Top Banner
0 Memo No (972) Introducing Microsoft Project 2007 by Dr. Abdalla ElDaoushy Feb, 2009 Dec, 2009
205

Introducing Microsoft Project 2007

Nov 18, 2014

Download

Documents

This is a very simple Training Material on using MS Project 2007
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Introducing Microsoft Project 2007

0

Memo No (972)

Introducing Microsoft Project 2007

by

Dr. Abdalla ElDaoushy

Feb, 2009 Dec, 2009

Page 2: Introducing Microsoft Project 2007

1

1

Contents Page Exploring Microsoft Project Environment . . . 4 MS Project 2007 Screen . . . . . . 4 Standard Toolbar . . . . . . . 4 Formatting Toolbar . . . . . . . 6 View Bar . . . . . . . . 7

Creating a New Project . . . . . . 7 Create New Blank Project . . . . . . 7 Create a New Project based on a Template . . . . 7 Setting Up a Project Calendar . . . . . . 11

o Create a New Calendar . . . . . 12 o Set Up a Working Time Exception . . . . 14 o Global Calendar . . . . . . 17

Create MileStone Tasks . . . . . . 20 Change the Date Format . . . . . . 20 Setting Schedule Options . . . . . . 20 Saving Project Files . . . . . . . 21 Saving Files as Templates . . . . . . 21 Protecting Files . . . . . . . 22 Entering Tasks . . . . . . . 23 Creating Summary Tasks . . . . . . 25 Displaying and Hiding Tasks . . . . . . 26 Project Summary Task . . . . . . 26 Using Recurring Tasks . . . . . . 27 Recurring Tasks: Application . . . . . . 36 Task Notes . . . . . . . . 41

Manipulating Tasks & Constraints . . . . 42 Using Deadline Dates . . . . . . . 43 Adding Constraints . . . . . . . 45 Editing Tasks . . . . . . . . 47 Deleting Tasks . . . . . . . 47 Moving Tasks . . . . . . . . 47

Tasks Relationships (Dependences) . . . . 49

Page 3: Introducing Microsoft Project 2007

2

2

Page Resources . . . . . . . . . 52 What are Resources . . . . . . . 52 Creating Resource List (Example) . . . . . 52 Working Time for Resources . . . . . . 53 Rates for Resources . . . . . . . 55 Resource Notes . . . . . . . 56 Assigning Resources (Example) . . . . . 57

View Information . . . . . . . 61 Gantt Chart View . . . . . . . 62 Calendar View . . . . . . . 64 Task Usage View . . . . . . . 65 Resource Graph View . . . . . . . 68 Resource Sheet View . . . . . . . 69 Resource Usage View . . . . . . . 70

Quick Viewing & Printing Reports . . . . 71 Using “Print Preview”. . . . . . . 71

Reports . . . . . . . . . 72 Overview Reports . . . . . . . 73 Current Activity Reports . . . . . . 74 Costs Reports . . . . . . . . 75 Workload Reports . . . . . . . 76 Assignment Reports . . . . . . . 76 Visual Reports . . . . . . . . 77

Case Studies . . . . . . . . 79 Case Study No 1 . . . . . . . 80

o Basic Data . . . . . . . 80 o Resources: Standard Rate & Overtime Rate . . . 81 o Working Steps . . . . . . . 82

Page 4: Introducing Microsoft Project 2007

3

3

Page

Case Study No 2 (Arabic) . . . . . 97 o Background . . . . . . . 97 o Working Steps . . . . . . . 99

1. Create New Project . . . . . 99 2. Change the Start Date & Current Date of the Project . 99 3. Create a New Calendar . . . . . 100 4. Assign the New Calendar to the Project . . . 101 5. Make New Calendar as a “Global Calendar” . . 101 6. Enter Tasks, Durations & Relationships . . . 101 7. Coding & Organization . . . . . 106 8. Record the Resources in the “Resource Sheet” . . 113 9. Assign different Resources to different Tasks . . 116 10. Project’s Resources . . . . . 120 11. Design and Display the different Reports . . . 127

Case Study No 2 (English) . . . . . 128

Tracking (Follow Up) . . . . . . 175

Understanding Tracking . . . . . . 175 Updating Form . . . . . . . 175 Tracking Process . . . . . . . 179

1. Setting BaseLine . . . . . . 180 2. Tracking Progress . . . . . . 183 3. Status Date . . . . . . . 187 4. Reviewing Progress & Progress Line . . . . 188 5. Reschedule Uncompleted Work (F9 in P3e) . . . 190 6. Reviewing Progress . . . . . . 191 7. Group . . . . . . . . 191 8. Filter . . . . . . . . 193 9. View . . . . . . . . 196 10. Reporting on Project’s Progress . . . . 197

Coordinating Multiple Projects & Sharing Resources Among Projects . . . . . . . . . 198 References . . . . . . . . 203

Page 5: Introducing Microsoft Project 2007

4

4

Exploring Microsoft Project Environment MS Project 2007 Screen:

Standard Toolbar: New Open Save Print Search Print Preview Spelling Cut Copy Paste Format Painter Undo & Redo Hyperlink

Page 6: Introducing Microsoft Project 2007

5

5

Link Tasks Unlink Tasks Split Task Task Information Task Notes Task Drivers Assign Resources Publish All Information Group by Zoom IN Zoom Out Go to Selected Task Copy Picture Microsoft Project Help

Page 7: Introducing Microsoft Project 2007

6

6

Formatting Toolbar: (View/Toolbars…/Formatting) Outdent Indent Show Subtasks Hide Subtasks Hide Assignments Show

o Font o Bold o Italic o Underline o Align Left o Center o Align Right o Filter o Gantt Chart Wizard

Page 8: Introducing Microsoft Project 2007

7

7

View Bar: (View/View Bar)

Creating a New Project: Create New Blank Project:

o Click on the “New” icon.

Create a New Project based on a Template: o Click “File/New”, the New Project Task Pane displays

towards the left edge of the window:

Page 9: Introducing Microsoft Project 2007

8

8

o To use a Template that is already installed on the computer’s hard disk, click on the “On Computer…” link, the “Templates” window appears:

Page 10: Introducing Microsoft Project 2007

9

9

o Click on the “Project Templates” tab, a range of templates appears:

o Select and double-click the desired Template and continue modifying and adding activities as we will explain later on.

Inputting Start & Finish Dates:

o Click “Project/Project Information…”, the “Project Information” window appears:

Page 11: Introducing Microsoft Project 2007

10

10

o Use the drop-down calendar in the “Start date:” to select the Start date of the Project (for example 1/1/2010).

o Use the drop-down calendar in the “Current date:” to change

the date to for example 1/1/2010.

Page 12: Introducing Microsoft Project 2007

11

11

Setting Up a Project Calendar:

o Click “Project/Project Information…” o Confirm that “Standard” is selected from the Calendar drop-

down menu in the “Project Information” dialog box:

Hint:

Be sure that “Project Start Date” is selected from the “Schedule from:” drop-down menu (“Project Start Date” is the default).

Page 13: Introducing Microsoft Project 2007

12

12

To Create a New Calendar:

o Click “Tools/Change Working Time” o Click on the “Create New Calendar…” button, the “Create

New Base Calendar” dialog box appears:

Page 14: Introducing Microsoft Project 2007

13

13

o Enter a name (for example My Calendar) for the new calendar in the “Name” field.

o Press OK.

Page 15: Introducing Microsoft Project 2007

14

14

To Set Up a Working Time Exception:

1. Use “Exception” & “Work Weeks” tabs to determine the holidays (from “Exception” tab) & exceptions for default holidays to become working days (from “Work Weeks” tab).

2. In the “Name” column on the “Exception” tab, type a name that helps you remembers the purpose of the exception (holidays/non-default workdays).

3. In the “Start” column, select the date on which the

exception starts. 4. In the “Finish” column, select the date on which the

exception ends. Project sets every day between the starting and ending dates as an exception on the calendar, and the “Details” button and the “Delete” button become available.

5. Click the “Details” button. Project displays the details

dialog box. Use this dialog box to define the working time exception.

6. In the top section of the dialog box, click the “Working

Times” option button and then set the working times. 7. To repeat this working time pattern every Wednesday for

example, click “Weekly” in the “Recurrence pattern” section and check the “Wednesday check box.

8. In the “Range of recurrence” section, Project set the

starting and ending dates for the working time exception using the dates you supplied in steps 2 and 3. You can change these dates if you want.

9. Click OK. When Project redisplays the “Change

Working Time” dialog box, every “Wednesday” between the beginning and ending dates you specified appears as an exception on the calendar.

Page 16: Introducing Microsoft Project 2007

15

15

To Create a New Calendar Example: Create a new calendar called “Egypt Calendar” with the

following specification:

o It will be a Global Calendar. o Weekly working days will be from SUN to THU. o It has the following Holidays:

7 January --- (repeated) 1 May --- (repeated) 23 July --- (repeated) 6 October --- (repeated)

(Use “Details” tab after assigning in the “Exceptions”)

Now, 1. Create a new Project. 2. Click “Tools/ Change Working Time…/Create New Calendar…”,

the “Create New Base Calendar” window appears. 3. Enter the Calendar Name: Egypt Calendar 4. Choose the option: Create New Base Calendar. 5. Press OK, the “Change Working Time” window appears. 6. Click “Options…” tab. 7. Choose “Week starts on: Sunday & Press OK 8. Choose “Work Weeks” tab & Press “Details…” button, the “Details

for [Default]” window appears.

a. Adjust the working & nonworking days in this window.

Page 17: Introducing Microsoft Project 2007

16

16

9. Choose “Exceptions” tab. a. Highlight 7 of January b. Write in the Exception Name: “7 January” and click in the

“Start” column, the highlighted day becomes a nonworking-day with nonworking-color.

c. Press “Details…” button, the [Details for “7 January”]

window appears. d. To make this day repeated holiday for 10 years as an example;

in the “Recurrence pattern” section, choose “Yearly”. e. Choose “End after” radio-button and write 10 occurrences.

