Initial Environmental Examination June 2016 PAK: MFF Power Transmission Enhancement Investment Program Tranche 4 ─220 KV Nowshera Grid Station and Allied Transmission Line Prepared by the National Transmission and Despatch Company for the Asian Development Bank. This is an updated version of the draft originally posted in December 2014 available on http://www.adb.org/projects/documents/pak-pteipt-tranche4-nowshera-grid-station-and-allied- transmission-line-iee. This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
83
Embed
Initial Environmental Examination PAK: MFF Power Transmission … · 2016-06-22 · The Pakistan Environmental Protection Act 1997, as adopted by KP Province in 2010, and other allied
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Initial Environmental Examination
June 2016
PAK: MFF Power Transmission Enhancement
Investment Program Tranche 4
─220 KV Nowshera Grid Station and Allied
Transmission Line
Prepared by the National Transmission and Despatch Company for the Asian Development Bank. This is an updated version of the draft originally posted in December 2014 available on http://www.adb.org/projects/documents/pak-pteipt-tranche4-nowshera-grid-station-and-allied-transmission-line-iee. This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
ESIC TOC-I
TABLE OF CONTENTS
LIST OF ACRONYMS ...................................................................................................... I
CHAPTER - 6: ENVIRONMENTAL MANAGEMENT PLAN AND INSTITUTIONAL REQUIREMENTS .............................................................................6-1
Table 3.1: Permissible Conductor Clearance at 65oC ......................................................................................... 3-2
Table 3.2 Estimated Works in Grid Station ......................................................................................................... 3-2
Table 3.3 Estimated Works on Transmission Line .............................................................................................. 3-3
Table 3.4 Materials Required for the Project ....................................................................................................... 3-3
Table 3.5 Sources of Raw Material Availability ................................................................................................... 3-3
Table 3.7 Equipment and Installation .................................................................................................................. 3-4
Table 3.8 Illustration Distribution of Labour ......................................................................................................... 3-5
Table 5.1: National Environmental Quality Standards for Noise ......................................................................... 5-5
Table 6.1: Grievance Redress Process .............................................................................................................. 6-4
Table 6.2: Cost Estimates for Environmental Management ................................................................................ 6-4
Table 7.1: Details of Public Consultation session ............................................................................................... 7-6
FIGURES:
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
ESIC TOC-VI
Figure 1.1: Location Map of Nowshera Grid Station Project in Pakistan ............................................................. 1-4
Figure 1.2: Map showing the location of Proposed Nowshera Grid Station ....................................................... 1-5
Figure 1.3: Map showing Existing and Proposed TL for Nowshera 220 KV Grid Station ................................... 1-6
Figure 1.4: Sketch of the Project Area ............................................................................................................... 1-7
Figure 3.1: Layout of the Proposed 220 KV Nowshera G/S Subproject .............................................................. 3-8
Figure 4.1: Location Map of Nowshera District ..................................................................................................4-13
Figure 4.2: Seismic Zoning Map of Pakistan ......................................................................................................4-15
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
i
LIST OF ACRONYMS
ADB Asian Development Bank
DXL Distribution Transmission Line
DGS Distribution Grid Substation
EARF Environment Assessment Review Framework
EIA Environment Impact Assessment
GDP Gross Domestic Product
GOP Government of Pakistan
GIS Gas Insulated Switchgear
G/S Grid Station
IA Implementing Agency
ILO International Labour Organization
IRR Internal Rate of Return
KP Khyber Pakhtunkhwa
LARP Land Acquisition and Resettlement Plan
Nowshera SP Nowshera 220KV Grid Substation and Associated T/Line Subproject
Leq Equivalent Sound Pressure Level
NEQS National Environmental Quality Standards
NGO Non-Governmental Organization
PC Public Consultation
PEPA Punjab Environmental Protection Agency
PEPA Pakistan Environment Protection Act 1997 (as regulated and amended)
PESCO Peshawar Electric Supply Company
RoW Right of Way
SP Subproject
SR Sensitive Receptor
TOR Terms of Reference
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
ES-1
EXECUTIVE SUMMARY
This document presents the Initial Environmental Examination (IEE) report of 220 kV Nowshera Grid Station and
its allied Transmission Line to be constructed with financial assistance of Asian Development Bank (ADB) under
its Multi Tranche Facility (MTF) by National Transmission and Despatch Company Limited (NTDCL) as part of its
Tranche-IV programme. This IEE has been conducted in response to ADB Environmental Safeguard Policy
Statement 2009 and according to ADB Environmental Assessment Guidelines 2003. The Pakistan Environmental
Protection Act 1997, as adopted by KP Province in 2010, and other allied laws were also kept in view.
The proposed project is located 10 km on west side of G.T Road on Cherat Cement Factory Road, between the
town of Nowshera and Pubbi in KP Province of Pakistan. The project will augment the efforts of Pakistan Water
& Power Development Authority (WAPDA) to overcome the shortage of electricity by ensuring an efficient and
loss free transmission of electricity available from Ghazi Barotha Hydel Power Project (GBHP). The site of the
proposed Grid Station consists of 40 acre (450m x 350m) of community grazing land of village Spin Khak. The
GPS coordinates of the site are 33° 56” 31.28” N and 71° 51” 55.71E.
This project will be completed by the end fall of 2016 at a preliminary total estimated cost of Pak. Rs. 1875
million. The design and construction of the project have been assigned to NTDC and its operation and
maintenance shall be done by NTDC under an overall control of WAPDA. The cost of environmental mitigation
measures and monitoring is estimated to be Rs. 2,293,250 Pak .
As part of this IEE study primary as well as secondary data were collected through field surveys, public
consultation particularly local communities, and literature research. Consultation were also held with other
stakeholders like WAPDA, NTDC, PESCO, ADB and related departments of Government of Pakistan as well as
KP screening and scoping of the study was carried out before preparing the IEE. The proposed Grid Station as
well as its associated Transmission Line is located in Peshawar valley which is partly flat and partly piedmont
with rolling topography. Whereas the Grid Station is situated on semi-barren community range land, the
transmission line shall pass through semi-arid grazing area as well as barani (rain fed) agricultural lands. Rainfall
is scanty (300-500 mm/annum) and is mainly received during the late monsoon season or early spring. The
Kabul River flows parallel to G.T Road on its east. The river can get in spate if there are heavy rains in its upper
watershed. Extremely cold winds blow during winter. Ambient air is generally clean. Main flora in and around the
project area consists of Kikar (Acacia militia), Walla (Zizyphus numularia), Capparis Aphylla and Mesquete
(Propis Glandulosa) along with typical semi-arid zone bushes, herbs and grasses. If water is available from rain
or tubewell, the valley is very suitable for fruit garden or plums and apricot. Main Fauna includes mammals like
Jackals, foxes, porcupines, jungle cats, hares and field rats; birds like common crows, sparrows, shikra, nuyena,
pigeon, doves, parrots, common kites and partridges. Common reptiles are snakes and lizards. Major amphibian
is common toad. Scorpion and spiders are other poisonous creatures of the area. There are no reported
endangered species nor there is any protected area. Along G.T Road, there is a Botanical Garden which is
maintained by KP Forest Department.
Barani agriculture is restricted to comparatively flat area, and its practice is rather limited. Domestic arrivals
include camels, horse, mules, donkeys, buffaloes, sheep and goats. Economy is mostly pastoral and therefore
the people of the area are mainly meat eaters.
Although union councils and civil courts of various levels are fully functional, Jirga system is still considered to be
the most dependable system for delivering justice by the local communities. The area is predominately inhabited
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
ES-2
by Khattak tribe and is popularly known as Khattak Nama. Almost 100% population is Muslim. Women are from a
less favoured section of society. Child labour is not considered as an objectionable practice.
Analysis of alternative has shown that project site as proposed and design as being prepared is the best option.
It has a cost benefit ratio (CBR) of 2.25 at 12% and 1.97 at 14% with an economic rate of return (EIRR) as
27.34 %. Logistically the best option is to locate all facilities of the contractor within the walled and gated campus
of proposed Grid Station. Best option of labour is an admixture of 100% unskilled with at least 50% semi-skilled
and at least 20% skilled labour from the local population. Although the local labour will be given the priority, in
case of unavailability, semi-skilled and skilled labour shall have to be bought from outside by the contractor.
This IEE has shown that the project construction with either cause no adverse impacts or will cause such impacts
which will be linked with contractors work practice matter that inherent potential and shall be easily mitigable and
manageable. Because of being of a localized nature, the project is unlikely to trigger any adverse impacts except
during fixing of towers for transmission lines which are manageable in the light of experience of WAPDA gained
from similar projects.
To ensure the implementation of mitigation measures of all potential adverse impacts, an environmental
monitoring plan (EMP) has been prescribed. EMP shall be made integral parts of tender bid and contract
agreement documents. The cost of implementation of mitigation as well as monitoring plan shall be reflected in
project Bill of Quantities (B.O.Q). A system of contractor’s non-compliance has been prescribed and its linkage
with contractor’s bill clearance has been provided.
This IEE study shows that the project does not have any negative environmental impacts inherently from design.
Any non-compliance, during work practice, can be committed by contactor but those can be forestalled or
mitigated through effective monitoring. The proposed project therefore is environmental friendly, socially
acceptable, financially viable, economically sustainable, neutral to gender and pro-poverty alleviation.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-1
CHAPTER - 1: INTRODUCTION
This document presents Initial Environmental Examination (IEE) of Nowshera 220 KV Grid Station, 1.
under Tranche-IV of a multi-tranche programme of Water and Power Development Authority (WAPDA) to be
financed by Asian Development Bank (ADB) and to be implemented by National Transmission Despatch
Company (NTDC).
1.1 Project Overview
Pakistan is suffering from serious shortage of energy. This shortage can be overcome by production 2.
of energy through optimizing the existing sources and discovering new sources. Of this effort hydropower can
constitute a major part. A major limitation on an effective use of the hydropower available out of existing
resources and to be available from potential resources is availability of an efficient transmission system. Absence
of a good transmission system results in unequal distribution of available hydropower and heavy line losses
along the way. For proper distribution of the hydropower produce from Ghazi Barotha Hydropower Project, a new
transmission line is required of which Nowshera Grid station is essentially required. The scope of work includes
addition of 6.3 MVA, 132/11 KM Power Transformers and allied equipment. The transmission line will require
installation of towers which will be installed on the route of In/Out 2 Km Ghazi Brotha-Shahi Bagh transmission
line. The Grid Station shall be located about 10 Km from Nowshera Town on a 450m x 350m (about 315 Kanals)
of acquired barren land located along Cherat Cement Factory road about 10 Km off G.T. Road. When developed,
the proposed Grid Station shall augment the transmission capacity of Peshawar Electric Supply Company
(PESCO) and shall enable it to meet the increased domestic and industrial demand of electricity in and around
Nowshera District. It will reinforce the transmission capacity of PESCO already existing in the area. For exact
location of the proposed project see Figs. 1.1, 1.2, 1.3 and 1.4.
