8/2/2019 Hvac Costing Bmt http://slidepdf.com/reader/full/hvac-costing-bmt 1/300 VARIABLE AIR VOLUME UNITS Variable air volume units, by pass type complete with thermostatic controller including VAV heaters, accessories, electrical connection and control wiring to complete the installation all in accordance with drawings and specifications. A VAV box 114 l/s air flow, inline 3 nr. B VAV box 117 l/s air flow, inline 4 nr. C VAV box 119 l/s air flow, inline 6 nr. D VAV box 122 l/s air flow, inline 1 nr. E VAV box 123 l/s air flow, inline 3 nr. F VAV box 127 l/s air flow, inline 1 nr. G VAV box 131 l/s air flow, inline 6 nr. H VAV box 132 l/s air flow, inline 2 nr. A VAV box 133 l/s air flow, inline 1 nr. B VAV box 138 l/s air flow, inline 6 nr. C VAV box 141 l/s air flow, inline 1 nr. D VAV box 143 l/s air flow, inline 3 nr. E VAV box 146 l/s air flow, inline 3 nr. F VAV box 148 l/s air flow, inline 4 nr. G VAV box 152 l/s air flow, inline 1 nr. H VAV box 134 l/s air flow, inline 2 nr. J VAV box 136 l/s air flow, inline 1 nr. A VAV box 154 l/s air flow, inline 1 nr. B VAV box 175 l/s air flow, inline 1 nr. C VAV box 181 l/s air flow, inline 2 nr. D VAV box 200 l/s air flow, inline 1 nr. E VAV box 210 l/s air flow, inline 1 nr. F VAV box 324 l/s air flow inline 4 nr
300

Hvac Costing Bmt

Apr 06, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 1/300

VARIABLE AIR VOLUME UNITS

Variable air volume units, by pass type complete with

thermostatic controller including VAV heaters,

accessories, electrical connection and control wiring to

complete the installation all in accordance with drawings

and specifications.

A VAV box 114 l/s air flow, inline 3 nr.

B VAV box 117 l/s air flow, inline 4 nr.

C VAV box 119 l/s air flow, inline 6 nr.D VAV box 122 l/s air flow, inline 1 nr.

E VAV box 123 l/s air flow, inline 3 nr.

F VAV box 127 l/s air flow, inline 1 nr.

G VAV box 131 l/s air flow, inline 6 nr.

H VAV box 132 l/s air flow, inline 2 nr.

A VAV box 133 l/s air flow, inline 1 nr.

B VAV box 138 l/s air flow, inline 6 nr.

C VAV box 141 l/s air flow, inline 1 nr.D VAV box 143 l/s air flow, inline 3 nr.

E VAV box 146 l/s air flow, inline 3 nr.

F VAV box 148 l/s air flow, inline 4 nr.

G VAV box 152 l/s air flow, inline 1 nr.

H VAV box 134 l/s air flow, inline 2 nr.

J VAV box 136 l/s air flow, inline 1 nr.

A VAV box 154 l/s air flow, inline 1 nr.

B VAV box 175 l/s air flow, inline 1 nr.C VAV box 181 l/s air flow, inline 2 nr.

D VAV box 200 l/s air flow, inline 1 nr.

E VAV box 210 l/s air flow, inline 1 nr.

F VAV box 324 l/s air flow inline 4 nr

Page 2: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 2/300

B VAV box 329 l/s air flow, fan assited 1 nr.

C VAV box 351 l/s air flow, inline 1 nr.

D VAV box 377 l/s air flow, inline 1 nr.

E VAV box 378 l/s air flow, inline 1 nr.

F VAV box 380 l/s air flow, inline 4 nr.

G VAV box 391 l/s air flow, inline 7 nr.

H VAV box 395 l/s air flow, fan assisted 15 nr.

J VAV box 432 l/s air flow, inline 1 nr.

A VAV box 457 l/s air flow, inline 4 nr.

B VAV box 470 l/s air flow, fan assisted 2 nr.

C VAV box 480 l/s air flow, fan assisted 3 nr.

D VAV box 491 l/s air flow, inline 4 nr.

E VAV box 566 l/s air flow, inline 1 nr.

F VAV box 650 l/s air flow, inline 1 nr.

G VAV box 669 l/s air flow, inline 1 nr.

Volume Control Damper (VCD)

Supply and install volume control damper as per

specification and tender drawings, sizes shown below

A 150 x 100 mm 6 nr.

B 200 x 100 mm 6 nr.

C 250 x 100 mm 30 nr.

D 300 x 100 mm 54 nr.

E 350 x 100 mm 18 nr.

F 350x150 mm 42 nr.

G 400 x150 mm 48 nr.

A 400 x 250 mm 36 nr.

B 450 x 150 mm 30 nr.

C 450 x 200 mm 12 nr.

D 450 x 200 mm 12 nr.

E 450 x 250 mm 12 nr.

Page 3: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 3/300

G 300 x 200 mm 5 nr.

H 300 x 250 mm 2 nr.

A 350 X 100 mm 3 nr.

B 350 x 200 mm 2 nr.

C 350 x 250 mm 1 nr.

D 400 x 150 mm 6 nr.

E 400 x 200 mm 5 nr.

F 450 x 200 mm 2 nr.

G 500 x 200 mm 3 nr.

H 500 x 250 mm 4 nr.

A 500 x 350 mm 1 nr.

B 550 x 250 mm 1 nr.

C 550 x 300 mm 1 nr.

D 550 x 350 mm 1 nr.

E 550 x 650 mm 5 nr.

F 600 x 250 mm 2 nr.

G 600 x 300 mm 1 nr.

H 650 x 250 mm 1 nr.

J 650 x 300 mm 1 nr.

A 650 x 450 mm 1 nr.

B 750 x 500 mm 2 nr.

C 800 x 350 mm 3 nr.

D 800 x 700 mm 1 nr.

E 850 x 400 mm 1 nr.

F 850 x 450 mm 3 nr.

G 850 x 550 mm 2 nr.

H 900 x 300 mm 1 nr.

J 900 x 450 mm 2 nr.

A 900 x 550 mm 1 nr.

B 900 x 600 mm 1 nr.

C 900 x 800 mm 3 nr.

D 950 x 500 mm 1 nr.

Page 4: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 4/300

F 1200 x 600 mm 3 nr.

G 1200 x 650 mm 1 nr.

H 1200 x 700 mm 3 nr.

J 1200 x 900 mm 1 nr.

A 1250 x 500 mm 1 nr.

B 1250 x 800 mm 18 nr.

C 1300 x 850 mm 2 nr.

D 1350 x 900 mm 2 nr.

E 1400 x 700 mm 1 nr.

F 1500 x 700 mm 1 nr.

G 1500 x 750 mm 1 nr.

H 1500 x 800 mm 1 nr.

J 1600 x 700 mm 2 nr.

K 1600 x 750 mm 1 nr.

Diffusers

Supply, install, test and commission Supply diffuser (600

x 600 mm face) Aluminum powder coated with volume

damper and complete with all required accessories,quantity of air flow . as per schedule in the drawing

A Supply diffuser 150 x 150 mm 21 nr.

B Supply diffuser 225 x 225 mm 193 nr.

C Supply diffuser 300 x 100 mm 11 nr.

D Supply diffuser 300 x 300 mm 293 nr.

E Supply diffuser 375 x 375 mm 78 nr.

F Supply diffuser 450 x 450 mm 13 nr.

G Supply diffuser 500 x 200 mm 5 nr.

H Supply diffuser 600 x 600 mm 11 nr.

Page 5: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 5/300

Supply, install, test and commission Exhaust diffuser

Aluminum power coated with complete with all required

accessories, quantity of air flow . as per schedule in the

drawing

A Exhaust diffuser 150 x150 mm 118 nr.

B Exhaust diffuser 225 x 225 mm 29 nr.

C Exhaust diffuser 225 x 255 mm 2 nr.

D Exhaust diffuser 300 x 100 mm 3 nr.

E Exhaust diffuser 300 x 300 mm 50 nr.

F Exhaust diffuser 375 x 375 mm 6 nr.

G Exhaust diffuser 450 x 450 mm 3 nr.

Supply Grilles

Supply, install, test and commission Supply Grilles

complete with all required accessories, quantity of air

flow .. as per schedule in the drawing

A Supply Grille 200 x 100 mm 4 nr.

B Supply Grille 225 x 225 mm 2 nr.

C Supply Grille 300 x 100 mm 46 nr.

D Supply Grille 350 x 150 mm 1 nr.

E Supply Grille 400 x 150 mm 3 nr.

F Supply Grille 500 x 100 mm 3 nr.

G Supply Grille 500 x 150 mm 8 nr.

H Supply Grille 500 x 200 mm 1 nr.

J Supply Grille 1210 x 610 mm 7 nr.

K Supply Grille 200 x 100 mm 4 nr.

Return Grill

Supply, install, test and commission return grilles

complete with all required accessories, quantity of air

Page 6: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 6/300

Exhaust cowl

Supply, install , test and commission Exhaust cowl,

complete with SS bird screen, all required accessories

and as hown on drawings.

A 45 Degree cowl size 300 x 150 mm 1 nr.

B 45 Degree cowl size 300 x 200 mm 1 nr.

C 45 Degree cowl size 400 x 200 mm 2 nr.

D 45 Degree cowl size 400 x 250 mm 1 nr.

E 45 Degree cowl size 500 x 300 mm 1 nr.

F 45 Degree cowl size 550 x 200 mm 1 nr.

G 45 Degree cowl size 550 x 300 mm 2 nr.

H 45 Degree cowl size 600 x 300 mm 1 nr.

A 45 Degree cowl size 650 x 200 mm 1 nr.

B 45 Degree cowl size 650 x 350 mm 1 nr.

C 45 Degree cowl size 750 x 350 mm 1 nr.

D 45 Degree cowl size 750 x 750 mm 6 nr.

E 45 Degree cowl size 800 x 700 mm 1 nr.

F 45 Degree cowl size 900 x 600 mm 1 nr.

G 45 Degree cowl size 950 x 800 mm 1 nr.

H 45 Degree cowl size 1000 x 600 mm 1 nr.

A 45 Degree cowl size 1000 x 750 mm 2 nr.

B 45 Degree cowl size 1000 x 800 mm 1 nr.

C 45 Degree cowl size 1000 x 900 mm 1 nr.

D 45 Degree cowl size 1000 x 950 mm 1 nr.

E 45 Degree cowl size 1100 x 750 mm 1 nr.

F 45 Degree cowl size 1100 x 800 mm 1 nr.

G 45 Degree cowl size 1200 x 700 mm 1 nr.

H 45 Degree cowl size 1250 x 800 mm 1 nr.

J 45 Degree cowl size 1300 x 850 mm 1 nr.

K 45 Degree cowl size 1350 x 900 mm 1 nr.

L 45 Degree cowl size 1500 x 800 mm 1 nr.

Page 7: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 7/300

58.548 controls

Unit AED Unit RO Total RO Consider

468.7 32.80 98.40  91.35 

468.7 32.80 131.20  91.35 

468.7 32.80 196.80  91.35 468.7 32.80 32.80  91.35 

468.7 32.80 98.40  91.35 

468.7 32.80 32.80  91.35 

468.7 32.80 196.80  91.35 

468.7 32.80 65.60  91.35 

468.7 32.80 32.80  91.35 

468.7 32.80 196.80  91.35 

468.7 32.80 32.80  91.35 468.7 32.80 98.40  91.35 

468.7 32.80 98.40  91.35 

468.7 32.80 131.20  91.35 

468.7 32.80 32.80  91.35 

468.7 32.80 65.60  91.35 

468.7 32.80 32.80  91.35 

468.7 32.80 32.80  91.35 

468.7 32.80 32.80  91.35 468.7 32.80 65.60  91.35 

576.2 40.30 40.30  98.85 

576.2 40.30 40.30  98.85 

645 45 10 180 40 103 65

Aldes

Page 8: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 8/300

645 45.10 45.10  103.65 

645 45.10 45.10  103.65 

645 45.10 45.10  103.65 

746.05 52.20 52.20  110.75 

746.05 52.20 208.80  110.75 

746.05 52.20 365.40  110.75 

746.05 52.20 783.00  110.75 

746.05 52.20 52.20  110.75 

746.05 52.20 208.80  110.75 

746.05 52.20 104.40  110.75 

746.05 52.20 156.60  110.75 

746.05 52.20 208.80  110.75 

746.05 52.20 52.20  110.75 

857.85 60.00 60.00  118.55 

857.85 60.00 60.00  118.55 

85.49 6.00 36.00  6.00 

90.2 6.30 37.80  6.30 

94.92 6.60 198.00  6.60 

96.29 6.70 361.80  6.70 

103.12 7.20 129.60  7.20 

89.97 6.30 264.60  6.30 

117.3 8.20 393.60  8.20 

159.86 11.20 403.20  11.20 

124.13 8.70 261.00  8.70 

161.29 11.30 135.60  11.30 

161.29 11.30 135.60  11.30 

161.29 11.30 135.60  11.30 

Page 9: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 9/300

168.65 11.80 59.00  11.80 

181.22 12.70 25.40  12.70 

167.67 11.70 35.10  11.70 

188.56 13.20 26.40  13.20 

194.79 13.60 13.60  13.60 

190.18 13.30 79.80  13.30 

198.4 13.90 69.50  13.90 

208.24 14.60 29.20  14.60 

218.08 15.30 45.90  15.30 

234.15 16.40 65.60  16.40 

267.24 18.70 18.70  18.70 

244.87 17.10 17.10  17.10 

262.15 18.30 18.30  18.30 

279.72 19.60 19.60  19.60 

418.45 29.30 146.50  29.30 

255.59 17.90 35.80  17.90 

273.74 19.10 19.10  19.10 

276.38 19.30 19.30  19.30 

295.41 20.70 20.70  20.70 

393.09 27.50 27.50  27.50 

443.58 31.00 62.00  31.00 

390.89 27.30 81.90  27.30 

536.83 37.50 37.50  37.50 

528.45 37.00 37.00  37.00 

560.43 39.20 117.60  39.20 

607.33 42.50 85.00  42.50 

477.9 33.40 33.40  33.40 

574.66 40.20 80.40  40.20 

622.46 43.50 43.50  43.50 

714.22 49.90 49.90  49.90 

771.42 53.90 161.70  53.90 

1947.5 136.20 136.20  136.20 

Page 10: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 10/300

830.29 58.10 174.30  58.10 

870.64 60.90 60.90  60.90 

911.55 63.70 191.10  63.70 

1466.9 102.60 102.60  102.60 

811.6 56.80 56.80  56.80 

1034.96 72.40 1,303.20  72.40 

1558.33 109.00 218.00  109.00 

1600.8 111.90 223.80  111.90 

1002.7 70.10 70.10  70.10 

1038.2 72.60 72.60  72.60 

1085.02 75.90 75.90  75.90 

1100.52 77.00 77.00  77.00 

1073.67 75.10 150.20  75.10 

1122.25 78.50 78.50  78.50 

- -  - 

- -  - 

- -  - 

- -  - 

678.24 47.40 995.40  47.40 

678.24 47.40 9,148.20  47.40 

678.24 47.40 521.40  47.40 

678.24 47.40 13,888.20  47.40 

678.24 47.40 3,697.20  47.40 

678.24 47.40 616.20  47.40 

678.24 47.40 237.00  47.40 

678.24 47.40 521.40  47.40 

- -  - 

- -  - 

Page 11: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 11/300

- -  - 

70.18 4.90 578.20  4.90 

166.67 11.70 339.30  11.70 

166.67 11.70 23.40  11.70 

166.67 11.70 35.10  11.70 

166.67 11.70 585.00  11.70 

236.05 16.50 99.00  16.50 

314.03 22.00 66.00  22.00 

- -  - 

- -  - 

- -  - 

- -  - 

33.58 2.30 9.20  2.30 

65.34 4.60 9.20  4.60 

46.25 3.20 147.20  3.20 

68.93 4.80 4.80  4.80 

77.22 5.40 16.20  5.40 

72.74 5.10 15.30  5.10 

95.3 6.70 53.60  6.70 

117.88 8.20 8.20  8.20 

701.82 49.10 343.70  49.10 

33.58 2.30 9.20  2.30 

- -  - 

- -  - 

- -  - 

Page 12: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 12/300

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - 

- -  - - -  - 

- -  - 

- -  - 

Page 13: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 13/300

VCD Unit AED Unit AED Unit RO

Size Qty.

