1 Integrated transit corridor development and street network/connectivity plan for the corridor/influence zone along with details of all intersections and mid-sections based on traffic and feasibility studies for the corridor/network: Outer Ring Road from Modi Mill Flyover to IIT Gate Presentation to Working Group II-B, UTTIPEC
71

Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Jun 07, 2018

Download

Documents

vuonglien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

1

Integrated transit corridor development and street network/connectivity plan for the corridor/influence zone along with details of all intersections and mid-sections based on traffic

and feasibility studies for the corridor/network:

• Outer Ring Road from Modi Mill Flyover to IIT Gate

Presentation to Working Group II-B, UTTIPEC

Page 2: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 3: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

3

Key Map showing the Project Corridor

1-E (A)

Ring Road

OuterRing Road

Page 4: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

4

Project Corridor marked on Master Plan of Delhi- 2021

1-E (A)

Modi Mill(ROB-22) to IIT Gate

Page 5: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Project Corridor marked on Zonal Development plan

1-E (A)

Page 6: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

STUDY AREA CHARCTERISTICS ON GOOGLE MAP

1-E (B)

Modi Mill

Outer

Page 7: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

1-E (C)

LOCAL STREET NETWORK PLAN

Chirag DelhiIntersection

Malviya NagarIntersection

PanchsheelIntersection

IIT Intersection

Nehru PlaceIntersection

Modi Mill (ROB-22)

Savitri Cinema Intersection

Page 8: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

8

SURVEY BASE MAP

• EXISTING ROAD

• BUILDING FOOTPRINT

• ROAD LEVELS

• EXISTING BUS STOP

Sri A

uro

bin

do

Mar

g

Savitri Cinema Intersection

Chirag DelhiIntersection

Malviya NagarIntersection

PanchsheelIntersection

IIT Intersection

Nehru PlaceIntersection

Modi Mill flyoverModi Mill flyoverModi Mill flyoverModi Mill flyover

Nehru PlaceIntersectionNehru PlaceIntersectionNehru PlaceIntersection

Chirag DelhiIntersection

Nagar

Chirag DelhiIntersection

Malviya Nagar

Chirag DelhiIntersection

Nagar

Sri A

uro

bin

do

MalviyaIntersection

PanchsheelIntersection

IIT IIT IIT Intersection

MalviyaIntersectionMalviyaIntersectionSr

i Au

rob

ind

o

Intersection

Sri A

uro

bin

do

Intersection

C

D

A

2-E (A)

Page 9: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

9

TO IIT

TO OKHLA

Building Footprints

ROW-45mROW-45m

2-E (A)

Section -A

Page 10: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

10

Nehru PlaceIntersection

Building Footprints

ROW-45m

2-E (A)

Section -B

Page 11: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

11

Chirag Delhi Intersection

Savitri CinemaIntersection

Building Footprints

ROW-45m

2-E (A)

Section -C

Page 12: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

12

PanchsheelIntersection

Building FootprintsMalviyanagarIntersection

IITIntersection

ROW-45m

2-E (A)

Section -D

Page 13: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

PHOTO DOCUMENTATION

2-E (B)

Page 14: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

3-arm signalized intersection of Outer Ring Road and Captain Gaur Marg

3 arm signalized intersection with uni-directional flyover (Kalkaji Flyover)

Reduced width of carriageway due to Bhairon temple on LHS of Outer Ring Road

General view of 4 arm signalized intersection with 2-way flyover at Nehru Place

2-E (B)

Page 15: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Ongoing metro construction work at Chiragh Delhi Intersection

General View of Outer Ring Road near Panchsheel Intersection

Metro construction under progress near the toe of Panchsheel flyover

View showing IIT Gate

2-E (B)

Page 16: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

162-E (B)

Page 17: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

172-E (B)

Page 18: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

182-E (B)

Page 19: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

192-E (B)

Page 20: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

202-E (B)

Page 21: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

2-E (C)

Page 22: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

22

Pedestrian Survey Location

TVC Survey locations

OD Survey Locations

LEGEND

Key Plan showing Traffic Survey Locations

Savitri Cinema Intersection

Chirag DelhiIntersection

Malviya NagarIntersection

IIT Intersection

Nehru PlaceIntersection

Modi Mill flyover

KalkajiIntersection

2-E (C)

Page 23: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Traffic and Travel Characteristics

Page 24: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Traffic Volume characteristics at intersections during Base Year ( 2016 )