1.2 Scope of the Study and Personnel
As a part of IEE study, primary and secondary data have been collected through field survey, public 3.
consultations, literature research, ADB internet research and public libraries at Nowshera and Peshawar.
WAPDA officials at Lahore, Peshawar and Islamabad were consulted. The information provided by PESCO staff,
in particular the Executive Engineer, the sub-Divisional Officer and PESCO Land acquisition Officer was of great
help. The information gathered from Soil Survey of Pakistan office, Meteorological Department Office,
Departments of Forests, Wildlife and Fisheries, Land Revenue Department, and Agriculture Department all
located at Peshawar was of great significance. The Geology, Botany and Zoology Departments of University of
Peshawar, the Agronomy Department of University of Agriculture, Peshawar and Watershed Management and
Range Watershed Management and Range Research Departments of Pakistan Forest Institute provided data
wherever required. ADB Questionnaire has been used for assessment of general features of environment of the
Project. Major data available out of these sources were land use, soil and physiography, climatic data, flora,
fauna, surface and ground water quality and biodiversity in general. In addition, the social data collected through
surveys was verified from Pakistan Statistical Year Book, Economic Survey of Pakistan and District Record in
DCO office Nowshera.
As stated above a structured survey was conducted for social data of nearby communities. For issues 4.
pertaining to Land Acquisition and Resettlement Plan (LARP), a separate stand-alone study has been
conducted. Its findings are contained in a separate report (LARP). Key findings of the LARP have, however, been
incorporated under social impact assessment under baseline study of the area.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-2
For various maps, the courtesy of Survey of Pakistan at Peshawar was used. The information 5.
available was also supplemented through a Google earth study on internet. Whereas necessary GPS
coordinates and photographs of the Project area and its surroundings were taken for record and reference. GPS
coordinates were used to derive site plans out of large maps.
A well trained local team of three experts, Mr. Afzal Chaudhry, Ms. Seher Waseem Ch. And Ms. Iman 6.
Meer carried out field surveys. They undertook two phased consultation programme, as detailed below.
Phase 1 composed of meetings and discussions with local and regional officials. Meeting with officials 7.
facilitated achieving multiple and diverse objectives such as:
• Provision of forum for initial definition of critical environmental issues
• Establishment of their implementation as official stakeholders, the key sector development issues and
linkage to the social, the key sector development issues and lineage to the environmental and social
development
• Confirmation of the suitability of initial list of communities selected for consultation
Phase 2 involved the understanding of a programme or a semi-structured discussion in communities 8.
in project area of influence. The programme induced both community discussion in general and discussion with
women through their family elders.
The area around the selected project area generally known as Khattak Nama is highly conservative 9.
where direct access to women for social surveys was not possible. Even when contacted through family elders in
selected localities, the women would not like to allow the recording of their names. However, through all available
means, women consultation was carried out according to the Gender Issue Study, commissioned by EPA and
ADB and is considered to be an essential part of IEE preparation. The ADB studies overlap those required out of
this study, which also include the “Gender Impact Assessment”. Accordingly three meetings were held with
women, through their family elders, in different small villages located part of Khattak Nama in Nowshera District.
1.3 The Study Objectives
The ultimate objective of this study is to assess realistically whether or not the project is 10.
environmentally manageable. This would make the project environmentally responsible and socially acceptable.
Specific objectives of this study can be identified as follows:
• To collect the baseline data on physical, biological and social conditions of the project area and its
surrounding area of influence.
• To carry out environmental (including physical, biological and social) assessment of supporting
administrative and legal framework of the proposed Grid Station.
• To identify mitigation measures for any potential environmental impacts
• To propose institutional responsibilities and methods of monitoring the mitigation measures and
monitoring procedures
• To prepare Management Plan for those environmental impacts which may be considered as adverse.
1.4 The Report Structure
The IEE document is structured, as per ADB outline, as follows: 11.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-3
Chapter 1: Introduction containing general information about the project, the IEE and the process of carrying out
the study.
Chapter 2: Legal and Policy Framework describes the policy, laws, regulations any protocols governing the IEE.
Chapter 3: The Project Description describes overall details of the works to be undertaken. This in fact provides
the physical framework in which various environmental impacts are likely to be generated.
Chapter 4: The Baseline Study gives data and explanatory information on Physical, Biological and Social
conditions collected through surveys of the Project and project area of influence.
Chapter 5: Environmental Impact Assessment identifies various environmental impacts and classifies them
according to their degree of effect on the environment. This classification makes the basis of the Mitigation
Measures in IEE.
Chapter 6: Environmental Management Plan contains comprehensive prescription regarding mitigation
measures for various adverse impacts of the project. This also includes institutional arrangement and short
environmental monitoring plan for implementation of the Mitigation measures. Despite its being only a part of an
IEE, the Mitigation Plan is included in the Tender as well as the contract Agreement Document.
Chapter 7: Public Consultations and Disclosures explain the process of public consultation and disclosure of the
IEE report at important public offices/ places/ libraries. This step makes an IEE a public legal document.
Chapter 8: Conclusion is based on the entire IEE report saying that the Environmental Impacts are either both
negligible and insignificant or can be easily and effectively mitigated.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-4
Figure 1.1: Location Map of Nowshera Grid Station Project in Pakistan
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-5
Figure 1.2: Map showing the location of Proposed Nowshera Grid Station
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-6
Figure 1.3: Map showing Existing and Proposed TL for Nowshera 220 KV Grid Station
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1-7
Figure 1.4: Sketch of the Project Area
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2-1
CHAPTER - 2: POLICY, LAW AND PROTOCOLS
A detailed preview of all the legislations encompassing the subproject is cited below. Direct legislation 12.
on environmental protection is contained in several statutes, namely the Pakistan Environmental Protection Act
(1997), the Forest Act (1927). In addition the Land Acquisition Act (1894) also provides powers in respect of land
acquisition for public purposes. There are also several other items of legislation and regulations which have a
bearing on the subproject or general environmental measures.
2.1 The ADB Environmental Assessment Guidelines
ADB’s guidelines for Environmental Impact Assessment (EIA) for the developing countries in Asia 13.
1997 is a useful tool for the environmental assessment for project loans. It is a useful guide for identifying
impacts, and designing mitigation measures and monitoring requirements for the specific projects in the
industrial, energy, social infrastructure, agriculture and natural resources, and transport sectors.
ADB’s Environmental Assessment Guidelines, 2003, describe ADB’s policies and procedures for 14.
preparation of IEE or EIA report for any project under consideration. It also provides strategic tools such as
country environmental analysis (CEA) and strategic environmental assessment (SEA). The guide is developed to
harmonize the procedures of multilateral banks development. These guidelines also specify the content and
format to be followed for preparation of IEE.
2.2 Statutory Framework
The Constitution of Pakistan distributes legislative powers between the federal and the provincial 15.
governments through two ‘lists’ attached to the Constitution as Schedules. The Federal List covers the subjects
over which the federal government has exclusive legislative power, while the Concurrent List contains subjects
regarding which both the federal and provincial governments can enact laws. “Environmental pollution and
ecology” is included in the concurrent list; hence both the federal and the provincial governments can enact laws
on this subject. However, to date, only the federal government has enacted laws on environment, and the
provincial environmental institutions derive their power from the federal law. The key environmental laws
affecting this subproject are discussed below.
2.2.1 Pakistan Environmental Protection Act, 1997
The Pakistan Environmental Protection Act, 1997 is the basic legislative tool empowering the 16.
government to frame regulations for the protection of the environment. The act is applicable to a wide range of
issues and extends to air, water, soil, marine, and noise pollution, as well as to the handling of hazardous
wastes. The key features of the law that have a direct bearing on the proposed subproject relate to the
requirement for an initial environmental examination (IEE) and environmental impact assessment (EIA) for
development subprojects. Section 12(1) requires that: “No proponent of a subproject shall commence
construction or operation unless he has filed with the Federal Agency an initial environmental examination [IEE]
or, where the subproject is likely to cause an adverse environmental effect, an environmental impact assessment
[EIA], and has obtained from the Federal Agency approval in respect thereof.” The Pakistan Environmental
Protection Agency has delegated the power of review and approval of environmental assessments to the
provincial environmental protection agencies, in this case the Khyber Pakhtunkhwa EPA.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2-2
2.2.2 National Conservation Strategy (NCS) – Pakistan
The National Conservation Strategy (NCS) – Pakistan, as approved by the Federal Cabinet in March 17.
1992 is the guiding document on the environmental issues in the country (Ref. EUAD / IUCN, 1992). The NCS
outlines the country’s primary approach towards encouraging sustainable development, conserving natural
resources, and improving efficiency in the use and management of resources.
The NCS has 68 specific programs in 14 core areas in which policy intervention is considered crucial 18.
for the preservation of Pakistan’s natural and physical environment. The core areas that are relevant in the
context of the envisaged project are pollution prevention and abatement, restoration of supporting forestry and
plantations, and preservation of cultural heritage.
2.2.3 Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, 2000
The Pakistan Environmental Protection Act, 1997 (PEP Act) provides for two types of environmental 19.
assessments: initial environmental examinations (IEE) and environment impact assessments (EIA). EIAs are
carried out for subprojects that have a potentially ‘significant’ environmental impact, whereas IEEs are conducted
for relatively smaller subprojects with a relatively less significant impact. The Pakistan Environmental Protection
Agency Review of IEE and EIA Regulations, 2001 (the ‘Regulations’), prepared by the Pak-EPA under the
powers conferred upon it by the PEP Act, categorizes subprojects for IEE and EIA. Schedules I and II, attached
to the Regulations, list the subprojects that require IEE and EIA, respectively.
The Regulations also provide the necessary details on the preparation, submission, and review of 20.
IEEs and EIAs. The following is a brief step-wise description of the approval process:
(i) A subproject is categorized as requiring an IEE or EIA using the two schedules attached to the
Regulations.
(ii) An EIA or IEE is conducted as per the requirement and following the Pak-EPA guidelines.