1500X500 1 722.84 961.97 1684.81 117.80 

1150X1000 1 642.84 1430.68 2073.52 145.00 

1900X900 1 2292.66 2040.65 4333.31 303.00 

1200X600 2 761.52 928.11 1689.63 118.20 

1700X650 3 1138.94 1350.29 2489.23 174.10 

1700X500 1 958.76 1079.34 2038.1 142.50 

1700X400 2 783.82 898.72 1682.54 117.70 

1200X400 2 537.63 665.87 1203.5 84.20 

1200X450 2 638.65 731.43 1370.08 95.80 

1850X800 1 1365.94 1785.59 3151.53 220.40 

1700X600 1 1115.46 1259.98 2375.44 166.10 

1800X1250 1 2307.97 2581.26 4889.23 341.90 

1550X1000 1 1468.62 1866.59 3335.21 233.20 

2000X600 2 2829.81 1453.78 4283.59 299.60 

1200X650 1 777.17 993.67 1770.84 123.80 

1700X650 1 1138.94 1350.29 2489.23 174.10 

1000X350 1 408.71 529.52 938.23 65.60 1400X500 1 700 914.36 1614.36 112.90 

1500X500 1 722.84 961.97 1684.81 117.80 

Size Qty. - 

200X100 2 - 

300X200 14 - 

350X250 1 - 550X200 3 - 

Aldes

SAND TRAP LOUVERS with filter and VCD

Motorised VCD

Sound Attenuator

Includedin MD

Page 14: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 14/300

1200x900 2 5774.74 403.80 

1200x600 1 4460.99 312.00 

1000x750 1 3998.43 279.60 

1200x700 4 4898.9 342.60 

1250x800 2 5412.06 378.50 

1000x800 2 4170.29 291.60 

1350x900 2 5925.22 414.40 

950x800 2 4206.16 294.10 

900x700 1 3754.85 262.60 

1300x850 2 5631.02 393.80 

1500x800 2 6657.1 465.50 

1300x550 1 4317.28 301.90 

1100x750 1 5042.62 352.60 

1100x800 2 5261.58 367.90 

Factors :

Import Duty

$ to RO

Frieght

Discount (%)

Clearing & FrwdgChrgs

Exchange Rates :UAE Dhs to R.O.

Page 15: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 15/300

Total RO

117.80 

145.00 

303.00 

236.40 

522.30 

142.50 

235.40 

168.40 

191.60 220.40 

166.10 

341.90 

233.20 

599.20 

123.80 

174.10 

65.60 112.90 

117.80  4,217.40 

- - 

Page 16: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 16/300

807.60 

312.00 

279.60 

1,370.40 

757.00 

583.20 

828.80 

588.20 

262.60 

787.60 

931.00 

301.90 

352.60 735.80  14,768.60 

18,986.00

11%

40%

0.105 

0.386 

Page 17: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 17/300

Actuator Unit AED Unit AED Unit RO Total ROSize Qty.

750X450 1 158 394.29 552.29 44.70  44.70 

600X300 2 158 257.79 415.79 33.60  67.20 

1400X750 1 158 1024.82 1182.82 95.60  95.60 

1000X500 3 158 607.07 765.07 61.90  185.70 

750X300 1 158 285.43 443.43 35.90  35.90 

550X300 2 158 248.56 406.56 32.90  65.80 

1350X900 2 158 1509.47 1667.47 134.80  269.60 

1250X800 2 158 994.12 1152.12 93.10  186.20 

1500X800 2 158 1071.04 1229.04 99.40  198.80 1200X900 2 158 1441.88 1599.88 129.40  258.80 

1050X650 2 158 817.56 975.56 78.90  157.80 

800X700 2 158 489.81 647.81 52.40  104.80 

1000X800 2 158 458.57 616.57 49.80  99.60 

1300X850 2 158 751.73 909.73 73.60  147.20 

1200X600 2 158 842.11 1000.11 80.90  161.80 

1200X700 4 158 531.01 689.01 55.70  222.80 

1000X900 1 158 1183.27 1341.27 108.40  108.40 

1000X600 3 158 788.79 946.79 76.50  229.50 

950X1050 2 158 1207.1 1365.1 110.40  220.80 900X600 2 158 762.13 920.13 74.40  148.80 

850X500 2 158 573.28 731.28 59.10  118.20 

1000X750 1 158 901.75 1059.75 85.70  85.70 

950X800 2 158 901.8 1059.8 85.70  171.40 

1300X500 2 158 758.91 916.91 74.10  148.20 

500X450 4 158 295.82 453.82 36.70  146.80 

350X150 5 158 161.4 319.4 25.80  129.00 

400X150 3 158 168.56 326.56 26.40  79.20 

300X450 4 158 250.73 408.73 33.00  132.00 

200x100 2 158 127.77 285.77 23.10  46.20 

300x200 14 158 189.66 347.66 28.10  393.40 

350x250 1 158 206.84 364.84 29.50  29.50 

550x200 3 158 236.38 394.38 31.90  95.70 

0 -  - 

83 4 585 10

MOTORIZED Volume control DAMPER

Aldes

Page 18: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 18/300

DUCTING : 7th June 11

Size

Rate / ton (C&F Muscat) (US$)

Landed Price/ton (R.O.) -

Size of sheet (sqmt) 2.97

Rectangular Ducting

No. of 

sheets / ton

24G 71 

22G 53 

20G 46 

18G 33 

16G 25 

Factors

Duty : (%)

Clearing & forwarding (%)

Discount : (%)

Freight : (%)

Addl for PO vs quote 17.5%

Exchg Rates :

UAE Dhs to R.O. 0.105

DUCTING : 7th June 11

Page 19: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 19/300

Clearing & forwarding (%)

Discount : (%) 5%

Freight : (%)

Addl for PO vs quote 17.5%

Exchg Rates :UAE Dhs to R.O. 0.105

FIRE RATED DUCTING : 7th June 11

Size

Rate / ton (C&F Muscat) (US$)

Landed Price/ton (R.O.) -

Size of sheet (sqmt) 2.97

1m2/kg Rectangular Ducting

No. of 

sheets / ton

4.95 24G 71 6.91 22G 53 

8.45 20G 46 

10.6 18G 33 

16G 25 

Factors

Duty : (%)

Clearing & forwarding (%)

Discount : (%) 5%Freight : (%)

Addl for PO vs quote 17.5%

Exchg Rates :

UAE Dhs to R O 0 105

Page 20: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 20/300

50 mm thick rigid fibre glass insulation of 48kg/m2

density

0

25 mm thick,48kg/m3 sound absorbed lining to

ductwork, internally 1MX1.2M

0

25 mm thick,48kg/m3 externally 0

35 or 15 mm thick rigid fibre glass insulation of 

48kg/m3 density

1

50mm thick,32-35kg/m3 density,polystrene 2828.98

Preinsulated Flexible Duct( Crayflex/Supaflex/Atflex)

Description Unit

150mm dia m

200mm dia m

250mm dia m

300mm dia m

Pipe Insulation 15th June 11;

Thermal insulation, as specified to following chilled

water pipes, as specified Sectional rigid fibreglass

0.914m/piece0.914

20 mm diameter pipe 40mm thick,96kg/m3354

Page 21: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 21/300

Pipe Insulation 16th Nov 11;

Thermal insulation, as specified to following chilled

water pipes, as specified Sectional rigid fibreglass

0.914m/piece0.914

Density 64kg/m3 all

12 mm diameter pipe 40mm thick4

13 mm diameter pipe 40mm thick126

20 mm diameter pipe 40mm thick194

25 mm diameter pipe 40mm thick389

32 mm diameter pipe 40mm thick 1145

42 mm diameter pipe 40mm thick1048

50 mm diameter pipe 50mm thick1438

65 mm diameter pipe 65mm thick995

80 mm diameter pipe 65mm thick1010

100 mm diameter pipe 65mm thick 1311

125 mm diameter pipe 65mm thick359

150 mm diameter pipe 75mm thick453

Page 22: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 22/300

20 mm diameter pipe 50mm thick,96kg/m3354

25 mm diameter pipe 50mm thick,96kg/m3160

32 mm diameter pipe 50mm thick,96kg/m3100

42 mm diameter pipe 50mm thick,96kg/m3100

50 mm diameter pipe 50mm thick,96kg/m3120

65 mm diameter pipe 50mm thick,96kg/m3 80

80 mm diameter pipe 50mm thick,96kg/m3 100

100 mm diameter pipe 50mm thick,96kg/m312

125 mm diameter pipe 50mm thick,96kg/m38

150 mm diameter pipe 50mm thick,96kg/m350

200 mm diameter pipe 50mm thick,96kg/m30

250 mm diameter pipe 50mm thick,96kg/m30

Note For external coating 57-86 with all access shall

be RO/m2 4.5

Ducting Insulation 8th June 11

Description Qty

Page 23: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 23/300

19 mm thick closed cell sponge or expanded rubber

sections, comply with ASTM C 534 type 2 insulation

fixed with adhesive to indoor supply and return air

rectangular ductwork

1,886

32 mm thick closed cell sponge or expanded rubber

sections, comply with ASTM C 534 type 2 insulation

fixed with adhesive to indoor outside air

rectangular ductwork and outdoor supply and

return air rectangular ductwork

0

Chilled water piping insulation 8th June 11 R

∏ d(m2/m) Description Qty

Armaflex Type 19mm thick

0.0942 20mm dia 329

0.109 25mm dia 596

0.132 32mm dia 483

0.1571 40mm dia 225

0.1885 50mm dia 459

0.2356 65mm dia 296

0.2827 80mm dia 324

0.3456 100mm dia Use Sheet will require 74sqm 212

0.5027 150mm dia will require 110sqm 196

0.6598 200mm dia will require 35sqm 50

0.817 250mm dia will require 69sqm 79

0.974 300mm dia will require 47sqm 45

above

80dia

Ro/m2 3

Acc RO/m2 1 8

Page 24: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 24/300

0.779216 200mm dia 351

0.936316 250mm dia 259

1.093416 300mm dia 288

1.250516 350mm dia

above80dia

Ro/m2 5.4 2912

Acc RO/m2 2.5

Chilled water piping insulation

Description 40kg/m3 density Qty

phenolic Type

20mm dia,25mm thk

25mm dia,25mm thk 227

32mm dia,25mm thk 113

40mm dia,25mm thk 250

50mm dia,25mm thk 10365mm dia,35mm thk 120

80mm dia,35mm thk 557

100mm dia ,35mm thk 108

125mm dia ,35mm thk 161

150mm dia ,35mm thk 375

200mm dia,35mm thk 351

250mm dia 259

300mm dia ,75mm thk 288350mm dia ,75mm thk

150mm dia , 75mm thk

40mm dia ,25mm thk

Dh

Page 25: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 25/300

20mm dia,25mm thk

25mm dia,25mm thk

32mm dia,25mm thk

40mm dia,25mm thk

50mm dia,25mm thk65mm dia,32mm thk

80mm dia,32mm thk

100mm dia ,32mm thk

125mm dia ,32mm thk

150mm dia ,32mm thk

200mm dia,32mm thk

250mm dia

300mm dia ,75mm thk350mm dia ,75mm thk

150mm dia , 75mm thk

40mm dia ,25mm thk

25mm dia ,25mm thk

0

Description Qty

Dh

Page 26: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 26/300

Acoustic Insulation for plenum boxes m224G 452

Acoustic Insulation for Equip m2

25mm thick,48kg/m3 density 1557.60

Piping in plant room Qty

∏ d(m2/m)0.1571 1" dia 185

0.179 1 1/4" dia

0.204 1 1/2" dia 48

0.235 2" dia

0.2827 2 1/2" dia 100

0.314 3" dia 220

0.392 4" dia 138

0.471 5" dia 830.549 6" dia 256

0.706 8" dia 175

0.864 10" dia 37

1.02 12" dia 71

Cladding 0.9mm (RO/m2) 4.5

External Coat 2

6.5

Page 27: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 27/300

Ancillary (R.O./ sq.mt) (At

Workshop)

Additionalloading (debit

for m/c) At site

FABRICATED DUCTS-

SEAGULL- 29.12.2010 P.O.

(AED) -Japanese sheets m2

Majeestech 11-

01-2012

Rate (R.O./

sq.mt) Access

36.55 2,347.57  3.800  1.500 

54.60 942.17  4.500  1.600 

59.00 1,004.95  5.500  1.800 

68.25 -  7.400  2.000 

Avg rate 24G 30% 5.300 1.59 

22G 50% 6.100 3.05 

20G 20% 7.300 1.46 

Total 6.10 

Page 28: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 28/300

Avg rate 24G 20% 5.000 1.00 

22G 55% 5.700 3.14 

20G 25% 7.000 1.75 

Total 5.90 

Ancillary (R.O.

/ sq.mt) (At

Workshop)

Additional

loading (debit

for m/c) At site

FABRICATED DUCTS-

SEAGULL- 29.12.2010 P.O.

