  • Unrestricted / © Siemens 2019. All rights reserved

    Introduction to

    Control Engineering

    at Power Plants

    Lesson 3

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Determination of configuration

    Page 2

    • Components of the new DCS

    control system are determined

    to comply with customer

    technical requirements

    • General configuration overview

    is prepared

    • Detailed network connection

    plan is prepared

    • Order codes of the

    components are listed

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Configuration of 3rd party communication interface

    Page 3

    • Determination of the 3rd party

    communication protocol

    • Redundant or singular,

    controlling station (master,

    slave), network topology (point

    to point, multipoint)

    • Signal list of exchange signals

    with communication

    addresses, data volume

    • Data format

    • Physical layer of the

    communication (RS232,

    RS422, RS485, Ethernet, full

    of half duplex, data Rate,

    transmission distance)

    • Type and length of the

    communication cables

    • Type and quantity of

    converters, repeaters

    • Definition of battery limit

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Finalization of signal list

    Page 4

    1RB13P003 Hot reheat steam pressure FUM 230 AI 2 wire

    1RB21P003 XQ01 IP bypass LH outlet pressure FUM 230 AI 4 wire

    1RB21S003 IP bypass LH control valve FUM 280 AO CLC

    1RB21S003 XQ01 IP bypass LH control valve position FUM 230 AI 2 wire

    1RB21T003 XQ01 IP bypass LH outlet temperature FUM 230 AI 2 wire

    1RB22P003 XQ01 IP bypass RH outlet pressure FUM 230 AI 4 wire

    1RB22S003 IP bypass RH control valve FUM 280 AO CLC

    1RB22S003 XQ01 IP bypass RH control valve position FUM 230 AI 2 wire

    1RB22T003 XQ01 IP bypass RH outlet temperature FUM 230 AI 2 wire

    1RM21S002 IP bypass LH spray control valve FUM 280 AO CLC

    1RM22S002 IP bypass RH spray control valve FUM 280 AO CLC

    1SA11P002 XQ01 Curtis stage steam pressure FUM 230 AI 4 wire

    • The next step is the finalization

    of signal list

    • There are two approaches for

    finalization of the signal list:

    1) Process supplier prepares

    the signal list for new built plants

    2) DCS supplier prepares the

    signals list for control system

    refurbishment projects of existing

    plants.

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Assignment of signals to the modules

    Page 5

    • Assignment of signals to the

    input output modules

    • Process redundancy is taken

    into consideration while

    assignment

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Planing field connection and cabinet projects

    Page 6

    • Interconnection diagrams,

    cable lists, cable routes,

    connection typicals, terminal

    plans, cabinet arrangement

    drawings, circuit diagrams

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Drawing HMI screens

    Page 7

    • Drawing HMI screens based

    on P&I diagrams or draft

    displays

    • Linking dynamic elements with

    function blocks

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Forming function diagrams

    Page 8

    • These diagrams or, in

    other words, software

    program runs in the

    background when the

    plant is in operation.

    • The function blocks read the signals on the input

    cards, process and send them to the output cards,

    operator screens, alarm, report pages and archive.

    • Function diagrams are formed based on the task

    description documents.

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Procurement, manufacturing and factory tests

    Page 9

    • The components of the control system are

    procured. Cabinet components are installed in

    cabinets during manufacturing in workshop.

    • When the cabinet manufacturing is completed, it is

    checked whether the mechanical structure and

    electrical connections are completed according to

    the project and standards. Similar conformity

    checks are also made for equipment that are not

    mounted in the cabinet.

    • A factory test is performed with the optional

    participation of the customer. The integrity,

    suitability and functionality of the cabinets, external

    components and documentation are checked once

    again together with the customer.

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Dismantling and installation

    Page 10

    • When the control system components arrive at the

    power plant, installation works can start. Prior to

    that dismantling works are necessary for

    refurbishment projects.

    • Some of the tasks are:

    Dismantling and mounting of the cabinets, cable

    laying and termination, installation of field devices

    and boxes, etc.

  • Unrestricted / © Siemens 2019. All rights reserved

    9 – Engineering Steps Commissioning steps

    Page 11

    Commissioning of

    I&C configuration

    Receiving inspection

    and preparation of

    commissioning for DCS

    Switching on the DCS Commissioning of 3rd

    party interfaces Installation

    DCS

    Testing safety instrumented functions

    (authority, adviser, customer)

    Commissioning under operating conditions

    (higher-level open-loop and closed-loop controls)

    Process commissioning: Functions (individual/

    drive /sub-loop/sub-group control, drive switch over)

    Alarm optimization,

    load cability test

    Commissioning of process technology

    Conduct trial run Acceptance

    Cold function testing

    System commissioning

    Field signal and

    equipment

    testing

    Supply power for

    auxiliary and special

    cabinets (Field)

    - Continuously motor - Open loop and closed loop actuator, Solenoid valve control - Binary transducer - Analog measurement - Black Box

    Field commissioning

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool

    Page 12

    Loop Drawings Cabinet Arrangement Symbol Library Document Query

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Cabinet arrangement)

    Page 13

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Terminal table)

    Page 14

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Loop drawing)

    Page 15

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-table of contest)

    Page 16

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-bus overview)

    Page 17

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-power supply)

    Page 18

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-power supply)

    Page 19

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-cabinet arrangement)

    Page 20

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-terminal table)

    Page 21

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-part list)

    Page 22

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (Outputs-loop drawing)

    Page 23

    DCS cabinet MCC cabinet

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (SW-HW tools navigation)

    Page 24

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools HW engineering tool (SW-HW tools navigation)

    Page 25

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools SW engineering tool (Login)

    Page 26

  • Unrestricted / © Siemens 2019. All rights reserved

    10 - Engineering Tools SW engineering tool (Workbench)

    Page 27

  • Unrestricted / © Siemens 2019. All rights reserved