I. INTRODUCTION Spurred by regulators, financial institutions have invested significant resources in risk management over the last decade. An actuarial statistical approach to estimates future losses based on past experiences was used to create an illusion of control. Unfortunately, markets are not actuarial tables. The magnitude of the error became apparent once the crisis unfolded. For example, Citibank is VAR, value at risk, at the end of 2007 was $190 mln. This means the maximum it could lose over a 1 day period at the 99% confidence level was $190 mln. Citi’s actual 2008 losses exceed $40 B. Other institutions with similar experiences include Merrill, Wachovia and Washington Mutual. These losses triggered massive shareholder value destruction resulting in dilutive recapitalizations and replacement of whole managements. Clearly, something is wrong with the current state of risk management requiring a rethinking of the activity. 1
22
Embed
I. INTRODUCTION Spurred by regulators, financial institutions have invested significant resources in risk management over the last decade. An actuarial.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
I. INTRODUCTION
Spurred by regulators, financial institutions have
invested significant resources in risk management over
the last decade. An actuarial statistical approach to
estimates future losses based on past experiences was
used to create an illusion of control. Unfortunately,
markets are not actuarial tables. The magnitude of the
error became apparent once the crisis unfolded. For
example, Citibank is VAR, value at risk, at the end of 2007
was $190 mln. This means the maximum it could lose
over a 1 day period at the 99% confidence level was $190
mln. Citi’s actual 2008 losses exceed $40 B. Other
institutions with similar experiences include Merrill,
Wachovia and Washington Mutual. These losses triggered
massive shareholder value destruction resulting in dilutive
recapitalizations and replacement of whole managements.
Clearly, something is wrong with the current state of risk
management requiring a rethinking of the activity.
1
INTRODUCTION (continued)
Institutions had moved further out on the curve
to maintain normal income growth. Risk was deemed
under control based on the twin illusions of liquidity and
risk distribution. In fact, rather than distribute risk, they
had concentrated risk. Liquidity evaporated once their
leveraged positions began losing value.
This article explores why this occurred and what
can be done to remedy the situation. What is needed is to
move risk management away from a hyper technical,
specialist control function with linkage to creation.
Instead, we need to move beyond risk measurement to
integrate risk into strategic planning, capital management
and governance. Enterprise risk management ERM,
provides the framework to integrate these functions.
functions tent to operate as independent silos with
little or no strategic connection. Additionally, there is
limited consideration of business models and market
states when evaluation transaction risks. Literally, it is
failing to see the forest because of the trees. What is
needed is the integration of risk into strategic
planning, capital management and performance
measurement. This would combine business and risk
considerations into a single, whole-firm view of value
creation.
6
VALUE IMPLICATIONS OF RISK APPETITE CHANGES
Figure 1
CEfficient frontier
for business portfolio
Beta
Return
A = Current position
A B = Value destruction–Uncompensated risk
C = Target position – no value change
Zeta (value loss)
B
Risk
Alpha (value creation)
Capital requirement
7
D = True value creation
D
III. RISK STRATEGY FRAMEWORK
Financial institutions have invested heavily in risk
management. Yet, there is surprisingly little agreement
concerning the value proposition of risk management. Value is
created on the left hand side (LHS) of the balance sheet through
investment decisions. The value of risk is to ensure funding of
the investment plan by maintaining capital market access under
all conditions. This entails maintaining a total risk profile
consistent with r?????? targets. This requiring balancing LHS
asset portfolio risk with right hand side (RHS) capital structure.
Failure to do so can under mind the institutions strategic
position and independence. Examples include Citi and Lehman.
Viewed as such, risk management is a capital structure
decisions linking strategy and capital levels. Risk management
needs to support the institution’s corporate strategy, which
determines the risk universe faced by the bank organization as
outlined in Figure 2. Then, using traditional underwriting,
mitigation and transfer risk management techniques, you
determine those risks which the institution is competitively
advantaged to own and eliminate the reset. For example: local
8
III. RISK STRATEGY FRAMEWORK(continued)
institutions have an informational advantage regarding
evaluations of local clients. Thus, they should retain such
risk up to prudent concentration levels. Alternatively, risks
like interest rate risk, not be held unless the institution
possesses special information. Then, the retained risk would
be covered by capital consistent with a ratings goal, most
likely investment grade, to ensure capital market access
sufficient to fund the investment plan (see Figure 3). Viewed
in this light, risk management and capital can be seen as
interchangeable with capital being the cost of risk. In fact,
risk management is essential synthetical equity. Equally,
capital can be seen as substitute to risk management. The
key is to avoid a mismatch between the LHS and RHS of the
balance sheet.
