10/31/2018 District Irrigation Profiles http://irrigationap.cgg.gov.in/wrd/getDistricts 1/23 IRRIGATION PROFILE OF ANANTAPURAMU DISTRICT *Click here for Ayacut Map INTRODUCTION Ananthapuramu District is situated in Rayalseema region of Andhra Pradesh state and lies between 13°-40'N to 15°-15'N Latitude and 76°-50'E to 78°-30'E Longitude with a population of 40,83,315 (2011 census). One of the famous spiritual center in this district is Puttaparthi and it is 80Km. away from Ananthapuramu. The District falls partly in Krishna basin and partly in Pennar basin. The District is surrounded by Bellary, Kurnool Districts on the North, Kadapa and Kolar Districts of Karnataka on South East and North respectively. The district is principally a hot country and temperatures vary from 17°C-40°C. The important rivers flowing in the District are (1) Pennar (2) Jayamangali (3) Chitravathi (4) Vedavathi (also called Hagari), (5) Papagni, (6) Maddileru. The district head quarter is connected by S.C. Railways broad gauge railway line from Secunderabad, Guntakal, Bangalore and Bellary (Via) Guntakal to Pakala. Most of the area in this District is covered under Minor Irrigation Sources only in addition to one completed Major Irrigation Project viz., Tungabhadra Project High level canal (TBP HLC) system stage-I (A joint venture of Karnataka and Andhra Pradesh States). The Right Bank High level canal (R.B.H.L.C.) takes off from right bank of T.B. Dam and runs in Karnataka and enters in Andhra Pradesh at Km. 105.437 and contemplated to irrigate an ayacut of 2.849 Lakh acres out of this 1,45,236 acres in Ananthapuramu district and remaining is Kurnool and Kadapa District. The T.B.P.H.L.C. Stage-II scheme, which is an Ongoing Project has been taken up during 1967 with a cost of Rs 914.70 Lakhs to provide irrigation facilities to an extent of 2,83,041 acres (including 1,01,600 acres under PABR Stage-II, i.e., Yadiki Canal System) in Ananthapuramu, Kadapa and Kurnool districts. Out of the total ayacut of 2,83,041 acres ayacut contemplated under T.B.P.H.L.C. Stage-II scheme, an ayacut of 1,33,807 acres is situated in Ananthapuramu district. Thus the total Ayacut contemplated in Ananthapuramu district under TBP HLC Scheme (Stage-I and II) is 2, 34,177 acres. Handri Neeva Sujala Sravanthi is another ongoing major Irrigation Project takenup in the district with utilization of 40 TMCft of Krishna water to irrigate 6.025 Lakh Acres in drought prone areas of Kurnool, Ananthapuramu and Chittoor Districts, out of this 3, 45,000 Acres is situated in Ananthapuramu District. Further in this district there are four Medium Irrigation projects 1) Upper Pennar Project (Ayacut 10048 Acres) 2) Pennar Kumudvathi Project (Ayacut 6126 Acres) 3) Bhairavanithippa Project ((Ayacut 12000 Acres) and 4) Yogivemana Reservoir Project (Ayacut 11510 Acres) and also called Maddileru Project. The classification of total area of the District is as follows: Population : 40,83,315 Mandals : 63 Nos. Geographical Area Area in hectares % of Total Area Total geographical area 19,13,000 100 Forest area 1,96,978 10.30 Cultivable area 11,79,000 61.63 Barren and uncultivable land 1,87,305 9.67 Land put to Non Agricultural use 1,20,791 6.31
23
Embed
I R R I G AT I O N P R O F I L E O F A N A N TA P U R A M ...apcada.in/APIIATP/Apiiatp_Ref_Files/Documents/Anathapuram_irrigation Profile.pdfirrigate an ayacut of 2.849 Lakh acres
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Ananthapuramu District is situated in Rayalseema region of Andhra Pradesh state and lies between 13°-40'N to 15°-15'N Latitude and76°-50'E to 78°-30'E Longitude with a population of 40,83,315 (2011 census). One of the famous spiritual center in this district is Puttaparthi and it is80Km. away from Ananthapuramu. The District falls partly in Krishna basin and partly in Pennar basin. The District is surrounded by Bellary, KurnoolDistricts on the North, Kadapa and Kolar Districts of Karnataka on South East and North respectively. The district is principally a hot country andtemperatures vary from 17°C-40°C. The important rivers flowing in the District are (1) Pennar (2) Jayamangali (3) Chitravathi (4) Vedavathi (also calledHagari), (5) Papagni, (6) Maddileru.
The district head quarter is connected by S.C. Railways broad gauge railway line from Secunderabad, Guntakal, Bangalore and Bellary (Via)Guntakal to Pakala.
Most of the area in this District is covered under Minor Irrigation Sources only in addition to one completed Major Irrigation Project viz.,Tungabhadra Project High level canal (TBP HLC) system stage-I (A joint venture of Karnataka and Andhra Pradesh States). The Right Bank High levelcanal (R.B.H.L.C.) takes off from right bank of T.B. Dam and runs in Karnataka and enters in Andhra Pradesh at Km. 105.437 and contemplated toirrigate an ayacut of 2.849 Lakh acres out of this 1,45,236 acres in Ananthapuramu district and remaining is Kurnool and Kadapa District. TheT.B.P.H.L.C. Stage-II scheme, which is an Ongoing Project has been taken up during 1967 with a cost of Rs 914.70 Lakhs to provide irrigation facilitiesto an extent of 2,83,041 acres (including 1,01,600 acres under PABR Stage-II, i.e., Yadiki Canal System) in Ananthapuramu, Kadapa and Kurnooldistricts. Out of the total ayacut of 2,83,041 acres ayacut contemplated under T.B.P.H.L.C. Stage-II scheme, an ayacut of 1,33,807 acres is situated inAnanthapuramu district. Thus the total Ayacut contemplated in Ananthapuramu district under TBP HLC Scheme (Stage-I and II) is 2, 34,177 acres.
