Top Banner

of 115

IEER Thul-keg 07-10-13 Draft

Jun 02, 2018

Download

Documents

Antra Chowdhury
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    1/115

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    2/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Executive Summary

    Background:

    This power transmission project proposed by Long-term Transmission Development Plan of CEB falls under

    categorization of prescribed project as per National Environment Act. Upon the environmental approval requestfrom CEB, as the project approving authority, Central Environmental Authority has delegated approval process toKegalle Regional Office. After the site visit of the proposed transmission line route by the Environmental Scoping

    Committee, the Terms of Reference (TOR) has been issued by CEA for the preparation of Initial Environmental

    Examination Report (IEER) for the project. This IEER has been prepared as per the said TOR.

    This IEER covers the construction and operation of above project, consists of following components.

    Construction of 132/33 kV GSS at Kegalle.

    Installation of 15 MVAr (3x5 MVAr) capacitor banks including 33 KV BSC bays at Kegalle 33 kV Bus

    Bar to control load PF.

    Construction of 132 kV 22.5 km, double circuit (Zebra) Thulhiriya to Kegalle transmission line.

    Augmentation of Thulhiriya GSS with 2 nos. of 132 kV line bays.

    Under Clean Energy and Network Efficiency Improvement Project, Asian Development Bank has extended

    financial support for power transmission infrastructure development in Sri Lanka, which includes the proposed132kV transmission line from Thulhiriya to Kegalle.

    Justification of the Project:

    Currently Kegalle and surrounding area is supplied by Kiribathkumbura GSS which is predicted to be overloadedby 2015 and Thulhiriya GSS which is predicted to be overloaded by 2018. With the increasing demand Kegalle,

    Mawanella, Polgahawela and Rambukkana areas will suffer voltage drop and frequent failures. Also lengthy

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    3/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Existing Environment:

    22.5km long proposed transmission line originates from existing Thulhiriya GSS and traverse through 9.16 km ofpaddy fields and 11.6 km on home gardens and rubber estates approximately. Lands in the project area havebeen used mainly for the purposes of residents, cultivation of paddy, commercial and other crops. This line routefollows undulating mountainous terrain for most of its length varying from 60m~210m. Total project area lieswithin wet zone which receives annual rainfall around 2500mm.

    Thulhirikanda and Hunuwala kanda forest reserves and Kegalle sanctuary are in close proximity of the line routebut proposed alignment is well away from any such environmentally sensitive areas.

    Home gardens exhibit the maximum floral bio diversity while faunal diversity is almost same in all land uses. Mostresidential lands are cultivated and have single story houses. People who are living in the project area have mixattitude towards the project and majority are willing to accept as this development is having national importance.

    Proposed Northern expressway is the most important infrastructure development take place in this region which isimplemented by Road Development Authority. CEB will work with RDA in close coordination to avoid any conflictsand come up with most environmentally, technically and financially sound solution for both projects.

    Anticipated Environmental Impacts:

    Generally, the environmental impacts from the transmission lines are minimal compared to many development

    projects of similar scale. The main impacts anticipated from this project are removal/pruning of trees along thetransmission line corridor of30m width (especially in the rubber cultivations and home gardens). Erosion due totower foundations and temporary access roads located in steep terrain is also a potential impact to a lesser

    magnitude. Obstruction to the natural waterways and disturbance to the natural ecosystems caused by location offoundations and access roads in wetlands is a possibility.

    Main social impact is the disturbance caused by location of tower footings within home gardens and thedisturbance and constraints caused by the conductors spanning over houses and/or home gardens. Temporarydisruption of farming activities and disturbance of crops (especially in the paddy fields) during foundation work isanother potential impact. Most of the environment and social impacts mentioned above have been avoided or

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    4/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    minimized by construction of earth retaining structures and/or turfing wherever necessary. In case new accessroads were absolutely necessary, they would be maximum 3-4m wide, and completely removed after the

    completion of project work.

    CEB has obtained a landslide investigation report on the proposed project from National Building Research

    Organization (NBRO), which is attached. The report gives a detailed description of the landslide prone areas,and the mitigation measures required to be adopted for the tower foundations located on such areas. Theserecommendations will be strictly adhered during the construction of the project.

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    5/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    ABBREVIATIONS

    CEA - Central Environmental Authority

    CEB - Ceylon Electricity Board

    DoF - Department of Forest

    DS - Divisional Secretary

    DSD - Divisional Secretaries Division

    DWLC - Department of Wild Life Conservation

    EMoP - Environmental monitoring plan

    EMP - Environmental management plan

    GoSL - Government of Sri Lanka

    GSS - Grid Substation

    ha - hectare (=10,000 square meters)

    IEE - Initial environmental examination

    IDSL - Irrigation Department of Sri Lanka

    km - kilometer

    kV - kilovolt

    m - Meter

    MoPE - Ministry of Power and Energy

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    6/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    INITIAL ENVIRONMENTAL EXAMINATION REPORT ON THE

    PROPOSED 132 kV TRANSMISSION LINE FROM THULHIRIYA TOKEGALLE

    1. Introduction 06

    2. Description of the proposed project and reasonable alternatives 09

    3. Description of existing environment 19

    4. Description of the anticipated environmental impacts 39

    5. Proposed mitigatory measures 58

    6. Monitoring program 65

    7. Conclusion and recommendation 70

    Annexes

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    7/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    1.

    Introduction1.1.

    Background of the project

    Ceylon Electricity Board has identified a list of projects, based on the Long-term Transmission

    Development Plan 2011-2020, which are critical for the overall development of the power system.

    Considering the requirements of Sri Lankas power system with medium to long term, it has been

    decided to implement transmission projects required for network efficiency improvement and loss

    reduction including proposed 132kV transmission line from Thulhiriya to Kegalle.

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    8/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    1.2.

    Objective of the proposed project and justification of the projectSummarize the need or problem being addressed by the project and how the proposed

    project is expected to resolve the problem or the issue.

    Due to the fast emerging energy demand of the area, there is a distinct necessity for strengthening and

    expanding the transmission network. Under the adopted standards, the forecast loading of each Grid

    Sub Station (GSS) is compared with the firm capacity and the necessary transformer augmentations as

    well as construction of new substations. According to the analysis done by CEB, it is evident that

    Kiribathkumbura GSS will get overloaded by the year 2015 and Thulhiriya GSS will get overloaded by

    the year 2018. With the increasing demand Kegalle, Mawanella, Polgahawela and Rambukkana areas

    will suffer voltage drop and frequent failures.

    This sub-project will meet the demand growth in Kegalle, Mawanella, Polgahawela and Rambukkana

    areas and thereby relieve loading of Thulhiriya and Kiribathkumbura Grid Substations. Proposed GSS

    will also improve the voltage profile of 33 kV distribution systems and reduce distribution losses hence

    this project will improve operational efficiency and quality of power, reliability of the system and at the

    same time will reduce losses. This improvement of transmission infrastructure will permit the

    electrification of rural areas which are inaccessible with the present situation.

    1.3.Objective of the IEE report

    Specify the objectives of the assessment and the relationship of the results to project design

    and implementation.

    This report intends to identify environmental, social and economical impacts of the proposed projectdevelopment and suggest adequate mitigation measures. The initial environmental examination (IEE)

    report comprises baseline data on the existing condition of physical, ecological, economical and social

    information together with anticipated environmental impacts and proposed mitigation measures IEER

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    9/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    1.5.

    Methodologies adopted in report preparation

    Secondary information was gathered from publication of government and other research groups in the

    preliminary stage. Two study teams were deployed for ecological and sociological surveys on 100m

    wide strip on either side from the center of the proposed transmission line by walking. With the aid of

    field study, baseline data on existing physical, ecological, economic, and social conditions were

    established.

    Field personnel walked along transects along the proposed route mostly during the day to record

    plants and animals. Species were then listed separately for each of the different taxonomic groups. Theconservation status of the species i.e. endemism, rarity and threatened status, was also determined.

    A questionnaire survey has been carried out to collect more quantitative data from affected parties.

    Respondents were selected from residents live in the vicinity of the line route. Data collected through

    questionnaire were analyzed to get information on demography, land ownership, nature of affected

    group and positive/ negative attitude towards the project and used for the final report.

    1.6.The approval needed for the proposed development from state agencies

    Department of Agrarian Develompent

    National Building Research Organization

    1.7.

    Any conditions laid down by state agencies in granting preliminary clearance for the project

    Request letter to the Dept. of Agrarian Development is attached as annex 6.1. Landslide Investigation

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    10/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    2. Description of the proposed project and reasonable alternatives

    Description of the project

    2.1.

    Aim and scope of the project

    State the projects main objectives, main beneficiaries and the expected social economic

    effects.

