Top Banner
Identification and Quantification of Incremental Market Risk By Sy Sarkarat Ph. D.* * Dr. Sarkarat is professor of economics at WVU-Parkersburg, his research interest is in real asset appraisals and valuation and economic impact studies.
33

Identification and Quantification of Incremental Market Risk

Jan 13, 2016

Download

Documents

Kyrie

Identification and Quantification of Incremental Market Risk. By Sy Sarkarat Ph. D.* * Dr. Sarkarat is professor of economics at WVU-Parkersburg, his research interest is in real asset appraisals and valuation and economic impact studies. Presentation Objectives. Introduction Background - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Identification and Quantification of Incremental Market Risk

Identification and Quantification of Incremental

Market Risk

BySy Sarkarat Ph. D.*

* Dr. Sarkarat is professor of economics at WVU-Parkersburg, his research interest is in real asset appraisals and valuation and economic impact studies.

Page 2: Identification and Quantification of Incremental Market Risk

Presentation Objectives

• Introduction

• Background

• Methods

• Results

• Conclusion

Page 3: Identification and Quantification of Incremental Market Risk

Introduction Prominent Techniques For Asset Valuation

• Discounted Cash Flow Analysis (DCF) n

NPV = ∑CF/(1+ r´)n - Io

1

• Option Valuation (Black/Scholes 1973).

Page 4: Identification and Quantification of Incremental Market Risk

Comparison for Pricing Models Stock Call Options and Undeveloped Reserves

+ Current value of Reserve

+ Variance of rate of return of developed reserve

- Development cost

+ Relinquishment requirement

+ Risk free rate of return

+ Stock price (S)

+ Variance of rate return on stock

- Exercise value (E)

+ Time to expiration (T)

+ Risk-free interest rate

Page 5: Identification and Quantification of Incremental Market Risk

Problems

• Discounted Cash Flow (DCF) analysis is “static analysis” that account only imperfectly with uncertainty and does not recognize the possibility of changing operations in reaction to changing future economic conditions.

• The Option Pricing Method (OPM) provides more flexibility for management in investment and operation decision making. However OPM could overvalue the worth of a given project if the output price is highly volatile.

• Where: DCF = Discounted Cash Flow, OPM = Option Pricing Method

Page 6: Identification and Quantification of Incremental Market Risk

Reasons for Alternative Evaluation Method

• DCF analysis - undervalues the project by assuming higher discount rate to adjust for risk, and

• OPM - overvalue a project with a high volatile output price.

• Absent of operational flexibility.

Page 7: Identification and Quantification of Incremental Market Risk

Expert Systems

• Expert systems (Es) are computer programs that mimic human logic and solve problems much as a human expert would.

• The expert system is written to obey the rules in decision making.

• Advantage of expert system in investment decision making include the opportunities to:

1. explore the alternatives; 2. recommend strategies; 3. determine the value of a project for given strategy; and 4. explain the expert system’s reasoning process.

Page 8: Identification and Quantification of Incremental Market Risk

DomainKnowledge

Base

DomainKnowledge

Base

ExpertExpert

UserUser

SpreadsheetSpreadsheet

Data Base Work Sheet

.WKS

Data Base Work Sheet

.WKSVP-Expert

.VPX

VP-Expert.VPX

Decision Rules.KBS

Decision Rules.KBS

The Architecture of the Expert System For The Project

Page 9: Identification and Quantification of Incremental Market Risk

SignificanceThe result of this study will:

1) Establish an empirical decision support system that mimics the actual decision process for investment and operation strategies; and

2) Provide an alternative valuation method for investment and operation decision making.

Page 10: Identification and Quantification of Incremental Market Risk

Significance… Contd.

• Compare the performance of the Expert Systems with other methods using simulation.

• Perform Sensitivity Analysis

• Using the results of the above comparison, identify the incremental market risk.

• Establish the statistical significance of the results using Hypothesis testing.