10. Repeat for “1 May”, “23 July”, & “6 October”. 11. The “Egypt Calendar” looks like this:

Page 18: Introducing Microsoft Project 2007

17

17

12. To make this Calendar a “Global” Calendar:

a. Choose “Tools/ Organizer…”, the “Organizer” window appears.

b. Click the “Calendar” tab, the window will looks like this:

Page 19: Introducing Microsoft Project 2007

18

18

c. Highlight “Egypt Calendar” and press “<<Copy”, the window will looks like the following window which means that the “Egypt Calendar” become Global and will be available for any project the same way as the “Standard Calendar”.

Hint: This is the place where you can delete any Calendar except the “Standard” one . . .

Page 20: Introducing Microsoft Project 2007

19

19

Applying (Assigning) the new calendar called “Egypt Calendar” to the Project:

o Click “Project/Project Information…” o Click on the “Calendar” down arrow. o Click on “Egypt Calendar” to select it. o Click OK.

Dates Format: Date format comes from Windows Setting as follows: Start / Setting / Control Panel

o “Regional Option” tab / Customize “Date” tab

• Short date format: dd-Mon-yy for example… • OK • Apply • OK

Page 21: Introducing Microsoft Project 2007

20

20

To Create Milestones Tasks:

o Milestones Tasks are tasks that usually have zero duration. o The symbol for a milestone on the “Gantt Chart” view is a

diamond shape.

o A Task does not have to have zero duration to be a milestone; you can mark any task as a milestone. On the “Advanced” tab of the “Task Information” dialog box, place a check mark in the “Mark Task As Milestone” check box. In this case, the task duration does not change to zero. However, the element that represents the task in the “Gantt Chart” changes from a bar, reflecting the task’s duration, to a milestone diamond symbol, representing the task as a moment in time. Hint: Check with 3 Sequential Activities: A (10 days & milestone), B (8 days), and C (2days) and see the result….

To Change the Date Format:

o Click “Tools/Options/View/Date Format”

Setting Schedule Options:

o “Tools/Options/Schedule” Show assignment units as a : Decimal (for example), Duration is entered in: days (for example), Work is entered in: days (for example), Default Task Type: Fixed Duration.

Page 22: Introducing Microsoft Project 2007

21

21

Saving Project Files:

o “File/Save” o Note:

By default, Project saves files in Project 2007 format with the extension .mpp. To save a file in a different format, such as a Microsoft Access database (.mdb) or a Project 2000 - 2003 file (also .mpp), you can select that format in the “Save As” type drop-down list. After you enter a name for your file and designate its location and type, click Save to save the file.

Saving Files as Templates:

o One format in the “Save As type” drop-down list is Template

as shown:

Page 23: Introducing Microsoft Project 2007

22

22

Protecting Files:

o “File/Save As” & “Tools” button as shown:

Page 24: Introducing Microsoft Project 2007

23

Entering Tasks:

o Create a new Project called “New Product Brochure_1” o Enter Tasks as shown:

Page 25: Introducing Microsoft Project 2007

24

Page 26: Introducing Microsoft Project 2007

25

Creating Summary Tasks: o Highlight row 1 and press “Ins” on the Keyboard; then type

“Write Brochure”. o Highlight rows 2, 3, 4, and 5 and press “Indent” button as

shown on the next page. o Repeat for the rest of activities as shown:

Page 27: Introducing Microsoft Project 2007

26

Page 28: Introducing Microsoft Project 2007

26

Displaying and Hiding Tasks (expanding or collapsing the Summary Tasks):

o The outline structure enables you to view your project at

different levels of detail by expanding or collapsing the summary tasks.

Project Summary Task:

o “Tools/Options/View tab” o Check “Show Project Summary Task”

Page 29: Introducing Microsoft Project 2007

27

27

Using Recurring Tasks:

Projects often have tasks that occur on a regular basis. For example, the following tasks:

o Weekly Staff Meetings. o Quarterly Reports, o Monthly Budget Reviews

may occur 20 or so weekly over the life of a 5-month project. Use the Project’s Feature that enables you to create the meeting

task, for example. Just once and assign a frequency and timing to it

Follow these steps to Create a Recurring Task:

1. Because Project inserts tasks above the selected task, select the

task that you want to appear below the recurring task and choose “Insert/Recurring Task” to open the “Recurring Task Information” dialog box, as shown:

4.8

Page 30: Introducing Microsoft Project 2007

28

28

2. Type the recurring task name in the “Task Name” field. 3. Set the task duration in the “Duration” field. For example, does

the meeting run for two hours, or does a report take a day to write? 4. Set the occurrence of the task by selecting one of the “Recurrence

Pattern” option buttons:

Daily, Weekly, Monthly, or Yearly.

5. Select the appropriate settings for the recurrence frequency. For a Weekly setting, place a check mark next to the day(s)

of the week on which you want the task to occur. For example, the task may occur every Tuesday.

For the Monthly or Yearly setting, select the day of the

month on which you want the task to occur. For example, the task occurs on Day 12 of every month.

For a daily task, you have only one choice: whether you

want it to occur every day or only on scheduled workdays. For example, to schedule a computer backup for every day of the week—regardless of whether anyone is at work—you can have the task occur every day. (Ask your IT department how to automate the process so that it occurs even when nobody is at work.)

6. Set the “Range of recurrence”, the period during which the task

should recur by entering “Start” and “End after” or “End by” dates. If you need to repeat a test weekly for only one month of your ten-month project, you can set “Start” and “End after” or “End by” dates that designate a month of time.

If you set the “End after” number of “occurrences”, Project calculates the date range that is required to complete that many occurrences of the recurring task and automatically displays the ending date in the “End by” box. This method can be useful if one of these events falls on a holiday:

Page 31: Introducing Microsoft Project 2007

29

29

If one of the occurrences falls on a holiday, Project displays a box that allows you to skip the occurrence or to schedule it on the next working day.

For a weekly staff meeting, you can skip that meeting or

schedule it on a different day.

On the other hand, if you must repeat a test 16 times during the project cycle, you can schedule the test to occur on the next working day to compensate for the holiday.

Therefore, set the number of occurrences rather than the

time range.

7. Click OK to create the task. Project creates the appropriate number of tasks and displays them as subtasks under a summary task with the name that you supplied in Step 2. FIGURE 4.10 Task bars appear for each occurrence of the recurring task in the “Gantt Chart”.

Returning back to our example called “New Product Brochure_1”:

Page 32: Introducing Microsoft Project 2007

30

Page 33: Introducing Microsoft Project 2007

31

Select row 10 and click “Insert/Recurring Task”, the “Recurring

Task Information” dialog box appears:

Enter “Team Meeting” in the “Task Name” box. Enter 1h in the “Duration” box. Select the “Daily” button in the “Recurrence pattern” area. Select the “Workdays” button.

Page 34: Introducing Microsoft Project 2007

32

32

In the “Range of recurrence” section, select the “End after” button

and write 3.

Click OK button to return back to the “Gantt Chart” view. Your

screen will now look like this:

Page 35: Introducing Microsoft Project 2007

33

Page 36: Introducing Microsoft Project 2007

34

Click on the “Outdent” button on the “Formatting” toolbar.

Page 37: Introducing Microsoft Project 2007

35

Expand the “Team Meeting” task by clicking on the “+” symbol.

Page 38: Introducing Microsoft Project 2007

36

Recurring Tasks: Application….. Suppose we would like to construct a Training Programs Plan for

the Year 2010. We have limited Training Classes & many Training Programs. We used to use a Class for two courses. Each course used to be held

for 3 days a week. For example, a class can be used for Windows Training Program to be held on SUN, TUE, and THU for two weeks & Word Training Program will be held at the same Class for SAT, MON, and WED for two weeks also.

After finishing of any of these Training Programs, another Training

Programs like Excel & Access will be held. In summary:

Class 1:

Course Title

Days

Working Days

1 Windows 6 SUN TUE THU . . . . . . 2 Word 6 SAT MON WED . . . . . . 3 Excel 9 SUN TUE THU After

Windows. 4 Access 12 SAT MON WED After Word

Page 39: Introducing Microsoft Project 2007

37

37

We have to do the following:

Create a new Calendar “Training Programs Calendar”: 6 Days/Week & Week Start on: SAT

Project Name: Class 1 Schedule Assign Calendar to Project Create the following Recurrence Tasks according to the above

information:

1. “Windows Program” Task 2. “Word Program” Task 3. "Excel Program” Task (Starts after “Windows Program”) 4. “Access Program” Task (Starts after “Word Program”)

Page 40: Introducing Microsoft Project 2007

38

38

Hint: Instead of writing the start date above, you can set the “Predecessor| for the “Excel Program 1” task (which is the “Windows Program 6”

task. Repeat for the rest of Tasks… Anyhow, this is not practical procedure….

Page 41: Introducing Microsoft Project 2007

39

39

Hint: Instead of writing the start date above, you can set the “Predecessor| for the “Access Program 1” task (which is the “Windows Program

6” task. Repeat for the rest of Tasks… Anyhow, this is not practical procedure….

Page 42: Introducing Microsoft Project 2007

40

40

Page 43: Introducing Microsoft Project 2007

41

Task Notes: Notes can be attached to a Task to quickly display information relating to that Task. Double-click on the “Print Brochure” Task; the “Task

Information” window appears. Select the “Notes” tab.

Type “Remember to ask Kate for recommended Printers”

Click OK.

Notice the symbol in the “Indicator” column.

Page 44: Introducing Microsoft Project 2007

42

42

Manipulating Tasks & Constraints: A Constraint is a restriction placed upon a task which limits the

Start or Finish Dates of that task. By default, the “As Soon as Possible” constraint is applied to every

task. The following represents a list of all of the Constraint Types:

o “As Soon As Possible”: Schedules the task to start as soon as

the beginning of the Project. o “As Late As Possible”: Schedules the task to end no later than

the end of the Project.

o “Finish No Earlier Than” or “Finish No Later Than”: Schedules the task to end no later or sooner than a specific date.

o “Must Finish On” or “Must Start On”: Schedules the task to

finish on or start on a specific date. o “Start No Earlier Than” or “Start No Later Than”:

Schedules the task to start no earlier than or later than a specific date.

