Top Banner
ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery 9 July 2015
20

ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Aug 17, 2018

Download

Documents

trinhdung
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

ICN Gateway Breakfast (SA)

Jon WhelanA/Manager Project Delivery

9 July 2015

Page 2: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery
Page 3: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Adelaide’s North‐South Corridor

78 km running between Old Noarlunga and Gawler

Page 4: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Adelaide’s North‐South Corridor

Torrens Road to River Torrens[due for completion 2018]

Page 5: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

The award of the major works contract for the $896 millionproject was announced on 29 April 2015

The successful tenderer was T2T Alliance, a consortiumconsisting of:

Leighton Contractors Pty LtdAurecon Australasia Pty Ltd andYork Civil Pty Ltd

Page 6: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Completion of works by end of 2018

Commence with T2T Alliance

Major Construction Works to begin on

site end of July 2015

Project Timeline

Page 7: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

3.7 km upgrade of South Road from just north of Torrens Road to just south of the River Torrens

River Torrens

Page 8: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

3 km of non-stop section of roadway (incorporating 2 km of lowered

motorway), approx 8 m below the existing surface under Port and

Grange Roads, and Hawker Street

Improved cycling & pedestrian facilities

Landscaping & noise barriers(where required)

Page 9: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

An overpass of the Outer Harbor rail line

Page 10: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Parallel surface (at-grade) roads along the length of the lowered

motorway to connect most local roads and arterial roads to South Road

Page 11: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

• An Alliance is a collaborative delivery method in whichthe Owner joins with one or more non-owner parties toshare all the risks and responsibilities in delivering aProject

• It is a proven infrastructure procurement method that isbeing used by governments across Australia to deliverinfrastructure to the community

Competitive Alliance – what is it?

Page 12: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Choosing a Competitive Alliance Procurement Model

• Delivering projects with unclear scope of works• Delivering projects with significant risk certainty • Managing stakeholder issues• Value-for-money

Page 13: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Alliance Contracting Key Benefits

• The parties are incentivised to work cooperatively tocomplete the project within time and budget forecasts

• To find the best solutions for the project (rather than fortheir own interests)

• To work quickly and collaboratively to resolve issues asthey arise

• Promote a positive culture to achieve outstanding resultsfor the Project

Page 14: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Projects of this scale and nature create a range ofopportunities for businesses along the supply chain inproviding goods and services to the major workscontractor. These typically include:

• Materials such as concrete, quarry products etc• Machinery hire• Landscaping• Fencing• Traffic control • Accommodation, food and drink• Fuel• Safety equipment, security etc

Page 15: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

A South Australian Industry Participation Plan is an important contractual requirement to:

• Promote economic contribution to the State including employment outcomes and economic growth

• Ensure equitable access for local industry • Monitor and record the outcomes of local industry

involvement

Page 16: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

The Industry Participation Plan will outline:

• How many jobs will be performed in SA• Goods and services sourced from local businesses• How tendering processes will provide full, fair and

reasonable opportunities for local businesses

The Office of the Industry Advocate will assist inensuring the contractual obligation is met.

Page 17: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

T2T Alliance South Australian Industry Participation PolicyThe Office of the Industry Advocate has been involvedthroughout the procurement phases of this project,T2T Alliancehas committed to:

• Use over 90% local labour with a value over $70 million• Over $1 million in new capital purchases to be permanently

located in the State and it will utilise a substantial list ofcapital equipment

• Over 90% of sub-contracts where most of the product orservice will be carried out in the State with a target spend of$290 million

Page 18: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

Workforce Participation

In accordance with the State Government’s ‘WorkforceParticipation in Government Construction Procurementpolicy’ and the State’s ‘Our Jobs Plan’, T2T Alliance will berequired to ensure that at least 20% of labour hours areundertaken by:– Apprentices & trainees– Aboriginal people– Local people with barriers to employment– Displaced automotive industry workers– Up-skilling existing staff

Page 19: ICN Gateway Breakfast (SA) Jon Whelan A/Manager …icn.org.au/sites/default/files/Jon Whelan_DPTI (A650802).pdf · ICN Gateway Breakfast (SA) Jon Whelan A/Manager Project Delivery

The South Australian Industry Participation Policy

The Policy is in place to ensure that capable SouthAustralian small and medium businesses are given full,fair and reasonable opportunity to tender and participatein significant public and private sector projects.