    The project envisages construction of

    Construction of 132 kV 22.5 km, double circuit (Zebra) Thulhiriya to Kegalle transmission line.

    Construction of 132/33 kV GSS at Kegalle.

    Augmentation of Thulhiriya GSS with 2 nos. of 132 kV line bays.

    Currently areas surrounding Kegalle experience poor service levels of electricity supply due to voltage

    drops and frequent interruptions. The proposed project will improve operational efficiency quality andreliability of power supply to the consumers in Kegalle and surroundings (Mawanella, Galigamuwa,

    Rambukkana, Aranayake etc.). At the same time, it will enhance the reliability of the system and will

    reduce system losses. Main beneficiaries would include the community in Kegalle and suburbs including

    small and large scale domestic/commercial consumers in Kegalle, Polgahawela, Mawanella,

    Galigamuwa, Aranayake and Rambukkana.

    Supply of power to both the local areas and regions will boost economic development of the area by

    strengthening the power transmission infrastructure. Surrounding areas will benefit from improved levelof service and more rural households will get connected to the grid.

    2.2. Justification of the project

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    11/115

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    12/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    i. Pradeshiya Sabha:

    Warakapola

    Kegalle

    Galigamuwa

    Rambukkana

    ii. Divisional Secretariat

    Warakapola

    Kegalle

    Galigamuwa

    Rambukkana

    ii. Provincial Council

    Sabaragamuwa

    2.3.4.

    Proposed timing and schedule including phased development (if any)

    Proposed timing and schedule is attached as annex 5.4.

    2.3.5.

    Applicable laws, regulations, standards and requirements covering the proposed

    project

    National Environmental Act N 47 of 1980, amendment N 56 of 1988, and other

    amendments

    Electricity Act No. 20 of 2009

    Agrarian Services Act (N 58 of 1979)

    Agrarian Development Act N 46 of 2000

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    13/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    estimate to (SLRDCC) for above consultancy work, and their report and consent of Department of

    Agrarian is expected within 01st

    week of October.

    In addition, considering the landslide hazards (if any) in the hilly areas encountered along certain parts

    of line route, CEB has obtained a report from National Building Research Organization regarding above

    (including their recommendations and proposed remedial measures). NBRO report is attached as annex

    6.2.

    2.3.7.

    Provide a location map indicating the project site, surrounding development and

    infrastructure within 100 m of the site (at appropriate scale)

    Location map is attached as annex 5.1.

    2.3.8.

    Give details of the project characteristics including its principal features; project

    related permanent structures, project related temporary structures. (Including route and

    length of the transmission line design of transmission towers, switch yard, grid

    substation etc. and indicate same on a plan)

    The project consists of the following components:

    Construction of 132kV 22.5km, double circuit (Zebra) Thulhiriya to Kegalle transmission line

    having approximately 82 Nos. Lattice towers

    Construction of 132/33kV Grid Substation at Kegalle

    1 Nos. 31.5MVA, 132/33kV transformers

    132kV single Busbar arrangement including bus section

    33kV single Busbar arrangement including bus section

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    14/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    for angles from 100to 300and have foundation of 3500x3500x3000mm. For angles from 30 0to 600, TD6

    towers are used and it has foundation size of 3800x3800x3500mm. Terminal towers from the ends of

    line routes where they connect to grid substations and has the largest base of 4000x4000x3500mm.Typically 132kV transmission towers have heights of 27~28m.

    2.3.9.

    Type of transformers to be installed and their capacity details should also include the

    location extent and type of grid substation/s

    This project envisages the construction of Kegalle GSS in Molagoda, 5km from Kegalle on Kandy road.

    One 31.5MVA, 132/33kV transformer will be installed in it along with other components stated inSection 2.3.8.

    Breaker Switched Capacitor (BSC) banks will be installed at the Kegalle GSS which are used for voltage

    support and reactive power compensation in grid substations. By doing so it helps to reduce the losses

    in power transformers and transmission lines, and to release the capacity constraints in transformers

    and lines. Other than that, they are installed to control the load power factor at the Grid Substation level

    (33kV).

    2.3.10.

    Drawing showing the project layout plan especially in relation to grid substations,

    switch yards etc.

    Layout plan for proposed Kegalle GSS is attached as annex 5.3 and proposed route for the 132kV

    transmission line is attached as annex 5.1.

    2.4.

    Methodology of construction

    2.4.1.

    State the proposed time schedule for construction

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    15/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    leveled. Substation site will be filled to a height of 1.2 m above the Kandy road. Since the part of the

    land is a paddy field, the clearance for filling and development of the land is requested from the

    Dept. of Agrarian Development. In order to maintain uninterrupted drainage of the area due tofilling, a drainage plan is requested from the Sri Lanka Land Reclamation and Development

    Corporation (SLLRDC), which will be incorporated into the filling plan.

    This plot of land will accommodate control building, main transformer foundation, other equipment

    foundations and gantry structures to support conductors. Depth of excavation is very unlikely to

    exceed 2.5m in good soils which are found in selected land for GSS.

    After few months of construction, vegetative cover will reinstate for some extent and in case ofhome gardens certain species of trees can be grown while in paddy fields, same land use may

    continue with some restriction on harvesting machinery. There is no natural forest or cultivations in

    selected land for GSS, therefore ecological impact is minimal.

    2.4.3.

    Nature and type of any structures

    There are two main types of towers in transmission lines which are steel lattice structures.

    Suspension towers- These structures are designed only to carry the weight of conductors in straight-

    line position of transmission line. Therefore, all conductors have been attached to tower cross arms

    with glass insulators and continuously run through these towers.

    Tension towers- These towers are used in angle points where transmission line deviates from its

    route. Since these towers are designed to withstand both conductor tension and weight, they are

    stronger and having a wider base, compared to suspension towers. The continuity of the electrical

    power transmission will be provided by a separate jumper loop. There are several types of tensiontowers to accommodate different angles of deviation as mentioned in section 2.3.8. Tension towers

    are also used as section towers in longer straight sections of the transmission line. Special type of

    tension tower is used at the termination point of transmission line at GSS which is called as terminal

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    16/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    The erection of structures needs some skilled personnel and supervisory staff. Although many

    different tower erection methods practiced and, the selection of an erection method depends on

    various parameters such as the adaptability of selected methods to each site conditions, time andthe cost, etc.

    Conductor stringing is a specialized process, which needs highly skilled linemen, tools and

    machineries. The earth wires and line conductors are strung at a tension using pilot wires,

    tensioners, pullers and pulleys. Adequate number of linemen and proper communication facility has

    to be available during the stringing process.

    2.4.5.

    Infrastructure facilities required / provided

    Separate parking and storage spaces should be allocated to construction vehicles, equipments,

    material storage yards, disposal sites, and labour camps for human resource during mobilization

    stage to avoid any environmental impact and public inconvenience. Selected sites must comply with

    the local laws and regulations and need approval from authorities to utilize these facilities.

    All construction sites and labor camps are to be provided with electricity either via temporary

    connection from national grid or onsite generator. Selecting accessible sites will eliminate the needof access road construction. Also it is important that selection of temporary lands is done reasonably

    away from highly populated areas, water bodies, natural flow paths, agricultural lands, important

    ecological habitats and residential areas.

    2.4.6.

    Details of any access roads to be built, improved (existing condition and anticipated

    improvement)

    Although the line construction will rely on many existing roads, new access roads/tracks may be

    built to reach certain tower locations without vehicular access, if it is absolutely necessary. In such

    locations, maximum efforts will be made to manually transport equipment in knocked-down state to

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    17/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    2.5.

    Work force

    Labor requirements, availability of labor in the area, employment of local people,

    occupational health and safety facilities required / provided.

    As the proposed project is a major construction, the CEB will call for tenders and award the

    construction to a contractor. It will be either a national or international contractor, and they will

    employ the relevant workforce. For skilled labor, it is highly likely that personals from outside the

    locality will be employed while in unskilled labor, personnel from within the locality are utilized.

    Nature of the works in construction activities has a high incidence of occupational ill health. In

    awarding the tenders, the CEB will also ensure that occupational health and safety of the workers arelooked after properly by the contractor. Health and safety impacts will be in terms of risk of accidents.

    Necessary training regarding the safety aspects of the personnel working on the line will be provided by

    the contractor. Contractors are obliged to maintain occupational health and safety facilities that

    comply with national labor rules and standards, in order to assure safe work environment. CEB will

    exercise necessary care and supervision over contractors execution of work and take suitable steps as

    are practicable in the circumstances to avoid a foreseeable risk of death or injury.

    2.6.

    Maintenance procedureState the standard practice and any deviation required

    The CEB does monitoring and supervision of the Project during the construction of the project as well

    as operational phase. Once the project is handed over to the CEB, it ensures that the transmission line

    is maintained properly and in good condition.

