INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management
13

INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

Mar 27, 2015

Download

Documents

Audrey Ruiz
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Clive Brown, Project Leader, Edinburgh

Optimal Planning Through Implementation of

Mobility Management

Page 2: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Marketing of Transport Initiatives

Page 3: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Marketing Measures Required

• Preparation of a Marketing Plan.

• Design and production of publicity material, targeted at employees (at major employers), about public transport improvements.

• Personalised Travel Assistance programme for at least 400 staff, from at least two employers.

Page 4: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Marketing Measures Applied

• Publicity and Information.

General: in the form of posters and postcards.

Specific: Edinburgh Park Cycling leaflet.• Project website.

Launched in November 2005. • Newsletters.

Three distributed, in electronic and hard copy formats over the project lifetime.

Page 5: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Marketing Measures Applied

• Personalised Travel Assistance (PTA)

Provided to a total of 590 staff at:

Royal Bank of Scotland, July 2005. Fort Kinnaird Retail Park, April 2006 and Telford College, August 2006. ”Travel Clinics” in Edinburgh Park offices.

• Personalised Journey PlanningManual and automated techniques used.

Page 6: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Final Monitoring

• Surveys Distributed: 15,800.

• Surveys Returned: 1,762.

• Response Rate: 11%.

Page 7: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Page 8: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

Localised Changes

• Walking: 1% increase at the Western General and Telford College.

• Cycling: 2% increase at the Royal Infirmary of Edinburgh, 3% at the Western General and 3% at Telford College.

• Bus: 10% increase at Fort Kinnaird and 3% at the Royal Infirmary of Edinburgh.

• Rail: 3% increase at Edinburgh Park and 2% at the Western General Hospital. 

Page 9: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

• Car: slight declines (2 - 3%) at both hospitals.

Page 10: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

What has been learned?

• Less specific approach to trip types seems to achieve more e.g. in Darlington.

• Project was about the behaviour of people, who can have non – linear reactions.

• Edinburgh is not alone.

• Council people benefit from involvement.

Page 11: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

What remains unanswered?

• Would a longer project have allowed a modal shift to public transport to be eventually detected?

• Why did people have their non – linear reactions?

Page 12: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.

For further further information on this project and our ”Cookbook” of mobility management measures, please see:

www.optimum2.org

Page 13: INTERREG III B Optimum2 Project. Clive Brown, Project Leader, Edinburgh Optimal Planning Through Implementation of Mobility Management.

INTERREG III B Optimum2 Project.