Hint: Constraints come from “Task Information/Advanced tab”

Page 45: Introducing Microsoft Project 2007

43

43

Using Deadline Dates:

o You also can establish a deadline date for a task. The deadline date differs from a constraint in that Project doesn’t use the deadline date when calculating a project’s schedule. Instead, the deadline date behaves as a visual cue (sign) to notify you with a deadline dates. If you place your mouse over the deadline indicator, Project displays the deadline information. If the task finishes after the deadline date, you also see a symbol in the Indicators column. Be aware that you won’t see an indicator if you complete the task prior to the deadline date.

Deadline Field:

Description: The Deadline field shows the date you enter as a deadline for the task. A deadline is a target date indicating when you want a task to be completed. If the deadline date passes and the task is not completed, Microsoft Office Project displays an indicator. A deadline is also shown as an arrow in the “Gantt Chart” view.

Best Uses: Apply a deadline to a task when you want to track a deadline for a specific task but don't want to lock your schedule by setting an inflexible constraint such as Must Finish On or Finish No Later Than. Such constraints affect scheduling while the Deadline field simply causes an indicator to show if a task has not been completed by its deadline. Add the Deadline field to a task sheet when you want to enter, view, or change the deadlines of tasks in your project. You can also use the Deadline field for sorting, filtering, and grouping by deadline date.

Hint: A Deadline Date comes from “Task Information/Advanced tab”

Page 46: Introducing Microsoft Project 2007

44

44

Example:

Certain tasks in your project should finish by specific target dates. However, you don't want these dates to actually affect how Project schedules the tasks; you just want to be alerted if the tasks are not completed by these dates. Add the Deadline field to the Entry Table of the “Gantt Chart” view, and set the deadline dates for these tasks.

Remarks:

You can also enter a task deadline in the “Task Information” dialog box. Click “Task Information” and then click the “Advanced” tab. Click the date in the “Deadline” box.

If you do want Project to schedule tasks according to a specific finish date, apply either a Finish No Later Than, Finish No Earlier Than, or Must Finish On constraint. You can set task constraints on the “Advanced” tab of the “Task Information” dialog box.

Page 47: Introducing Microsoft Project 2007

45

45

Adding Constraints: Double-click the “Print Brochure” Task; the “Task Information”

dialog box appears. Click “Advanced” tab. Select “Start No Earlier Than” from the “Constraint type” drop-

down menu. Type 7/1/2004 in the “Constraint date” field Click OK. Notice how the “Print Brochure” tasks have been moved

in the “Gantt Chart” view.

Page 48: Introducing Microsoft Project 2007

46

Page 49: Introducing Microsoft Project 2007

47

Editing Tasks:

Tasks can be edited through their “Task Information” dialog box Double-click the “Teem Meeting 1” task to open its “Task

Information” dialog box. Change the “Duration” to 2h. Click OK.

Deleting Tasks:

Highlight the Task(s) in the “Gantt Chart” view and Press the “Del” key.

Undo the deletion by clicking on the “Undo” button in the “Toolbar”.

Moving Tasks:

Move the mouse-pointer over the “ID” number of the Task until the mouse-pointer changes to the shape of a “Move Cursor”.

Click and hold the mouse button. Drag the mouse-pointer until the “horizontal grey stripe” is above the row where the moved Task will be.

Page 50: Introducing Microsoft Project 2007

48

Page 51: Introducing Microsoft Project 2007

49

Tasks Relationships (Dependences):

There are two types of Tasks in a Relationship.

o A Predecessor Task must occur before another Task. o A Successor Task must occur after another Task.

Finish-to-Start (FS) Relationships:

It is the most common type of relationship. The start of one Task

begins as soon as its Predecessor Task finishes. The Successor Task can not start until the Predecessor Task finishes.

Start-to-Start (SS) Relationships: In the SS relationship, the Successor Task can not start until the

Predecessor Task starts. The Tasks can happen simultaneously, but the Predecessor Task needs to have started in order for the Successor Task to start.

Start-to-Finish (SF) Relationships: In a SF relationship, the Successor Task is completed after its

Predecessor Task starts. In other words, the Successor Task can not finish until the Predecessor Task starts. The SF relationship is rarely used.

Finish-to-Finish (FF) Relationships: In the FF relationship, the Successor Task can not finish until the

Predecessor Task finishes. For example; you finish installing computers at the same time that you finish moving employees into the building so that the employees can begin using the computers right away.

Page 52: Introducing Microsoft Project 2007

50

50

Hint: You can create Tasks Relationships from:

o “Task Information/Predecessor tab”, o “Window/Split”, or o Adding Predecessor/Successor column in the “Gant Chart”

Now, it is the time to create the Tasks Relationship in our example “New Product Brochure” using the following information:

Task

Predecessor

Type

Research New Product --- Create an Outline Research New Product Write a Rough Draft Create an Outline Edit Rough Draft Write a Rough Draft Prepare through Desktop Edit Rough Draft Get Quotes from Printer Prepare through Desktop Get Printed Get Quotes from Printer Create Mailing List Get Printed SS Do Mass Mail Out Create Mailing List

Page 53: Introducing Microsoft Project 2007

51

51

Page 54: Introducing Microsoft Project 2007

52

52

Resources

What are Resources:

Resources are People, Equipments, and Materials (Supplies) used to accomplish tasks and goals of the project.

Creating Resource List (Example):

Click “View/Resource Sheet”.

Click in the 1st row of the “Resource Name” column. Type “Jane Doe” and press “Return”.

Repeat for “Katie Aiko” & “Postage”.

For the resource “Postage”, select “Material” from the drop-down-list in the “Type” column.

Enter “Stamps” as a “unit of measurement” in the “Material Label” column.

Click “Save” in the “Toolbar” to save your work.

Page 55: Introducing Microsoft Project 2007

53

53

Working Time for Resources:

The “Base Calendar” which you choose for a resource determines its availability.

You can customize a resource’s calendar if necessary (i.e., blocking off vacation time for specific resource).

Double-click on “Jane Doe” in the “Resource Name” column. This will open the “Resource Information” dialog box. If necessary, click on the “General” tab.

Click on the “Change Working Time…” button, the “Change Working Time” window appears:

Page 56: Introducing Microsoft Project 2007

54

54

In the above screen, you can change the “Base calendar” and you can customize the Calendar from the “Exception” & Work Weeks” tabs.

Page 57: Introducing Microsoft Project 2007

55

55

Rates for Resources:

It is important to enter rates for a resource, as this allows MS-Project to calculate the overall cost of a project.

The resource’s cost may increase or decrease during the life of the project, and you need to be able to reflect these changes.

MS-Project allows entering up to 125 different cost rates for a resource and specifying the date at which the new rates takes effect.

In the “Resource Sheet” view, enter the following rates information for the different resources as shown:

Page 58: Introducing Microsoft Project 2007

56

56

Resource Notes:

You use Resource Notes in much the same way as Task Notes.

For example, double-click the “Jane Doe” resource which will display the “Resource Information” dialog box. Select the “Notes” tab.

Type “Send reminder regarding Team Meeting” in the “Notes” area:

Click OK button to save and attach the note to the resource.

Notice the “note symbol” in the “Indicator” column of the “Resource Sheet” view. Move your mouse cursor over it to display the note.

Page 59: Introducing Microsoft Project 2007

57

57

Assigning Resources (Example):

Open the “Gantt Chart” view.

Double-click on the “Team Meeting 1” Task; the “Task Information” dialog box appears. Click on the “Resources” tab:

In “Resource Name” column, select “Jane Doe” & “Kati Aiko” resources for this Task as shown:

Page 60: Introducing Microsoft Project 2007

58

58

Click OK button to close the dialog box.

Now, assign the following Tasks to “Jane Doe” using the “Resource Names” column in the “Gantt Chart”.

o Research New Product o Create an Outline o Write a Rough Draft

Assign the resource “Katie Aiko” to the following Tasks:

o Edit Rough Draft o Prepare through Desktop Publishing o Create Mailing List

Double-click on the “Do Mass Mail Out” Task to open its “Task Information” dialog box. Assign resources & units as shown:

Hint: “Assignment Owner” is a new feature in MS Project 2007. In this field, assign the Individual who is responsible for entering actual work or reporting progress against an assignment (MS Project 2007 Bible, page 510)

Page 61: Introducing Microsoft Project 2007

59

59

Save your Project.

The Gantt Chart view will look like this”

Page 62: Introducing Microsoft Project 2007

60

60

Page 63: Introducing Microsoft Project 2007

61

61

View Information:

You can use most views to enter and edit information, although some views can only display information.

All views are made up of 3 basic components:

o Chart or Graph: Information is represented by pictures.

o Sheet: Information is represented in a table format, similar to a worksheet.

o Form: Information about a single item is represented as it might be on a paper form.

Page 64: Introducing Microsoft Project 2007

62

62

Gantt Chart View: “View/Gantt Chart”

It is useful for entering task information and viewing the timing and relationship between tasks.

The “Gantt Chart” view is the default view within MS-Project. It consists of the Gantt Table & Gantt Chart.

The Timescale at the top of the “Gantt Chart” is set to show weeks (in the middle tier) and days (in the bottom tier) as the default.

However, you can adjust it to show any Timescale you wish:

o Double-click on the Timescale. This will display the “Timescale” dialog box:

o You can format any tier on the Timescale.

Page 65: Introducing Microsoft Project 2007

63

63

o Select Days (for example) instead of Weeks for the middle tier. A preview of changes is shown in the bottom portion of the dialog box:

Page 66: Introducing Microsoft Project 2007

64

64

o The “Gantt Chart” will now look like this:

o You can zoom in or out to view larger or smaller time increments in the Gantt Chart using the “Zoom In” and “Zoom Out” buttons in the “Toolbar”.

o You can also use “View/Zoom”. Experiment with using different levels of Zoom.

Calendar View:

The Calendar View is useful for a general overview of what needs to be done on a specific day. It uses a monthly format to show scheduled tasks.

To display the “Calendar View”, just click “Calendar” icon on the “View Bar” or “View/Calendar”.

Page 67: Introducing Microsoft Project 2007

65

65

Task Usage View: “View/Task Usage”

This View is useful for showing and organizing assigned Resources for each Task:

Page 68: Introducing Microsoft Project 2007

66

66

By default, the “Task Usage” table is shown in the left pane. To choose a different table, click on the “Select All” button (at the top-left-corner of the table).