(iii) The EIA or IEE is submitted to the concerned provincial EPA if it is located in the provinces or the
Pak-EPA if it is located in Islamabad and federally administrated areas. The Fee (depending on the
cost of the subproject and the type of the report) is submitted along with the document.
(iv) The IEE/EIA is also accompanied by an application in the format prescribed in Schedule IV of the
Regulations.
(v) The EPA conducts a preliminary scrutiny and replies within 10 days of the submittal of a report, a)
confirming completeness, or b) asking for additional information, if needed, or c) returning the report
requiring additional studies, if necessary.
(vi) The EPA is required to make every effort to complete the IEE and EIA review process within 45 and
90 days, respectively, of the issue of confirmation of completeness.
(vii) Then the EPA accords their approval subject to certain conditions:
(viii) Before commencing construction of the subproject, the proponent is required to submit an
undertaking accepting the conditions.
(ix) Before commencing operation of the subproject, the proponent is required to obtain from the EPA a
written confirmation of compliance with the approval conditions and requirements of the IEE.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2-3
(x) An EMP is to be submitted with a request for obtaining confirmation of compliance.
(xi) The EPAs are required to issue confirmation of compliance within 15 days of the receipt of request
and complete documentation.
(xii) The IEE/EIA approval is valid for three years from the date of accord.
(xiii) A monitoring report is to be submitted to the EPA after completion of construction, followed by annual
monitoring reports during operation.
Distribution lines and grid substations of 11 kV and above are included under energy subprojects in 21.
Schedule II, under which rules EIA is required by GoP. Initial environment examination (IEE) is required for
distribution lines less than 11 kV and large distribution subprojects (Schedule I). A review of the need for EIA/
IEE submission is therefore required by the relevant EPA, in this case the Khyber Pakhtunkhwan Environment
Protection Agency (EPA) as the proposed subproject will be located in KP.
2.2.4 NTDC Safety Considerations
NTDC Design Directorate has issued safety considerations which must be borne in mind during 22.
selection of route for a Transmission Line. The main points of the guidelines are:
� Operation in environmentally sensitive areas with special respect for fragile ecosystems and their
inherent biodiversity are to be avoided to the extent possible;
� Similarly, ROW for a Transmission Line through natural features like mountains, hilly terrain
susceptible to landslides, large lakes, reservoirs, marshes, human habitations and reserved forests or
national parks are to be avoided to the extent possible;
� ROW is selected after due consideration for location of telecommunication lines and railway circuits to
avoid electrical interference due to mutual induction;
� Residential structures are kept a minimum of 12m out from the plumb line of the outer conductor in
the ROW. However, in the absence of an alternative alignment, an exception can be made for farm
buildings and single floor factory buildings, provided neither is used for purposes of residence;
� Innovative technologies and latest equipment must be adopted or used to abate pollution in
construction activities and operations;
� Routes of Transmission Lines are avoided to the maximum extent through areas of cultural or
historical importance and religious places;
� Tubewells and open wells using a surface pump are not permitted under high voltage conductors as
piping and cranes used to recondition such wells could make contact with high voltage conductors;
� Existing orchards can remain within the ROW although Towers are kept out of orchards wherever
possible. Orchards are to be over-sailed by a clearance of 6m above the height of a mature orchard
whereas all other trees are to be removed;
� Brick kilns should be kept at 30m outside the centerline of ROW;
� Alternative route alignments should be used if any school, rural dispensary, mosque or local shrine
(ziarat) falls within 200m of the centerline of a planned route;
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2-4
� Existing open wells and hand pumps can remain under high voltage conductors, provided open wells
are capped;
� Selection of sites for Tower foundation and Tower erection is made consciously on stable surfaces
and by rejecting sites susceptible to erosion, slips and landslides;
� Alignment of the Transmission Line is made by NTDC after discussions with key persons of the area
and by avoiding properties and infrastructure to the extent feasible;
� Spacing between Towers/poles may not be uniform and ranges could vary for physical and other
considerations, such as crossing of main roads, residential areas, streams and canals and trees and
for avoiding graveyards and big ditches in between Towers/poles;
� The route alignment of the Transmission Line, location of the Towers/poles and the corridors are
identified by NTDC;
� The main consideration relating to public safety is a safe horizontal and vertical distance of conductor
from ground level to prevent electrocution of people or animals under the Transmission Line. A
corridor having a minimum width of 30m, clear of all obstructions, is provided for extra high voltage
(500KV and 220KV) Transmission Lines (half on either side from the centerline). However, general
farming within this corridor is allowed and tree plantations that do not exceed a height of 1.5m are
also allowed to remain under the lines. Similarly, open wells, including Persian wheels, can remain
under Transmission Lines. Tubewells and pumps are not permitted under high voltage conductors,
because piping and cranes used to refurbish such wells may come into contact with the lines; and
� No residential or other public buildings such as factory, school, hospital and mosque, except for
graves/graveyards, are permitted within the corridor. However, farm buildings which are used for
residential purposes may remain under extra high voltage lines, provided vertical clearance of at least
8m is maintained. The height of Towers can be increased to accommodate such buildings.
2.2.5 National Environmental Quality Standards - 2010
The National Environmental Quality Standards (NEQS) were first promulgated in 1993 and have been 23.
amended in 1995 and 2000. They have been revised and the latest NEQS were issued in 2010. The following
standards that are specified in the NEQS are relevant to the proposed Subproject (See detailed Tables in
Appendix III).
NEQS for Ambient Air – November, 2010 state the Maximum allowable concentration of pollutants (9 24.
parameters) in gaseous emissions from vehicle exhaust.
NEQS for Drinking Water Quality 2010 describe the drinking water properties by outlining the defined 25.
physical and chemical parameters.
NEQS for Noise – November 2010 states the maximum allowable limit of noise arising from vehicles 26.
in decibels (dB) separately for day and night times.
NEQS for Waste Effluents 2000 states the Maximum allowable concentration of pollutants (32 27.
parameters) in municipal and liquid industrial effluents discharged to inland waters, sewage treatment facilities,
and the sea.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2-5
2.2.6 The Constitution of Pakistan 1973
It contains concurrent legislative power to federation and provinces to legislate in respect of 28.
environment and ecology (Article 142(b), Clause 24). Any gaps in the environmental law can be referred to
National as well as the provincial assembly for passage of an appropriate law.
2.2.7 Pakistan Penal Code 1860
It treats pollution and destruction of ecology as a mischief and makes it a public offence. The 29.
Pakistan Penal Code further prohibits corrupting and fouling water, any public spring, reservoir or river or
rendering it less fit for the purpose for which it is ordinarily used.
2.2.8 The Drainage Act 1973
The Act binds the public water users to restore the environment of the water bodies, should there be 30.
any damage by the community in any way.
2.2.9 Local Government Ordinance 1979
The ordinance empowers Zila Councils to control environmental pollution by preparing and 31.
implementing appropriate schemes to protect air, water and land in their respective jurisdictions.
2.2.10 The Telegraphy Act 1910
This act was promulgated for installation of telegraph polls and stringing. This act makes a provision 32.
of installing poles/towers without acquiring any land. However provision is there for temporary acquisition of land
during the construction period. As such compensation is made for the loss of crop for a specific period.
2.2.11 The Khyber Pakhtunkhwa (KP) Wildlife (Protection, Preservation, Conservation and
Management) Act 1974
The Act provides full protection to the listed birds and animals and their habitat including the 33.
migratory ones.
2.2.12 Guidelines for Sensitive and Critical Areas
Specifying the sensitive and critical areas in Pakistan, these guidelines apply to both the natural 34.
environment and cultural aspects of Pakistan.
2.2.13 The Forest Act 1927
The Act provides full protection to the reserved forests as well as to wildlife habitats. The Act also 35.
prohibits certain acts in protected forests.
2.2.14 The Antiquities Act 1976
The Act provides full protection and safety to archives, monuments, physical cultural heritage or 36.
chance finds and binds communities to cooperate, collabourate and report to the archeological department.
2.2.15 Factories Act 1934
Permission to establish an industry along the road can only be permitted by Government of Khyber 37.
Pakhtunkhwa.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2-6
2.2.16 The Public Health (Emergency Provision Act 1954 read with West Pakistan Epidemic Control
Act 1958) Act
These two laws cover the preservation of human health by prohibition of any disease, safeguarding 38.
the public health and providing and maintaining adequate medical services and other services essential to the
health of communities in the project area. Protection against HIV/AIDS and infectious diseases like Cholera and
Hepatitis B in labour camps would come under the same preview.
2.2.17 Explosive Act 1884
Under the Explosive Act 1884, the Project Contractors are bound by regulation on properly and 39.
securely handling, transporting and using explosives during quarrying, blasting and any other purpose. A prior
notice has to be given to local public and road users in collabouration with Resident Engineer.
2.2.18 Conventions, Protocols, Agreements and Understandings at International Level
On international level Pakistan is a signatory to a number of conventions, agreements, protocols and 40.
understandings. Not all of these may be directly applicable to this project but most important of these are listed
below for any possible reference.
• Convention on Biological Diversity popularly called the Earth Charter (1992)
• Convention on wetlands of international importance especially wetland habitats (Ramsar 1971)
• Convention on conservation of Mitigatory migratory species of Wild Animals (Bonn 1979) a follow up
of Ramsar 1971
• ILO convention No. 62 regarding ergonomic limitation of labour
2.2.19 Employment of Child Act, 1991
Article 11(3) of the Constitution prohibits employment of children below the age of fourteen years in 41.
factories, mines or any other hazardous employment. The Employment of Child Act, 1991, was accordingly
enacted to comply with the Constitutional provision as also abide by international conventions and treaties in
order to prohibit child labour.
2.2.20 Labour Laws
Construction and operational activities during project implementation can affect occupational health of 42.
workers. Employers are required to abide by labour laws in respect of their own employees and also to ensure
that contractors also follow the relevant labour laws and rules relating to safety of the workforce and creating a
healthy working environment. The proponents shall ensure that workers engaged at project site are not exposed
to any danger by monitoring the contractor’s work frequently.
2.2.21 Electricity Act IX of 1910 with Electric Rules 1937
Electricity Act 1910 and rules of 1937 are related to the supply and use of electrical energy in 43.