Handri Neeva Sujala Sravanthi is another ongoing major Irrigation Project takenup in the district with utilization of 40 TMCft of Krishnawater to irrigate 6.025 Lakh Acres in drought prone areas of Kurnool, Ananthapuramu and Chittoor Districts, out of this 3, 45,000 Acres is situated inAnanthapuramu District. Further in this district there are four Medium Irrigation projects 1) Upper Pennar Project (Ayacut 10048 Acres) 2) PennarKumudvathi Project (Ayacut 6126 Acres) 3) Bhairavanithippa Project ((Ayacut 12000 Acres) and 4) Yogivemana Reservoir Project (Ayacut 11510 Acres)and also called Maddileru Project.
The classification of total area of the District is as follows:
Population : 40,83,315Mandals : 63 Nos.
Geographical Area Area in hectares % of Total AreaTotal geographical area 19,13,000 100Forest area 1,96,978 10.30Cultivable area 11,79,000 61.63Barren and uncultivable land 1,87,305 9.67Land put to Non Agricultural use 1,20,791 6.31
1. Tungabhadra Project Hight Level Canal System ( TBPHLC)
Preamble
The T.B.P.H.L.C. scheme is a joint venture of Karnataka and Andhra Pradesh states. The Right Bank High Level Canal (R.B.H.L.C) takes offfrom Right bank of T.B. Dam and runs in Karnataka and enters in Andhra Pradesh at Km 105.437 and contemplated to irrigate an ayacut of 2.849 LakhsAcres out of this 1,45,236 Acres are in Ananthapuramu District and the remaining is Kurnool and Kadapa Districts.
The distribution of 21.73 T.M.Cft. of water within Ananthapuramu District for T.B.P.H.L.C. System is as given below.
S.No. Subsystem Entitlement out of 32.50 T.M.Cft.Ananthapuramu District
3 Mid Pennar South Canal 4.32 T.M.cft.4 Mid Pennar North Canal 1.87 T.M.cft.5 T.B.C. including M.B.R & S.S.B.R. T.B.P HLC Stage-I 3.70 T.M.cft.
Total 21.73 T.M.cft.
The scheme has been taken up in the following two stages.
T.B.P.H.L.C. Scheme Stage-I
T.B.P.H.L.C. Scheme Stage-II
T.B.P.H.L.C. Stage-I:
The T.B.P.H.L.C. Scheme Stage-I has been taken up in the year 1960 and completed by 1966 with a cost of Rs.11.74 Crores creating anIrrigation Potential of 1,07,516 in Ananthapuramu District The T.B.P HLC consists of the following Components.
1. High Level Main Canal (H.LM.C) from A.P. Border to Vagu leading to Mid Pennar Reservoir (M.P.R)
2. Mid Pennar Reservoir (M.P.R) with a Gross Storage Capacity of 5 T.Mcft.
3. Mid Pennar South Canal (M.P.S.C)
4. Tadipatri Branch Canal (T.B.C).
5. Mid Pennar North Canal (M.P.N.C).
T.B.P.H.L.C. STAGE-II:
The T.B.P.H.L.C. Scheme Stage-II has been taken up during 1967 contemplating an irrigation potential to an extent of 32,063 acres inAnanthapuramu District.
The T.B.P.H.L.C. Scheme Stage-II consists of the following components with in the District.
(1) Subbaraya Sagar Balancing Reservoir (S.S.B.R)
(2) Muchukota Balancing Reservoir (M.B.R)
(3) Guntakal Branch Canal (G.B.C) System
(4) Penna Ahobilam Balancing Reservoir (P.A.B.R)
(5) Excavation of Penna Ahobilam Balancing Reservoir Right Canal (P.A.B.R.Right Canal)
(6) Yadiki Canal system
Out of the above works, item No. 1 and 2 are completed. Item No. 3 to 5 are almost completed except distributory and No. 6 is in Progressunder EPC turn key system.
The details of the completed and ongoing components of the system are as follows.
TBPHLC System (Stage-I) HIGH LEVEL MAIN CANAL (H.L.M.C)
From A.P. Border to Mid Pennar Dam.
Preamble
The High Level Main Canal (H.L.M.C) enters in to Andhra Pradesh at Km. 105.437 near Bommanahal (v), Ananthapuramu District andterminates in to a vanka which leads to Mid Pennar Reservoir.
Salient Features
Location : The High Level Main Canal (H.L.M.C) enters in to Andra Pradesh at Km. 105.437 near Bommanahal(v), Ananthapuramu District and terminates in to a vanka which leads to Mid Pennar Reservoir.
Ayacut : 35,541 AcresMandals Benefitted : Bommanahal, D'Hirehal, Kanekal, Vidapankal, UravakondaWater Allocation : 7.32 T.Mcft. of Tungabhadra water is allocatedDetails Of The CanalLength : 84.24 Km.