Right-click and select the view you wish to see.

Work is shown in the “Details” section in the right pane. To select different options for the “Details” section, click on the “Select All” button and right-click. This gives you access to the “Timescale”, “Zoon”, and “Change Working Time” dialog boxes.

Right-click on “Work” in the “Details” column of the “Task Usage” chart, and select “Cost”.

Page 69: Introducing Microsoft Project 2007

67

67

Notice that now both “Work” & “Cost” are listed in the “Task Usage Chart”. The cost is displayed in the table.

Page 70: Introducing Microsoft Project 2007

68

68

Resource Graph View: “View/Resource Graph”

Click on the “Resource Graph” icon within the “View Bar”; or click “View/Resource Graph”:

Note: If the Resources are not visible, use the scroll bar at the bottom of the Graph Pane to navigate to the dates in which the project fall.

Notice how a red color represents Over-Allocations

Hint:

If there is no red color appears in the “Resource Graph” above, make the relationship between “Research New Product” & “Create an Outline” Tasks as of “SS” Type.

Page 71: Introducing Microsoft Project 2007

69

69

Resource Sheet View:”View/Resource Sheet”

This view is very useful for viewing, entering, and editing resource information. It contains detailed resource information in a worksheet format.

If an over-allocation exists, a warning flag is displayed in the “Indicator” column. In addition, the resource appears in red color.

Page 72: Introducing Microsoft Project 2007

70

70

Resource Usage View: “View/Resource Usage”

This view is useful for seeing each resource and the tasks assigned to that resource.

This view can be used for entering and editing resource information, or assigning tasks. To assign or reassign a task, drag and drop between resources.

Page 73: Introducing Microsoft Project 2007

71

71

Quick Viewing & Printing Reports:

Not all information is relevant to everyone, so it is important to be able to present the appropriate data to the right people.

Using “Print Preview”:

Returning back to our example “New Product Brochure.mpp”.

Display the “Print Preview” window, the screen will now look like this:

Note that “Print Preview” has its own toolbar; so Use this toolbar & “File/Page Setup” to arrange for the desired obtained report.

Page 74: Introducing Microsoft Project 2007

72

72

Reports:

Click on the “Report/Reports…”, the “Reports” dialog box displays:

Page 75: Introducing Microsoft Project 2007

73

73

Overview Reports:

Click “Overview…” report and then click “Select” button. You will see the following “Overview Reports” window:

There are 5 types of “Overview Reports”:

o Project Summary o Top-Level Tasks o Critical Tasks o Milestones o Working Days

Experiment the different types of reports, by choosing each of the options and clicking on the “Select” button.

Close the “Reports” dialog box.

Page 76: Introducing Microsoft Project 2007

74

74

Current Activity Reports:

There are 6 types of “Current Activity Reports”:

o Unstarted Tasks o Tasks Starting Soon o Tasks In Progress o Completed Tasks o Should Have Started Tasks o Slipping Tasks

Experiment the different types of reports, by choosing each of the options and clicking on the “Select” button.

Close the “Reports” dialog box.

Page 77: Introducing Microsoft Project 2007

75

75

Cost Reports: “Reports/Reports…/Costs”

Click “Reports/Reports…/Costs/Select”, the following “Cost Reports” window appears:

Experiment the different types of reports, by choosing each of the options and clicking on the “Select” button.

Close the “Reports” dialog box.

Page 78: Introducing Microsoft Project 2007

76

76

Workload Reports: “Reports/Reports…/Workload…”

Assignment Reports: “Reports/Reports…/Assignments…”

Page 79: Introducing Microsoft Project 2007

77

77

Visual Reports: “Reports/Visual Reports”

This allows taking the data from within a MS-Project, formatting that data, and then exporting that data to a different application as MS Excel or MS Visio.

Click “Report/Visual Reports…”, the “Visual Reports” dialog box appears:

Page 80: Introducing Microsoft Project 2007

78

78

Notice that at the top of the dialog box, by default, templates are shown that involve both “MS Excel” & “MS Visio”.

If you do not have “MS Visio” installed on computer, then you can remove the tick next to this option, so that only “MS Excel” templates are used.

Spend a little time experimenting with the Visual Reports feature.

Page 81: Introducing Microsoft Project 2007

79

79

Case Studies

Page 82: Introducing Microsoft Project 2007

80

80

Case Study No 1: Project Name: Case_1

Starting Date: 1/1/2010 Project Calendar: 5 days/Week [SUN]

The Resource “Trainer” is working one Overtime hour every day

Basic Data:

No Task Predecessor Rel. Type

OD (Day)

Resources (Work/ Equipment)

Max Units

Material Cost (Expenses)

1 Introduction --- --- 1 Trainer 1 $200 Project Manager 1 CAD Operator 1 Facilitator 1 Computers 10 Data Show 1

2 MS Project Introduction FS 1 Trainer 1 $20 CAD Operator 1 Computers 10 Data Show 1

3 Data Entry MS Project FS 1 Trainer 1 $20 CAD Operator 1 Computers 10 Data Show 1

4 Logical Relations

MS Project FS 2 Trainer 1 Data Entry SS CAD Operator 10 Computers 1 Data Show 1

5 Constraints Logical Relations

FF 1 Trainer 1 $20

CAD Operator 1 Computers 10 Data Show 1

6 Improvements Constraints FS 1 Trainer 1 $300 Project Manager 1 CAD Operator 1 Facilitator 1 Computers 10 Data Show 1

Page 83: Introducing Microsoft Project 2007

81

81

Resources: Standard Rate & Overtime Rate: No Resource Name Resource

Type Std Rate Overtime

Rate 1

Trainer Work $20/hr $30/hr

2

CAD Operator Work $7/hr $10/hr

3

Project Manager Work $30/hr $45/hr

4

Facilitator Work $4/hr $6/hr

5

Computer Equipment $2/hr ---

6

Data Show Equipment $4/hr ---

7

Expenses Cost --- ---

Page 84: Introducing Microsoft Project 2007

82

82

Working Steps: 1. Create a New Project called “Case_1”

2. Change the Start Date & Current Date of the Project to “1/1/2010”.

a. “Project/Project Information” b. Start date: 1/1/2010

c. Current date: 1/1/2010

3. Create a New Calendar: “Case_1 Cal”.

a. “Tools/Change Working Time” b. “Create New Calendar…”

Page 85: Introducing Microsoft Project 2007

83

83

c. Name: Case_1 Cal

Page 86: Introducing Microsoft Project 2007

84

84

d. Press “Options”

e. Week Starts on: Sunday f. Press OK g. Press “Work Weeks” tab on the “Change Working Time”

window, the “Details…” button becomes active.

h. Press “Details…” button.

Page 87: Introducing Microsoft Project 2007

85

85

i. Change the “Sunday” to Working day j. Change “Friday” to Non-working day

k. Press OK. 4. Assign “Case_1 Cal” to “Case_1” Project.

a. “Project/Project Information” b. Calendar: Case_1 Cal.

Page 88: Introducing Microsoft Project 2007

86

86

Page 89: Introducing Microsoft Project 2007

87

87

5. Enter Tasks, Durations & Relationships.

a. Sometimes, the Calendar in the “Bar-Chart” area does not coincide with the Project Calendar especially for the non-working days.

b. To resolve this problem, click in the “Bar-Chart” area and right-click to choose “Nonworking Time…”

c. Choose “Case_1 Cal” for “Calendar:” field, then the Gantt-Chart will look like the one above.

Page 90: Introducing Microsoft Project 2007

88

88

6. Record the Resources in the “Resource Sheet”.

a. “View/Resource Sheet”

Page 91: Introducing Microsoft Project 2007

89

89

7. Resource Assignment --- Assign different Resources to different Tasks:

a. Before Assigning Resources, It will be useful to change the

Task Types to “Fixed Duration” Tasks & Change the “Effort Driven” to “No”.

b. To facilitate this process, insert two columns as shown above

the make the necessary changes.

c. Now, assign the Resources.

i. Highlight the 1st activity and click the “Assign Resources” icon on the “Tool Bar” shown in the window above, the “Assign Resources” window appears:

Page 92: Introducing Microsoft Project 2007

90

90

ii. Choose the different resources to the specified task as shown:

Hint: “R/D” above means Request/Demand…

iii. Repeat with the other Tasks.

Page 93: Introducing Microsoft Project 2007

91

91

8. To check Resource Allocation, Click “Resource Sheet”:

9. Notice the Resource with red color. This means that there is an over-

allocation for this Resource.

10. Resolve Resource Over-Allocation: a. “Tools/ Level Resources”, the “Resource Leveling” window

appears:

Page 94: Introducing Microsoft Project 2007

92

92

b. Press “Level Now”. the result will be shown as follows:

c. Return back to the “Resource Sheet” and notice that there is a

problem with the “Trainer” Resource. To resolve this problem, assign a “Max. Units” of 10 Trainers; otherwise, the problem will exist.

Page 95: Introducing Microsoft Project 2007

93

93

Page 96: Introducing Microsoft Project 2007

94

94

11. Using Overtime:

Overtime work does not represent additional work on a Task;

instead, it represents the amount of time that is spent on a Task outside regular hours.

To Enter Overtime:

1. Display the “Gantt Chart” View (“View/Gantt Chart”) 2. Choose “Window/Split” to reveal the “Task Form” in the bottom

pane. 3. Click the “Task Form” to make it the active pane. 4. Choose “Format/Details/Resource Work”. Project adds the “Ovt.

Work” column to the “Task Form”:

5. Move to the top pane, and select the task to which you want to assign overtime.

Page 97: Introducing Microsoft Project 2007

95

95

6. Move to the bottom pane and fill in the “Overtime Work” for the appropriate Resource.

7. Click OK, Project adjusts the schedule. 8. You can adjust the “top pane” of the “Gant Chart” so that you

can display the “Overtime Work” & “Overtime Cost” columns as shown:

Page 98: Introducing Microsoft Project 2007

96

96

12. Design and Display the different Reports

Page 99: Introducing Microsoft Project 2007

97

97

Case Study No 2 (Arabic): Background:

1. You have been assigned the responsibility for scheduling and monitoring the progress of Building the 2nd Floor of a Villa.

