Interim Great Artesian Basin Infrastructure Investment Program Client Guidelines DNRME issues this addendum to the Interim Great Artesian Basin Infrastructure Investment Program Client Guidelines (guidelines), first published on 27 February 2018. Section 15 of the guidelines states: “The department may at any time issue an addenda to or vary these guidelines in writing”. 1. Final Date for Funding Submissions This addendum changes the final date for funding submissions. Under Section 4.2 of the guideline: “Submissions for funding will be received up until 5.00 pm AEST on 29 March 2018.” changes to “Submissions for funding will be received up until 5.00 pm AEST on 30 April 2018”. 2. Eligible Activities and Expenses This addendum changes the eligible activities relating to transport, unloading, movement, and storage of materials. Under Section 2.3 of the guideline: Bore rehabilitation Controlled watering system Activities eligible • Flow meter/pressure monitoring device (mandatory, see section 10) • Pre-works bore flow testing • Geophysical log • Drilling works by Class 3 drilling contractor • Materials (e.g. muds, casing, headworks etc.) • Applicant administration (e.g. solicitor, accountant, applicant management, contractor management, associated fees etc.) • Hydrogeological assessment • Construction materials required to build a pad for drilling contractor, e.g. gravel. Labour not included • Telemetry infrastructure • Flow meter/pressure monitoring device (mandatory, see section 10) • Pre-works bore flow testing • Engineer costs for design of controlled watering system and RPEQ certification • Materials (e.g. tanks, troughs, pipe etc.) • Applicant administration (e.g. solicitor, accountant, applicant management, contractor management, associated fees etc.) • Self-installation costs for the controlled watering system e.g. pipe laying, tank and trough hook-ups • Provision of electricity to pump infrastructure • Telemetry infrastructure Addendum 01 to the Interim Great Artesian Basin Infrastructure Investment Program Client Guidelines
23
Embed
Interim Great Artesian Basin Infrastructure Investment ... · Water efficiency programs in the Queensland section of the Great Artesian Basin Six water efficiency programs have been
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Interim Great Artesian Basin Infrastructure Investment Program Client Guidelines
DNR
Gui
Sec
in w
1.
This
“Su
cha
“Su
2.
This
Und
s
Addendum 01 to the Interim Great Artesian Basin Infrastructure Investment Program Client Guideline
ME issues this addendum to the Interim Great Artesian Basin Infrastructure Investment Program Client
delines (guidelines), first published on 27 February 2018.
tion 15 of the guidelines states: “The department may at any time issue an addenda to or vary these guidelines
riting”.
Final Date for Funding Submissions
addendum changes the final date for funding submissions. Under Section 4.2 of the guideline:
bmissions for funding will be received up until 5.00 pm AEST on 29 March 2018.”
nges to
bmissions for funding will be received up until 5.00 pm AEST on 30 April 2018”.
Eligible Activities and Expenses
addendum changes the eligible activities relating to transport, unloading, movement, and storage of materials.
er Section 2.3 of the guideline:
Bore rehabilitation Controlled watering system
Activitieseligible
• Flow meter/pressure monitoring device (mandatory, see section 10)
1 What is the IGABIIP The Interim Great Artesian Basin Infrastructure Investment Program (IGABIIP) supports the delivery of
strategic investments in groundwater infrastructure renewal and related activities to improve sustainable
management of Great Artesian Basin groundwater resources. The Department of Natural Resources, Mines
and Energy (department) delivers the IGABIIP, to which the Queensland and Australian governments
contribute equal funding.
The IGABIIP will recover water and maintain water pressure within the Great Artesian Basin, and deliver the
following outputs:
a) replacement of old bores legally operating in an uncontrolled state with controlled bores and
efficient controlled watering systems; and
b) restoration of critical infrastructure assets.
There has been a long history of successful water efficiency programs in the Queensland section of the Great
Artesian Basin. These programs have seen targeted financial assistance provided to eligible bore owners.
This investment is starting to address pressure decline, however more work is needed.
Water efficiency programs in the Queensland section of the Great Artesian Basin
Six water efficiency programs have been run since 1989.
More than 1000 projects have been completed.
These projects represent over:
• 700 uncontrolled bores rehabilitated
• 14,318 km of bore drains replaced with controlled watering systems • 207,205 ML/year water savings (estimate).