Modernisation of TBP High Level Main Canal from Km.105.437 to Km. 189.680
In addition to 32.50 T.Mcft of Tungabhadra water allocated by the KWDT, a quantity of 10 T.Mcft of water is also allocated by theGovernment of Andhra Pradesh to PABR for catering the drinking requirement and other incidental needs of the District, vide G.O. Ms. No. 3 Irrigation& CAD (P.W..MAJ.Irr.VI) Department, Dated: 04.01.2006. In order to draw 42.50 T.Mcft (32.50 + 10.00) of Tungabhadra water, the High Level MainCanal (HLMC) is to be widened to carry a discharge of 4200 cusecs at A.P. Border as suggested by the Committee of Experts.
The Administrative Approval has been accorded by the Government for Rs. 463.50 Crores vide G.O.Ms. No. 249 I&CAD (PW-Maj. IX)Dept. Dated : 23.11.2007. This work is being taken up in 6 Packages (Period of contract: 51 months) and the works have been taken up in the closureperiod i.e. from March, 2009 onwards.
2. TBPHLC System (Stage-I)
MID PENNAR RESERVOIR (M.P.R)
Preamble
The Mid Pennar Reservoir has been constructed across River Pennar near Penakacherla (v), Garladinne Mandal, Ananthapuramu District ofAndhra Pradesh witha storage capacity of 5.17 TMC.
Total 24 Anantapur 2 Peddapappuru 1Narpala 6 Total 22
Total 46
Modernisation of Mid Pennar South Canal (MPSC) from Km. 0.00 to Km. 84.00
It is proposed to modernize the M.P. South Canal from Km. 0.00 to Km. 84.00 by providing C.C. Lining for Bed and Sides to carry adischarge of 1825 Cusecs against the present Capacity of 1342 Cusecs.
The Administrative Approval has been accorded by the Government for Rs.124.41 crores vide G.O.Ms. No. 48 I&CAD (PW-Maj. IX) Dept.Dated : 01.03.2007.
The works are proposed to be taken up in 2 Packages viz Package No.43 & 44.
3. TBPHLC System (Stage-II)
Subbaraya Sagar Balancing Reservoir (S.S.B.R)
Preamble
Subbaraya Sagar Balancing Reservoir (S.S.B.R) has been constructed across local vagu near Kadavakallu (v), Tadipatri Mandal,Ananthapuramu District. Subbaraya Sagar Balancing Reservoir is a percolating tank which exits at the tail end of Mid Pennar South Canal with a capacityof 0.42 TMC. This reservoir feeds water to 29th distributory of Mid Pennar South Canal and to Tadipatri Branch Canal.
Salient Features
Location:
Longitude: 77° 53' 21'' ELatitude : 14° 48' 54'' N
Ayacut : No direct ayacut is contemplated. Intended to stabilize the ayacut under Tadipatri Branch Canal and29th distributary of M.P.South Canal
Mandals Benefitted : Putluru, Tadipatri, Yellanuru, PeddapappuruDependable Net Yield : Insignificant. It is only a Balancing Reservoir.
Water Allocation : 0.420 T.Mcft. of Tungabhadra water is intended to be stored at the reservoir to stabilize the ayacutunder T.B.C and 29th distributary of M.P.S.C
Maximum Flood Discharge : 2100 Cusecs
Mutchukota Balancing Reservoir (M.B.R)
Location : Mutchukota Balancing Reservoir (M.B.R) has been constructed across local vagu near Mutchukota(v), Tadipatri Mandal, Ananthapuramu District.
Longitude : 77° 52' 16'' ELatitude : 14° 49' 37'' NAyacut : No direct ayacutis contemplated. Intended to stabilize the ayacut under Tadipatri Branch Canal.Mandals Benefitted : Putluru, Tadipatri, Yellanuru, PeddapappuruDependable Net Yield : Insignificant. It is only a Balancing Reservoir.
Water Allocation : 0.668 T.Mcft. of Tungabhadra water is intended to be stored at the reservoir to stabilize the aycutunder Tadipatri Branch Canal.
Maximum Flood Discharge : 2870 Cusecs
The Guntakal Branch Canal (G.B.C) System
Location : The Guntakal Branch Canal (G.B.C) System takes off from H.L.M.C at Km. 181.136.Ayacut : 32,063 AcresMandals Benefitted : Vidapankal, Uravakonda, Guntakal, Gooty.
Water Allocation : 4.52 T.Mcft. of Tungabhadra water is allocated for Guntakal Branch Canal (G.B.C) and Gooty Sub-Branch Canal (G.S.B.C) in Ananthapuramu District.
Details Of The Canals G.B.C G.S.B.CLength 59.40 Km 8.41 Km
Mandal No. Of Vilages Mandal No. Of VilagesUravakonda 2 Guntakal 5Vidapanakal 11 Gooty 15Vajrakaruru 6 Pamidi 2
Total 19 Total 22
ONGOING MAJOR IRRIGATION PROJECTS
TBPHLC SYSTEM (Stage-II)
1. Penna Ahobilam Balancing Reservoir (DR. KS. P.A.B.R)
Preamble
The Penna Ahobilam Balancing Reservoir is located across River Pennar near Korrakodu (v), Kuderu Mandal, Ananthapuramu District. It isintended to store 11.10 T.Mcft. to provide irrigation facilities to 1.00 lakh acres (50,000 Acres under P.A.B.R. Right Canal and 50,000 Acres under Yadiki
Canal System). In addition, it is intended to feed tanks enrout P.A.B.R. Right Canal and driking water facility to the Chronically drought prone uplandareas in Ananthapuramu District.