2. Major Engineering Design tasks have been completed.

3. The Project consists of 28 major Activities (Tasks). The

following list of Project Activities includes the basic information which you need to schedule and track the principle Activities in the Project.

4. While you are in charge of the scheduling and implementation

of the overall Project, you will receive monthly reports of Project Implementation Progress from the Construction Site Supervisors.

5. On the basis of monthly reports from the Project Site, you will

monitor the progress of Project Execution.

6. In carrying out your assignment, you are aware that the OWNER is anxious to open the Project as early as possible.

Page 100: Introducing Microsoft Project 2007

98

98

This Case Study will cover the following points:

1. Project Calendar(s), 2. Work Breakdown Structure (WBS) with Responsible

Managers Assignment. 3. Entering Project Activities with their Duration and

Relationships.

4. Scheduling & Assigning Constraints. 5. Establishing Project & Activity Codes which may determine

Responsibilities and Type of Work. 6. Establishing Roles & Resources Dictionaries and Assign

them to Activities as needed to execute the Project which may be Labor, nonlabor (Equipment) [Work], Material, and Money (Expenses - Cost/Use).

7. Analyze Project Resources, Optimize the Project Plan,

Baselining the Project Plan, Execute, and Control (Update). 8. Producing different set of Reports, for example:

Tabular Schedules,

Bar Charts,

Time-Scaled Logic Diagrams,

Project Network Diagrams,

Resource and Cost Reports:

o Project Labor, Nonlabor (Equipment), Material,

and Expenses Costs,

o Project Cash-Flow, etc….

Page 101: Introducing Microsoft Project 2007

99

99

Now, Project Name: Case_2 Project Start Date: 1 Jan 2010 Project Current Date: 1 Jan 2010 Project Calendar: Case_2 Cal

Holidays:

o 7 January (Christmas --- repeated)

o 1 May (Workers Day --- repeated)

o 23 July (July Revolution --- repeated)

o 6 October (Vector Day --- repeated)

Working Steps:

1. Create New Project called “Case_2.1”

2. Change the Start Date & Current Date of the Project to “1/1/2010”.

b. “Project/Project Information”

c. Start date: 1/1/2010 d. Current date: 1/1/2010

Page 102: Introducing Microsoft Project 2007

100

100

3. Create a New Calendar: “Cae_2 Cal”.

a. “Tools/Change Working Time”

b. “Create New Calendar…”

i. Name: Case_2 Cal

ii. Press “Options”

iii. Week Starts on: Sunday

iv. Press OK

v. Press “Workweek” tab on the “Change Working Time” window.

vi. Change the “Sunday” to working day

vii. Change Friday to Non-working Day

viii. Press OK.

ix. Create the Calendar Holidays as mentioned above.

Page 103: Introducing Microsoft Project 2007

101

101

4. Assign “Case_2 Cal” to “Case_2.1” Project.

a. “Project/Project Information” b. Calendar: Case_2 Cal.

c. Press OK.

5. Make “Case_2 Cal” as a “Global Calendar”. 6. Enter Tasks, Durations & Relationships.

a. Look at the Gantt-Chart Area and notice the non-working days which contradicts the Project Calendar named “Case_2 Cal”.

b. To resolve this problem, click in the Bar-Chart Area and right-click to choose “Nonworking Time…”

c. Choose “Case_2 Cal” for “Calendar:” field.

d. Enter the Project Tasks & Relationships:

Page 104: Introducing Microsoft Project 2007

102

102

Page 105: Introducing Microsoft Project 2007

103

103

Page 106: Introducing Microsoft Project 2007

104

104

Page 107: Introducing Microsoft Project 2007

105

105

Page 108: Introducing Microsoft Project 2007

106

106

7. Coding & Organization:

a. Create two Fields from “Custom Fields” named “Responsibility” & “Type of Work” to represent just Codes for the Project Activities.

b. This can be done by creating “Custom Fields” as follows:

c. Click “Tools/Customize/Fields…”, the “Custom Fields”

window appears:

d. Write the field name “Responsibility” as Text1

Page 109: Introducing Microsoft Project 2007

107

107

e. Press “Lookup…” button to enter the different values for the

custom field as shown:

f. In the “Gantt Chart” view, insert a new column and choose “Responsibility” Custom Field.

g. Fill in and assign the Responsible for each Task in the Project.

Page 110: Introducing Microsoft Project 2007

108

108

h. Now, you can organize by “Responsibility” as follows:

i. Click “Project / Group by / Customize Group By…”, the following “Customize Group By” Window appears:

ii. Choose the Custom Field “Responsibility” as shown above.

iii. Press OK, the following Layout appears:

Page 111: Introducing Microsoft Project 2007

109

109

Page 112: Introducing Microsoft Project 2007

110

110

Page 113: Introducing Microsoft Project 2007

111

111

iv. Repeat with the Custom Field “Type of Work”

Page 114: Introducing Microsoft Project 2007

112

112

Page 115: Introducing Microsoft Project 2007

113

113

8. Record the Resources in the “Resource Sheet”:

a. “View/Resource Sheet” b. Fill in the Resources as shown:

Page 116: Introducing Microsoft Project 2007

114

114

Units of Measurements

Page 117: Introducing Microsoft Project 2007

115

115

Page 118: Introducing Microsoft Project 2007

116

116

9. Assign different Resources to different Tasks.

a. Before Assigning Resources, It will be useful to change the Task Types to “Fixed Duration” Tasks & Change the “Effort Driven to “No”.

b. To facilitate this process, insert two columns as shown:

Page 119: Introducing Microsoft Project 2007

117

117

Page 120: Introducing Microsoft Project 2007

118

118

c. You can also do the following at the beginning of Creating the Project:

“Tools/Options/Schedule”

• Duration is entered in: Days • Work is entered in: Days • Default Task Type: Fixed Duration

Page 121: Introducing Microsoft Project 2007

119

119

d. Now, assign the Resources:

i. Display the “Gantt Chart” and Split the Window.

ii. Display “Resource Work” in the bottom window

1. Right-click & choose “Resource Work”

2. Highlight the 1st activity and click on the bottom pane to Assign Resources.

3. Use the following “Table of Project’s Resources”

Page 122: Introducing Microsoft Project 2007

120

120

PROJECT’s RESOURCES (Activities are sorted by ES and TF)

ID Act. ID

Task

OD

Resource

Label UOM

Units

BQ (Work)

01

STA2 Start 2nd floor activities التجهيز لبدء العمل

01 0.00 0.00

02

CO22C100 2nd floor form work columns أعمال شد النجارة لألعمدة

07 CARPENTR نجار مسلح

6.00 42.00

03-1 CO22C200 2nd floor R.F.T columns رص الحديد لألعمدة

04 R.F.T حديد تسليح

TON 3.00 12.00

03-2

CO22C200 2nd floor R.F.T columns رص الحديد لألعمدة

04 STEELMEN حداد مسلح

3.00 12.00

04-1 CO22C300 2nd floor cast in place concrete columns صب الخرسانة المسلحة لألعمدة

03 CONC.MIX الخالطة الخرسانية

DAY 1.00 3.00

04-2 CO22C300 2nd floor cast in place concrete columns صب الخرسانة المسلحة لألعمدة

03 CON.LABR طقم الطبلية

1.00 3.00

04-3 CO22C300 2nd floor cast in place concrete columns صب الخرسانة المسلحة لألعمدة

03 CEMENT األسمنت

TON 10.00 30.00

04-4 CO22C300 2nd floor cast in place concrete columns صب الخرسانة المسلحة لألعمدة

03 SAND الرمل

CM 11.67 35.00

04-5

CO22C300

2nd floor cast in place concrete columns صب الخرسانة المسلحة لألعمدة

03 GRAVEL الزلط

CM 23.33 70.00

05-1 CO22C400 2nd floor curing time for columns فك الشدة الخشبية + أعمال المعالجة

05 WATERPRI ثمن المياه

CM 1.60 8.00

Page 123: Introducing Microsoft Project 2007

121

121

05-2

CO22C400 2nd floor curing time for columns فك الشدة الخشبية+ أعمال المعالجة

05 LABOUR 1.00 5.00

06

CO22S100 2nd floor (slabs+stairs) form work شد النجارة المسلحة لألسقف والساللم

11 CARPENTR نجار مسلح

10.00 110.00

07-1 CO22S200 2nd floor (slabs+stairs) R.F.T رص الحديد لألسقف والساللم

07 STEELMEN حداد مسلح

2.29 16.00

07-2

CO22S200 2nd floor (slabs+stairs) R.F.T رص الحديد لألسقف والساللم

07 R.F.T حديد تسليح

TON 3.71 26.00

08-1 CO22S300 2nd floor (slabs+stairs) cast in place صب الخرسانة المسلحة لألسقف والساللم

03 CON.LABR طقم الطبلية

2.00 6.00

08-2 CO22S300 2nd floor (slabs+stairs) cast in place صب الخرسانة المسلحة لألسقف والساللم

03 CONC.MIX الخالطة الخرسانية

DAY 2.00 6.00

08-3 CO22S300 2nd floor (slabs+stairs) cast in place صب الخرسانة المسلحة لألسقف والساللم

03 CEMENT األسمنت

TON 25.00 76.00

08-4 CO22S300 2nd floor (slabs+stairs) cast in place صب الخرسانة المسلحة لألسقف والساللم