Projects
Examples of water efficiency measures previously approved for funding include:
• rehabilitation of legally operating uncontrolled flowing bores
• replacement of legally operating open bore drains with controlled watering systems
• rehabilitation of bores previously rehabilitated under earlier programs where there has been a critical infrastructure failure.
2 Eligibility The criteria to be eligible to apply for IGABIIP funding are as follows.
2.1 Applicants Applicants meeting all of the following criteria are eligible to apply for funding for reimbursement for eligible
works under the IGABIIP:
• owners of legally operating bores in Queensland within the Great Artesian Basin
• able to enter into a legal agreement with the Queensland Government
4
• are responsible to ensure agreement, including a legally binding arrangement if necessary, between the
users of that infrastructure for protection of its continued use by all affected parties upon completion of
the works (where the proposed works will affect or have an impact on any shared water infrastructure)
• able to enter into a contract with a Class 3 driller and other suppliers of materials and works
• able to oversee and implement the project in accordance with State and national laws and standards
(including health and safety and any applicable building codes).
2.2 Projects The water efficiency projects eligible under the IGABIIP are:
Project Eligibility Criteria
Rehabilitation or replacement of old bores legally operating in an uncontrolled state (particularly where such works will maintain or improve the flow of water to high value Great Artesian Basin-dependent springs)
• the bore is uncontrolled, located in Queensland, and taps the Great Artesian Basin (Figure 1), and; o was drilled in or before 1954; or, o has steel production casing and is located in a
designated corrosive area
Replacement of bore drains with controlled watering systems (piping)
• the bore drain is legal, in use, and taps the Great Artesian Basin.
Critical infrastructure failure • rehabilitation or replacement of a bore previously rehabilitated under earlier programs, which has had a critical infrastructure failure due to the impact of highly corrosive areas or a generic failure of technology.
• poor workmanship, lack of maintenance, or bore maintenance costs are not classed as a critical infrastructure failure.
Definitions
Uncontrolled: The total flow from the bore cannot be shut off fully by a gate valve/s, without water leakage at the surface.
1954: In 1954 a report titled ‘Artesian Water Supplies in Queensland’ investigated certain aspects relating to the Great Artesian Basin (Queensland portion). The report led to improved bore construction requirements in Queensland from 1954.
Designated corrosive area: Department-designated areas in which production casing must be manufactured of inert materials. Mild steel casing cannot be used for production casing in these areas.
5
Figure 1. Great Artesian Basin
Eromanga
Basin
Mulgildie
Basin
Clarence-Moreton
Basin
SuratBasin
Carpentaria
Basin
CANBERRA
BRISBANE
MELBOURNE
SYDNEY
ADELAIDE
Cairns
Mackay
Townsville
EmeraldRockhampton
Nambour
Bundaberg
Roma
Goondiwindi
Winton
Longreach
Mt Isa
Boulia
Charleville
Eromanga
Cunnamulla
Birdsville
Normanton
ChartersTowersHughenden
Bauhinia
Capital city
Legend
GAB sedimentary basins
GAB eligible basins
Major town
0 200 400 600100
Kilometres
6
2.3 Activities and expenses The government will contribute to the activities that are wholly, exclusively and necessarily incurred to meet
the project objective. The following table demonstrates eligible and ineligible activities. The department will
exercise its discretion in determining whether any particular activities are reasonable, seek clarification
where needed and set limits on what may be claimed for each activity. Where the applicant wishes to claim
expenses for an activity not listed below, prior approval must be obtained from the department.
Bore rehabilitation Controlled watering system
Activitieseligible
• Flow meter/pressure monitoring device (mandatory, see section 10)
• Self-installation costs for the controlled watering system e.g. pipe laying, tank and trough hook-ups
• Provision of electricity to pump infrastructure
• Telemetry infrastructure
Activities not eligible
• Deepening the bore asset or redrilling a replacement bore beyond the department’s recorded total depth and the associated materials
• Stand-down rates by the driller
• Transport, unloading, movement, and storage of materials
• Meals and accommodation of contractors
• Clearing of tracks and pads
• Work completed on the bore to bring it up to the minimum requirements of the bore construction standards
• Transport, unloading, movement, and storage of materials
• Meals and accommodation of contractors
• Decommissioning of the replaced bore drain
• Clearing of tracks and pads
• Materials and associated installation expenses that are in excess of what is required to replace the existing bore drain
3 Funding Funding is available for the rehabilitation of eligible bores and replacement of bore drains with efficient
controlled watering systems. Applicants must identify a commitment of at least 10 per cent of the estimated
total project cost. See section 5 for more information on value for money.