    The lifetime of a transmission line is more than 50 years, during which maintenance works are

    comparatively less, and limited to following.

    (i)

    Removal of rust and re-painting (old galvanizing) of any tower steel members with

    i

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    18/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    (i)

    Filtering/changing of topping up transformer oils

    (ii)

    Removal and replacement of equipment

    Since no transformers, circuit breakers or any other equipment containing PCB would be installed in the

    GSS under this project there will be no environmental or social impacts anticipated die above activities.

    During construction of grid substations, CEB will not use PCB or asbestos for any new transformers, and

    disposal of none of those substances from old transformers are involved in this project. Construction of

    project components will not generally result in hazardous or electronic waste. In case of such event, CEB

    will proceed according to the CEA guidelines of hazardous waste disposal.

    2.7.

    Evaluation of alternatives

    Describe reasonable alternative considered and the basic environmental engineering and

    economic parameters used in their investigation and evaluation. Compare alternatives in

    terms of potential environmental impacts, mitigation measures, capital and operating costs,

    reliability, suitability under local conditions and monitoring requirements.

    The following alternatives could be considered:

    2.7.1.

    The no action alternative (i.e. one based on current practices without approval of

    the project)

    "No-action" would mean the proposed activity would not take place, and the resulting

    environmental effects from taking no action would be compared with the effects of permitting the

    proposed activity or an alternative activity to go forward. The no-action alternative is developed

    for two reasons. It is almost always a viable choice in the range of reasonable alternatives, and itsets a baseline of existing impact continued into the future against which to compare impacts of

    action alternatives. This is important context information in determining the relative magnitude

    and intensity of impacts.

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    19/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    down of trees in rich plantations of rubber, temporary impacts to the paddy fields during

    construction of tower foundations, and prompting of soil erosion in the hilly terrain. However,

    most of the social impacts could be properly compensated as explained in later chapters, whilethe environmental impacts involved are easily mitigable, except cutting down of trees, which do

    not involve protected areas or those with high biodiversity, but mostly trees of commercial value.

    So when compared, positive benefits adequately justify the implementation of the project.

    Therefore no-action alternative is not acceptable.

    2.7.2.

    Alternative routes, design and technology selection, construction techniques, and

    maintenance procedures etc.

    Alternatives considered as bellow

    The No action alternative

    Option 1

    Option 2

    Option 3

    The other alternatives are shown against 1:50,000 topographical map and attached as

    annex 5.2. These were evaluated based on the impact on the land and socioeconomic

    condition, the cost effectiveness of the transmission line etc. The Alternative I which

    traverses along more or less straight line is cost effective as there are less angle towers

    required. Evaluation of alternative is summarized in section 7.1.

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    20/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    3. Description of the existing environmentSTUDY AREA

    Grid Substation (s) / Switchyards

    The project sites and 100m from the boundaries of the project site (include Gongan Ela

    levels, GSS contour levels and reservation demarcated in a map of Kegalle)

    Transmission line

    Transmission line route and 50m on either side of the center line of proposed line routes or

    the area of maximum risk.

    3.1.

    Physical Environment

    3.1.1.

    Topology

    Recent Topographical data clearly indicating reserve areas, marshy areas, water bodies,

    canals, streams, drainage, channels

    Kegalle is the capital city of the district which is one of the two districts of

    Sabaragamuwa province the other being Ratnapura district. The elevation of the

    district of Kegalle varies from 30-170m from the MSL. The highest elevation is towards

    the South-East of the district. The landform features vary from plateaus to steep

    escarpments with medium to high elevations: and from broad valleys to steep gullies.

    The district of Kegalle exhibits complex topographical features consist of hills and ridges,

    broad valleys, gorges and plateaus.

    Proposed line traverse through northern part of the district, which is also a hilly terrain.

    Highest peak along the line route was observed in Puwakdeniya area while

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    21/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    considered as the coldest months while April to June as the hottest months. Humidity

    of the district increases with the altitude and also varies from the wet zone to dry zone.

    The average humidity varies between 70-80% during the day time and between 88-94%during the night. Highest monthly rainfall receives in October as 302.7mm and lowest

    rainfall recorded in January as 33.6mm. About 60%-75% of the district receives rainfall

    over 3,000 mm per year.

    3.1.3.

    Geology & soil

    General geology of the area, soil types and distribution

    The district of Kegalle lies within the southern part of Vanni Complex as per litho-

    tectonic classification of the island. This project area is made up of Charnockite, Garnet-

    biotite gneiss and Quartzite. Main soil types encountered in this rolling, hilly and steeply

    dissected terrain are Red-Yellow Podzolic soils with Low Humic Gley soils. These soil

    characteristics and weather makes desirable conditions for commercial crops such as

    tea, rubber and coconut which occupy vast area of the district.

    3.2.Ecological Resources

    3.2.1.

    Existing natural and man-made habitats in and around the project site and,

    distribution and density of fauna and flora of them.

    Following table shows the details of the habitats that will be intercepted by the

    transmission line and their extents in the total corridor.

    Table 3.2.1 1 Land use of the line corridor including the types of habitats and their extents (ha)

    No Total Line Length 21 5 km

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    22/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    The full list of flora and fauna species encountered in the Project affected areas is shown

    in annex 7.

    Flora

    Table 3.2.1 2 Summary of the distribution of flora according to the habitats in the project area

    Habitats The

    extent inthe

    corridor

    (30m) %

    No. of

    speciesin the

    habitat

    types

    Biodiversity

    % in theecosystem

    Endemic

    species

    % Nationally

    Threatened species

    % Vulnerable

    species

    %

    Paddy lands 42.64 22 14.86486 1 4 1 4 0 0

    Home gardens 31.3 96 64.86486 2 2 2 2 1 1

    Rubber 18.79 19 12.83784 0 0 0 0 0 0

    Scrublands 6.4 11 7.432432 1 9 0 0

    Total 148 2 2 0

    Fauna

    Table 3.2.1 3 Summary of the fauna in the different habitats in the Project area

    Habitats Theextent

    in the

    id

    %biodiver

    sity

    Categoryof fauna

    No ofspeci

    es

    b

    Endemic

    specie

    % Endangered

    species

    % Vulnerable

    species

    % NearThre

    aten

    d

    %

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    23/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Mammals 2 1 1 NA

    RubberPlantati

    ons

    10 23.6842

    Butterflies 8

    4.4

    4

    2.

    22

    1 2.22

    2.22Dragonflies 1 NA

    Amphibian

    0 NA

    Reptiles 4 NA

    Birds 29 1 NA

    Mammals 3 1 1 NA

    Open

    Scrub

    lands

    5 25.7894

    Butterflies 13

    6.1

    2

    2.

    04

    1 1 2.04

    Dragonflies 0 NA

    Amphibian

    0 NA

    Reptiles 4 1 NA

    Birds 29 1 NA

    Mammals 3 1 1 NA

    3.2.2.

    Rare threatened and endemic species

    Table 3.2.2 1 The distribution of endemic, threatened and vulnerable flora in the

    Project areashows the distribution of endemic, threatened and vulnerable flora in the

    Project area.

    Flora

    Table 3.2.2 1 The distribution of endemic, threatened and vulnerable flora in the Project area

    Family Scientific Common Habitat Species Conservation PA HG R OS

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    24/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Fauna

    Table 3.2.2 2 The distribution of endemic, threatened and vulnerable fauna in the Project area

    Family Scientific

    name

    Common

    name

    Species

    category

    Species

    Status

    Conservation

    Status

    PA HG R OS

    Nymphalidae Euploea

    sylvester

    Double

    Banded

    Butterfly Native Near

    Threatened

    * *

    Hesperiidae Notocrypta

    paralysos

    Common

    Banded

    Butterfly Native Vulnerable * *

    Coenagrionidae Onychargia

    atrocyana

    Marsh

    Dancer

    Dragonfly Native Vulnerable *

    Libellulidae Orthetrum

    luzonicum

    Marsh

    Skimmer

    Dragonfly Native Near

    Threatened

    *

    Dicroglossidae Fejervarya

    kirtisinghei

    Kirtisinghe's

    Frog

    Amphibians Endemic Vulnerable *

    Ranidae Hylarana

    gracilis

    Sri Lanka

    wood frog

    Amphibians Endemic LC *

    Agamidae Otocryptiswiegmanni Sri Lankankangaroo Reptiles Endemic LC *

    Phasianidae Gallus lafayetii Sri Lanka

    Jungle fowl

    Birds Endemic LC * * * *

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    25/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    The origin of this forest reserve had been a Mahogany mono-cultural plantation established by

    the Forest Department about 25 years ago. However, with time due to dearth of management

    this area had become naturalized. The predominant vegetation is Mahogany ( Swieteniamacrophylla) trees and their seedlings while others like Halmilla (Berrya cordifolia) , Puwak

    (Areca catechu), Kitul (Caryota urens) , Alstonia Lunimidella (Melia dubia),, Kaduru (Cerbera

    manghas), Gadumba (Trema orientalis), Bowitiya (Melastoma malabathricum), Hik (Lannea

    coramandelica), Ginisapu (Michelia champaca) also prevail.