03 SAND الرمل

CM 29.00 87.00

08-5

CO22S300 2nd floor (slabs+stairs) cast in place 03 GRAVEL الزلط

CM 58.00 174.00

09-1 CO22S400 2nd floor (curing time+removal of form work) slab

لألسقف والساللم فك الشدة الخشبية+ أعمال المعالجة

10 LABOUR عمالة عادية

1.00 10.00

09-2

CO22S400 2nd floor (curing time+removal of form work) slab

لألسقف والساللم فك الشدة الخشبية+ أعمال المعالجة

10 WATERPRI ثمن المياه

CM 2.00 20.00

10-1 BLO2 100 2nd floor block work thick 25 cm سم 25أعمال مباني

12 BRIC.LAY بنا

3.00 36.00

10-2 BLO2 100 2nd floor block work thick 25 cm سم 25أعمال مباني

12 CEMENT األسمنت

TON 1.75 21.00

Page 124: Introducing Microsoft Project 2007

122

122

10-3

BLO2 100 2nd floor block work thick 25 cm سم 25عمال مباني أ

12 BRICKMAT سم 25طوب

SM 180.00 2160.00

11-1 BLO2 200 2nd floor block work thick 12 cm سم 12أعمال مباني

04 BRIC.LAY بنا

2.00 8.00

11-2 BLO2 200 2nd floor block work thick 12 cm سم 12أعمال مباني

04 BRICKMAT سم 12طوب

SM 79.50 318.00

11-3

BLO2 200 2nd floor block work thick 12 cm سم 12أعمال مباني

04 CEMENT األسمنت

TON 0.75 3.00

12

WOD2 100 2nd floor (windows+doors) sub frames تركيب حلوق األبواب والشبابيك

07 DOORCARP نجار باب وشباك

4.00 28.00

13-1 ELE2 100 2nd floor electrical conduits تركيب مواسير الكهرباء في الحوائط

07 0.00 0.00

13-2

ELE2 100 2nd floor electrical conduits تركيب مواسير الكهرباء في الحوائط

07 0.00 0.00

14-1 INP2 100 2nd floor internal plastering for (walls+slabs) البياض الداخلي لألسقف والحوائط

20 PLAS.MEN صص بياض متخ

5.00 100.00

14-2 INP2 100 2nd floor internal plastering for (walls+slabs) البياض الداخلي لألسقف والحوائط

20 CEMENT األسمنت

TON 1.15 23.00

14-3

INP2 100 2nd floor internal plastering for (walls+slabs) البياض الداخلي لألسقف والحوائط

20 SAND الرمل

CM 5.55 111.00

14-4

INP2 100 2nd floor internal plastering for (walls+slabs) البياض الداخلي لألسقف والحوائط

20 GUYPSUM جيبس

TON 0.10 2.00

15-1 SAN2 100 2nd floor sanitary pipes تركيب مواسير الذهر

20 PLUMBER سباك

3.00 60.00

15-2

SAN2 100

2nd floor sanitary pipes تركيب مواسير الذهر

20 SAN.PIPE مواسير الصرف

الصحي

LM 7.50 150.00

Page 125: Introducing Microsoft Project 2007

123

123

16-1 INP2 200 2nd floor TRATZO plastering م عادة ما يكون في الممرات 2سفل بأرتفاع

08 PLAS.MEN متخصص بياض

3.00 24.00

16-2 INP2 200 2nd floor TRATZO plastering م عادة ما يكون في الممرات 2سفل بأرتفاع

08 CEMENT األسمنت

TON 1.25 10.00

16-3 INP2 200 2nd floor TRATZO plastering م عادة ما يكون في الممرات 2سفل بأرتفاع

08 SAND الرمل

CM 29.38 235.00

16-4 INP2 200 2nd floor TRATZO plastering م عادة ما يكون في الممرات 2سفل بأرتفاع

08 GUYPSUM جيبس

TON 0.13 1.00

16-5

INP2 200 2nd floor TRATZO plastering م عادة ما يكون في الممرات 2سفل بأرتفاع

08 WHITECEN أسنت أبيض

TON 0.38 3.00

17-1 SAN2 200 2nd floor potable water piping circuits سباكة تركيب مواسير الشرب -

09 PLUMBER سباك

3.00 27.00

17-2

SAN2 200 2nd floor potable water piping circuits سباكة تركيب مواسير الشرب -

09 IRON.PIP مواسير حديد

LM 21.11 190.00

18-1 ELE2 200 2nd floor electrical wires أدخال األسالك في المواسير الكهربية

14 0.00 0.00

18-2

ELE2 200 2nd floor electrical wires أدخال األسالك في المواسير الكهربية

14 0.00 0.00

19-1 FLO2 100 2nd floor mosaic tiles dim 40*40 cm سم 40*40تركيب بالط

10 MOSAIC سيراميك

SM 125.00 1250.00

19-2 FLO2 100 2nd floor mosaic tiles dim 40*40 cm سم 40*40تركيب بالط

10 TILE.MEN مبلط

2.00 20.00

19-3 FLO2 100 2nd floor mosaic tiles dim 40*40 cm سم 40*40تركيب بالط

10 SAND الرمل

CM 5.00 50.00

19-4

FLO2 100 2nd floor mosaic tiles dim 40*40 cm سم 40*40تركيب بالط

10 CEMENT األسمنت

TON 0.80 8.00

20-1 ISO2 100 2nd floor bathrooms proofing مال العزل للحمامات أع

02 ISO.MEN متخصص عزل

1.00 2.00

Page 126: Introducing Microsoft Project 2007

124

124

20-2

ISO2 100 2nd floor bathrooms proofing أعمال العزل للحمامات

02 INSULATI مادة عازلة

SM 100.00 200.00

21-1 CER2 100 2nd floor ceramic (walls+slabs) تركيب السيراميك للحمامات

04 CERAMIC سيراميك

SM 50.00 200.00

21-2 CER2 100 2nd floor ceramic (walls+slabs) تركيب السيراميك للحمامات

04 CER.MEN متخصص تركيب

سيراميك

2.00 8.00

21-3

CER2 100 2nd floor ceramic (walls+slabs) تركيب السيراميك للحمامات

04 SAND الرمل

CM 2.25 9.00

22-1 PAI2 100 2nd floor painting preparation layers أعمال البطانة للدهانات

06 PAINTMEN بياض متخصص

2.00 12.00

22-2

PAI2 100 2nd floor painting preparation layers أعمال البطانة للدهانات

06 PAINTMAT مواد الدهانات

SM 308.33 1850.00

23-1 FRP2 100 2nd floor frontal plastering بياض الواجهات

21 FRON.PLA مبيض محارة -

واجهات

4.00 84.00

23-2 FRP2 100 2nd floor frontal plastering بياض الواجهات

21 CEMENT األسمنت

TON 1.48 31.00

23-3 FRP2 100 2nd floor frontal plastering بياض الواجهات

21 SAND الرمل

CM 4.05 85.00

23-4 FRP2 100 2nd floor frontal plastering بياض الواجهات

21 GUYPSUM متخصص بياض

TON 0.05 1.00

23-5

FRP2 100 2nd floor frontal plastering بياض الواجهات

21 WHITECEN TON 0.14 3.00

24-1 SAN2 300 2nd floor install of sanitary fixtures سباكة تركيب األحواض والحنفيات -

06 PLUMBER سباك

2.00 12.00

24-2

SAN2 300 2nd floor install of sanitary fixtures سباكة تركيب األحواض والحنفيات -

06 SAN.FIXT صيني

PART 2.00 12.00

Page 127: Introducing Microsoft Project 2007

125

125

25-1 WOD 2200 2nd floor install (doors+windows) تركيب األبواب والشبابيك

10 DOORCARP نجار باب وشباك

7.20 72.00

25-2

WOD 2200 2nd floor install (doors+windows) تركيب األبواب والشبابيك

10 MOS.DOOR أبواب وشبابيك

موسكي

PART 7.20 72.00

26-1 PAI2 200 2nd floor final painting layers أعمال الدهانات النهائية

12 PAINTMAT مواد الدهانات

SM 308.33 3700.00

26-2

PAI2 200 2nd floor final painting layers أعمال الدهانات النهائية

12 PAINTMEN نقاش

2.00 24.00

27-1 ELE2 300 2nd floor electrical switches lighting fix تركيبات كهربائية نهائية

14 LIG.FIXT تركيبات كهربية

PART 17.86 250.00

27-2

ELE2 300 2nd floor electrical switches lighting fix هربائية نهائيةتركيبات ك

14 0.00 0.00

28

END2 2nd floor hand over activities تسليم المشروع

01 0.00 0.00

Page 128: Introducing Microsoft Project 2007

126

126

Work = Budget Quantity

Page 129: Introducing Microsoft Project 2007

127

127

10. Design and Display the different Reports

Page 130: Introducing Microsoft Project 2007

128

128

Case Study No 2 (English): Project Name: Case_2 Project Start date: 1 Jan 2010 Calendar: Case_2 Cal Holidays:

o 7 January (repeated) o 1 May (repeated) o 23 July (repeated) o 6 October (repeated)

Working Steps:

1. Create New Project called “Case_2.1 Basic Data”. 2. Change the Start Date of the Project to “1/1/2010”.

a. “Project/Project Information”

b. Start date: 1/1/2010

3. Create a New Calendar: “Case_2 Cal”.

a. Click “Tools/Change Working Time…” b. Click “Create New Calendar…”

i. Name: Case_2 Cal ii. Press “Options”

iii. Week Starts on: Sunday iv. Press OK v. Press “Work Weeks” tab on the “Change Working

Time” window. vi. Change the “Sunday” to working day

vii. Change Friday to Non-working day viii. Press OK.

ix. Create the Calendar Holidays as mentioned above.

Page 131: Introducing Microsoft Project 2007

129

129

4. Assign “Case_2 Cal” to “Case_2.1 Basic Data”.

a. Click “Project/Project Information” b. Calendar: Case_2 Cal.

c. Press OK.

