Top Banner
Mortlock Terrace Catchment Study Flood Mitigation Options Report City of Port Lincoln July 2017 Ref No. 20160179R001B I20175905 14.19.2.121
45

I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Mar 31, 2018

Download

Documents

ĐỗĐẳng
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Mortlock Terrace Catchment Study

Flood Mitigation Options Report

City of Port Lincoln

July 2017

Ref No. 20160179R001B

I20175905 14.19.2.121

Page 2: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report

© Tonkin Consulting 2016 This document is, and shall remain, the property of Tonkin Consulting. The document may only be used for the purposes for which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this document in any form whatsoever is prohibited.

Document History and Status Rev Description Author Reviewed Approved Date

A For Client Comment JDN TAK TAK 30 Jun 2017

B Revised draft JDN JT TAK 4 July 2017

Page 3: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report

Contents 1 Introduction 1

1.1 Background 1

1.2 Study Intent and Scope 1

2 Existing infrastructure 4

2.1 Existing systems and flood behaviour 4 2.1.1 Liverpool Street catchment 4 2.1.2 Mortlock Terrace catchment 5 2.1.3 Stevenson Street and Brougham Place 9

2.2 Liverpool Street Pump Station 10 2.2.1 Pump station condition assessment 10 2.2.2 Implications of pump station condition assessment 14

3 Hydrodynamic model setup 15

3.1 Changes to hydrology 15

3.2 Hydraulic model refinements 15

4 Options Assessment 17

4.1 Mortlock Terrace Flow Split Reconfiguration 17 4.1.1 Description of Upgrade 17 4.1.2 Options Analysis and Assessment 17

4.2 Mortlock Terrace Gravity Outfall Upgrade 18 4.2.1 Description of Upgrade 18 4.2.2 Options Analysis and Assessment 18

4.3 Liverpool Street Gravity Outfall Option 18 4.3.1 Description of Upgrade 18 4.3.2 Options Analysis and Assessment 18

4.4 Eastern Levee Bank 19 4.4.1 Description of Upgrade 19 4.4.2 Options Analysis and Assessment 19

4.5 Liverpool Street Pump Station Rising Main Realignment 20 4.5.1 Description of Upgrade 20 4.5.2 Options Analysis and Assessment 20

4.6 Liverpool Street Pump Station Discharge Capacity Upgrade 20 4.6.1 Description of Upgrade 20 4.6.2 Options Analysis and Assessment 20

5 Concept design and site selection 23

5.1 Concept design 23

5.2 Site selection desktop assessment 23

5.3 General site conditions 26

5.4 Detailed site selection assessment 26 5.4.1 Site 1 26

Page 4: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 1

5.4.2 Site 2 26 5.4.3 Site 3 28 5.4.4 Site 4 28 5.4.5 Site 5 28

5.5 Selection of preferred site 30

6 Economic assessment 31

6.1 Potential flood damages 31

6.2 Actual flood damages 31

6.3 Annual average damage 32

6.4 Benefit–cost ratio 32

7 Conclusion 34

8 References 35

Tables Table 5.1 Indicative Cost Estimates 23 Table 5.2 Assessment against site selection criteria 30 Table 6.1 Indirect damage factors 31 Table 6.2 Annual average damage of upgrade options 32 Table 6.3 Cost–benefit ratios for pump upgrade options 33

Figures Figure 1.1 Liverpool Street Pump Station and surrounds 3 Figure 2.1 100 year ARI peak flowrates arriving at Liverpool Street pump station 4 Figure 2.2 Liverpool Street Height–Storage relationship 5 Figure 2.3 Liverpool Street catchment drainage system 6 Figure 2.4 Liverpool Street 5 year ARI flood map 7 Figure 2.5 Liverpool Street 100 year ARI flood map 8 Figure 2.6 Construction of the Mortlock Terrace splitter box 9 Figure 2.7 View looking west, note the layer of sand and debris on pump station base slab 11 Figure 2.8 View of pump unit discharge pipework 11 Figure 2.9 View of northern wall of pump station, with off form casting marks still evident 12 Figure 2.10 Pump Unit 2 (foreground) and 3 (background) 12 Figure 2.11 Pump Unit 3 and discharge pipe work 13 Figure 2.12 Pump Unit 2 support and guide rail corrosion 13 Figure 3.1 Long term development scenario directly connected impervious area proportion 16 Figure 4.1 Liverpool Street pump station upgrade options flood inundation map 22 Figure 5.1 Pump station concept design options 24 Figure 5.2 Possible pump station locations 25 Figure 5.3 Liverpool Street road reserve 27 Figure 5.4 Unsealed car parking area of untenanted commercial site 27 Figure 5.5 Carpark at Napoleon and Coorong Streets 28 Figure 5.6 Entrance to Council carpark at Eyre Street 29 Figure 5.7 Eyre Street verge area 29 Figure 6.1 Actual flood damages (long term scenario with and without new pump stations) 32

Page 5: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 2

Appendices Appendix A Cost Estimates

Page 6: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 1

1 Introduction 1.1 Background

The Liverpool Street catchment is approximately 27 ha in size and situated within the primarily commercial sector of the town centre (refer Figure 1.1). Ground levels within the catchment vary from approximately 1 mAHD to 10 mAHD with the slope of the land typically less than 1%. The majority of the catchment drains to an existing pump station situated at the low point within Liverpool Street. This pump station comprises three pumps with an approximate combined duty of 0.76 m3/s. Two of these pumps run on mains power. A generator is used when all three pumps are required to operate. The pump station discharges via a DN600 RCP rising main into the Mortlock Terrace gravity drain which then discharges into Boston Bay.

Previous investigative work, undertaken by Tonkin Consulting as part of the Port Lincoln Stormwater Management Plan (SMP) project, estimated that the existing pump station has less than a 2 year Average Recurrence Interval (ARI) standard (Tonkin Consulting, 2014). High intensity, short duration rainfall events during November 2015 and February 2016, resulted in flooding and damage to surrounding businesses that brought the operation of the pump station into the public eye. As such the City of Port Lincoln has undertaken to address the issue. Tonkin Consulting was engaged in mid-2016 to undertake highly detailed 2D flood modelling of the Port Lincoln township. In late-2016, Tonkin Consulting was engaged to undertake a flood mitigation options study for the Mortlock Terrace catchment, with particular focus on the Liverpool Street low spot.

1.2 Study Intent and Scope Given the interconnectivity of the Liverpool Street catchment with surrounding catchments, and the uncertainty as to the capacity and reliability of the existing pump station the City of Port Lincoln have engaged Tonkin Consulting to undertake an options study to determine the optimal solution to reduce flood risk in the vicinity of the Liverpool Street pump station. This study will aim to quantify the impact of surrounding catchments and assess the cost-benefit ratio of different upgrade options. Recommendations as to the optimal upgrade(s) to reduce the impact, and frequency of flooding within Liverpool Street will be provided.

This study will also develop a better understanding of the performance of the existing Liverpool Street Pump Station and identify options to improve the pump station performance.

Ultimately, this study will better inform the optimal solution(s) for detailed design.

As part of this study the following key tasks were undertaken:

Detailed 2D floodplain modelling including critical analysis of results to quantify the impact of upstream catchments on flooding within the Liverpool Street low spot based on a “long term” development scenario.

Review of the hydraulic and electrical capacity and condition of the existing pump station.

Undertook a high level options analysis to quantify the performance of different options to reduce the flooding risk within Liverpool Street. Options investigated included:

Modifications to the Mortlock Terrace splitter box and increasing the capacity of the Mallee Park basin while limiting any increase in downstream flood risk .

Increasing the capacity of the Mortlock Terrace gravity outfall drain.

Construction of a new gravity outfall from the Liverpool Street pump station to sea.

Diversion of flows from the upstream Brougham Place and Stevenson Street catchments by construction of a levee within the railway yard and/or upgrade to the Stevenson Street drain.

Page 7: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 2

Construction of a new rising main from the Liverpool Street pump station to the sea to relieve pressure on the existing gravity outfall within Mortlock Terrace.

Increasing the discharge capacity of the pump station, including options to utilise components of the existing pump station, full pump station replacement, and options to increase buffer storage.

Undertook a desktop Geotechnical investigation to determine the likely subsurface conditions – soil and groundwater.

Identification of a preferred option and undertaking of a cost benefit assessment of the preferred option including assessment of the trade-off between reduction in damages and construction cost of the preferred scheme to various ARI design standards.

Page 8: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

0 100 200 300 400 500 m

Job Number:Filename:Revision:Date:Drawn:

2016.0179

Rev. B2 Jul 2017JDN

Data Acknowledgement:Aerial imagery by AAM Pty Ltd, 2016, used with permission of City of Port Lincoln.Road and rail data by PBI, 2014.

City of Port Lincoln

MORTLOCK TERRACE CATCHMENT STUDYMortlock Terrace catchment and surrounds

Figure 1.1

Pump station

Control structure

Major catchment

Underground drainage system

Major road

Minor road

Local road

Railway

Legend

Page 9: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 4

2 Existing infrastructure 2.1 Existing systems and flood behaviour

2.1.1 Liverpool Street catchment

The Liverpool Street catchment drains to an existing pump station situated at the low point within Liverpool Street. This pump station comprises three pumps with an approximate combined duty of 0.76 m3/s. Two of these pumps run on mains power. When all three pumps are required to operate a generator is used. The pump station discharges into the Mortlock Terrace drain via a DN600 rising main which in turn discharges to Boston Bay.

The pump station is served by two main underground pipe systems: a DN750 RCP trunk main along Liverpool Street and a smaller DN600 RCP trunk system in Napoleon Street. Details of the underground system were determined by the Port Lincoln Flood Mapping Study using field survey and drawings from Council archives. Smaller lateral drains feed stormwater into the trunk system from the surrounding inlet pits. Five side entry pits above the storage chamber discharge directly into the storage chamber. A storage chamber adjacent the pump chamber provides approximately 115 m3 of balance storage during flood events. In comparison to the rainfall runoff volume (approximately 20,000 m3 in the 100 year ARI event) the balance storage is quite limited.

Recent mapping of the 5 year ARI flood event show ponding up to 400 mm deep at the Liverpool Street low spot; indicating that the pump station provides less than a 5 year ARI standard of protection (see Figure 2.3). Previous investigative work, undertaken by Tonkin Consulting as part of the Port Lincoln SMP project, estimated that the existing pump station has less than a 2 year ARI standard (Tonkin Consulting, 2014). Significant flooding occurs in the 100 year ARI flood event, with stormwater ponding up to 900 mm deep (refer Figure 2.5). Figure 2.1 shows the peak flows arriving at the pump station from key overland flow paths as well as the underground drainage system during the 100 year ARI flood event. It is clearly shown that the inflow to low spot exceed the capacity of the pump station.

Figure 2.1 100 year ARI peak flowrates arriving at Liverpool Street pump station

Page 10: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 5

A key feature of the Liverpool Street catchment is that the catchment drains to a trapped low spot; there are no overland flow paths that allow water to escape before significant flooding has occurred. Elevations within the trapped low spot range from 1.1 mAHD to 2.7 mAHD, a difference of 1.7 metres. Figure 2.2 demonstrates the limited storage available at low elevations within the low spot. No appreciable storage is available until 1.5 mAHD at which point storm water is up to 400 mm deep and beginning to inundate areas outside of the road corridor.

