IH 35E Proposed Improvements Stakeholder Work Group Meeting October 1, 2008 1 Texas Department of Transportation Dallas District IH 35E Proposed Improvements 35E October 1, 2008 Stakeholder Work Group Meeting Texas Department of Transportation Dallas District 35E Recap Since Meeting No. 1 Project Overview Refined Modified Concepts Stakeholder Outreach Schedule Other Issues/Next Steps Agenda Agenda Texas Department of Transportation Dallas District 35E
10
Embed
IH 35E Proposed Improvements 35E - Keep It Moving Dallas · IH 35E Proposed Improvements Stakeholder Work Group Meeting October 1, 2008 4 Texas Department of Transportation Dallas
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
1
TexasDepartment
of Transportation
Dallas District
IH 35E Proposed Improvements
35E October 1, 2008Stakeholder Work Group Meeting
TexasDepartment
of Transportation
Dallas District
35E
Recap Since Meeting No. 1
Project Overview
Refined Modified Concepts
Stakeholder Outreach
Schedule
Other Issues/Next Steps
AgendaAgenda
TexasDepartment
of Transportation
Dallas District
35E
id404052359 pdfMachine by Broadgun Software - a great PDF writer! - a great PDF creator! - http://www.pdfmachine.com http://www.broadgun.com
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
2
TexasDepartment
of Transportation
Dallas District
35EGood News
Denton County and the Regional Transportation Council have dedicated $535 Million of the total money received from the 121 Toll concession
payment to fund reconstruction of improvements to IH 35E.
Bad NewsFederal Highway Trust fund which is funded by your Gas Taxes needs additional funding and remaining funds only cover maintenance with
minimal new construction � therefore no federal funding can be expected.
Current Status on Operations & FundingCurrent Status on Operations & Funding
TexasDepartment
of Transportation
Dallas District
35E
Operations � Future Traffic Projections Indicate Less Directional
Split with More Balance in Directional Flow
� Managed Lanes Provide an Option for Users to Choose a High-Speed, Predictable Trip
Funding� Revenue from the Managed Lanes would be
Dedicated to the Capital and Operating Costs of the Corridor
Reasons for ModificationsReasons for Modifications
TexasDepartment
of Transportation
Dallas District
35E
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
3
TexasDepartment
of Transportation
Dallas District
35E
TxDOT developed a Preliminary Financial Feasibility Study
Requested by NTTA �to exercise one-time right to undertake the IH 35E Managed Lanes Project�
Delivered September 2, 2008 to NTTA
NTTA Board Decided at Sept. 17 Meeting to Waive Primacy
Refined Plan with Stakeholder InputRefined Plan with Stakeholder Input
TexasDepartment
of Transportation
Dallas District
35E
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
6
TexasDepartment
of Transportation
Dallas District
35E
Recap Since Meeting No. 1
Project Overview
Refined Modified Concepts
Stakeholder Outreach
Schedule
Other Issues/Next Steps
AgendaAgenda
TexasDepartment
of Transportation
Dallas District
35E
TexasDepartment
of Transportation
Dallas District
35E
DRAFT CONCEPTUAL TYPICAL SECTIONS
PREVIOUSLY EVALUATED TYPICAL SECTIONS
EXISTING TYPICAL SECTIONS
TexasDepartment
of Transportation
Dallas District
Typical SectionsTypical Sections
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
7
TexasDepartment
of Transportation
Dallas District
35E
Alt. 1 Slip Ramps � Managed Lanes to Main Lanes at Grade
Alt. 2 Wishbone Ramps � Managed Lanes to Frontage Road or Cross Street by Bridge over General Purpose Lanes
Alternative 3 Refined Alternative 3 Refined �� Overview on PDF Overview on PDF
Managed Lanes Access Line Diagrams
Managed Lanes Access Line Diagrams
TexasDepartment
of Transportation
Dallas District
35E
Recap Since Meeting No. 1
Project Overview
Refined Modified Concepts
Stakeholder Outreach
Schedule
Other Issues/Next Steps
AgendaAgenda
TexasDepartment
of Transportation
Dallas District
35E
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
8
TexasDepartment
of Transportation
Dallas District
35E
Individual City Meetings � Next Meeting Series Oct. 13-17One on one meetings with meetings with corridor cities, counties and agencies to review alternatives and obtain feedback
Policy Work Group � Next Meeting late OctoberIntended for elected officials and executive level management ofcorridor cities, counties, & agencies to meet quarterly for next 6 months
Technical Work Group � Next Meeting Nov. 5Intended for staff of corridor cities, counties, & agencies to meet monthly to bi-monthly for next 6 months
Public Meetings � First Series � mid NovemberOpen house format to solicit citizen input on the plan. Only public meetings until Public Hearings in Summer/Fall 2009.
Stakeholder OutreachStakeholder Outreach
TexasDepartment
of Transportation
Dallas District
35E
July to December 2008
Work with corridor cities to adjust proposed improvements to allow for a 4-2-2-4 segment
December 2008
Submit Schematic to TxDOT Design Division/ FHWA for review
Summer-Fall 2009 -Public Hearings
December 2009 - FONSI
NEPA ScheduleNEPA Schedule
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
9
TexasDepartment
of Transportation
Dallas District
35E
Access Location Decisions �Finalize per Comments from Stakeholders Review Submitted to TxDOT by Oct. 10with Follow Up Meetings Oct. 13-17
Policy Work Group �Scheduling for late October Meeting
Detailed Schematic Design �60% Draft by Nov. 5 with City Comments Due Nov. 14
Public Meetings � mid November
Next StepsNext Steps
TexasDepartment
of Transportation
Dallas District
35E
Recap Since Meeting No. 1
Project Overview
Refined Modified Concepts
Stakeholder Outreach
Schedule
Other Issues/Next Steps
AgendaAgenda
TexasDepartment
of Transportation
Dallas District
35E
IH 35E Proposed ImprovementsStakeholder Work Group Meeting
October 1, 2008
10
TexasDepartment
of Transportation
Dallas District
35E
Nasser Askari, P.E.Texas Department of TransportationDallas DistrictP.O. Box 133067Dallas, Texas 75313-3067