Salient Features
Location :Latitude : 14° 47' 26" NLongitude : 77° 17' 57" ECatchment area : 6165 Sq.Km(2420 Sq.Miles)Deep river bed level : 400.0 mDeepest foundation level : 399.5 mMaximum Flood Discharge : 4596 CumecsF.R.L. : 443.000 mTop Level of Dam : 446.0 mGross capacity at F.R.L. : 11.100 TMCftLive storage at F.R.L : 10.740 TMCftWater spread area at F.R.L : 27.56 M.Sq.m(296.5 M.Sq.ft)Length of Spillway : 101.44 mTotal length of dam : 1920 mCrest level of spillway : 434.34 m(1424.6')No. and size of spillway gates : 101.44 mSill level : 423.000 mPower generation : 2 Units of 10 MW each Kaplan Turbines 15400 B.H No.s 10 MW each
Irrigation potential:
It is intended to provide irrigation facilities to 1.01 lakh acres (50,000 Acres under P.A.B.R. Right Canal in addition to stabilization of ayacut7,500 acres under tanks enroute and 51,600 Acres under Yadiki Canal System).
Dam : All the Dam works are almost completed except erecting of Gantry Crane and certain rehabilitation works (Drilling and Grouting toprevent leakages). An amount of Rs. 13.50 Crores is necessary to complete the above works.
PABR Right Canal :
The PABR Right Canal has been taken up in 1978 to provide irrigation facilities to an extent of 50,000 Acres to serve in Kuderu,Singanamala, Anantapur, Raptadu, Dharmavaram and Tadimarri Mandals of Ananthapuramu District in addition to stabilization of ayacut of 7,500 acresunder tanks enroute.
Longitude : 77° 17' 57'' E
Latitude : 14° 47' 26'' E
Contemplates irrigation facilities to an extent of 5000 acres to serve 7 mandals in Ananthapuramu district in addition to stabilization ofayacut of 7500 acres under M.I tanks.
The works are almost completed except distributory network. It is estimated that Rs. 20.00 Crores is necessary for physical completion of allbalance works to provide contemplated benefits.
Yadiki Canal system is intended to provide Irrigation facilities to an ayacut of 50,000 acres I.D. during Rabi season by utilising 5 TMCft ofwater to be stored in P.A.B.R. to benefit arid areas of Yadiki, Peddavadugur, Peddapappuru and Tadipatri Mandals of Ananthapuramu district.
Pendekallu Balancing Reservoir to a capacity of 0.65 TMC is constructed at Pendekallu village, Peddapappuru Mandal, Anantapur District.
Ayacut : Creates I.P. of 18500 acresMandals Benefitted : Peddapappuru and Tadipatri
Chagallu Barrage
Preamble :
Chagallu Barrage is constructed to a capacity of 1.50 T.Mcft at Chagallu village, Peddapappuru Mandal, Ananthapuramu District.
Ayacut : Creates an I.P of 4500 acresMandals Benefitted : Peddapappuru and Tadipatri
2. Handri Neeva Sujala Sravanthi Project
Preamble :
The Anantha Venkata Rami H.N.S.S. Project is conceived to provide irrigation facilities to 6.025 Lakh acres (Khariff ID) in the four districtsof Rayalaseema and supply of drinking water to about 33 Lakh People, utilizing 40 TMC of flood water from the Krishna River. This flood water is to bedrawn from the foreshore of Srisailam reservoir with an approach channel of 3.4 Kms length and the Main canal runs for a length of 565 Kms. Water is to
be drawn during the 120 flood days from August to November. This scheme involves lifting of water in 8 stages in Phase-I Main Canal and 4 stages onPhase-II main canal with a total lift height of 369.83m, excavation of 5 Nos. of tunnels for a total length of 13.05 Kms and formation of 8 balancingreservoirs enroute.
The water utilization proposed under the project is as follows:-
2 Drinking water supply to the Urbanand Rural areas enroute the canals 4.00 TMC
3 Evaporation losses under balancingReservoirs 1.70 TMC
Total 40.00 TMC
Four branch canals namely, Peruru Branch Canal, Madakasira Branch Canal, Punganur Branch Canal and Niva Branch Canal are proposedalong the main canal. Three distributories Viz., Atmakur, Thamballipalli and Vayalpadu are also proposed along the main canal.
