Improvements to High Street and Kingstown Road (Route 108) Main Street to North Road South Kingstown, RI
20

Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Mar 19, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Improvements to High Street and Kingstown Road (Route 108)

Main Street to North Road

South Kingstown, RI

Page 2: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Project Aerial View

Page 3: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Purpose of Project

• To revitalize the roadway corridor

• Mitigate flooding in several problem areas through replacement of the drainage system

• Improve pedestrian safety 

• Improve sidewalks and enhance ADA compliance

Page 4: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Project Scope

• Pavement Replacement• New Sidewalks, Wheelchair Ramps, and Granite Curbing

• Stamped Concrete Crosswalks• Improved Signing and Pavement Striping• Drainage System Replacement/Catchment• Coordination with municipal utilities for advance contracts– Gas– Water

Page 5: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Traffic Data

Page 6: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Existing Pavement

Page 7: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Existing Pavement

Page 8: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Typical Section(Main Street to Schaeffer St)

Page 9: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Typical Section(Schaeffer St to Route 108)

Page 10: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Typical Section(High Street to Railroad Street)

Page 11: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Typical Section(Railroad Street to North Road)

Page 12: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Existing Sidewalks

Page 13: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Existing Sidewalks

Page 14: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Sidewalks / Wheelchair Ramps and Crosswalks

• Installation of new ADA compliant concrete sidewalk throughout entire length of High Street

• Installation of ADA compliant concrete wheelchair ramps at every street corner and crossing

• Replacement of crosswalks

• Installation of granite curbing

Page 15: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Crosswalks

Page 16: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

High Street Existing Structures/Pipes

Page 17: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Route 108 Flooding

Page 18: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Proposed Drainage 

• High Street– Entirely new closed system of pipes and structures– Improved collection on western side streets

• Route 108– Additional structures and pipes added to existing system to increase catchment and capacity

– Additional curbing added to more effectively define gutter lines and eliminate ponding

– Cleaning and flushing of existing pipes / structures to remain

Page 19: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Construction

• Construction anticipated to begin Spring 2014

• Traffic during construction will consist of a standard 1 lane closure with alternating traffic

• Work schedule to be coordinated with school calender

Page 20: Improvements to High Street - PowerPoint · Improvements to High Street ... • Stamped Concrete Crosswalks • Improved Signing and Pavement Striping • Drainage System Replacement/Catchment

Questions and Answers