S.No Intersection

Peak Hour Traffic Volume

(in PCU)

Morning Evening

1Outer Ring Road – Aurobindo Marg Intersection (IIT Gate

Intersection) 19886 17936

2Outer Ring Road – Maharishi Dayanand Marg Intersection

(Panchsheel Intersection) 18090 16669

3Outer Ring Road – Josip Broz Tito Marg Intersection (Chirag

Delhi Intersection) 23211 24043

4Outer Ring Road – GK 2 Main Road Intersection (Savitri

Cinema Intersection) 15146 15748

5Outer Ring Road – Lala Lajpat Rai Road Intersection (Nehru

Place Intersection) 20169 16814

6Outer Ring Road – Ma Anandmayee Marg Intersection

(Kalkaji Mandir Intersection) 12814 16321

7Outer Ring Road – Captain Gaur Marg Intersection (Modi

Mill Intersection) 11466 127562-E (C)

Page 25: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

2524

Key Plan Showing Speed and Delay Nodes

Speed and Delay Nodes

Speed-Delay Survey Network2-E (C)

Page 26: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

NODES DISTANCE JOURNEY TIME IN

SECONDS

STOPPED DELAY WITH REASON

TIME EXCLUDING

DELAY

AVERAGE JOURNEY SPEED

RUNNING SPEED

FROM TO (m) (SECONDS) SECONDS (Km/h) (Km/h)

42 43 1130 280 25 Congestion 255 14.5 16.0

43 44 1050 124 35 Congestion 89 30.5 42.5

44 45 1071 110 26 Congestion 84 35.1 45.9

45 46 754 80 30Metro

Construction50 33.9 54.3

46 47 2293 190 21 Congestion 169 40.4 41.2

47 48 1100 140 22Congestion 118 28.3 33.6

7398 924 159 765 28.2 34.2

Speed and Delay characteristics along project corridor

Page 27: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

27

Traffic Zones delineated for the purpose of this study

2-E (C)

Page 28: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Desire line diagram for two wheelers in the study area

2-E (C)

Page 29: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Desire line diagram for four wheelers in the study area

65

2-E (C)

Page 30: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Desire line diagram for LCVs in the study area

662-E (C)

Page 31: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Desire line diagram for Trucks in the study area

2-E (C)

Page 32: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Peak hour Traffic Volumes on different sections for Base year (2016)

63

Volume (pcu) v/c

12599 1.67

Volume (pcu) v/c

13670 1.82

Volume(pcu) v/c

8409 1.12

Volume (pcu) v/c

11224 1.49

Volume (pcu) v/c

13365 1.78

Volume (pcu) v/c

15148 2.01

PANCHSHEEL INTERSECTION

CHIRAG DELHI

INTERSECTION

SAVITRI CINEMAINTERSECTION

NEHRU PLACE

INTERSECTION

KALKAJI INTERSECTION

MODI MILLINTERSECTION

2-E (C)

Page 33: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Volume (pcu) v/c

13575 1.81

Volume (pcu) v/c

14950 1.99

Volume(pcu) v/c

9196 1.22

Volume (pcu) v/c

12093 1.63

Volume (pcu) v/c

14400 1.92

Volume (pcu) v/c

16567 2.20

Peak hour Traffic Volumes on different sections for Design year (2036)

69

PANCHSHEEL INTERSECTION

CHIRAG DELHIINTERSECTION

SAVITRI CINEMAINTERSECTION

NEHRU PLACEINTERSECTION

KALKAJI INTERSECTION

MODI MILLINTERSECTION

2-E (C)

Page 34: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

34

Savitri Cinema Intersection

Chirag DelhiIntersection

Malviya NagarIntersection

PanchsheelIntersection

IIT Intersection

Nehru PlaceIntersection

3-E

Page 35: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

35

PROPOSED IMPROVEMENT OPTIONS

Page 36: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

36

COMPOSIT LAYOUT PLAN

Savitri Cinema Intersection

Malviya NagarIntersection

PanchsheelIntersection

IIT Intersection

Nehru PlaceIntersection

Kalkaji Mandir Intersection

Chirag Delhi Intersection

TO RK PURAM

TO OKHLA

Page 37: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Layout Plan for Ch 0.000 to Ch 1.000

Captain Gaur Marg Intersection

A

B

A

B

Proposed Underpass

Existing Flyover

Option-1

Page 38: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

D

D

Layout Plan for Ch 0.000 to Ch 1.000

Option-2

Page 39: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Captain Gaur Marg Intersection