The Ayacut proposal under Four Districts is as follows:
Intake Location : Foreshore of Srisailam Reservoir near Malyala(V) Nanchikotkur(M) Kurnool(Dt)Canal bed level at starting point atMalyala(V) (-1.922 km) : 261.450 m
Canal F.S.L at starting point : 266.150 mCanal Section : 16.00 m & 4.70 mHead Discharge of main canal : 5820 cusecs (164.803 Cumecs)Pumping period : 120 days (Aug. to Nov. in a year) (as per approved HP's)The total project cost is Rs.6850.00 Crores. In view of the enormity of the total project, it is contemplated to take up the scheme in 2 Phasesi.e., HNSS Phase-I(Rs.2774.00 Crores) and HNSS Phase-II.(Rs.4076.00 Crores)Administrative approval for Phase-I : Rs: 1305 CroresRevised Administrative approval forthe Phase-I : for Rs.2774 Crores
Administrative approval for the -Phase-II : Rs:1880 Crores
Description Reach @ Km.(-) 4.806 Reach @ Km.(+) 0.392Discharge Designed in cumeces 164.803 114.526Discharge Required in cumeces 163.5 109.000Bed width in Meters 16.00 9.50FSD in metes 4.70 4.70Surface fall 1 in 4000 1 in 6000Side slopes 2:1 1.5:1Velocity in m/sec 1.38 1.472Value of 'n' 0.018 0.018Bed level @ start in m 253.00 287.235FSL @ Start in m 257.700 291.935
HNSS Project Phase-I (Kurnool and Ananthapuramu Districts)
HNSS Project Phase-I, starts near Malyala(v), Nandikotkur(m), Kurnool District and contemplates lifting 14 TMC of water from Krishnariver in 9 lifts (including Muchchumarri Lift ) ranging from 24 to 31.20m height, including construction of 3 reservoirs on main canal, and to conveythem through HNSS canal of 216.00 Kms length connecting to the pump houses, to provide irrigation facilities to 1.98 lakh acres in Kurnool andAnanthapuramu Districts besides providing drinking water to a population of 10 lakh in 144 villages. One Branch canal i.e., Peruru Branch Canal (80,600Acres) with 3 lifts is included in Phase-I. Ayacut proposed under HNSS Phase-I is 1,98,000 acres
Kurnool district : 80,000 acresAnantapur district : 1,18,000 acres
Total : 1,98,000 acres
Main component works
1. HNSS Main Canal Starts from Lifting of Water from Foreshore of Srisailam Reservoir Near Mallyala Village to Jeedipalli Reservoir 216.300 Km.
2. Pumping Stations :2 Nos. in foreshore of Srisailam7 Nos. on HNSS Main canal3 Nos. on Peruru Branch Canal.
The work of Phase-I are taken up under EPC turnkey system in 23 Packages (Civil works) and the main canal works from Km.(-) 3.40 toKm.216.300 i.e., up to Jeedipalli Reservoir were completed and distributory works are in progress. The works of Mechanical package works (lifts) are atcompletion stage.
HNSS Phase-II (Anantapuramu, Kadapa and Chittoor Districts):
The Phase-II of the project involves
The 5 Reservoirs are proposed in Phase-II as follows
1.Gollapalli Reservoir(Anantapuramu Dist)
2.Cherlopalli Reservoir (Anantapuramu)
3.Marala Reservoir(Anantapuramu Dist)
4.Srinivasapuram Reservoir (Kadapa Dist)
5.Adivipalli Reservoir(Chittoor Dist).
Ayacut Contemplateda) Anantapuramu District : 2,27,000 Acresb) Kadapa District : 37,500 Acresc) Chittoor District : 1,40,000 Acres
i) HNSS Main canal runs from 216.300 Km to 565.000 Km with 3 lifts
ii) Number of Branch canals and distributaries.
1) Madakasira Branch Canal (Anantapuramu)
2) Punganur Branch Canal (Chittoor)
3) Thamballapalle Canal (Chittoor)
4) Vaylpadu Canal (Chittoor)
5) Neeva Branch Canal (Chittoor)
iii) Requirement of Power for lifts in Phase-II: 228.76 MW.
iv) Reservoirs in Phase-II
Gollapalli Reservoir (Anantapuramu) : 1.610 TMC
Cherlopalli Reservoir (Anantapuramu): 1.425 TMC
Marala Reservoir (Anantapuramu) : 0.464 TMC
Srinivasapuram Reservoir (Kadapa) : 0.354 TMC
Adivipalli Reservoir (Chittoor) : 1.100 TMC
HNSS Project In Anantapuramu District
(a) Ananthapuramu District:- Phase-I:
Jeedipalli Reservoir
Preamble
The HNSS Main Canal enters in Anantapur district at Ch Km 143.825 and ends at Km 216.300 ( Total length :72.475 Kms).The works underPhase-I of Anantapuramu District are nearing completion in packages 30 to 34 i.e., from Km 114.000 to Km 210.000. The work of construction ofJeedipalli Reservoir is completed in Package No. 35 and water stored in the Reservoir up to F.R.L (1.686 T.M.C) during 2103-2014. Peruru Branch canalto a length is 6.07 km to feed an ayacut of 80,600 Acres is taken up under Package No. 36.The total ayacut proposed under Phase-I in Anantapur Districtis 1,18,000 Acres.
The Phase-II of HNSS in Anantapur District commences at Km 216.300 and ends @ Km 463.000(total length :246.700 km).It is proposed toprovide irrigation facilities to a tune of 2,27,000 Acres and drinking water facilities to 16 Lakh People covering 257 villages in Anantapur District. In thisphase 9 Packages works and one Mechanical Package work is under progress and 5 Packages taken up in Mandakasira Branch Canal to a length is 151.04km to feed an ayacut of 38,000 Acres in Anantapuramu District. Phase-II works in Anantapuramu district were taken up under 15 Packages Such asPackage no: 1,2,3,4,5, 7,12,13, 17, 54,55,56,57,58 and one Mechanical package.
Salient Features
Location : Near Marala, Bukkapatnam (M)Longitude : 77° 56'ELatitude : 14° 18'NFRL : (+) 445.00mCross capacity : 0.483TMC(13.68M Cum)Live capacity : 0.465 TMC(13.16 M.Cum)Dead Storage : 0.018 TMC (0. 520 M Cum)Ayacut : H.N.S.S Main canalCropping pattern in nantapuramuDist : Ground nuts, Millets, sunflower and pulses.