(AED) -Japanese sheets

Fire rated

coating/m2

Majeestech 11-

01-2012

Tuleila 16th

Jan 2012

Rate (R.O./

sq.mt)

Rate (R.O./

kg)

Access/m2

36.55 11.40  3.800  0.768 1.500 

54.60 11.40  4.500  0.651 1.500 

59.00 11.40  5.500  0.651 2.000 

68.25 11.40  7.400  0.698 2.500 

Avg rate 24G 20% 3.800 0.76 

22G 55% 4.500 2.48 

20G 25% 5.500 1.38 

Total 4.60 

Page 29: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 29/300

m2

336 sheets RO 2.600/sheet 2.17  2.825

m2

4959 Sheets RO 2.500/sheet 2.08  1.2

m21.34  1.835

m2

1.75  1.835

m2 2.60  1.835

25mm 70% 3.18 

4th June 2011 50mm 30% 4.993

Unit RO/m0.91

1.05

1.30

1.38

or Gulf college

RO/Piece

 

InsulationRO/

m AccessRO/m2

10% 2.50

m 2.500  2.5 2.74  1.10

Page 30: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 30/300

for LULU

RO/Piece

 

InsulationRO/

m AccessRO/m2

Internal 1.80

Discount 5% External 2.50

m 2.30 2.200  0.70

m 2.30 2.200  0.80

m 2.80 2.700  0.80

m 2.90 2.800  0.80

m 3.30 3.100  0.90

m 3.60 3.400  0.90

m 4.30 4.100  1.00

m 4.60 4.400  1.00

m 4.80 4.600  1.10

m 7.00 6.700  1.20

m 8.00 7.600  1.40

m 8.60 8.200 2.50

Page 31: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 31/300

RO/Piece

 

InsulationRO/

m AccessRO/m2

2.50

m 3 2.50  1.10

m 3.5 2.92  1.10

m 3.8 3.17  1.20

m 4 3.33  1.30

m 4 3.33  1.30

m 4.2 3.50  1.50m 5 4.17  1.60

m 7.5 6.25  1.70

m 8.2 6.83  1.90

m 9.2 10.07  2.10

m 11.6 12.69  2.50

m 15.8 17.29  2.90

Unit Unit Oman Rial Access Unit RO/m2

Adhe,foam

tape,PVC

tape,canvas,co

ating

Page 32: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 32/300

m2 3.000

2.5 9.500 17917

m2 5.300

2.5 15.250

O tender Access RO/m

Unit unit RO

Adhe,foam

tape,PVC tape

Total Unit

RO/m

2.5

m 0.500 0.2355 0.736 164.5

m 0.600 0.2725 0.873 357.6

m 0.700 0.33 1.030 338.1

m 0.800 0.39275 1.193 180

m 1.000 0.47125 1.471 459m 1.300 0.589 1.889 384.8

m 2.000 0.70675 2.707 648

m 1.037 0.864 1.901 219.8016

m 1.508 1.25675 2.765 295.5876

m 1.979 1.6495 3.629 98.97

m 2.451 2.0425 4.494 193.629

m 2.922 2.435 5.357 131.49

Page 33: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 33/300

m 4.208 2.50 6.71 2354.426006

m 5.056 2.90 7.96 2060.631558

m 5.904 3.30 9.20 2650.880563

m 6.753 3.70 10.45 0

15,689.81 

Cape Access RO/m Considered

Unit unit RO unit RO

Adhe,foam

tape,PVC tape

Total Unit

RO/m

2.5

m 1.8 1.38 1.10 2.48

m 2.1 1.61 1.10 2.71

m 2.3 1.76 1.20 2.96

m 2.6 1.99 1.30 3.29

m 2.7 2.07 1.30 3.37m 5 3.83 1.50 5.33

m 5.5 4.21 1.60 5.81

m 6.5 4.97 1.70 6.67

m 7.8 5.97 1.70 7.67

m 9.5 7.27 2.10 9.37

m 13.2 10.1 2.50 12.60

m 25 19.13 2.90 22.03

m 30.9 23.64 3.30 26.94m 38.8 29.68 3.70 33.38

m 21.5 16.45 2.10 18.55

m 2.6 1.99 1.30 3.29

far 09/1/2012

Page 34: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 34/300

m 1.8 1.38 1.10 2.48

m 2.1 1.61 1.10 2.71

m 2.3 1.76 1.20 2.96

m 2.6 1.99 1.30 3.29

m 2.7 2.07 1.30 3.37m 4.7 3.6 1.50 5.10

m 4.8 3.67 1.60 5.27

m 5.6 4.28 1.70 5.98

m 7.1 5.43 1.70 7.13

m 9.4 7.19 2.10 9.29

m 11.7 8.95 2.50 11.45

m 0 2.90 2.90

m 30.9 23.64 3.30 26.94m 38.8 29.68 3.70 33.38

m 21.5 16.45 2.10 18.55

m 2.6 1.99 1.30 3.29

m 2.1 1.61 1.10 2.71

0%

2%

25.0%0.0%

0.105

0.386

Unit Unit Oman Rial Unit Oman Rial Access Unit RO/m2Adhe,foam

tape,PVC

tape,canvas,co

Factors :

Import Duty

Frieght

Discount (%)Clearing & FrwdgChrgs

Exchange Rates :

UAE Dhs to R.O.

$ to RO

far 09/1/2012

Page 35: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 35/300

Ducting rate Insulation Total unit/m2 Total3.800 5.26 9.06 4,094.49 

Ducting rate Insulation Total unit/m2 Total

- 3.28 3.28 5114.56

RO/m Total

1.02 188.91

1.16 0.00

1.33 63.65

1.53 0.00

1.84 183.76

2.04 449.02

2.55 351.62

3.06 254.103.57 913.54

4.59 803.08

5.62 207.79

6.63 470.73 3886.197

Page 36: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 36/300

Additional TOTAL (R.O.)

Rate/kg

Rate (R.O./

sq.mt)

5.300 1.100  12,442.12 

6.100 1.000  5,747.24 

7.300 1.000  7,336.14 

9.400 0.900 

- 25,525.49 

Seismic supports

Amount in R.O. - 

Ducting amount w/o Seismic 368,000 

%age 0.00%

Page 37: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 37/300

Amount in R.O. - 

Ducting amount w/o Seismic 368,000 

%age 0.00%

Additional TOTAL (R.O.)

Rate/kg

Fire rated

Ducting/m2

Access/kg Rate (R.O./

sq.mt)

Dasmal 19th

Jan 2012 Labour (Mhrs/

0.150  5.300 1.071  3.25 

0.250  6.000 0.868  4

0.400  7.500 0.888 22.50  4.75

9.900 0.934  6.2

Seismic supports

Amount in R.O. - 

Ducting amount w/o Seismic 368,000 

%age 0.00%

Page 38: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 38/300

4.99  - 

3.28  - 

3.18  -  - 

3.59  3.59 

4.44  12,546.53 

2.22 

1.50 

3.72 

Total RO/m

3.60

Page 39: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 39/300

Total RO/m

2.90 8.80 

3.00 277.20 

3.50 523.80 

3.60 1,089.20 

4.00 3,549.50 

4.30 3,563.20 

5.10 5,895.80 

5.40 4,378.00 

5.70 4,646.00 

7.90 8,783.70 

9.00 2,728.40 

10.70 3,714.60

Page 40: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 40/300

Total RO/m

3.60

4.02

4.37

4.63

4.63

5.005.77

7.95

8.73

12.17

15.19

20.19

Cape Phenolic Unit Oman

Rial

Page 41: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 41/300

7.000

12.750

3471.4782

Page 42: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 42/300

0

615.17

334.48

822.5

347.11

639.6

3236.17

720.36

1234.87

3513.75

4422.6

5705.77

7758.72

0

0

0

Page 43: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 43/300

0

0

0

0

00

0

0

0

0

0

0

00

0

0

0

Page 44: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 44/300

Page 45: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 45/300

Page 46: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 46/300

Labour (R.O./kg)

0.66 

0.58 0.56 

0.58 

89230978.xlsx.ms_office

Page 47: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 47/300

Rectangular Ducting Measurement Sheet (SMCANA, Metric)Project:- Drg. Ref.:- AHU No:- Drg. Ref.:-

Sr. Duct Typical Duct Size Length Insulation Code Area SMACNA Gaugewise Ducting Area (Sq.M.) DW-142 Gau

No. No. W(mm)xH(mm) m. Therm. Acoust. Sq.m. 24G 22G 20G 18G 16G 24G 22G

1 850 400 32.50 81.25 0.00 81.25 0.00 0.00 0.00 81.

1 550 300 32.00 54.40 54.40 0.00 0.00 0.00 0.00 54.1 1350 900 62.70 282.15 0.00 282.15 0.00 0.00 0.00 0.

1 1200 900 13.00 54.60 0.00 54.60 0.00 0.00 0.00 0.1 1050 650 28.50 96.90 0.00 96.90 0.00 0.00 0.00 0.

1 750 350 20.50 45.10 45.10 0.00 0.00 0.00 0.00 45.1 750 300 5.00 10.50 10.50 0.00 0.00 0.00 0.00 10.

1 1000 800 39.00 140.40 0.00 140.40 0.00 0.00 0.00 140.1 750 300 14.50 30.45 30.45 0.00 0.00 0.00 0.00 30.

1 1200 600 27.50 99.00 0.00 99.00 0.00 0.00 0.00 0.1 850 300 18.50 42.55 0.00 42.55 0.00 0.00 0.00 42.1 1250 800 37.30 152.93 0.00 152.93 0.00 0.00 0.00 0.

1 1500 800 20.00 92.00 0.00 92.00 0.00 0.00 0.00 0.1 900 350 14.00 35.00 0.00 35.00 0.00 0.00 0.00 35.1 800 400 14.00 33.60 0.00 33.60 0.00 0.00 0.00 33.

1 950 800 21.50 75.25 0.00 75.25 0.00 0.00 0.00 75.1 1200 700 22.50 85.50 0.00 85.50 0.00 0.00 0.00 0.

1 1000 550 12.00 37.20 0.00 37.20 0.00 0.00 0.00 37.1 1000 450 7.00 20.30 0.00 20.30 0.00 0.00 0.00 20.

1 1300 550 18.50 68.45 0.00 68.45 0.00 0.00 0.00 0.1 650 250 19.50 35.10 35.10 0.00 0.00 0.00 0.00 35.

1 850 350 6.00 14.40 0.00 14.40 0.00 0.00 0.00 14.1 1100 400 8.00 24.00 0.00 24.00 0.00 0.00 0.00 0.

1 1200 450 2.00 6.60 0.00 6.60 0.00 0.00 0.00 0.1 300 250 1.50 1.65 1.65 0.00 0.00 0.00 1.65 0.1 600 250 3.00 5.10 5.10 0.00 0.00 0.00 0.00 5.1 650 300 7.50 14.25 14.25 0.00 0.00 0.00 0.00 14.1 650 250 10.50 18.90 18.90 0.00 0.00 0.00 0.00 18.

1 900 600 27.50 82.50 0.00 82.50 0.00 0.00 0.00 82.1 1000 750 19.50 68.25 0.00 68.25 0.00 0.00 0.00 68.1 850 500 21.50 58.05 0.00 58.05 0.00 0.00 0.00 58.1 850 400 10.00 25.00 0.00 25.00 0.00 0.00 0.00 25.1 1000 500 21.50 64.50 0.00 64.50 0.00 0.00 0.00 64.

89230978.xlsx.ms_office

Page 48: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 48/300

Rectangular Ducting Measurement Sheet (SMCANA, Metric)

Project:- Drg. Ref.:- AHU No:- Drg. Ref.:-

Sr. Duct Typical Duct Size Length Insulation Code Area SMACNA Gaugewise Ducting Area (Sq.M.) DW-142 Ga

No. No. W(mm)xH(mm) m. Therm. Acoust. Sq.m. 24G 22G 20G 18G 16G 24G 22G

(without wastage) (Sq.Ft.) 30448 3059 27389 0 0 0 250 166

NO. OF DUCT SHEETS 1047 105 942 0 0 0 9 5

TOTAL 24G 22G 20G 18G 16G 24G 22G

INSULATION SUMMARY (Sq.M.)

Indoor Insulation Outdoor Insulation Acoustic Insulation

(I1) :25mmx24kg F 0 (E1) :50mm Polysty. 0 (A1) :25mmx24kg FG 0COST ESTIMATE'!A1

(I2) :50mmx24kg F 0 (E2) :50mmx48kg FG 0 (A2) :15mmx48kg FG 0(I3) :25mmx48kg F 0 (E3) :25mm Polysty. 0 (A3) :25mmx48kg FG 0

Page 49: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 49/300

Description unit Access Qty unit $ Unit RO Total

Chilled water Pumps

P1 TO P5 56L/S@25M No 0 5 0.00 - - 

PP Control panel 30KW No 0 1

S1 TO S5 110L/S@45M No 0 3

SP Control panel 75KW+VFD No 1

Pressurization Unit;7.8m3/[email protected] No 1 0.00 - - 

Chemical dosing pot No 1 - - 

Air Separator No 1 - - 

0.00

5%

0%

5.0%

2.5%

0.105

0.386

Discount (%)

Factors :

ITT Bell & Gosset

Frieght

Import Duty

Clearing & FrwdgChrg

Exchange Rates :

$ to RO

UAE Dhs to R.O.

Page 50: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 50/300

unit RO Unit RO Total unit RO Unit RO Total unit RO Unit RO

2,195.00 2,030.38 10,151.90 - - 5,480.00 4,932.00 

1,170.00 1,082.25 1,082.25 - 1,082.25 

7,535.00 6,969.88 20,909.64 - - 7,880.00 7,092.00 

11,255.00 10,410.88 10,410.88 - 10,410.88

2,466.00 2,281.05 2,281.05 - - 2,281.05 

500.00 462.50 462.50 462.50 462.50 462.50 

500.00 462.50 462.50 0.00 462.50 462.50 462.50 

45,760.72 925.00

0% 0%

0% 0%

7.5% 15.0%0.0% 0.0%

0.105 0.105

0.386 0.386

Discount (%) Discount (%) Discount (%)

Wilo

Factors : Factors : Factors :

Ebara

Import Duty

Frieght Frieght Frieght

KSB

Import Duty Import Duty

Clearing & FrwdgChrgs Clearing & FrwdgChrgs Clearing & FrwdgChrgs

$ to RO $ to RO $ to RO

Exchange Rates : Exchange Rates : Exchange Rates :

UAE Dhs to R.O. UAE Dhs to R.O. UAE Dhs to R.O.

Page 51: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 51/300

Consider

Total per unit

24,660.00  2,030.38 

1,082.25  216.45  2,246.83 

21,276.00  6,969.88 

10,410.88  3,470.29  10,440.17

2,281.05  2,281.05 

462.50  462.50 

462.50  462.50 

60,635.18

0%

0%

10.0%0.0%

0.105

0.386

Page 52: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 52/300

Sl.No Description Fig.No.Size

(mm)U/Rate( R.O)

QtyNos.

1 Bronze Gate Valve - PN16 C31 15 3.500 2

1 Bronze Gate Valve - PN16 C31 20 4.100 12

2 Bronze Gate Valve - PN16 C31 25 5.600 33

3 Bronze Gate Valve - PN16 C31 32 7.400 189

4 Bronze Gate Valve - PN16 C31 40 9.800

5 Bronze Gate Valve - PN16 C31 50 14.700 48

6 C.I Gate Valve - PN16 541 65 51.300 97 C.I Gate Valve - PN16 541 80 61.300 11

8 C.I Gate Valve - PN16 541 100 86.500 26

9 C.I Gate Valve - PN16 541 125 119.800 10

10 C.I Gate Valve - PN16 541 150 159.700 5

10 C.I Gate Valve - PN16 541 200 191.600 3

10 C.I Gate Valve - PN16 541 250 304.300 1

10 C.I Gate Valve - PN16 541 300 454.000 2

10 C.I Gate Valve - PN16 541 350 1147.000 2

11 C.I NRV - PN 16 651 125 114.300

C.I NRV - PN 16 651 150 153.700

C.I NRV - PN 16 651 300

C.I Y strainer - PN16 810 20 4.000

C.I Y strainer - PN16 810 25 6.100

C.I Y strainer - PN16 810 32 10.000C.I Y strainer - PN16 810 40 14.300

C.I Y strainer - PN16 810 50 22.800

C.I Y strainer - PN16 810 65 32.000

Hattersley 12

SCHEDULE OF VALVES

Page 53: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 53/300

22 C.I DRV with Test ports - PN16 737 350 2175.100 2

23 D.I Semi Lugged Butterfly Valve - PN16 C950 125 40.100

24 Bronze Draining Tap 370 15 5.100

TOTALDiscount 17%

S.No Description Fig.No.

Size

(mm)

U/Rate

( R.O)

Qty

Nos.

1

Flexible Connector-Double Bellow

Threaded type FCU-12 32 9.300 2

2

Flexible Connector-Double Bellow

Threaded type FCU-15 40 11.600 22

3

Flexible Connector-Double Bellow

Threaded type FCU-20 50 14.300 4

4

Flexible Connector-Single Bellow

Flanged type FCS-50 125 39.500 16

5

Straight Thermometer Range 0-50deg,110/63mm 15.100 32

6

Pressure Gauge 4" Dial 1/2" BSP -Bottom Connection, 0-150 PSI

- -

7.800 44

TOTALDiscount 15%

Grand Total

SCHEDULE OF FLEXIBLE CONNECTORS & INSTRUME

Grand Total

Grand Total

Page 54: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 54/300

AmountR.O.