Pakistan. This Act will apply together with supplementary rules issued from time to time. It states the laws of
electricity distribution system and the terms and conditions relevant to electric supply. It also states rules for
abiding to the license provision. In a nutshell it outlines safe and practical distribution of electric Transmission
lines, imposing penalties for those not abiding by the Act.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
3-1
CHAPTER - 3: DESCRIPTION OF THE PROJECT
3.1 Type of the Project
The subproject has two components the grid station and transmission line. The 220 kV grid station 44.
and transmission line (total 2 km) will be located in KPK Province. The grid station will have equipment including
220 kV substation with 3*250 MVA Transformers.
3.2 Categorization of the Project
As studied locally, and as learnt from the experience of similar projects financed by ADB for WAPDA, 45.
the project does not cause high environmental sensitivity as per ADB classification of development projects.
Either the project shall have negligible or conveniently mitigable environmental impacts. Hence it qualifies to fall
in Category B project as per ADB guidelines. Accordingly its Environmental Assessment has been done at a
manageable environmental sensitivity level and an Initial Environmental Examination (IEE) has been produced to
provide an Environmental Assessment cover to the Project. In the chapters to follow, therefore, the study shall
meet the requirements of an IEE as per latest guidelines provided by ADB.
3.3 Need for the Project
The conditions of the power distribution system in Pakistan are inadequate to meet rapidly growing 46.
demand for electrical power. This situation limits national development and economic growth. Electricity demand
is expected to grow by 7.80% per annum during next 10 years over the period 2009-19. The existing power
distribution infrastructure has to be improved and upgraded to ensure a reliable power supply to increasing
number of industrial, agricultural, commercial, and domestic consumers. The overall contribution of power
infrastructure also requires institutional arrangements and capacity that support strategic management of the
sector, and planning and management of investments. Overall the proposed MFF facility has been designed to
address both investment and institutional aspects in the electrical power sector.
As the result of this, enhancement in capacity of NTDC transmission system is required for power 47.
evacuation. The proposed project has therefore been prepared to meet the requirement which will also result in
overall power efficiency and stability to deliver adequate & quality power to the consumers.
Main objective of project is to enhance the transmission capacity of NTDC system by addition of new 48.
220 kV Nowshera Substation to meet the growing power demand of DISCOs, particularly PESCO.
• This improvement in system will help to bridge the demand supply gap to eliminate the sever load shedding of the country.
• Improvement and enhancement in overall power system efficiency, reliability and power supply position in PESCO area, particularly in the vicinity of Malakand, Charsadda and Mardan.
• Improvement in voltage profile of 132 kV Grid stations in PESCO area.
3.4 Location and Scale of the Project
WAPDA Tranch IV Nowshera subproject consists of a new 220 KV Grid Station along with its allied 49.
transmission line. The proposed site is located adjacent to Cherat Road some 10 Km on West side of G. T. Road
between towns of Nowshera and Pubbi. The link road connecting to the proposed site with G. T. road is a single
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
3-2
lane metalled road. The GPS coordinates of the proposed site are 33o 56’ 31.28’ N and 50o 55’ 71” E (See Figure
1.2 and 1.3).
The proposed site is a 450m x 350m piece of community grazing land situated lengthwise about 5 km 50.
short of Cherat Cement Factory. The area is semi-barren and supports grass and semi-arid zone shrubs and
small trees only. The NTDC has already initiated the land acquisition process in collaboration with KP Revenue
Department.
3.5 Design Criteria
3.5.1 Design Criteria for Grid Station
The layout plan of a substation which involves various installations of equipment, control room and 51.
ancillary facilities are standardized by NTDC.
3.5.2 Design Criteria for Transmission Lines
The NTDC has developed design parameters for the planning and design of transmission systems in 52.
Pakistan (see table below). The design parameters are based on standard NTDC’s existing specifications and
practices for the existing as well as proposed Grid Stations and transmission lines.
ADB: Asian Development Bank AM: Assistant Manager AP: Affected Party C&W: Communication & Works DFO: District Forest Officer DM: Deputy Manager DO: District Officer EMA: External Monitoring Agency GM: General Manager LAC: Land Acquisition Collector PHE: Public Health Engineering PMC: Project Management Consultants
- Manager (E&SIC) - DM (Environment) - AM (Social Safeguards) - AM (Environment)
- AM (MIS/ Data Management)
Grievance Redress Committee (GRC)
- Executive Engineer (NTDC) - DO (Revenue)/ LAC - Representatives of E&SIC - AM (Social Mobilization)
- Representative of APC
PMU
(GM Projects)
Affected Persons Committee
External Monitor/ EMA
Contractor
Project Management
Consultants (PMC)
- DO (R)/ LAC - Executive Engineer (NTDC) - DO (Agri.) - Directorate (Horticulture) - DFO - C&W Department
- WAPDA
- PHED
- Other concerned (PHE)
Environmental &Social
Impact Cell
Affected Party
(AP)
NTDC
ADB (Coordination)
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
6-3
The EMP was prepared taking into account the capacity of the NTDC to conduct environmental 168.
assessments of the subprojects. But it is envisaged that the NTDC’s Environmental and Social Impact Cell
(ESIC) will conduct monitoring of subproject to check the compliance of EMP provisions and will obtain
environmental approval from EPA Khyber Pakhtunkhwa. The ESIC is composed of one Manager, one Deputy
Manager, and three Assistant Managers (refer to Fig 6.1). Most of the environmental work is delegated to
consultants. Specific areas for immediate attention are in EMP auditing, environmentally responsible
procurement, air, water and noise pollution management, Social and ecological impact mitigation. It is
recommended that an environmental specialist should be made part of team of supervisory consultants for
effective monitoring of EMP provisions.
6.2 Grievance Redressal System
This section describes mechanism to receive and facilitates the resolution of affected party including 169.
women’ concerns and grievances. A grievance mechanism will be available to allow an AP appealing any
disagreeable decision, practice or activity arising from land or other assets compensation. APs will be fully
informed of their rights and of the procedures for addressing complaints whether verbally or in writing during
consultation, survey, and time of compensation.
APs/ local community will enter their complaints/ concerns and issues formally including the 170.
information of date, name and address of complainant, description of complain. The Assistant Manager (social
mobilization) at PIU will maintain a register named as “community complaint register (CCR)”. The register will
include the information as date, name and address of complainant, description of complaints, and will enter the
complaints in a date covering the minimum information of name and address of complaint, description of
complaints, action taken, status of redress of complaints and reasons in case issue not resolved.
GRC will work at field level, while unsettled issues will be referred to the PMU at sub-project level. 171.
The field level PIU (AM Environment) will inform the affected persons about GRC and its mechanism by passing
the information at known places.
Efforts will be made to avoid the APs/ community concerns by implementing the sub-project in 172.
accordance with the EMP, i.e. proper information disclosure, community consultations, payments as per
entitlements and coordination with APs/ APC, PIU and PMU. However, a Grievance Redress Committees (GRC)
will also be established to redress the unresolved issues.
The composition of GRC will as below: 173.
GRC at PIU Level
i). Executive Engineer (NTDC) ii). DO (Revenue)/ LAC iii). Representative of E&SIC iv). Assistant Manager (Social Mobilization)/ Social mobilizer v). Representative of Affected Person Committee (APC) vi). Patwari
A comprehensive grievance redress process regarding land compensation and other compensation is 174.
described below:
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
6-4
Table 6.1: Grievance Redress Process
Land / Crop Compensation Issues Other Items Compensation Issues
• First, complaints will be redressed at field
level through the involvement of PIU and
APC as well as other local committees.
• First, complaints will be redressed at field level
through the involvement of PIU and APC as well
as other local committees.
• If issue is unresolved, then it will be lodged
to the DO (Revenue)/ LAC who will have 14
day to make decision on it.
• If no solution is accomplished, then grievance will
be lodged to GRC.
• The GRC will provide the decision within 3 weeks.
The GRC decision must be in compliance with this
EMP and provisions given in the EMP.
• If issue still unsettled, then grievance will be
forwarded to GRC.
• GRC will provide decision within 3 weeks,
which should be in compliance with the
EMP and provisions given in the EMP.
• If the grievance redress system does not satisfy
the APs, then, the grievance can be submitted to
the GM Projects (PMU), where decision will be
made in a period of 2 weeks.
• In case, the grievance redressal system
does not satisfy the APs, then they can
pursue by submitting their case to the
appropriate court of law.
• If still APs are not satisfied, they can pursue their
case to appropriate Court of law.
6.3 Environmental Management and Monitoring Cost
The total cost of the environmental management of the proposed project is about 2,293,250 Pak. 175.
Rupees. This includes the cost of environmental implementation of mitigation measure. Cost estimates of
mitigation and other environmental management measures are summarized
in Table – 6.2.
Table 6.2: Cost Estimates for Environmental Management
Particulars Details Total Cost
(PKR)
One dedicated
Environmental Officer
1 person for 2 years
(60,000/month) 1,440,000
Implementation of
Mitigation Measures
Provision of PPEs (Safety Goggles, shoes, safety
masks, eye shields, ear muffs, etc.) and first aid kits. 300,000
Procurement of one noise level meter 35,000
Arrangements for daily water sprinkling 250,000
Plantation of trees 50,000
Arrangements for careful collection and disposal of
wastes, oils, lubricants etc. 150,000
Contingency 3% contingency
Total 2,293,250
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
CHAPTER - 7: PUBLIC CONSULTATION
7.1 Approach to Public Consultation
The Public Consultation (PC) process with various stakeholders has been approached so as to 176.
involve public and other stakeholders from the earliest stages. Public consultation has taken place during the
planning and design and viewpoints of the stakeholders have been taken into account and their concerns and
suggestions for possible improvements have been included where appropriate. Much of the PC process to date
has revolved around concerns for the mitigation of construction impacts and the possible side effects from the
proximity of high voltage power lines.
There is also a requirement for ongoing consultation for preparation of Land Acquisition and 177.
Resettlement Plan (LARP), which is being documented separately. It is expected that this process will continue
through all the stages of the subproject in order to accommodate stakeholders' aspirations and to orient the
stakeholders positively towards the project implementation and where possible to harness cooperation over
access issues in order to facilitate timely completion.
7.2 Public Consultation Process
The public consultation process has commenced in the initial feasibility stages (prior to construction) 178.
in order to disclose the project information to the stakeholders and record feedback regarding the proposed sub
project and preferences. The stakeholders involved in the process were the population likely to be impacted
along the route of the proposed power lines; the village leaders and relevant departments.
Prior to the implementation of the sub project, the consultations have been carried out to support this 179.