F

F

Layout Plan for Ch 0.000 to Ch 1.000

Existing Flyover

Proposed Flyover

Option-3

Page 40: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

G

G

Layout Plan for Ch 0.000 to Ch 1.000

Existing Flyover

Proposed Flyover

Option-4

Captain Gaur Marg Intersection

Page 41: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 42: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 43: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 44: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 45: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 46: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 47: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 48: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 49: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 50: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO
Page 51: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

51

Page 52: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Ring Road from Bhairon Marg to DND Flyway

Bhairon Marg

DNDBarapullah ElevatedCorridor

PURANA

QUILA

Uni-Directional Flyover at NH-24 Bypass Intersection

Uni-Directional Flyover at Sarai Kale Khan Intersection

Barapullah Elevated Corridor over Ring Road

1.Length of Corridor: 5 Km2. No. of Intersections: 43. No. of Grade Separators: 3

Page 53: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Traffic and Travel Characteristics

Page 54: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Key Plan showing Traffic Survey Locations

LEGEND

Pedestrian Survey Location

TVC Survey locations

OD Survey Locations

Page 55: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

S.No Intersection

Peak Hour Traffic Volume

(in PCU)

Morning Evening

1 NH-24 Bypass and Ring Road Intersection 16730 22410

2 Ring Road – Bhairon Marg Intersection 16155 17810

3 Sarai Kale Khan Intersection 13374 16376

Peak Hour Traffic Volume at Intersections during Base Year ( 2016 )

Page 56: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Traffic Zones delineated for the study

DELHI(UT)BOUNDARY

ZONE BOUNDARY

25 ZONE NUMBER

ZONE CENTROID

Page 57: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Travel Desire Line diagram for 2-Wheelers in the study area

100-500 Veh Trips

501-1000 VehTrips

1001-1500 Veh Trips

Above 2000 VehTrips

Rohini

Noida

Faridabad

Gaziabad

Haryana, Punjab, J&K etc.

Shahdra

Gurgaon

Pitampura

Nehru Place

Laxmi Nagar

Greater-Noida

Khanpur

Dwarka

MeeraBagh

Page 58: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Travel Desire Line diagram for 4-Wheelers in the study area

100-500 Veh Trips

501-1000 VehTrips

1001-1500 Veh Trips

Above 2000 VehTrips

Rohini

Noida

Faridabad

Gaziabad

Haryana, Punjab, J&K etc.

Shahdra

Gurgaon

Pitampura

Dwarka

MeeraBagh

Greater-Noida

Khanpur

Page 59: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Bhairon Marg

3

1

2

Base Year (2016) Peak hour Traffic volume and V/C Ratio for different segments (Without Project)

Page 60: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Bhairon Marg

3

1

2

Base Year (2016) Peak hour Traffic volume and V/C Ratio for different segments (With Project)

Page 61: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Bhairon Marg

3

1

2

Design Year (2036) Peak hour Traffic volume and V/C Ratio for different segments(Without Project)

Page 62: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Bhairon Marg

3

1

2

Design Year (2036) Peak hour Traffic volume and V/C Ratio for different segments (With Project)

Page 63: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Ring Road

Sarai Kale Khan Intersection

Existing Flyover

Proposed Flyover

ROW-90 m

Layout Plan for Ch 0.000 to Ch 1.000CH

100

0

Page 64: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Proposed Flyover at Sarai Kale Khan Intersection

Sarai Kale Khan Intersection

To ITO

Page 65: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Cross Section for Proposed flyover at Sarai Kale Khan

Intersection

Page 66: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Right turning ramp at Sarai Kale Khan intersection

Page 67: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Ring Road - NH-24 Bypass Intersection ( Integration with Proposal of NHAI)

ROW-90 m

ROW-90 m

EXISTING FLYOVER

Page 68: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

B B

Layout Plan for Ch 3.000 to Ch 4.000

Ring Road

PROPSED UNDERPASSTo ASHRAM

To ITO

ROW-90 m

Page 69: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Cross Section for Proposed Underpass

Page 70: Integrated transit corridor development and street …uttipec.nic.in/writereaddata/discussionimages/2275290802.pdfKalkajiMandir Intersection Chirag Delhi Intersection TO RK PURAM TO

Proposal of Underground Tunnel at ITPO Area

Proposed Tunnel

To Purana Quila