Page 11: Identification and Quantification of Incremental Market Risk

Context of the Present Research: Valuation of Gold Mine Project

• An investment simulation was developed using a gold mine project with stochastic output price.

• Time series data for 1973 to 84 (gold price).

• To test the behavior of the simulation for 1985 to 1994.

• The simulation was based on Decision Rule and NPV.

Page 12: Identification and Quantification of Incremental Market Risk

Which Investment Model Maximizes Project’s Value?

Max. NPV = ∑ (1-δ)-t [(pt qt) – Cv,t qt] – Io1

n

Subject to Rt = qt , Investment method

Given Ro, qt ≥ 0

Where: NPV = expected net present value, Pt = exogenous gold price qt = gold output per year, Cv = extraction cost Io = initial capital expenditure, Ro = original stock of ore δ = discount rate

Page 13: Identification and Quantification of Incremental Market Risk

Model Specification

The life of this project is assumed to be 10

years (ℓ = 10) and there are 10 individual

project cycles Pcj, j = 1 to 10. Net present

value of each project cycle is determine as:

Page 14: Identification and Quantification of Incremental Market Risk

Model Specification…….Contd Net Present Value

ℓ• Pcj = Io - ∑ [(Pi – Vi) Qi / (1+δ)t ], j = 1 to 10. 1

where 1(1+δ)t discount factor (r and r), t = 1, 2,….T

ℓ = the life of gold mine project, (ℓ = 10).

Pcj, j = 1 to10 (number of individual project cycles, i.e. jth project cycle).

n = life of each individual project cycle (PCj ), and for j = 1 to 6, n is 5, and for j = 7 to 10, n is 11 - j, (ℓ = 10).

Io Capital outlay 10

NPV =∑ [(CF1+ CF2 +…..+ CF0)/ (1+δ)t ]

Page 15: Identification and Quantification of Incremental Market Risk

Process of project valuationAn Example

1

CFDcf, 1 to 10.

CFEs, 1 to 10.

2

34

56

CFDcf

CFEs’

NPV Dcf

NPV Es

For 10 Pcj with n price Iterations, n = 50

˝ ˝ ℓ = 10˝ ˝ ˝ ˝ ˝

78

910

for n = 50

Pc1

1) Using u & σ on historical gold price 2) Price forecast for n iterations3) Data period 1973 to 84, add a year for PCt +1

4) Ex post simulation 1985 - 94

μ NPVDcf

μ NPVEs

10 NPV =∑ [(CF1+ CF2 +…..+ CF10)/ (1+δ)t ]

1

Page 16: Identification and Quantification of Incremental Market Risk

Case I          

P_TODAY 317.32 Case 1  

Year_1 1985 1986 1987 1988 1989

  = = = = =

  Pf Pf Pf Pf Pf

  - - - - -

  5.00 4.00 3.00 2.00 1.00

CASE1_P 277.42 301.67 312.33 265.00 330.11

Total Revenue 2774.20 3016.70 3123.30 2650.00 3301.10

CASE1_AFC 0.00 0.00 0.00 0.00 0.00

CASE1_AVC 280.00 280.00 280.00 280.00 280.00

CASE1_TFC 0.00 0.00 0.00 0.00 0.00

CASE1_TotalVC 2800.00 2800.00 2800.00 2800.00 2800.00

  - - - - -

Total_Cost 2800.00 2800.00 2800.00 2800.00 2800.00

CASE1A_CF -25.80 216.70 323.30 -150.00 501.10

  - - - - -

CASE1A_NPV -566.23 -465.70 -593.60 -846.00 -660.44

CASE1A_ONPV 507.79 590.09 437.29 164.15 339.72

CASE1A_RNPV 487.23 573.75 426.43 157.77 335.55

RESULTS1B Wait Wait Wait Wait Wait

CASE1B_CF 0.00 0.00 0.00 0.00 0.00

NPV without expert system -566.23

NPV with expert system -1100.00  

 