A wet system exists between Edinburgh Street and Napoleon Street and is a primary cause of flooding in Edinburgh Street. Figure 2.3 shows the layout of the drainage system in the Liverpool Street and Mortlock Terrace catchments.

Figure 2.2 Liverpool Street Height–Storage relationship

2.1.2 Mortlock Terrace catchment

Previous investigations have posited that the Liverpool Street catchment receives overland runoff from the 350 ha Mortlock Terrace North catchment. This behaviour was confirmed during the Port Lincoln Flood Mapping Study and occurs through two mechanisms. Firstly, runoff arriving at Park Terrace exceeds the inlet capacity of the Park Terrace drainage system. Consequently, excess stormwater flows across the oval of the Port Lincoln Primary School to the intersection of Mortlock Terrace and Lincoln Place. Secondly, the limited capacity of the Mortlock Terrace system causes water to surcharge from the inlet pits, located at the intersection of Mortlock Terrace and Lincoln Place, and flow into the Liverpool Street catchment (Tonkin Consulting, 2017). Due to the interconnection of the pump station and Mortlock Terrace drain, surcharge from the Lincoln Place inlet pits is increased during operation of the pump station. This in turn increases the volume of stormwater that flows towards Liverpool Street from the Mortlock Terrace catchment.

A flow split exists on the Mortlock Terrace drain near the intersection with Sinclair Street (refer Figure 1.1). Stormwater enters the splitter box from the south via twin DN1350 pipes. During small rainfall events, base flows will pass into a single DN900 pipe, which runs north along the length of Mortlock Terrace, discharging into Boston Bay. During rainfall events in which the flowrate exceeds the capacity of the DN900 pipe, stormwater is directed over an weir into twin DN1275 pipes (see Figure 2.6) that discharge into the Mallee Park detention basin.

Page 11: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Pump station rising main

Pump station

Inlet pitUnderground drainage system(with conduit size)Local road

Legend

Figure 2.3

MORTLOCK TERRACE CATCHMENT STUDY Liverpool Street drainage system layout

City of Port Lincoln

Data Acknowledgement:Aerial imagery by AAM Pty Ltd, 2016, used with permission of City of Port Lincoln.Road and rail data by PBI, 2014.

2016.0179

Rev. B2017-07-04JDN

Job Number:Filename:Revision:Date:Drawn:

0 40 80 120 160 200 m

Page 12: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify
Page 13: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify
Page 14: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 9

2.1.3 Stevenson Street and Brougham Place

These two systems collect stormwater flows from west facing catchments of Kirton Point (refer Figure 1.1). Both systems act to divert stormwater north and away from the Liverpool Street catchment low spot.

The Stevenson Street system is a DN1050 pipe system with close to a 5 year ARI standard. Due to the gradient of east-west roads, some stormwater bypasses inlets on Stevenson Street and flows into the Brougham Place catchment.

The Brougham Place is a DN450 pipe system with very limited capacity which runs north through the wharf facilities. In a 5 year ARI event ponding up to 0.45 m deep occurs in the rail corridor and approximately 0.08 m3/s flows from the railway corridor into the Liverpool Street catchment. In a 100 year ARI event, ponding up to 0.6 m deep occurs in the rail corridor and approximately 1.0 m3/s flows into the Liverpool Street catchment. The flows from the rail corridor into Liverpool Street is the most significant external contribution to the Liverpool Street catchment.

Figure 2.6 Construction of the Mortlock Terrace splitter box Photo is facing downstream. Note the DN900 primary outlet on the left and secondary DN1275 outlet pipes in the background beyond the weir crest. (Image source: City of Port Lincoln)

Page 15: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 10

2.2 Liverpool Street Pump Station The Liverpool Street pump station was commissioned in 1975. There are three pump units which pump from the balance storage chamber. The original design discharge of the pump station was 10,000 gpm (0.76 m3/s) at 25 ft (7.62 m) head. Council records indicate that a single Flygt Model CP3200 LT pump (with No. 605 impeller) and two Flygt Model CP3300 LT pumps (with No. 614 impeller) were installed. Each pump is incorporated into the flood model

2.2.1 Pump station condition assessment

An inspection of the existing pump station chamber was undertaken by Tonkin Consulting in November 2016. The purpose of the inspection was to determine the condition of the existing infrastructure and assess the feasibility of retrofitting the pump station chamber with new, larger capacity pumps.

At the time of inspection, the standing water level (SWL) was approximately 800 mm above the invert of the incoming drains, which is approximately 1.5 m above the floor of the pump sump. Review of the pump station SCADA records indicates that this SWL is typical and commensurate with the ground water table surrounding the pump station. The SWL also highlights that the stormwater network in the area has a high rate of ground water infiltration. Given the proximity to the coastline, the groundwater is thought to be highly saline; however, no testing of the water was undertaken to confirm this.

Inspection of the pump chamber was limited to a visual assessment of the internal concrete surfaces. Inspection of the floor required frequent draw down of the residual water in the chamber. The pump chamber floor was covered in a thick layer of sand and sediment that had accumulated over time which obstructed a full inspection of the floor (refer Figure 2.7). An inspection of the valve chamber was not undertaken due to access issues.

Given the aggressive nature of the environment—coastal proximity, saline water conditions and constant immersion—the concrete structure was considered to be in good condition. There was no obvious signs of deterioration or spalling of the concrete. There was little to no staining or other defects adjacent the pipe and conduit penetrations (refer Figure 2.8) that suggests the water tightness of the structure has been compromised.

The concrete surface finish is a hard, tight and predominately smooth surface, commensurate with an off-form cast in situ concrete pour. The off-form casting marks were still evident on the vertical wall faces (refer Figure 2.9). Joints in the concrete were visible suggesting that the construction of the box structure was undertaken with a number of concrete pours. Some minor honeycombing and pock marks were evident. However, these defects are considered minor and have not affected the structural integrity of the chamber. The concrete inlet has a smooth finish with no signs of erosion due to water flows from the incoming stormwater drains.

The condition of the pump sets varies. Pump Unit 3 had recently been refurbished prior to the inspection (see Figure 2.10 and Figure 2.11). During refurbishment the external coating had been reapplied. Pump Unit 1 and 2 showed signs of corrosion to the external surfaces and based on the external coating condition. Pump Unit 2 has also been serviced, although not as recently as Unit 3. The discharge pipework and vertical supports show a greater degree of corrosion (see Figure 2.12).

The valve chamber (located within the road carriageway), non-return valves (NRV), and discharge manifold were not inspected due to restricted access. Discussions with Council’s contractor revealed that the NRV for Pump Unit 1 was scheduled for replacement as it had been identified that the valve was leaking.

An inspection of the electrical switch room was undertaken in April 2016. This inspection noted that the electrical infrastructure was serviceable but quite dated.

Page 16: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 11

Figure 2.7 View looking west, note the layer of sand and debris on pump station base slab

Figure 2.8 View of pump unit discharge pipework

Page 17: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 12

Figure 2.9 View of northern wall of pump station, with off form casting marks still evident

Figure 2.10 Pump Unit 2 (foreground) and 3 (background)

Page 18: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 13

Figure 2.11 Pump Unit 3 and discharge pipe work

Figure 2.12 Pump Unit 2 support and guide rail corrosion

Page 19: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 14

2.2.2 Implications of pump station condition assessment

Based on the inspection carried out, the pump station chamber structure is in good condition and suitable for continued use. As such, reuse of the chamber structure could form part of a preferred mitigation option. It should be noted, however, that there are a number factors that would need to be considered if this approach was adopted. These include:

Any option to refurbish and reuse the existing pump chamber would require removal of the existing systems. Whilst the station is inactive the risk of a flood event would require effective mitigation which may involve the use of a temporary pump system to cater for any large rainfall events during construction.

The dimensions of the existing pump chamber would limit the size of any new pump set that could be installed. Based on the original drawings and the recorded dimensions, it is considered that the largest pump unit that could physically fit within the chamber has a capacity of 0.40 m3/s. Three of these pumps could be installed side-by-side leading to a maximum upgrade to the pump station capacity of 1.20 m3/s.

Any upgrade of the existing pump capacity would likely trigger a need to upgrade the electrical supply and controls of the pump station. This would include the need to replace electrical cables between the pump station and the switch room located on Napoleon Street. The upgrade may also require significant alterations to the main electrical supply, which could result in a significant cost for augmentation works. Additionally, the capacity of the existing generators would need to be assessed to ensure sufficient redundancy of supply to the pump station in the event of a mains supply outage.

If the pump station capacity is increased, it is likely that a new rising main would be required to prevent excessive flow velocities within the rising main. Preliminary estimates suggest a DN900 pipe would be required for a pump rate of 1.20 m3/s. The existing manifold and pipe penetrations would need modification to suit.

Retention of the existing balance storage is possible as it is in good condition. Expansion may be possible but difficult due to site conditions.

Page 20: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 15

3 Hydrodynamic model setup This study utilises the 1D–2D hydrodynamic flood model developed during the Port Lincoln Flood Mapping study (Tonkin Consulting, 2017).

3.1 Changes to hydrology A long-term development scenario was created to ensure that the proposed mitigation measures would be adequately sized to accommodate the additional runoff that increase development within the contributing catchments will produce.

The long-term development scenario involved estimating future development levels within the township and the corresponding imperviousness of the catchment. The estimation of future development levels was based on the long-term development scenario used by the Port Lincoln Stormwater Management Plan (refer Tonkin Consulting, 2014). The imperviousness of the catchment was adjusted where current development had exceeded that predicted by the SMP. Figure 3.1 illustrates the adopted imperviousness of the long-term development scenario.

Across all catchment in the township the average increase in catchment imperviousness was close to 20%. Liverpool Street catchment is already highly developed. Consequently, there is little change in the imperviousness of the Liverpool Street catchment between the existing and long-term development scenarios. The Stevenson Street, Brougham Place and Mortlock Terrace catchments have moderate increase in imperviousness in the range of 15-20%.

No changes in rainfall intensity due to climate change were considered, nor any change in sea level.

3.2 Hydraulic model refinements To improve the estimates of which buildings were subject to flooding in the vicinity of the Liverpool Street low spot, finished floor levels (FFLs) were surveyed for buildings shown to be at risk of inundation in the Port Lincoln Flood Mapping Study. The FFLs were integrated into the 2D flood model so that the depth of any above floor flooding could be better assessed.

Page 21: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

0 250 500 750 1000 m

Job Number:Filename:Revision:Date:Drawn:

2016.0179

Rev. B2017-07-05JDN

City of Port Lincoln

MORTLOCK TERRACE CATCHMENT STUDYLong-term catchment DCIA proportion

Figure 3.1

Pump station

Major Catchment Boundary

2D Flood Model Boundary

Major road

Minor road

Railway

Directly Connected Impervious Area (DCIA) Proportion

0.00 - 0.10

0.10 - 0.20

0.20 - 0.30

0.30 - 0.40

0.40 - 0.50

0.50 - 0.60

0.60 - 0.70

0.70 - 0.80

0.80 - 0.90

0.90 - 1.00

Legend

Page 22: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 17

4 Options Assessment This section of the report outlines each of the upgrade options investigated and summarises the performance of each option in mitigating flooding within the Liverpool Street low spot. For the most part each option has been assessed independently. Assessing the impacts of combined options was outside the scope of this study.

