2011 Chapter 6 updates and accomplishments ♦ 1 Appendix D: Progress on State Plan Implementation Tasks 6.1 Local Working Group Milestones Task Responsible Party 2009-2011 Accomplishments Next Steps or Target Deadline 6.1.1. Initiate formal Local Working Group (LWG) in Mountain Home. Idaho Department of Fish and Game (IDFG) Group met 6 times in 2011, but no progress towards development of local plan. Target Deadline: July 1, 2010 6.1.2. LWGs provide annual report to Sage- grouse Advisory Committee Technical Assistance Team (SAC TAT). LWGs Statewide LWG Annual Report published annually. Next Steps: Due January 15, annually 6.1.3. LWGs without completed plans will finalize their plans. LWGs 9 LWGs have completed plans as of January 1, 2012. Next Steps: LWGs complete their plans within 2 years of formation of the group. 6.1.4. Identify funding needs and funding sources to implement the Conservation Plan for the Greater Sage-grouse in Idaho (i.e. State Plan) and LWG plans, including support for LWG facilitators. LWGs, Sage- grouse Advisory Committee (SAC), SAC Funding Subcommittee Funding and cost-share has been received from numerous organizations including Bureau of Land Management (BLM), IDFG, U.S. Forest Service (FS), Natural Resources Conservation Service (NRCS), U.S. Fish and Wildlife Service (USFWS), Idaho Department of Lands (IDL), Department of Energy (DOE), North American Grouse Partnership, the Nature Conservancy (TNC), Resource Conservation and Development councils, soil conservation districts, cooperative weed management areas, private landowners, other non-governmental organization, Shoshone-Paiute Tribes, Shoshone- Bannock Tribes, etc. IDFG and OSC provided a funding summary at the November 2011 SAC meeting. Next Steps: Develop a 5- year plan of funding needs and existing commitments for plan implementation by October 31, 2010. This plan will be updated in October each year. At the November 2011 SAC meeting, the SAC Funding Subcommittee delayed the 5-year plan given current uncertainty regarding federal funding sources. A funding summary will be included in the 2009 Annual Statewide Sage-grouse Report and annually
41
Embed
Idaho Fish and Game | Idaho Fish and Game - Idaho Sage-grouse … · 2019-05-28 · measurable habitat restoration (based on Restoration Emphasis Areas) or maintenance goals for each
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
2011 Chapter 6 updates and accomplishments ♦ 1
Appendix D: Progress on State Plan Implementation Tasks
6.1 Local Working Group Milestones
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
6.1.1. Initiate formal Local Working Group
(LWG) in Mountain Home.
Idaho Department
of Fish and Game
(IDFG)
Group met 6 times in 2011, but no progress towards
development of local plan.
Target Deadline: July 1,
2010
6.1.2. LWGs provide annual report to Sage-
grouse Advisory Committee Technical Assistance
Team (SAC TAT).
LWGs Statewide LWG Annual Report published annually. Next Steps: Due January
15, annually
6.1.3. LWGs without completed plans will
finalize their plans.
LWGs 9 LWGs have completed plans as of January 1, 2012. Next Steps: LWGs
sage-grouse project successes. In addition, see 6.2.13
and 6.2.14.
Target Deadline: January
2010
2011 Chapter 6 updates and accomplishments ♦ 5
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
6.2.13. Develop sage-grouse educational
materials to be incorporated into education
curricula, such as Idaho Rangeland Resource
Commission (IRRC).
SAC Education
Subcommittee in
coordination with
IRRC and other
interested groups
IDFG had a project WILD program for educators
about sage-grouse and sharp-tailed grouse in Twin
Falls in 2010. Dialogue has been established between
this program and IRRC.
Target Deadline: April
2010
6.2.14. Develop planning and support protocols
to assist SAC and LWGs on field trips.
