Canadian Nuclear Utility Principles for Beyond Design Basis Accidents IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects Ontario Power Generation
31

IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Jun 23, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Canadian Nuclear Utility Principles for Beyond Design Basis Accidents

IAEA-J4-TM-46463 TM for Evaluation of Design Safety

Mark R Knutson P Eng.

Director of Fukushima Projects

Ontario Power Generation

Page 2: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Overview of Presentation

• Canadian Nuclear Utility Principles for Beyond Design Basis Events

• 1 Objective

• 9 Principles

• Supporting actions planned or taken by the utilities

• Our Commitment

• Summary

2

Page 3: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Canadian Nuclear Utility Principles for Beyond Design Basis Events

• Developed and agreed to by the 3 Utilities

• Provide guidance for utility decision making to maintain consistency

• Intended to position Canadian utilities at the forefront of the Post Fukushima Response

3

Page 4: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...
Page 5: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Objective of the Principles

Practically eliminate the potential for societal disruption due to a nuclear incident by maintaining multiple and flexible barriers to severe event progression

5

Page 6: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 1 – Event Progression Defences

Actions and defences will focus on stopping accident progression prior to a severe accident.

• Maintaining adequate fuel cooling prevents fuel failures.

• Severity of consequences escalates with event progression.

• Prevention should receive the majority of the actions and focus from the utilities.

6

Page 7: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 1 - OPG Event Progression Defences Actions

• Robustness of OPG stations confirmed for beyond design basis (BDB) seismic events

• BDB wind analysis completed for Pickering 5-8 and Darlington – Resulted in revisions to P5-8 Emergency Operating Procedures

• BDB wind analysis in-progress for Pickering 1-4 – TCD Dec 31, 2013

7

• BDB flooding analysis completed for Pickering and Darlington – Installed flood barriers around

essential systems at both sites

Page 8: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 2 – Multiple Barriers Multiple barriers to event progression and multiple means to supply water or electricity will be used to ensure adequate defence

8

Page 9: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 2 - OPG Multiple Barriers Actions

9

• Procured diesel driven pumps and generators

• Sufficient number (N+1) of pumps and generators to supply all units at a site simultaneously

• Multiple different connection points

• Design in progress to simplify connections

Page 10: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

CANDU

10

Page 11: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 3 – Early Fuel Cooling

Methods and actions to initiate heat transport system (HTS) cool-down and maintain fuel cooling will be a primary and early priority

• Rapid cooldown is achieved by opening Steam Release Valves (SRVs) – Increases margin to fuel failures (lower temperature).

– Allows for EME to inject additional water into a depressurized steam generators.

• Actions to open SRVs need to be simple and reliable.

11

Page 12: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 3 - OPG Early Fuel Cooling Actions

• Procedures

– Load shedding strategies

• Training

– Initiation of early cool-down of the HTS

12

• Design

– Seismic capacity of Class II battery banks

– Portable Uninterruptable Power Supplies (PUPS)

Page 13: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 4 – Containment Integrity

Actions to maintain Containment integrity will be utilized to minimize radioactive releases

• Control pressure – Containment Cooling

– Containment Venting (Principle 5)

• Control hydrogen – Minimize generation

– Effective removal

• Control water inventory to minimize flooding – Water injection and recovery

13

Page 14: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 4 - OPG Containment Integrity Actions Design

Larger generators as part of Phase 2 EME to repower most Emergency Power System loads, including, – Vault and boiler room air cooling units (condense steam)

– Post Accident Containment Filtered Venting System

– Emergency Water Systems to cool safety-critical loads

– Reactor water recovery and recirculation

14

Page 15: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 4 - OPG Containment Integrity Actions

Design (continued) – Water make-up to moderator and shield

tank to arrest accident • Provide fuel cooling

• Minimize generation of hydrogen

– Shield tank integrity assessed for severe accidents • Additional shield tank overpressure relief

committed for Darlington

• Current overpressure relief confirmed adequate for Pickering

– Additional filtered venting system (beyond phase 2 EME) • Committed as part of Darlington refurbishment

• Under evaluation for Pickering

– Passive Autocatalytic Recombiners for hydrogen removal – 6 of 10 Units complete

15

Page 16: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 4 - OPG Containment Integrity Actions

• Procedures

• Severe Accident Management Guidelines developed

• Improved through multiple iterations

16

• Training

• Classroom

• Practice deploying actual EME equipment

• SAMG Drills with EME deployment

• 2 one-day drills for each of PA and PB in 2013

• 1 two-day drill planned for Darlington (August 2013)

Page 17: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 5 – Filtered Venting

Containment venting will be controlled through a filtered system

• With a functional containment, decisions can be made when to vent and for how long.