7
4 How to apply Participation in the IGABIIP is voluntary. Applicants should obtain independent advice to make a well-
informed decision about their submission. Prior to applying, it is recommended applicants should:
• contact the department for information and guidance on project implementation
• contact the department for information and guidance on proposal development if required
• where the works proposed to be undertaken by the applicant affects or impacts on shared water
infrastructure, consult with third parties with an interest in the shared water infrastructure for the
purposes of:
o entering into a water agreement if necessary, if the application is approved,
o discussing the impact of the proposed works on the shared water infrastructure
• seek advice from rural water engineering specialists, legal, business and financial advisors.
Department contact details are provided at section 16.
4.1 Completing the submission form Only applicants who meet the eligibly criteria in section 2 should apply for funding by completing the
submission form. If you have any queries with respect to eligibility contact the department (see section 16)
prior to completing the form. Applicants must answer the questions on the submission form sufficiently to
allow a full assessment of the submission. Incomplete submissions may be accepted at the discretion of the
department.
For more information on preparing a complete and competitive submission, refer to project assessment
criteria in section 5.
4.1.1 Bore rehabilitation submission The submission must include a bore rehabilitation proposal which is certified by a Class 3 driller. The driller is
certifying that the proposed work and materials meet the requirements of the ‘Minimum standards for the
construction and reconditioning of water bores that intersect the sediments of artesian basins in
Queensland’. A copy of the standard can be found at:
• works meet the ‘Minimum standards for the construction and reconditioning of water bores that
intersect the sediments of artesian basins in Queensland’.
Upon completion of controlled watering system works, the RPEQ is required to certify in the Disbursement
Form that the:
• controlled watering system has been inspected,
• controlled watering system has been designed and is constructed in accordance with the
department’s Installation Guidelines, otherwise an alternative industry standard is to be specified,
• materials used have a 50 year design life, excluding tanks and troughing, and
• tanks and troughs used have a 20 year design life.
Note, the controlled water system and rehabilitation works compliance certificate in the Disbursement Form
(see section 11), must be certified by the respective RPEQ or Class 3 driller identified in the executed works
agreement. Payment can only be made to the applicant if the approved RPEQ or Class 3 driller certifies their
respective statements.
It is a requirement for all projects to install either a water meter or pressure-monitoring device. The
applicant must certify in the Disbursement Form, that the installed water meter is pattern approved (by the
manufacture or supplier) in accordance with requirements of the National Measurement Institute, and
installed and operated in accordance with ATS 4747 of the Standards Australia.
The department reserves the right to inspect works at any reasonable time and may undertake compliance
monitoring activities. These activities will include site inspections and observation of drilling works by
departmental officers. The applicant must provide property access to the department for these activities
(see section 8). The department will provide the applicant with reasonable notice.
While the provision of a geophysical log at the completion of works is not a requirement for the government
funding to be disbursed, it is highly recommended that one be undertaken. The geophysical log and
associated report will confirm to the applicant that contractual obligations have been met, including
compliance with the ‘Minimum standards for the construction and reconditioning of water bores that
intersect the sediments of artesian basins in Queensland’.
11 Disbursement Disbursement of the government funding under the works agreement will only take place if:
• all work identified in the works agreement has been completed to the satisfaction of the
department;
• all work has been completed by the approved date; and
• the Disbursement Form and other documents are submitted, complete and certified (see section
10).
Disbursement of the government funding will be made in one payment on completion of the project and
only to the applicant. The department will not distribute funding between multiple landowners, even where
the works affect shared infrastructure. The interested parties must make their own arrangements with
respect to the application of funds by the applicant towards works affecting any shared infrastructure.
Prior to the government contributing to any expenses associated with a project, the applicant must provide
the following information to the department.