SAC Education
Subcommittee
Completed, available from IDFG upon request. Target Deadline: April
2010
6.2.15. Consider biennial LWG Conference, to
focus on sharing information and success stories
among LWGs.
SAC and SAC
Education
Subcommittee
On hold, pending future funding. Target Deadline: April
2010
6.2.16. Consider sage-grouse educational seminar
that would be open to the general public.
SAC and SAC
Education
Subcommittee
On hold, pending future funding. Target Deadline: April
2011
6.2.17. Develop PowerPoint presentation
materials that can be used by SAC, LWG
members, and agency personnel to educate the
public and user groups (e.g., Off-Highway
Vehicle [OHV] groups) about sage-grouse and
their habitat.
SAC Education
Subcommittee
Target Deadline: April
2010
6.2.18. Pursue opportunity to use uncompensated
time and expenses from non-governmental
organization members, landowners, and general
public for funding cost share on sage-grouse
projects.
SAC Funding
Subcommittee
In 2011 SAC and LWG volunteer hours were used as
matching funds to secure grants from the BLM and
USFWS for SAC and LWG facilitation.
Target Deadline: July
2010 and annually
thereafter
2011 Chapter 6 updates and accomplishments ♦ 6
6.3 Rangewide Policy Milestones
Task Responsible Party
2009-2011 Accomplishments Next Steps or Target
Deadline
6.3.1. Work with other Western states and federal
agencies to assure that development stipulations
(e.g., lek buffers, No Surface Occupancy
stipulations) are similar among states, with a clear
link to science.
IDFG in
coordination with
other agencies
Target Deadline: Initiate
discussion at July 2010
Western Association of
Fish and Wildlife Agencies
(WAFWA) meeting.
6.3.2. Work with other Western states and federal
agencies to assure that “core areas” are defined,
delineated, and mapped similarly among states.
IDFG in
coordination with
other agencies
Target Deadline: Initiate
discussion at July 2010
WAFWA meeting.
6.3.3. Work with other Western states and federal
agencies to develop rangewide lek status
definitions.
IDFG in
coordination with
other agencies
Target Deadline: Initiate
discussion at July 2010
WAFWA meeting.
2011 Chapter 6 updates and accomplishments ♦ 7
6.4 Conservation Measures Milestones
6.4.1 Wildfire
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
6.4.1.1. Ensure the BLM/FS Fire Management
Plans, Fire Management Unit Databases, and
related tools are updated annually, based on the
most recent Sage-Grouse Habitat Planning Map.
BLM, FS Five dispatch centers in southern Idaho send
interagency fire suppression resources based on
predetermined response plans for each response
area. The response is dependent on fire danger
levels, weather, access, and resource availability. In
multiple ignition events, fire managers make
judgment calls to adjust the response. Implemented
BLM Idaho Instruction Memorandum (IM) IM ID-
2008-051 Districts update Fire Management Plans
and dispatch information with the latest sage-grouse
habitat information. Also directed Districts to
identify, in GIS, highest priority sage-grouse
habitats for use by dispatch.
FS fire management plans in southern Idaho reflect
priorities for protecting sage-grouse habitat. Fire
Management Plans have been reviewed and updated
annually since 2005.
Next Steps: BLM and FS
will continue to review and
validate Fire Management
Plans annually.
6.4.1.2. Require, if practical, the washing of the
undercarriage of fire vehicles and equipment
prior to deployment and prior to demobilization
from fires, to reduce spread of seeds of invasive
species.
BLM, FS, IDL
BLM Idaho Falls and Twin Falls Districts: The
2008 Record of Decision for the Fire, Fuels and
Related Vegetation Management Direction Plan
Amendment recommends cleaning equipment
before and after Type I and II wildfire incidents. It
also recommends that staging areas and fire camps
should avoid sites with noxious weeds.
The Southwestern Idaho (Boise District) Fire
Planning Unit Fire Management Plan directs that
equipment will be cleaned before arriving on-site,
and where possible vehicle wash stations will be set
up in base camps. Staging areas and fire camps
should be located on sites free of invasive non-
native species.
