Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse Logistics
26

Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Mar 28, 2015

Download

Documents

Sam Peck
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Implementing Material Resource Efficiency practices and Logistics

Malcolm WaddellConstruction Project Manager

MRE Guide Material Logistics Plans Reverse Logistics

Page 2: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

MRE Guide for Regeneration and Major Project Support

Page 3: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Regeneration

Linking the demolition and new-build stages to maximise resource efficiency.

WRAP regeneration guideBrings together:ICE Demolition ProtocolUsing reclaimed materialsGood practice site waste

managementIncreasing recycled content

Page 4: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Current Projects

• England• Moss Side, Manchester• Loam Pit Vale, Lewisham

• Scotland• Bishopsbriggs, Glasgow• Raploch, Stirling• Clyde Gateway• Dumfries and Galloway

Page 5: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Ongoing Work

Major Project Support– Work is being contracted.– Further five projects– Varied size and sector across England and

Wales– Client and Contractor Campaign Support

Page 6: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Material Logistics Plans

Page 7: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Material Logistics Plans

A tool to manage all materials from project conception through to demobilisation and completion.

Key aspects:Setting objectives and KPIs for

efficient material useMinimisation of materials through

attention to specifications, delivery & storage, handling & use, disposal

Identifying lessons learnt and best practice.

Page 8: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Participating developments & projects

Leith Docks, Western and Granton Harbour on Edinburgh Waterfront

CaltongateCentral Edinburgh

Page 9: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Participating developments & projects

Carmel CollegeSt Helens

Tubney BarnNear Oxford

Kennet IslandReading

Page 10: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Participating projects

Farringdon StationCentral London

CrossrailMaidenhead - London - Essex - Kent

Page 11: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Participating projects

Central St GilesCentral London

The Dartford HubDartford

HolboroughNear Maidstone

Page 12: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

A cross section

• Any type of project Housing - commercial - retail - public - schools

- transport - infrastructure

• Any size of project £ 16 billion - £600k

• Any location City centre - urban - rural

Page 13: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

How can material logistics help?

• Efficient construction• Reduced transport and associated CO2• Reduced productivity loss• Improved health & safety• Reduced damaged by:

Weather Bad storage conditions Unnecessary movements Poor handling

Page 14: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Strategies

• Just-in-time• On site logistics specialists• Construction consolidation centres• Off-site manufacture• 4th party logistics• On-site marketplaces• IT solutions

Page 15: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Traditional transport to site

Site

• Many separate deliveries• Un-coordinated arrivals • Risk of congestion on site and at gates• Many half empty lorries or …• Consignments too large• High stock levels on site• Empty return journeys• High traffic flow - high CO2

Page 16: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Construction Consolidation Centres CCC

Site

Concrete, steelwork, very large items, and full vehicle loads when required, go directly to site

• Contractors deliver to CCC

• Mixed loads from CCC• Daily deliveries - JIT• Logistics operator runs

the CCC• Transport to site • On site handling• Waste removed on

return journeys• Bulked up, compacted

etc at the CCC

Page 17: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Off site manufacturing OSM

• Controlled manufacturing environment

• Standardisation• Consistent quality• Shorter time on site• Design freeze• Packaging• Transport and Travel• Reduced cost and risk

Page 18: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

WRAP case studiesSpecific case studies examples developed by WRAP looking at:

Volumetric methods – CAD CAM software helps reduce waste <0.6% Pre-fabrication: Pods – post production waste <1%

Pre-cast concrete – Bison have reduced waste to landfill <1% using their system

Timber frame - <2% waste sent to landfill

Light Steel Frame – materials requirements down 5% and wastage reduced from 12% to <1%

Page 19: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

SECTION 1 RESPONSIBLE PERSONS, TRAINING AND COMMUNICATIONSECTION 2 TRAINING AND COMMUNICATIONS PLANSECTION 3 MATERIAL REQUIREMENTSSECTION 4 MATERIALS RECEIPT, STORAGE AND MANAGEMENT SECTION 5 MANAGEMENT OF SUB-CONTRACTORS SECTION 6 SITE MOBILISATION AND CONSTRUCTIONSECTION 7 PROJECT DEMOBILISATION AND COMPLETION SECTION 8 REVIEW

Material Logistics Plan

Page 20: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Implementation of MLP

Pilot project using WRAP

template

Internal review

Adapt and make part of

co procedures

Programme for co-wide

rollout

Monitor performance, SWMP data

Build own database of

KPIs

Continuous review of KPI and

procedures

Engage with contractors

Phase 1Phase

2Phase

3

Engage with contractors

Page 21: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Reverse LogisticsWAS620

Efficient use of vehicles visiting site – promoting better waste management

Page 22: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Materials arrive on site in delivery vehicles, are dropped off, and the vehicle leaves empty

Waste vehicles arrive on site empty and leave full with waste

The reverse logistics concept

A logistics operation that seeks to avoid the empty journeys, and promote the take-back of un-used and wasted materials could have a range of environmental benefits

Page 23: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

The concept

Take-back schemes are becoming more common offerings to UK construction sites

There is a real opportunity here to:

Promote the take-back of unused / waste product and packaging by delivery vehicles

Reduce vehicle movements and mileages associated with material supply and waste management

Reduce the environmental impact of construction

Page 24: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

The Reverse Logistics ModelExcel based model compares current against potential

The model reports the results in terms of:

The proportions of waste, recyclate and back-hauled material

The costs of material purchase, waste management and back-hauling

The number of miles travelled for delivery and waste travelled

The associated carbon footprint

Page 25: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Current Case Study – North Staffs Hospital (Laing O’Rourke)

Page 26: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse.

Any questions?