4.1 Mortlock Terrace Flow Split Reconfiguration

4.1.1 Description of Upgrade

The existing flow split directs low flowrates through a DN900 pipe into the Mortlock Terrace system. Higher flowrates are directed over a four metre wide weir into the Mallee Park Basin (part of the Mortlock Terrace South system).

It was thought that flow from the DN900 contributes to overloading of the Mortlock Terrace system, thereby exacerbating flooding in Liverpool Street (via the mechanisms detailed in Section 2.1).

The upgrade concept was to alter the splitter box configuration so that flow was first directed into the Mallee Park Detention basin rather than Mortlock Terrace. This could result in a number of benefits:

Reduced peak flow in the Mortlock Terrace system would potentially lead to less surcharging from that system into the Liverpool Street catchment. A reduction in flood volumes arriving at Liverpool Street would reduce the peak pumping rate required to mitigate flooding.

If the reduction in peak flow was substantial, it could lead to a situation whereby spare capacity was created in the Mortlock Terrace system. This capacity could then be used to offset any increase in pumping from Liverpool Street thus avoiding a net increase in peak flow in the lower section of the Mortlock Terrace drain. If no net increase in peak flow could be achieved, it may be possible to upgrade the pump station without also constructing a new rising main.

4.1.2 Options Analysis and Assessment

To assess this option, the DN900 outlet pipe was removed from the splitter box and the weir height lowered such that all flows were diverted into the Mallee Park detention basin. The modelling shows that the peak flow rate in the Mortlock Terrace system (near Liverpool Street) was reduced by 0.2 m3/s as a result of the reconfiguration. In turn, this reduced the flows that surcharge into Edinburgh Street by 0.060 m3/s. Ponding in Liverpool Street was reduced from 0.90 m deep to 0.87 m deep; a reduction of 30 mm. The modelling shows that despite an additional 0.6 m3/s being diverted into Mallee Park Basin, the spare capacity created in the Mortlock Terrace system becomes filled by other lateral systems connecting to Mortlock Terrace drain between the splitter box and Liverpool Street.

One added benefit of this option was that ponding at the Bligh–Liverpool Street intersection was reduced by 50 mm. Although the greatest depth of flooding was still up to 0.70 m deep at this location.

Due to the minimal reduction of flood depth in Liverpool Street and the risk of exacerbating flooding downstream of the Mallee Park Basin this option was not investigated further.

Page 23: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 18

4.2 Mortlock Terrace Gravity Outfall Upgrade

4.2.1 Description of Upgrade

This option focussed on increasing the capacity of the Mortlock Terrace system by upgrading a portion of the outfall to Boston Bay.

Upgrading the Mortlock Terrace outfall has the potential to prevent stormwater surcharging from the Mortlock Terrace drainage system into the Liverpool Street catchment and the potential to allow higher discharge rates from the Liverpool Street pump station without adversely affecting flooding in Mortlock Terrace.

Additionally, flooding at the intersection of Bligh Street and Liverpool Street could be reduced by this option by improving the hydraulic conditions for the minor lateral drains that feed into the Mortlock Terrace trunk system.

4.2.2 Options Analysis and Assessment

To assess this option the following changes were made to the Mortlock Terrace system:

1. The section of 2400×1200 RCBC between Liverpool Street and the system outlet was replaced with a 3600×1200 RCBC. A 3600 mm width was assumed to be the widest possible box section that would be practical to use due to service conflicts.

2. The section of DN1675 RCP between Lincoln Place and Liverpool Street was replaced with a DN2400 RCP. A DN2400 pipe was assumed to be the largest possible diameter that would not require lowering the invert of the current drain.

3. Seven additional SEPs were added to collect water at the intersection of Lincoln Place and Mortlock Terrace.

The alterations from this upgrade succeeded in eliminating surcharge flows from Mortlock Terrace into Liverpool Street; this eliminates up to 0.60 m3/s of stormwater flowing into Liverpool Street. The peak flow in the Mortlock Terrace outfall was increased by 1.0 m3/s. Ponding in Liverpool Street was reduced by 55 mm, however this is insufficient to reduce the number of properties affected by flooding. Ponding in the Bligh–Liverpool Street intersection was reduced by 120 mm.

Although upgrades to the Mortlock Terrace outfall reduce flooding at the Bligh–Liverpool Street intersection, the benefit such an upgrade provides to Liverpool Street is not considered significant enough to warrant the substantial construction costs of the outfall upgrade.

4.3 Liverpool Street Gravity Outfall Option

4.3.1 Description of Upgrade

This option considered construction of a new gravity outfall along Eyre Street from the low point in Liverpool Street to Boston Bay. The intent for this new outfall was to supplement the existing or a new pump station and provide additional discharge capacity. This option was analysed using 1D modelling techniques.

4.3.2 Options Analysis and Assessment

Analysis of this option showed that a new gravity outfall along Eyre Street would need to navigate several underground service crossings at Liverpool Street, Washington Street and Tasman Terrace, including optic fibre, high and low voltage electrical, telecommunication cables, water and sewer services.

Investigation showed that the top level of the sewer main, which runs east-west along Washington Street, would likely govern the maximum depth of the new gravity outfall. This level was estimated to be approximately -0.50 mAHD. The existing pump chamber invert is

Page 24: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 19

approximately -1.34 mAHD. Therefore, a gravity outfall option would not fully drain the existing pump chamber. Therefore, pumps would be required to remove water below a level of approximately -0.35 mAHD.

As this option is highly sensitive to the outlet water level, a sea level of 1.01 mAHD was adopted in the analysis of this option. This level is composed of the mean high water spring (MHWS) tide level plus an additional 300 mm allowance for sea level rise. In contrast, the lowest road surface level within Liverpool Street is 1.10 mAHD.

Preliminary estimates indicate stormwater in Liverpool Street would need to build up to a level of 1.31 mAHD (approximately 200 mm deep) in order to overcome friction and box losses along the outfall. In storm events that coincide with higher tide events (e.g. storm tides), stormwater would be required to reach an even greater depth of ponding due to the increase in outlet water level. Stormwater will breach the confines of the roadway at a level of approximately 1.40 mAHD. The lowest FFL surveyed in Liverpool Street is approximately 1.70 mAHD. Given the above, there is little margin for error in the system. If the predicted performance of the system were adversely affected by sea level rise or blockage then the system could fail to adequately protect properties.

To protect properties from flooding requires a net outflow from the Liverpool Street low spot of 2.8 m3/s. To achieve this with the adopted tide level would require construction of a twin DN1200 system.

A new gravity outfall would need to incorporate a check-valve to protect the outfall from blockage and prevent sea water flow into Liverpool Street. An adequate outlet structure and maintenance schedule would also be required to reduce the extent and frequency of sand deposition at the outlet.

As this option will only reach maximum potential once flooding reaches a depth of approximately 300 mm within the roadway, even during small rainfall events, and there is a high likelihood that system performance will be reduced due to blockage or rises in sea level, Tonkin Consulting do not recommend that Council pursue this option.

4.4 Eastern Levee Bank

4.4.1 Description of Upgrade

During analysis of the flood maps, it was noted that a substantial volume of water was entering the Liverpool Street catchment from the Brougham Place catchment (east of Liverpool Street); the peak inflow in the 100 year ARI event was 1.5 m3/s. It was expected that there would be a reduction in flooding in Liverpool Street, and particularly at the intersection of Liverpool Street and Porter Street, if this water could be prevented from draining into the Liverpool Street catchment. Additionally, if the reduction in flooding was substantial this option could lead to a reduced pump upgrade requirement. To investigate this option, a levee was inserted into the flood model to direct water from the Brougham Place catchment towards King Street and the wharf area.

An alternate approach suggested, but not investigated as it was outside the scope of the study, was the interception of flows from Brougham Place and Stevenson Street catchments prior to arrival at the rail yard. This would require upgrades to upstream pipe systems, or installation of entirely new pipe systems, to minimise surface runoff flowing through the railyard and then into Railway Place.

4.4.2 Options Analysis and Assessment

An artificial levee was placed on the western side of the rail yard to direct water west beneath London Street bridge and towards King Street.

The model showed a substantial decrease in flooding (160 mm) in Liverpool Street as a result of the levee. However, this is not sufficient to prevent above floor flooding in the 100 year ARI event. Conversely, flooding in the railyard is increased by 170 mm. Construction of a levee would

Page 25: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 20

require works in private property and would require careful consideration to ensure operation of the railway yard and railway museum were not adversely affected.

Given the substantial decrease in flooding in Liverpool Street this option was also considered in combination with an upgraded pump station (refer Section 4.6 below). In discussion with Council, Tonkin Consulting were advised that the eastern levee option in any form would be unacceptable that due to the increase in flooding within the rail corridor.

4.5 Liverpool Street Pump Station Rising Main Realignment

4.5.1 Description of Upgrade

This option involved directing discharge from the Liverpool Street pump station into Boston Bay via a new rising main rather than the Mortlock Terrace drain. It was thought that this would potentially eliminate surcharge flows from the Mortlock Terrace drain into the Liverpool Street catchment. This option could also potentially reduce flooding in Mortlock Terrace at the Bligh–Liverpool Street intersection.

4.5.2 Options Analysis and Assessment

The flood model was reconfigured to direct flows from an unaltered pump station into Boston Bay via a new rising main. As a result, in the 100 year ARI event, the peak flowrate in the Mortlock Terrace drain (downstream of the current junction with the rising main) is reduced by 0.5 m3/s.

By reducing the peak flowrate in the Mortlock Terrace drain, flooding at the Bligh–Liverpool Street intersection is reduced by 40 mm. Discharge into Edinburgh Street is reduced by 0.06 m3/s but not completely eliminated. However, flooding in Liverpool Street is virtually unchanged because the peak discharge rate of the Liverpool Street pump station is unaltered.

Therefore, whilst this option manages to reduce flooding at the Bligh–Liverpool Street intersection, it has minimal impact on flooding in Liverpool Street. In order for this option to reduce flooding in Liverpool Street, it will need to be combined with an increase in the capacity of the pump station.

4.6 Liverpool Street Pump Station Discharge Capacity Upgrade

4.6.1 Description of Upgrade

This option investigated the management of flooding in Liverpool Street via increased pump discharge rates. In addition to increased pump rates this option involved construction of a new rising main along Eyre Street to eliminate the effects of the pump station on flooding of the Bligh–Liverpool Street intersection.

Field inspection of the existing pump station revealed that it would be possible to install three new pumps with a combined design discharge of 1.2 m3/s within the existing pump chamber. Larger design discharges would require pumps that would require enlarging the chamber. Various new pump rates were simulated, ranging from 1.2 m3/s through to 3.2 m3/s.

This option was also considered in combination with the Eastern Levee bank option to assess sensitivity of the design discharge requirements.