Next Steps: Ongoing
2011 Chapter 6 updates and accomplishments ♦ 8
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
All National Forests in Southern Idaho have
incorporated invasive species prevention practices
into their Forest Fire Management Plans as of 2008.
IDL requires the washing of undercarriage of all its
fire vehicles and equipment prior to deployment to
reduce spread of invasive species.
6.4.1.3. Use knowledgeable resource advisors on
fires threatening sage-grouse habitats to provide
guidance on sage-grouse habitat protection.
Incorporate maps of sage-grouse habitats into
fire management plans to ensure the protection
of these habitats during wildfire suppression
efforts.
BLM, FS, IDL
BLM implemented IM ID-2008-051 emphasizing
Resource Advisors, knowledgeable about local
wildlife habitat concerns, are assigned to fires
within or threatening Key habitat.
FS assigns Resource Advisors to extended attack or
large fires. A person knowledgeable about sage-
grouse habitat is assigned when these fires occur in
sage-grouse habitat.
Next Steps: Ongoing.
6.4.1.4. Incorporate training in sage-grouse
conservation and suppression priorities during
annual agency firefighter training; include Rural
Fire Districts when possible.
BLM, FS, IDL
BLM implemented IM ID-2008-051. Managers/fire
personnel ensure that briefings are provided to
incident commanders, dispatch and engine bosses
early in the fire season regarding the importance of
protecting sage-grouse habitat and sagebrush
steppe.
The FS discusses the importance of protecting sage-
grouse habitat annually at Inter-Agency Spring Fire
Operations Meetings.
Next Steps: Annually,
before the ensuing fire
season.
6.4.1.5. Minimize loss of sagebrush during fire
suppression and mop up activities.
BLM, FS
BLM issued IM ID-2008-051 which emphasizes
tactics that are intended to minimize loss of
sagebrush, such as avoiding burn-out of islands of
unburned sagebrush.
The BLM Idaho Falls District issues suppression
instructions for the liberal use of retardant in
sagebrush steppe habitat, especially occupied and
known historic sage-grouse habitat.
Next Steps: Ongoing.
2011 Chapter 6 updates and accomplishments ♦ 9
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
The FS discusses the importance of leaving
unburned islands of sagebrush within fire
perimeters at annual Inter-Agency Spring Fire
Operations Meetings.
6.4.1.6. Identify access roads where the
installation of additional fire danger signs may
be warranted. Install new signs as needed.
BLM, FS, IDL, in
cooperation with
LWGs
BLM and FS have installed numerous new signs
since 2006.
North Magic Valley: Sent letter to Kimama
Highway District requesting information on
maintenance of Carey-Kimama road in relation to
fire danger.
Upper Snake: Signs have been installed on high
access roads that pose fire hazards. There are
approximately 50 permanent fire danger signs on
the Targhee NF. Due to public concerns about sign
pollution, new signs are not placed. However, fire
crews patrol throughout the summer educating the
public about fire safety, putting out abandoned
campfires, and placing temporary signs during high
fire danger periods or during periods of fire
restrictions.
Next Steps: Ongoing as
needed
6.4.1.7. Increase emphasis on mapping known
water sources to ensure Interagency Fire
Dispatch Centers have the latest information for
fire suppression.
BLM, FS, state
agencies, in
cooperation with
landowners and
LWGs
Big Desert, Challis: Completed.
Upper Snake: Known water sources in the Big
Desert have been mapped. Efforts to map water
sources in Medicine Lodge and Sand Creek are
currently occurring. Additionally, efforts to
determine compatibility of existing water sources
with currently owned equipment is presently
occurring.
On the Forest, all known water sources are already
mapped and this information is at the interagency
fire dispatch center. They even know which water
bodies have whirling disease. The FS does not
utilize water troughs because that would create
conflicts with permittees and grazing management.