15
Activity Works Evidence
Rehabilitation works
Controlled watering system works
Geophysical log ☑ copy of tax invoice issued by the contractor to the applicant for the geophysical logging
Pre-work bore flow testing
☑ ☑ copy of tax invoice by the bore flow testing contractor to the applicant, for the pre-work flow testing of the bore
Drilling works ☑ copy of tax invoice issued by the Class 3 drilling contractor to the applicant for the rehabilitation work completed on the bore. The tax invoice must:
• itemise all works performed to easily distinguish if works were undertaken to extend (deepen) the bore asset. Works associated with extending (deepening) the bore asset are not included in the works agreement and the department will not contribute to these works. These works must be itemised separately
• not include stand-down rates by the driller. The department will not contribute to any stand down rates and will only contribute to actual works undertaken
copy of all cementing report/s
copy of a bore completion report
photographs of the decommissioned and new bore
Engineering design & RPEQ certification
☑ copy of tax invoice issued by the RPEQ to the applicant for controlled watering system design, and RPEQ certification
Materials ☑ ☑ copy of tax invoices for the materials (e.g. casing, muds, headworks) used by the drilling contractor:
• tax invoices itemise all materials to easily distinguished if materials extend the bore asset or not (e.g. unit metres of casing). The department will not contribute to materials which extend (deepen) the bore asset; or
• copy of tax invoices for the materials (e.g. pipe, tanks, troughs) used in the controlled watering system
Installation of controlled water system
☑ where the bore did not meet the minimum construction standards, provision of a copy of all cementing reports, a bore completion report, and photographs demonstrating the work completed to bring the bore up to the department’s minimum construction standards
16
Activity Works Evidence
certification by RPEQ that the controlled watering system has been constructed in accordance with
the original submission to the department
photographs of the decommissioned bore drain. The bore drain must be shut down permanently at completion of works
for self-installation – installation expenses will be capped at $1,100/km including GST of bore drain
replaced; or
for contractor installation – copy tax invoice issued by the contractor to the applicant
Power connection ☑ ☑ copy of tax invoices from energy supplier and licenced electrician to applicant, including a map with proposed location of power infrastructure
copy of approval from the energy supplier
Water meter or pressure monitoring device
☑
☑
copy of tax invoice issued by the supplier to applicant, including a photograph of either device fitted to the bore head
Administration costs by the applicant
☑ ☑ the maximum project administration expense claimable is the lesser of 5 per cent of the total project cost and $5,500 including GST
Hydrogeological assessment
☑ copy of tax invoice issued by consultant to applicant
Telemetry infrastructure
☑ ☑ copy of tax invoice issued by the supplier to applicant
The final payment may be adjusted pro-rata according to the actual amount of works completed or expenses
incurred. The total amount of funds paid for any project will not exceed the approved government funding
identified in the works agreement.
12 Other considerations
12.1 Winter bore drain length The winter bore drain must be surveyed and attached to the submission. The winter bore drain is measured
to the furthest point which water will travel down the delved network of bore drain in winter. A handheld
GPS is normally sufficient for this task.
Only one bore and associated bore drain can be referenced in a submission. In instances where multiple
bores discharge into a bore drain, the applicant must ensure that the drain length is counted only once in all
submissions. To demonstrate this, the applicant must describe the total length of the bore drain and
apportion this length between submissions. Each submission must show the bore drain apportionment, see
Figure 3.
17
Figure 3 Winter bore drain distributed between submissions
12.2 Stock routes The department will provide notice of any stock route water requirement at the time of the department
certification. The Stock Routes section’s contact details will be provided to the applicant to begin discussions
on stock route water facility requirements for integration in to the controlled watering system design.
Where a water point/s is required on the stock route, details of the government funding disbursement
arrangement for the stock route must be specified in the submission.
12.3 Aboriginal Cultural Heritage Act 2003 When planning and installing works, applicants must fulfil their obligations regarding cultural heritage under
Queensland legislation. More information can be found at:
The Queensland Government supports and encourages the dissemination and exchange of its information.
The copyright in this publication is licensed under a Creative Commons Attribution 4.0 International (CC BY
4.0) licence.
Under this licence you are free, without having to seek our permission, to use this publication in accordance
with the licence terms.
You must keep intact the copyright notice and attribute the State of Queensland as the source of the
publication.
Note: Some content in this publication may have different licence terms as indicated.
For more information on this licence, visit https://creativecommons.org/licenses/by/4.0/.
The information contained herein is subject to change without notice. The Queensland Government shall not be liable for technical or other errors or omissions contained herein. The reader/user accepts all risks and responsibility for losses, damages, costs and other consequences resulting directly or indirectly from using this information.