Top Banner
Introduction SAP Material Planning Dr. Djamal Ziani King Saud University
14

Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Dec 21, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Introduction SAP Material Planning

Dr. Djamal ZianiKing Saud University

Page 2: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Organizational Level in Material Planning

• Client• Company code• Plant• Storage location

Page 3: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Master Data Used

• Material Master• Bill Of Material (BOM)• Routings

Page 4: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Material Master

Page 5: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Material Type

• Raw materials• Operating supplies• Semi-finished products• Finished products

Page 6: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Bill of Material (BOM)

• The BOM contains the assemblies or components, to be included in the

production of a material.

• Used in MRP, production, procurement and for product costing

Page 7: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Bill of Material (BOM)

• The BOM are single level.

• The items of the BOM can themselves contain further BOM

Page 8: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Bill of Material (BOM)

• Plant: is the plant for which you wish to create or process the BOM. You can

assign more than one plant.

• Alternative BOM: For distinguish the different BOM for the same material

• BOM usage: Where you want to use the BOM (production, engineering,

costing…)

Page 9: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Routings

• Routings contain the steps that are necessary for production: – The corresponding operations– The sequence– Work center in which these operations are to be

executed– Time elements that are relevant for scheduling

the operations

Page 10: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

Routings

Page 11: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP: Material Requirement Planning• The system calculates the quantity required to continue the sales of the

final product without any delays, considering the following resources: – Stock on hand.– Receipts: purchase orders, production orders (for the parent item)

• The system then subtracts the following requirements:– Sales orders– Forecasts– Production orders (for the child items)– A/R reserve invoices

• The system uses the planning policy to make the production/purchase order recommendations. The planning policy is based on:

– Lead time, Minimum amount ,, Time intervals

• Complete production orders for the parent item, quantities of the child items that comprise the BOM are needed. The system calculates the quantity of the child items, taking the MRP-dependent requirements into account. The system then recommends purchase/ production orders for the child items required for producing the parent item.

Page 12: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP: Material Requirement Planning

Page 13: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP

Page 14: Introduction SAP Material Planning Dr. Djamal Ziani King Saud University.

MRP-Processing Key• NEUPL : Regenerative Planning. It will process ALL materials,

disregards the fact whether or not planning relevant changes were made to the material.

• For NETCH and NETPL: the system take into consideration only changes that are relevant for planning a material (like sales order entry, purchase order entry, stock release, etc.). – NETCH : Net Change Planning– NETPL : Net Change Planning within Planning Horizon. if a change

occurs outside the planning horizon (e.g. a sales order is entered 2 months away and your planning horizon is 6 weeks), then the material is not included in MRP even though there is a change.