IEE and recorded. The focus of attention has been the population near the proposed grid station and
transmission line that may be affected by the subproject. The level of engagement varied from the stakeholder to
stakeholder with some registering no major comment but it is noted that none registered any outright opposition
to subproject
Public consultation (PC) about the proposed project was held at the project site on August 6, 2014, 180.
with the assistance of notables from adjacent villages namely Jabba Khan, Bhakti, Shah Kot, Kotli Kalan, Kotli
Khurd an Saleh Khana. In all 27 notables participated whose names are given in section 7.4.
The women of the villages were consulted through elderly persons from each village because the 181.
Khattak tribe living in the area around the proposed project is tribalistic and highly conservative. The women
declined to get their names in the list. However their opinion was included in the overall public suggestions.
7.3 Results of Public Consultation
Generally people were found to be aware of the benefits of the establishment of the grid station. They had some
personal quarries but on overall scale almost all were in full support of the project. Local communities however
expressed that they would like to be part of continuous consultation process. Various concerns expressed by the
local community have already been listed in Table 7.1.
Local staff also joined the public consultation session and assisted in answering the public questions. 182.
Important questions asked by the public and answers answered by the consultation team are as follows:
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
Table 7.1: Details of Public Consultation session
Sr.
No. Question Answer
1 If you take away my land what shall I get in
return?
You will get due compensation for your land. The
rate shall be equal to average of last three years
sale price for similar land.
2 Can we get land for land?
There is a procedure for that but due to paveity of
land in the area; the preferred method is payment of
land.
3 The land is a grazing are which shall be
lost. Where shall we graze our animals?
This is a very small area of about 40 acres. Grazing
lands (barren lands) are in abundance in the area.
For this land you will get compensation.
4
We obtain fuel wood from trees and bushes
growing in the area. All these trees and
bushes shall be lost. What shall we do?
Compensatory fuel wood plantation shall be carried
out through forestry for which project shall supply
nursery and advice.
5
Shall there be reduction in load shedding
when this grid station is built? (Question
from women).
Obviously there shall be a positive effect on
electricity supply. The construction of this grid
station is a proof that electricity production at the
source shall improve.
6 Shall more land be acquired after the GS is
completed?
No. the land to be acquired now shall be adequate
for the project.
7
The ground water is sweet. Will enough
electricity be available for installation of tube
wells and expand agriculture?
Hopefully so. When the ground water is pumped out
it will not only help agriculture to expand but will
also help livestock and dairy farming.
8
“Hakoomat” is notorious for not paying
compensation in time. How about this
project?
This time Insha Allah you will have a better
experience.
9
We understand that a colony shall also be
built in the project. Can we use school and
dispensary built there in.
Yes your children can come to colony school and
dispensary.
10 How will the effluent sewage water from
colony be disposed?
A sump shall be constructed. In addition, the
excess water shall be treated in a tank and supplied
to agricultural fields.
11
A number of people living near the project
steal electricity by putting hooks. Can you
stop them?
We all shall try our best that the electricity is not
stolen and all villages get full load.
12 Where the electricity shall be taken from
GS?
There shall be two incoming and four outgoing lines
totaling to 220kV. The electricity shall be generated
in Ghazi Barotha Hydroelectric dam.
13 Will project support local schools?
The project may not be able help schools outside
the project area. However educational facilities
within the project shall be open to all.
14 Will project support local health system?
The project will rely on the medical facilities in
general area. Any dispensary service available in
project shall be open to public.
15 Will electricity be available to local people Electricity shall not be available free or at
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
Sr.
No. Question Answer
free or at concessional rates? concessional rates.
7.4 Records of Consultation
Table 7.2: Names of Local people consulted
Sr.No. Name of the Person Name of the Village
1 Shan Gul Jabba Khan
2 Fareed Gul Jabba Khan
3 Naek Muhammad Khattak Jabba Khan
4 Mumtaz Ali Jabba Khan
5 Dr. Tahir Jabba Khan
6 Habib Khan Bakhti
7 Hameed Khan Bakhti
8 Umar Ali Bakhti
9 Malik H. Bakhti
10 Imandar Shah Kot
11 Malik Shahzad Gul Shah Kot
12 Dr. Dildar Shah Kot
13 Zubair Shah Kot
14 Jaan Malik Shah Kot
15 Subhan Khan Shah Kot
16 Ashar Iqbal Kotli Kalan
17 Tariq Mehmood Kotli Kalan
18 Ghani Shah Kotli Kalan
19 Abdur Rahim Kotli Kalan
20 Zahid Farooq Kotli Khurd
21 Shehzad Kotli Khurd
22 Tariq Kotli Khurd
23 Inam Kotli Khurd
24 Noor e Islam Saleh Khana
25 Ilam Khan Saleh Khana
26 Dr. Khan Saleh Khana
27 Iqbal Shah Saleh Khana
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
CHAPTER - 8: CONCLUSIONS
8.1 Findings and Recommendations
This study was carried out at the planning stage of the project. Primary and secondary data were 183.
used to assess the environmental impacts. The potential environmental impacts were assessed in a
comprehensive manner. The report has provided a picture of all potential environmental impacts associated
with the Project. It was found that either potential impacts due to the project are not negative or are minor in
significance and can be mitigated with suitable mitigation measures.
There are some further considerations for the planning stages such as obtaining clearance for the 184.project under the Pakistan Environmental Protection Act (1997) but environmental impacts from the power
enhancements will mostly take place during the construction stage though these impacts can be mitigated.
Impacts during construction phase will mainly be dust pollution, noise pollution, soil contamination, waste
disposal, removal of flora, disturbance to fauna, wastewater generated by labour camps. In operational
phase impacts such as soil contamination due to oil/ grease or sewage and waste generation from colony
are anticipated which can be controlled by Good Housekeeping, proper drainage system and proper waste
disposal plan.
It is recommended that plans such as Waste Disposal, Traffic Control, Health and Safety, Good 185.
Housekeeping, temporary drainage system for labour camps be made before the construction phase so that
these can be implemented as soon as the construction of the project starts.
Baseline monitoring activities should be carried out during project detailed design stage to establish 186.
the baseline of parameters for checking during the construction stage. The monitoring schedule recommends
monitoring on two occasions at the site location. The results should be integrated with the contract
documentation to establish performance action thresholds, pollution limits and contingency plans for the
contractor’s performance.
During the commissioning phase noise monitoring should ensure that statutory requirements have 187.
been achieved. Monitoring activities during project operation will focus on periodic recording environmental
performance and proposing remedial actions to address any unexpected impacts.
8.2 Summary and Conclusions
As a result of overall findings of this study it is concluded that there are no major impacts associated 188.
with this project. The minor impacts that are identified can be mitigated or managed. Hence Environmental
Impact Assessment (EIA) for this project is not required.
The New 220KV Nowshera DGS is a feasible and sustainable option from the power transmission, 189.engineering, environmental, and socioeconomic points of view. Implementation of the EMP is required and
the environmental impacts associated with the subproject need to be properly mitigated, and the existing
institutional arrangements are available.
This IEE, including the EMP, should be used as a basis for an environmental compliance program 190.
and be included as an Appendix to the contract. The EMP shall be reviewed at the detailed design stage.
In addition, any subsequent conditions issued by PEPA as part of the environmental clearance should
also be included in the environmental compliance program.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
APPENDICES
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1
Appendix – I: Environmental Management Plan
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
DESIGN STAGE
1. Social Impacts
To ensure that the adverse
impacts on crops and trees
are mitigated according to
the LARP provisions.
1. NTDC to select the route in a way that
minimum impact on trees and crops occur.
2. Assessment of losses of tree and crops
damages (if any) during construction stage
3. Preparation of LARP for the proposed
project before commencement of
construction activities.
4. All the payments / entitlements are paid
according to the Entitlement Matrix,
prepared according to the LARP.
5. All the impacts identified by the IEE are
incorporated in to the project as well as the
LARP and relevant entitlements included
into the Entitlement Matrix.
Before the
construction of the
Grid Station,
associated TL and
all other structures,
the APs should be
given sufficient time
and compensation
to satisfy them.
Affected Persons will
be compensated by
NTDC through its
land acquisition
officers.
NTDC
MC and
External
Monitors
2. Hydrological
Impacts
To minimize hydrological
and drainage impacts
during constructions.
1. Hydrological flow in areas where it is
sensitive, such as water courses or bridges
and culverts.
2. Adequate culverts should be provided
where any water channel is needed to be
crossed for construction activities.
Before the
commencement of
construction
activities/during
designing stage.
Considered locations
are as in the design
report.
NTDC with the
Design
Consultant
NTDC
3. Noise Barriers
Ensure cumulative noise
impacts are acceptable in
operational phase.
1. Conduct detailed acoustic assessment for
all residential buildings, schools, (other
sensitive structures) within 30m of RoW.
2. If noise at sensitive receiver exceeds the
During detailed
design stage, and
include in the
contract.
Noise sensitive
locations to be
identified after
detailed design.
NTDC with the
design
consultant
NTDC and
Construction
Supervision
Consultant
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
permissible limit, the construction activities
should be monitored and controlled.
(CSC if any)
4. Waste Disposal
Ensure adequate disposal
options for all waste
including unsuitable soils,
scrap metal.
1. Identify sufficient locations for disposal of
transformer oils, unsuitable soils, scrap
metal “cradle to grave”.
2. Include in contracts for unit rates for re-
measurement for disposal.
3. Designate disposal sites in the contract and
cost unit disposal rates accordingly.
4. Prepare a PCB spill handling procedure
and equip such teams with special clothing,
steel containers and solvents.
1. During designing
stage no later
than pre-
qualification or
tender
negotiations.
2. Include in the
contract.
Locations approved
by EPA and NTDC
and waste disposal
local authorities.
EPA and
NTDC with the
design
consultant
NTDC and
CSC
5. Temporary
Drainage and
Erosion Control
Include mitigation in
Preliminary and detailed
designs for erosion control
and temporary drainage.
1. Identify locations where drainage or
irrigation crossing RoW may be affected by
works.
2. Include in protection works contract as a
payment milestone(s).
During designing
stage no later than
pre-qualification or
tender negotiations.
Locations based on
drainage or irrigation
crossing RoW.
NTDC and
Design
Consultant
NTDC and
CSC
6. Site-specific
environmental
management plan
Prior to the onset of the
construction, the
Construction Contractor
will be obliged to develop a
site-specific environmental
management plan
(SSEMP), which must be
submitted to NTDC for
approval.
