Welcome to this assessment
It will test your
knowledge in Instrumentation & Control (I&C)
mastery of the contents of Chapter 11 of The Guide1
1 ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, 2015
http://www.editionstechnip.com/fr/catalogue-detail/1111/oil-gas-engineering-guide-the.html
Instrumentation & Control (I&C) knowledge assessment
Page 2
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
?
Equipment room Control room
System
cabinet
Operator
station
Please name this equipment
Page 3
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet Operator
station
System
cabinet
Equipment room Control room
Page 4
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Please name this equipment
?
Operator
station
Marshalling
cabinet
Equipment room Control room
Page 5
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet Operator
station
Equipment room Control room
Page 6
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
In which cabinet are the I/O cards installed?
Page 7
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
In which cabinet are the I/O cards installed?
Page 8
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
In which cabinet are the controllers installed?
Page 9
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet
Equipment room Control room
Operator
station
In which cabinet are the controllers installed?
System
cabinet
Page 10
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
Is this a serial or hard wired link?
Page 11
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
Is this a serial or hard wired link? Hard wired (cross wiring)
Page 12
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
What do you call this cable?
Page 13
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
What do you call this cable? Secondary (or unit) cable
Page 14
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
What do you call this cable?
Page 15
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
PT JB
Process line
Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
What do you call this cable? Multi(core) cable
Page 16
HERVE BARON
© 2015 – Hervé Baron
What do you call such a drawing?
Page 17
HERVE BARON
© 2015 – Hervé Baron
What do you call such a drawing? System architecture drawing
Page 18
HERVE BARON
© 2015 – Hervé Baron
The lead time of a control valve is 1) 3 months 2) 6 months 3) 9 months
Page 19
HERVE BARON
© 2015 – Hervé Baron
The lead time of a control valve is 1) 3 months 2) 6 months 3) 9 months
Page 20
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
In your opinion, which Milestone is reached first?
Page 21
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
In your opinion, which Milestone is reached first?
Hardware freeze, for lead time of cabinets. Usually 3 months ahead of Software freeze.
Page 22
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
Hardware freeze means instrument index freeze. Right or Wrong?
Page 23
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
Hardware freeze means instrument index freeze. Right or Wrong?
Right: Instrument index 100% complete, i.e., number, type & location of instruments, including within packages for centrally controlled packages.
Page 24
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
Which of the following documents are required to reach Hardware freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams
Page 25
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
Which of the following documents are required to reach Hardware freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams
Page 26
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
Which of the following documents are required to reach Software freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams
Page 27
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
Which of the following documents are required to reach Software freeze? 1) Plot Plan 2) IFD P&IDs 3) IFC P&IDs 4) Control narratives 5) Safeguarding narratives and Cause & Effect diagrams 6) JB wiring diagrams 7) Packaged units sequence description and diagrams
Page 28
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
What is challenging to meet the schedule?
Page 29
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Software freeze, for the configuration (programming) of the system
What is challenging to meet the schedule?
When control systems of machinery and packages engineered by Vendors are integrated in the Plant control system, the consolidation of information to be transfered to the Integrated Control System Supplier is complex and requires a specific schedule for on-time hardware & software Freeze.
Page 30
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What do you call such a drawing?
Page 31
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What do you call such a drawing? Logic analysis & grafcet
Page 32
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What do you call such a drawing? Logic analysis & grafcet Who issues it?
Page 33
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What do you call such a drawing? Logic analysis & grafcet Who issues it? Package vendors
Page 34
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
A serial link is a continuous link. Right or Wrong?
Page 35
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
A serial link is a continuous link. Right or Wrong?
Wrong
Page 36
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The following is adjusted at Site during commissioning/Start-Up:
1) settings of controllers (Proportional, Integral, Derivative)
2) Settings of alarms
3) Setting of trips
Page 37
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The following is adjusted at Site during commissioning/Start-Up:
1) settings of controllers (Proportional, Integral, Derivative)
2) Settings of alarms
3) Setting of trips
Page 38
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What is a serial link?
1) a sequential communication regulated by a protocole,
2) a parallel link,
3) a point-to-point connection,
Page 39
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What is a serial link?
