8/8/2019 Infrastructure Cost Estimates 24102008 http://slidepdf.com/reader/full/infrastructure-cost-estimates-24102008 1/6 Mudgeeraba to Tugun network upgrade To reinforce and ensure a dependable electricity supply to the rapidly growing southern Gold Coast, ENERGEX is proposing to build a 110kV powerline from Mudgeeraba to a new substation at Tugun. Purpose The following report outlines the preliminary and additional cost estimates for the proposed ENERGEX Mudgeeraba to Tugun network upgrade project. The cost estimates have been prepared for the community to better consider the nancial diffncs btwn difcult route assumptions. Scenarios The following scenarios have been prepared: 1. Uou powerline construction from Mudgeeraba (Varsity Lakes Transit Orientated Development) to Tugun (13 km) 2. O powerline construction from Mudgeeraba (Varsity Lakes Transit Orientated Development) to Tugun (13 km) 3. Uou powerline construction from Tallebudgera Creek Road, Tallebudgera to Duringan Road, Currumbin. (Originally released in discussion with key stakeholders June 2008) (4.5 km) 4. O powerline construction for the comparative section referred to in scenario 3 utilising the same overhead route adopted in scenario 1 5. Uou powerline construction from the Elanora Water Treatment Plant (North of Almond Court, Elanora) to ENERGEX’s Currumbin Substation, Station Street, Currumbin Waters 6. O powerline construction for the comparative section referred to in scenario 5 utilising the same overhead route adopted in scenario 1. Base Assumptions • Ttal ut lngth cnsidd f th cost estimates have excluded the section traversing the Varsity Lakes Transit Orientated Development, as this is being separately developed. The length of this section is approximately 1.2 km. The total length between the respective substations is approximately 14.2 km • Gnal cnstuctin stimats a based on actual costs of recently completed 110kV underground projects within the ENERGEX area • N ld suvy data cllctin has been undertaken to identify any spcic cnstuctin issus and general assumptions have been assumed consistently across the length of the project • Undgund cnstuctin typically involves considerable uncertainty over the entire length of the corridor. Overhead construction can have similar uncertainty at just the pole locations but this would involve a much smaller land area. Risk assessments in the estimates have accounted for this difference • Us f th jint cid f th installation of underground cables Infrastructure Cost Estimates Report Typical cable cross section for 110kV underground powerline
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
proposing to build a 110kVpowerline from Mudgeeraba
to a new substation at Tugun.
PurposeThe following report outlines thepreliminary and additional cost estimatesfor the proposed ENERGEX Mudgeerabato Tugun network upgrade project.
The cost estimates have been preparedfor the community to better consider thenancial diffncs btwn difcultroute assumptions.
ScenariosThe following scenarios havebeen prepared:
1. Uou powerlineconstruction from Mudgeeraba(Varsity Lakes Transit OrientatedDevelopment) to Tugun (13 km)
2. O powerline constructionfrom Mudgeeraba (Varsity LakesTransit Orientated Development)to Tugun (13 km)
3. Uou powerlineconstruction from Tallebudgera CreekRoad, Tallebudgera to DuringanRoad, Currumbin. (Originally releasedin discussion with key stakeholdersJune 2008) (4.5 km)
4. O powerline constructionfor the comparative section referredto in scenario 3 utilising the sameoverhead route adopted in scenario 1
5. Uou powerlineconstruction from the Elanora Water Treatment Plant (North of AlmondCourt, Elanora) to ENERGEX’sCurrumbin Substation, Station Street,Currumbin Waters
6. O powerline construction for
the comparative section referred to inscenario 5 utilising the same overheadroute adopted in scenario 1.