The overall institutional risk level is dependent on
their risk appetite – the level of risk the organization is willing
to assume on both sides of their balance sheet in the pursuit
of their strategy. Risk
9
III. RISK STRATEGY FRAMEWORK(continued)
appetite is a relative term among stakeholders.
Usually aligned, there are instances when
management and stakeholder appetites differ, usually
leading to new management. Management risk
appetite is best expressed as a con???? as reflected in
Figure 4. The relevant risk constraint for most
managers is being replaced.
Unfortunately, many financial held large
amounts of risk in which they had limited competitive
advantages. This beta risk, while increasing nominal
income, failed to create shareholder value.
10
11
Need for financial flexibility
Risk management strategy
Corporate Strategy
Investment plan and opportunities
Business Model Operating cash flow forecast
volatility Frequency
US$ millions
Stakeholder(Investors,
Regulators and Rating Agencies)
perspective
Financial structure impact
And Ratings target
Cost of financial flexibility
12
3
4
Adapted from T. Oliver Leautier, Corporate Risk management for Value Creation(Risk Books, 2007)
DRIVERS OF RISK MANAGEMENT STRATEGYFigure 2
Figure 3 Connect Capital and Risk
to Investment Strategy12
Figure 3 Connect Capital and Risk to Investment Strategy
Risk and capital as inputs into strategic planning:Choice of Markets with attractive economics in which the organization enjoys a competitive advantage
Risk the organization is willing and able to accept in pursuit of its strategy
R/A level retention types capital buffer
Risks underwritten and retain comparative advantage
Capital relative to Rating Agencies, Regulators and Peers
Actual Physical Capital
Return capital to shareholders when actual capital exceeds need, or raise capital when need exceeds actual capital
Allocation to business units based on an economic capital determination
Strategy
Risk Appetite
Risk Assessment
Capital need
Capital Assessment
Capital Plan
Capital Allocation
Return on capital relative to cost of capital total risk facing firm risk appetite risk to be transferred net risk vs. capital need/level
??????
… and not just consequences
Which markets
How much risk
determines ?????
What type of risks based on
??????
How much capital do we
need vs. have?
Capital Assessment
Risk Appetite ContinuumFigure 3
13
Profit / Loss Distribution
Profit Warning – National city
Rating Watch – Fifth Third
Dividend cut – Citi
Downgrade – Morgan Stanley
Raise capital – Merrill
Management replaced – Prince, O’Neil Regulatory Action – Cease and Desist, Memorandum of Understanding
Failure – Bear, Lehman, WaMu
Risk Appetite ContinuumFigure 3
- 0 +
Probability
Profitability
14
Risk Appetite
Reconciled by Board
External Stakeholders
InternalStakeholders
CEO: Investment StrategyRegulators
Shareholders Agencies
Internal Risk AppetiteExternal Risk Appetite
CFOHow muchCapital do
I need
CROWhat Risks
Do IRetain
AssetPortfolio
CapitalManagement
CapitalRequired
CapitalAvailability
Capital Structure
RiskStructure
Value Creation
Economic Capital
(Use)
15
Risk Appetite Strategy Earnings Ratings
Business Model Strategic Objectives Annual Goals
Organizational Culture structure Shareholders
Risk Assessment
Risk Analysis
Risk Strategy
Infrastructure
Risk Identification
The ERM Funnel – Figure 7
P. Sobel, Auditor’s Risk Management Guide: Integrating Audit and ERM (CCH, 2007)
16
ExternalStakeholders
Regulators
Shareholders Rating Agencies
Assets(Return)
CapitalRequired(Risk)
CapitalAvailability/(Funding)
CapitalManagement
Value Creation
Portfolio ofEnterprise Risks
Portfolio ofCapital Resources
Capital Structure
Cost of Capital
Return onRisk
Risk Structure
Economic Capital(Use)
Match Internal/External
Risk Appetite
…You can lose money
External Risk Appetite
Not always in balance
17
Price
Time
Panic
Normal
Offer
Bid
Figure 5Asset Price Liquidity
DAR Control Framework
Asymmetric Information Behavioral Bias ControlAdverse selection-lack Optimism Internal: Board information and chose Over confident
monitoring incorrectly Illusion of control
Incentives Moral hazard-lack Sanctions
Information on Performance DAR External Regulators