INVITED PAPER Integration Issues of Distributed Generation in Distribution Grids This paper considers the probable operating problems and challenges in connecting distributed generation to low- and medium-voltage electric power grids. By Edward J. Coster, Student Member IEEE , Johanna M. A. Myrzik , Bas Kruimer, Member IEEE , and Wil L. Kling, Member IEEE ABSTRACT | In today’s distribution grids the number of distributed generation (DG) units is increasing rapidly. Com- bined heat and power (CHP) plants and wind turbines are most often installed. Integration of these DG units into the distribu- tion grid leads to planning as well as operational challenges. Based on the experience of a Dutch distribution system ope- rators (DSO), this paper addresses several possibilities to handle grid planning issues. Effects on voltage control, grid protection, and fault levels are investigated and described. These aspects are illustrated with the aid of simulations on an existing distribution grid. It is demonstrated that in compact distribution grids voltage control problems and blinding of protection are not likely to occur and that false tripping and fault level have to be considered carefully. KEYWORDS | Distributed generation (DG); distribution grids; grid planning; protection; voltage control I. INTRODUCTION The nature of today’s distribution grids is changing from passive to active. The penetration level of distributed generation units (DG units) is increasing and it is expected that this growth will continue over the next years. At the moment not only the number of DG units is increasing, but also, in specific areas, the size of the units. In this way, in the near future, the DG may contribute in a substantial part of the power generation. DG technologies can be categorized in renewable and nonrenewable [1]. Examples of renewable technologies are, e.g., solar, wind, and geothermal, while examples of nonrenewable technologies are internal combustion en- gines, microturbines, and fuel cells. Two most popular and widely used DG schemes are: • wind turbines; • combined heat and power (CHP) plants. Currently, wind turbines have a large share in the generation of electricity by DG units. Originally, small wind turbines were connected to low-voltage networks. Wind turbines increased in size and therefore in gener- ating power and have also been clustered in groups, thus making it necessary to connect to medium-voltage (MV) and even high-voltage (HV) grids. CHP plants are most often used to generate heat, with the generation of electricity as an important side product. These types of DG units are mostly installed in industrial environments, where the heat is used in the production processes and the generated electricity is either used for own consumption or sold to the market. Small CHP plants are also used for district heating. In The Netherlands local authorities have designated specific areas for the development of greenhouses. Each greenhouse may contain a CHP plant with a capacity in the range of 1–3 megavoltsampere (MVA) and thus to be connected to the local MV grid. Due to the high density of greenhouses in such areas, the penetration level of CHP plants in the MV grid is very high. This can amount to a total generated power of 100 MW or even more, and with loads far less than the generation power. In Fig. 1, an overview of the development of the small CHP plants in The Netherlands during the past ten years is given. Due to financial stimuli, such as a subsidy for saved Manuscript received January 8, 2010; revised May 6, 2010; accepted May 12, 2010. Date of publication September 7, 2010; date of current version December 17, 2010. E. J. Coster is with Network Planning, STEDIN, Rotterdam 3015 EK, The Netherlands (e-mail: [email protected]). J. M. A. Myrzik and W. L. Kling are with the Electrical Power Systems, Eindhoven University of Technology, Eindhoven 5612 AZ, The Netherlands (e-mail: [email protected]; [email protected]). B. Kruimer is with Quanta Technology Europe, Rotterdam 3085 BW, The Netherlands (e-mail: [email protected]). Digital Object Identifier: 10.1109/JPROC.2010.2052776 28 Proceedings of the IEEE | Vol. 99, No. 1, January 2011 0018-9219/$26.00 Ó2010 IEEE
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
INV ITEDP A P E R
Integration Issues of DistributedGeneration in Distribution GridsThis paper considers the probable operating problems and challenges
in connecting distributed generation to low- and medium-voltage
electric power grids.