• Define boundaries
• Identify sensitive receptors & environmental
values
• Specify construction activities
• Conduct risk assessment
• Assign environmental management measures
• Prepare monitoring plan
• Prepare site plans
3. • Prepare environmental work plan
Prior to
construction
Construction
contractor
CSC and
NTDC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
3
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
CONSTRUCTION STAGE
1. Hydrology and
Drainage Aspects
To ensure the proper
implementation of any
requirements mentioned in
EPA conditions of approval
letter in relation to
Hydrology of the project.
1. Consideration of weather conditions when
particular construction activities are
undertaken.
2. Limitations on excavation depths in use of
recharge areas for material exploitation or
spoil disposal.
3. Use of landscaping as an integrated
component of construction activity as an
erosion control measure.
4. Minimizing the removal of vegetative cover
as much as possible and providing for its
restoration where construction sites have
been cleared of such areas.
1. Prepare a
thorough plan to
be approved by
SC one month
prior to a
commencement
of construction.
2. Proper timetable
prepared in
consideration
with the climatic
conditions of
each area, the
different
construction
activities
mentioned here
to be guided.
1. Locations of each
construction
activity to be listed
by the engineer.
2. Special locations
are identified
along the RoW by
the contractor to
minimize
disturbance.
3. A list of locations
of irrigation
channels/ drains to
be compiled by the
contractor.
NTDC to
actively
supervise and
enforce
NTDC
2. Orientation for
Contractors, and
Workers
To ensure that the CSC,
contractor and workers
understand and have the
capacity to ensure the
environmental
requirements and
implementation of
mitigation measures.
1. NTDC to engage environmental specialist
in the PMC to monitor and progress all
environmental statutory and recommended
obligations.
2. Conduct special briefing for managers and /
or on-site training for the contractors and
workers on the environmental requirement
of the project. Record attendance and
achievement test.
3. Agreement on critical areas to be
Induction of all
relevant staff
required for
implementation of
EMP.
At early stages of
construction for all
construction
employees as far
All staff members in
all categories.
Monthly induction
and six month
refresher course as
necessary until
contractor complies.
Contractor
and the CSC
and record
details
NTDC & CSC
to observe and
record
success
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
4
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
considered and necessary mitigation
measures, among all parties who are
involved in project activities.
4. Continuous progress review and refresher
sessions to be followed.
as reasonably
practicable.
3. Water Quality
To prevent adverse water
quality impacts due to
negligence and ensure
unavoidable impacts are
managed effectively.
Ensure adverse impacts
on water quality caused by
construction activities are
minimized.
1. Compile temporary drainage management
plan one month before commencement of
works.
2. Proper installation of Temporary Drainage
(TD) and Erosion Control (EC) before
works within 50 m of water bodies.
3. Proper construction of TD and EC
measures, maintenance and management
including training of operators and other
workers to avoid pollution of water bodies
by the considerate operation of
construction machinery and equipment.
4. Storage of lubricants, fuels and other
hydrocarbons in self-contained dedicated
enclosures >50m away from water bodies.
5. Proper disposal of solid waste from
construction activities and labor camps.
6. Cover the construction material and spoil
stockpiles with a suitable material to reduce
material loss and sedimentation and avoid
stockpiling near to water bodies.
7. Topsoil stripped material shall not be stored
where natural drainage will be disrupted.
Prior to
construction, 50 m
from water bodies.
Timing will depend
on the construction
timetable.
Relevant locations to
be determined in the
detailed project
design
1. Contractor
CSC to
enforce
2. Contractor
has to check
water quality
and report to
NTDC.
3. CSC
supervises
monitoring
activities.
NTDC
review results
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
5
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
8. Borrow sites (if required) should not be
close to sources of drinking water.
4. Air Quality
To minimize effectively and
avoid complaints due to
the airborne particulate
matter released to the
atmosphere.
1. Control all dusty materials at source.
2. All heavy equipment and machinery shall
be fitted in full compliance with the national
and local regulations. (Relevant regulations
are in the Motor vehicles fitness rules and
Highway Act).
3. Stockpiled soil and sand shall be slightly
wetted before loading, particularly in windy
conditions.
4. Fuel-efficient and well-maintained haulage
trucks shall be employed to minimize
exhaust emissions.
5. Vehicles transporting soil, sand and other
construction materials shall be covered.
6. Limitations to speeds of such vehicles
necessary. Transport through densely
populated area should be avoided.
7. To plan to minimize the dust within the
vicinity of orchards and fruit farms.
8. Spraying of bare areas with water.
9. Concrete plants to be controlled with
statutory requirements should not be close
to sensitive receptors.
All construction
sites within 100 m
of sensitive
receivers.
A list of locations to
be included in
contract and other
sensitive areas
identified by the CSC
along the ROW
during works.
Contractor
should
maintain
acceptable
standard
CSC to
supervise
activities.
NTDC/CSC
5. Noise / Ground
Vibration To minimize noise level
increases and ground
1. All heavy equipment and machinery shall
be fitted in full compliance with the national
Maximum allowable
noise levels should
During construction
stage, the most
Contractor
should NTDC / CSC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
6
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
vibrations during
construction operations.
and local regulations and with effective
silencing apparatus to minimize noise.
2. As a rule, the operation of heavy equipment
shall be conducted in daylight hours.
3. Hammer- type percussive pile driving
operations shall be not be allowed at night
time.
4. Construction equipment, which generates
excessive noise, shall be enclosed or fitted
with effective silencing apparatus to
minimize noise.
5. Well-maintained haulage trucks will be
used with speed controls.
6. Contractor shall take adequate measures
to minimize noise nuisance in the vicinity of
construction sites by way of adopting
available acoustic methods.
be below 80 dB (A)
LEQ at the boundary
of the construction
site.
sensitive locations
need special
attention.
maintain the
acceptable
standards
CSC to
supervise
relevant
activities.
6. Soil Erosion/
Surface Run-off
Prevent adverse water
quality impacts due to
negligence and ensure
unavoidable impacts are
managed effectively.
To minimize soil erosion
due to the construction
activities of towers,
stringing of conductors and
creation of access tracks
1. Schedule works in sensitive areas (e.g.
rivers) for dry season
2. Temporary erosion control plan one month
before commencement of works.
3. Proper installation of TD and EC before
works within 50m of water bodies.
4. Meaningful water quality monitoring up and
downstream at any tower site within a river
or stream during construction. Rapid
reporting and feedback to CSC.
5. Back-fill should be compacted properly in
Because the area
can be subject to
un seasonal heavy
rain plan before and
during construction
(cut and fill, land
reclamation etc.)
while considering
the climatic
conditions.
1. Locations based
on history of
flooding problems.
2. A list of sensitive
areas during
construction to be
prepared by the
detail design
consultant in
consideration with
the cut and fill,
Contractor
and CSC
NTDC/
CSC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
7
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
for project vehicles. accordance with design standards and
graded to original contours where possible.
6. Cut areas should be treated against flow
acceleration while filled areas should be
carefully designed to avoid improper
drainage.
7. Stockpiles should not be formed within
such distances behind excavated or natural
slopes that would reduce the stability of the
slopes.
8. In the short-term, either temporary or
permanent drainage works shall protect all
areas susceptible to erosion.
9. Measures shall be taken to prevent
pounding of surface water and scouring of
slopes. Newly eroded channels shall be
backfilled and restored to natural contours.
10. Contractor should arrange to adopt suitable
measures to minimize soil erosion during
the construction period. Contractor should
consult concerned authorities in the area
before deciding mitigation measures.
11. Clearing of green surface cover to be
minimized during site preparation.
12. Replanting trees to be done before the site
is vacated and handed back to NTDC with
appropriate trees (other vegetation cover
as appropriate) to ensure interception of
rainwater and the deceleration of surface
land reclamation,
borrow areas etc.
3. Locations of all
culverts, irrigation
channels, road
and highway.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
8
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
run-off.
7. Exploitation
Handling,
Transportation
and Storage of
Construction
Materials
To minimize contamination
of the surroundings
(Due to Implementation of
works, concrete and
crushing plants).
1. In order to minimize and or avoid adverse
environmental impacts arising out of
construction material exploitation, handling,
transportation and storage measures to be
taken in line with any EPA
conditions/recommendations in approval.
2. Conditions that apply for selecting sites for
material exploitation.
3. Conditions that apply to timing and use of
roads for material transport.
4. Conditions that apply for maintenance of
vehicles used in material transport or
construction.
5. Conditions that apply for selection of sites
for material storage.
6. Conditions that apply for aggregate
production.
7. Conditions that apply for handling
hazardous or dangerous materials such as
oil, lubricants and toxic chemicals.
Update monthly
1. List of borrow
areas to be prepared
one month prior to
construction.
2. List of routes of
transport of
construction material
is to be prepared for
the contract and
agreed one month
prior to construction.
3. Report of vehicle
conditions is
available.
4. Map of locations of
storage is prepared
by the contractor.
5. Environmental
accident checklist
and a list of banned
substances are
included in the
contractor’s manual.
Contractor
and CSC to
agree format
of reporting
NTDC/CSC
8. Construction
Waste Disposal
Minimize the impacts from
the disposal of
construction waste.
1. Waste management plan to be submitted to
the CSC and approved by MC one month
prior to starting works.
2. Estimating the amounts and types of
Update monthly
A list of temporary
stockpiling areas and
more permanent
dumping areas to be
Contractor
and
CSC should
supervise and
NTDC/
CSC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
9
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
construction waste to be generated by the
project.
3. Investigating whether the waste can be
reused in the project or by other interested
parties.
4. Identifying potential safe disposal sites
close to the project or those designated
sites in the contract.
5. Investigating the environmental conditions
of the disposal sites and recommendation
of most suitable and safest sites.
6. Piling up of loose material should be done
in segregated areas to arrest washing out
of soil. Debris shall not be left where it may
be carried by water to downstream flood
plains, dams, lagoons etc.
7. Used oil and lubricants shall be recovered
and reused or removed from the site in full
compliance with the national and local
regulations.
8. Oily wastes must not be burned. Disposal
location to be agreed with local
authorities/EPA.
9. Machinery should be properly maintained
to minimize oil spill during the construction.
10. Solid waste should be disposed at an
approved solid waste facility, open burning
is illegal and contrary to good
prepared at the
contract stage for
agreement
take action to
complete
contractor’s
relevant
activities
according to
EIA/IEE/
EMP
requirement &
environmental
standards.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
10
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
environmental practice
9. Work Camp
Operation and
Location
To ensure that the
operation of work camps
does not adversely affect
the surrounding
environment and residents
in the area.
1. Identify location of work camps in
consultation with local authorities. The
location shall be subject to approval by the
NTDC. If possible, camps shall not be
located near settlements or near drinking
water supply intakes.