The FS has several engines and water tenders (both
Target Deadline: Ongoing
2011 Chapter 6 updates and accomplishments ♦ 10
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
in-house and contract) that can get water to a dry
site. USFS fire fighting protocols have incorporated
sage-grouse considerations including ensuring that
incident command has information about leks, key
habitat, and brood areas; highly aggressive initial
attacks, and efforts to contain and maintain islands
of intact habitat.
6.4.1.8. In areas of limited water availability
identify new water sources for fire suppression.
Locate such water access facilities near suitable
access roads. Mark locations of new sites on
maps and distribute maps to Interagency
Dispatch Centers.
BLM, FS, state
agencies, in
cooperation with
landowners and
LWGs
Big Desert: 48,000 gallons available on private
landowner’s NRCS project. BLM installed 1.4
miles of pipeline which benefits sage-grouse by
reducing water truck activity in the allotment during
lekking and nesting and providing a source of water
for potential use during wildfire suppression
activities.
Upper Snake: Identification of new wells is on-
going. In addition, one local crop duster is known
to keep his plane loaded with water during fire
season and he responds to calls for spot fire
suppression on private ground.
Target Deadline: Ongoing
6.4.1.9. Work with lessees, permittees and
private landowners to encourage that water
storage facilities remain full during the fire
season.
BLM, FS, IDL, in
cooperation with
LWGs
Big Desert: Addressed in BLM’s permitting
process.
Upper Snake: This is on-going. Generally done
verbally one-on-one between ranchers and
firefighters.
USFS permittees always keep their troughs full
during the fire season/grazing season. They have to
in order to provide for the cattle and maintain
distribution which enables them to keep their cattle
on the allotment for the full permitted season.
Target Deadline: June 1,
2010
6.4.1.10. Identify, prioritize, and implement fuel
breaks (e.g., mowing, herbicide application,
strictly managed grazed strips or green strips,
etc.) to aid in controlling wildfire should wildfire
occur near key sage-grouse habitats. Location of
fuel breaks should be based on 1) areas of high
BLM, FS, IDL,
IDFG, NRCS,
working with
LWGs
FS identified and implemented fuel breaks on the
Curlew National Grasslands in 2007 and 2008 in
order to protect remaining areas of unburned
sagebrush.
BLM identified and implemented fuel breaks on the
Next Steps: Ongoing
2011 Chapter 6 updates and accomplishments ♦ 11
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
fire risk; 2) protection of intact sagebrush
habitats; 3) protection of important sage-grouse
nesting, brood-rearing, and wintering areas; and
4) utilize existing roads where possible.
Big Desert in 2007-2011.
6.4.1.11. Explore options for agreements with
railroad companies to manage fuels/invasives
within railroad rights-of-way to minimize
wildfire ignitions.
BLM, FS, IDL As of January 2009, BLM is coordinating with
railroad companies. BLM provides fire prevention
presentations to railroad workers, and actively
pursues investigations and enforcement actions for
railroad fires, including reimbursement for fire
suppression costs associated with railroad-caused
fires.
Target Deadline: July 31,
2010
6.4.1.12. Work closely with utility companies to
reduce wildfire ignitions within rights-of-way.
BLM, FS, IDL BLM provides fire safety and prevention
presentations to power-line workers annually, and
has established a Memorandum of Agreement with
Idaho Power, with protocols for fire prevention and
safety, and for coordination during fires.
IDL (SW District) meets with all the three power
companies twice a year in the fall and spring.
East Idaho Dispatch meets with utility companies in
their dispatch area each spring.
Target Deadline:
December 31, 2010
6.4.1.13. Explore and implement use of targeted
grazing1 where fuel reduction is needed to
protect and enhance sage-grouse habitat.
BLM, FS, IDL,
NRCS, in
cooperation with
universities,
livestock operators,
and LWGs
Draft guidance is being developed by BLM.