1) a sequential communication regulated by a protocole,
2) a parallel link,
3) a point-to-point connection,
Page 40
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What does IP level of electrical and instrumentation equipment stand for?
Page 41
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What does IP level of electrical and instrumentation equipment stand for?
Ingress Protection. It means mechanical protection and protection again ingress of water, dust etc. Reference code is IEC 60529 "Degree of Protection provided by enclosures". Typically a certain IP level is specified for outdoor equipment and another one for indoor equipment.
Page 42
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What do you call the drawing showing all details of wiring, terminations and inter-connections from primary to final element?
Page 43
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
What do you call the drawing showing all details of wiring, terminations and inter-connections from primary to final element?
The loop diagram
Page 44
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Which documents from a packaged equipment Vendor are critical for instrumentation & Control discipline?
1) General Arrangement
2) P&IDs
3) Instrument index, I/O list
4) Junction boxes drawings
5) C&E diagrams
6) hook-up drawings
7) cable routing drawings
Page 45
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Which documents from a packaged equipment Vendor are critical for instrumentation & Control discipline?
1) General Arrangement
2) P&IDs
3) Instrument index, I/O list
4) Junction boxes drawings
5) C&E diagrams
6) hook-up drawings
7) cable routing drawings
Page 46
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Where are located the main processors of a Process Control System?
1) in the workstation in the control room
2) in the system cabinets in the technical rooms
3) in the marshalling cabinet in the technical rooms
Page 47
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Where are located the main processors of a Process Control System?
1) in the workstation in the control room
2) in the system cabinets in the technical rooms
3) in the marshalling cabinet in the technical rooms
Page 48
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Process discipline issues "Process Data sheets" and Instrumentation discipline issues "Mechanical data sheets" of instruments. Right or Wrong?
Page 49
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Process discipline issues "Process Data sheets" and Instrumentation discipline issues "Mechanical data sheets" of instruments. Right or Wrong?
Right, Instrument data sheets include mechanical data from Piping
Page 50
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Pressure gauge/transmitters are fitted a diaphragm seals in case of:
1) low pressure
2) high pressure
3) liquid service
4) risk of plugging of impulse line/instrument
Page 51
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Pressure gauge/transmitters are fitted a diaphragm seals in case of:
1) low pressure
2) high pressure
3) liquid service
4) risk of plugging of impulse line/instrument
Page 52
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
In which document(s) are the set points of process controllers indicated?
1) Process description
2) Instrument list
3) Instrument data sheet
4) Operating Manual
5) Process Flow Diagrams
Page 53
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
In which document(s) are the set points of process controllers indicated?
1) Process description
2) Instrument list
3) Instrument data sheet
4) Operating Manual
5) Process Flow Diagrams
Page 54
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The low low level instrument is part of which system:
1) Process Control System (DCS)
2) Safety Instrumented System (SIS)
Page 55
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The low low level instrument is part of which system:
1) Process Control System (DCS)
2) Safety Instrumented System (SIS)
Page 56
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The Safety Instrumented System (SIS) includes
1) The ESD system
2) The PSD system
3) The F&G system
Page 57
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
The Safety Instrumented System (SIS) includes
1) The ESD system
2) The PSD system
3) The F&G system
Page 58
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
A single equipment shutdown is performed by
1) The ESD system
2) The Process Control system
3) The PSD system
Page 59
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
A single equipment shutdown is performed by
1) The ESD system
2) The Process Control system
3) The PSD system
Page 60
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Hardwired logic is non-programmable. Right or Wrong?
Page 61
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Hardwired logic is non-programmable. Right or Wrong?
Right
Page 62
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Remote Terminal Units (RTU) are local control stations. Right or wrong?
Page 63
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Remote Terminal Units (RTU) are local control stations. Right or wrong?
Right
Page 64
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Which segregation is made between signals (different JBs)?
1) Control / Shutdown
2) Analog / Digital
3) IS/non-IS
Page 65
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
Which segregation is made between signals (different JBs)?
1) Control / Shutdown
2) Analog / Digital
3) IS/non-IS
Page 66
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
To which of the following is a package PLC normally connected?