2. Cutting of trees shall be avoided and
removal of vegetation shall be minimized.
3. Water and sanitary facilities (at least pit
latrines) shall be provided for employees.
Worker camp and latrine sites to be
backfilled and marked upon vacation of the
sites.
4. Solid waste and sewage shall be managed
according to the national and local
regulations. As a rule, solid waste must not
be dumped, buried or burned at or near the
project site, but shall be disposed off to the
nearest sanitary landfill or site having
complied with the necessary permission of
local authority permission
5. The Contractor shall organize and maintain
a waste separation, collection and transport
system.
6. The Contractor shall document that all
liquid and solid hazardous and non-
hazardous waste are separated, collected
and disposed of according to the given
Update once a
month
Location Map is
prepared by the
Contractor.
Contractor NTDC/
MC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
11
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
requirements and regulations.
7. At the conclusion of the project, all debris
and waste shall be removed. All temporary
structures, including office buildings,
shelters and toilets shall be removed.
8. Exposed areas shall be planted with
suitable vegetation.
9. NTDC and Supervising Engineer shall
inspect and report that the camp has been
vacated and restored to pre-project
conditions.
10. Loss of Trees and
Vegetation Cover
of the Areas for
Towers and
Temporary Work-
space
To avoid several negative
impacts due to removing of
landmark, sentinel and
specimen trees as well as
green vegetation and
surface cover.
1. Land holders will be paid compensation for
their standing trees in accordance with
prevailing market rates (LARP). The land
holders will be allowed to salvage the wood
of the affected trees. They will also be
encouraged to plant suitable new trees in
lieu of tree removed.
2. The contractor’s staff and labor will be
strictly directed not to damage any
vegetation such as trees or bushes.
3. Clearing of green surface cover for
construction, for borrow of for development,
cutting trees and other important vegetation
during construction should be minimized.
4. Landscaping and road verges to be re-
installed on completion.
5. Compensatory planting of
Rerouting and site
identification during
design stage and
other matters
during construction
of relevant activities
A list of Locations
with a Map to be
compiled by the
design consultant
during detailed
design and CSC to
update as necessary.
Design
consultant,
Contractor
and CSC
NTDC/CSC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
12
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
trees/shrubs/ornamental plants (at a rate of
3:1) to contribute to the aesthetic value of
the area and compensate for the lost
capability of the area to absorb carbon
dioxide in line with best international
practice.
6. At completion all debris and waste shall be
removed.
7. All temporary structures, including office
buildings, shelters and toilets shall be
removed.
11. Safety
Precautions for
the Workers
To ensure safety of
workers
1. Providing adequate warning signs.
2. Providing workers with skull guard or hard
hat.
3. Contractor shall instruct his workers in
health and safety matters, and require the
workers to use the provided safety
equipment.
4. Establish all relevant safety measures as
required by law and good engineering
practices.
Prior to
commencement
and during
construction
Location to be
identified by the CSC
with contractor.
Contractor
and CSC
NTDC/
CSC
12. Traffic Condition
Minimize disturbance of
vehicular traffic and
pedestrians during haulage
of construction materials,
spoil and equipment and
machinery, blocking
access roads during works
1. Submit temporary haul and access routes
plan one month prior to start of works.
2. Formulate and implementation of a plan of
alternate routes for heavy vehicles.
3. Vicinity of schools and hospitals to be
considered.
Prior to and
throughout the
construction.
The most important
locations to be
identified and listed.
Relevant plans of the
Contractor on traffic
arrangements are
available.
Contractor
and Engineer
NTDC/CSC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
13
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
damage/maintenance
problems for roads and
bridges used by the
haulage trucks, dust
nuisance to school and
hospitals.
4. Installation of traffic warning signs, and
enforcing traffic regulations during
transportation of materials and equipment
and machinery. Conditions of roads and
bridges to be considered.
5. Provision of culverts on water channels and
drains.
6. Widening/upgrading of access paths/roads
13. Social Impacts
To ensure minimum
impacts from construction
labor force.
To ensure minimum
impacts on public health.
To ensure minimum effects
of indirect impacts of
constructions to the people
who are living close to the
boundaries of ROW; Dust,
Noise, Vibration and Rock
blasting effects etc.
To minimize access
problems for local
population during
construction.
1. Potential for spread of vector borne and
communicable diseases from labor camps
shall be avoided (worker awareness
orientation and appropriate sanitation
should be maintained).
2. Claims/complaints of the people on
construction nuisance/damages close to
ROW to be considered and responded to
promptly by the Contractor.
3. Contractor should organize temporary
means of access and make alternative
arrangements to avoid local community
impacts and to avoid such short-term
negative impacts.
Complaints of APs
to be solved as
soon as possible.
Necessary
evacuations to be
done as when
necessary if
construction
impacts are of
significant duration
and close to APs.
The whole project
area
Contractor
and the CSC
NTDC/
CSC
14. Institutional
Strengthening
and Capacity
Building
To ensure that NTDC
officials are trained to
understand and to
appreciate EMP.
Capacity building activities were taken by
Environmental Officer in Tranche 1 and 2.
Environmental and Social Impact Cell (ESIC) was
setup with in NTDC under GM (Projects) in
Initiate
preconstruction and
continue beyond
project completion
Awareness training
for all management
and senior staff in
NTDC at senior
NTDC NTDC & ADB
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
14
Environmental
Concern Objectives
Mitigation Measures (MM)
Recommended
Timing to
Implement
MM
Location to
Implement MM
Resp imp
MM
Resp
mon
MM
Tranche 1.
Trainings and provisions of proper monitoring
facilities to ECIS are recommended.
engineer and above
in PMU and related
units.
OPERATIONAL STAGE
1. Air Quality No Impacts NTDC NTDC
2. Noise No significant Impacts by Tranche-IV subprojects. All subprojects of
tranche-IV. NTDC NTDC
3. Compensatory
Tree Planting
Maintain survival of trees
planted
Employ landscaping contractor to monitor,
waterfeed and replace dead specimens as
necessary.
All subprojects of
tranche-IV. NTDC NTDC
4. Landslides and
soil erosion
Avoid landslips and loss of
productive land No significant Impacts.
All subprojects of
tranche-IV. NTDC NTDC
5. Water Quality Avoid disruption to water
bodies. No significant Impacts from this subproject.
All subprojects of
tranche-IV. NTDC NTDC
6. Crops and
Vegetation
Monitor impacts from
maintaining tree clearance Track growth of large trees under the conductors.
All subprojects of
tranche-IV. NTDC NTDC
7. Social safety
Impacts
Ensure no encroachments/
construction in the project
area. No violation of
clearances spaces.
Necessary signboards with limits of height
clearances to be placed properly.
Identify and prevent any illegal encroachments in
or immediate surroundings of the project area
All subprojects of
tranche-IV. NTDC NTDC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
15
Appendix – II: Environmental Monitoring Plan
FOR GRID STATION
Environmental
concern Performance indicator (PI) Frequency to monitor
Timing to check
PI
Locations to
implement PI
Responsible
to implement
PI
Resp PI
supervision
Design & Pre-construction Phase
1. Review of
Mitigation
Measures
Mitigations Matrix reviewed
During detailed design
(later monthly by
Contractor to cover any
unidentified impacts)
By completion of
detailed design.
All project
alignment Contractor
NTDC, ESIC cell /
ADB*
2. Social
Impacts
Inventory of losses, Property
acquisition, and compensation
completed to RP requirements.
Completed prior to
commencement of
construction
Before removal of
houses and
structures.
APs according to
RP & LAFC. NTDC’s Cell
NTDC, ESIC cell
/ADB*
3. Project
disclosure Design changes notified
During detailed design by
Contractor to cover any
access roads and
alignment changes,
additional Villages.
Completion of
detailed design.
All project
alignment. Contractor
NTDC, ESIC cell /
ADB*
4.
Environmenta
lly
Responsible
Procurement.
(ERP)
Contract follows ADB Guidelines on
ERP. Performance bond. Deposited
Contractual clauses include
implementation of environmental
mitigation measures tied to a
performance bond.
Once, before Contract is
signed.
Before Contract is
signed.
Method Statements
include resources
for mitigation
measures.
NTDC, ESIC
cell
NTDC, ESIC cell /
ADB*
5. Waste
disposal
Disposal options for all waste
transformer oil, residually contaminated
soils, scrap metal agreed with NTDC’S
and local authority.
Monthly to identify
sufficient locations for,
storage and reuse of
transformers and recycling
of breaker oils and
1.Prior to detailed
design stage no
later than pre-
qualification or
tender
Locations approved
by local waste
disposal authorities.
NTDC, ESIC
cell
consultant.
NTDC, ESIC cell /
ADB*
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
16
Environmental
concern Performance indicator (PI) Frequency to monitor
Timing to check
PI
Locations to
implement PI
Responsible
to implement
PI
Resp PI
supervision
disposal of transformer oil,
residually contaminated
soils and scrap metal
“cradle to grave”.
2. Include in contracts for
unit rates for re-
measurement for disposal.
3. After agreement with
local authority, designate
disposal sites in the
contract and cost unit
disposal rates accordingly.
negotiations
2. Include in
contract.
6. Noise and air
quality
mitigation in
design.
Changes in the design of construction
processes as approved by the
Contractors and appointed engineers
During detailed design by
Contractor.
Completion of
detailed design.
As defined in
Mitigation Plans.
NTDC, ESIC
cell
NTDC, ESIC cell /
ADB*
7. Hydrological
Impacts
Temporary Drainage in Mitigation
Measures
During detailed design by
Contractor and monthly to
cover any unidentified
impacts
One month before
commencement of
construction
Considered
locations to be as
identified in the
Detailed Drainage
Report.
Contractor NTDC, ESIC cell /
ADB*
8. Temporary
drainage and
erosion
control
Erosion Control and Temporary
Drainage completed.
During detailed design
updated by Contractor
monthly to cover any
unidentified impacts.
One month before
construction
commences.
All stream and river
crossings and
where slopes
indicate erosion will
be a problem.
Contractor. NTDC, ESIC cell /
ADB*.
9. Planning
construction
Use of land agreed with surrounding
residents & Villages.
During detailed design
updated by Contractor
One month before
construction
Locations agreed
NTDC’s cell in
Contractor/
NTDC Cell
NTDC, ESIC cell /
ADB*.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
17
Environmental
concern Performance indicator (PI) Frequency to monitor
Timing to check
PI
Locations to
implement PI
Responsible
to implement
PI
Resp PI
supervision
camps monthly to cover any
unidentified impacts.
commences. consultation with
community and the
Contractor.
facilitate.