    3.3.Socio economic considerations

    3.3.1.

    Present land use pattern

    As shown in the Table 3.3.1 1 Land Use Data, lands in the project area have been used

    mainly for the purposes of residents, cultivation of paddy, commercial and other crops.

    The total line length is 21.4 km. and 42.64% of it traverses over paddy land whereas

    37.37% and 18.79% run over home gardens and Rubber Cultivations respectively. There

    were 52 families residing in or in the vicinity of line route and only 34% of them had

    cultivated their home gardens (Table 3.3.1.2.). As the public roads are concerned the

    proposed line crosses over two points of major roads.

    Table 3.3.1 1 Land Use Data

    No Land Use Data

    Total Line Length 21.4 km

    Land UsagePercentage of

    total line length

    (%)

    Corridor width

    (m)

    Total affected

    Area (ha)

    i) Open scrubland 6.4 30 -

    ) bb

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    26/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    3.3.2.

    Population characteristics

    The proposed transmission line traverses through four divisional secretarys divisions

    such as Rmbukkana, Kegalle, Galigamuwa and Warakapola in the District of Kegalle.

    According to the census year 2001, the total population of Kegalle District remained at

    785,524, accounting for 4.2% of the total population of the country. As estimated by the

    Department of Census in 2011 that number had increased up to 837,179. However the

    District percentage of the total population of the country still remains the same. The

    four Divisional Secretarys Divisions under consideration of this study have a populationof 359,392 accounting for 43% of the total population of the District of Kegalle. The

    distribution of population in the four Divisions is as shown in the Table 3.3.2.1. The

    highest number of population (31.3%) is recorded from the Warakapola Division. Ethnic

    composition of the population of those four Divisions is evident from the Table. 3.3.2.2.

    Being the majority, Sinhalese accounts for 34.4%, whereas the Tamil and Muslim people

    represents 2.8% and 2.6% respectively. Religious information of the people in the four

    divisions is given in the Table.3.3.2.3. Accordingly 92.7% are Buddhists and the rest

    belongs to other religions such as Hinduism, Islam, Catholic and Christian.

    Table 3.3.2.1 1 Population by Divisional Secretarys Divisions

    DivisionsPopulation

    No %

    Rambukkana 82,373 23

    Kegalle 90,494 25.2

    Galigamuwa 73,942 20.5

    Warakapola 112 583 31 3

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    27/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Division Buddhists Hindu Islam Roman

    Catholic

    Other

    Christian

    Other Total

    Rambukkana 75093 799 2817 1282 2368 14 82373

    Kegalle 85209 1985 1235 1488 561 16 90494

    Galigamuwa 69712 2241 1263 451 267 8 73942

    Warakapola 103316 2773 5731 536 246 17 112583

    Total

    333330

    (92.7% )

    7798

    (2.2%)

    11046

    (3.1%)

    3757

    (1.0%)

    3442

    (1.0%)

    55

    (0.01%)

    359392

    (100%)

    Source : Department of census and statistics 2011

    3.3.3.

    Socio Economic status

    Housing

    Quality and quantity of housing units reveal socio-economic status of people in any

    society. As the Divisions under consideration are concerned, majority of people live in

    permanent housing units. As the Table 3.3.3 1 Distribution of Housing Units byDivisional Secretarys Divisions indicates, 91.1% of the housing units is single storied

    and only 5.6%is two storied. Line-rooms and shanty units account for only 1.2% and

    0.4% of the shelters respectively. Quality of the housing units could be understood by

    analyzing the principle material used for the construction of walls and roof. The Table

    3.3.3 2 Distribution of Housing Units by the Principle Material of Constructionprovides

    data on the type of material used for building houses. There are 92,172 housing units in

    the four Divisions and 67.5% of them have been constructed with bricks and another

    23.8% with cement blocks and stones. The housing units that had been made of

    materials such as mud cadjans and planks account for 7% of the total number of

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    28/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Total 85834

    91.1%

    5606

    5.6%

    342

    0.4%

    244

    0.3%

    25

    0.02%

    163

    0.2%

    1475

    1.2%

    414

    0.4%

    69

    0.07%

    94172

    Source : Department of census and statistics 2011

    Table 3.3.3 2 Distribution of Housing Units by the Principle Material of Construction

    Divisional

    Secretarys

    Division

    Brick

    Cement

    block

    stones

    Cabook Pressed

    soil

    bricks

    Mud Cadjan Plank Other Total

    Rambukkana 18088 2021 72 331 1178 67 175 24 21956

    Kegalle 15774 5473 88 608 1184 15 178 22 21342

    Galigamuwa 12893 4899 125 487 1134 86 86 19 19729

    Warakapola 15448 9570 226 1517 2029 78 209 68 29145

    Total 62203

    (67.5%)

    21963

    (23.8%)

    511

    (0.6%)

    2943

    (3.2%)

    5525

    (6.0%)

    246

    (0.3%)

    734

    (0.8%)

    133

    (0.1%)

    92172

    (100%)

    Source : Department of census and statistics 2011

    Table 3.3.3 3 Distribution of Housing Units by the Principle Material of Construction

    Divisional

    Secretary's

    Division

    Tile Asbestos Concrete Zink,

    Aluminum

    sheet

    Metal

    sheet

    Cadjan Other Total

    Rambukkana 15037 4060 672 196 1765 200 26 21956

    Kegalle 13661 6293 900 174 2167 120 27 23342

    Galigamuwa 13359 3676 383 204 1953 133 21 19729

    Warakapola 21244 4461 668 288 2170 252 62 29145

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    29/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Kegalle 13563 6672 1245 23407

    Galigamuwa 16606 707 1491 19760

    Warakapola 25451 938 1226 29188

    Source : Department of census and statistics 2011

    Table 3.3.3 5 Households by the Principle Type of Lightingprovides data pertaining to

    the principle type of energy used for illuminating the households. The national grid of

    electricity serves 31.7% of households for lighting their houses, where as kerosene oil is

    used in 8.2% of the households in the four Divisions. The percentage of households

    depending on solar power, biogas and other source of energy remains below one for the

    whole area.

    A household survey was conducted with reference to the families residing in or in the

    vicinity of the proposed transmission line route. The following Tables reveal the socio-

    economic and other relevant information of families in the range of the project, as the

    line traverses over their home gardens and other cultivations.

    Table 3.3.3 5 Households by the Principle Type of Lighting

    Division Electricity

    from national

    grid

    Kerosene Solar

    power

    Bio gas Other Total

    Rambukkana 20370 1622 21 11 10 22034

    Kegalle 21732 1654 13 - 08 23407

    Galigamuwa 17993 1742 19 1 6 19761Warakapola 26350 2773 48 8 9 29188

    Total 86445

    (91 6%)

    7791

    (8 2%)

    101

    (0 1%)

    20

    (0 02%)

    33

    0 03%)

    94390

    (100%)

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    30/115

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    31/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Graph for table 3.3.3 7

    As shown in the Table 3.3.3 8 Distribution of the Families by the Number of Family

    Membersthere are 190 members in the 52 families. Families with four or more

    members account for 57% of total families. Female population represents 51.1% (Table

    3.3.3 9 Distribution of population of families by gender). As the age of the household

    members is concerned nearly 59% is below the age of 18 years and over 60% is in

    between 19 and 55 years. Only 3.2% is over the age of 65. (Table 3.3.3 10 Distribution

    of population of families by Age), According to the Table 3.3.3 11 Distribution of

    0

    5

    10

    15

    20

    25

    No. of Families by GN Division

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    32/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Table 3.3.3 9 Distribution of population of families by gender

    Gender No. of People %

    Male 93 48.9

    female 97 51.1

    Total 190 100.0

    Table 3.3.3 10 Distribution of population of families by Age

    Age category No. of People %Below 18 years 55 28.9

    19-30years 37 19.5

    31-55years 78 41.1

    56-65years 14 7.4

    Above 65 years 6 3.2

    Total 190 100.0

    Table 3.3.3 11 Distribution of members of families by work or Education

    work or Education Number %

    Employed 62 32.6

    School children 43 22.6

    Pre- school 11 5.8

    Total 190 100.0

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    33/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    above e0.25 to 0.5 acre 11 21.2

    above 1 to 2 acre 6 11.5

    above 5 acre 1 1.9Total 52 100.0

    Table 3.3.3 13 Distribution of families by the nature of land Ownership

    Land ownership frequency %

    Private lands 45 86.5

    Lease lands 2 3.8

    Other(No Deeds/No Permits) 5 9.6Total 52 100.0

    Residence of people

    As the residence is concerned, 94.2% of families have been in their lands as permanent

    residents and only 3 families (5.8%) live as temporary residents. (TABLE 3.3.3 14 Distribution

    of families by the residence). The period of residence is, over for 10 years for 67.3% familiesand between 6 and 10 years for 7.7% of families. The rest has been there for less than 5 years (

    TABLE 3.3.3 15 DISTRIBUTION OF FAMILIES BY THE PERIOD OF RESIDENCE).Except one

    family living in a wattle and daub house, all the families possess permanent houses but with

    limited space (TABLE 3.3.3 16 DISTRIBUTION OF FAMILIES BY THE CONDITION OF THE

    HOUSE). The floor area of houses of 77% of families ranged between 500 and 1000 square feet.

