Introduction of Liquid Organic Hydrogen Carrier and the Global Hydrogen Supply Chain Project Daisuke Kurosaki Chiyoda Corporation Advanced Hydrogen Energy Chain Association for Technology Development (AHEAD) 12 th September 2018 SPERA derives from the Latin word for “hope”. We at Chiyoda Corporation chose the name to represent our desire that hydrogen technology will give people around the world the hope they need to build a better future.
22
Embed
Introduction of Liquid Organic Hydrogen Carrier and the ... · Introduction of Liquid Organic Hydrogen Carrier and the Global Hydrogen Supply Chain Project Subject Presentation by
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Introduction of Liquid Organic Hydrogen Carrier
and the Global Hydrogen Supply Chain Project
Daisuke Kurosaki
Chiyoda Corporation
Advanced Hydrogen Energy Chain Association for Technology Development (AHEAD)
12th September 2018
SPERA derives from the Latin word for “hope”. We at Chiyoda Corporation chose the name to represent our desire that hydrogen technology will give people around the world the hope they need to build a better future.
1
INDEX
I. Chiyoda’s Hydrogen Technology & Projects
II. The Global H2 Supply Chain Project
I. Chiyoda’s Hydrogen Technology & Projects
Hydrogen Storage & Transportation Technology
• Chiyoda has established an efficient and large scale hydrogen storage and
• After lab tests, another 10,000hr of demo plant operation was successfully
completed.
• Expected performance was confirmed.
Hydrogen Demonstration Projects
7
8
Chiyoda and its partners established the Advanced Hydrogen Energy Chain Association for Technology Development (AHEAD), and started the world’s first global hydrogen supply chain demonstration project toward 2020.
Brunei
Darussalam
Kawasaki
City, Japan
1. Global Hydrogen Supply Chain Demonstration
2. Power to X Technology
Demonstration project to produce hydrogen by variable renewable energy, funded by the
New Energy and Industrial Technology Development Organization (NEDO)
9
TOL
MCH*HGN*
TOL
MCH De HGN**
Existing
demo plant
MCH***
TOL****
H2
electricity
Heat
Solid Oxide Fuel Cell
Heat Exchange
Purification
New
laboratory
test
New
demo
plant
Electro-lyser
Rectifier
Purifi-cation
Electricity
H2
Variable outputof wind power
(simulated)HGN* : hydrogenation
DeHGN**:Dehydrogenation,
MCH***: Methylcyclohexane
TOL****: Toluene
Location : Chiyoda Koyasu Office & Research Park (Yokohama - city)
3. Hydrogen Fueling Station Technology
Develop compact-type dehydrogenation facility (downsizing and automatic operation) in
order to fit for FCV fuel stations, funded by NEDO.
10Location : Chiyoda Koyasu Office and Research Park (Yokohama - city)
MCH Large
Storage
Tanks
Storage Tank
(underground)
Dehydrogenation
Reactor
Compressor
MCH
Tanker
lorry
Fuel
Dispenser
Pressure
Reservoir
Dehydrogenation facility downsized
Hydrogen
Purification
UnitFCV, FC
Fork LiftHydrogen Fueling Station
II. Global H2 Supply Chain Project
PROJECT OVERVIEW
LNG Plant(BLNG)
MCH
ProcessedGas Hydrogenation
Plant
TOL
ContainerYard
ContainerYard
Power Generation
(Kawasaki)
TOL
MCH
TOL
MCH
ContainerVessel
Brunei
Japan
ISO ContainerLand Transport
MCH : Methyl cyclohexane, TOL : Toluene
De-Hydrogenation
Plant
ISO Container Land Transport
SPARKIndustrial Park
LUMUT
KAWASAKI
[Plant Scale] 300 Nm3/h – H2 (Plant Capacity)
[Transport] ISO Tank Container (5 Containers / week)
HydrogenGas
MUARA
KAWASAKI
Gas Liquid
12
1. Brunei
1) GEOGRAPHICAL LOCATION
• Hydrogen production / hydrogenation plant will be located at SPARK, and hydrogen will be transported on land using ISO tank containers (in form of MCH) to Muara Port for shipping.
SPARK
Muara Port
ISO lorry
Hydrogenation Storage & Shipping
To Japan
13
1. Brunei
2) HYDROGENATION PLANT (IMAGE)
Hydrogenation plant will consist of Hydrogenation unit, H2 production unit, utility & offsite facilities, administration/control building and ISO tanks area.
14
1. Brunei
3) GROUND BREAKING CEREMONY
15
• Ground breaking ceremony was hold on April 21, 2018, and the guest of honor was Deputy Minister of Ministry of Energy and Industry, together with 150 other guests.
1. Brunei
4) CONSTRUCTION WORK (as of July 2018)
16
• Construction started in April 2018, and foundation/building work is ongoing.
2. Kawasaki
1) GEOGRAPHYICAL LOCATIONThe site of dehydrogenation will be located at Keihin Industrial Zone in Kawasaki, and ISO tank containers from Brunei Darussalam will arrive at Kawasaki Port.
17
Tokyo International Airport(Haneda)
Tokyo
Kawasaki
Yokohama
Kawasaki PortContainer Terminal
Keihin Industrial Zone
2. Kawasaki
2) H2 SUPPLY INFRASTRUCTURE
Dehydrogenation Plant will be located inside TOA OIL's Keihin Refinery, and extracted hydrogen gas will be transported to existing power generation by pipeline.