• Controlled filtered venting will minimize radioactive releases and their potential impact on the environment.

• The ability to delay when containment will be vented allows for short lived material to be reduced through decay.

17

Page 18: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 5 – OPG Filtered Venting Actions

• Both Pickering and Darlington have Post Accident Containment Filtered Venting Systems

– Repowered as part of Phase II EME

– Additional filtered venting capacity to be installed as part of Darlington Refurbishment. • Pickering is under review, decision by end of 2013.

• Post accident procedures are available and trained

• Installed remote radiation monitoring system

18

Page 19: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 5 – OPG Filtered Venting Actions

19

• Installed near boundary automated gamma monitoring at Pickering and Darlington • Provide early indication of impact of venting

Page 20: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 6 – Equipment Integrity

Necessary systems, structures and components will be confirmed to survive rare yet credible conditions for external hazards

• Review Level Conditions (RLCs) established for rare yet credible conditions.

e.g., seismic Design Basis ~1,000 yr; RLC ~10,000 yr

• Provides assurance that the EME will meet its objectives for Beyond Design Basis Events

20

Page 21: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 6 – OPG Equipment Integrity Actions

• Seismic Margin Assessment completed:

– Passive water supply to Steam Generators (Dearator)

– Class II batteries and rack

• EME Quick connects designed to meet system requirement

• Analyzed impact of seismically induced fires and floods at Pickering and Darlington.

– No significant incremental impact on station risk.

• Instrumentation and Equipment Survivability Assessment is in progress for Pickering and Darlington

• Diversity and independence of EME connection points included in plan to address extreme external hazards.

21

Page 22: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 7 – Spent Fuel Cooling

Irradiated Fuel Bay (IFB) water levels will be maintained sufficiently above the top of the fuel to mitigate high radiation fields, hydrogen production, and fuel damage

• The time required to respond to a loss of IFB cooling is typically quite long.

• The volume of water in the IFB should be maximized within normal water levels to the extent practicable.

• EME to supply water to account for leakage and steaming.

22

Page 23: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 7 – OPG Actions

23

• IFB time to boil > 72 hrs

• EME deployment time < 4 hours • Procedures developed for

EME deployment

• Seismic / Thermal Analysis confirmed leakage plus evaporation << EME water make-up capacity

• Design in progress for portable measurement of level and temperature

Page 24: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 8 – Readily Deployed

Emergency Mitigating Equipment will be robust, readily available, easily deployable within required timeframes, and have adequate redundancy • Stored at higher elevation, away from station, close enough for timely

deployment and accessible following BDBE

– Pre-staging is an option for predictable events (e.g., severe weather)

• Deployable by diverse work groups, supported by procedures, training and practice and validated by drills

• More than one method for deployment (trucks, tractors, security vehicles)

• Reliability of EME supported by using proven technology, preventative maintenance and routine testing

• On-site fuel supplies adequate for > 72 hour run time, with provisions for refueling in place.

24

Page 25: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 8 – OPG “Readily Deployed” Actions

25

Page 26: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 8 – OPG “Readily Deployed” Actions

26

Page 27: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 8 – OPG “Readily Deployed” Actions

27

Page 28: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 9 - Common Philosophy

Canadian utilities will utilize a common philosophy for the prevention of a Beyond Design Basis Accident (BDBA)

• Interaction between utilities gives a larger perspective and experience base

– Encourages challenging and learning

– Improves capability to respond and to provide mutual assistance

– Provides credibility

– Facilitates regulatory concurrence.

28

Page 29: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 9 - Common Philosophy Actions

COG - Candu Industry Integration Team Bi-weekly domestic meetings

Monthly CNO meetings

Quarterly international meetings

COG Severe Accident Joint Project Technical Reports Shutdown and Low Power

Multi-unit Station

Technical Basis Document and SAMG Update

Containment Integrity

In-Vessel Retention

Instrument Survivability

Habitability

29

Page 30: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Principle 9 – OPG Common Philosophy Actions

COG Emergency Preparedness Work Shop III June 3&4,

Diverse participation including CNSC, Health Canada and provincial agencies.

WANO SOER 13-2 corrective action plans

Developed cooperatively

WANO Peer Review at Pickering June 10-21

“Strength” awarded for Fukushima response.

Mutual Aid Agreement in effect

Regional Emergency Response Support Centre

Conceptual design report under review

30

Page 31: IAEA-J4-TM-46463 TM for Evaluation of Design Safety · 2013-08-29 · IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects ...

Our Commitment

We are committed to these principles in order to protect against Beyond

Design Basis Events such as the one that occurred at Fukushima

31