    Only 11% of families responded to have floor areas over 1000 square feet (TABLE 3.3.3 17

    DISTRIBUTION OF FAMILIES BY THE QUANTITY OF FLOOR AREA). Additional building is

    available only for 32% of families in their residential lands. (TABLE 3.3.3 18 AVAILABILITY

    OF THE OTHER BUILDINGS SITUATED IN THE HOUSEHOLD LANDS)

    Table 3 3 3 14 Distribution of families by the residence

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    34/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Table 3.3.3 16 Distribution of families by the condition of the House

    Condition of the house frequency %

    Permanent Building in Good Condition 51 98

    Wattle and daub house 1 2

    Total 52 100

    Table 3.3.3 17 Distribution of families by the quantity of floor area

    Square Feats of the floor Frequency %

    2001 1 1.9

    NR 6 11.5

    Total 16 100.0

    Table 3.3.3 18 Availability of the other buildings situated in the household lands

    Building frequency %

    No any other building 35 67.3

    Other buildings(Toilets/Store/Ect) 17 32.7

    Total 52 100

    Use of mass media and IT

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    35/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Table 3.3.3 19 Distribution of families by the use of television sets

    Response frequency %

    yes 48 92.3

    No 4 7.7

    Total 52 100

    Table 3.3.3 20 Distribution of families by the use of radio

    Response frequency %

    yes 43 82.7No 9 17.3

    Total 52 100

    Table 3.3.3 21 Distribution of families by the use of antenna

    Response frequency %

    yes 40 76.9

    No 12 23.1

    Total 52 100

    Table 3.3.3 22 Distribution of families by the place where the antenna is fixed

    Place frequency %

    Inside the house 2 5

    Fixed on roof 9 22.5Fixed outside 29 72.5

    Total 40 100

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    36/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    yes 7 13.5

    No 45 86.5

    Total 52 100.0

    Domestic industries

    As the domestic industries are concerned, only 15.4% of families reported to have such

    industries (TABLE 3.3.3 26 DISTRIBUTION OF FAMILIES BY THE AVAILABILITY OF

    DOMESTIC INDUSTRIES).

    Table 3.3.3 26 Distribution of families by the availability of domestic industries

    Response frequency %

    yes 8 15.4

    No 44 84.6

    Total 52 100.0

    Occupation of householders

    The information given in the TABLE 3.3.3 27DISTRIBUTION OF FAMILIES BY THE

    OCCUPATION OF HOUSEHOLDER show the types of occupation and the number of

    householders involved in them. State sector permanent employees represent only 15.4

    of householders, whereas permanent employees in the private sector represent 5.8%.

    Over 15% are employed in temporary capacities in the private sector. Self employment

    accounts for 46.2% of householders. Over 13% has not directly revealed their means of

    living. (TABLE 3.3.3 28 DISTRIBUTION OF FAMILIES BY THE OCCUPATIONCATEGORY OF HOUSEHOLDER)

    T bl 3 3 3 27 Di t ib ti f f ili b th ti f h h ld

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    37/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Income of the family is a good indicator of the economic status of people. The level of

    income as revealed by the respondents is shown in the TABLE 3.3.3 28 DISTRIBUTION

    OF FAMILIES BY THE OCCUPATION CATEGORY OF HOUSEHOLDER. For over 36% offamilies the monthly income ranged between Rs. 5000 and 25000. Over 25% of families

    enjoy an income that ranged between Rs. 25000 and 50000 per month. As income is a

    sensitive factor for people, some refrained from revealing it. In the present study 17

    families (32.7%) remained silent without responding to the question of their monthly

    income.

    Table 3.3.3 28 Distribution of families by the occupation category of householder

    Occupation category Frequency %

    Permanent Government Job 8 15.4

    Permanent Privet sector job 3 5.8

    Temporary privet sector 8 15.4

    Self Employment 24 46.2

    Retired 2 3.8

    Not mentioned 7 13.5Total 52 100

    Table 3.3.3 29 Distribution of families by the level of monthly income

    Income range Frequency %

    Rs 5000-15000 8 15.4

    Rs15001-25000 11 21.2Rs25001-50000 13 25

    Above Rs.50000 3 5.8

    N R 17 32 7

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    38/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Yes 5 9.6

    No 47 90.4

    Total 52 100.0

    Table 3.3.3 31 Type of Construction

    construction Frequency %

    House/Reconstructions 3 60

    Building for Business 2 40

    Total 5 100

    Table 3.3.3 32 Distribution of families by preference for the proposed power line

    Response Frequency %

    Yes 23 44.2

    No 23 44.2

    No response 6 11.5Total 52 100.0

    Peoples opinion on the project

    The survey focused its attention to learn about peoples opinion on the proposed power

    project and it reveals mixed responses. Whereas, 44.2% of families expressed their

    opposition to it a similar number accepts the project. Six families (15.5%) are on thefence being unable to have a proper calculation of the project. (TABLE 3.3.3 32

    DISTRIBUTION OF FAMILIES BY PREFERENCE FOR THE PROPOSED POWER LINE)

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    39/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    their current income. (Table 3.3.3 34 Distributions of families by unwilling to accept the

    proposed power line by reason)

    Table 3.3.3 33 Distributions of families by willing to accept the proposed power line by reason

    Reason Frequency %

    Necessary for 15 65.2

    Because of Compensation 2 8.7

    Because it is Compulsory 2 8.7

    No response 4 17.4Total 23 100

    Table 3.3.3 34 Distributions of families by unwilling to accept the proposed power line by reason

    Reason Frequency %

    No response 2 8.7

    Loss of value of lands 7 30.4Risk/Unsafe 9 39.1

    Loss of trees 2 8.7

    Not Trusted on 1 4.3

    Loss of Income source 2 8.7

    Total 23 100

    Table 3.3.3 35 Distribution of families willing to accept a reasonable compensation and allow theuprooting of Trees

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    40/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    suspicion over getting a reasonable compensation and loss of valuable cultivation

    (TABLE 3.3.3 37 DISTRIBUTION OF FAMILIES BY REASONS GIVEN FOR THE

    UNWILLING TO ACCEPT COMPENSATION AND ALLOW THE UPROOTING OF TREES) Thoseaccepting the compensation reiterated the same reason given for their positive stand

    towards the project (TABLE 3.3.3 36 DISTRIBUTION OF FAMILIES BY REASONS GIVEN

    FOR THE WILLINGNESS TO ACCEPT COMPENSATION AND ALLOW THE UPROOTING OF

    TREES).

    Table 3.3.3 36 Distribution of families by reasons given for the willingness to accept compensation

    and allow the uprooting of trees

    Reasons Frequency %

    No response 8 29.6

    Development of the country 5 18.5

    Because of Compensation 8 29.6

    Because it is Compulsory 6 22.2

    Total 27 100

    Table 3.3.3 37 Distribution of families by reasons given for the unwilling to accept compensation and

    allow the uprooting of trees

    Reasons Frequency %

    No Response 3 18.8

    Loss of value of the land 4 25

    Loss of trees 4 25

    Because it is compulsory 4 25

    No trust on Compensation 1 6 3

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    41/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    4. ENVIRONMENTEL IMPACTS

    4.1.

    Construction Impacts State Briefly the following

    4.1.1.

    Physical Resources

    4.1.1.1.

    Impacts on surface water quality due to soil erosion and silting

    Construction and operation of power transmission lines have minimal impact on surface

    or ground water quality. Water bodies may contaminate due to spilling of construction

    materials and surface runoff from construction site. If the surface runoff meets the river,

    there may be temporary increase in turbidity level of the river. When the soil is

    excavated to erect towers, they should be levelled so that this would not disrupt the

    movement of water and drainage. During the construction of foundations in paddy

    fields, the soil excavated will be generally utilized for backfilling, except in rare

    connections where excavated soil is not suitable for backfilling. In such cases, theexcavated soil would not be left in the paddy field, but will be carried away and dumped

    in a suitable place. Considering the relatively small amount of excess soil, in most of the

    cases these are given to the neighbouring landowners, upon their request. If such

    places are not readily available, a proper place/s for dumping excess soil would be

    located in consultation with relevant DS, and levelled properly.