By Edward J. Coster, Student Member IEEE, Johanna M. A. Myrzik,
Bas Kruimer, Member IEEE, and Wil L. Kling, Member IEEE
ABSTRACT | In today’s distribution grids the number of
distributed generation (DG) units is increasing rapidly. Com-
bined heat and power (CHP) plants and wind turbines are most
often installed. Integration of these DG units into the distribu-
tion grid leads to planning as well as operational challenges.
Based on the experience of a Dutch distribution system ope-
rators (DSO), this paper addresses several possibilities to
handle grid planning issues. Effects on voltage control, grid
protection, and fault levels are investigated and described.
These aspects are illustrated with the aid of simulations on an
existing distribution grid. It is demonstrated that in compact
distribution grids voltage control problems and blinding of
protection are not likely to occur and that false tripping and
fault level have to be considered carefully.
KEYWORDS | Distributed generation (DG); distribution grids;
grid planning; protection; voltage control
I . INTRODUCTION
The nature of today’s distribution grids is changing from
passive to active. The penetration level of distributed
generation units (DG units) is increasing and it is expected
that this growth will continue over the next years. At the
moment not only the number of DG units is increasing, butalso, in specific areas, the size of the units. In this way, in
the near future, the DG may contribute in a substantialpart of the power generation.
DG technologies can be categorized in renewable and
nonrenewable [1]. Examples of renewable technologies
are, e.g., solar, wind, and geothermal, while examples of
nonrenewable technologies are internal combustion en-
gines, microturbines, and fuel cells. Two most popular and
widely used DG schemes are:
• wind turbines;• combined heat and power (CHP) plants.
Currently, wind turbines have a large share in the
generation of electricity by DG units. Originally, small
wind turbines were connected to low-voltage networks.
Wind turbines increased in size and therefore in gener-
ating power and have also been clustered in groups, thus
making it necessary to connect to medium-voltage (MV)
and even high-voltage (HV) grids.CHP plants are most often used to generate heat, with
the generation of electricity as an important side product.
These types of DG units are mostly installed in industrial
environments, where the heat is used in the production
processes and the generated electricity is either used for
own consumption or sold to the market. Small CHP plants
are also used for district heating.
In The Netherlands local authorities have designatedspecific areas for the development of greenhouses. Each
greenhouse may contain a CHP plant with a capacity in the
range of 1–3 megavoltsampere (MVA) and thus to be
connected to the local MV grid. Due to the high density of
greenhouses in such areas, the penetration level of CHP
plants in the MV grid is very high. This can amount to a
total generated power of 100 MW or even more, and with
loads far less than the generation power.In Fig. 1, an overview of the development of the small
CHP plants in The Netherlands during the past ten years is
given. Due to financial stimuli, such as a subsidy for saved
Manuscript received January 8, 2010; revised May 6, 2010; accepted May 12, 2010. Date
of publication September 7, 2010; date of current version December 17, 2010.
E. J. Coster is with Network Planning, STEDIN, Rotterdam 3015 EK, The Netherlands
tection can solve the problem [15]. However, directionalprotection is slower, more expensive, and usually not a
standard solution for grid operators.
Trying to solve blinding of protection may introduce
false tripping. This example is discussed in [22] in which
a small wind farm is connected to a weak existing net-
work causing blinding of protection. This is solved by
reducing the pickup current but it causes false tripping
for faults in some specific locations. The proposed solu-tion is to install protection devices with an additional
time delay giving the feeder as well as the wind farm a
longer fault clearing time.
VII. GRID SIMULATIONS
In this section, the simulation results of an existing Dutch
distribution grid including a DG is discussed. The grid is
located in a greenhouse area and has 21 CHP plants
equipped with synchronous generators connected. A single
line diagram of the grid as well as the network data aregiven in Fig. 15 and Tables 3–7. The 10-kV distribution grid
is connected via three transformers to the 25-kV sub-
transmission grid. The 10-kV substation consists of three
sections coupled via coupling breakers and eight feeders
connecting the 21 DGs. Each feeder is equipped with a
definite-time overcurrent protection set to 1650A-0.4 s.
