Top Banner
Installation of Subsea Processing System in Deepwater 5 th June 2013 Marin Abélanet
18

Installation of Subsea Processing System in Deepwater

Feb 03, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Installation of Subsea Processing System in Deepwater

Installation of Subsea Processing System in Deepwater

5th June 2013

Marin Abélanet

Page 2: Installation of Subsea Processing System in Deepwater

2 Page 10-Jun-13

Pazflor Project Overview Subsea Separation Unit Information Challenges and Outcomes: 1. IMF and SM Seafastening and

Transportation

2. Limiting Sea States for SSU Deployment

3. Structure Installation

4. SSU Tie-In

Conclusions

Agenda

Page 3: Installation of Subsea Processing System in Deepwater

3 Page 10-Jun-13

Pazflor Project Overview

3 x Subsea Separation Units

Page 4: Installation of Subsea Processing System in Deepwater

4 Page 10-Jun-13

Pazflor Project Overview

•Client: Total •Contractor:

Subsea 7 - Technip Consortium

•Contract: EPIC •Scope:

– Installation of 3 SSUs - the first ever to be deployed in deepwater fields

– 54km of rigid pipelines – 10 flowline piles – 18 rigid jumpers – 87km of dynamic and static

umbilicals – Three manifolds – 16 FPSO mooring lines and

piles – Two flexible dynamic risers

Page 5: Installation of Subsea Processing System in Deepwater

5 Page 10-Jun-13

Pazflor Project Overview Subsea Separation Unit Information Challenges and Outcomes: 1. IMF and SM Seafastening and

Transportation

2. Limiting Sea States for SSU Deployment

3. Structure Installation

4. SSU Tie-In

Conclusions

Agenda

Page 6: Installation of Subsea Processing System in Deepwater

6 Page 10-Jun-13

Subsea Separation Unit Information

No Description Envelope Dimensions In Air Weight

1 FBS 15m x 15m x 14m 205 Te

2 IMF 20m x 20m x 8m 264 Te

3 Separator Module (SM) 6m x 6m x 20m 440 Te

1 2 3

Page 7: Installation of Subsea Processing System in Deepwater

7 Page 10-Jun-13

Pazflor Project Overview Subsea Separation Unit Information Challenges and Outcomes: 1. IMF and SM Seafastening and

Transportation

2. Limiting Sea States for SSU Deployment

3. Structure Installation

4. SSU Tie-In

Conclusions

Agenda

Page 8: Installation of Subsea Processing System in Deepwater

8 Page 10-Jun-13

IMF and SM Seafastening and Transportation

•Grillage for structures sensitive to fatigue •Grillage design for guiding for deployment & recovery offshore •Grillage design for 2 journeys

– Norway to Angola on a heavy lift vessel across Bay of Biscay in November – Luanda to field on a cargo barge

•Grillage design to enable lift with IMF/SM for – Load-out on heavy lift vessel – Transfer onto cargo barge in Luanda bay – Grillage clamped on each structure (no weld) – Additional stoppers for sea-fastening of SM/IMF on grillage

• Protruding and sensitive equipment – SM landing area on the IMF – Hubs for future connections – Piping and valves

Page 9: Installation of Subsea Processing System in Deepwater

9 Page 10-Jun-13

IMF and SM Seafastening and Transportation

Page 10: Installation of Subsea Processing System in Deepwater

10 Page 10-Jun-13

IMF and SM Seafastening and Transportation

Page 11: Installation of Subsea Processing System in Deepwater

11 Page 10-Jun-13

IMF and SM Seafastening and Transportation

Structure Delivery in Luanda:

Page 12: Installation of Subsea Processing System in Deepwater

12 Page 10-Jun-13

Structure Lifting and Installation

Structure Lift Rigging:

•Very strict tolerance on structure inclination – (+/- 0.5 degree)

• Uncertainties with structure weight and CoG – Estimated submerged weight – Estimated preservation fluids – Entrapped water

• Adjustment of Rigging Lengths – Schedule constraint

Page 13: Installation of Subsea Processing System in Deepwater

13 Page 10-Jun-13

SSU Tie-In

Hurdle Challenge Mitigation

1

Stroking of such a large and heavy object • 300Te of downward force from the Separator Unit, 800mm stroking • Very high centre of gravity, resulting in eccentricity from the stroking location

SIT’s, SIT’s, and then more SIT’s • Use of 2 x stroking cyclinders became the base case after onshore trials

2 Hub preparation prior to stroking • Extremely tight ROV working area • Impact of dropped objects

• 3D ROV access simulation • Dry and wet trials with mock ROV

3

Hub alignment and tie-in • Alignment of 3 hubs in a single stroking operation • Double CAT tie-in and several flying leads

• Good design, which was significantly challenged prior to getting to the testing phase • Checked during SIT

4 Interfacing with Company, SPS Contractor and Installation Contractor The Client’s strong will

Page 14: Installation of Subsea Processing System in Deepwater

14 Page 10-Jun-13

SSU Tie-In - Stroking

800mm

Before After

The vertical separator weight is 300Te

181kg Stroking Tool

Page 15: Installation of Subsea Processing System in Deepwater

15 Page 10-Jun-13

SSU Tie-In – Hub Preparation

102 Kg Max

274 Kg

Dropped objects would prevent structure stroking, with no real proven contingency for retrieving them

Page 16: Installation of Subsea Processing System in Deepwater

16 Page 10-Jun-13

Pazflor Project Overview Subsea Separation Unit Information Challenges and Outcomes: 1. IMF and SM Seafastening and

Transportation

2. Limiting Sea States for SSU Deployment

3. Structure Installation

4. SSU Tie-In

Conclusions

Agenda

Page 17: Installation of Subsea Processing System in Deepwater

17 Page 10-Jun-13

Conclusions

1. What can be achieved in our projects is impressive

2. Interfaces are the key

3. Early Installation Contractor Involvement

4. Company Involvement and Follow-Up

Page 18: Installation of Subsea Processing System in Deepwater

10.01.11 18 Page

seabed-to-surface www.subsea7.com