    Project activities including excavation, cut and fill operations, removal of trees and

    green cover vegetation etc., will enhance the soil erosion during the rainy season. The

    impact on soils will be due to the soil erosion at the tower construction site and along

    the access routes. Excavation activity and land clearance in the erosion prone areas

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    42/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    mitigation measures to minimize anticipated impact due to obstruction of natural flow

    paths and existing drainage are listed in the following chapter.

    Proposed land for Kegalle GSS is adjacent to Gongan Ela and its development activities

    will include filling of the existing land above 1.2m from Kandy road level. Since the filling

    will be carried out totally outside the reservation of Gongan Ela, no impact will be

    caused to the hydrological pattern of it. All filling activities will be carried out under

    guidelines of SLLRDC with minimum hindrance to local drainage patterns.

    4.1.1.3. Impacts on fauna and flora or on existing habitats due to changing land use

    patterns

    Proposed route alignment does not cross any protected forest or wildlife areas or

    ecologically sensitive wetland. As mentioned earlier on section 2.3.2 about present land

    use, this line does not traverse any natural forest areas or forest plantations. No land

    use change take place when power line follows paddy fields which is the highest

    percentage of land use type (42.64%) traversed by the transmission line. Paddy

    cultivation can be continuing even under the tower itself. Rubber and home gardens arethe secondly most affected by transmission line. Since all the trees growing above 3m

    height will have to be removed/ pruned along 30m corridor along the transmission line

    route, number of trees removed would be high in rubber plantations, and home gardens

    with high-grown trees. Rubber plantations and home gardens are generally considered

    as degraded habitats. Hence impacts in such areas are also relatively lesser.

    Ecological impacts related to flora and fauna on existing habitats is addressed underchapter 5.

    4 1 1 4 Impacts on canals other irrigation structure and water bodies

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    43/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    4.1.1.5.

    Impacts on other proposed or planned government / private sector /

    development activities in the vicinity

    As per regulations enacted by GoSL, it is mandatory for CEB to seek clearance prior to

    construction from highways, railways, telecommunications and wherever necessary

    from aviation authorities that are likely to be affected by construction of lines. In case

    of any interference of utilities, CEB wishes to follow best practice guidelines.

    Northern expressway

    Accordingly CEB has written to Road Development Authority to provide RoW ofNorthern Expressway in Devalegama area. Any line crossing with road corridor will be

    constructed with adherence to technical specifications and RDA guidelines.

    Road Development Authority has planned a new highway from Enderamulla to

    Habarana to be constructed in four stages. Stage 3 of this new road has been proposed

    to build from Ambepussa to Katugastota. According to the preliminary layout made

    available to CEB by RDA, several sections of this road corridor and transmission lineshare same right of way, particularly in Devalegama area.

    RDA is currently in the process of optimizing the ROW. CEB will work in close

    coordination with RDA during the project implementation period to come up with most

    cost effective, technically and environmentally sound solution beneficial to the country.

    4.1.2.

    Human and socio - economic impacts

    4.1.2.1.

    Public safety / potential relocation of people etc.

    Safety

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    44/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    As highvoltage lines are having an arc across an air gap they may have a lethal impact on

    people working or moving very close to such transmission lines even without any physical

    contact. As the transmission line runs over home gardens and paddy fields, people living andworking in those areas have to take precautionary measures to protect themselves keeping the

    maximum distance over 15-17 feet between themselves/ objects in their hands or physical

    contact and the power line. In particular, farmers using modern harvesting and other

    equipments have to be ever conscious about the precautionary measures.

    Fallen lines

    With all the technical and other safety measures taken by the project, still one cannot hundred

    percent assure the smooth functioning of the systems as unexpected natural or anthropogenic

    incidence might cause severe damage to towers, lines and grid stations.

    Peoples fear of transmission lines

    People in the area expressed their views and attitudes towards transmission line with special

    emphasis on the negative impact on their physical well-being. They believed that high tensionpower lines cause disabilities and diseases in human beings living in the close vicinity of such

    lines. Cancer and skin diseases were cited as dangerous impacts of power lines.

    Another strong belief among people was that transmission lines and towers connected to them

    attract thunder strikes and thereby endanger the lives of people. They also had the fear of

    spreading the fire emanating from the thunder caused ignition in transmission lines.

    Potential Relocation of People

    As the transmission line has been designed with special emphasis on minimum impact on

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    45/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    (with same width of the existing road) along the boundary of the land to be purchased. The

    people of the village are also prepared to accept such an alternative within the land area of the

    project.

    4.1.2.2.

    Impact on the agriculture / plantation sector and land use of the area

    Impact on the land use pattern

    As shown in the Table 4.1.2.2 1, lands in the project area have been used mainly for the

    purposes of residents, cultivation of paddy, commercial and other crops. The total line length is

    21.5 km. and 42.64% of it traverses over paddy land whereas 37.37% and 18.79% run over

    home gardens and Rubber Cultivations respectively. There were 52 families residing in or in the

    vicinity of line route and only 34% of them had cultivated their home gardens (Table 4. 2.), as

    the public roads are concerned the proposed line crosses over two points of major roads.

    Table 4.1.2.2 1 Land Use in the line route

    No Land Use Data

    Total Line Length 21.5 km

    Land UsagePercentage of total

    line length (%)

    Corridor width

    (m)

    Total affected

    Area (ha)

    i) Coconut - 30 -

    ii) Rubber 18.79 30 12.1

    iii) Home Garden 37.37 30 24.2

    iv) Paddy 42.64 30 27.4

    No of Crossing

    i) Railway -ii) Major (A ,B type )road crossing 2

    iii) River Crossing -

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    46/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    reduction of paddy lands available for cultivation as farmers could cultivate the area under the

    towers leaving only the tower bases.

    The construction phase of the power line over the paddy field definitely keep the line route,

    access roads and tower bases out of cultivation and the construction activities may also

    disturbs the irrigation system leaving the adjacent paddy land out of cultivation for a

    considerable period of time depending on the completion of the project. Any disturbance to

    the irrigation system may cause inundation over a vast area of paddy lands causing damage to

    cultivations. Existing access roads and newly constructed access roads for the transportation of

    materials are needed to be turned back to their original condition so that they may not causeunanticipated negative impacts.

    Rubber cultivations

    As mentioned earlier Rubber cultivations are subjected to 18.8% of the total length of the

    power line and that length with its due width is to be cleared removing all the high grown trees.

    This requirement would cause a considerable lost to the owners of the lands of those

    cultivations. Furthermore, the conditions imposed preventing the cultivation of high grown

    trees would compel the owners to change their pattern of land use. The impact of land

    clearance for the construction and maintenance of the power line, results in reducing the

    income that people earn from their home gardens, and other cultivations. It should not be

    taken for granted as most of people economically depend on the income of their home

    gardens, paddy and other cultivations for meeting the basic needs. Over 35% of the 52

    households under consideration earn Rs. 25000 or less than per month.

    Home gardens

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    47/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    The people of the affected area are highly concerned about the traversing of power line over

    their buildings and the inevitable ceiling on the height of constructions imposed by the project.

    Nearly 10% of the households have future plans of construction. However all expressed theirapprehension about the negative impact of the power line on their safety and future use of

    their lands for constructions. Construction of tower bases in small plots of lands will further

    reduce the quantity of land area available human use if such lands are selected.

    Degrading of land and property values

    People in the areas to be affected by the project were dissatisfied with an anticipated impact of

    decreasing land and property values as a result of the restrictions accompanied by the project.

    They anticipated a considerable decrease in land price after project implementation.

    The symbolic value of lands, properties, and cultivations are higher than their real value as

    people assign various cultural meanings to them on the ground of inheritance, memories, and

    emotional attachments. Any negative impacts on such properties are deeply felt by the owners

    as their lives are interwoven with them.

    Quality improvement of electricity supply

    With new substation to be built in Kegalle, number of current issues in electricity supply to

    surrounding areas to be resolved. New substation will eliminate lengthy 33kV lines which

    currently supply Kegalle, Mawanella, Polgahawela and Rambukkana areas from

    Kiribathkumbura and Thulhiriya GSSs. This will respond to low voltage problems encountered

    and improve the reliability of electricity supply to consumers of the said areas. On the otherhand, this project will reduce distribution losses and improve overall efficiency of the network.

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    48/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    encountered in home gardens. Therefore when taken as a summary for the flora, the

    percentage endemism and species with high conservation status was highest in home

    gardens (71.42%) followed by paddy lands (28.57%) and then open scrublands (14.28%).However, when the project area is taken overall, the level of endemism of flora is 3.37%

    while the percentage of nationally threatened species is 2% and the percentage of

    vulnerable species is 0.67%.

