IDP Conference 2004 “Developmental Governance in Action” SESSION 5: SESSION 5: Managing the IDP: The Amatole Managing the IDP: The Amatole District District Municipality Experience’ Municipality Experience’ - Andile Fani - Andile Fani Manager: Municipal Support Manager: Municipal Support Amatole District Municipality Amatole District Municipality Eastern Cape Province Eastern Cape Province 5 March 2004 5 March 2004
47

IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

Dec 18, 2015

Download

Documents

Dayna Barnett
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

IDP Conference 2004“Developmental Governance in Action”

SESSION 5:SESSION 5:

‘‘Managing the IDP: The Amatole DistrictManaging the IDP: The Amatole District Municipality Experience’ Municipality Experience’

- Andile Fani- Andile Fani Manager: Municipal SupportManager: Municipal Support Amatole District MunicipalityAmatole District Municipality Eastern Cape Province Eastern Cape Province

5 March 20045 March 2004

Page 2: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

2

AMATOLE DISTRICT MUNICIPALITY

INTEGRATED DEVELOPMENT PLAN

Page 3: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

3

IDP REVIEW

Page 4: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

4

Legislative context

Section 34 of the Municipal Systems Act states that:  A municipal council-

a)      Must review its integrated development plan–

 i.      Annually in accordance with an assessment of its

performance measurements in terms of section 4 i;

and

         ii.   To the extent that changing circumstances so

demand; and b)    May amend its IDP in accordance with a prescribed process.

Page 5: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

5

Why Review?While the legislation requires a review, it makes sense for us to review for the following reasons: To ensure that the IDP is relevant

(implementation performance, check targets, objectives, changing circumstances etc.)

IDP is the municipality’s strategic plan and as such should inform aspects such as the institutional and financial.

To inform other spheres of government.

Page 6: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

6

Content elements of review

IDP Review

Comments from the MEC

Changing circum-stances

Process and content improve-ments

Page 7: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

7

Process elements of review

A: Preparing for IDP (A)

B+C: Monitoring and evaluation

D: Refined objectives, strategies and projects phase

E: Drafting review document - including budget

F: Approval

PU

BL

IC P

AR

TIC

IPA

TIO

N

PERFORMANCE MANAGEMENT

IDP IMPLEMENTATION

Page 8: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

8

What are ADM’s themes for IDP Review?

While there are many areas that require “tightening up” in ADM’s IDP, some areas require particular attention:

Institutional issuesSector plans and associated spatial

framework IDP-budget linkUpdated list of projects

Page 9: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

9

Municipal Vision

The Amatole District Municipality strives for The Amatole District Municipality strives for a future where constituent communities a future where constituent communities have a peaceful, stable and sustainable have a peaceful, stable and sustainable environment with basic needs being met environment with basic needs being met through a participatory development through a participatory development process and where communities have process and where communities have access to economic opportunities. access to economic opportunities.

Page 10: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

10

Organisational arrangements

Executive Mayor

Municipal/ Strategic Manager

DIMAFO

IDP Steering Committee

IDP Representative Forum (including Sector Plan Consultative Forums)

Support providers and planning professionals – PIMSS…

Page 11: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

11

Strategic Cluster approachCluster Priority issues

Institution and Finance Institution

Finance

Communication

PIMSS

Municipal Support

Special Programmes

LED and Environment Agriculture

Manufacturing

Tourism

Environment

Page 12: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

12

Cont...Clusters Priority Issues

Social Needs Municipal (environ..) health

HIV/AIDS

Disaster Management and Fire Fighting

Primary Health Care

Safe and healthy environment

Infrastructure Water/Sanitation

Roads

Telecommunication, Electricity

Solid Waste

Land and Housing

Public Transport

Community Facilities

Building Control

Page 13: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

CLUSTER PROJECTS AND PROGRAMMES

Page 14: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

14

Cluster Projects

Institution and Finance Cluster

Institutional study

Development of appropriate policies regarding rendering of authority functions

Special Programmes capacity building and awareness programmes

Finance and Budget reform Programme

Appointment of international advisor in financial division

Page 15: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

15

Inst and Fin..(cont..)

Municipal Support ProgrammeEstablishment of Internal Audit capacity at Category B’sRoll-out of PMSRoll-out human resource policiesContinue with the implementation of the equity planReview and implementation of skills development plan.