The test system is used to investigate in what ways the
CHP plants affect voltage control, grid protection, andfault level.
A. Voltage ControlTo study the effect of the CHP plants on the voltage
profile of the feeders, Bfeeder 8[ is taken as an example.
Based on stationary power flow calculations, the voltage
profiles of Bfeeder 8[ are determined for the cases includ-
ing and excluding CHP plants, and are depicted in Fig. 11.
In this area, the distribution grid is dominantly loaded
with CHP plants and the connected load is limited. Hence,
the voltage drop along the feeder excluding the CHP plants
is also limited. An important factor herein is the relativelyshort feeder length and the low cable impedance. As is
expected, a voltage rise occurs when the CHP plants are
connected. However, due to the mentioned factors, this
voltage rise is modest and does not exceed the maximum
allowable voltage deviation of �10%. It can be concluded
that in this distribution grid connection of CHP plants does
not lead to unacceptable voltage profiles.
B. Grid ProtectionAs discussed in Section VI, false tripping and blinding
of protection are mechanisms which are independent of
the type of feeder (cable or overhead line). To determine if
false tripping occurs, the contributions of the CHP plantsper feeder have to be known. The feeder contributions are
highest during a three-phase fault at the busbar. When the
feeder contributions do not exceed the protection pickup
current, then false tripping will not occur. Fig. 12 gives an
overview of the contribution to the faulted busbar per
feeder as well as the pickup current of the overcurrent
protection.
In six feeders, the feeder contribution exceeds thepickup current of the overcurrent protection and false
tripping can occur. However, the clearing time of the
overcurrent protections is 0.4 s and all CHP plants are
equipped with an undervoltage protection clearing the
CHP plants within 100–200 ms. After disconnection of a
CHP plant, the specific feeder contribution drops below
the pickup current and all relays reset. In this way, false
tripping is prevented, however it is dependent on the CHP
Fig. 11. Voltage profile along ‘‘feeder 8’’ including and excluding
CHP plants.
Fig. 12. Overview of feeder contributions to a three-phase
busbar fault.
Coster et al. : Integration Issues of Distributed Generation in Distribution Grids
Vol. 99, No. 1, January 2011 | Proceedings of the IEEE 35
plant undervoltage protection. To achieve independence of
the CHP plants, the overprotection pickup current needs
to be increased in such a way that the worst case fault can
be still detected. Due to the high fault level, it is possible tofind a suitable setting which fulfills both requirements. In
weaker systems, the overcurrent protections have to be
equipped with the directional protections.
Blinding of protection is studied using feeders 1 and
8 by illustrating the effect of the connected CHP plants
on the grid contribution to the fault current. Along the
feeders, a short circuit is simulated which means that the
location of the fault is equidistant taken along the feeders.During the fault calculations, the grid contribution is
stored. Fig. 13 shows the grid contribution to the fault
current for the varying fault locations. It demonstrates that
the CHP plants do not affect the grid contribution when
the location of the fault in the feeders is between the
substation and the first CHP plant. The effect of the
contribution of the CHP plants becomes noticeable for
faults further along the feeder passed the first CHP plant.However, in this grid, the effect is modest and does not
lead to blinding of protection.
C. Fault LevelDuring the development of the greenhouse area, CHP
plants have been installed and connected to the local dis-
tribution grid, which prior to that time did not have any
local power generation but loads only. For the fault cur-
rent, there was only one source of supply and fault levels of
the main substation and the ring main units (RMUs) were
dimensioned to withstand the maximum fault current of
that single source. With integrated CHP plants additional
sources have been introduced leading to an increased faultlevel.
To study the effect of the CHP plants on the fault level,
short-circuit calculations are applied to the test system.
Disturbances are applied to the substation busbar and to
three feeder locations: RMU1, RMU2, and RMU3. The
10-kV substation fault level is 25 kA and for the RMUs it
is 14.5 kA. The results are shown in Fig. 14.