- - - -

 

Example

Page 17: Identification and Quantification of Incremental Market Risk

Case VI                    

  317.20 Case 6  

Year_6 * * * * * 1990 1991 1992 1993 1994

  = = = = =

  5.00 4.00 3.00 2.00 1.00

  Pf Pf Pf Pf Pf

  - - - - -

CASE6_P * * * * * 272.23 350.99 340.37 295.87 350.19

Total Revenue 2722.30 3509.9

0 3403.7

0 2958.7

0 3501.9

0

CASE6_AFC * * * * * 0.00 0.00 0.00 0.00 0.00

CASE6_AVC * * * * * 280.00 280.00 280.00 280.00 280.00

CASE6_TFC * * * * * 0.00 0.00 0.00 0.00 0.00

CASE6_TotalVC * * * * * 2800.00

2800.00

2800.00

2800.00

2800.00

Total_Cost 2800.00 2800.0

0 2800.0

0 2800.0

0 2800.0

0

CASE6A_CF * * * * * -77.70 709.90 603.70 158.70 701.90

CASE6A_NPV * * * * * 244.08 509.95 25.44 -

420.70 -

484.30

CASE6A_ONPV * * * * * 1441.01 1659.2

0 1109.4

2 616.37 523.94

CASE6A_RNPV * * * * * 1393.85 1622.9

3 1087.3

2 604.36 518.09

RESULTS6B * * * * *Shutdown

ReStart

Operate

Operate

Operate

CASE6B_CF * * * * * -155.00 589.90 603.70 158.70 701.90

NPV without expert system

244.08

NPV with expert system 83.93  

 

Example

Page 18: Identification and Quantification of Incremental Market Risk

Year 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 NPV

= = = = = = = = = = = =

IT1  

CF I II III IV V VI VII VIII IX X  

   

C.CF52

-25.80

-71.40 267.40 385.00 351.40 -77.70

172.50 444.50 86.50

332.60 -280.95

   

VP.Inst. Wait Wait InvestOperat

eOperat

eShutdow

n

ReStart

Operate

Shutdown

ReStart  

   

ES.CF52 0.00 0.00

-832.60 385.00 351.40 -155.00 52.50 444.50 -155.00

212.60 -46.33

Cash Flows

Page 19: Identification and Quantification of Incremental Market Risk

Convergence test for the expected NPVs.

Methods Values % Change

μ NPVc, n = 30 7.70

μ Nave, n = 30 12.2

μ NPVc, n = 40 9.10 0.14

μ Nave, n = 40 13.5 0.10

μ NPVc, n =50 9.30 0.01

μ Nave, n = 50 13.9 0 02r =9% r’ = 14%

==========================

Value of Project with Alternative Valuation Methods

0

2

4

6

8

10

12

14

16

? NPVc, n =30

? NPVe, n =30

? NPVc, n =40

? NPVe, n =40

? NPVc, n=50

? NPVe, n =50

In m

illi

on

of

$

Page 20: Identification and Quantification of Incremental Market Risk

Hypothesis Testing:

Test of Difference in means μ NPV State hypothesis

Ho μ NPVEs - μ NPV Dcf = 0

H1 μ NPVEs - μ NPV Dcf # 0

@ α =0.05 (+ & - 1.96 )The test of significant rejects the null hypothesis and accepts the alternative hypothesis

μ Es = 13.97 & σ Es = 6.00,

μ Dcf = 9.26 & σ Dcf = 5.53, n = 50

Page 21: Identification and Quantification of Incremental Market Risk

The ResultsItems μ Es μ Dcf

Minimum 3.60 -2.50

Maximum 26.41 21.95

Expected value 13.97 9.26

Standard Deviation 6.10 5.50

Coefficient of Variation (CVar)

0.43 0.60

P ( μ < 0 ) 0.00 5%

Page 22: Identification and Quantification of Incremental Market Risk

Risk of Project With Each Evaluation Method

The probability project will yield negative

return

( μ < 0 ) = 0.00

Where:

