Hybrid Riser Tower Monitoring An Operations Perspective
13

Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

Sep 17, 2018

Download

Documents

duongdat
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

Hybrid Riser Tower Monitoring

An Operations Perspective

Page 2: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential

2

Key Questions

Why is riser monitoring important?

What can we do with the data?

What do we need to consider for future systems?

Page 3: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Greater Plutonio Overview

3

3

Greater Plutonio Subsea Layout

Control Umbilicals

12” Service Line

14” Northern Water Injection line

12” Southern Water Injection line

12” Gas Injection line

Riser Tower

12” Northern Production Line

12” Southern Production Loop

Offloading Buoy

DWSSM

S1

S3

S4 S2

N2

N1

N3 N4

Page 4: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential The Riser Tower Structure

4

Page 5: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential

5

Buoyancy Tank Design

• HRT designed with 814 Te buoyancy

• Buoyancy tank comprises 36 compartments.

• Four ballast compartments are filled with treated fresh water.

• HRT is designed to operate with one compartment flooded. Two flooded compartments represents a shut-in condition.

• Ballast tanks are included as mitigation of flooding threat

• Flooding of peripheral and central compartments will result in loss of tension of 400kN and 800 kN respectively.

• Flooding of compartments…

− Tension monitoring primary means of detection

− Influence of environment and operating conditions impacts attitude, bending, and global position – prevents immediate identification.

Page 6: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential

Riser Tower Monitoring Equipment

Tension Monitoring through Linear Variable Differential Transformers (LVDTs)

Attitude monitoring (6 Degrees of Freedom, IXSEA Octans)

Position monitoring (Transponder, Compatt5 Sonardyne

Hybrid Riser Tower Monitoring System

Buoyancy Tank Integrity known

Core Pipe Integrity known

Offset between FPSO and top of riser tower known

Riser Tower monitoring gives: • Assurance that it is safe to continue operating • Builds a picture of the tower’s behaviour for operating

life

Page 7: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Riser Tower Response to Operating Conditions

7

Page 8: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Detecting a Problem

• 2 key areas of concern:

− Catastrophic / sudden failure

− Slow leak

• Sudden failure will be detected by alarms, including dynamic tension alarm

• Slow leak can be seen in long term trends

8

Upp

er Te

nsio

n

Page 9: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Detecting a Problem

9

Page 10: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Obtaining the Data

• Old System:

• New System:

10

Data Offshore

Copied to CD

CD hand carried to

UK

CD posted to USA

Data Processed

Processed data sent to IM contractor

Quarterly Report issued

Data Offshore

Selected channels to ProcessNet

Data to USB stick

offshore

Offshore upload to

Sharepoint

IM contractor accesses data

Page 11: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Monitoring System Design Lessons Learned

• The monitoring system is only as good as the data you get back from it!

• Design of a monitoring system should include thought into methods for obtaining the data and what the data will be used for

• Response to offshore alarms is hindered when engineers on the beach do not have access to the data

• Redundancy and retrievable equipment is important for long term operability

• Operations input into projects system design is valuable

11

Page 12: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

BP Confidential Conclusions

Why is riser monitoring important?

• Understanding of the integrity - the riser tower is a complex system

• Safe ongoing operations, including possible field life extension

• Possible use for future design optimisation

What can we do with the data?

• Detect faults – catastrophic failures and slow degradations

• Calibrate models – useful for predicting tower behaviour

What do we need to consider?

• Data, data, data! If you’re producing good data, engineers need to be able to see it

• Redundancy and maintainability

• What are you actually looking for? A monitoring system is just one possibility…

12

Page 13: Hybrid Riser Tower Monitoring - MCEDDmcedd.com/wp-content/uploads/Leah Regel - BP.pdf · 14” Northern Water Injection line . 12” Southern Water Injection line . 12” Gas Injection

Leah Regel

Riser and Flowline Engineer

[email protected]

BP International Centre for Business and Technology

Chertsey Road

Sunbury

Middlesex

TW16 7LN

Acknowledgments: Brian O’Keefe, Woodgroup Kenny Soma Maroju, BMT