    With regards to fauna, the habitats exhibited a relatively high biodiversity. Paddy lands and

    open scrublands exhibited the highest (26.84% and 25.79% respectively) followed by home

    gardens and rubber plantations (23.68% and 23.0% respectively). There were two endemicamphibians and one endemic bird found in the paddy lands. Percentage endemism was

    highest in open scrublands (6.12%) followed by paddy lands (5.9%), home gardens (4.4%)

    and rubber plantations (4.44%). With regards to the species with high conservation status,

    the percentage of endangered species was 2.22% in all the habitats except in paddy lands.

    Percentage vulnerable species was highest in paddy lands (4.44%) followed by rubber

    plantations. Paddy lands recorded the highest near threatened species percentage (4%)

    followed by rubber plantations (2.22%) and open scrublands (2.04%).

    When the species diversity was considered, highest was recorded in birds (33.73%) followed

    by butterflies (26.50%), reptiles (10.84%), dragonflies (8.41%) and mammals (4.81%).

    Despite the fact that there was a high biodiversity in birds they were rather common in

    almost all the habitats. However, dragonflies were more prevalent in paddy lands.

    Amphibians were seen in paddy lands as well as wet areas in open scrublands. While

    reptiles were common to all the habitats mammals were seen mostly in other habitatsexcept in paddy lands.

    I t f th j t th h bit t

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    49/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    In order to ascertain the significance of the impact of the project on the habitats and their

    function, a scoring system was developed (Impact Score) using the following criteria.

    The extent of the habitat affected

    Present status of disturbance

    % Biodiversity

    % Endemism

    Percentage occurrence of species with high conservation status (CR, EN, NT, VU)

    Marks were given from 1-5, the 1 being the least affected while 5 being the most affected.The results are shown below;

    Table 4.1.3.2 1 Rating of habitats for their importance in biodiversity, endemism and

    conservation status

    Habitat

    type

    Extent

    affected

    %

    Level of

    disturba

    nce

    Biodiversity

    %

    Endemism

    %

    CR

    %

    EN % NT % VU % Total

    score

    Paddy 42.64 (3) 2 20.85 (2) 5.22 (4) 0 4.27 (2) 2 14

    Home 31.3 (3) 3 44.27 (3) 3.24 (3) 2.22 (3) 2.08 (2) 2.52 (1) 18

    Rubber 18.79 (2) 2 18.25 (2) 2.22 (2) 2.22 (3) 1.1 (2) 1.11 (1) 14

    Open 6.4 (1) 1 16.605 (2) 7.6 (4) 2.04 (3) 1.2 (2) 1.02 (1) 14

    Land area affected More than 80% (5); 40-80% (4); 20-40% (3); 10-20% (2);

    less than 10% (1)

    Biodiversity More than 60% (5); 40-60% (4); 20-40 % (3) 10-20% (2) 0-10% (1)

    Endemism More than 10% (5) 5 -10% (4); 2 5 5% (3) 1-2 5 % (2); < 1

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    50/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    many birds in all these habitats, when trees are removed the trees used by birds for roosting

    and nesting will be affected and in turn their continuity will be affected. However, in these

    ecosystems except for Sri Lanka Jungle Fowl other birds are not endemic or with highconservation status. Due to the clearing of trees especially in the home gardens, rubber

    plantations and also open scrublands, the arboreal mammal (Sri Lanka Purple Faced Langur)

    and other animals like squirrels, monkeys etc. will be affected. Due to the ground clearing along

    the transmission line, habitats of ground inhabiting animals like amphibians, reptiles etc. will be

    affected; such openings will encourage the encroachment of these natural and naturalized

    habitats reducing the habitats for wildlife further. During the construction of the towers which

    are situated 300m apart, there would be lot of activity especially during the day time which

    includes noises from equipment, vehicles and others which affects the fauna adversely. The

    conglomeration of a large labour force located in labour camps during the construction period,

    may cause intrusion into the day to day life of the area as well as cause disposal of waste both

    solid and liquid to the surrounding land uses causing pollution.

    Another prominent impact especially during the operational stage is the electrocution of fauna.

    The types of animals which will be mostly at risk are arboreal mammals and birds. Animals

    cannot understand that electrical power lines and transformers carry deadly current. Tomonkeys and other arboreal wildlife, power poles and lines look like trees and vines. When an

    animal grasps a live electrical line while its feet or trail touches the parallel line beneath it, a

    deadly circuit formed, and it is electrocuted. However, in the design of this high tension 220 kV

    power line, about 4m is kept vertically between two parallel lines and 10m distance kept

    horizontally and therefore there is a remote chance for an animal to touch two lines which is a

    prerequisite for electrocution. However, at the proximal end where the lines are hanged to the

    tower, there is a chance of this happening as the distance becomes small. Further, a distance of

    17.5m is kept on either side of the transmission line as the buffer area so that the animals

    jumping on to the transmission line from nearby trees is very remote. However, if the

    transmission line is not kept clean of vegetation there is a chance of damage to wildlife from

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    51/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Construction and maintenance equipment that crosses wetlands can stir up sediments,

    endangering fish and other aquatic life.

    Clearing forested areas can expose the land to invasive and shrubby plants, thusremoving habitat for species in the forest interior. Vehicles and construction equipment

    can introduce exotic plant species.

    Any of these activities can impair or limit wetland functions. Organic soils consist of layers of

    decomposed plant material that formed very slowly. Disturbed wetland soils are not easily

    repaired. Severe soil disturbances may permanently alter wetland hydrology. A secondary

    affect of disturbance is the opportunistic spread of invasive weedy species. These invasive

    species provide little food and habitat for wildlife.

    Impacts on scrub forests/forests

    There are no high canopied forest areas along the transmission line route. At Thulhiriya, the

    Thulhirikanda Forest Reserve is located more than 100m from the line route. However, there

    are scrub lands with scattered trees in certain sections of the line route. However, the impact

    on these will be less as the occurrence of trees more than 3m height occurring on the line routeis not a common occurrence.

    Impact on the Project on the survival of the species with high conservation status

    The following criteria was used in the development of a scoring system to assess the impact of

    the Project on the survival of the species in the habitats with special reference to those who are

    endemic and having high conservation status. The parameters of the criteria were;

    Conservation Status

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    52/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    When the distribution of a species within Sri Lanka was considered, 5 marks were given to

    those who are found only in the Project area. The species found in another climatic zone were

    given 4 marks while those that inhabit more than one climatic zone were given 2 marks.

    When mobility of the species was considered, those who have higher mobility and could move

    fast will be less affected than those who have less mobility. Species having highest mobility

    were given 1 mark (birds) while those having little mobility can be given 5.

    Table 4.1.3.2 2 the details of the assessment and the rating done on the floral species encountered

    Species CS Global distribution Distribution in SL Overall

    ratin

    C

    R

    E

    N

    D

    D

    N

    T

    V

    U

    Endemic to

    Sri Lanka

    In

    India

    and

    SL

    In S.

    Asi

    a

    In

    Asia

    In other

    contine

    nts too

    Restrict

    ed to

    Project

    area

    Found

    in one

    climatic

    zone

    Found

    in more

    than

    one

    climatic

    zones

    Waliddaantidysenterica(Idda)

    5

    4 9

    Garciniaquaesita(Goraka)

    5 2 7

    Cycas nathorstii(Madu) 1 1 4 6

    Lagerstroemiaspeciosa

    2 3 4 9

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    53/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    Table 4.1.3.2 3 The details of the assessment and the rating done on the faunal species

    encountered

    Species CS Global

    distribution

    Distributio

    n in SL

    Level

    ofmobi

    lity

    Over

    allratin

    g

    C

    R

    E

    N

    D

    D

    N

    T

    V

    U

    Endemi

    c to Sri

    Lanka

    In

    India

    and

    In S.

    Asia

    In

    Asia

    In

    other

    contin

    Rest

    rict

    ed

    Foun

    d in

    othe

    Fou

    nd

    on

    Euploea

    sylvester(Double branded

    crow)

    2 1 2 3 8

    Notocrypta

    paralysos

    (Common

    banded demon)

    1 1 2 3 7

    Onychargiaatrocyana

    (Marsh dancer)

    2 1 2 3 8

    Orthetrum

    luzonicum

    (Marsh skimmer)

    2 4 2 3 11

    Fejervarya

    kirtisinghei

    1 5 () 2 4 12

    H l ili 5 2 4 11

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    54/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    When the probable impacts on the survival of species in different habitats were considered,

    the proposed project will have moderate impacts on the survival of the following species;

    Orthetrum luzonicum (Marsh skimmer)

    Fejervarya kirtisinghei (Frog)

    Hylarana gracilis (Sri Lanka Wood Frog)

    Otocryptis wiegmanni (Sri Lanka Kangaroo Lizard)

    Gallus lafayetii (Sri Lanka Jungle Fowl)

    Therefore, despite the fact that the line route traverses along paddy lands major part of its

    route, the impact on the trees on the borders cannot be considered as non significant.