4.6.2 Options Analysis and Assessment

To achieve no above floor flooding of existing buildings the following pump rates are required:

1.2 m3/s in the 20 year ARI flood event

2.8 m3/s in the 100 year ARI flood event

In the 100 year ARI event with a 2.8 m3/s pump rate, flooding in Liverpool Street is significantly reduced; from 900 mm deep down to 350 mm deep. Ponding of water along Liverpool Street and

Page 26: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 21

Eyre Street is not entirely eliminated, however, the majority of above floor flooding is averted. Flooding is very similar when a 1.2 m3/s pump rate is used in the 20 year ARI event. Figure 4.1 shows the effect of each upgrade option.

It is important to note that the intersection of Porter Street and Liverpool Street is inundated to the same extent regardless of the simulated pump rate upgrade. This occurs because the eastern side of this intersection is isolated from the Liverpool Street pump station by the crown of Porter Street. The only paths for stormwater to move from this intersection to the pump station are through the underground system or over the crown of Porter Street. The underground system beneath Porter Street is not capable of conveying the 100 year ARI flowrate. As a result, regardless of the pump station upgrade the intersection will pond to the height of the Porter Street crown (approximately 2.3 mAHD).

If combined with the eastern levee option the following pump rates are required:

1.2 m3/s in the 20 year ARI flood event

2.0 m3/s in the 100 year ARI flood event

As 1.2 m3/s was the smallest discharge rate simulated in the 2D model, the same flow rate is required for both the levee and non-levee arrangements. With further analysis a smaller pump rate may be found to be sufficient in combination with the eastern levee, however, this was outside of the scope of this study.

When combined with the eastern levee option, flood depth in the Porter Street–Liverpool Street intersection is reduced by approximately 60 mm and flow over the Porter Street crown is reduced from 1.4 m3/s to 0.10 m3/s. By eliminating flows over Porter Street into Liverpool Street the net flow of stormwater into the pump station is significantly reduced. In turn, a lower pump station discharge of 2.0 m3/s is possible whilst still achieving a 100 year ARI level of protection.

Balance storage increase

After simulation of the various pump upgrades the option to increase the balance storage of the pump station was considered. Added balance storage can be used to reduce the required peak pump rate and thus lower costs associated with the pump station construction. The minimum additional balance storage required to reduce the pump rate from 2.8 m3/s to 2.4 m3/s is approximately 1,500 m3. Accommodating this amount of additional storage will prove difficult. Assuming that ground water would limit the depth of any storage basin to 1 metre, then a 1,500 m2 footprint would be required. Examining the surrounds of the pump station reveals that a footprint of this magnitude would likely require locating a basin within private property. An underground system contained within the road corridor would require 1,300 metres (or 3×450 metres) of DN1200 RCP to be installed under the roadway which would be impractical due to conflicts with other services.

The additional cost of providing an increase balance storage is considered to be in excess of the reduced pump station construction costs and as such was not considered further.

Page 27: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Data Acknowledgement:Aerial imagery by AAM Pty Ltd, 2016, used with permission of City of Port Lincoln.Roads data by DPTI, 2016.

20160179

Rev. B2017-07-04JDN

Job Number:Filename:Revision:Date:Drawn:

0 50 100 150 200 m

Figure 4.1

MORTLOCK TERRACE CATCHMENT STUDYPump station upgrade options

Flood inundation map

City of Port Lincoln

Long term 100 year ARIno upgrade

Long term 20 year ARIno upgrade

Long term 100 year ARI2,800 L/s pump upgrade

Long term 20 year ARI1,200 L/s pump upgrade

Page 28: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 23

5 Concept design and site selection 5.1 Concept design

Based on the findings of Section 4, three main options have been identified for further consideration:

Option 1: An entirely new pump station providing a 100 year ARI level of protection. This pump station would have a peak discharge rate of 2.8 m3/s. This option considers the construction of a new underground pump station, switch room and generator building. Modification of the gravity stormwater system is also included.

Option 2: As for Option 1, but also includes construction of an eastern levee combined with smaller pumps to achieve a peak discharge rate of 2.0 m3/s.

Option 3: Refurbishment of the existing pump station to provide a 20 year ARI level of protection. This option allows reuse of existing infrastructure, including the original pump chamber, balance storage, and the existing switch room and generator at Napoleon Street. The maximum possible discharge rate from this option has been determined to be 1.2 m3/s. This solution would provide partial protection in a 100 year ARI flood.

Tonkin Consulting has developed concept designs for the three different pump station options. Each option includes construction of a new rising main along Eyre Street to an ocean outfall located adjacent the Port Lincoln Yacht Club. A sketch of the various concepts is presented in Figure 5.1.

Cost estimates for each concept have been developed to give a high level, order of magnitude measure of costs for budget purposes.

Table 5.1 Indicative Cost Estimates

Pump Station Options Indicative Cost (ex GST)

Option 1 – 100 year protection, Q= 2.8 m3/s $ 5.5 M

Option 2 – 100 year protection, Eastern levee & Q= 2.0 m3/s

$ 4.9 M

Option 3 – 20 year protection, Q= 1.2 m3/s $ 3.2 M

A detailed breakdown of costs is provided in Appendix A. The cost estimates are also used to inform the cost–benefit ratio of each option (refer Section 6).

It has been assumed that the existing pump station will be decommissioned if a new pump station is constructed. This ignores the possibility of retaining the existing pump station to augment or complement the capacity of a new pump station. There are some challenges associated with achieving this in a practical manner as two pump stations operating simultaneously adds complexity to the control systems. During detailed design there may be potential to investigate a twin pump station solution.

5.2 Site selection desktop assessment A desktop assessment was performed to identify suitable locations for the construction of a new pump station. The following selection criteria were adopted to assess possible construction sites:

Proximity to the existing gravity network: this ensures that a stormwater gravity connection can be readily made to the new pump station;

Availability of land: the footprint of a new pump station is estimated to require a 9×8 m underground pump chamber, a 9×3 m above ground switch room and a 5×2 m above ground diesel generator housing.

Page 29: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

0 10 20 30 40 50 m

Job Number:Filename:Revision:Date:Drawn:

2016017920160179GQ004REV D2017-07-04JDN

Data Acknowledgement:Roads data from PBI, 2015.Aerial imagery from CPL, 2016.

City of Port Lincoln

MORTLOCK TERRACE CATCHMENT STUDYConcept design options

Figure 5.1

PIPE OUTLETMin 100m

Page 30: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 25

Constructability: consideration on the construction techniques that will be employed and difficulties associated with access, existing services, traffic management and public safety.

Flood risk during construction: management of the existing flood risk during construction, particularly if the existing pump station is taken offline at any point during the construction period. Ensuring that there is some level of protection against a flood events during the construction activities will be critical to success of any option.

Five possible locations were identified by the desktop assessment and are shown in Figure 5.2 below. A site inspection of each of the identified sites was undertaken to determine any additional constraints or issues that may impact construction or operation of the pump station.

Figure 5.2 Possible pump station locations

Page 31: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 26

5.3 General site conditions The general site conditions for each location are similar. The area is low lying, with elevations in the range of 1.0-3.0 mAHD. The sites are all developed in some form, with the majority covered with a hot-mix wearing course seal of some description.

The groundwater levels in the area have not been measured, but anecdotal evidence has indicated that the groundwater table is tidally influenced. Groundwater has been assumed to be approximately 1.0 m below ground level in these locations.

The soil conditions in this area are expected to be predominately sand and grit given the proximity to the coastline. Based on historical knowledge of the area and regional geology profiles these sands are expected to be poorly graded and result in collapse when disturbed.

5.4 Detailed site selection assessment A description of each of site and the advantages and disadvantages of each is provided below.

5.4.1 Site 1

Site 1 is located within the northern carriageway of Liverpool Street opposite the existing pump station. Figure 5.3 shows the existing layout of the site. This location would mimic the configuration of the existing pump station. It is proposed that a new kerb protuberance would be created, with the pump station chamber located beneath the ground surface. The road corridor of Liverpool Street is owned by the Department for Planning, Transport and Infrastructure (DPTI). Use of this site would require negotiation with DPTI for access. It is proposed that this site would be serviced by the current switch room located in Napoleon Street.

5.4.2 Site 2

Site 2 is located within currently unoccupied private property. The rear of the site consists of an unsealed car parking area (see Figure 5.4). An easement or land acquisition could be negotiated for this site to enable the construction of a new pump station and an extension of the existing Liverpool Street stormwater system to provide connection to the pump station.

Page 32: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 27

Figure 5.3 Liverpool Street road reserve

Figure 5.4 Unsealed car parking area of untenanted commercial site

Page 33: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 28

Figure 5.5 Carpark at Napoleon and Coorong Streets

5.4.3 Site 3

Site 3 is situated within the privately owned carpark located on the corner of Napoleon Street and Coorong Street (refer Figure 5.5). The carpark services commercial businesses facing towards Liverpool Street. An easement or land acquisition could be negotiated for this site to enable the construction of a new pump station and an extension of the existing Liverpool Street stormwater system to provide connection to the pump station. This site is located relatively close to the existing switch room and generator that services the existing pump station.

5.4.4 Site 4

Site 4 is located within the Council owned carpark area bounded by King Street, Eyre Street and London Street. This area forms part of Council’s road reserve. The elevation of the site is significantly higher than the other sites (approximately 3.0 mAHD). This would help protect the switch room and generator from inundation during a flood but will make connecting the pump chamber with the existing stormwater system more complex. The proximity of the site to the coast significantly reduces the length of rising main required, although the extension of the gravity stormwater system from Liverpool Street is increased proportionately. This site would be serviced by a new switch room and generator area. In addition, there is a SA Power Networks transformer that may be used for a new grid supply (see Figure 5.6Figure 5.5).

5.4.5 Site 5

Site 5 is located within the western verge of Eyre Street (see Figure 5.7), directly adjacent the unoccupied commercial premises on the corner of Eyre Street and Liverpool Street. This location would mimic the configuration of the existing pump station and it is proposed that a new kerb protuberance would be created to accommodate the pump station and associated infrastructure. The Eyre Street road reserve is owned by Council, unlike Site 1 located in Liverpool Street.

Page 34: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 29

Figure 5.6 Entrance to Council carpark at Eyre Street

Figure 5.7 Eyre Street verge area

Page 35: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 30

5.5 Selection of preferred site Each site was assessed against the site selection criteria to identify the benefits and challenges of each site. Table 5.2 summarises the assessment against the site selection criteria.

Based on the site selection assessment it is recommend that Site 5 (Eyre Street verge) be considered the most suitable site for a new pump station and associated infrastructure. Site 5 provides the best compromise between land availability, accessibility and constructabi lity issues.

We recommend that the assumptions and selection criteria used be confirmed during detailed design.

Table 5.2 Assessment against site selection criteria

Site Proximity to existing

pump station

Land availability Constructability Preference

1 High No. Proximity to shop frontage undesirable. Requires DPTI approval to construct in

Liverpool Street. High disruption of local traffic during

construction. Easily connected to existing pump station and

stormwater system. Requires upgrade of cables and refurbishment

of existing switch room to service the site.