Page 16: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

16

Infrastructure Cluster

Water and Sanitation projects

Local municipal roads projects

Water Services Authority Development Programme

Solid Waste Projects

Land Reform and settlement Plan

Housing Projects

Page 17: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

17

LED and Environmental Cluster

•Small business support programmeSmall business support programme

•Facilitate LED Initiatives linked to Facilitate LED Initiatives linked to opportunities arising from IDZ & SDIopportunities arising from IDZ & SDI

•Establishment of LED units in Category BsEstablishment of LED units in Category Bs

•LED development of funding source LED development of funding source databasedatabase

•Establishment of LED Development Agency Establishment of LED Development Agency

Page 18: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

18

LED cluster (cont…)•Marketing plan for ADM tourismMarketing plan for ADM tourism

•Establishment of RTO and LTOsEstablishment of RTO and LTOs

•Investigate the options for development of Investigate the options for development of Calgary MuseumCalgary Museum

•Facilitate and support resuscitation of Kiwane Facilitate and support resuscitation of Kiwane Tourism Resort and community tourismTourism Resort and community tourism

•Establishment of one-stop service centre for Establishment of one-stop service centre for investment for investment enquiries linked to investment for investment enquiries linked to development agency development agency

Page 19: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

19

LED and Environ. (cont…)

• Undertake an environmental skills audit and Undertake an environmental skills audit and design educational programmes design educational programmes

• Encourage sustainable use of renewable Encourage sustainable use of renewable resourcesresources

• Develop and Implement Municipal Coastal Develop and Implement Municipal Coastal Management ProgrammesManagement Programmes

• Ensure ADM owned land is free of alien Ensure ADM owned land is free of alien vegetationvegetation

• Ensure ADM complies with all SA environmental Ensure ADM complies with all SA environmental legislationlegislation

Page 20: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

20

Social Needs Cluster

District wide water source mapping

Waterborne diseases control programme

District wide sanitation education mapping

ADM prevalence study and impact assessment of HIV/Aids

Page 21: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

21

Social Needs Cluster (cont…)

HIV/Aids awareness and prevention campaigns

Community based care

Integrated communicable diseases and health programme

District Health council Implementation

Page 22: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

22

Sector Plans and Programmes

- Land Reform and Settlement plan

- Integrated Transport plan

- Integrated Waste Management plan

- Integrated Environmental Programme

- Local Economic Development plan

- Disaster Management plan

Page 23: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

23

Sector Plans (cont..)

- Water Services Development plan

- Safe and healthy environment

- Communicable Diseases Programme

- District Spatial Development Framework

Page 24: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

24

IDP Assessment

GENERAL CHALLENGES:

- Alignment of cluster envelopes

- New powers and functions

- Capacity to develop and operationalise PMS

- Non participation of government departments – alignment

- Financial and Human Capacity to implement IDP

Page 25: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

MECHANISM TO MONITOR MECHANISM TO MONITOR THE IMPLEMENTATION OF THE IMPLEMENTATION OF

THE IDPTHE IDP

ADM PERFORMANCE ADM PERFORMANCE MANAGEMENT SYSTEMMANAGEMENT SYSTEM

Page 26: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

26

Process

Legislative Context: Municipal Systems Act and Regulations;

IDP 2002/2003 – setting of Objectives and KPI’s for ADM;

Framework for PMS adopted June 2002 – customised Balanced Scorecard adopted;

2002/2003 – First year of implementation;

District Scorecard and Departmental Scorecards developed and implemented.

Page 27: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

27

Process (cont…)

2003/2004 reviewed IDP adopted – reworked objectives and strategies;

These reworked objectives and strategies informed Departmental and District Scorecards;

2002/2003 financial year – first PMS Audit completed by AG – qualified report: PMS Audit Committee (Reg 14).

Page 28: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

28

The Municipal Scorecard

ResourceManagementPerspective

Service Delivery

Perspective

MunicipalDevelopmentPerspective

Governance Process Perspective

The Municipal Organisation

The Municipal Area

Inputs

Process

OutcomesOutputs

Page 29: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

29

The District Scorecard

DistrictDevelopmentPerspective

Governance Process Perspective

The District Area Process

Outcomes

DistrictDistrictServiceServiceDeliveryDelivery

DistrictDistrictResourceResource

ManagementManagement

MunicipalMunicipalServiceServiceDeliveryDelivery

MunicipalMunicipalResourceResource

ManagementManagement

OutputsInputs

Page 30: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

30

Implementation Processes

Departmental scorecards drafted for current financial year in line with reviewed IDP;

District scorecard completed;

Generic reporting format , including KPI reporting sheets, for Section 57 employees developed and used for quarterly reviews to ensure uniformity of approach;

Page 31: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

31

Implementation Processes (cont…)

Accountability agreements put in place through all HOD’s – inclusion in all departmental scorecards

PMS Audit Committee appointed by Council – Reg 14(2) – first review of Sect 57 employees nearing completion and report to Council to be tabled during Feb 2004.