    Impact on this on paddy lands is minimal as there are fewer trees compared with other

    habitats. The impact on the open scrublands will also be small as these areas are dominated

    by shrubs and the trees are seen scattered. The impact on the rubber plantations and the

    home gardens are the most as these ecosystems are dominated by trees.

    Impacts on agriculture/plantation sector and land use of the area

    The proposed transmission line has been planned to traverse above paddy lands for about

    42.64% of its path followed by 31.3% over home gardens, 18.79% over rubber lands, about

    6.4 % above scrub forest areas. When it is traversing along the paddy lands it is not

    expected to change the land use very much. However, when an area of 30m is cleared from

    home gardens leaving only trees which are less than 3m in height, the land use of the same

    will be affected. It has been estimated that an area equivalent to 12 ha of rubber

    plantations in the Kegalle Districts will be removed and therefore the land use of these

    areas will be changed. Since there are only scattered trees in the scrub forest areas the

    impact on this is not very significant

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    55/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    rivers, lagoons, or ponds even the ground water can get contaminated. Water plants and

    fish can also be affected. Due to the small scale and scattered nature of construction,

    intensity of such impact is very minimal. Further, even during the operational period, the

    presence of towers and power lines on top will hinder the use of high tech equipment in

    farming i.e. combined harvester.

    Rubber cultivations

    According to the land use along the transmission line, 12 ha of rubber lands will be directly

    affected. About 19,200 rubber trees will be lost to the country. When an average yield of

    rubber plantations is taken as 1200 kg/ha/yr the yield loss from rubber will be 14,400 kg/yr.Therefore, the loss of these trees should be compensated adequately. The advice of the

    Rubber Cultivation Board should be requested with regard to designing a proper

    compensation package for this.

    Home gardens

    About 24.2 ha of home gardens will be directly affected along the transmission line route.These gardens comprise of a mixture of trees and crops which provides multitudes of needs

    to the home gardener i.e. timber, small wood, fuel wood, fruits, food and medicine. As it is

    required to clear 30m width of the area from vegetation especially those which are more

    than 3m in height or those which has potential to grow more than 3m the a good part of the

    vegetation will be lost to the home gardener who will lose cash income as well as security

    from food, timber and other essential goods. For the houses which are having small extents

    of land, the area available for cultivation will be greatly limited. The loss of these valuable

    crops needs to be adequately compensated. Although it is allowed to grow crops with short

    statures, people do not like to work under these lines due to safety reasons.

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    56/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    affected will be amphibians which inhabit the streams associated with paddy lands. There

    are two endemic frogs i.e. Kirtisinghe's Frog and Sri Lanka wood frog that are also endemic.

    The former is vulnerable too. As major land use affected (42.64%) is paddy the impact on

    the amphibians due to the project could be high especially since they are less mobile and

    would be localized.

    4.2.

    Safety and security

    4.2.1. State briefly the structural safety of the transformers and transmission lines specially

    during unpredictable operational loads

    Transmission lines are designed to trip out of service (turn off), if they fall and touch

    ground or contact trees. Transmission lines are not likely to fall unless encounters a severe

    impact such as hit by a tornado or a truck or due to anthropogenic activity. All the tower

    types are been tested for critical load combinations in state of the art laboratory facilities

    in India. Therefore it can be certain that structural failure of towers is very unlikely.

    4.2.2.

    State briefly lightning danger from transformers and transmission lines:

    Tall objects such as transmission towers, poles and trees are more likely to intercept

    lightning strikes. Transmission lines are therefore usually built with a grounded shield wire

    at the top of the poles. This protects the transmission line from lightning. Lightning is not

    more likely to strike houses or cars near the transmission line. Shorter objects under or

    very near a line may actually receive some protection from lightning.

    4.2.3.

    Indicate the possibility of any accidental hazards or fire hazards:

    When working near high-voltage transmission lines, electrical contact can occur even if

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    57/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    b.

    Communities in the neighborhood:

    It will be ensured that anybody working on the property is properly briefed on the

    electrical infrastructure, clearance zones and plant, machinery and equipment

    specifications.

    c.

    Surrounding environment to be taken in the event of any possible accident, fire

    hazards:

    Activities may create accidental damage to public and the construction workers.

    Therefore, contractors should take necessary action to enhance personal safetyduring the Construction through the following measures:

    Organize awareness programs relevant to the personal safety of the workers and the

    public in the area. Installation of warning signs to particular locations such as

    transverse points of local road network of transmission lines. Provide protective safety

    belts, footwear, helmets, goggles, eye-shields, and clothes of workers depending on their

    duty. Arrangement of proper first aid unit, fire fighting gear and transport facilities to

    take injured people to the hospitals.

    4.2.5.

    Impact on visual environment, historical sites and sites of special values

    No archeological, historical or cultural important sites are affected by the construction of

    the line. During profile survey, it is ensured that the proposed route of transmission line

    does not affect any public places like playgrounds, schools, places of worship or other

    similar establishment etc,. Pinnawala Elephant Orphanage is the most important tourist

    attraction in the area and selected line route option traverses about 4km away from it.

    Proposed line does not traverse places of known archeological importance

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    58/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    None of proposed 132 kV Thulhiriya to Kegalle transmission line is traverse across any railway

    tracks but this transmission line cross A6 road near to Exsisting Thulhiriya Substation, B539

    Nelundeniya- Alawwa Road , A19 Polgahawela- Kegalle Highway , B 199 Karandupona-

    Rambukkana Road.

    4.3.2.

    Provide details regarding the distance from the middle of the road to the posts. The height of

    the line route from the roads.

    In case of road crossing, CEB will ensure to keep required safety clearance as recommended by

    RDA. Clearance to the bottom conductor from the finished road level will be 6.7m as per

    technical specification of CEB which is greater than RDA requirement.

    4.4.

    Mono cultivation land areas

    Provide full details of Mono cultivation land areas in the line path

    Paddy fields are the main land use type and the only farmland traversed by the transmission

    lines. As explained above, 42.64% of the Thulhiriya - Kegalle line has been located over paddy

    lands, in order to reduce the social impacts caused by locating the proposed transmission linealong residences and/or home gardens.

    As mentioned earlier in section 4.1.2.2, rubber cultivations are encountered in 18.8% of the

    total length of the power line and that length with its due width is to be cleared removing all

    the high grown trees. Extent of this impact is discussed in section 4.1.3.1.

    4.5. Wildlife and forest reserve areas

    Provide full details

    None of proposed 132 kV Thulhiriya - Kegalle line is traverse across any areas under the

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    59/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    ecological survey confirm the high species diversity exist in the home gardens. Impacts to the

    home gardens due to project activities are discussed in section 4.1.3.1.

    4.7.

    Irrigation tanks

    Provide full details of irrigation tanks and related information related to the line route

    a)

    Names of the tanks and co-ordinates

    Proposed 132 kV Thulhiriya to Kegalle line does not traverse any irrigation tanks under the

    purview of Irrigation Department.

    b)

    Angle point A6 riverine environment near Thalgahayaya

    The only riverine ecosystem along the line route can be observed in between angle point 5 and

    6 related to Ragala oya in Egalla GN division in Warakapola DS division. At this location, line

    route crosses the stream in perpendicular angle causing minimum damage to the vegetation

    along the waterway.

    4.8.

    Agrarian development mattersProvide full details of agrarian related areas

    Paddy fields are the main land use type and the only farmland traversed by the transmission

    lines. As explained earlier, there will be no change in the land use planning due to the project

    in the paddy fields, except for the safety precautions to be adopted when using the harvesting

    machines with a higher reach. Paddy cultivation will be continued under the transmission line,

    and even under the towers, during the operational phase of the project. However it may causesome problems for those working in the paddy lands for cultivation and harvesting of paddy, if

    necessary actions are not taken to prevent such impact. In particular use of some of modern

  • 8/10/2019 IEER Thul-keg 07-10-13 Draft

    60/115

    PROPOSED 132kV TRANSMISSION LINE FROM THULHIRIYA TO KEGALLE

    encountered even at a later stage, CEB will ensure to make necessary deviations, as per the

    directives of Department of Archeology.

    5.

    Proposed Mitigatory MeasuresThis chapter should set out the proposed measures to minimize the impacts identified in Chapter

    4 to acceptable levels (including conformity to gazetted Sri Lankan Standards) Mitigatory

    measures should be defined in specific practical terms. Alternative methods of mitigation should

    be discussed