2

2 Low Yes, however privately owned and requires land acquisition/easements. Installation compromises future development opportunities of the site.

Minimal traffic control and management of public required.

Considerable augmentation of existing stormwater system required to connect to new pump station. Requires deeper construction to suit.

5

3 Low Yes, however privately owned and requires land acquisition/easements. Minimal impact carpark use once installed.

Minimal traffic control and management of public required.

Considerable augmentation of gravity stormwater required to connect to new pump station, resulting in greater depths, Coorong Street congested with underground services, risks of large excavation and service locations is high.

Minimal cable runs to existing switch room required.

4

4 Low Yes, Council owned. Minimal impact to carpark use once installed.

Considerable augmentation of gravity stormwater required to connect to new pump station, resulting in greater depths.

3

5 High Yes, Council owned. Proximity to commercial shop frontage undesirable.

Traffic controls can be easily implemented to minimise disruption during construction

Easily connected to existing pump station and stormwater system

New switch room and generator can be installed within Council’s road reserve to service the pump station

1

Page 36: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 31

6 Economic assessment 6.1 Potential flood damages

A flood damages assessment was undertaken to determine the financial impacts of each pump station concept. The flood damages assessment uses the Rapid Appraisal Method (RAM) developed by the Victorian Department of Natural Resources and Environment (DNRE, 2000). Full details of the methodology as applied to Port Lincoln are given in the Port Lincoln Flood Mapping Study report (20150098R001).

The RAM relies on classifying land-use into categories that describe the relative damage potential of properties thereby simplifying the damages assessment process. Four flood damages categories were used in this study: residential, low, medium and high.

Two types of damages are determined during the analysis. Direct damages relate to physical or functional damages incurred from direct interaction with flood waters. Indirect damages consist of damages incurred indirectly from flooding, such as loss of revenue during clean-up or lost wages whilst businesses are closed for repair. Indirect damages are calculated as a proportion of direct damages. Table 6.1 lists the proportions used for each damage category. Damage to vehicles, damage to roads, and economic costs due to injury or loss of life have not been included as part of the flood damages assessment.

Table 6.1 Indirect damage factors

Potential damage category Indirect factor

Residential 15%

Low 15%

Medium 60%

High 60%

6.2 Actual flood damages The potential direct and indirect damages are distinct from realised damages due to mitigating factors such as how prepared the community is to respond to flooding. The more prepared a community is, the more damages they can offset with their preparations. Therefore, potential damages must be adjusted to actual damages based on mitigating factors the communities experiences responding to floods. Another mitigating factor is the warning time prior to flooding.

Given that the community has responded to multiple flood events in the last five years, they are considered to be experienced with flooding. Additionally, the Liverpool Street catchment has a response time typically less than two hours. As such the an adjustment factor of 0.8 for conversion of potential damages to actual damages has been adopted. This value is based on Table 3.5 of the Rapid Appraisal Method for Floodplain Management (DNRE, 2000).

Figure 6.1 shows the difference in actual damages within the Liverpool Street catchment incurred during flood events with and without new pump stations. Each flood is plotted using the Annual Exceedance Probability (AEP) of the event. All three concept designs achieve roughly the same reduction in damages in the 20 year ARI event (5% AEP). Differences in the concept designs are move obvious in the 100 year ARI event (1% AEP).

Page 37: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 32

Figure 6.1 Actual flood damages (long term scenario with and without new pump stations)

6.3 Annual average damage The annual average damage (AAD) is an estimate of the expected annual cost of flood damages averaged over a long period of time. AAD balances low but more frequent flood damages with high but less frequent flood damages and provides a convenient way to compare different floodplain management measures across all magnitudes of flooding. It is a probability-weighted mean of the actual flood damages and is equivalent to the area beneath the flood damage-probability curve. In calculating AAD it was assumed that there are no flood damages for events that have an ARI less than or equal to 5 years. Table 6.2 lists the AAD for three pump station upgrade options.

Table 6.2 Annual average damage of upgrade options

Option AAD Reduction in AAD from base case

No upgrade (base case) $320,000 N/A

Option 1 $249,600 $70,400

Option 2 $261,400 $58,600

Option 3 $283,900 $36,100

6.4 Benefit–cost ratio The benefit–cost ratio (BCR) of each option was calculated to assess the value for money of each option. Options with a BCR greater than 1.0 indicate good value for money.

The BCR of each upgrade option was calculated assuming a 50 year service life for the pump station. The cost of the pump stations was estimated using the construction costs only. The benefit of the pump station was estimated using the reduction in AAD over the 50 year service life expressed as a discounted present value. A 4.4% discount rate was used. Sensitivity of the BCR was tested using discount rates of 3.1% and 5.7% (i.e. ±30% from 4.4%).

Page 38: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 33

Table 6.3 Cost–benefit ratios for pump upgrade options

Option BCR (4.4%) BCR (3.1%) BCR (5.7%)

No upgrade (base case) - - -

Option 1 0.257 0.324 0.210

Option 2 0.240 0.303 0.196

Option 3 0.227 0.286 0.185

Based on the BCRs, none of the options could be considered good value for money based on the reduction in flood damages. With consideration of other social and environmental factors the BCR for each option may become more favourable. Consideration of other factors however was outside the scope of this study.

Page 39: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 34

7 Conclusion The Mortlock Terrace and Liverpool Street Catchment Study has confirmed the interconnectivity of the Mortlock Terrace, Stevenson Street, Brougham Place and Liverpool Street catchments and highlights the need to manage stormwater from these catchments in a holistic manner through strategic upgrade of the existing stormwater systems.

Modelling of the Liverpool Street catchment with an upgraded pump station has identified the likely flow rates required to reach a 100 year ARI flood protection standard. The costs associated with providing a 100 year ARI level of protection were found to be significant and as such alternate standards of protection were also investigated.

In all cases, economic assessment of the proposed options undertaken to date suggests the capital costs of construction far exceed the expected reduction in flood damages.

This may warrant further discussion on the alternative scenarios for flood protection and the community expectation on the cost to achieve an “acceptable” level of flooding protection for the area.

Tonkin Consulting is happy to discuss the findings of this report with Council to assist them in their deliberations.

Page 40: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report 35

8 References DNRE, 2000, Rapid Appraisal Method (RAM) for Floodplain Management, Melbourne, Australia.

Tonkin Consulting, 2014, Port Lincoln Stormwater Management Plan, Reference No. 20070307RA2I, Adelaide, Australia.

Tonkin Consulting, 2017, Port Lincoln Flood Mapping Study – Hydrologic and Hydraulic Modelling Report, Reference No. 20150098R001A, Adelaide, Australia.

Page 41: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

Ref No. 20160179R001B Mortlock Terrace Catchment Study Flood Mitigation Options Report

Appendix A Cost Estimates

Page 42: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

INDICATIVE CONSTRUCTION COST ESTIMATELiverpool Street Pump Station Upgrade - City of Port Lincoln

Project Element: Summary of OptionsJob No: 20160179Date: 29/06/2017

Estimated by: DGSReview by: JT

Note: Costs are inclusive of Port Lincoln locality allowance

Item No Description 1200L/s 2000L/s 2800L/s Comments

1 PRELIMINARIES, ESTABLISHMENT, ONGOING SITE AND PROJECT MANAGEMENT 300,000$ 410,000$ 410,000$ Additional works and longer duration for construction of 2000L/s and 2800L/s option2 HANDLING OF INFLOWS 140,000$ 50,000$ 50,000$ 1200L/s option assumes some existing PS capacity retained during construction, existing PS off line for 2000L/s and 2800L/s options

Cost shown is an allowance only and no consideration has been given to how flows are to be managed during construction at this stage3 DEMOLITION 10,000$ 40,000$ 40,000$ Greater demolition allowance for 2000L/s and 2800L/s options4 PUMP SUMP STRUCTURE

4.1 New Pump Sump Structure 20,000$ 540,000$ 600,000$ Assumes existing sump retained for 1200L/s with only minor safety improvements. No remedial works to existing sump4.2 New Valve Pit Structure -$ 120,000$ 130,000$ New valve pit required for 2000L/s and 2800L/s options5 PUMP SUPPLY AND INSTALLATION (3 x 400L/s Pumps, No Jockey Pump) 170,000$ 340,000$ 390,000$ Based on Xylem quote6 VALVE AND MANIFOLD SUPPLY AND INSTALLATION 180,000$ 260,000$ 300,000$ Based on costs for Wellington Street Port Adelaide project7 ELECTRICAL SUPPLY 340,000$ 510,000$ 640,000$ Assumes generator located at Napoleon Street with new cabling8 NEW RISING MAIN AND GRAVITY DRAIN

8.1 New Rising Main and Break Pressure Junction Box 440,000$ 530,000$ 610,000$ DN900 for 1200L/s option, DN1050 for 2000L/s and DN1200 for 2800L/s8.2 New Gravity Drain and Outfall Structure 430,000$ 530,000$ 570,000$ DN900 for 1200L/s option, DN1050 for 2000L/s and DN1200 for 2800L/s8.3 Dewatering and Service Relocation Allowance 330,000$ 370,000$ 400,000$ 8.4 Road Sealing 30,000$ 30,000$ 30,000$ 9 SYSTEM COMMISSIONING, AS CONTRUCTED DRAWINGS, MANUALS ETC 60,000$ 60,000$ 60,000$

Subtotal (exc. GST) 2,450,000$ 3,790,000$ 4,230,000$ Contingency at 30% 740,000$ 1,140,000$ 1,270,000$ TOTAL (exc. GST) 3,200,000$ 4,900,000$ 5,500,000$

ASSUMPTIONS Estimate based on providing pump station to similar basic standard to existingAll land acquisition costs excludedAssumes adequate working areas available throughout construction period and for operation thereafterAssumes corridor available for new rising main and gravity drain along Liverpool Street and Eyre Street with outfall adhacent Yacht ClubAssumes existing PS sump to be used with adequate working room for 1200L/s option. Assumes land available for new pump station (2000L/s and 2800L/s option) on road reserve opposite existing PS site. If the existing PS site or immediately adjacent/opposite sideof road to the site is not available, additional costs for carrying inflows to a new PS site and additional rising main and power length will applyNo consideration as to ongoing inflow management method during works, nominal cost allowance onlyAssumes standard excavation, dewatering and shoring methods will be used to allow for insitu concrete construction. Alternative methods e.g. piling for the sump structure due to restricted space have not been costedand methods such as this will likely result in additional costsNo allowance for any building works (excuding for new switchroom for 2000L/s and 2800L/s option), amenities, sheltered work areas etcNo allowance for new screens, hoists, monorailsNo allowance for any increase in size of or any remediation to existing buffer storage, inlets, screens etcAssumes existing sump and valve pit are in a suitable condition for ongoing use for 1200L/s option. No condition assessment has been completed on the existing sump, valve pit and storageBased on initial assessment, pumps for 1200L/s can be located within the existing sump. However, the pump layout in the existing sump does not conform with pump supplier's recommendations for hydraulic purposes and requires confirmation from the pump supplierRefer to individual cost estimate sheets for specific allowances for each option

ESTIMATE

Note: Indicative construction estimates are prepared for general information only. We recommend that an appropriately qualified quantity surveyor be consulted to provide detailed advice regarding construction costs. In particular, without developed design, geotechnical and services information, actual construction costs are subject to significant variation from the values shown. Rates have been developed using a combination of Rawlinsons 2016/2017, previous tendered rates, rates developed in-house and some nominal allowances.

