Top Banner
In the name of Allah the Most Gracious the Most Merciful
24

In the name of Allah the Most Gracious the Most Merciful

Feb 25, 2016

Download

Documents

aurla palmer

In the name of Allah the Most Gracious the Most Merciful. Construction Management and Planning. Float. Total Float is Calculated by Subtracting Early Start and Duration from the Activity’s Late Finish Time An Activity that has Zero Total Float is a Critical Activity - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: In the name of Allah the Most Gracious the Most Merciful

In the name of Allah the Most Gracious the Most Merciful

Page 2: In the name of Allah the Most Gracious the Most Merciful

2

Construction Management and Planning

Page 3: In the name of Allah the Most Gracious the Most Merciful

Float Total Float is Calculated by Subtracting Early

Start and Duration from the Activity’s Late

Finish Time An Activity that has Zero Total Float is a Critical

Activity An Activity’s Start may be Critical Even Though

an Activity itself may not be Critical Start Float may be Calculated by Subtracting

an Activity’s Early Start Time from Its Late Start

Time

Page 4: In the name of Allah the Most Gracious the Most Merciful

Float Finish Float is Calculated by Subtracting an

Activity Early Finish Time from its Late Finish

Time

Page 5: In the name of Allah the Most Gracious the Most Merciful

Project Scheduling

Probabilistic PERT

Page 6: In the name of Allah the Most Gracious the Most Merciful

History of PERT

• Project Evaluation and Review Technique (PERT)–U S Navy (1958) for the POLARIS

missile program–Multiple task time estimates

(probabilistic nature)–Activity-on-arrow network construction–Non-repetitive jobs (R & D work)

6

Page 7: In the name of Allah the Most Gracious the Most Merciful

PERT Probability Approach to Project Scheduling

• Activity completion times are seldom known with certainty.

• Completion time estimates can be estimated using the Three Time Estimate approach. In this approach, three time estimates are required for each activity:

a = an optimistic time to perform the activity m = the most likely time to perform the activity b = a pessimistic time to perform the activity

Page 8: In the name of Allah the Most Gracious the Most Merciful

PERT

–pessimistic time (a) - the time the activity would take if things did not go well

–most likely time ( m) - the consensus best estimate of the activity’s duration

–optimistic time (b) - the time the activity would take if things did go well

8

Page 9: In the name of Allah the Most Gracious the Most Merciful

3-Time Estimate ApproachProbability Distribution

• With three time estimates, the activity completion time can be approximated by a Beta distribution.

• Beta distributions can come in a variety of shapes:

a m b ba mm a b

Page 10: In the name of Allah the Most Gracious the Most Merciful

Mean and Standard Deviation for Activity Completion Times

• The best estimate for the mean is a weighted average of the three time estimates with weights 1/6, 4/6, and 1/6 respectively on a, m, and b.

• Since most of the area is with the range from a to b (b-a), and since most of the area lies 3 standard deviations on either side of the mean (6 standard deviations total), then the standard deviation is approximated by Range/6.

6

a-b=deviation standard the=

6b+4m+a= timecompletionmean the=

Page 11: In the name of Allah the Most Gracious the Most Merciful

The three assumptions imply that the overall

project completion time is normally distributed,

with:

The Project Completion Time Distribution

= Sum of the ’s on the critical path

2 = Sum of the 2 ’s on the critical path

Page 12: In the name of Allah the Most Gracious the Most Merciful

PERT analysis• Draw the network.• Analyze the paths through the network and find the

critical path.• The length of the critical path is the mean of the project

duration probability distribution which is assumed to be normal

• The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum

• Probability computations can now be made using the normal distribution table.

12

Page 13: In the name of Allah the Most Gracious the Most Merciful

Probability computation

13

• Determine probability that project is completed within specified time

Z =

x -

where = tp = project mean time

= standard deviationx = (proposed ) specified time

Page 14: In the name of Allah the Most Gracious the Most Merciful

Normal Distribution of Project Time

14

= tp Timex

Z

Probability

Page 15: In the name of Allah the Most Gracious the Most Merciful

15

Immed. Optimistic Most Likely Pessimistic

Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8B -- 1 4.5 5C A 3 3 3

D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7

Page 16: In the name of Allah the Most Gracious the Most Merciful

16

Page 17: In the name of Allah the Most Gracious the Most Merciful

PERT Example

17

Activity Expected Time (μ) Variance (σ2) (a + 4m + b)/6 [(b – a)/6]2

A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9

Page 18: In the name of Allah the Most Gracious the Most Merciful

18

Page 19: In the name of Allah the Most Gracious the Most Merciful

19

σ2path = σ2

A + σ2C + σ2

F + σ2I + σ2

K

= 4/9 + 0 + 1/9 + 1 + 4/9 = 2σpath = 1.414Mean project completion time = 23Proposed completion time = 24

z = (24 - 23)/(24-23)/1.414 = .71

From the Standard Normal Distribution table:

P(z < .71) = .5 + .2612 = .7612

Page 20: In the name of Allah the Most Gracious the Most Merciful

Using the PERT-CPM Template for Probabilistic Models

• Instead of calculating µ and by hand, the Excel template may be used.

• Instead of entering data in the µ and columns, input the estimates for a, m, and b into columns C, D, and E.– The template does all the required

calculations– After the problem has been solved, probability

analyses may be performed.

Page 21: In the name of Allah the Most Gracious the Most Merciful

Enter a, m, b instead of

Call SolverClick SolveGo to PERT OUTPUT worksheet

Page 22: In the name of Allah the Most Gracious the Most Merciful

Call SolverClick Solve

Page 23: In the name of Allah the Most Gracious the Most Merciful

To get a cumulativeprobability, entera number here

Page 24: In the name of Allah the Most Gracious the Most Merciful

P(Project is completed in less than 180 days)