Pump House
No. of lifts in Anantapuramu Dist. : 2 Nos. on main canal (1) Ragulapadu Lift @ Km.173.837, Height of lift=33.91m &(2) Jeedipalli Lift @Km.216.300
Pumps : 12 Nos. of Pumps proposed at pumping station at Ragulapadu lift (point No.8) @ Km.173.837. & 8 Nos Pumps atJeedipalli Pumping station.
Water User Association details and ayacut under TBP HLC system
S.No Name of the Irrigation system in Ananthapuramu district No. of PC's No. of DC's No. of WUA's Total Ayacut (acres)1 High Level Main Canal (Stage - I)
Upper Pennar Project was constructed across Pennar River near Peruru Village in Ramagiri Mandal in Ananthapuramu District and it wasconstructed across River Pennar in 1956 having an ayacut of 10,048 Acres under left and right flank main canals.
Salient Features
Location : Upper Pennar Project constructed across the Pennar river near Peruru Village in Ramagiri Mandal inAnanthapuramu District.
Details Of The Canals RF CANAL LF CANALLength 24.60 Km 5.79 Km
Discharg e 245 cusecs 12.71 cusecsAyacut in Acres 9448 Acres 600 AcresCropping Pattern Paddy, Goundnut Paddy, Goundnut
Villages benefited:
1) Peruru
2)Maddalacheruvu
3)Thogarakunta
4)K.N.Palyam
5) Gunthapalli
6)Gandlaparthi
7)Thumucherla
8)Palacherla
2. Pennar Kumudvathi Project (P.K.PROJECT)
Preamble
This is a diversion scheme constructed across Pennar River 0.80 Kms down stream of confluence of the Pennar and Kumudvathi Rivers.ThisProject envisages supplementation of water to 7 tanks enroute both Left & Right side canals of the project and it was constructed during the year 1948 -1956 across Pennar River half a mile below the confluence of the Pennar and Kumudvathi River.
This is constructed prior to construction of Pennar Kumudvathi Project across Jayamangali river to divert water through a old 4KMS lengthof supply channel to Parigi tank. But, after completion of Pennar Kumudvathi Project Jayamangali anicut is connection with a new channel of 6.2 KMlength from the head sluice.
3. Bhairavanithippa Project
Preamble
This project is located in Gummagatta Mandal near border of Karnataka and Andhra Pradesh states, across Vedavathi River (also calledPedda Hagari River) in Krishna basin and it was constructed across River Hagari during 1955 to 1961 with a designed localization pattern of 12,000Acres in both left and right flank main canals.
Salient Features
Latitude : 14° 32' 10''Longitude : 76° 50' 30''
Levels : FRL in Mts 504.440, MDDL in Mts 497.738, TBL in Mts 506.550 Left Canal Starting: 497.738,Ending: 491.846, Right Canal Starting :497.738, Ending 493.717
This project is constructed across river Maddileru which is a tributary to Chitravathi River. This project is located near Adavibramhana palliThanda, of about 9KM from Mudigubba and was Constructed across the Maddileru river (Tributory to Chitravathi River) was completed with a year 2001with an ayacut under this project 12,880 Acres both left and right flank main canals.
Salient Features
Latitude : 14° 21' 25''Longitude : 78° 08' 13''
Levels : FRL in Mts 383.000, MDDL in Mts 377.505, TBL in Mts 386.450 Left Canal Starting: 376.745,Ending: 359.880, Right Canal Starting : 376.845, Ending: 337.700
Capacity : FRL M.cum 25.845, MDDL in M cum 8.495Ayacut : 12,880 AcresMandals Benefitted : MudigubbaUtilisation : 0.600 TMCMaximum Flood Discharge : 1,25,190 Cusecs
Details Of The Canals Right CANAL Left CANALLength 19.815 KM 20.97 KM
Formation of new M.I tank across Jilledubanda vagu near Guddampalli thanda of Gunjepalli (V) Mudigubba(M)
Preamble
This tank is being constructed across Jilledubanda vagu which is a tributary to Maddileru river and is located in Pennar basin. The total costis Rs.1146.01 Lakhs including LA for head works. The head works is taken up at a cost of Rs. 598 Lakhs for head works during 7/2004.
The head works are almost completed. The contractor has stopped the work. The balance work is proposed to be taken up as per clause 60 ofAPDSS and no contractor is coming forward to do the work at the old rates. The Revised Estimate is submitted to Chief Engineer, Minor Irrigation,
Hyderabad for obtaining Revised Administrative approval. The Land Acquisition for canals is under process. Soon after completion of Land Acquisition,estimates will be prepared and submitted to Chief Engineer, Minor Irrigation, Hyderabad for obtaining administrative approval.
Land Acquisition
An amount of Rs.75.66 lakhs has been deposited with the revenue department for acquiring an extent of 336.07 acres for Head works and LAcompleted. Rs. 16.00 lakhs was deposited with the Revenue Department for acquiring an extent of about 118 Acres of Land for Left side and right sidecanals. The Land Acquisition is under process.
Status Report On Groundwater Resources And Activities Of Groundwater Department In Anantapuramu District-August-2014
The Ground Water Department is Carrying out integrated Hydrogeological & Geophysical surveys for selection of different wells both forirrigation as well as Drinking water for District Agencies such as Scheduled Caste Corporation, BC Corporation, DRDA, DWMA, APSCRIC, PR, MI,RWS Departments and Private Parties on their request. In addition to this the Department is carrying out of Surveys for the selection of sites forconstruction of Artificial Recharge Structures like check dams/Percolation tanks.