Upper Snake: Currently working with ranchers to
target roadsides by leaving at least one band of
sheep or goats behind to graze through the growing
season along roadsides.
The USFS has flexibility built into allotment
management plans regarding on/off and pasture
rotation dates for fuel reduction or drought. Further,
utilization levels are limited to 50%. Upland areas
do not always reach 50%, but this approximate level
of utilization reduces fuels.
Target Deadline: Ongoing.
LWGs provide lists of
accomplishments, needs,
and proposals as part of
LWG annual reporting.
1 Targeted grazing is an application of livestock grazing at a specified season, duration and intensity to accomplish specific vegetation management goals. The
term “targeted” refers to the specific plant or landscape that is the aim of controlled grazing practices (American Sheep Industry Association 2006).
2011 Chapter 6 updates and accomplishments ♦ 12
6.4.2 Infrastructure
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
6.4.2.1. Research mitigation and crediting
programs used by other states and the federal
government in shrubsteppe or other habitats
(e.g., wetlands). Compile results and develop
options for mitigation and crediting program for
sagebrush steppe habitats in Idaho.
SAC Mitigation
Subcommittee, in
cooperation with
OSC
The Mitigation Subcommittee researched a variety
of mitigation and crediting programs. Options from
various programs were considered during the
development of a mitigation framework for sage-
grouse habitat in Idaho.
Target Deadline: July 31,
2010
6.4.2.2. Develop proposal for a mitigation and
crediting program for sagebrush steppe habitats
in Idaho with on-site mitigation as the primary
priority and develop recommendations for policy
consideration.
SAC Mitigation
Subcommittee, in
cooperation with
OSC, SAC TAT
The Mitigation Subcommittee presented a draft of a
compensatory mitigation framework to state and
federal agencies, and the SAC August-October
2010. In December 2010, the SAC approved the
mitigation framework to be submitted for
consideration by relevant entities. In early 2011,
the Mitigation Subcommittee presented the
framework to IDFG, BLM, FS, OSC, Office of
Energy Resources, the Governor’s Office, the Idaho
Association of Counties, and Rocky Mountain
Power. Some minor changes were made after these
meetings. In August 2011, the Mitigation
Subcommittee submitted the proposal to IDFG and
OSC for consideration. The agencies replied they
could not provide a definitive response but commit
to being as timely as the need for multi-level state
coordination allows.
Next Steps: Finalize
proposal by December 1,
2010
6.4.2.3. Implement appropriate timing
stipulations for construction and maintenance
activities on federal land and encourage on state,
private, and tribal land within 1 km of occupied
leks; emphasize timing restrictions in Rights of
Way issuances, project planning, and
maintenance of existing structures. On state
lands, IDL to coordinate with IDFG to identify
lek locations early in project planning phase.
BLM, FS, IDL,
IDFG, Shoshone-
Paiute Tribes
BLM issued IM ID-2009-006 which directs BLM
personnel to adopt sage-grouse conservation
measures in the State Plan, including the use of
timing restrictions for human disturbance around
leks.
The Curlew National Grassland Plan requires
timing stipulations of activities and restricts some
activities to reduce disturbance of leks.
Next Steps: Ongoing
IDL will implement
procedures to contact IDFG
prior to any installation.
2011 Chapter 6 updates and accomplishments ♦ 13
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
6.4.2.4. Develop a collision risk assessment
process to be used by land management
agencies, IDFG, NRCS, DOE, and landowners
(volunteer basis) when placing new fences or
other tall structures (e.g., wind towers,
communication towers, MET towers,
transmission lines) in sage-grouse habitat.
Utilize conservation measures in section 4.3.2.3
(page 4-42) and 4.3.4.3. (page 4-63) until
completed.
BLM, IDFG Target Deadline: After
completion of University of
Idaho tall structures study
(expected by May 2011).