μ Es = 13.97 & σ E = 6.00, P (μ Es < 0) = 0

μ Dcf = 9.26 & σ Dcf = 5.53, P (μ Dcf < 0) = 5%

Page 23: Identification and Quantification of Incremental Market Risk

Sensitivity AnalysisItems μ Es (M $)

Discount rate 5%

Mean

Std

CVar

ρ (u < 0)

Discount rate 9%

Mean

Std

CVar

ρ (u < 0)

Discount rate 13%

Mean

Std

CVar

ρ (u < 0)

18.80

7.908

0.41

0.00

13.90

6.00

0.41

0.00

10.50

4.35

0.41

0.00

1) As r , μ Es 2) ρ (u < 0) =

0.00, invest. & operations are postponed.

Page 24: Identification and Quantification of Incremental Market Risk

Alternative Value OF The Project

n = 30

μ Dcf 7.96

μ Es 12.24

OPM 22.30

n = 40

μ Dcf 9.10

μ Es 13.50

OPM 22.30

n = 50

μ Dcf 9.30

μ Es 13.90

OPM 22.30

Page 25: Identification and Quantification of Incremental Market Risk

Identification Of Incremental Market Risk Captured By Expert System

1. Find μ Dcf @ r’ =14% (risk adjusted discount rate), which amounted to $9.30 million;

2) Find μ Es @ r = 9% (risk free rate of return), which amounted to $13.97 million;

3) Find that discount rate (r*) which equates μDcf to μ Es at risk-free @ r = 9% (risk free rate of return), which is 10.6%; and

4) Find the differences in discount rates used in step 3. This difference is the values of incremental market risk (r m = r* - r) that is removed through operational flexibility using expert system technology in project evaluation.

Page 26: Identification and Quantification of Incremental Market Risk

Identification Of Incremental Market Risk Captured By Expert System

(r m = r* - r) = 10.60% - 9% = 1.60%

Where:r = r + r m + r a

r m = market risk incrementr a = market risk increment due to other risk elementsr = risk free discount rater = risk adjusted discount rate

Page 27: Identification and Quantification of Incremental Market Risk

Estimation of Incremental Market Risk

0

5

10

15

20

25

0% 10% 20% 30%

Discount Rate

Va

lue

s o

f p

roje

ct

(M

$)

DCFEX

9% 14%

10.60% - 9% = 1.60%

Page 28: Identification and Quantification of Incremental Market Risk

Analysis of Result

• Expert system Vs. DCF

• Conduct sensitivity analysis (responsiveness to change in disct. rate?)

• Ability of Es to quantify and capture the incremental market risk through O.F.

Page 29: Identification and Quantification of Incremental Market Risk

Analysis contd……

• Expert System valuation resulted in lower relative risk in project’s expected NPV;

• Expert System diversified a portion of market risk by recognizing the value of operational flexibility;

• Expert System quantified the increment of market risk captured through operational flexibility; and

• Expert System recognized the effects active management may have on the value of a project.

Page 30: Identification and Quantification of Incremental Market Risk

Analysis contd…..

• Te ρ (μ NPV < 0 ) exist with DCF valuation, but not

with Es.

• Value (μ NPV ) obtained by DCF analysis is more

volatile than value obtained with Es.

• Thus supporting the notion that Es diversify increment of market risk through operational flexibility.

Page 31: Identification and Quantification of Incremental Market Risk

Thank you

Page 32: Identification and Quantification of Incremental Market Risk

Questions

Page 33: Identification and Quantification of Incremental Market Risk

Risk Adjusted Discount Rate

r = r + ßi (r m – r) = 9% + 1 (14% – 9%)

r = 14% (rate of return on gold investment, 1974- 84), r =9% (interest return on short-term U.S. Securities for early 80s) and ß = 1, historical volatility of rate of return on gold for Newmont mining co.