1) DCS
2) MCC
3) PDCS
Page 67
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
To which of the following is a package PLC normally connected?
1) DCS
2) MCC
3) PDCS
Page 68
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?
Page 69
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?
Page 70
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?
Page 71
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
By which system are these valves controlled? 1) The Process Shutdown System (PSD)? 2) The Emergency Shutdown System (ESD)? 3) Process Control System (DCS)?
Page 72
HERVE BARON
© 2015 – Hervé Baron
I&C knowledge assessment test
That’s all for now folks, but I won’t be long with tests on knowledge acquisition for the other chapters of the guide…
Page 73
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Page 74
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Discipline presentation: activities and deliverables
Table of Contents
The overall process
Methods & tools
Page 75
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Discipline presentation: activities and deliverables
Page 76
HERVE BARON
© 2015 – Hervé Baron
The work of each Engineering
discipline is described
Page 77
HERVE BARON
© 2015 – Hervé Baron
Design activities are explained, e.g., Plant
Equipment layout
Page 78
HERVE BARON
© 2015 – Hervé Baron
Complex activities, such as
QRA, are explained through a practical example.
Page 79
HERVE BARON
© 2015 – Hervé Baron
How are materials of
construction selected ?
Page 80
HERVE BARON
© 2015 – Hervé Baron
How and when are Piping
Materials ordered?
Page 81
HERVE BARON
© 2015 – Hervé Baron
A sample of all common Engineering documents is
included
Page 82
HERVE BARON
© 2015 – Hervé Baron
A sample of all common Engineering documents is
included
Use this to specify what you
want to your Engineering supplier !
Page 83
HERVE BARON
© 2015 – Hervé Baron
Verify the contents of
engineering documents with check lists.
Page 84
HERVE BARON
© 2015 – Hervé Baron
Difference between
Engineering and Shop drawings
Page 85
HERVE BARON
© 2015 – Hervé Baron
Understand the main
technical aspects, e.g., DCS vs ESD
Page 86
HERVE BARON
© 2015 – Hervé Baron
The common 2 types of
package control
Page 87
HERVE BARON
© 2015 – Hervé Baron
The different Plant drainage
systems
Page 88
HERVE BARON
© 2015 – Hervé Baron
The dynamic forces to
which an Off-Shore Plant is subject
Page 89
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
The overall process
Page 90
HERVE BARON
© 2015 – Hervé Baron
Use this as standard, question deviations.
Page 91
HERVE BARON
© 2015 – Hervé Baron
Understand the new 3D-model centered engineering process
Page 92
HERVE BARON
© 2015 – Hervé Baron
Know the interfaces
between disciplines... and with Vendors
Page 93
HERVE BARON
© 2015 – Hervé Baron
Understand what drives
the Project schedule
Page 94
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Methods & tools
Page 95
HERVE BARON
© 2015 – Hervé Baron
Use these methods as
standard, question deviations.
Page 96
HERVE BARON
© 2015 – Hervé Baron
Implement powerful
procedures
Page 97
HERVE BARON
© 2015 – Hervé Baron
Request meaningful progress
reports
Page 98
HERVE BARON
© 2015 – Hervé Baron
Implement effective Project
Control
Page 99
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
This book is destined to both:
Oil & Gas companies Project execution personnel
Oil & Gas contractors Project execution personnel
Date of publication: March, 2015.
Page 100
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide 2nd edition
If your are on the Client side, i.e., contracting Engineering services, this book will help you to:
Specify to an Engineering supplier what you want: what deliverables and with what contents,
Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.
Specify the progress report you want, with the meaningful indicators,
Ask the right questions to assess the true progress,
Page 101
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide 2nd edition
If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:
Understand the work of each discipline and the overall picture,
Challenge what one discipline tells you,
Understand the critical areas,
Put in place the right methods to be successful,
Page 102
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide 2nd edition
Order from the publisher:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html
Or on Amazon:
http://www.amazon.com/Oil-Gas-Engineering-Guide-2ND/dp/2710811510/ref=sr_1_1?ie=UTF8&qid=1437160937&sr=8-1&keywords=the+oil+and+gas+engineering+guide