Introduction about Uncertainties Power System Planning in Presence of Uncertainties Content :
Aug 17, 2015
Introduction about Uncertainties
Power System Planning in Presence of
Uncertainties
Content :
is a term used in subtly different ways in a number of
fields, including physics statistics economics engineering
and information science. It applies to predictions of future
events, to physical measurements that are already made, or
to the unknown. Uncertainty arises in partially observable
on different environments,
Introduction Uncertainty
1.Measurement of Uncertainty: A set of possible states or outcomes where
probabilities are assigned to each possible state or outcome – this also
includes the application of a probability density function to continuous
variable
2.Measurement of Risk: A set of measured uncertainties where some
possible outcomes are losses, and the magnitudes of those losses – this also
includes loss functions over continuous variables
Uncertainty in Calculations
to determine the uncertainty for a quantity that was calculated from
one or more measurements ,There are complicated and less
complicated methods of doing this.
The simple one The Upper-Lower Bounds method of uncertainty in
calculations is not as formally correct, but will do. The basic idea of this
method is to use the uncertainty ranges of each variable to calculate
the maximum and minimum values of the function.
measurement = best estimate ±
uncertainty
the area would be:
A = l * w = 1.2 * 1.3 = 1.56 m^2
Area Presence of Uncertainties
The minimum area would be using the "minimum" measurements so
l = 1.2 - 0.2 = 1.0
w = 1.3 - 0.3 = 1.0
So the "minimum' area is A-min = 1.0 * 1.0 = 1.0 m^2
Likewise for the maximum area, l = 1.2 + 0.2 = 1.4 and
w = 1.3 + 0.3 = 1.6
So the Maximum area is A-max = 1.4 * 1.6 = 2.24 m^2
We can say ¥ = ±(0.2)(0.3) = 0.6 the area is A = 1.5 +/- 0.6 m^2
For example you want to find the area of a square and measure one side as a length of 1.2 +/-
0.2 m and the other length as 1.3 +/- 0.3 meters,
power system planning namely,
• Base on Load forecasting (LF)
• Generations expansions planning (GEP)
• Substations expansion planning( SEP,)
• Network expansion planning (NEP)
• Reactive power planning (RPP)
We assumed, implicitly, that all decisions are made by a single entity
and the information used lacks any uncertainty. None of the above is
strictly true.
If Generations expansions planning is decided by some entities
based on the other entities cannot proceed towards the other
steps (SEP, NEP and RPP) if they cannot make sure what the GEP
players do in actual life. Still, there are more uncertainties
involved for their various decision makings .
The uncertainties play major roles in power system planning
issues of the new environment.
Power System regulating industry
In the regulated industry, power system structure consists of
generation, trans mission and distribution owned by a single entity;or owned by
different owners, controlled or regulated by a single entity.
the single entity decides on where and how to allocate generation and/or
transmission facilities. The investment and the operational costs as well as an
appropriate level of profit for the owners are compensated by regulated tariffs
imposed on the customers.
Power system in de-regulated In de-regulated environment,
The electricity is provided by some suppliers known as generation companies (
Gen.Co)$
The customers may wish to buy this commodity either from the high voltage or
low voltage (through distribution companies also called (Dis.Cos),may be
Owned by transmission company
electricity should be transferred from the suppliers to the customers through
the available transmission facilities (transmission lines and/or cables, ) That
owned by the transmission company and also called (TransCo)
The other facilities have to be owned investments or (owned
by the transmutation companies (TransCo ) is still fully or
partially
The electricity price is determined based on by suppliers from
one side and customer from other
de-regulated environment,
Generation company
Transmission line company
Distribution company
customers
Reactive power
Two terms of uncertainty and risk are widely used in power system planning
. There are no fixed definitions for these terms. Some believe that they are
the same, while some believe one is the result of another. Still, some think
of these to be quite independent..
we assume that the uncertainties involved may result in risk. For instance,
as GEP, SEP and NEP are based on the forecasted load,
any uncertainty in the forecasted load may result in risk so that the
network planned may be unable to fulfill its functions properly to supply all
loads
On the other hand, the uncertainties affect all short- power system
planning and long- power system planning deci sions.
Power System Uncertainties
1 Uncertainties module in a Regulated Environment power system planning is depend on load fore casting (LF)
and consists of GEP, SEP, NEP and RPP, input parameters.
The studies are to be carried out for some years in the
future depended on historical information so the input
parameters should be, accordingly, predicted
these parameters are in turn, dependent upon some other
parameters. As a result,
the input parameters to power system planning modules
may face uncertainties which obviously affect our decisions
Power planning modules input parameters are
Economic growth load forecasting (LF)
Economic parameters, such as inflation, depreciation and interest rates of
• Load forecasting (LF)
• Generations expansions planning (GEP)
• Substations expansion planning( SEP,)
• Network expansion planning (NEP)
• Reactive power planning (RPP)
• The Fuel cost (directly on GEP and indirectly on SEP, NEP and RPP
Technological developments (LF, GEP, SEP, NEP and RPP)
Environmental limitations (directly or indirectly)
Investment costs (GEP, SEP, NEP and RPP)
Demand side management programs (LF)
Operation and maintenance costs (GEP, SEP, NEP and RPP)
Resource (such as fuel and water,) availability (GEP)
Mane company or entity
trans mission line
Generations Distribution
regulated environment
2-Uncertainties module in De-regulated Environment
The power system de-regulating has resulted in appearing new independent
entities such as (GenCos, TmnsCos, DisCos,.)
The single-player environment has replaced by a multi-player, with its
risks and uncertainties involved.
each aiming at making, the maximum profit (revenues minus costs) from
its properties.
The de-regulation of the power industry leads to separation of the
transmission planning from the generation expansions. This will increase
the uncertainties and challenges
Each entity now should make its own decisions. And how to behaviors
with the other players into consideration in this new situation,
The electricity price is determined based on the supply-demand rule.
We discuss differentiate between the uncertainties involved in GEP
from one side and, TEP) from the other side.
Uncertainties in Generations expansions planning GEP This uncertainty introduced for the regulated environment, as
an owner should now make its own decision in investing on a
power plant, it new uncertainties.
The electricity price is the most important If investor may
invest in a location with an anticipated high electric price.
However, the behaviors of the other players should also be
predicted and taken into account. This prediction is not an easy task
at all
uncertainties more effects in the de-regulated environment For example ,
the costs of primary resources (such as gas, oil, etc.) may make an owner
to defer its investment in a place or changes its decision and invests in
another place.
In a regulated environment, although these costs are still effective, the
investor may still invest at the same place and time; as the money is
guaranteed to be back by some appropriate tariffs.
Uncertainties in transmission line expansion
planning TEP• This uncertainties in a regulated environment,
• Deal with how transmission line expansion planning may be properly
performed
• the most important uncertain factor which influences TEP ,the
uncertain GEP output.
• If GEP is decided upon by the other market players As the costs of
TEP should be recovered from the market par ticipants (both the
suppliers and the customers)
• an over design may result in players dissatisfactions or uneconomic decision .
• Under design can result in similar effects as the suppliers may be unable to sell
or cover the loads of the customers
Advanced of calculate Uncertainties in power planning
Reduced the risk and error
more accuracy Measurements for planning
Give robust power planning
Give more reliably for power system for short and long planning
Thank for listing
Reference1- Hossein Seifi • Mohammad Sadegh Sepasian electric power planning Issues, Algorithms
and solution chapter 11 section 11:1 -11:4
2- http://www.ivsl.org/?language=en