U/Rate( R.O)

QtyNos.

AmountR.O.

U/Rate( R.O)

QtyNos.

7.000 0.000 0.000 0.000

49.200 4.807 0.000 4.300

184.800 6.739 0.000 5.800

1398.600 10.442 0.000 7.800

0.000 14.352 0.000 10.300

705.600 22.402 0.000 15.300

461.700 59.064 0.000 43.600674.300 74.000 0.000 48.300

2249.000 104.000 0.000 73.800

1198.000 142.000 0.000 89.700

798.500 164.000 0.000 114.700

574.800 0.000 0.000 0.000

304.300 0.000 0.000 0.000

908.000 0.000 0.000 0.000

2294.000 0.000 0.000 0.000

0.000 107.000 0.000 76.100

0.000

0.000

0.000

0.000

0.000

0.000

0.000

Econostth Nov 2011 Crane

Page 55: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 55/300

4350.200 0.000 0.000 0.000

0.000 42.000 0.000 46.800

0.000 2.320 0.000 2.320

28,323.30 TOTAL - TOTAL2832.330 Discount 10% 0.000 Discount 10%

25,490.97 - 

Amount

R.O.

U/Rate

( R.O)

Qty

Nos.

Amount

R.O.

U/Rate

( R.O)

Qty

Nos.

18.600 9.300 2 18.600 8.600 2

255.200 11.600 22 255.200 10.900 22

57.200 11.900 4 47.600 13.600 4

632.000 30.200 16 483.200 32.100 16

483.200 13.500 32 432.000 10.700 32

343.200 6.600 44 290.400 6.000 44

1789.400 TOTAL 1527.000 TOTAL178.940 Discount 10% 152.700 Discount 10%

1610.460 1374.300

27,101.43 1,374.30 

Grand Total

Grand Total

TS

Grand Total

Grand Total

Page 56: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 56/300

Access Considered

AmountR.O.

0.000 2.91 

0.000 3.40 

0.000 4.65 

0.000 6.14 

0.000 8.13 

0.000 12.20 

0.000 6 48.58 0.000 7 57.88 

0.000 8.5 80.30 

0.000 11 110.43 

0.000 15 147.55 

0.000 22 181.03 

0.000 35 287.57 

0.000 46 422.82 

0.000 82 1,034.01 - 

0.000 11 105.87 

127.57 

192.00 

3.32 

5.06 

8.30 

11.87 

18.92 

6 32.56

Page 57: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 57/300

0.000 82 1,887.33 

0.000 11 44.28 

0.000 4.23 

- 0.000

Amount

R.O.

17.200

239.800

54.400

513.600

342.400

264.000

1431.400143.140

1288.260

1,288.26 

Page 58: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 58/300

Sl.No Description Fig.No. Size (mm)U/Rate( R.O)

Accessflange

Gate Valves

1 Bronze Gate Valve - PN16 C31 20 4.100

2 Bronze Gate Valve - PN16 C31 25 5.600

3 Bronze Gate Valve - PN16 C31 32 7.400

4 Bronze Gate Valve - PN16 C31 40 9.800

5 Bronze Gate Valve - PN16 C31 50 14.700

6 C.I Gate Valve - PN16 541 65 51.300 6.000

7 C.I Gate Valve - PN16 541 80 61.300 7.000

8 C.I Gate Valve - PN16 541 100 86.500 8.500

9 C.I Gate Valve - PN16 541 150 159.700 15.000

Strainer

10 Bronze Y strainer - PN16 817 20 4.000

11 Bronze Y strainer - PN16 817 25 6.100

12 Bronze Y strainer - PN16 817 32 10.000

13 Bronze Y strainer - PN16 817 40 14.300

14 Bronze Y strainer - PN16 817 50 22.80015 C.I Y strainer - PN16 810 65 32.000 6.000

16 C.I Y strainer - PN16 810 80 39.800 7.000

17 C.I Y strainer - PN16 810 100 57.900 8.500

DRV

18 Bronze DRV with Test ports - PN20 1732 20 20.300

19 Bronze DRV with Test ports - PN20 1732 25 22.000

18 Bronze DRV with Test ports - PN20 1732 32 26.000

19 Bronze DRV with Test ports - PN20 1732 40 34.500

20 Bronze DRV with Test ports - PN20 1732 50 42.60021 C.I DRV with Test ports - PN16 737 65 85.900 6.000

22 C.I DRV with Test ports - PN16 737 80 132.400 7.000

23 C I DRV ith T t t PN16 737 100 172 400 8 500

SCHEDULE OF VALVES 12-06-2011( RGO & Majan)

Page 59: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 59/300

4

Flexible Connector-Single Bellow

Flanged type FCS-60 150 44.400

5Straight Thermometer Range 0-50deg, 110/63mm

- -15.100

6Pressure Gauge 4" Dial 1/2" BSP -Bottom Connection, 0-150 PSI

- -7.800

Factors :

Import Duty 5.0%

Frieght 10.0%

Discount (%) 5.0%

Clearing & Forwarding Chrgs 2.5%

Exchange Rates :

UAE Dhs to R.O. 0.105

RO to RO 1

Sl.No Description Qty Unit AED Unit RO

Access

flange

Automatic balancing valves

1 20mm dia 229.46 24.0933

2 25mm dia 245.64 25.7922

3 32mm dia 449.9 47.2395

4 40mm dia 467.5 49.0875

5 50mm dia 825 86.625

6 65mm dia 1320 138.6 6.000

7 80mm dia 1430 150.15 7.000

8 100mm dia 1991 209.055 8.500

Motorised Butterfly valves

1 100mm dia 2905 305.025 8.500

2 150mm dia 3866 405.93 15.000

Factors :Import Duty 5.0%

Frieght 10.0%

Discount (%) 5.0%

Technoflow Trading 10th July 2011

Page 60: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 60/300

8 100mm dia 806 8.500 814.5

1.2

Sl.No Description Qty Unit RO

Thermostat

 /flange

Unit

Amount

R.O.

2 way on/off Control Valves with

actuator & thermostat

1 20mm dia 27.6 10 37.6

2 25mm dia 34.8 10 44.8

32mm dia

2 way modulating motorised valves

with return air duct temp

sensor,thermostat & actuator

20mm dia

25mm dia

3 32mm dia 204 0 204

4 40mm dia 210 0 210

5 50mm dia 276 0 276

6 65mm dia(either 50 or 80mm) 336 6.000 342

7 80mm dia 336 7.000 343

8 100mm dia 967.2 8.500 975.72way on/off motorised Valves with

actuator & thermostat

8 125mm dia 450 15.000 465

Factors :

Import Duty 5.0%

Frieght 10.0%

Discount (%) 5.0%

Clearing & Forwarding Chrgs 2.5%

Exchange Rates :UAE Dhs to R.O. 0.105

RO to RO 1

Johnson Control

Page 61: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 61/300

Unit AmountR.O.

Discountassume(Hattersley)

U/Rate( R.O)

Unit AmountR.O.

Discountassume(Crane)

4.100 3.90  7.06 7.06  6.70 

5.600 5.30  11.00 11.00  10.50 

7.400 7.00  17.07 17.07  16.20 

9.800 9.30  22.99 22.99  21.80 

14.700 14.00  34.95 34.95  33.20 

57.300 54.40  59.06 65.06  61.80 

68.300 64.90  74.00 81.00  77.00 

95.000 90.30  104.00 112.50  106.90 

174.700 166.00  164.00 179.00  170.10 

-  -  - 

4.000 3.80  4.50 4.50  4.30 

6.100 5.80  7.00 7.00  6.70 

10.000 9.50  11.40 11.40  10.80 

14.300 13.60  16.35 16.35  15.50 

22.800 21.70  26.16 26.16  24.90 

38.000 36.10  40.00 46.00  43.70 

46.800 44.50  46.00 53.00  50.40 

66.400 63.10  67.00 75.50  71.70 

-  -  - 

20.300 19.30  23.20 23.20  22.00 

22.000 20.90  26.00 26.00  24.70 

26.000 24.70  30.00 30.00  28.50 

34.500 32.80  40.00 40.00  38.00 

42.600 40.50  49.00 49.00  46.60 

91.900 87.30  96.00 102.00  96.90 

139.400 132.40  129.00 136.00  129.20 

180 900 171 90 168 00 176 50 167 70

Hattersley Crane

 

Page 62: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 62/300

44.400 42.20 

15.100 14.30  13.50 

7.800 7.40  6.60 

Unit Amount

R.O. Discount assume

24.0933 22.90 

25.7922 24.50 

47.2395 44.90 

49.0875 46.60 

86.625 82.30 

144.6 137.40 

157.15 149.30 

217.555 206.70 

313.525 297.80 

420.93 399.90 

773 80

Page 63: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 63/300

773.80 

Unit AED Unit RO

Access

flange/thermo

stat

Unit Amount

R.O.

Discount

assume Unit RO

35.70  2610.36 274.09 274.0878 260.38341 16

42.60  2741.04 287.81 287.8092 273.41874 17

-  22

-  33

-  35

193.80  3021.84 317.29 317.2932 301.42854 37

199.50  3283.2 344.74 344.736 327.4992 180

262.20  3715.2 390.10 390.096 370.5912 195

324.90  5603.04 588.32 6.00 594.3192 564.60324 305

325.90  11770.92 1,235.95 7.00 1242.9466 1180.7993 452

926.90 13478.4 1,415.23 8.50 1423.732 1352.5454 605

441.80  0

Clorius Control 10th July 2011 T

Page 64: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 64/300

Page 65: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 65/300

Page 66: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 66/300

Thermostat/ flange

Unit

AmountR.O.

Discountassume

Discount

assume &Considered

18 34 32.30 32.30 

18 35 33.30 33.30 

18 40 38.00 38.00 

- - 

20 53 50.40 50.40 

20 55 52.30 52.30 

20 57 54.20 54.20 

20 200 190.00 190.00 

20 215 204.30 204.30 

58 363 344.90 344.90 

64 516 490.20 490.20 

78 683648.90 648.90 

- - 

0.000 0 - 441.80 

REND-HONEYWELL 22/8/11

Page 67: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 67/300

Unit RO Unit RO Total RO Unit RO

S. No Cap TR Qty

Access

w/o Ref 

Pipe

1 1 16 20 135 128.30 2,052.80  135

2 1.5 351 20 195 185.30 65,040.30 150

3 2 113 20 230 218.50 24,690.50 185

4 2.5 0 20 402 381.90 - 402

5 3 0 20 470 446.50 - 470

6(Ducted) 2.5 0 30 525 498.80 - 525

91,783.60 

Factors : Factors :

0%

0%

5.0%

0.0%

0.105

0.386

Actual rate

$ to RO $ to

UAE Dhs to R.O. UAE Dh

Exchange Rates : Exchang

Clearing & FrwdgChrgs Clearing &

Discount (%) Discou

Frieght Frie

Split Units

Import Duty Import

LG (Korea)

Page 68: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 68/300

YORK

Consider

Unit RO Total RO Unit RO Unit RO Total RO Unit RO Unit RO

128.30 2,052.80 135 124.90 1,998.40  144.90  135

142.50 50,017.50 140 129.50 45,454.50  149.50  155

175.80 19,865.40 185 171.10 19,334.30  191.10  210

381.90 - 255 235.90 -  255.90  402

446.50 - 440 407.00 -  427.00  470

498.80 - 525 485.60 -  515.60  525

71,935.70 66,787.20 

Factors : Factors :

0% 0%

0% 0%

5.0% 7.5%

0.0% 0.0%

0.105 0.105

0.386 0.386RO $ to RO $ to

to R.O. UAE Dhs to R.O. UAE Dh

Discou

Rates : Exchange Rates : Exchang

rwdgChrgs Clearing & FrwdgChrgs Clearing &

nt (%) Discount (%)

ght Frieght Frie

Duty Import Duty Import

LG (China) York

Page 69: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 69/300

Unit RO Total RO Unit RO Unit RO Total RO Unit RO Unit RO

128.30 2,052.80 135 128.30 2,052.80 135 128.30 

147.30 51,702.30 195 185.30 65,040.30 245 232.80 

199.50 22,543.50 230 218.50 24,690.50 325 308.80 

381.90 - 402 381.90 - 402 381.90 

446.50 - 470 446.50 - 470 446.50 

498.80 - 525 498.80 - 525 498.80 

76,298.60 91,783.60 

Factors : Factors :

0% 0%

0% 0%

5.0% 5.0%

0.0% 0.0%

0.105 0.105

0.386 0.386RO $ to RO

to R.O. UAE Dhs to R.O.

Exchange Rates :

$ to RO

UAE Dhs to R.O.

nt (%) Discount (%)

Rates : Exchange Rates :

Discount (%)

rwdgChrgs Clearing & FrwdgChrgs Clearing & FrwdgChrgs

ght Frieght Frieght

Import DutyDuty Import Duty

Lennox Classic Make Genera

Page 70: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 70/300

Total RO Unit RO Unit RO Total RO Unit RO Unit RO

2,052.80 135 128.30 2,052.80 135 128.30 

81,712.80 245 232.80 81,712.80 220 209.00 

34,894.40 270 256.50 28,984.50 245 232.80 

- 402 381.90 -  402 381.90 -  470 446.50 - 470 446.50 

-  525 498.80 - 530 503.50 

118,660.00 112,750.10 

Factors : Factors :

0% 0%

0% 0%

5.0% 5.0%

0.0% 0.0%

0.105 0.105

0.386 0.386

Exchange Rates : Exchange Rates :

$ to RO $ to RO

UAE Dhs to R.O. UAE Dhs to R.O.

Discount (%) Discount (%)

Clearing & FrwdgChrgs Clearing & FrwdgChrgs

Frieght Frieght

Import Duty Import Duty

Carrier McQul

Page 71: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 71/300

Total RO Unit RO Unit RO Total RO

2,052.80 135 128.30 2,052.80 

73,359.00  185 175.80 61,705.80 

26,306.40 230 218.50 24,690.50 

-  356 338.20 - - 370 351.50 - 

- 530 503.50 - 

101,718.20 88,449.10 

Factors :

0% 0%

0% 0%

5.0% 5.0%

0.0% 0.0%

0.105 0.105

0.386 0.386

Exchange Rates :

$ to RO

UAE Dhs to R.O.

