding”, Kluwer
Academic Publishers, ISBN: 978-1-4757-2500-1 (e-book).
16. “Training and Operating Manual” – Sampat Aluminium Rolling Mill,
Ahmedabad, Gujarat
17. Vincke P. (1992), “Multicriteria Decision-Aid”, John Wiley & Sons, Chichester,
ISBN: 978-0-4719-3184-3.
Websites Reports:
1. Farley T., Miller D., “Maintaining Rolling Mill Performance Part I, II, III”,
Innoval Technology Ltd., accessed via: http://www.innovaltec.com/aluminium-
rolling-models-blog/
2. “Indian Electrical & Electronics Manufacturers’ Association”, 68TH ANNUAL
REPORT 2014 – 2015 (September 2015), accessed via:
http://ieema.org/wpcontent/uploads/2015/09/IEEMA-Annual-Report_2014-
15.pdf
3. “Indian Electrical Equipment Industry Mission Plan 2012-2022”, accessed via:
http://www.cea.nic.in/reports/monthly/installedcapacity/2016/installed_capacity-
03.pdf.
4. Michael R. Lyu, Software Reliability Engineering – A Roadmap, accessed from:
http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.109.8051&rep=rep1&t
ype=pdf
5. “Review of Blueprint for Infrastructure in Gujarat (BIG 2020) – Final Report
Volume 1 – Summary and Vision” (August 2009), accessed via
http://www.gidb.org/Document/2014-12-31_112.pdf
6. Yoe (2002), “Trade-Off Analysis Planning and Procedures Guidebook”,
Prepared for Institute for Water Resources, U.S. Army Corps of Engineers,
accessed from: http://www.iwr.usace.army.mil/Portals/70/docs/iwrreports/02-R-
2.pdf.
112
List of Publications
National/International Journals:
1. Pancholi Nilesh, Bhatt M. G., (2016), “Multi criteria FMECA based decision-
making for aluminium wire process rolling mill through COPRAS-G”, Journal of
Quality and Reliability Engineering, Volume 2016, Article ID 8421916, 8 pages,
ISSN: 2314-8055, http://dx.doi.org/10.1155/2016/8421916. (Scopus Cite Score
2016:0.53, SCImago Rank: 0.22, H Index: 4)
2. Pancholi Nilesh, Bhatt M. G., (2016), “Performance reliability improvement by
optimizing maintenance practices through failure analysis in process industry – a
comprehensive literature review”, IOSR Journal of Mechanical and Civil
Engineering (IOSR-JMCE), vol. 13, Issue 6, pp. 66-73, e-ISSN: 2278-1684, p-
ISSN: 2320-334X.
3. Pancholi Nilesh, Bhatt M. G., (2016), “Traditional and multi-factor decision
making based FMECA through preference selection index method for continuous
process industry”, International Journal of Darshan Institute on Engineering
Research & Emerging Technologies (IJDI-ERET), vol. 5, No. 2, ISSN: (Print):
2320-7590.
4. Pancholi Nilesh, Bhatt M. G., (2017), “Identifying Critical Components of
Identified Process Industry through Shop-floor Failure Data”, International
Journal of Engineering Technology, Management and Applied Sciences, vol. 5,
Issue 2, ISSN: 2349-4476.
5. Pancholi Nilesh, Bhatt M. G., (2017), “TOPSIS and COPRAS-G based
maintenance optimization of aluminium wire rolling mill components”, Journal
of Basic and Applied Research International, International Knowledge Press, vol.
20, Issue 3, pp.189-201, ISSN: 2395-3438 (P), ISSN: 2395-3446 (O).
6. Pancholi Nilesh, Bhatt M. G., (2017), “Traditional and TOPSIS based failure
mode effect and criticality analysis for maintenance planning of aluminium wire
rolling mill components”, GIT – Journal of Engineering and Technology, vol. 10,
ISSN: 2249 – 6157.
7. Pancholi Nilesh, Bhatt M. G., (2017), “Quality enhancement in maintenance
planning through non-identical FMECA approaches”, International Journal for
113
Quality Research, vol. 11(3), pp. 603-626, ISSN: 1800-6450. (Scopus Cite
Score 2016:0.78, SCImago Rank: 0.234, H Index: 7)
8. Pancholi Nilesh, Bhatt M. G., (In print), “FMECA based maintenance planning
through COPRAS-G and PSI”, Journal of Quality in Maintenance Engineering,
vol. 24, Issue 2, pp. 224-243, Emerald, ISSN: 1355-2511. (Scopus Cite Score
2016:1.16, SCImago Rank: 0.340, H Index: 41)
National/International Conference:
1. Pancholi Nilesh, Bhatt M. G., (2015), “Comparative study of traditional failure
mode effect and criticality analysis (FMECA) and TOPSIS based FMECA for
bearings of aluminium rolling mill plant – a case study”, 2nd
National Conference
on Emerging trends in Engineering, Technology & Management (NCEETM), IU,
Ahmedabad, ISBN: 978-93-80867-75-5.
2. Pancholi Nilesh, Bhatt M. G., (2017), “Identifying critical components of
identified process industry through shop-floor failure data”, International
Conference on Latest Concepts in Science, Technology and Management
(ICLCSTM-2017) at National Institute of Technical Teachers Training &
Research (NITTTR), MHRD, Govt of India, Chandigarh, ISBN: 978-81-932712-
4-7.
3. Pancholi Nilesh, Bhatt M. G., (2017), “Maintenance planning through FMECA
based multi-criteria decision-making PSI approach for aluminium wire rolling
mill plant”, IEEE 2nd
International Conference for Convergence of Technologies
(I2CT), ISBN: 978-1-5090-4307-1/17.