10.Traffic
Condition
Temporary Pedestrian and Traffic
Management Plan agreed.
During detailed design
updated by Contractor
monthly to cover any
unidentified impacts.
One month before
construction
commences.
Locations agreed
with NTDC’S cell in
consultation with
community and the
Contractor.
Contractor NTDC, ESIC cell /
ADB*.
11. Institutional
strengthening
and capacity
building
1. Strengthening plan agreed for NTDC’s
cell.
2. International environment specialist
(IES)
3. Increase staffing of NTDC’s Cell.
4. Train NTDC’s Cell officials.
1. Once,
2. Once
3. Ongoing
4. Ongoing
1. As soon as
practicable
2, 3, 4. No later
than one month
before Contract
award.
Throughout the
project
NTDC’S
Project Cell.
NTDC, ESIC cell /
ADB*
Construction Phase
1.Orientation for
Contractor, and
Workers
1. Contractor agreed to provide training
to professional staff and workers.
2. Special briefing and training for
Contractor completed.
3. Periodic progress review sessions.
1. Once
2. Ongoing
3. Ongoing
1. Before contract
is signed
2. Before
construction areas
are opened up
3. Every six
months
All BOT staff
members in all
categories. monthly
induction and six
month refresher
course
Contractor
with IES
assistance
and record
details.
NTDC to observe
and record
success
2. Plans to
control
environmental
impacts
1. Drainage Management plan
2. Temp. Pedestrian & Traffic
Management plan,
3. Erosion Control & Temp. Drainage
plan
4. Materials Management plan,
Deliverable in final form to
NTDC’s cell one month
before construction
commences for any given
stretch.
One month before
construction
commences.
All of NTDC’S
alignment. Contractor
NTDC, ESIC cell /
ADB*.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
18
Environmental
concern Performance indicator (PI) Frequency to monitor
Timing to check
PI
Locations to
implement PI
Responsible
to implement
PI
Resp PI
supervision
5. Waste Management plan;
6. Noise and Dust Control plan,
7. Safety Plan
8. Agreed schedule of costs for
environmental mitigation.{N.B. Forest
Clearance and Compensatory Planting
plan is prepared by NTDC’s cell}
3. Water quality
Meaningful water quality monitoring up
and downstream during construction
within 100m of rivers. Rapid reporting
and feedback by NTDC’s
Once (line item when
opening up construction
near water bodies).
During detailed
design by
Contractor and
update to cover
any unidentified
impacts.
Locations to be
provided with the
detailed designs
including all bridges
during construction
within 100m of
rivers
Independent
experienced
laboratory.
NTDC, ESIC cell
4. Water
Resources
1. Availability of water acceptable to
community. No complaints.
2. Guidelines established to minimize
the water wastage during construction
operations and at worker camps.
1. Monthly
2. Monthly
Prior to
submission of
progress reports.
All local water
supply resources
and rivers.
Contractor NTDC, ESIC cell
5. Spoil disposal
and construction
waste disposal
1. Use of land agreed with surrounding
residents & Villages.
2. Waste Management Plan
implemented.
3 No open burning
Monthly (line item when
opening up construction).
Prior to
construction.
Update monthly.
All NTDC’S
alignment. Contractor NTDC, ESIC cell
6. Noise
Noise mitigation measures
implemented in line with guidelines for
noise reduction from ISO/TR11688-
1:1995(E)
Monthly (line item when
opening up construction).
Maximum
allowable noise
levels are
45dB(A)LEQ.
All NTDC’s
alignment.
Contractor
should
maintain the
accepted
NTDC, ESIC cell.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
19
Environmental
concern Performance indicator (PI) Frequency to monitor
Timing to check
PI
Locations to
implement PI
Responsible
to implement
PI
Resp PI
supervision
standards
7. Air quality Noise and dust control plan
implemented.
Monthly (line item when
opening up construction).
Prior to
construction.
Update monthly.
All NTDC’s
alignment. Contractor NTDC, ESIC cell
8. Soil
Contamination
Contractors workforce to instructed and
train handling of chemicals
Monthly (line item when
opening up construction).
Prior to
construction.
Update monthly.
All NTDC’s
alignment. Contractor NTDC, ESIC cell
9. Work Camp
Location and
Operation
1. Use of land agreed with surrounding
residents & Villages.
2. Waste Management Plan
implemented.
3 No open burning
Monthly (line item when
opening up construction).
Prior to
construction.
Update monthly.
All NTDC’s
alignment. Contractor NTDC, ESIC cell
10. Safety
Precautions for
Workers
Safety Plan submitted Once (update monthly as
necessary)
One month before
construction and
update quarterly.
All NTDC’s
alignment. Contractor.
NTDC (ESIC cell
to actively
supervise and
enforce.
11. Social
Impacts
1. Local labour is used and workforce
2. Local educated people for office
work.
3. Complaints on construction nuisance
damages close to ROW are responded
to promptly by the Contractor.
4. Quarterly meetings with local
VILLAGE for liaison purposes to
monitor complaints.
Monthly (line item when
opening up construction).
During
construction.
Update monthly.
All NTDC’s
alignment. Contractor NTDC, ESIC cell
12.
Enhancements
Contractor has included for some
enhancements in detailed designs
Including planting of trees in addition to
Once (update monthly as
necessary)
One month before
construction and
update quarterly.
All NTDC’s
alignment. Contractor.
NTDC Cell to
actively supervise
and enforce.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
20
Environmental
concern Performance indicator (PI) Frequency to monitor
Timing to check
PI
Locations to
implement PI
Responsible
to implement
PI
Resp PI
supervision
bioengineering such as in median
Operational Phase
1. Air Quality
1. Roadworthiness of vehicles on
NTDC’s
2. Monitor NO2 and PM10 as indicators.
1. Roadworthiness of
vehicles on NTDC’s Daily
during operations
2. Yearly intervals for 3
years after opening for
reassurance.
During operation.
5 locations on
NTDC’S alignment
nearest
settlements.
Contractor NTDC / and ESIC
Cell
2. Vegetation
1. Follow up on Tree Clearance and
Compensatory Planting Plan.
2. Records on survival of planted trees.
3. The compensatory planting
maintained
4. Audited report by ESIC cell for on-
site and off-site compensatory planting.
1) Quarterly
2) Quarterly
3) Quarterly
4) Quarterly
1) Throughout
project
2) Each of three
years after initial
planting.
3) Continuous for
three years after
project completion
4) For four years
after initial
clearance of the
forest.
All NTDC’S
alignment. Contractor NTDC
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
21
FOR TRANSMISSION LINE
Environmental concern Performance
indicator Frequency to monitor Timing to check
Locations to
implement
Responsible to
implement Resp supervision
Construction Phase for TL
1. Encroachment and
Physical Disfiguration
Landscape
Conditions, Baseline
Environment
Once (update monthly
as necessary)
One Month after
Construction Work
All NTDC’S
alignment Contractor NTDC, ESIC cell
2. Soil Erosion
Soil Compression,
Land Clearing,
Vegetation Removal
Once (update monthly
as necessary)
Prior to construction.
Update monthly
All NTDC’S
alignment Contractor NTDC, ESIC cell
3. Soil Contamination Fuels Spillage,
Chemicals Containers Monthly During Construction
All NTDC’S
alignment Contractor NTDC, ESIC cell
4. Ecological Resources Land Clearing,
Habitat destruction Monthly Update monthly
All NTDC’S
alignment Contractor NTDC, ESIC cell
5. Loss of Barani Crops
Number of People
affected due to
unavailability of
Opportunistic
Agriculture
Once (update monthly
as necessary) During Construction
All NTDC’S
alignment Contractor NTDC, ESIC cell
6. Local Community Work
Force
Disturbance due to
Stringing, Good
engineering practices
adopted
Once (update monthly
as necessary) Update monthly
All NTDC’S
alignment Contractor NTDC, ESIC cell
7. Safety Hazards Safety Precautions as
per ILO Monthly Update monthly
All NTDC’S
alignment Contractor NTDC, ESIC cell
Operational Phase for TL
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
22
Environmental concern Performance
indicator Frequency to monitor Timing to check
Locations to
implement
Responsible to
implement Resp supervision
1. Electric Current
Earthing of the
Towers, Safety Plan
by the contractor to
be followed
Monthly During Operation All NTDC’S
alignment Contractor
NTDC, ESIC Cell
2. Breaking of Conductors
Frequency of
Conductors Tripping,
Complaints reported
Quarterly Throughout the Project All NTDC’S
alignment Contractor
NTDC, ESIC Cell
3. Towers Collapse
Soil Geology, Climatic
Conditions, Records
on displacement (if
any)
Six Monthly During Implementation
Phase
All NTDC’S
alignment Contractor
NTDC, ESIC Cell
4. Avifauna Movement
Reported death of
Birds, Audit Report by
the ESIC cell
Quarterly After Transmission
Line is erected
All NTDC’S
alignment Contractor
NTDC, ESIC Cell
5. Safety
Security Plan, Good
Engineering
Practices, Complaints
on the Register
Quarterly During Operational
Phase
All NTDC’S
alignment Contractor
NTDC, ESIC Cell
Note: LAFC = Land Acquisition Compensation Fixation Committee. RAP, SIA and other engineering considerations may change, EIA=environmental impact Assessment. EPA= Environmental Protection Agency.
ADB * = ADB checks that processes have been completed and signed off by NTDC’s before moving to construction stage. MoFSC = Ministry of Forest and Soil Conservation.
ESIC = Environmental and Social Impact Cell (NTDC)
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
1
APPENDIX – III: PHOTOLOG
Photo N-1: General view of the proposed project site from road leading to Cherat Cement Factory
Photo N-2: At a number of places the water erosion during winter rains has built erosion pavement.
The stones covering the soil are mostly sandstones broken off from sandstones and quartziterocks
underneath.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
2
Photo N-3: At places the top soil has totally been eroded away and no vegetation is visible on surface.
At a distance towards the west of the area, a 220kV transmission line connecting Ghazi
Barotha hydroelectricity with existing GS at Nowshera.
Photo N-4: Prevalent current used of the land in project area is grazing. Sheeps are preferred animals
for the range land.
Power Transmission and Enhancement Multi-tranche Financing Facility Tranche-IV NTDC New 220 kV Nowshera Grid Station
Initial Environmental Examination
3
Photo N-5: Survey team with some local staff and some members of public who joined public