Discount (%)

Clearing & FrwdgChrgs

Import Duty

Frieght

ay Daikin

11/20/2011

Page 72: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 72/300

11/20/2011

2 Refrigerant piping with fittings MAJEES TECH

Maksal Mueller

Size : Unit RO/m Unit RO/m

Cu pipe- bare :

SOFT Fittings :

Unit Rate 30%

6.4 mm 0.67 0.85 0.60 0.18 

9.5 mm(3/8) 1.13 1.46 1.00 0.30 

12.7 mm(1/2) 1.57 1.8 1.50 0.45 

15.9 mm(5/8) 2 2.5 2.20 0.66 

19.10 mm(3/4) 2.33 3 2.80 0.84 

22.2 mm(7/8) 4.3 4.9 3.50 1.05 28.58 mm (1 1/8) 5.5 6.6 5.10 1.53 

34.9 mm(1 3/8) 7.8 8.8 6.90 2.07 

42 mm(1 5/8) 9 12 8.90 2.67 

54 mm( 2 1/8) 13.5 17.5 14.30 4.29 

67mm( 2 5/8) 18.5 25.2 20.20 6.06 

Safety factor 5% 5%

3 Ref. Pipe InsulationNitrile rubber Armaflex Gulf-o-flex 1.80 

Size : 25 mm thk Unit RO/m Ancillaries Total unit (R.O.)/m

Adhesive,Tape,30-

36 coating,canvas(

1.5RO/m2)

6.4 mm 0.6 0.31 0.300 0.6109.5 mm(3/8) 0.8 0.425 0.300 0.725

12.7 mm(1/2) 0.8 0.425 0.300 0.725

28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 

42 mm(1 5/8) 11 2 1 50

Page 73: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 73/300

42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

67mm( 2 5/8) 25.3 1.50 - 

2500 5000Trunking 100x100 3 1 - 

Guard Room & Admin

Size Qty m Unit Pipe RO MH Total Pipe RO

6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 90 1.2 0.80 108.00 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 90 2.8 0.80 252.00 19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 

28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 

42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

67mm( 2 5/8) 25.3 1.50 - 

180 360Trunking 100x100 3 1 - 

Guard Room & office

Size Qty m Unit Pipe RO MH Total Pipe RO

6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 430 1.2 0.80 516.00 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 430 2.8 0.80 1,204.00 19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 

42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

67mm( 2 5/8) 25 3 1 50

Page 74: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 74/300

67mm( 2 5/8) 25.3 1.50 - 

780 1560

Trunking 100x100 3 1 - 

Officer Accomodation

Size Qty m Unit Pipe RO MH Total Pipe RO

6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 1040 1.2 0.80 1,248.00 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 1040 2.8 0.80 2,912.00 

19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 

42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

67mm( 2 5/8) 25.3 1.50 - 

2080 4160

Trunking 100x100 3 1 - 

prayer Hall

Size Qty m Unit Pipe RO MH Total Pipe RO

6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 40 1.2 0.80 48.00 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 40 2.8 0.80 112.00 

19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 

67mm( 2 5/8) 25.3 1.50 - 

1540 3080

Trunking 100x100 3 1 -

Page 75: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 75/300

Trunking 100x100 3 1 - 

Substation

Size Qty m Unit Pipe RO MH Total Pipe RO6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 110 1.2 0.80 132.00 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 110 2.8 0.80 308.00 

19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 

28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

67mm( 2 5/8) 25.3 1.50 - 

220 440

Trunking 100x100 3 1 - 

BMT

Size Qty m Unit Pipe RO MH Total Pipe RO6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 225 1.2 0.80 270.00 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 225 2.8 0.80 630.00 

19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 

28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

Trunking 100x100 3 1 - 

Page 76: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 76/300

AHU'S

Size Qty m Unit Pipe RO MH Total Pipe RO6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 1.2 0.80 - 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 2.8 0.80 - 

19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 

28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 17.9 1.50 - 

67mm( 2 5/8) 25.3 1.50 - 

0 0

Trunking 100x100 0 3 1 - 

Mini Splits

Size Qty m Unit Pipe RO MH Total Pipe RO6.4 mm 0.8 0.80 - 

9.5 mm(3/8) 1 1.2 0.80 1.20 

12.7 mm(1/2) 1.9 0.80 - 

15.9 mm(5/8) 1 2.8 0.80 2.80 

19.10 mm(3/4) 3.5 0.85 - 

22.2 mm(7/8) 4.4 1.00 - 

28.58 mm (1 1/8) 6.4 1.20 - 

34.9 mm(1 3/8) 8.7 1.20 - 42 mm(1 5/8) 11.2 1.50 - 

54 mm( 2 1/8) 0 17.9 1.50 - 

Page 77: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 77/300

Maksal Mueller

Total unit(R.O.)/m Unit RO/m Unit RO/m

0.80 0.6 0.65

1.20 0.94 0.97

1.90 1.47 1.52

2.80 2.13 2.19

3.50 2.69 2.78

4.40 3.38 3.56.40 4.87 5.04

8.70 6.58 6.78

11.20 8.49 8.75

17.90 13.59 14.04

25.30 19.26 19.89

0% 0%

Unigulf 20/12/2011

0 0.99 1 0 0

0 1.21 1 0 0

0 1.38 1.2 0 0

Page 78: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 78/300

0 1.78 1.4 0 0

0 1.95 1.4 0 0

2000 1843.75 1875 6,843.75 0 - 0 0 0 - 

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat

0 0.61 0.75 0 0

72 0.73 0.75 65.25 67.5

0 0.73 0.75 0 0

72 0.75 0.75 67.5 67.50 0.93 1 0 0

0 0.95 1 0 0

0 0.99 1 0 0

0 1.21 1 0 0

0 1.38 1.2 0 0

0 1.78 1.4 0 0

0 1.95 1.4 0 0

144 132.75 135 492.75 0 - 0 0 0 - 

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat

0 0.61 0.75 0 0

344 0.73 0.75 311.75 322.5

0 0.73 0.75 0 0

344 0.75 0.75 322.5 322.50 0.93 1 0 0

0 0.95 1 0 0

0 1.38 1.2 0 0

0 1.78 1.4 0 0

0 1.95 1.4 0 0

Page 79: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 79/300

624 575.25 585 2,135.25 

0 - 0 0 0 - 

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat

0 0.61 0.75 0 0

832 0.73 0.75 754 780

0 0.73 0.75 0 0

832 0.75 0.75 780 780

0 0.93 1 0 0

0 0.95 1 0 00 0.99 1 0 0

0 1.21 1 0 0

0 1.38 1.2 0 0

0 1.78 1.4 0 0

0 1.95 1.4 0 0

1664 1534 1560 5,694.00 

0 - 0 0 0 - 

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat

0 0.61 0.75 0 0

32 0.73 0.75 29 30

0 0.73 0.75 0 0

32 0.75 0.75 30 30

0 0.93 1 0 0

0 0.95 1 0 00 0.99 1 0 0

0 1.21 1 0 0

0 1.95 1.4 0 0

1232 1135.75 1155 4,215.75 

0 - 0 0 0 - 

Page 80: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 80/300

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat0 0.61 0.75 0 0

88 0.73 0.75 79.75 82.5

0 0.73 0.75 0 0

88 0.75 0.75 82.5 82.5

0 0.93 1 0 0

0 0.95 1 0 0

0 0.99 1 0 0

0 1.21 1 0 00 1.38 1.2 0 0

0 1.78 1.4 0 0

0 1.95 1.4 0 0

176 162.25 165 602.25 

0 - 0 0 0 - 

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat0 0.61 0.75 0 0

180 0.73 0.75 163.125 168.75

0 0.73 0.75 0 0

180 0.75 0.75 168.75 168.75

0 0.93 1 0 0

0 0.95 1 0 0

0 0.99 1 0 0

0 1.21 1 0 00 1.38 1.2 0 0

0 1.78 1.4 0 0

0 - 0 0 0 - 

Page 81: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 81/300

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat0 0.61 0.75 0 0

0 0.73 0.75 0 0

0 0.73 0.75 0 0

0 0.75 0.75 0 0

0 0.93 1 0 0

0 0.95 1 0 0

0 0.99 1 0 0

0 1.21 1 0 00 1.38 1.2 0 0

0 1.78 1.4 0 0

0 1.95 1.4 0 0

0 0 0 - 

0 - 0 0 0 0

Total MH Insulation RInsulation MH Total Insulation Total Insulation MH Total Mat0 0.61 0.75 0 0

0.8 0.73 0.75 0.725 0.75

0 0.73 0.75 0 0

0.8 0.75 0.75 0.75 0.75

0 0.93 1 0 0

0 0.95 1 0 0

0 0.99 1 0 0

0 1.21 1 0 00 1.38 1.2 0 0

0 1.78 1.4 0 0

Page 82: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 82/300

Page 83: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 83/300

3,875.00 - 

Total MH

279.00 - 

Total MH

1 209 00

Page 84: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 84/300

1,209.00 

Total MH

3,224.00 

Total MH

2,387.00 

Page 85: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 85/300

Total MH

341.00 

Total MH

Page 86: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 86/300

Total MH

0

Total MH

Page 87: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 87/300

Description unit Qty unit AED Unit RO

Steel pipe,ASTM A106 type

S(seamless),Grade B,Sch 40,black

steel,plain ends

20mm dia m 26.50 3.10 25mm dia m 227 23.67 2.80 

32mm dia m 112 30.67 3.60 

40mm dia m 250 43.33 5.10 

50mm dia m 103 41.17 4.80 

65mm dia m 120 64.83 7.60 

80mm dia m 557 82.67 9.70 

100mm dia m 108 120.00 14.10 125mm dia m 158 120.00 19.35 

150mm dia m 375 210.17 24.60 

200mm dia m 351 333.67 39.10 

250mm dia m 259 499.67 58.60 

300mm dia m 288 651.83 76.40 

350mm dia m - 

2908

Factors :

Import Duty 5% Fittings 35%

Alinco

22nd June 11

25mm dia m 227 11.67 1.20 

32mm dia m 112 15.00 1.50 

Page 88: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 88/300

40mm dia m 250 18.00 1.80 

50mm dia m 103 24.33 2.40 

65mm dia m 120 38.83 3.90 

80mm dia m 557 50.17 5.00 

100mm dia m 108 70.33 7.00 

125mm dia m 158 72.00 7.20 

150mm dia m 375 132.00 13.20 

200mm dia m 351 201.50 20.10 

250mm dia m 259 282.00 28.10 

300mm dia m 288 386.67 38.60 350mm dia m 0.00 - 

700mm dia m 0.00 - 

Factors : 2908

Import Duty 0%

Frieght 0%

Discount (%) 5.0%

Clearing & Forwarding Chrgs 0.0%Exchange Rates :

UAE Dhs to R.O. 0.105

FCU Valves Qty Unit RO Total RO

20mm dia 36.000

Flexible connectors 2.000 5.900 11.80

Gate Valve 2.000 3.590 7.18 

2 way motorised valve 0.000 - 

Duct flexible connectors 2.000 5.000 10.00 

P t 1 000 2 000 2 00

Page 89: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 89/300

P trap 1.000 2.000 2.00 

Vibration Isolators 4.000 5.000 20.00  68.790

32mm dia 69.000 - 

Flexible connectors 2.000 9.300 18.60 

Gate Valve 2.000 6.480 12.96 

Test point 3.000 2.000 6.00 

AAV 1.000 6.000 6.00 

DRV 1.000 22.750 22.75 

2 way motorised valve 1.000 - Duct flexible connectors 2.000 5.000 10.00 

P trap 1.000 2.000 2.00 

Vibration Isolators 4.000 5.000 20.00  98.310

40mm dia 5.000 - 

Flexible connectors 2.000 9.300 18.60 

Gate Valve 2.000 8.580 17.16 Test point 3.000 2.000 6.00 

AAV 1.000 6.000 6.00 

DRV 1.000 30.190 30.19 

2 way motorised valve 1.000 - 

Duct flexible connectors 2.000 5.000 10.00 

P trap 1.000 2.000 2.00 

Vibration Isolators 4.000 5.000 20.00  109.950

50mm dia 8.000 - 

DRV 1.000 18.000 18.00 

2 way motorised valve 1.000 - 

Strainer 1 000 6 100 6 10

Page 90: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 90/300

Strainer 1.000 6.100 6.10 

AAV 1.000 6.000 6.00 

Thermometer 2.000 10.700 21.40 

Pressure test point 4.000 2.000 8.00 

U trap 1.000 2.000 2.00 

Duct flexible connector 2.000 5.000 10.00 

Vibration Isolators 4.000 5.000 20.00  113.740

32mm dia

Flexible Connectors 2.000 9.300 18.60Gate valve 2.000 7.020 14.04 

DRV 1.000 23.760 23.76 

2 way motorised valve 1.000 - 

Strainer 1.000 10.000 10.00 

AAV 1.000 6.000 6.00 

Thermometer 2.000 10.700 21.40 

Pressure test point 4.000 2.000 8.00 U trap 1.000 2.000 2.00 

Duct flexible connector 2.000 5.000 10.00 

Vibration Isolators 4.000 5.000 20.00 

133.800

50mm dia

Flexible Connectors 2.000 30.000 60.00

Gate valve 2.000 13.770 27.54

DRV 0.000 34.020 -

2 way motorised valve 1.000 -

Thermometer 2.000 10.700 21.40 

Pressure gauge 2.000 7.800 15.60

Pressure test point 2 000 2 000 4 00

Page 91: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 91/300

Pressure test point 2.000 2.000 4.00 

U trap 1.000 2.000 2.00 

Duct flexible connector 2.000 8.000 16.00 

Vibration Isolators 4.000 15.000 60.00  426.780

80mm dia - 

Flexible Connectors 2.000 40.000 80.00 

Gate valve 2.000 57.880 115.76 

DRV 1.000 116.890 116.89 

2 way motorised valve 1.000 490.200 490.20 Strainer 1.000 40.030 40.03 

AAV 1.000 6.000 6.00 

Thermometer 2.000 10.700 21.40 

Pressure gauge 2.000 7.800 15.60

Pressure test point 2.000 2.000 4.00 

U trap 1.000 2.000 2.00 

Duct flexible connector 2.000 8.000 16.00 Vibration Isolators 4.000 15.000 60.00  967.880