Page 32: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

32

The District Scorecard

DistrictDevelopmentPerspective

Governance Process Perspective

The District Area Process

Outcomes

DistrictDistrictServiceServiceDeliveryDelivery

DistrictDistrictResourceResource

ManagementManagement

MunicipalMunicipalServiceServiceDeliveryDelivery

MunicipalMunicipalResourceResource

ManagementManagement

OutputsInputs

Page 33: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

33

Critical Success Factors

Quality of IDP – specifically in relation to objectives, strategies and KPI’s (per cluster);

Consensus on scorecard content (linked to municipal powers and functions);

Regular performance review and feedback using standardised measurement tools;

Legislative compliance to be ensured

Page 34: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

AMATOLE DISTRICT MUNICIPALITY’S

PROGRAMME OF SUPPORT

TO

LOCAL MUNICIPALITIES

Page 35: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

35

Introduction

ADM has embarked on a strategic initiative to provide integrated approach to support Local Municipalities and is now in a position to meaningfully fulfill its Section 83(3)(c) functions in terms of the Municipal Structures Act.

Departmental support has been significantly enhanced through the formation of a dedicated strategic Municipal Support Unit (MSU) which is institutionalised in the District Municipality.

Page 36: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

36

Municipal Support UnitMUNICIPAL MANAGER

STRATEGIC MANAGER

MUNICIPAL SUPPORT MANAGER

FINANCEFINANCE HRHR TECHNTECHNEng.Eng.

ADMINADMIN IDPIDPPIMSSPIMSS

TECH.TECH.TP/LUMTP/LUM

LED/LED/Environ.Environ.

ITIT

Local Municipalities (Cat B’s)Local Municipalities (Cat B’s)

Project Project ManageManagesupportsupport

HOD

HOD

HOD

HOD

Page 37: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

37

ProcessPerformed an environmental scan

Assessed impact of phase 1 support to LMs

Identified other role-players in ADM’s area

Identified areas of support to be provided by the Municipal Support Unit.

Developed a programme of support currently being rolled out to LMs (2003 onwards)

Page 38: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

38

Determination of Training Needs

Analysis of phase 1 of support to LMs

Environmental scans

Financial health survey, based on AG

check list

Page 39: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

39

Determination of Training Needs (cont…)

OTHER MECHANISMS:

CFO Co-ordinating Committee meetings

Human Resources Managers Forums

Administration Managers Forum

LED Managers Forum

Reports submitted to DIMAFO

Interaction with LMs

In-depth status quo analysis of Ward Committees

Page 40: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

40

Support needs addressed by:

Identifying available funding

Allocating funding to prioritized needs

Addressing unfunded needs through- Interacting with LMs- Facilitating workshops- Learning and sharing forums- Ad hoc support on request

Page 41: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

41

Support needs addressed by: (cont…)

Sourcing additional funding

Establishment of Donor Funding Forum , including donor funding policy & database, to access donor funding …- To supplement equitable share & own

revenue sources- To improve budget allocations to

municipal programs

Page 42: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

42

Subsidiary Support

Co-ordination of CFO Co-ordinating Committee, HR Managers’ Forum, Administration Managers’ Forum, MSC and DIMAFO meetings

Evaluation of LM priority project business plans to ensure compliance with respective IDPs and cluster funding envelopes

Page 43: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

43

Subsidiary Support (cont…)

Evaluation of LM CMIP business plans to ensure compliance with respective IDPs

Job description writing (ToR)

Identification of MSIG and LGSG as sources of funding and preparation of business plans

Page 44: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

44

Monitoring tools developed to achieve the following objectives:

To inform planning & co-ordination of support activities of functional departments.

To provide quantifiable measures of achievement of support objectives.

To inform on project areas requiring additional focussed and dedicated support.

LM Support Monitoring

Page 45: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

45

LMs submit monthly reports for purposes of discussing the following key issues …

Monitoring and evaluation of linkages between IDP and operating and capital budgets

IDP implementation and monitoring

Financial management (i.e. in-year reporting as required by Proclamation R1536)

Key issued for consideration at DIMAFO

Page 46: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

46

Preparation, approval and submission of annual reports, financial statements and responses to Auditor-General’s comments

Implementation of free basic services

Political and administrative governance

Public participation and communication

Intergovernmental relations

Key issued for consideration at DIMAFO (cont…)

Page 47: IDP Conference 2004 “Developmental Governance in Action” SESSION 5: ‘Managing the IDP: The Amatole District Municipality Experience’ ‘Managing the IDP:

Thank You