Base Assumptions• Ttal ut lngth cnsidd f th
cost estimates have excluded thesection traversing the Varsity LakesTransit Orientated Development, asthis is being separately developed.The length of this section isapproximately 1.2 km. The totallength between the respective
substations is approximately 14.2 km
• Gnal cnstuctin stimats abased on actual costs of recentlycompleted 110kV undergroundprojects within the ENERGEX area
• N ld suvy data cllctinhas been undertaken to identifyany spcic cnstuctin issus
and general assumptions have beenassumed consistently across thelength of the project
• Undgund cnstuctin typicallyinvolves considerable uncertaintyover the entire length of the corridor.Overhead construction can havesimilar uncertainty at just the polelocations but this would involvea much smaller land area. Riskassessments in the estimates haveaccounted for this difference
• Us f th jint cid f th
installation of underground cables
Infrastructure Cost Estimates Report
Typical cable cross section for 110kV underground powerline
has additional risks. These includestructural damage during transportconstruction, derating of the cable dueto additional soil cover, and relocationf th lin du t nal dsign changsby other infrastructure projects sharingthe corridor
• Undgund cnstuctin quishigh isk tchniqus t tavs thcks and th bstacls. Difcultis
have been experienced in underboringlarge creeks, which has resulted insignicant cst vuns
• N ppty acquisitin csts hav bnconsidered in any of the scenarios
• N appval csts csts f consultation have been considered inthe cost summaries, as these would becommon to all options
• N vgtatin wks hav bnconsidered in these cost estimates i.e:
• Landscaping / vgtatin
• Pvisin f vgtatin ffsts asoutlined in the Memorandum of Undstanding with th Dpatmntof Natural Resources and Water
• Pvisin / cntibutins f anyfauna corridors
• N dtaild glgical infmatinwas usd f cnsidatin f spcicconstruction impacts i.e:
• Acid Sulphat sils
• Cntaminatd lands
• N additinal csts hav bnconsidered for relocation of other utilityinfrastructure
• N csts hav bn includd f cnnctin / augmntatin at thsubstation for Mudgeeraba, Currumbinor Tugun, as this would be commonto all options
• N ail spcic cnstuctinaugmentation methods havebeen considered in the undergroundcost estimates.
Route Descriptions
Scio 1 – Mub to TuuUndergrOUnd solutio
The underground route has utilised theexisting overhead (scenario 2) routeas a basis with some minor amendmentsas outlined below:
a) Oyster Creek Drive to TallebudgeraCreek Road – the undergroundinghas followed closely with a proposedservice road rather than the foot of thenew motorway
b) Rees Court to K P McGrath Drive,Elanora – the underground route hascrossed under the motorway further south to avoid vegetation clearing
c) Sarawak Avenue to Station Street –the underground route has crossedunder the motorway at Sarawak Avenue,then underbored across CurrumbinCreek and progressed along StationRoad to minimise vegetation impacts
d) John Flynn Hospital to TugunSubstation – the underground routedeviates from the overhead corridor,adopting a more direct route to the
Tugun Substation.
Note: The same corridor has been adopted for
the section relevant for Scenario 5
(Refer to maps 1 and 2 – Pink line is Underground)
Scio 2 – Mub to TuuOverhead solutio
The overhead route cost estimate is basedon current publicly released informationand represents a corridor length of 13 km.
(Refer to maps 1 and 2 – Yellow line is Overhead)
Scio 3 – Tllbu Ck
to Cuumbi CkUndergrOUnd solutio
(Released previously in June 2008 through
discussions with key stakeholders and
community reference group)
The underground section of this routefollows the motorway along the easternside of the corridor from the northern endof Tallebudgera Creek to the southern endof Currumbin Creek. The remainder of theroute follows the existing overhead route.
(Refer to maps 1 and 2 – Purple line is Underground)
Scio 4 – Tllbu Ckto Cuumbi Ck Overheadsolutio
(Released previously in June 2008 through
discussions with key stakeholders and
community reference group)
Follows the existing overhead corridor
(Refer to maps 1 and 2 – Yellow line is Overhead)
Scio 5 – elo Wt Ttmt Plt to CuumbiSubsttio UndergrOUnd
solutio
This underground route utilises the existingoverhead route as a basis with some minor amendments asoutlined below:
a) Rees Court to K P McGrath Drive,Elanora – the underground route hascrossed under the motorway further south to avoid vegetation clearing, and
b) Sarawak Avenue to Station Street –the underground route has crossedunder the motorway at SarawakAvenue, then under bored across
Currumbin Creek and progressedalong Station Road to minimisevegetation impacts.