100mm dia - 

Flexible Connectors 2.000 40.000 80.00 

Gate valve 2.000 80.300 160.60 

DRV 1.000 151.590 151.59 

2 way motorised valve 1.000 648.900 648.90 

Strainer 1.000 56.560 56.56 

AAV 1.000 6.000 6.00 

Pressure test point 2.000 2.000 4.00 

U trap 1.000 2.000 2.00 

Duct flexible connector 2 000 8 000 16 00

Page 92: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 92/300

Duct flexible connector 2.000 8.000 16.00 

Vibration Isolators 4.000 15.000 60.00  707.080

150mm dia - 

Flexible Connectors 2.000 45.000 90.00 

Gate valve 2.000 231.750 463.50 

DRV 0.000 340.120 - 

2 way motorised valve 1.000 - 

Strainer 1.000 194.520 194.52 

AAV 1.000 6.000 6.00 Thermometer 2.000 10.700 21.40 

Pressure gauge 2.000 7.800 15.60

Pressure test point 2.000 2.000 4.00 

U trap 1.000 2.000 2.00 

Duct flexible connector 2.000 8.000 16.00 

Vibration Isolators 4.000 25.000 100.00  913.020

Chillers Valves Qty Unit RO Total RO

200mm dia

Vibration isolators 6.000 55.000 330.00 

Flexible connector 4.000 45.000 180.00

Thermometer 4.000 10.700 42.80 

Pressure gauge 2.000 6.000 12.00 

Test points 6.000 3.400 20.40 

DRV with MS 2.000 536.930 1,073.86

Strainer 2.000 187.000 374.00 

Secondary Pumps Valves Qty Unit RO Total RO

250mm dia 3.000

Vibration isolators 4 000 55 000 220 00

Page 93: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 93/300

Vibration isolators 4.000 55.000 220.00 

Flexible connector 2.000 45.000 90.00

Pressure gauge 2.000 6.000 12.00 

Gate valve 2.000 287.570 575.14 

DRV with MS 1.000 813.870 813.87 

Strainer 1.000 187.000 187.00 

NRV 1.000 180.000 180.00 

Drain Cock 1.000 8.000 8.00  2086.010

TPC Abu Dhabi

Page 94: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 94/300

TPC Abu Dhabi

(Arcelor

Mittal,Europe) Considered

unit AED Unit RO Unit RO unit AED Unit RO unit AED

with fittings

13.95 1.40 1.62 15.00 1.50  11.8319.75 2.00 2.30 17.00 1.70  17.50

26.75 2.70 2.97 21.00 2.20  22.49

31.95 3.30 3.38 24.00 2.50  26.86

41.25 4.20 4.59 33.00 3.40  36.08

65.45 6.70 7.29 53.00 5.40  57.24

85.60 8.80 9.59 69.00 7.10  74.89

117.75 12.10 13.77 99.00 10.20  106.59

159.00 16.30 18.50 133.00 13.70  144.40

199.95 20.50 24.03 173.00 17.80  187.45

301.05 30.90 39.15 301.05 30.90  282.23

426.70 43.80 59.13 426.70 43.80  400.04

578.15 59.40 72.23 521.00 53.50  490.05

-  85.00  - 

TPC Dubai (Interpipe) Lucerne c

27th June 11 29th June 2011 14th Aug

0.96 1.49 10.00 1.00 10.94 1.10 

1.30 2.03 13.00 1.30 14.83 1.50 

1.55 2.43 15.00 1.50 17.72 1.80 

Page 95: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 95/300

2.08 3.24 20.00 2.10 23.80 2.40 

3.30 5.13 32.00 3.30 37.75 3.80 

4.31 6.62 42.00 4.30 49.38 4.90 

6.14 9.45 59.00 6.10 70.29 7.00 

7.40 12.83 72.00 7.40 95.22 9.50 

11.00 16.61 104.00 10.70 123.61 12.30 

16.50 25.11 161.00 16.50 186.12 18.60 

24.50 35.51 238.00 24.50 263.80 26.30 

30.00 44.01 363.00 37.30 326.70 32.60 37.40 50.49 0.00 - 374.63 37.40 

84.80 114.48 0.00 - 850.46 84.80 

Page 96: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 96/300

Page 97: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 97/300

Page 98: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 98/300

Page 99: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 99/300

Page 100: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 100/300

6258.030

14087.980

Page 101: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 101/300

Unit RO

1.20  - 1.80 522.10 

2.30 332.64 

2.80 845.00 

3.70 472.77 

5.90 874.80 

7.70 5,341.63 

11.00 1,487.16 

14.80 2,923.00 

19.30 9,011.25 

29.00  13,741.65 

41.10 15,314.67 

50.30 20,802.24 

- - 

71,668.91 

nada

2011

338.23 

227.36 

607.50 

333 72

Page 102: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 102/300

333.72 

615.60 

3,687.34 

1,020.60 

2,027.14 

6,228.75 

8,813.61 

9,197.09 

12,674.88 - 

45,771.82 

25,897.09  savings

Typical Duct Size Length Area DW-142 Gaugewise Ducting Area (Sq.M.) Remarks

W(mm)x H(mm) m. Sq.m. 24G 22G 20G 18G 16G

1 900 500 8.00 22.40 0.00 22.40 0.00 0.00 0.00 AHU-1.1

1 750 450 8.00 19.20 0.00 19.20 0.00 0.00 0.00

Page 103: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 103/300

1 1400 700 8.00 33.60 0.00 0.00 33.60 0.00 0.00 AHU-1.21 600 300 0 0.00 0.00 0.00 0.00 0.00 0.00

1 1500 750 8.00 36.00 0.00 0.00 36.00 0.00 0.00

1 600 300 0 0.00 0.00 0.00 0.00 0.00 0.00

1 900 600 8.00 24.00 0.00 24.00 0.00 0.00 0.00 AHU-1.3

1 900 600 8.00 24.00 0.00 24.00 0.00 0.00 0.00

1 1000 500 8.00 24.00 0.00 24.00 0.00 0.00 0.00 AHU-1.4

1 1200 500 8.00 27.20 0.00 0.00 27.20 0.00 0.00

1 1200 1000 8.00 35.20 0.00 0.00 35.20 0.00 0.00 AHU-1.5

1 800 350 8.00 18.40 0.00 18.40 0.00 0.00 0.00

1 850 400 8.00 20.00 0.00 20.00 0.00 0.00 0.00 AHU-1.6

1 550 300 8.00 13.60 0.00 13.60 0.00 0.00 0.00

1 1050 650 8.00 27.20 0.00 0.00 27.20 0.00 0.00 AHU-2.1

1 750 300 8.00 16.80 0.00 16.80 0.00 0.00 0.00

1 1000 900 8.00 30.40 0.00 30.40 0.00 0.00 0.00 AHU-2.31 1000 500 0 0.00 0.00 0.00 0.00 0.00 0.00

1 1000 650 8.00 26.40 0.00 26.40 0.00 0.00 0.00

1 1000 600 0 0.00 0.00 0.00 0.00 0.00 0.00

1 1200 900 8.00 33.60 0.00 0.00 33.60 0.00 0.00 AHU-2.4

1 1200 900 8.00 33.60 0.00 0.00 33.60 0.00 0.00

1 1200 600 8.00 28.80 0.00 0.00 28.80 0.00 0.00 AHU-3.1

1 1000 750 8.00 28.00 0.00 28.00 0.00 0.00 0.00

1 1200 700 8.00 30.40 0.00 0.00 30.40 0.00 0.00 AHU-3.2

1 1200 700 8.00 30.40 0.00 0.00 30.40 0.00 0.00

2 1100 800 8.00 60.80 0.00 0.00 60.80 0.00 0.00 AHU-5.4(A,B)

2 1200 700 8.00 60.80 0.00 0.00 60.80 0.00 0.00

2 1100 800 8.00 60.80 0.00 0.00 60.80 0.00 0.00

2 1200 700 8.00 60.80 0.00 0.00 60.80 0.00 0.00

Total 1,557.60  0.00 481.60 1076.00 0.00 1557.60

Page 104: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 104/300

Page 105: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 105/300

Page 106: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 106/300

Logstor Pre-insulated Pipes & Fittings

Annexure

Page 107: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 107/300

Logstor Pre insulated Pipes & Fittings

Sl Logstor size steel pipe OD/ Qty Unit U. Price AmountNo Jacket pipe OD (R.O) (R.O)

Pipes Pre-insulated #20001 88/160mm 12mtr 16 length 138.500 2,216.0002 139/225mm 12mtr 5 length 229.000 1,145.000

3 323/450mm 12mtr 7 length 791.000 5,537.000

Elbow Pre-insulated #25004 88/160mm 90deg 10 nos 33.500 335.0005 139/225mm 90deg 10 nos 59.000 590.0006 323/450mm 90deg 6 nos 222.500 1,335.000

T-Fitting Pre-insulated 45º #35007 88/160 X 60/125 X 88/160mm 2 nos 88.500 177.000

8 139/225 X 60/125 X 139/225mm 2 nos 98.000 196.0009 323/450 X 60/125 X 323/450mm 4 nos 381.000 1,524.000

BX Joints #502210 60/125mm 780mm 8 nos 15.000 120.00011 88/160mm 780mm 32 nos 16.500 528.00012 139/225mm 780mm 16 nos 33.000 528.00013 323/450mm 780mm 26 nos 53.000 1,378.000

TOTAL AMOUNT 15,609.000

Project:Construction of Haematology and BMT centre building

12

Page 108: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 108/300

Qty m

19260

84

VENTILATING FANS

Supply, installation, testing & commissioning of ventilating

fan with electrically operated louvers, as specified on the

drawings, complete with all mounting requirements, flexible

Page 109: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 109/300

connections, electrical connections, support, back draftdampers, auto changeover controller, complete all in

accordance with drawings, specification and to the Engineer

approval.

Access

A Twin Exhaust Fan Ref EXF-1; 375 air flow 150 Pa static fan. 1

B Twin Exhaust Fan Ref EXF-2; 450 air flow 150 Pa static fan. 1

C Twin Exhaust Fan Ref EXF-3; 350 air flow 150 pa static fan. 1

D Twin Exhaust Fan Ref EXF-4; 150 air flow 75 Pa static fan. 1

E Twin Exhaust Fan Ref EXF-5; 575 air flow 150 Pa static fan. 1

F Twin Exhaust Fan Ref EXF-7; 1052 air flow 200 Pa static fan. 1

G Twin Exhaust Fan Ref EXF-8; 675 air flow 150 Pa static fan. 1

A Twin Exhaust Fan Ref EXF-9; 225 air flow 150 Pa static fan. 1

B Twin Exhaust Fan Ref EXF-10; 870 air flow 150 Pa static fan. 1

C Twin Exhaust Fan Ref EXF-11; 1321 air flow 200 Pa static fan. 1

D Twin Exhaust Fan Ref EXF-12; 1000 air flow 200 Pa static fan 1E Twin Exhaust Fan Ref EXF-13; 875 air flow 150 Pa static fan. 1

F Twin Exhaust Fan Ref EXF-14; 1455 air flow 250 Pa static fan. 1

G Twin Exhaust Fan Ref EXF-15; 150 air flow 75 Pa static fan. 1

A Kitchen Exhaust Fan Ref K-EXF; 650 air flow 150 Pa static fan. 1

B

Staircase Pressurization Fan Ref FAN-1T05; 9567 air flow 350 Pa staticfan. 5

Supply, installation, testing & commissioning of ventilating

fan with electrically operated louvers as specified on the

E Smoke Exhaust Fan Ref S-EXF-11; 1

F Smoke Exhaust Fan Ref S-EXF-12; 1

A Smoke Exhaust Fan Ref S-EXF-13; 1

B Smoke Exhaust Fan Ref S-EXF-14; 1

C Smoke Exhaust Fan Ref S-EXF-15; 1

Page 110: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 110/300

C Smoke Exhaust Fan Ref S EXF 15; 1

D Smoke Exhaust Fan Ref S-EXF-16; 1

E Smoke Exhaust Fan Ref S-EXF-17; 1

A Smoke Exhaust Fan Ref S-EXF-18; 1

B Smoke Exhaust Fan Ref S-EXF-19; 1

C Smoke Exhaust Fan Ref S-EXF-20; 1

D Smoke Exhaust Fan Ref S-EXF-21; 1

E Smoke Exhaust Fan Ref S-EXF-22; 1

A

EXF-16 (Substation); Twin axial fan, 4000 L/s air flow, 100 Pa.ESP, 3kW motor capacity

2

Xpelair Dynair

Page 111: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 111/300

Unit RO Unit RO Total RO Consider Unit RO Unit RO Total RO

875 612.50 612.50  510.30  567 510.30 510.30 

875 612.50 612.50  510.30  567 510.30 510.30 

875 612.50 612.50  422.82  469.8 422.82 422.82 

150 105.00 105.00  444.69  494.1 444.69 444.69 

950 665.00 665.00  517.59  575.1 517.59 517.59 

2200 1,540.00 1,540.00  517.59  575.1 517.59 517.59 

1500 1,050.00 1,050.00  517.59  575.1 517.59 517.59 

875 612.50 612.50  510.30  567 510.30 510.30 

1600 1,120.00 1,120.00  510.30  567 510.30 510.30 

2200 1,540.00 1,540.00  838.35  931.5 838.35 838.35 

1800 1,260.00 1,260.00  670.68  745.2 670.68 670.68 1600 1,120.00 1,120.00  510.30  567 510.30 510.30 

2300 1,610.00 1,610.00  860.22  955.8 860.22 860.22 

550 385.00 385.00  444.69  494.1 444.69 444.69 

552.58 552.58  552.58  613.98 552.58 552.58 

900.32 4,501.60  900.32  1000.35 900.32 4,501.60 

- -  -  - - 

775 542.50 542.50  759.62  844.02 759.62 759.62 

775 542.50 542.50  1,245.13  1383.48 1,245.13 1,245.13 

1700 1,190.00 1,190.00  787.32  874.8 787.32 787.32 

1700 1,190.00 1,190.00  658.26  731.4 658.26 658.26 

1800 1,260.00 1,260.00  1,186.81  1318.68 1,186.81 1,186.81 

Page 112: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 112/300

1800 1,260.00 1,260.00  1,186.81  1318.68 1,186.81 1,186.81 

1700 1,190.00 1,190.00  753.79  837.54 753.79 753.79 

950 665.00 665.00  787.32  874.8 787.32 787.32 

950 665.00 665.00  502.28  558.09 502.28 502.28 

950 665.00 665.00  602.88  669.87 602.88 602.88 

950 665.00 665.00  787.32  874.8 787.32 787.32 

1800 1,260.00 1,260.00  1,476.23  1640.25 1,476.23 1,476.23 

875 612.50 1,225.00  1,128.49  1253.88 1,128.49 2,256.98 42,154.18 35,723.90

0% 0%0% 0%

30.0% 10.0%0.0% 0.0%

0.105 0.1051 1

Exchange Rates :

UAE Dhs to R.O.$ to RO

Factors :

Import DutyFrieght

Discount (%)Clearing & FrwdgChrgs Clearing & FrwdgChrgs

Exchange Rates :

UAE Dhs to R.O.$ to RO

Factors :

Import DutyFrieght

Discount (%)

Qty Access Unit $

Supply, installation, test & commission of Air

cooled chiller; as per the contract specification and

drawings; including hoisting and setting in positin,

Chillers

Page 113: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 113/300

anti vibration mountings, control panel, wiring ,

labelling, final connections and other required

materials to complete all works in accordenec with

drawings and specifications. .

AChiller 1 to 5 ; Screw type 1134 kW cooling capacity 54 L/sflow Rate

5138000

Qty Access Unit $

Plate heat exchanger unit on steel frame including

base channels, double skin, with all required

dampers, 2 way motorized valve, sand trap louver

filters, cooling coils, heaters wherever shown on

drawings , fans , fittings, flexible connections andspring mount, vibration damper .. as per capacity

as specified in drawings specifications and to the

Air handling Units

Fact

ImportFrie

DiscouClearing & Fr

Exchang

UAE Dh$ to

Heat Recovery Air handling unit on steel frame

including base channels, double skin, with all

required dampers, 2 way motorized valve, cooling

coils, heaters wherever shown on drawings , fans ,

fittings, flexible connections and spring mount,

Page 114: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 114/300

vibration damper, .. as per capacity as specified indrawings , specifications and to the Engineer

approval.

A AHU-1.1; 95 kW cooling capacity, 2389 L/s air flow 1 9,784.00 

B AHU-1.2; 175 kW cooling capacity, 7147 L/s air flow 1 19,992.00 

C AHU-1.3; 106 kW cooling capacity, 3480 L/s air flow 1 12,221.00 

D AHU-1.4; 107 kW cooling capacity, 3657 L/s air flow 1 11,913.00 

E AHU-1.5; 195 kW cooling capacity, 6845 L/s air flow 1 17,629.00 

A AHU-1.6; 108 kW cooling capacity, 2127 L/s air flow 1 8,322.00 

B AHU-2.1; 115 kW cooling capacity, 4039 L/s air flow 1 13,256.00 

C AHU-2.4; 187.5 kW cooling capacity, 6302 L/s air flow 1 16,939.00 

D AHU-3.1; 123 kW cooling capacity, 4249 L/s air flow 1 13,374.00 

E AHU-3.2; 130 kW cooling capacity, 4888 L/s air flow 1 15,720.00 

A AHU-3.3; 169 kW cooling capacity, 5824 L/s air flow 1 16,866.00 

B AHU-3.4; 87 kW cooling capacity, 3601 L/s air flow 1 12,219.00 

C AHU-4.1; 135 kW cooling capacity, 4720 L/s air flow 1 15,720.00 

D AHU-4.2; 180 kW cooling capacity, 7387 L/s air flow 1 20,084.00 

E AHU-4.3; 120 kW cooling capacity, 4494 L/s air flow 1 13,464.00 

F AHU-4.4; 90 kW cooling capacity, 2989 L/s air flow 1 10,397.00 

G AHU-5.1; 182kW cooling capacity, 6688 L/s air flow 1 17,877.00 

AAHU-5.2;204 kW cooling capacity,7064 L/s air flow

119,806.00 

Fact

Supply, Installation and commissioning the

following specified fan coil unit to suit the indicated

capacity, complete with coils, valves, thermostatic

controller, 2 way motorized valve, filters including

all accessories , plumbing and electrical

connection to complete the installation as per

Page 115: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 115/300

specification , described in drawings and to theEngineer approval s.

