Top Banner
Innovative Approaches to Managing Stormwater: Lessons from Rotterdam, New Jersey and New York Learning Lunch: Monday September 19, 2016 City of Hoboken, New Jersey
30

Innovative Approaches to Managing Stormwater: The Hoboken Approach

Feb 14, 2017

Download

Environment

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Innovative Approaches to Managing Stormwater:Lessons from Rotterdam, New Jersey and New York

Learning Lunch:Monday September 19, 2016

City of Hoboken, New Jersey

Page 2: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Population: 52,575Households: 26,855Real Property Ratable Base: $9.7 BillionLand Area: 1.275 Square Miles

Hoboken, New Jersey

Page 3: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Landmass within Flood Zone (A): 63.85%Landmass within Flood Zone (V): 7.41% Landmass within Flood Zone (X): 7.66%Hoboken NFIP Total Liability: $1,922,187,500Hoboken NFIP Annual Premiums: $5,984,720

Flood Risk

Page 4: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Hurricane Irene August 2011

Page 5: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Superstorm Sandy October 2012

Page 6: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Rain EventJanuary 4, 2016

Page 7: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Rebuild by Design Hudson River: ▪ Resist ▪ Delay ▪ Store ▪ Discharge ▪

REBUILDBYDESIGN▪ RESIST ▪ DELAY ▪ STORE ▪ DISCHARGE ▪

HUDSON RIVERHOBOKEN WEEHAWKEN JERSEY CITY │ NEW JERSEY

Page 8: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 9: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 10: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Rainfall model depicting a 5-year rainfall event (high-tide) “No Action Alternative.”

Model estimates future flood (rainfall) event if Project is not built.

Model assumes Hoboken and NHSA’s existing on-going initiatives WILL be built:• Southwest Park• H1 and H5 Pump Stations• Washington Street Rain Garden• City Hall Green Infrastructure

Washington

Street Rain Gardens

H5 Pump Station

City Hall GI

Project

H1 Pump Station

Southwest Park

Areas that

Flood

Page 11: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Southwest Park

Page 12: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 13: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 14: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 15: Innovative Approaches to Managing Stormwater: The Hoboken Approach

H1 and H5 Pump Stations

Page 16: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Washington Street Redesign

Page 17: Innovative Approaches to Managing Stormwater: The Hoboken Approach

City Hall Green Infrastructure

Page 18: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 19: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 20: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 21: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Baseline Conditions (NAA) Proposed DSD Alternative

WashingtonStreet Rain

Gardens

H5 Pump Station

City Hall GI Project

H1 Pump Station

Southwest Park

BASF Site

NJ Transit Site

Block 10 Site

Page 22: Innovative Approaches to Managing Stormwater: The Hoboken Approach

BASF Site

NJ Transit Site

Block 10 Site

Proposed underground detention facilities with green/open space on ground surface with discharge features such as pumps to manage rainfall runoff volume

ROW Green/Grey Infrastructure Practices

‐ Total of 61 sites to manage street drainage for approx. 13 acres

NJ Transit site

‐ Manages rainfall runoff for approx. 15 acres

Block 10 site

‐ Manages rainfall runoff for approx. 8 acres

BASF site

‐ Manages rainfall runoff for approx. 55 acres

Page 23: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 24: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 25: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 26: Innovative Approaches to Managing Stormwater: The Hoboken Approach
Page 27: Innovative Approaches to Managing Stormwater: The Hoboken Approach

• Integrated flood management solutions to complement RBD

• Proposed a combined surface and sub-surface plan to utilize 4 contiguous acres of the 6-acre BASF site that would include:• Stormwater detention facility• Underground parking garage• Surface park space • Integrated green infrastructure

Re.Invest

Page 28: Innovative Approaches to Managing Stormwater: The Hoboken Approach

N

Northwest Park

Page 29: Innovative Approaches to Managing Stormwater: The Hoboken Approach

• Create an “ecological zone” in part of the H6 and H7 drainage areas

• Would install new storm sewer infrastructure to separate the currently combined system

• Stormwater would flow to the BASF site where solids and floatables would be removed

• Stormwater would be detained under BASF site until the detention facility is at capacity

• New stormwater pump station on BASF site would pump to a new outfall in Weehawken Cove

• Engineered wetlands in Cove would filter stormwater

NHSA Eco-Zone

Page 30: Innovative Approaches to Managing Stormwater: The Hoboken Approach

Jennifer Gonzalez AICP, ENV SP

Principal PlannerCity of [email protected]

www.hobokennj.gov

https://www.facebook.com/hoboken

https://twitter.com/cityofhoboken

https://www.instagram.com/hobokennj

https://vimeo.com/hobokennj

https://www.flickr.com/photos/hoboken

Thank you!