Page 43: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

INDICATIVE CONSTRUCTION COST ESTIMATELiverpool Street Pump Station Upgrade - City of Port Lincoln

Project Element: 1200 L/s Pump Option (Nominal 180kW New PS), 370m DN900 pipeJob No: 20160179Date: 29/06/2017

Estimated by: DGSReview by: JT

Item No Description Quantity Unit Rate Cost Comments

1 PRELIMINARIES, ESTABLISHMENT, ONGOING SITE AND PROJECT MANAGEMENTMobilisation 1 Item $50,000 $50,000 Based on Disher Creek (Renmark) project, value $1.5MQA, PM, JSEA - initial and ongoing 20 weeks $5,000 $100,000 Based on 20 weeks, reduced rates based on Hargraves Street stormwater pipelay ($15 000/week)Survey, setout, service locations 1 Item $40,000 $40,000 Based on Hargraves Street stormwater pipelay (450m, $50 000)Site security and facilities 20 weeks $1,500 $30,000 Based on 20 weeks, reduced rates based on Hargraves Street stormwater pipelay ($1 500/week)Demobilisation 1 Item $25,000 $25,000 AllowanceSubtotal $250,000

2 HANDLING OF INFLOWSEstablishment of equipment 1 Item $40,000 $40,000 Nominal allowance, pump station to remain partially functionalDaily hire / operation of equipment 140 days $500 $70,000 Allow for $500/dayDisestablishment of equipment 1 Item $10,000 $10,000 Nominal allowance, pump station to remain partially functionalSubtotal $120,000

3 DEMOLITION3.1 Demolition of redundant works 1 Item $10,000 $10,000 Nominal allowance only, assumes existing PS and RM kept in place

Subtotal $10,000

4 PUMP SUMP STRUCTURE4.1 New Pump Sump Structure

i) Excavate volume of sump structure and make good to subgrade level Retain existing PS => Item not applicableii) Base blinding layer Retain existing PS => Item not applicableiii) Sump walls Retain existing PS => Item not applicableiv) Sump base Retain existing PS => Item not applicablev) Sump cover slab and beams Retain existing PS => Item not applicablevi) Sump access 1 Item $20,000 $20,000 Allow for modifications to improve access / egressvii) Allowance for shoring Retain existing PS => Item not applicableviii) Allowance for dewatering Retain existing PS => Item not applicableix) Allowance against flotation Retain existing PS => Item not applicablex) Connection to existing storage and pipework Retain existing PS => Item not applicablexi) Make good - site surface pavements and surrounds Retain existing PS => Item not applicableSubtotal $20,000

4.2 New Valve Pit Structurei) Excavate volume of sump structure and make good to subgrade level Retain existing sump => Item not applicableii) Base blinding layer Retain existing PS => Item not applicableiii) Pit walls Retain existing sump => Item not applicableiv) Pit base Retain existing sump => Item not applicablev) Pit cover slab and beams Retain existing sump => Item not applicablevi) Pit access Retain existing sump => Item not applicablevii) Allowance for shoring Retain existing sump => Item not applicableviii) Allowance for dewatering Retain existing sump => Item not applicableix) Allowance against flotation Retain existing sump => Item not applicablex) Connection to existing storage and pipework Retain existing sump => Item not applicablexi) Make good - site surface pavements Retain existing sump => Item not applicableSubtotal $0

5 PUMP SUPPLY AND INSTALLATION (3 x 400L/s Pumps, No Jockey Pump)I) Modification of existing supports for new pumps 3 Item $1,500 $4,500 Nominal allowance onlyii) Supply and installation of new supports Existing supports to be modified +> Item not applicableiii) Supply of new duty pumps 400L/s 3 No. $41,000 $123,000 Supply and delivery of NP3301.180 LT 812 Imp Code 37kW + 15% Contractor Feeiv) Installation of new duty pumps 400L/s 3 No. $3,000 $9,000 Based on Hargraves Street stormwater PS large pump install ($3 800 each)v) Supply of jockey pump Item not applicable due to space limitationsvi) Installation of new jockey pump Item not applicable due to space limitationsSubtotal $140,000

6 VALVE AND MANIFOLD SUPPLY AND INSTALLATIONi) Removal of existing valve pit cover slab and make good after 1 Item $15,000 $15,000 Allowance only to provide access for installation of new manifold and replacement of slabii) Supply and install new DN900 manifold with 3 x DN350 branches 1 Item $100,000 $100,000 Based on Wellington Street manifold, DN1000 with 3 x 600 branches, $130000iii) Supply and install new DN350 non return valves 3 No. $7,000 $21,000 Based on internet price list of $6000 for DN300iv) Connecting DN350 pipework from pumps to manifold 3 No. $5,000 $15,000 Nominal allowance onlySubtotal $150,000

7 ELECTRICAL SUPPLYi) Supply new generator - low flows - assume 50kVA 1 No $20,000 $20,000 Nominal allowance based on quoted price for 220kVA generatorii) Install and commission new generator - low flows - assume 50kVA 1 Item $10,000 $10,000 Nom. allow. inc. site prep, controls, auto-switching. Total sup+inst cost R/insons = $40K to $60Kiii) Supply new generator - duty flows 220kVA generator 1 No $43,000 $43,000 Quoted price for 220kVA generator from MacFarlane Generators + 15% contractor markupiv) Install and commission new generator - duty flows 1 Item $40,000 $40,000 Nom. allow. inc. site prep, controls, auto-switching, security. Total sup+inst cost R/insons = $80K to $100Kv) New power supply cabling 260A from generator to PS site including excavation, laying, reinstatement 130 m $260 $33,800 Rate built up based on 4 x 120 sqmm cables and Rawlinson ratesvi) New VSD - 50kW 1 No $17,000 $17,000 From Danfoss price list 2012 + 20% for CPI and Contractor markupvii) Harmonic filter on VSD 1 No $10,000 $10,000 Nominal allowance - Hargraves St PS PC allowance of $17000viii) New controls, automation, SCADA 1 Item $45,000 $45,000 Nominal allowance only $15 000 SCADA (as per Hargrave St) + $30000ix) New switchboard and control panel 1 Item $75,000 $75,000 Nominal allowanceSubtotal $290,000

8 NEW RISING MAIN AND GRAVITY DRAIN8.1 New Rising Main and Break Pressure Junction Box

i) Connection to manifold 1 Item $30,000 $30,000 Nominal allowance onlyii) Supply and install new DN900 rising main 250 m $1,300 $325,000 Rate developed through Rawlinsons and interpolation of Hargrave Street ratesiii) New 1800 square JB break pressure box 1 No $20,000 $20,000 Hargraves St S/W - 1800x900 = $14000

8.2 New Gravity Drain and Outfall Structureii) Supply and install new DN900 gravity drain 120 m $1,300 $156,000 Rate developed through Rawlinsons and interpolation of Hargrave Street ratesii) New ocean outfall adjacent yacht club (100m buried gravity drain, screen and steel pile with hazard sign) 1 Item $210,000 $210,000 Based on ALB estimates

8.3 Dewatering and Service Relocation Allowancei) Dewatering of trenches 220 m $600 $132,000 Nominal length. Assumes trenches below 2.5mAHD to be dewatered.ii) Service relocation allowance 300 m $500 $150,000 Nominal allowance only. Hargraves St 460m, $350K, $760/m, likely fewer services at Liverpool Street

8.4 Road SealingI) Allowance for new spray seal / AC surface over 5m width 1500 m2 $15 $22,500 Hargraves St SW $18/m2 for profiling and 30ACSubtotal Item 7 $1,050,000

9 SYSTEM COMMISSIONING, AS CONTRUCTED DRAWINGS, MANUALS ETCi) System commissioning - assume 3 persons x 3 weeks 3 Weeks $15,000 $45,000 Assume 3 persons x 3 weeksii) As constructed drawings 1 Item $10,000 $10,000 Nomnial allowance onlyiii) Compilation of manuals - assume 1 person x 1 week 1 Week $5,000 $5,000 Assume 1 person x 1 week

$60,000

$2,080,00018% $370,000 From Rawlinsons

$2,450,00030% $740,000

$3,200,000

ASSUMPTIONS All land acquisition costs excludedAssumes adequate working areas available throughout construction period and for operation thereafterAssumes corridor available (Eyre Street) for new rising main and gravity drainAssumes land available for new pump station (2000L/s and 2800L/s option) adjacent existing PS site (within road reserve) with no allowance for piping flows to an alternative siteNo consideration as to ongoing inflow management during works, nominal cost allowance onlyNo allowance for any building works, amenities, sheltered work areas etcNo allowance for new screens, hoists, monorailsNo allowance for any increase in size of or any remediation to existing buffer storage, inlets, screens etcNo allowance made for new SAPN customer supply chargeNo allowance made for any fees or charges with service authorities or governement agenciesAssumes existing switch room is utilised with no provision for refurbishment of building structure, space available for new switchboardAssumes one VSD only on single 400L/s pump

Subtotal 1Locality Allowance

Project Size AllowanceSubtotal 2

ContingencyTOTAL (exc. GST)

Note: Indicative construction estimates are prepared for general information only. We recommend that an appropriately qualified quantity surveyor be consulted to provide detailed advice regarding construction costs. In particular, without developed design, geotechnical and services information, actual construction costs are subject to significant variation from the values shown. Rates have been developed using a combination of Rawlinsons 2016/2017, previous tendered rates, rates developed in-house and some nominal allowances.