Normally, the substation is operated with closed
coupling breakers. The short-circuit calculations show
that the fault level of the main substation and RMUs are
exceeded. Operating the substation with open couplingbreakers reduces the fault level significantly.
In the region, other greenhouse areas are being dev-
eloped causing reduction of the fault level in an upstream
subtransmission substation. This also affects the fault level
of the test system. However, this is not sufficient to ope-
rate the substation with closed coupling breakers as indi-
cated in Fig. 14. Therefore, the grid needs to be operated
with open coupling breakers both in the local substation aswell as in the upstream subtransmission substation. So,
operational measures need to be taken to manage fault
levels because of the integration of CHP plants in the
distribution grid, which influences grid availability and
thus the customer reliability.
VIII . CONCLUSION
This paper deals with integration issues of DG units in
medium voltage grids. The significant increase of
integration of DG units in distribution grids can lead tomajor planning issues and conflicts with the legal and
regulatory framework. Some approaches to overcome
these planning issues are discussed. When integration of
DG units in the distribution grid also causes expansion of
the transmission grid, a prediction-based grid planning is
recommended.
There may be some operational challenges as well.
Major aspects which are influenced by the connection ofDG units are voltage control, grid protection, and fault
level. Simulating different scenarios in an existing distri-
bution grid with a significant number of CHP plants im-
plemented shows that voltage control problems in compact
distribution grids consisting of cables are not to be ex-
pected. It is also demonstrated that in such a grid the effect
of the CHP plants on the grid contribution to the fault
Fig. 13. Grid contribution including/excluding CHP plants as a
function of fault location.
Fig. 14. Effect of CHP plants on the fault level in the distribution grid.
Coster et al. : Integration Issues of Distributed Generation in Distribution Grids
36 Proceedings of the IEEE | Vol. 99, No. 1, January 2011
Fig. 15. Overview of the simulated distribution grid.
Table 3 Line Data of the Simulated Distribution Grid
Table 4 Generator Data of the Simulated Distribution Grid
Table 5 Cable Data
Table 6 Transformer Data
Coster et al. : Integration Issues of Distributed Generation in Distribution Grids
Vol. 99, No. 1, January 2011 | Proceedings of the IEEE 37
current is limited. Therefore, blinding of protection is not
likely. Because of the short feeder length, false tripping
can occur and has to be considered during the design of the
protection system. At specific locations in the grid, shortfeeder length also leads to exceeding the allowed fault
level. It is shown that fault level can be managed to stay
within the limits by operational measures. This is a cost-
effective way to control the fault level, however, these
measures do affect customer reliability which can be seenas a drawback. h
REF ERENCE S
[1] H. B. Puttgen, P. R. Macgregor, andF. C. Lambert, BDistributed generation:Semantic hype or the dawn of a new era,[IEEE Power Energy Mag., vol. 3, no. 1,pp. 22–29, Jan./Feb. 2003.
[2] R. C. Dugan, T. E. McDermott, and G. J. Ball,BPlanning for distributed generation,[ IEEEIndustry Appl. Mag., vol. 7, no. 2, pp. 80–88,Mar./Apr. 2001.
[3] R. C. Dugan and S. K. Price, BIncludingdistributed resources in distributionplanning,[ in Proc. IEEE PES Power Syst.Conf. Expo., 2004, pp. 1694–1698.
[4] E. J. Coster and D. van Houwelingen,BIntegration of DG in MV-grids: Challengesencountered by the grip operator,[ in Proc.CICRE/IEEE Joint Symp. Integr. Wide-ScaleRenewable Resources into the Power DeliverySyst., Calgary, AB, Canada, 2009.
[5] T. Ackermann and V. Knyazkin, BInteractionof distributed generation and the distributionnetwork: Operation aspects,[ in Proc. PEST&D Conf., Asia Pacific, 2002, vol. 2,pp. 1357–1362.