5. Make “Case_2 C al” as a “Global Calendar”. 6. Enter Tasks, Durations & Relationships.

a. Do the following before Entering Tasks, Duration, & Relationship:

“Tools/Options/Schedule”

• Duration is entered in: Days • Work is entered in: Days • Default Task Type: Fixed Duration

Page 132: Introducing Microsoft Project 2007

130

130

Page 133: Introducing Microsoft Project 2007

131

131

b. Look at the Gantt-Chart area and notice the non-working days which contradicts the Project Calendar named “Case_2 al”.

c. To resolve this problem, click in the Bar-Chart area and right-click to choose “Nonworking Time…”

d. Choose “Case_2 Cal” for “Calendar:” field.

e. Enter the Project Tasks & Relationships:

Page 134: Introducing Microsoft Project 2007

132

132

Page 135: Introducing Microsoft Project 2007

133

133

Page 136: Introducing Microsoft Project 2007

134

134

Page 137: Introducing Microsoft Project 2007

135

135

Page 138: Introducing Microsoft Project 2007

136

136

7. Coding & Organization:

a. Create two Custom Fields from “Tools / Custom Fields…” named “Responsibility” & “Type of Work” to represent just Codes for the Tasks of Project.

b. This can be done by creating “Custom Field” as follows:

Page 139: Introducing Microsoft Project 2007

137

137

c. Press “Lookup…” button to enter the different values for the custom field as shown:

d. In the “Gantt Chart” view, insert a new column and choose “Responsibility.

e. Fill in and assign the responsibility value for each task in the

Project. f. Now, you can organize by “Responsibility” as follows:

Page 140: Introducing Microsoft Project 2007

138

138

i. “Project / Group by: No Group / Customize Group By…”, the following window appears:

ii. Choose “Responsibility” in the “Field Name” of “Group By” as shown above.

iii. Press OK, the following Layout appears:

Page 141: Introducing Microsoft Project 2007

139

139

Page 142: Introducing Microsoft Project 2007

140

140

Page 143: Introducing Microsoft Project 2007

141

141

Coding & Organization:

In the previous Project “Case_2 Arabic”, we exercised the Project

Organization using the Task Code called “Responsibility”.

Now, let us create a Custom Field named “Type of Work” to represent just another Task Code in the Project.

This can be done by clicking “Tools / Customize / Fields…”, the Custom Fields window appears:

Page 144: Introducing Microsoft Project 2007

142

142

Write the name “Type of Work” as Text3:

Press “Lookup…” button to enter the different values for the Custom Field as shown:

Page 145: Introducing Microsoft Project 2007

143

143

In the “Gantt Chart” View, insert a new column and choose “Type

of Work”.

Assign the specific Value corresponding to each Task as shown:

Page 146: Introducing Microsoft Project 2007

144

144

Page 147: Introducing Microsoft Project 2007

145

145

Now, Let us ask a Question Like this: Display All Tasks of Concrete for Columns.

To answer this Question, make a Filter using:

o “Project / Filtered for / More Filters… / New…”, the following window appears:

Press “New…”, the following window appears:

Page 148: Introducing Microsoft Project 2007

146

146

Fill in as shown:

Press OK, the following Layout including only the requested Tasks

appears:

Page 149: Introducing Microsoft Project 2007

147

147

Page 150: Introducing Microsoft Project 2007

148

148

In the same manner, you can display what you want.

Exercise you self and try to answer any question concerning this

Project.

Page 151: Introducing Microsoft Project 2007

149

149

8. Record the Resources in the “Resource Sheet”: a. “View/Resource Sheet” b. Fill in the Resources as shown:

Units of Measurements

Page 152: Introducing Microsoft Project 2007

150

150

Page 153: Introducing Microsoft Project 2007

151

151

9. Assign different Resources to different Tasks. a. Before Assigning Resources, It will be useful to change the

Task Types to “Fixed Duration” Tasks & Change the “Effort Driven to “No”.

[Default: Task Type—Fixed Units & Effort Driven=Yes] b. To facilitate this process, insert two columns as shown:

c. You can also do the following:

i. “Tools/Options/Schedule”

• Duration is entered in: Days • Work is entered in: Days • Default Task Type: Fixed Duration

Page 154: Introducing Microsoft Project 2007

152

152

Task Types (Fixed Duration, Fixed Units, Fixed Work): The way MS Project uses Work, Duration, and Resources to schedule Tasks is called effort-driven scheduling, which is the default scheduling method. With effort-driven scheduling, the more Resources you assign to a Task, the shorter the Duration becomes. To have MS Project schedule a Task exactly the way you want it, you need to know how these factors do that. Changing the Task Type:

The Duration of each Task is determined by Resource Availability

and (most important) by the formula:

Duration = Work ÷ Resource Units or

Work = Duration * Resource Units If you assign Resources, MS Project uses this formula as the basis for

all its scheduling.

A Task Type (Fixed Duration, Fixed Units, or Fixed Work) is a method MS Project uses to calculate the Work, Duration, and Resource Units for a Task. You can choose the method you want MS Project to use on a Task-by-Task Basis.

Page 155: Introducing Microsoft Project 2007

153

153

Fixed-Units Tasks: Example, say you assign 2 full-time Painters to paint the walls

in 4 days. If you assign 2 more full-time Painters, MS Project reduces the duration to 2 days.

Page 156: Introducing Microsoft Project 2007

154

154

If you assign 2 more Painters, MS Project reduces the Duration to 2 days:

Page 157: Introducing Microsoft Project 2007

155

155

Fixed-Work Tasks:

When you set a Task to Fixed-Work, MS Project does not calculate the Work for the Tasks or Resources. Instead, as you change Resource Assignments, MS Project calculates Duration. For example, if you assign 2 Painters full-time to paint the walls in 4 days, and then you assign 2 more full-time Painters to the Task, MS Project reduces the Duration to 2 days.

Page 158: Introducing Microsoft Project 2007

156

156

Fixed-Duration Tasks:

When Duration is fixed, it remains at whatever value you enter and MS Project calculates Resource Units as you change Assignments. For example, say you assign 2 Painter full-time to paint the walls in 4 days:

Page 159: Introducing Microsoft Project 2007

157

157

Later, you assign 2 more full-time Painters. MS Project set the units for each Painter to %50 because 4 Painters need to work only half-time to complete the walls in 4 days: How ! ! !

Page 160: Introducing Microsoft Project 2007

158

158

Effort-Driven Tasks: Fixed-Work Tasks are always Effort-Driven Task.

For Fixed-Duration and Fixed-Units Tasks, you can tell MS Project

to modify the % of Total Work that is allocated to each Resource based on the number of Assigned Resources if the number of Resources changes.

Page 161: Introducing Microsoft Project 2007

159

159

In summary: Task Type: Fixed Units Effort Driven: Checked Task Duration Resource

(Units) New Duration

Work

A 10 1 10 10d 2 5 10d 5 2 10d Task Type: Fixed Duration Effort Driven: Checked/Unchecked Task Duration Resource

(Units) New Duration

Work

A 10 1 10 10d 2 10 10d 5 10 50d Task Type: Fixed Work Effort Driven: Checked by Default Task Duration Resource

(Units) New Duration

Work

A 10 1 10 10d 2 5 10d 5 2 10d Recommendation: It is better to set Fixed-Duration & No Effort-Driven in the normal and most common cases.

Page 162: Introducing Microsoft Project 2007

160

160

Page 163: Introducing Microsoft Project 2007

161

161

Page 164: Introducing Microsoft Project 2007

162

162

d. Now, Assign the Resources:

i. Display the “Gantt Chart” and Split the Window.

ii. Display “Resource Work” in the bottom window o right-click & choose “Resource Work”

iii. Highlight the 1st activity and click down to Assign

Resources.

iv. Use the following sheet to assign Resources to different Activities.

Page 165: Introducing Microsoft Project 2007

163

163

Recourse Assignment تخصيص الموارد لألنشطة

ID Task name

D

Resource

Budget Quantity (Work)

1 Start 0 2 FormWork for Columns 7

Carpenter 42 days 3 RFT for Columns 4

R.F.T 12 Ton Steel.Men 20 days

4 Cast-in-Place Concrete for Columns 3

Cement 30 Ton Conc.Labor 3 days Conc.Mix 3 days Gravel 70 CM Sand 35 CM

5 Curing Time for Columns 5 Ord.Labor 5 days Water 8 CM

6 FormWork for Slab & Stairs 11 Carpenter 110 days

7 RFT for Slab & Stairs 7 R.F.T 26 Ton Steel.Men 14 days

8 Cast-in-Place for Slab & Stairs 3 Cement 25 Ton Conc.Labor 6 days Conc.Mix 6 days Gravel 58 CM Sand 29 CM

9 Curing Time& Removal for FormWork 10

Ord.Labor 10 days Water 2 CM

10 Block Working thick 25 cm 12 Bric.Lay 36 days BrickMat 180 SM Cement 2 Ton

11 Block Working thick 12 cm 4 Bric.Lay 8 days BrickMat 80 SM Cement 1 Ton

Page 166: Introducing Microsoft Project 2007

164

164

12 Windows & Doors SubFrames 7 Door.Carp 28 days

13 Electrical Conduits 7

14 Internal Plastering for Walls & Slab 20

Cement 1 Ton Gypsum 0.1 Ton Plast.Men 100 days Sand 6 CM

15 Sanitary Pipes Fixation 20 Plumber 60 days Iron.Pipes 7.5 LM

16 TRATZO Plastering height 2 m 8 Cement 1.25 Ton Guypsum 0.13 Ton Sand 29 CM TRATZO.Plasters 24 days White_Cement 0.38 Ton

17 Potable Water Piping Circuits 9 Plumber 27 days Iron.Pipes 21 LM

18 Electrical Wires Fixation 14

19 Mosaic Tiles dim 40*40 cm Fixation 10

Cement 0.8 Ton Mosaic 125 SM Sand 5 CM Tiles.Men 20 days

20 Bathrooms Proofing 2 IsolationMaterial 100 SM Iso.Men 2 days

21 Ceramic Fixation for Walls & Slab

4 Cer.Men 8 days Ceramic 50 SM Sand 2 CM

22 Painting Preparation Layers 6 Paint.Materials 308 SM

Paint.Men 12 days 23 Frontal Plastering 21

Cement 1.48 Ton Front.Plaster 84 days Gypsum 0.05 Ton Sand 4 CM

Page 167: Introducing Microsoft Project 2007

165

165

White_Cement 0.14 Ton 24 Sanitary Installation 6

Plumber 12 days San.Fixation 2 Part

25 Doors & Windows Installation 10 Door.Carp 70 days Moskey.Doors 7 Part

26 Final Painting Layers 12 Paint.Materials 308 SM Paint.Men 24 days

27 Final Electrical Switches Fixation 14 Electrical.Fixation 18 Part

28 Hand Over 0

Page 168: Introducing Microsoft Project 2007

166

166

Page 169: Introducing Microsoft Project 2007

167

167

Task Usage View:

This View is useful for showing and organizing Assigned Resources under each Task:

Hint:

o By default, the Task Usage Table is shown in the Left-Pane.