Under APWALTA Groundwater surveys were carried and 17 sites recommended out of 4 sites surveyed; 34 sites recommended out of 89sites surveyed under SCP; 5 sites recommended out of 14 sites surveyed under TSP; 35 sites recommended out of 65 sites surveyed under drinkingschemes; 13 sites recommended out of 15 sites surveyed for sectoral offices; 3 sites recommended out of 3 sites surveyed for Environmental Clearance. 7sites recommended out of 18 sites surveyed under check dams for the financial year - 2014-15.
Ground Water resource available, Utilization and stage of utilization based on Groundwater estimation in 2010(Base Year 2010-11)
The total Groundwater resource available is 1,44,156 Ha.m (50.87 TMC). Utilization is 1,14,182 Ha.m (40.29 TMC). The available balanceis 29,974 Ha.m (10.57 TMC).
The stage of Groundwater development (Utilization) is 79% and categorized as semi critical.
62% Mandals (39) are categorized as Groundwater stress areas falling in over exploited (OE) (21) ; critical (2) ; semi critical (16) categoriesand only 38% Mandals (24) are in safe category.
Categorization of Mandals
Over Exploited (OE)Mandals (utilization more than 100%): 21 Mandals-Agali, Am adaguru, Amarapuram, Bathalapalli, Brahmasamudram,Gandlapenta, Hindupur, Kalyandurug, Kambadur, Kothacheruvu, Kundurpi, Lepakshi, Madakasira Parigi, Peddapappur, Putlur, Rolla, Tadimarri,Tadipartri, Yadki and Yellanur.
Critical (C)Mandals (utilization between >90 to 100%): 2 mandals-Roddam and Talupula.
Semi-Critical (SC)Mandals (utilization between 70 to 90%): 16 mandals-Beluguppa, Bukkapatnam, Dharmavaram, Garladinna, Gudibanda,Gummagatta, Kanaganapalli, Kudair, Narpala, O.D.Cheruvu, Penukonda, Puttaparthi, Rapthadu, Rayadurgam, Somandepalli and Tanakallu.
Safe (S) Mandals (utilization less than 70%): 24 Mandals-Ananthapuramu, Atmakur, Bukkaraya Samudram, Bommanahal, C.K.Palli,Chilamathur, D.Hirehal, Gooty, Gorantla, Guntakal, Kadiri, Kanekal, Mudigubba, N.P.Kunta, Nallacheruvu, Nallamada, Pamidi, Peddavaduguru,Ramagiri, Settur, Singanamala, Uravakonda, Vajrakaruru and Vidapanakal.
Statement showing the Tank Wise ayacut particulars Constituency, Mandal wise Water Users Associations (WUA) - Minor Irrigation
Report On Ground Water Level Scenario In Anantapuramu District Based On Water Level Recorded From Piezometers During August-2014
Introduction
Ground Water Department is monitoring the changes in ground water regime continuously through a network of OB Wells from June-1974and piezometers from 1997. Total 73 piezometers were constructed in the District. The piezometric Groundwater levels of the district are monitoredthrough automatic water level recorders and manual and the fluctuations noticed seasonally and annually are analysed in relation to rainfall, rechargemeasures, drought and extraction of ground water in the area. The water level data collected in the month of August-2014 is analysed and compared withearlier periods for studying the seasonal and annual fluctuations in water level in relation to rainfall continuously.
Rainfall
Rainfall is the principal source of ground water recharge. The behaviour of ground water table is essentially governed by rainfall, it's quantity,intensity, duration and frequency.
Rainfall deviation in the mandals during 2014-15 Water year (up to August-2014)
Sl.No. Rainfall Deviation No of Mandals1 EXCESS (20%& above) 32 NORMAL (+19% to-19%) 153 DEFICIT (-20% to-59%) 334 SCANTY (-60% to -99%) 125 NO RAINFALL(-100) 06 TOTAL 63
Revenue division wise average rainfall recorded during 2014-15 Water year (STATEMENT II) (up to August-2014)
S.No Revenuedivision
Cumulative Normal Rain fall upto August in 'mm'
Cumulative Actual Rain fall during water year2014-15(up to August in'mm'
The depth to ground water level recorded in August-2014ranges from 3.90m to 71.18m. The shallowest water level is recorded in thepiezometer at P.K.Cheruvu(v), Guntakal (M) where as the deepest water level is recorded in the piezometer of Madhudi (v), Agali (M).
Water levels in the range of 2 to 5m.bgl are prevailed in 2 of the piezometers monitored during August-2014 where as 2 piezometers fall inthis range in August-13.
Water level in the range of 5m to 10m. bgl. are noticed in 8 of the piezometers monitored during August-2014where as 9 piezometers fall inthis range August-13.
Moderate depth to water level in the range of 10 to 20m.bgl. is observed in 19 of piezometers monitored during August-2014, where as 18piezometers fall in this range in August-13.
Deeper water levels in the range of 20-30 m bgl are recorded in 21 of piezometers monitored during August-2014, where as 21 piezometersfall in this range in August-13 in the district.
Deepest water levels of more than 30 m bgl are recorded in 7 piezometers monitored during August-2014 where as 7 piezometer falls in thisrange in August-13.