[6] J. Morren and S. W. H. de Haan, BImpactof distributed generation units with powerelectronic converters on distribution networkprotection,[ in Proc. IET 9th Conf. Develop.Power Syst. Protection, Glasgow, Scotland,2008, pp. 664–669.
[7] C. L. Masters, BVoltage rise the big issue whenconnecting embedded generation to long11 kV overhead lines,[ Power Eng. J., vol. 16,no. 1, pp. 5–12, Feb. 2002.
[8] R. O’ Gorman and M. A. Redfern, BVoltagecontrol problems on modern distribution
systems,[ in Proc. Power Eng. Soc. GeneralMeeting, 2004, vol. 1, pp. 662–667.
[9] N. Jenkins, R. Allen, P. Crossley, D. Kirchen,and G. Strbac, Embedded Generation,vol. 31, 1st ed. London, U.K.: IET, 2000,ser. Power & Energy.
[10] B. Fox, D. Flynn, L. Bryans, N. Jenkins,D. Milborrow, M. O’Malley, R. Watson, andO. Anaya-Lara, Wind Power integration,Connection and System Operational Aspects,vol. 50, 1st ed. London, U.K.: IET, 2007,ser. Power & Energy.
[11] J. H. R. Enslin and P. J. M. Heskes,BHarmonic interaction between largenumbers of Photovoltaic inverters and thedistribution network,[ IEEE Trans. PowerElectron., vol. 19, no. 6, pp. 1586–1593,Nov. 2004.
[12] P. M. J. Heskes, J. F. G. Cobben, andH. H. C. de Moor, BHarmonic distortionin residential areas due to large scalePV implementation is predicable,[J. Distrib. Energy Resources, pp. 17–32,vol. 1, no. 1, Jan.–Mar. 2005.
[13] P. M. J. Heskes, J. M. A. Myrzik, andW. L. Kling, BSurvey of harmonic reductiontechniques applicable as ancillary service ofdispersed generation,[ in Proc. IEEE YoungRes. Symp., Eindhoven, The Netherlands,Feb. 7–8, pp. 1–4.
[14] J. F. G. Cobben, BPower quality, implicationsat the point of connection,[ Ph.D. thesis,Dept. Electr. Eng., Univ. TechnologyEindhoven, Eindhoven, The Netherlands,2008.
[15] K. Kauhaniemi and L. Kumpulainen, BImpactof distributed generation on the protectionof distribution networks,[ in Proc. 8th IEE
Conf. Develop. Power Syst. Protection, 2004,pp. 315–318.
[16] L. K. Kumpulainen and K. T. Kauhaniemi,BAnalysis of the impact of distributedgeneration on automatic reclosing,[ inProc. IEEE Power Eng. Soc. Power Syst. Conf.Exhib., 2004, pp. 603–608.
[17] S. M. Brahma and A. A. Girgis,BDevelopment of adaptive protectionscheme for distribution systems with highpenetration of distributed generation,[IEEE Trans. Power Delivery, vol. 19, no. 1,pp. 56–63, Jan. 2004.
[18] S. M. Brahma and A. A. Girgis,BMicroprocessor-based reclosing tocoordinate fuse and recloser in a systemwith high penetration of distributedgeneration,[ in Proc. IEEE Power Eng. Soc.Winter Meeting, 2002, vol. 1, pp. 453–458.
[19] P. M. Anderson, Power System Protection.New York: IEEE, 1998.
[20] E. J. Coster, J. M. A. Myrzik, and W. L. Kling,BEffect of distributed generation on protectionof medium voltage cable grids,[ in Proc.CIRED 19th Int. Conf. Electricity Distrib.,2007, pp. 1–6.
[21] E. J. Coster, J. M. A. Myrzik, and W. L. Kling,BIntegration of distributed generation inmedium voltage gridsVProtection issues,[Int. J. Distrib. Energy Resources, vol. 5, no. 3,pp. 167–186, Jul. 2009.