To choose a different Table, click on the “Select All” button (at the top-left-corner of the Table

o Right-click and select the View you wish to see…..

o Right-click on “Work” in the “Details” column of the “Task Usage Chart”, and select “Cost”. Notice that both the “Work” & “Cost” are listed in the “Task Usage Chart”.

Page 170: Introducing Microsoft Project 2007

168

168

Resource Graph (Histogram) View:

Click on the “Resource Graph” icon within the “View Bar”.

Hint:

o If the Resources are not visible, use the “Scroll Bar” at the bottom

of the “Graph Pane” to navigate to the Dates in which the Project fall.

o Notice how a red column represents “Over-Allocations”.

Page 171: Introducing Microsoft Project 2007

169

169

Resource Sheet View: This View is useful for viewing, entering, and editing information. It

contains detailed Resource Information in a Worksheet Format.

This View is very helpful in determining which Group, a Resource belongs to.

If an “Over-Allocation” exists, a warning flag is displayed in the “Indicator” column. In addition, the Resource appears in red color.

Page 172: Introducing Microsoft Project 2007

170

170

Page 173: Introducing Microsoft Project 2007

171

171

Resource Usage View: This View is useful for seeing each Resource and the Tasks assigned

to that Resource..

The View can be used for entering and editing Resource Information, or Assigning Tasks.

To Assign or Re-Assign a Task, drag-and-drop between Resources.

A warning flag appears in the “Indicator” column if an “Over-

Allocation” exists.

Page 174: Introducing Microsoft Project 2007

172

172

Page 175: Introducing Microsoft Project 2007

173

173

Hint: Sometime, the Gant-Chart Pane did not coincide with the Project

Calendar.

If this is the case, do the following:

o Double-click on the “Timescale”, the “Timescale” window appears:

o Click on the “Non-working time” tab as shown:

Page 176: Introducing Microsoft Project 2007

174

174

Choose the “Project Calendar” from the “Calendar” field as shown above.

Page 177: Introducing Microsoft Project 2007

175

175

Tracking (Follow Up) Understanding Tracking: Up to this point, you have been in the Planning Phase (Building a

Project Schedule, Entering Tasks, Adding Resources, and Resolving Resource Conflicts).

A good Plan is only half way. How you execute that Plan is the Key.

You now have a Workable, Good-Looking Project in hand --- and

now, you are ready to start the Project. Updating Form: If your organization has forms and processes to capture actual and

status information, use those forms and processes as much as possible.

You may want to create a form for participants to use for their regular reports. These reports should provide the information that you need to update your project plan in MS-Project. You may be able to use one of the reports in MS-Project (or customize one of the Project’s Reports) to provide the necessary information.

Create New Table as follows:

o Click “View/Table/More Tables/New…”

o Choose:

ID Name Duration

Page 178: Introducing Microsoft Project 2007

176

176

o Insert Blank columns (Text3) with the following Titles:

AS --- Actual Start AF --- Actual Finish AD --- Actual Duration RD --- Remaining Duration % --- Percent Complete AC --- Actual Cost AW --- Actual Work Notes --- Notes

Page 179: Introducing Microsoft Project 2007

177

177

o Click OK & Apply, the following Table appears.

o You can distribute it on the Engineers at the Site to fill in and make feedback.

Page 180: Introducing Microsoft Project 2007

178

178

Page 181: Introducing Microsoft Project 2007

179

179

Tracking Process:

First of all, Record the Start & Finish Date before tracking. In our case, these Dates are shown as follows:

Now,

Page 182: Introducing Microsoft Project 2007

180

180

1. Setting BaseLine:

o Click “Tools/Tracking/Set Baseline” o Press OK. This saves Baseline and displays it in the Gantt-

Chart area

o The following shows the Gantt-Chart before and after the Baseline:

Page 183: Introducing Microsoft Project 2007

181

181

Page 184: Introducing Microsoft Project 2007

182

182

Page 185: Introducing Microsoft Project 2007

183

183

2. Tracking Progress:

o Click “View/Table/Tracking”, the Tracking Table displays:

Page 186: Introducing Microsoft Project 2007

184

184

Page 187: Introducing Microsoft Project 2007

185

185

Updating Tasks to Reflect Actual Information: o Record Actual Information for the Project by filling in the

following fields for each Task that tracks the Progress of the Project (Actual Data from the Site):

ID

Task Name Dur AS AF PCT

1

Start 0 1/1/2010 1/1/2010

2 FormWork for Columns

7 4/1/2010 11/1/2010

3 RFT for Columns

4 8/1/2010 12/1/2010

4 Cast-in-Place Concrete for Columns

3 13/1/2010 16/1/2010

5 Curing Time for Columns

5 19/1/2010 25/1/2010

6 FormWork for Slab & Stairs

11 24/1/2010 10/2/2010

7 RFT for Slab & Stairs

7 30/1/2010 … 80.0

o Notice the AF of Task of ID=6; the Act Dur becomes 14

days instead of 11 days…..

Page 188: Introducing Microsoft Project 2007

186

186

Page 189: Introducing Microsoft Project 2007

187

187

3. Status Date: You can find the Project’s Status Date (Data Date) in the “Project

Information” dialog box. If the Status Date is not set, Project uses the Current Date.

Page 190: Introducing Microsoft Project 2007

188

188

4. Reviewing Progress & Progress Line

a. Progress Line:

Click “Tools/Tracking/Progress Lines…”

Page 191: Introducing Microsoft Project 2007

189

189

Page 192: Introducing Microsoft Project 2007

190

190

5. Reschedule Uncompleted Work (F9 in P3e):

a. Click “Tools/Tracking/Update Project…”

b. Fill in the above window as shown above. That is, choose the option shown. Note that “11 feb” was the Status Date (Data Date --- Date of calculation for remaining tasks…)

c. Press OK. d. Now, notice the new Finish Date from the “Project

Information” as shown:

e. Notice that the Project delays 6 days. Before Updating, it was 2 September.

Page 193: Introducing Microsoft Project 2007

191

191

6. Reviewing Progress:

This phase needs to create the following:

1. Group, 2. Filter, 3. View including Screen, Table, Group, and Filter

7. Group: Click “Project/Group by/More Groups…/New…”, the following

window appears:

Fill in as shown above. Then, Click OK & Apply to check if it works.

Page 194: Introducing Microsoft Project 2007

192

192

Page 195: Introducing Microsoft Project 2007

193

193

8. Filter: Create a Dynamic Filter as follows:

o Click “Project/Filtered for/More Filters…/New…” o Name: Case_2 Dynamic Filter o Low Value <= Early Start <= High Value o Check “Show in menu” o Click OK & Apply:

Press OK & Apply, the following window appears

Page 196: Introducing Microsoft Project 2007

194

194

Fill in ,for example, as follows:

Press OK, another window appears for “High Value”. Fill it as

follows:

The following window appears. Notice the “Indicator”. The symbol

“√” appears for Completed Tasks:

Page 197: Introducing Microsoft Project 2007

195

195

Page 198: Introducing Microsoft Project 2007

196

196

9. Views:

Beside the Predefined Views discussed earlier, you can customize

your Views by clicking “View/More View…/New”.

Page 199: Introducing Microsoft Project 2007

197

197

10. Reporting on Project’s Progress:

Refer to Chapter 13, Microsoft Office Project 2007, Elaine Marmel, Reference No 2.

Page 200: Introducing Microsoft Project 2007

198

198

Coordinating Multiple Projects &

Sharing Resources Among Projects Example: Create a Project “S1”:

ID Task D Pred. 1 A1 5 2 A2 3 A1 3 A3 7 A2

Create a Project “S2”:

ID Task D Pred. 1 B1 5 2 B2 3 B1 3 B3 7 B2

Create a Project “S3”:

ID Task D Pred. 1 C1 5 2 C2 3 C1 3 C3 7 C2

Page 201: Introducing Microsoft Project 2007

199

199

Linking Tasks Across Projects:

To create a link between Tasks in different Projects, type the Project Name, a backslash, and then the Predecessor ID Number. For example: c:\MyProject.mmp\10. If the Predecessor Information is too long, use the “Task Information” dialog box.

o Now, open the 3 Projects at the same time to see the Task IDs

with their updating WBS Codes o Press “Window/Arrange All” o Double-click B1. Its predecessor will be: S1\1 [or S1.mmp\1]

(1 means ID of Task A1 or A1’s WBS Code).

o Double-click C1. Its predecessor will be: S2\1 (1 means ID of Task B1 or B1’s new WBS Code).

o Notice the dummy Activities due to relationships between

subprojects:

Page 202: Introducing Microsoft Project 2007

200

200

Page 203: Introducing Microsoft Project 2007

201

201

Create Resource Pool Project named RP.mmp o “View/Resource Sheet” o Enter the following Resources:

Resource Max. Units Rate Plumber 3 200/day Carpenter 5 150/day

Resource Sharing :

o Open S1.mmp & RP.mmp o With S1 Active:

“Tools/Resource Sharing/Share Resources…”, the “Share Resources” window appears.

Choose “Use resources From: RP” as shown. Press OK

o Close S1 and Open S2 and repeat Resource Sharing. o Close S2 and Open S3 and repeat Resource Sharing.

Hint: in the same manner, you can share resources between all Projects.

Page 204: Introducing Microsoft Project 2007

202

202

Create a Main Project called “Main.mmp”: o Insert the 3 Projects. o Assign Resources to different Tasks . . .

o Notice the “Over-Allocation” of Resources . . .

Page 205: Introducing Microsoft Project 2007

203

203

References

1. CHELTENHAM Courseware

Microsoft Project 2007 Manual – Foundation Level USA / Canada Email: [email protected] Web: www.cheltenhamcourseware.com

2. Elaine Marmel, Microsoft Office Project 2007 Bible_Hendoone

3. Abdalla ElDaoushy, Projects Time Management & Controlling using Project Management Software, Memo No (971), Institute of National Planning, Cairo, Egypt

4. Abdalla ElDaoushy, Projects Cost Management (Computer Software Oriented), Memo No (973), Institute of National Planning, Cairo, Egypt