Ducted FCU 4 2 625

E Fan Coil Unit ref. FCU-3 decorative 30 525

Qty Access Unit RO

BMS 1 107000

Cabling & Conduiting 1 15%

$ to

Fact

ImportFrie

DiscouClearing & Fr

Exchang

UAE Dh

BMS

Fact

ImportFrie

DiscouClearing & Fr

ExchangUAE Dh

$

Unit RO Total RO Consider

McQuay

Page 116: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 116/300

50,105.21 250,526.05  50,105.21 

250,526.05 

5%0%

12.5%2.5%

0.1050.386

Unit RO Total RO

McQuay

rs :

Dutyghtnt (%)wdgChrgs

Rates :

to R.O.RO

Page 117: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 117/300

- -  - 

3,552.39 3,552.39  3,552.39 

7,258.72 7,258.72  7,258.72 

4,437.22 4,437.22  4,437.22 

4,325.39 4,325.39  4,325.39 

6,400.76 6,400.76  6,400.76 

3,021.56 3,021.56  3,021.56 

4,813.01 4,813.01  4,813.01 

6,150.23 6,150.23  6,150.23 

4,855.85 4,855.85  4,855.85 

5,707.64 5,707.64  5,707.64 

6,123.73 6,123.73  6,123.73 

4,436.49 4,436.49  4,436.49 

5,707.64 5,707.64  5,707.64 

7,292.12 7,292.12  7,292.12 

4,888.53 4,888.53  4,888.53 

3,774.96 3,774.96  3,774.96 

6,490.80 6,490.80  6,490.80 

7,191.19 7,191.19  7,191.19 134,459.90 

rs :

Page 118: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 118/300

233.41 466.82  233.41 

196.06 5,881.80  196.06 

198.39 

5%0%

10.0%2.5%

0.1050.386

Unit RO Total RO Unit RO Unit RO Total RO

85,600.00 85,600.00  66,886.50  73200 66,886.50 66,886.50

16,050.00 16,050.00  10,980.00  10,980.00 10,980.00101,650.00  77,866.50  77,866.50

0% 5%0% 0%

20.0% 15.0%0.0% 2.5%

1 10 386 0 386

Clearing & FrwdgChrgs

Exchange Rates :UAE Dhs to R.O.

$ RO

Johnson

Factors :

Import DutyFrieght

Discount (%)

RO

rs :

Dutyghtnt (%)wdgChrgs

Rates :

to R.O.

TAC

rs :

Dutyghtnt (%)wdgChrgs

Rates :to R.O.

RO

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Page 119: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 119/300

Code AMOUNT   Unit Rate

Figures R.O. RO

HVAC

CHILLED WATER PIPING

Supply, install, test and commission of Black

steel class B seamless pipe to BS 1387

including all fittings , valves, balancing valve,

brackets, clamps, clips and supports,

complete all as specified in flexible connection

. as shown on drawings or as require to

complete the connection and installations.

A 300 mm Dia 76 P lin m 122.400 9,302.400 72.230

B 250 mm Dia 259 P lin m 98.500 25,511.500 59.130

C 200 mm Dia 241 P lin m 68.500 16,508.500 39.150

D 150 mm Dia 155 P lin m 44.100 6,835.500 24.030

E 125 mm Dia 144 P lin m 36.800 5,299.200 18.500

F 100 mm Dia 108 P lin m 28.600 3,088.800 13.770

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Page 120: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 120/300

Code AMOUNT   Unit Rate A

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

CHILLED WATER PIPING (Cont'd)

A 65 mm Dia 88 P lin m 15.500 1,364.000 7.290

B 50 mm Dia 22 P lin m 9.300 199.950 4.590

C 40 mm Dia 195 P lin m 7.700 1,501.500 3.380

D 32 mm Dia 64 P lin m 6.800 435.200 2.970

E 25 mm Dia 186 P lin m 5.400 1,004.400 2.300

4,505.050

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Page 121: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 121/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

INSULATION FOR PIPE

preformed rigid sections PUF/polyisocanurate

moulded in cylindrical foam 35 kg./m3 density

insulation with canvas / cloth to pipes

complete all in accordance with drawings andspecification

A 300 mm Dia 76 PI lin m 41.400 3,146.400 26.940

B 250 mm Dia 259 PI lin m 34.600 8,961.400 22.030

C 200 mm Dia 241 PI lin m 21.000 5,061.000 12.600

D 150 mm Dia 155 PI lin m 15.300 2,371.500 9.370

E 125 mm Dia 144 PI lin m 12.500 1,800.000 7.670

F 100 mm Dia 108 PI lin m 11.100 1,198.800 6.670

G 80 mm Dia 224 PI lin m 9.700 2,172.800 5.810

H 65 mm Dia 88 PI lin m 8.900 783.200 5.330

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Page 122: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 122/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

INSULATION PIPE (Cont'd)

A 50 mm Dia 22 PI lin m 6.100 131.150 3.370

B 40 mm Dia 195 PI lin m 5.900 1,150.500 3.290

C 32 mm Dia 64 PI lin m 5.400 345.600 2.960

D 25 mm Dia 186 PI lin m 5.000 930.000 2.710

Pre insulated Pipes laid below groundincluding all excavation/ rock(If any), bed and

backfilling, warning tape, thrust block,

complete with all in accordance with drawings

and specification

E 300 mm Dia 106 PIP lin m

F 125 mm dia 106 PIP lin m Inc in Bill 09

G 80 mm dia 106 PIP lin m

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Page 123: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 123/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

EQUIPMENT

Supply, installation, test & commission of

direct split unit including indoor and outdoor

units; complete with all refrigeration pipe work,

proprietary connectors, manifold andinsulation, all necessary electrical and

plumbing connection, fittings , supports, pipe

and cable containment, holding down bolts or

like all in accordance with specification ,

drawings and approval .

A IU-01/OU-01Split, 7kW cool ing capacity 1 SU nr. 440.500 440.500 345.084

Supply, installation, test & commission ofoutdoor unit for cold room freezers; complete

with refrigeration pipe work, proprietary

connectors, manifold and insulation, all

necessary electrical and plumbing connection,

fittings , supports, pipe and cable containment,

holding down bolts, DDC panels to connect

with BMS and like all in accordance with

specification and drawings to the Engineer

approval.

BODC-01 one working and one stand by , 7 kW

cooling capacity;7 CR ODU Set 605.700 4,239.900 495.084

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Page 124: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 124/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

Plate heat exchanger unit on steel frame

including base channels, double skin, with all

required dampers, 2 way motorized valve, sand

trap louver filters, cooling coils, heaterswherever shown on drawings , fans , fittings,

flexible connections and spring mount,

vibration damper .. as per capacity as specified

in drawings , specifications and to the Engineer

approval.

AAHU-2.2; 250 kW cooling capacity, 5010 L/s air

flow with plate heat exchanger1 AHU nr. 12090.900 12,090.900 10,105.430

B AHU-2.3 300 kW cooling capacity, 5980 L/s airflow with plate heat exchanger

1 AHU nr. 13106.700 13,106.700 10,959.040

CAHU-5.3; 420 kW cooling capacity, 4826 L/s air

flow with plate heat exchanger1 AHU nr. 13070.800 13,070.800 10,928.900

DAHU-5.4; 430 kW cooling capacity, 4929 L/s air

flow with plate heat exchanger1 AHU nr. 13070.800 13,070.800 10,928.900

51,339.200

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Page 125: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 125/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

Heat Recovery Air handling unit on steel frame

including base channels, double skin, with all

required dampers, 2 way motorized valve,cooling coils, heaters wherever shown on

drawings , fans , fittings, flexible connections

and spring mount, vibration damper, .. as per

capacity as specified in drawings ,

specifications and to the Engineer approval.

A AHU-1.1; 95 kW cooling capacity, 2389 L/s air flow 1 AHU nr. 5444.600 5,444.600 4,520.270

BAHU-1.2; 175 kW cooling capacity, 7147 L/s air

flow1 AHU nr. 10158.300 10,158.300 8,481.370

CAHU-1.3; 106 kW cooling capacity, 3480 L/s air

flow1 AHU nr. 6497.500 6,497.500 5,405.100

DAHU-1.4; 107 kW cooling capacity, 3657 L/s air

flow1 AHU nr. 6364.400 6,364.400 5,293.270

AHU-1 5; 195 kW cooling capacity 6845 L/s air

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Page 126: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 126/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

AHU (Cont'd)

AAHU-1.6; 108 kW cooling capacity, 2127 L/s air

flow1 AHU nr. 4812.900 4,812.900 3,989.440

BAHU-2.1; 115 kW cooling capacity, 4039 L/s air

flow1 AHU nr. 6944.700 6,944.700 5,780.890

CAHU-2.4; 187.5 kW cooling capacity, 6302 L/s air

flow1 AHU nr. 8839.200 8,839.200 7,372.880

DAHU-3.1; 123 kW cooling capacity, 4249 L/s air

flow1 AHU nr. 6995.700 6,995.700 5,823.730

EAHU-3.2; 130 kW cooling capacity, 4888 L/s air

flow1 AHU nr. 8009.300 8,009.300 6,675.520

35,601.800

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

UNIT RATE

Page 127: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 127/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

AHU (Cont'd)

AAHU-3.3; 169 kW cooling capacity, 5824 L/s air

flow1 AHU nr. 8807.600 8,807.600 7,346.380

B AHU-3.4; 87 kW cooling capacity, 3601 L/s air flow 1 AHU nr. 6496.700 6,496.700 5,404.370

CAHU-4.1; 135 kW cooling capacity, 4720 L/s air

flow1 AHU nr. 8312.500 8,312.500 6,930.290

DAHU-4.2; 180 kW cooling capacity, 7387 L/s air

flow1 AHU nr. 10198.000 10,198.000 8,514.770

EAHU-4.3; 120 kW cooling capacity, 4494 L/s air

flow1 AHU nr. 7034.600 7,034.600 5,856.410

F AHU-4.4; 90 kW cooling capacity, 2989 L/s air flow 1 AHU nr. 5709.400 5,709.400 4,742.840

GAHU-5.1; 182kW cooling capacity, 6688 L/s air

flow1 AHU nr. 9244.500 9,244.500 7,713.450

55,803.300

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

C d AMOUNT U i RUNIT RATE

Page 128: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 128/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

AHU (Cont'd)

A AHU-5.2;204 kW cooling capacity,7064 L/s air flow 1 AHU nr. 10077.900 10,077.900 8,413.840

SAND TRAP LOUVER

BProvide sand trap louver for all AHU's complete all

in accordance with drawings and specifications.1 ATD Item 5953.000 5,953.000 4,217.400

THERMOMETER

CProvide thermometer for AHUS , as shown on

drawings.44 V nr. 21.400 941.600 15.100

PRESSURE GAUGE UNIT

DProvide pressure gauges for AHUS , as shown on

drawings.44 V nr. 11.800 519.200 7.800

FAN COIL UNIT

Supply, Installation and commissioning the

following specified fan coil unit to suit the

indicated capacity, complete with coils, valves,

thermostatic controller, 2 way motorized valve,

filters including all accessories , plumbing and

electrical connection to complete theinstallation as per specification , described in

drawings and to the Engineer approval s

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT Unit RateUNIT RATE

Page 129: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 129/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

VARIABLE AIR VOLUME UNITS

Variable air volume units, by pass type

complete with thermostatic controller including

VAV heaters, accessories, electrical connection

and control wiring to complete the installationall in accordance with drawings and

specifications.

A VAV box 114 l/s air flow, inline 3 VAV nr. 119.200 357.600 91.348

B VAV box 117 l/s air flow, inline 4 VAV nr. 119.200 476.800 91.348

C VAV box 119 l/s air flow, inline 6 VAV nr. 119.200 715.200 91.348

D VAV box 122 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

E VAV box 123 l/s air flow, inline 3 VAV nr. 119.200 357.600 91.348

F VAV box 127 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

G VAV box 131 l/s air flow inline 6 VAV nr 119 200 715 200 91 348

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT Unit RateUNIT RATE

Page 130: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 130/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (cont'd)

VARIABLE AIR VOLUME UNITS (Cont'd)

A VAV box 133 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

B VAV box 138 l/s air flow, inline 6 VAV nr. 119.200 715.200 91.348

C VAV box 141 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

D VAV box 143 l/s air flow, inline 3 VAV nr. 119.200 357.600 91.348

E VAV box 146 l/s air flow, inline 3 VAV nr. 119.200 357.600 91.348

F VAV box 148 l/s air flow, inline 4 VAV nr. 119.200 476.800 91.348

G VAV box 152 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

H VAV box 134 l/s air flow, inline 2 VAV nr. 119.200 238.400 91.348

JVAV box 136 l/s air flow, inline

1 VAVnr.

119.200 119.200 91.348

2 622 400

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT Unit RateUNIT RATEITEM ESTIMATED

Page 131: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 131/300

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (cont'd)

VARIABLE AIR VOLUME UNITS (Cont'd)

A VAV box 154 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

B VAV box 175 l/s air flow, inline 1 VAV nr. 119.200 119.200 91.348

C VAV box 181 l/s air flow, inline 2 VAV nr. 119.200 238.400 91.348

D VAV box 200 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

E VAV box 210 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

F VAV box 324 l/s air flow, inline 4 VAV nr. 133.800 535.200 103.648

G VAV box 325 l/s air flow, inline 1 VAV nr. 133.800 133.800 103.648

1,402.000

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT Unit Rate UNIT RATE ITEM ESTIMATED

Page 132: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 132/300

Code AMOUNT  

Figures R.O. RO

UITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (cont'd)

VARIABLE AIR VOLUME UNITS (Cont'd)

A VAV box 211 l/s air flow, inline 2 VAV nr. 128.100 256.200 98.848

B VAV box 215 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

C VAV box 217 l/s air flow, inline 3 VAV nr. 128.100 384.300 98.848

D VAV box 218 l/s air flow, inline 18 VAV nr. 128.100 2,305.800 98.848

E VAV box 229 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

F VAV box 230 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

G VAV box 238 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

H VAV box 241 l/s air flow, inline 3 VAV nr. 128.100 384.300 98.848

J VAV box 245 l/s air flow, inline 1 VAV nr. 128.100 128.100 98.848

3 971 100

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM ESTIMATED

Page 133: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 133/300

Figures R.O. RO

ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (cont'd)

VARIABLE AIR VOLUME UNITS (Cont'd)

A VAV box 250 l/s air flow, inline 2 VAV nr. 128.100 256.200 98.848

B VAV box 259 l/s air flow, inline 9 VAV nr. 128.100 1,152.900 98.848

C VAV box 278 l/s air flow, inline 7 VAV nr. 128.100 896.700 98.848

D VAV box 287 l/s air flow, inline 1 VAV nr. 133.800 133.800 103.648

E VAV box 295 l/s air flow, inline 1 VAV nr. 133.800 133.800 103.648

F VAV box 304 l/s air flow, inline 4 VAV nr. 133.800 535.200 103.648

G VAV box 309 l/s air flow, inline 6 VAV nr. 133.800 802.800 103.648

3,911.400

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM ESTIMATED

Page 134: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 134/300

Figures R.O. RO

ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (cont'd)

VARIABLE AIR VOLUME UNITS (Cont'd)

A VAV box 329 l/s air flow, inline 2 VAV nr. 133.800 267.600 103.648

B VAV box 329 l/s air flow, fan assited 1 VAV nr. 133.800 133.800 103.648

C VAV box 351 l/s air flow, inline 1 VAV nr. 133.800 133.800 103.648

D VAV box 377 l/s air flow, inline 1 VAV nr. 133.800 133.800 103.648

E VAV box 378 l/s air flow, inline 1 VAV nr. 142.300 142.300 110.748

F VAV box 380 l/s air flow, inline 4 VAV nr. 142.300 569.200 110.748

G VAV box 391 l/s air flow, inline 7 VAV nr. 142.300 996.100 110.748

H VAV box 395 l/s air flow, fan assisted 15 VAV nr. 142.300 2,134.500 110.748

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

DESCRIPTIONESTIMATED 

UNIT

Page 135: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 135/300

Figures R.O. RO NO.