(Refer to maps 1 and 2 – Green line is Underground)
Scio 6 – elo Wt Ttmt Plt to CuumbiSubsttio Overhead solutio
This route follows the existing overhead corridor.
Total Cost Estimate Comparisons Scenario Length Cost ($M)
1 Mudgeeraba to Tugun UNDerGroUND solution 13.0 km (*) $83
2 Mudgeeraba to Tugun OVERHEAD solution 13.0 km (*) $20
3 Tallebudgera Creek to Currumbin Creek UNDerGroUND solution 4.5 km (#) $32
4 Tallebudgera Creek to Currumbin Creek OVERHEAD solution 4.5 km (#) $7
5 Elanora Water Treatment Plant to Currumbin Substation UNDerGroUND solution 4.4 km $28
6 Elanora Water Treatment Plant to Currumbin Substation OVERHEAD solution 4.4 km $7
Note: Please refer to the assumptions when considering the estimates above i.e: these gures do not include property acquisition costs, cost of approvals,
revegetation / landscaping costs, relocation of other utilities, infrastructure, consultation etc. (*)These estimates do not include 1.2 km Varsity Lakes Transit
Orientated Development section. (#) Originally released in discussion with key stakeholders, June 2008.
Overhead Structure• 22-25 m tall cnct pls
• Dubl cicuit 110kV pw lin
• ovhad and undslung ath wi
(Refer to maps 1 and 2 for location of the different scenarios)
50 to 75mm ASPHALT
COMPACTED LEAN
MIX CONCRETE
FLOWABLE FILL
CABLE PROTECTION
COVER STRIPS
NOT TO SCALE
TYPE: 110-E CONDUITS
SURFACE: PAVED CABLE
BEDDING: FTB
BACKFILL: FTB/LEANMIX
650
100(NOM)
1400
A P P R O X 1 4 0 0
9 0 0 ( N O M
) 3 0 0
1 0 0 ( M A X
)
1 0 0 ( M I N )
1 5 0
7 5 ( N O M )
Reasonable consistant
Straight, neat cut on edges
FINISHED SURFACE LEVEL
ELECTRICAL
WARNING TAPES
100(NOM)
110kV trench cross-section
Underground Construction• Cnduit and cabl cnstuctin
• Maj itms includ all cablingquid f cnducts, athingand communications.
Ciil costuctio
• Maj itms includ all civil wksfor overhead structures andunderground trenches. Includespreparation, poles, excavation,backll and mval f spil. Includspvisin f plant, quipmnt andresources associated with the civilconstruction. Includes provisions for normally expected risks associatedwith such works. Excludes accesstacks, claing and -vgtatinbased remediation.
Mcicl Istlltio
• Major items include for overhead,conductor stringing and attachmentand for underground, all pullingof cables and jointing. Includespvisin f plant, quipmnt and
resources associated with themechanical construction.
Pojct ii
• Major items include planning,design, procurement, stakeholder communication and generalpjct cdinatin /administatin.Includes job factors, fees and costof capital provisions.
Milton BC QLD 4064If yu hav any futh qustins,please call us on our free callnumber 1800 025 158 or email us atthe address given above.For more information visitthe ENERGEX website onwww.energex.com.au/network
vsity Lks Uou
Queensland Transport (QT) is planning
to utilise land around the VarsityLakes Railway station as a Transport
Orientated Development (TOD). This willincorporate residential and commercial
development. As part of the planning
for this development QT has engagedENERGEX to undertake feasibility and
design work to underground a 1.2km
section of the existing Mudgeeraba toBurleigh 110kV overhead powerline
located in an easement alongside
Scottsdale Drive Varsity Lakes. Since
this corridor is also proposed to be used
for the Mudgeeraba to Tugun networkupgrade, the feasibility and design work
includes provision for undergrounding the
new powerline and other future 33kV and
11kV circuits.
In accordance with strict legislative and
plicy quimnts, this wk is bing
undertaken on a fully cost recoverable
basis fm th qusting paty, QT.
QT have not yet agreed to fund the
construction phase of this work as it
is subject to their approval after the
design estimates are complete. Should
this undergrounding work not proceed,ENERGEX proposes to install the