30/06/2017 \\filesvr04\projects\2016\20160179 Liverpool St Pump Station Upgrade - City of Port Lincoln\3_Development\4 Calculations\Cost Estimate\20160179 Cost Estimation_June_2017

Page 44: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

INDICATIVE CONSTRUCTION COST ESTIMATELiverpool Street Pump Station Upgrade - City of Port Lincoln

Project Element: 2000 L/s Pump Option (Nominal 180kW New PS), 370m DN1050 pipeJob No: 20160179Date: 29/06/2017

Estimated by: DGSReview by: JT

Item No Description Quantity Unit Rate Cost Comments

1 PRELIMINARIES, ESTABLISHMENT, ONGOING SITE AND PROJECT MANAGEMENTMobilisation 1 Item $70,000 $70,000 Based on Disher Creek (Renmark) project, value $1.5M, plus additional allowance for structural worksQA, PM, JSEA - initial and ongoing 30 weeks $5,000 $150,000 Based on 20 weeks, reduced rates based on Hargraves Street stormwater pipelay ($15 000/week)Survey, setout, service locations, as constructed drawings 1 Item $50,000 $50,000 Based on Hargraves Street stormwater pipelay (450m, $50 000) plus additional building setoutSite security and facilities 30 weeks $1,500 $45,000 Based on 20 weeks, reduced rates based on Hargraves Street stormwater pipelay ($1 500/week)Demobilisation 1 Item $30,000 $30,000 AllowanceSubtotal $350,000

2 HANDLING OF INFLOWS (Minor allowance only as new pump sump being constructed)Establishment of equipment 1 Item $20,000 $20,000 Nominal allowance, existing pump station may lose functionalityDaily hire / operation of equipment 1 Item $10,000 $10,000Disestablishment of equipment 1 Item $10,000 $10,000Subtotal $40,000 Nominal allowance only

3 DEMOLITION3.1 Demolition of redundant works 1 Item $30,000 $30,000 Nominal allowance only

Subtotal $30,000

4 PUMP SUMP STRUCTURE4.1 New Pump Sump Structure

i) Excavate volume of sump structure and make good to subgrade level 500 m3 $60 $30,000 Based on new PS internal size of 7.2x6.9x3.3 high + 0.4 thick walls + blind layer + 20%. Use trench rate - 25%ii) Base blinding layer 100 m2 $100 $10,000 Based on new PS internal size of 7.2m x 6.9m + 0.4 thick walls + 1m perimeter x 0.5 thickiii) Sump walls 50 m3 $2,000 $100,000 Based on 7.2x6.9x3.3 high, 0.4 thick walls + 25% for internal walls. R/son $1400/m3, quoted rates have been greateriv) Sump base 25 m3 $750 $18,750 Based on 7.2x6.9, 0.4 thick base. R/son $250/m3, quoted rates have been greaterv) Sump cover slab and beams 70 m2 $500 $35,000 Assume precast, Rawlinson rate of $250/sqm x 2 to allow for beamsvi) Sump access 1 Item $20,000 $20,000 Nominal allowance for access locations and safetyvii) Allowance for shoring 1 Item $120,000 $120,000 Based on initial installation $70,000 +$5,000/week during construction and removal $15,000viii) Allowance for dewatering 1 Item $60,000 $60,000 Based on nominal $20 000 establishment + $5000 disestablishment + $1000/day x 5 weeksix) Allowance against flotation 10 m3 $500 $5,000 Provide additional 0.5 wide toe to base slabx) Connection to existing storage and pipework 1 Item $50,000 $50,000 Nominal allowance only, assumes new PS adjacent existingxi) Make good - site surface pavements and surrounds 130 m2 $100 $13,000 Assume 3m wide perimeter to pump sumpSubtotal $460,000

4.2 New Valve Pit Structurei) Excavate volume of sump structure and make good to subgrade level 85 m3 $60 $5,100 Based on dimensions (5.2x3.3x1.8 nom. equal to Wellington Street, 3 pumps, DN1000 manifold)ii) Base blinding layer 30 m2 $100 $3,000 Based on 5.2x3.3 + 0.3 thick walls + 0.5m perimeter x 0.4 thickiii) Pit walls 8.2 m3 $2,000 $16,400 Based on 5.2x3.3x1.8 high, 0.25 thick walls + 10% for manifold supportiv) Pit base 6.5 m3 $750 $4,875 Based on 5.2x3.3, 0.3 thick base. R/son $250/m3, quoted rates have been greaterv) Pit cover slab and beams 27 m2 $500 $13,500 Assume precast, Rawlinson rate of $250/sqm x 2 to allow for beamsvi) Pit access 1 Item $10,000 $10,000 Nominal allowance for access locations and safetyvii) Allowance for shoring 1 Item $21,000 $21,000 Based on $20/m2/day (trench rate) x 50 sqm x 3 weeks. Establishment included in 3.1viii) Allowance for dewatering 1 Item $21,000 $21,000 Based on $1000/day x 3 weeks. Establishment included in 3.1ix) Allowance against flotation 4 m3 $500 $2,000 Provide additional 0.5 wide toe to base slabx) Connection to existing storage and pipework Item N/Axi) Make good - site surface pavements 55 m2 $100 $5,500 Assume 2m wide perimeter to valve pitSubtotal $100,000

5 PUMP SUPPLY AND INSTALLATION (3 x 670L/s Pumps plus Jockey Pump)I) Modification of existing supports for new pumps N/A, new sump being installedii) Supply and installation of new supports 4 No. $2,000 $8,000 Nominal allowanceiii) Supply of new duty pumps 670L/s 3 No. $81,000 $243,000 Supply and delivery of NP3531/736 1270 60kW + 15% Contractor Feeiv) Installation of new duty pumps 670L/s 3 No. $3,800 $11,400 Based on Hargraves Street stormwater PS large pump install ($3 800 each)v) Supply of jockey pump 1 No. $29,000 $29,000 Supply and delivery of NP3202.185 LT 617 Imp Code 22kW + 15% Contractor Feevi) Installation of new jockey pump 1 No. $2,000 $2,000 Based on Hargraves Street stormwater PS large pump install ($3 800 each)Subtotal $290,000

6 VALVE AND MANIFOLD SUPPLY AND INSTALLATIONi) Removal of existing valve pit cover slab and make good after N/A as new pit to be providedii) Supply and install new DN1050 manifold with 3 x DN500 branches 1 Item $140,000 $140,000 Based on Wellington Street manifold, DN1000 with 3 x 600 branches, $130000iii) Supply and install new DN350 non return valves 1 Item $52,000 $52,000 Extrapolated based on internet price list of $6000 for DN300iv) Connecting DN350 pipework from pumps to manifold 4 No. $7,500 $30,000 Nominal allowance onlySubtotal $220,000

7 ELECTRICAL SUPPLYi) Supply new generator - low flows - assume 50kVA 1 No $20,000 $20,000 Nominal allowance based on quoted price for 220kVA generatorii) Install and commission new generator - low flows - assume 50kVA 1 Item $10,000 $10,000 Nominal allowance including site prep, controls, auto-switching. Total cost Rawlinsons = $40K to $60Kiii) Supply new generator - duty flows 275kVA generator 1 No $67,000 $67,000 Quoted price for 275kVA generator from MacFarlane Generators + 15% contractor markupiv) Install and commission new generator - duty flows 1 Item $50,000 $50,000 Nom. allow. inc. site prep, controls, auto-switching, security. Total sup+inst cost R/insons = $80K to $100Kv) New power supply cabling 430A from generator to PS site including excavation, laying, reinstatement 130 m $400 $52,000 Rate built up based on 4 x 240 sqmm cables and Rawlinson ratesvi) New switch room (9m x 3m x 2.4m high) prefabricated hut, inclusive of foundation and underfloor vault 1 Item $40,000 $40,000 Based on Williams Prefabricated building and concrete underfloor vault for cable entryvii) New switchboard and control panel 1 Item $100,000 $100,000 Nominal allowanceviii) New VSD - 75kW 1 No $26,000 $26,000 From Danfoss price list 2012 + 20% for CPI and Contractor markupix) Harmonic filter on VSD 1 No $15,000 $15,000 Nominal allowance - Hargraves St PS PC allowance of $17000x) New controls, automation, SCADA 1 Item $50,000 $50,000 Nominal allowance only $15 000 SCADA (as per Hargrave St) + $35000Subtotal $430,000

8 NEW RISING MAIN AND GRAVITY DRAIN8.1 New Rising Main and Break Pressure Junction Box

i) Connection to manifold 1 Item $35,000 $35,000 Nominal allowance onlyii) Supply and install new DN1050 rising main 250 m $1,550 $387,500 Rate developed through Rawlinsons and interpolation of Hargrave Street ratesiii) New 1800 square JB break pressure box 1 No $25,000 $25,000 Hargraves St S/W - 1800x900 = $14000 with benching allowance

8.2 New Gravity Drain and Outfall Structureii) Supply and install new DN1050 gravity drain 120 m $1,550 $186,000 Rate developed through Rawlinsons and interpolation of Hargrave Street ratesii) New ocean outfall adjacent yacht club (100m buried gravity drain, screen and steel pile with hazard sign) 1 Item $210,000 $210,000 Based on ALB estimatesiii) Connection from existing PS sump to new PS sump (15m DN1200 + break into existing) 1 Item $50,000 $50,000 Nominal allowance only

8.3 Dewatering and Service Relocation Allowancei) Dewatering of trenches 250 m $600 $150,000 Nominal length. Assumes trenches below 2.5mAHD to be dewatered.ii) Service relocation allowance 300 m $550 $165,000 Nominal allowance only. Hargraves St 460m, $350K, $760/m, likely fewer services at Liverpool Street

8.4 Road SealingI) Allowance for new spray seal / AC surface over 5m width + pump sump 1650 m2 $15 $24,750 Hargraves St SW $18/m2 for profiling and 30ACSubtotal Item 7 $1,230,000

9 SYSTEM COMMISSIONING, AS CONTRUCTED DRAWINGS, MANUALS ETCi) System commissioning - assume 3 persons x 3 weeks 3 Weeks $15,000 $45,000 Assume 3 persons x 3 weeksii) As constructed drawings 1 Item $10,000 $10,000 Nomnial allowance onlyiii) Compilation of manuals - assume 1 person x 1 week 1 Week $5,000 $5,000 Assume 1 person x 1 week

$60,000

$3,220,00018% $580,000 From Rawlinsons

$3,800,00030% $1,140,000

$4,900,000

ASSUMPTIONS All land acquisition costs excludedAssumes adequate working areas available throughout construction period and for operation thereafterAssumes corridor available (Eyre Street) for new rising main and gravity drainAssumes land available for new pump station (2000L/s and 2800L/s option) in road reserve opposite existing PS with no allowance for piping flows to an alternative siteNo consideration as to ongoing inflow management during works, exisitng PS remains in service throughout constructionNo allowance for any building works, amenities, sheltered work areas etcNo allowance for new screens, hoists, monorailsNo allowance for any increase in size of or any remediation to existing buffer storage, inlets, screens etcNo allowance made for new SAPN customer supply charge or upgrade to SAPN supplyNo allowance made for any fees or charges with service authorities or governement agenciesAssumes one VSD only on single 670L/s pump

Subtotal 1Locality Allowance

Note: Indicative construction estimates are prepared for general information only. We recommend that an appropriately qualified quantity surveyor be consulted to provide detailed advice regarding construction costs. In particular, without developed design, geotechnical and services information, actual construction costs are subject to significant variation from the values shown. Rates have been developed using a combination of Rawlinsons 2016/2017, previous tendered rates, rates developed in-house and some nominal allowances.