The district has an average water level of 20.47 m.bgl. (Plate-I,II).
Zoning of areas as per depth to ground water table: (August-2014)
(STATEMENT-I)& (STATEMENT-II)
The Study of depth to water level of August-2014 indicates deep water levels more than 20m. are observed in major parts of Kalyanadurgam,Penukonda, Anantapuramu,Kadiri Divisions.
Zones of moderate ground water levels of 10 to 20m deep are noticed in most parts of, Kalyanadurgam Kadiri, Anantapuramu, Penukonda,Divisions.
Water levels zones of 5 to 10m. are observed in most parts of Kalyanadurgam division , Darmavaram, Anantapuramu Divisions.
Shallow ground water levels less than 5m are observed in some parts of Ananthapuramu, Division.
Ground water level fluctuation of August-2014 in comparison with May-14(Seasonal): (STATEMENT-I)
Rise in water levels was observed in 9 piezometers in the district covering 2 piezometers of Ananthapuramu division, 1 piezometers ofDharmavaram division, 1 piezometers of Kadiri division, 5 piezometers of Kalyanadurgam.
Fall in water levels levels was observed in 48 piezometers in the district covering 15 piezometers of Penukonda division, 12 piezometers ofAnanthapuramu division ,8 piezometers of Kalyanadurgam division, 5 piezometers of Dharmavaram division and 8 piezometers of Kadiri division.
Comparison of water level fluctuation of August-2014 and August-2013 (Annual): (STATEMENT)
Rise in water levels was observed in 23 Piezometers in the district covering 7 piezometers of Ananthapuramu division, 2 piezometers ofDharmavaram division, 10 piezometers of Penukonda division, 1 piezometers of Kalyanadurgam division and 3 piezometers of Kadiri division.
Fall in water levels levels was observed in 21 piezometers in the district covering 5 piezometers of Ananthapuramu division, 4 piezometers ofPenukonda division, 7 piezometers of Kalyanadurgam division and 2 piezometers of Kadiri division,3 piezometers of Dharmavaram division.
Conclusions
(STATEMENT-I)In the present water year 2014-15, Ananthapuramu district has a normal rainfall of 220.0 mm up to August-2014. It hasreceived 144.3 mm (34% deficit) rainfall in the water year 2014-15, where as it was 206.5 mm (6% deficit) during the same period in the previous wateryear. The net fall of water level from August-2014 and August-2013 is 0.88m, which is due to excess rainfall in the current year, than the previous year.
Ananthapuramu division:- has a Normal rainfall of 222.3 mm up to August-2014, It has received 157.8 mm (29 % deficit) rainfall in thewater year 2014-15, where as it was 239.4 mm (8% excess) during the same period in the previous water year and observed a fall in water level of 0.15 min the water level, which which is due to over exploitation on usage of ground water.
Dharmavaram division:- has a normal rainfall of 210.8 mm up to August-2014, where as it has received 123.5mm (41% deficit) rainfall inthe water year 2014-15, and it was 184.9mm (12% deficit) during the same period in the previous water year and observed a rise in water level of 1.23min water levels which is due to less exploitation on usage of ground water.
Kadiri division:- has a normal rainfall of 233.7 mm up to August-2014, it has received 129mm(45% deficit) rainfall in the water year 2014-15, where as it was 243.3 mm (4% excess) during the same period in the previous water year and observed a rise in water level 1.70 m which is due toless exploitation on usage of ground water.
Kalyanadurg division:- has a normal rainfall of 209.8 mm up to August-2014, it has received 180.5 mm(14% deficit) rainfall in the wateryear 2014-15, where as it was 164 mm (22% deficit) during the same period in the previous water year and observed a fall in water level of 0.27 m whichis due to over exploitation on usage of ground water.
Penukonda division:- has a normal rainfall of 218.2 mm up to August-2014, it has received 120.7 mm(45% deficit) rainfall in the water year2014-15, where as it was 174 mm (20% deficit) during the same period in the previous water year and observed a rise in water level of 1.11m which isdue to less exploitation on usage of ground water.
Ground Water resource available, Utilization and stage of utilization based on Groundwater estimation in 2010(Base Year 2010-11):
The total Groundwater resource available is 1,44,156 Ha.m (50.87 TMC). Utilization is 1,14,182 Ha.m (40.29 TMC). The available balanceis 29,974 Ha.m (10.57 TMC).
The stage of Groundwater development (Utilization) is 79% and categorized as semi critical.
62% Mandals (39) are categorized as Groundwater stress areas falling in over exploited (OE) (21) ; critical (2) ; semi critical (16) categoriesand only 38% Mandals (24) are in safe category.
In this situation the need of the hour is 1) To harvest the rainfall run-off and recharge the groundwater body and 2) Judicial use/Efficient useof Groundwater in water stressed areas i.e., Over exploited (OE), Critical, Semi Critical areas to mitigate the drought situation effectively.
1) Harvesting of rainfall runoff:-
a) Renovation of existing water bodies to restore the original storage capacity by I & CAD and DWMA.
b) Tank desilting by Water Resources Department, DWMA under MGNREGS.
c) On farm water harvesting through farm ponds by DWMA & Agriculture Department.
d) New water harvesting structures i.e., check dams, percolation tanks etc by DWMA and I & CAD Departments.
2) Judicial use/Efficient use of Groundwater:-
a)Change in cropping pattern as suggested by Agriculture and Horticulture Department.