[22] K. Maki, S. Repo, and P. Jarventausta, BEffectof wind power based distributed generationon protection of distribution networks,[ inProc. 8th IEE Int. Conf. Develop. Power Syst.Protection, 2004, vol. 1, pp. 327–330.
ABOUT THE AUT HORS
Edward J. Coster (Student Member, IEEE) was born in Leiden, The
Netherlands, in 1972. He received the B.Eng. degree in electrical engi-
neering from Technische Hogeschool Rijswijk (TH Rijswijk), Rijswijk, The
Netherlands, in 1997 and the M.Sc. degree in electrical engineering
from Delft University of Technology, Delft, The Netherlands, in 2000. In
April 2006, he joined part-time the Electrical Power System group,
Eindhoven University of Technology, Eindhoven, The Netherlands, to start
a Ph.D. research project.
Since 2000, he has been a Senior Specialist for Network Planning with
STEDIN, Rotterdam, The Netherlands. His fields of interest are: distrib-
uted generation, power system protection, dynamic behavior, and
stability of power systems.
Johanna M. A. Myrzik was born in Darmstadt, Germany, in 1966. She
received the M.Sc. degree in electrical engineering from Darmstadt
University of Technology, Darmstadt, Germany, in 1992 and the Ph.D.
degree in the field of solar inverter topologies from Kassel University,
Kassel, Germany, in 2000.
From 1993 to 1995, she was a Researcher at the Institute for Solar
Energy Supply Technology (ISET e.V.), Kassel, Germany. Since 2000, she
has been with the Eindhoven University of Technology, Eindhoven, The
Netherlands. In 2002, she became an Assistant Professor and in 2008 an
Associate Professor in the field of residential electrical infrastructures.
Her fields of interests are: power electronics, renewable energy,
distributed generation, and electrical power supply.
Table 7 Load Data
Coster et al. : Integration Issues of Distributed Generation in Distribution Grids
38 Proceedings of the IEEE | Vol. 99, No. 1, January 2011
Bas Kruimer (Member, IEEE) was born in Curaçao, The Netherlands
Antilles, in 1963. He studied power engineering at the Delft Technical
University, Delft, The Netherlands, graduating in 1988.
He worked for ABB in substation automation, protection, and network
control nationally and internationally. In 2002, he joined KEMA T&D
Consulting leading the design and engineering team. In 2006, he led the
Quality Management Systems business of KEMA Quality, and in early
2008, he joined the Infra company of Dutch Utility Eneco, today named
Joulz. In August 2010, he joined Quanta Technology, Rotterdam, The
Netherlands. During his professional years, he has contributed to Dutch
Cigre and to IEEE and has been an active player in the IEC 61850
developments for many years.
Wil L. Kling (Member, IEEE) was born in Heesch, The Netherlands, in
1950. He received the M.Sc. degree in electrical engineering from the
Technical University of Eindhoven, Eindhoven, The Netherlands, in 1978.
From 1978 to 1983, he worked with KEMA and from 1983 to 1998 with
Sep. Then, he was with TenneT, the Dutch Transmission System Operator,
as a Senior Engineer for Network Planning and Network Strategy. In 1993,
he joined the Delft University of Technology, Delft, The Netherlands, as a
part-time Professor, and in 2000, he joined the Electrical Power Systems
(EPS) group at the Eindhoven University of Technology, Eindhoven, The
Netherlands, as a part-time Professor, where at the end of 2008, he was
appointed a Full-Time Professor and Chair of the EPS group. He leads
research programs on distributed generation, integration of wind power,
network concepts, and reliability.
Mr. Kling is involved in scientific organizations such as Cigre and IEEE.
He is the Dutch representative in the Cigre Study Committee C6
Distribution Systems and Dispersed Generation.
Coster et al. : Integration Issues of Distributed Generation in Distribution Grids
Vol. 99, No. 1, January 2011 | Proceedings of the IEEE 39