Project Size AllowanceSubtotal 2

ContingencyTOTAL (exc. GST)

30/06/2017 \\filesvr04\projects\2016\20160179 Liverpool St Pump Station Upgrade - City of Port Lincoln\3_Development\4 Calculations\Cost Estimate\20160179 Cost Estimation_June_2017

Page 45: I20175905 14.19.2.121 Mortlock Terrace Catchment Study · Mortlock Terrace Catchment Study ... 1.2 Study Intent and Scope 1 ... Undertook a high level options analysis to quantify

INDICATIVE CONSTRUCTION COST ESTIMATELiverpool Street Pump Station Upgrade - City of Port Lincoln

Project Element: 2800 L/s Pump Option (Nominal 375kW New PS), 370m DN1200 pipeJob No: 20160179Date: 29/06/2017

Estimated by: DGSReview by: JT

Item No Description Quantity Unit Rate Cost Comments

1 PRELIMINARIES, ESTABLISHMENT, ONGOING SITE AND PROJECT MANAGEMENTMobilisation 1 Item $70,000 $70,000 Based on Disher Creek (Renmark) project, value $1.5M, plus additional allowance for structural worksQA, PM, JSEA - initial and ongoing 30 weeks $5,000 $150,000 Based on 20 weeks, reduced rates based on Hargraves Street stormwater pipelay ($15 000/week)Survey, setout, service locations, as constructed drawings 1 Item $50,000 $50,000 Based on Hargraves Street stormwater pipelay (450m, $50 000) plus additional building setoutSite security and facilities 30 weeks $1,500 $45,000 Based on 20 weeks, reduced rates based on Hargraves Street stormwater pipelay ($1 500/week)Demobilisation 1 Item $30,000 $30,000 AllowanceSubtotal $350,000

2 HANDLING OF INFLOWS (Minor allowance only as new pump sump being constructed)Establishment of equipment 1 Item $20,000 $20,000 Nominal allowance, existing pump station may lose functionalityDaily hire / operation of equipment 1 Item $10,000 $10,000Disestablishment of equipment 1 Item $10,000 $10,000Subtotal $40,000 Nominal allowance only

3 DEMOLITION3.1 Demolition of redundant works 1 Item $30,000 $30,000 Nominal allowance only

Subtotal $30,000

4 PUMP SUMP STRUCTURE4.1 New Pump Sump Structure

i) Excavate volume of sump structure and make good to subgrade level 600 m3 $60 $36,000 Based on new PS internal size of 8.8x7.5x3.3 high + 0.4 thick walls + blind layer + 20%. Use trench rate - 25%ii) Base blinding layer 120 m2 $100 $12,000 Based on new PS internal size of 7.2m x 6.9m + 0.4 thick walls + 1m perimeter x 0.5 thickiii) Sump walls 56 m3 $2,000 $112,000 Based on 8.8x7.5x3.3 high, 0.4 thick walls + 25% for internal walls. R/son $1400/m3, quoted rates have been greateriv) Sump base 32 m3 $750 $24,000 Based on 8.8x7.5, 0.4 thick base. R/son $250/m3, quoted rates have been greaterv) Sump cover slab and beams 90 m2 $500 $45,000 Assume precast, Rawlinson rate of $250/sqm x 2 to allow for beamsvi) Sump access 1 Item $20,000 $20,000 Nominal allowance for access locations and safetyvii) Allowance for shoring 1 Item $130,000 $130,000 Based on initial installation $80,000 +$7,500/week during construction and removal $15,000viii) Allowance for dewatering 1 Item $60,000 $60,000 Based on nominal $20 000 establishment + $5000 disestablishment + $1000/day x 5 weeksix) Allowance against flotation 10 m3 $500 $5,000 Provide additional 0.5 wide toe to base slabx) Connection to existing storage and pipework 1 Item $50,000 $50,000 Nominal allowance only, assumes new PS adjacent existingxi) Make good - site surface pavements and surrounds 150 m2 $100 $15,000 Assume 3m wide perimeter to pump sumpSubtotal $510,000

4.2 New Valve Pit Structurei) Excavate volume of sump structure and make good to subgrade level 95 m3 $60 $5,700 Based on dimensions (5.2x3.3x1.8 nom. equal to Wellington Street, 3 pumps, DN1000 manifold), increased for DN1200ii) Base blinding layer 36 m2 $100 $3,600 Based on 5.2x3.6 + 0.3 thick walls + 0.5m perimeter x 0.4 thickiii) Pit walls 8.5 m3 $2,000 $17,000 Based on 5.2x3.6x1.8 high, 0.25 thick walls + 10% for manifold supportiv) Pit base 7 m3 $750 $5,250 Based on 5.2x3.6, 0.3 thick base. R/son $250/m3, quoted rates have been greaterv) Pit cover slab and beams 30 m2 $500 $15,000 Assume precast, Rawlinson rate of $250/sqm x 2 to allow for beamsvi) Pit access 1 Item $10,000 $10,000 Nominal allowance for access locations and safetyvii) Allowance for shoring 1 Item $23,100 $23,100 Based on $20/m2/day (trench rate) x 55 sqm x 3 weeks. Establishment included in 3.1viii) Allowance for dewatering 1 Item $21,000 $21,000 Based on $1000/day x 3 weeks. Establishment included in 3.1ix) Allowance against flotation 4 m3 $500 $2,000 Provide additional 0.5 wide toe to base slabx) Connection to existing storage and pipework Item N/Axi) Make good - site surface pavements 60 m2 $100 $6,000 Assume 2m wide perimeter to valve pitSubtotal $110,000

5 PUMP SUPPLY AND INSTALLATION (3 x 930L/s Pumps plus Jockey Pump)I) Modification of existing supports for new pumps N/A, new sump being installedii) Supply and installation of new supports 4 No. $2,000 $8,000 Nominal allowanceiii) Supply of new duty pumps 400L/s 3 No. $93,000 $279,000 Supply and delivery of NP3531/736 870 125kW + 15% Contractor Feeiv) Installation of new duty pumps 400L/s 3 No. $3,800 $11,400 Based on Hargraves Street stormwater PS large pump install ($3 800 each)v) Supply of jockey pump 1 No. $29,000 $29,000 Supply and delivery of NP3202.185 LT 617 Imp Code 22kW + 15% Contractor Feevi) Installation of new jockey pump 1 No. $2,000 $2,000 Based on Hargraves Street stormwater PS large pump install ($3 800 each)Subtotal $330,000

6 VALVE AND MANIFOLD SUPPLY AND INSTALLATIONi) Removal of existing valve pit cover slab and make good after N/A as new pit to be providedii) Supply and install new DN1200 manifold with 3 x DN500 branches 1 Item $160,000 $170,000 Based on Wellington Street manifold, DN1000 with 3 x 600 branches, $130000iii) Supply and install new DN350 non return valves 1 Item $52,000 $52,000 Extrapolated based on internet price list of $6000 for DN300iv) Connecting DN350 pipework from pumps to manifold 4 No. $7,500 $30,000 Nominal allowance onlySubtotal $250,000

7 ELECTRICAL SUPPLYi) Supply new generator - low flows - assume 50kVA 1 No $20,000 $20,000 Nominal allowance based on quoted price for 220kVA generatorii) Install and commission new generator - low flows - assume 50kVA 1 Item $10,000 $10,000 Nominal allowance including site prep, controls, auto-switching. Total cost Rawlinsons = $40K to $60Kiii) Supply new generator - duty flows 580kVA generator 1 No $105,000 $105,000 Quoted price for 275kVA generator from MacFarlane Generators + 15% contractor markupiv) Install and commission new generator - duty flows 1 Item $50,000 $50,000 Nom. allow. inc. site prep, controls, auto-switching, security. Total sup+inst cost R/insons = $80K to $100Kv) New power supply cabling 600A from generator to PS site including excavation, laying, reinstatement 130 m $580 $75,400 Rate built up based on 4 x 300 sqmm cables and Rawlinson ratesvi) New switch room (9m x 3m x 2.4m high) prefabricated hut, inclusive of foundation and underfloor vault 1 Item $40,000 $40,000 Based on Williams Prefabricated building and concrete underfloor vault for cable entryvii) New switchboard and control panel 1 Item $125,000 $125,000 Nominal allowanceviii) New VSD - 150kW 1 No $40,000 $40,000 Extrapolated from Danfoss price list 2012 + 20% for CPI and Contractor markupix) Harmonic filter on VSD 1 No $20,000 $20,000 Nominal allowance - Hargraves St PS PC allowance of $17000x) New controls, automation, SCADA 1 Item $55,000 $55,000 Nominal allowance only $15 000 SCADA (as per Hargrave St) + $40000Subtotal $540,000

8 NEW RISING MAIN AND GRAVITY DRAIN8.1 New Rising Main and Break Pressure Junction Box

i) Connection to manifold 1 Item $35,000 $40,000 Nominal allowance onlyii) Supply and install new DN1200 rising main 250 m $1,800 $450,000 Rate developed through Rawlinsons and interpolation of Hargrave Street ratesiii) New 2000 square JB break pressure box 1 No $30,000 $30,000 Hargraves St S/W - 1800x900 = $14000 with benching allowance

8.2 New Gravity Drain and Outfall Structurei) Supply and install new DN1200 gravity drain 120 m $1,800 $216,000 Rate developed through Rawlinsons and interpolation of Hargrave Street ratesii) New ocean outfall adjacent yacht club (100m buried gravity drain, screen and steel pile with hazard sign) 1 Item $210,000 $210,000 Based on ALB estimatesiii) Connection from existing PS sump to new PS sump (15m DN1500 + break into existing) 1 Item $60,000 $60,000 Nominal allowance only

8.3 Dewatering and Service Relocation Allowancei) Dewatering of trenches 270 m $600 $162,000 Nominal length. Assumes trenches below 2.5mAHD to be dewatered.ii) Service relocation allowance 300 m $580 $174,000 Nominal allowance only. Hargraves St 460m, $350K, $760/m, likely fewer services at Liverpool Street

8.4 Road SealingI) Allowance for new spray seal / AC surface over 5m width + pump sump 1700 m2 $15 $25,500 Hargraves St SW $18/m2 for profiling and 30ACSubtotal Item 7 $1,370,000

9 SYSTEM COMMISSIONING, AS CONTRUCTED DRAWINGS, MANUALS ETCi) System commissioning - assume 3 persons x 3 weeks 3 Weeks $15,000 $45,000 Assume 3 persons x 3 weeksii) As constructed drawings 1 Item $10,000 $10,000 Nomnial allowance onlyiii) Compilation of manuals - assume 1 person x 1 week 1 Week $5,000 $5,000 Assume 1 person x 1 week

$60,000

$3,580,00018% $640,000 From Rawlinsons

$4,220,00030% $1,270,000

$5,500,000

ASSUMPTIONS All land acquisition costs excludedAssumes adequate working areas available throughout construction period and for operation thereafterAssumes corridor available (Eyre Street) for new rising main and gravity drainAssumes land available for new pump station (2000L/s and 2800L/s option) in road reserve opposite existing PS with no allowance for piping flows to an alternative siteNo consideration as to ongoing inflow management during works, exisitng PS remains in service throughout constructionNo allowance for any building works, amenities, sheltered work areas etcNo allowance for new screens, hoists, monorailsNo allowance for any increase in size of or any remediation to existing buffer storage, inlets, screens etcNo allowance made for new SAPN customer supply charge or upgrade to SAPN supplyNo allowance made for any fees or charges with service authorities or governement agenciesAssumes one VSD only on single 930L/s pump

Subtotal 1Locality Allowance

Note: Indicative construction estimates are prepared for general information only. We recommend that an appropriately qualified quantity surveyor be consulted to provide detailed advice regarding construction costs. In particular, without developed design, geotechnical and services information, actual construction costs are subject to significant variation from the values shown. Rates have been developed using a combination of Rawlinsons 2016/2017, previous tendered rates, rates developed in-house and some nominal allowances.

Project Size AllowanceSubtotal 2

ContingencyTOTAL (exc. GST)