6.4.2.5. Upon completion of University of Idaho
tall structures study, SAC (Chapter 6
Subcommittee) will reconvene to consider how
to use collision risk assessment and
recommended actions on planned and existing
structures.
SAC Stevens, B. S. 2011. Impacts of fences on greater
sage-grouse in Idaho: collision, mitigation, and
spatial ecology. MS thesis, University of Idaho,
Moscow.
Target Deadline:
December 2011.
6.4.2.6. Recommend that all new anemometer
(MET) towers be self-supporting, or, if guy
wires are needed, require that they have
permanent markers along their entire length to
increase visibility to birds and reduce collision
risk.
BLM BLM IM-2009-006.
Next Steps: Ongoing
6.4.2.7. Avoid the placement of new MET
towers within 2 miles of active sage-grouse leks
(Connelly et al. 2000) unless they are out of the
direct line of sight of the active lek.
BLM, FS, IDL,
IDFG
BLM IM-2009-006.
Addressed in Curlew National Grassland Plan 2002.
Next Steps: Ongoing
IDL will review the
location of MET towers on
IDL land with IDFG prior
to installation. IDL will
implement procedures to
contact IDFG prior to any
installation.
6.4.2.8. Identify specific roads or road sections
where sage-grouse mortality has been
documented. Work collaboratively with the
appropriate agency(s) to develop measures to
reduce the risk of road-related mortality of sage-
LWGs Upper Snake: The A2 road from Dubois to Kilgore
was identified as a road segment with potential to
create hazards to lekking sage-grouse. Road was
monitored during spring 2010 and high use areas
were mapped. Measures were developed to
Target Deadline: April
2010
Next Steps: Explore
possibility for and
implications of “sage-
2011 Chapter 6 updates and accomplishments ♦ 14
Task Responsible Party 2009-2011 Accomplishments
Next Steps or Target
Deadline
grouse. Consider speed limits, brush control,
signing, and public education.
encourage birds to stay off the roadway. These
measures will be implemented in 2011.
“Sage-grouse Crossing” signs were installed at lek
sites on the Red Road.
In 2010, the Great Basin Restoration Initiative
Workgroup prepared the document titled
“Considerations for Strategically Reducing Fuels
and Wildfires on Public Lands in the Great Basin
with Targeted Grazing.” The document is available
to interested parties via BLM State Offices.
grouse crossing” signs.
6.4.2.9. Coordinate with the Idaho Office of
Energy Resources to regularly obtain updated
geospatial information on new and proposed
energy projects (e.g., wind energy and MET
towers; electrical transmission; geothermal
development; and oil and gas pipelines) and
associated infrastructure (e.g., distribution lines
and roads). Consider posting data on
www.insideidaho.org
SAC TAT Not able to accomplish. Target Deadline: Set up
process by July 1, 2010.
6.4.2.10. SAC to stay informed and consider
commenting on infrastructure projects in
coordination with LWGs.
SAC, in
coordination with
LWGs
SAC submitted comment letter on Mountain States
Transmission Intertie (MSTI) in 2008.
Next Steps: Ongoing
6.4.2.11. Work with utilities (energy and
communications) to site new infrastructure
projects away from occupied leks and identified
important seasonal habitats, in accordance with
section 4.3.2.3 (pages 4-42 to 4-46).
LWGs, BLM, FS,
IDFG, and IDL, in
coordination with
utilities.
Challis: LWG influenced transmission line siting;
developer chose to avoid key habitat.
EIU: Letters sent regarding UAMPS Horse Butte
project. The company provided lek data to IDFG
based on their monitoring. LWG will continue
providing comments on the Gateway West project
as opportunities arise.
Jarbidge: LWG member comments on the China
Mountain Sage-grouse Conservation Plan.
North Magic: Continued to be involved with the
Friedman Airport Relocation, SWIP and MSTI
updates, and any pending wind farm applications in