DESCRIPTION S

QUANTITY UNIT 

HVAC (cont'd)

VARIABLE AIR VOLUME UNITS (Cont'd)

A VAV box 457 l/s air flow, inline 4 VAV nr. 142.300 569.200 110.748

B VAV box 470 l/s air flow, fan assisted 2 VAV nr. 142.300 284.600 110.748

C VAV box 480 l/s air flow, fan assisted 3 VAV nr. 142.300 426.900 110.748

D VAV box 491 l/s air flow, inline 4 VAV nr. 142.300 569.200 110.748

E VAV box 566 l/s air flow, inline 1 VAV nr. 142.300 142.300 110.748

F VAV box 650 l/s air flow, inline 1 VAV nr. 151.500 151.500 118.548

G VAV box 669 l/s air flow, inline 1 VAV nr. 151.500 151.500 118.548

2,295.200

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

DESCRIPTIONESTIMATED 

UNIT

Page 136: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 136/300

Figures R.O. RO NO.

DESCRIPTION QUANTITY 

UNIT 

HVAC (cont'd)

VENTILATING FANS

Supply, installation, testing & commissioning

of ventilating fan with electrically operated

louvers, as specified on the drawings,complete with all mounting requirements,

flexible connections, electrical connections,

support, back draft dampers, auto changeover

controller, complete all in accordance with

drawings, specification and to the Engineer

approval.

ATwin Exhaust Fan Ref EXF-1; 375 air flow 150 Pa

static fan.1 EF nr. 620.300 620.300 510.300

B Twin Exhaust Fan Ref EXF-2; 450 air flow 150 Pastatic fan.

1 EF nr. 620.300 620.300 510.300

CTwin Exhaust Fan Ref EXF-3; 350 air flow 150 pa

static fan.1 EF nr. 516.200 516.200 422.820

DTwin Exhaust Fan Ref EXF-4; 150 air flow 75 Pa

static fan.1 EF nr. 542.300 542.300 444.690

ETwin Exhaust Fan Ref EXF-5; 575 air flow 150 Pa

static fan.1 EF nr. 629.000 629.000 517.590

FTwin Exhaust Fan Ref EXF-7; 1052 air flow 200 Pa

i f1 EF nr. 629.000 629.000 517.590

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

DESCRIPTIONESTIMATED 

UNIT

Page 137: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 137/300

Figures R.O. RO NO.

DESCRIPTION QUANTITY 

UNIT 

HVAC (cont'd)

ATwin Exhaust Fan Ref EXF-9; 225 air flow 150 Pa

static fan.1 EF nr. 620.300 620.300 510.300

BTwin Exhaust Fan Ref EXF-10; 870 air flow 150 Pa

static fan.1 EF nr. 620.300 620.300 510.300

CTwin Exhaust Fan Ref EXF-11; 1321 air flow 200

Pa static fan.1 EF nr. 1010.700 1,010.700 838.350

DTwin Exhaust Fan Ref EXF-12; 1000 air flow 200

Pa static fan1 EF nr. 811.200 811.200 670.680

ETwin Exhaust Fan Ref EXF-13; 875 air flow 150 Pa

static fan.1 EF nr. 620.300 620.300 510.300

FTwin Exhaust Fan Ref EXF-14; 1455 air flow 250

Pa static fan.1 EF nr. 1036.800 1,036.800 860.220

GTwin Exhaust Fan Ref EXF-15; 150 air flow 75 Pa

static fan.1 EF nr. 542.300 542.300 444.690

5,261.900

Construction of Haematology and BMT Centre Building- Issue

Bill 4 - Haematology and BMT Cen

Code AMOUNT   Unit Rate AmUNIT RATE ITEM 

NODESCRIPTION 

ESTIMATED 

QUANTITYUNIT 

Page 138: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 138/300

Figures R.O. RO RNO. QUANTITY 

HVAC (cont'd)

AKitchen Exhaust Fan Ref K-EXF; 650 air flow 150Pa static fan.

1 EF nr. 670.700 670.700 552.580

B Staircase Pressurization Fan Ref FAN-1T05; 9567air flow 350 Pa static fan.

5 EF nr. 1084.500 5,422.500 900.320 4

6,093.200 5,

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

NODESCRIPTION

ESTIMATED 

QUANTITYUNIT

Page 139: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 139/300

Figures R.O. RO NO.

DESCRIPTION QUANTITY 

UNIT 

Supply, installation, testing & commissioning

of ventilating fan with electrically operated

louvers, as specified on the drawings,

complete with all mounting requirements,

flexible connections, electrical connections,support, back draft dampers, auto changeover

controller, complete all in accordance with

drawings, specification and to the Engineer

approval.

A Smoke Exhaust Fan Ref S-EXF-1; 1 EF nr. 1485.300 1,485.300 1,237.110

B Smoke Exhaust Fan Ref S-EXF-2; 1 EF nr. 796.500 796.500 658.290

C Smoke Exhaust Fan Ref S-EXF-3; 1 EF nr. 950.000 950.000 787.320

D Smoke Exhaust Fan Ref S-EXF-4; 1 EF nr. 1009.900 1,009.900 837.620

E Smoke Exhaust Fan Ref S-EXF-5; 1 EF nr. 1485.300 1,485.300 1,237.110

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

NODESCRIPTION 

ESTIMATED 

QUANTITYUNIT 

Page 140: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 140/300

Figures R.O. RO NO. QUANTITY 

HVAC (cont'd)

A Smoke Exhaust Fan Ref S-EXF-7; 1 EF nr. 950.000 950.000 787.320

B Smoke Exhaust Fan Ref S-EXF-8; 1 EF nr. 1346.400 1,346.400 1,120.470

C Smoke Exhaust Fan Ref S-EXF-9; 1 EF nr. 1485.300 1,485.300 1,237.110

D Smoke Exhaust Fan Ref S-EXF-10; 1 EF nr. 910.100 910.100 753.790

E Smoke Exhaust Fan Ref S-EXF-11; 1 EF nr. 917.000 917.000 759.620

F Smoke Exhaust Fan Ref S-EXF-12; 1 EF nr. 1494.800 1,494.800 1,245.130

7,103.600

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

NODESCRIPTION 

ESTIMATED 

QUANTITYUNIT 

Page 141: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 141/300

Figures R.O. RO NO. QUANTITY 

HVAC (cont'd)

A Smoke Exhaust Fan Ref S-EXF-13; 1 EF nr. 950.000 950.000 787.320

B Smoke Exhaust Fan Ref S-EXF-14; 1 EF nr. 796.400 796.400 658.260

C Smoke Exhaust Fan Ref S-EXF-15; 1 EF nr. 1425.400 1,425.400 1,186.810

D Smoke Exhaust Fan Ref S-EXF-16; 1 EF nr. 1425.400 1,425.400 1,186.810

E Smoke Exhaust Fan Ref S-EXF-17; 1 EF nr. 910.100 910.100 753.790

5,507.300

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITYUNIT 

Page 142: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 142/300

Figures R.O. RO NO. QUANTITY 

HVAC (cont'd)

A Smoke Exhaust Fan Ref S-EXF-18; 1 EF nr. 950.000 950.000 787.320

B Smoke Exhaust Fan Ref S-EXF-19; 1 EF nr. 610.800 610.800 502.280

C Smoke Exhaust Fan Ref S-EXF-20; 1 EF nr. 730.500 730.500 602.880

D Smoke Exhaust Fan Ref S-EXF-21; 1 EF nr. 950.000 950.000 787.320

E Smoke Exhaust Fan Ref S-EXF-22; 1 EF nr. 1769.800 1,769.800 1,476.230

5,011.100

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITYUNIT 

Page 143: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 143/300

Figures R.O. RO NO. QUANTITY 

DUCT WORK

Supply and install Galvanized steel duct work

to HVAC DW-144 including control dampers,

fittings, joints, supports, hangers, stiffeners,

bends, black ends, bell mouths, protectivecoating , allow for acoustic lining, all required

accessories to complete installation as per

drawing and specification

ASupply G.I. Duct work 18 g. as per drawings based

on the size And associated insulation as per spec411 D kg 2.100 863.100 0.934

BSupply G.I. Duct work 20 g. as per drawings based

on the size And associated insulation as per spec3,105 D kg 2.000 6,210.000 0.888

CSupply G.I. Duct work 22 g. as per drawings based

on the size And associated insulation as per spec16,146 D kg 2.000 32,292.000 0.868

DSupply G.I. Duct work 24 g. as per drawings based

on the size And associated insulation as per spec18,885 D kg 2.400 45,324.000 1.071

EReturn G.I. Duct work 18 g. as per drawings based

on the size And associated insulation as per spec948 D kg 2.100 1,990.800 0.934

F Return G.I. Duct work 20 g. as per drawings basedon the size And associated insulation as per spec

542 D kg 2.000 1,084.000 0.888

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 144: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 144/300

Figures R.O. RO O QU

DUCT WORK

AReturn G.I. Duct work 24 g. as per drawings based

on the size as per spec15,843 D kg 2.400 38,023.200 1.071

B Exhaust G.I. Duct work 24 g. as per drawingsbased on the size as per spec

3,393 D kg 2.400 8,143.200 1.071

CExhaust G.I. Duct work 22 g. as per drawings

based on the size as per spec419 D kg 2.000 838.000 0.868

DExhaust G.I. Duct work 18 g. as per drawings

based on the size as per spec95 D kg 2.100 199.500 0.934

EFresh air intake G.I. Duct work 18 g. as per

drawings based on the size as per spec

34 D kg 2.100 71.400 0.934

FGeneral exhaust air intake G.I. Duct work 18 g. as

per drawings based on the size as per spec401 D kg 2.100 842.100 0.934

GToilet exhaust air intake G.I. Duct work 18 g. as

per drawings based on the size as per spec514 D kg 2.100 1,079.400 0.934

H

Allow for flexible connections; Flexible duct

connections to plenum boxes, grills and diffusers;

Anchor expansion loops, support for pipes and

duct work at expansion joint as applicable

1 D Item 6900.300 6,900.300 5,000.000

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Fi R O RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 145: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 145/300

Figures R.O. RO

DUCT WORK

Thermal insulation, as specified

A

Allow for access doors and panels for duct work

adjacent to fire damper as per required and

approval of HVAC Engineer/tender document/site

condition

1 Item 0.000 Excluded

B

40 mm thick , 48 kg/m3 Fibre reinforced

aluminium foil faced rigid fibreglass fixed to

ductwork and finished with 8 oz glass . Cora cloth

and three coats of vapour barrier as speified in

specification

12,421 DI sq m 7.900 98,125.900 3.877

C50 mm thick, expanded polystyrene rigid boards 35

kg/m3 insulation system to exposed/external

ductwork as specified.

1 DI Item 25018.100 25,018.100 12,546.526

D0.8 mm thick hammered aluminium cladding finish

to exposed ducts and pipes1 AL Item 26797.900 26,797.900 16,616.607

Acoustic insulation, as specified

E

25 mm thick, 48kg/m3 density sound absorbent

lining to ductwork, internally upto 8 meter distance

from HVAC unit outlet and to all supply / return air

plenums. .

1 A Item 21721.500 21,721.500 9,209.050

FTenderers are required to price for the complete

requirement of motorized volume control damper .

required

1 ATD Item 6664.500 6,664.500 4,585.100

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R O RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 146: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 146/300

Figures R.O. RO

Volume Control Damper (VCD)

Supply and install volume control damper as

per specification and tender drawings, sizes

shown below

A 150 x 100 mm 6 ATD nr. 9.400 56.400 6.000

B 200 x 100 mm 6 ATD nr. 9.800 58.800 6.300

C 250 x 100 mm 30 ATD nr. 10.200 306.000 6.600

D 300 x 100 mm 54 ATD nr. 10.300 556.200 6.700

E 350 x 100 mm 18 ATD nr. 11.000 198.000 7.200

F 350x150 mm 42 ATD nr. 9.800 411.600 6.300

G 400 x150 mm 48 ATD nr. 12.300 590.400 8.200

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R O RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 147: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 147/300

Figures R.O. RO

Volume Control Damper (VCD) (cont'd)

A 400 x 250 mm 36 ATD nr. 16.300 586.800 11.200

B 450 x 150 mm 30 ATD nr. 13.000 390.000 8.700

C 450 x 200 mm 12 ATD nr. 16.400 196.800 11.300

D 450 x 200 mm 12 ATD nr. 16.400 196.800 11.300

E 450 x 250 mm 12 ATD nr. 16.400 196.800 11.300

F 500 x 200 mm 6 ATD nr. 17.200 103.200 11.900

G 500 x 250 mm 7 ATD nr. 17.800 124.600 12.400

1,795.000

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 148: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 148/300

Figures R.O. RO

Volume Control Damper (VCD) (cont'd)

A 500 x 350 mm 6 ATD nr. 19.200 115.200 13.400

B 550 x 100 mm 6 ATD nr. 14.200 85.200 9.100

C 550 x 150 mm 8 ATD nr. 14.900 119.200 9.600

D 550 x 250 mm 6 ATD nr. 19.400 116.400 13.000

E 550 x 300 mm 26 ATD nr. 20.000 520.000 13.500

F 800 x 400 mm 7 ATD nr. 33.200 232.400 23.500

G 950 x 600 mm 9 ATD nr. 62.500 562.500 45.600

1,750.900

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 149: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 149/300

gu es O O

Volume Control Damper (VCD) (cont'd)

A 1200 x 500 mm 19 ATD nr. 60.500 1,149.500 43.000

B 1200 x 600 mm 12 ATD nr. 69.900 838.800 50.100

Fire Damper(FD)

Supply and install Fire damper as per

specification and tender drawings, sizes shown

below

C 200 x 100 mm 1 ATD nr. 14.300 14.300 9.200

D 200 x 150 mm 1 ATD nr. 15.300 15.300 9.900

E 250 x 100 mm 1 ATD nr. 15.100 15.100 9.800

F 300 x 100 mm 2 ATD nr. 15.900 31.800 10.400

G 300 x 200 mm 5 ATD nr. 17.800 89.000 11.800

H 300 x 250 mm 2 ATD nr. 19.000 38.000 12.700

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 150: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 150/300

g

Fire Damper (FD) (cont'd)

A 350 X 100 mm 3 ATD nr. 17.600 52.800 11.700

B 350 x 200 mm 2 ATD nr. 19.600 39.200 13.200

C 350 x 250 mm 1 ATD nr. 20.200 20.200 13.600

D 400 x 150 mm 6 ATD nr. 19.800 118.800 13.300

E 400 x 200 mm 5 ATD nr. 20.600 103.000 13.900

F 450 x 200 mm 2 ATD nr. 21.500 43.000 14.600

G 500 x 200 mm 3 ATD nr. 22.400 67.200 15.300

H 500 x 250 mm 4 ATD nr. 23.900 95.600 16.400

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 151: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 151/300

Fire Damper (FD) (cont'd)

A 500 x 350 mm 1 ATD nr. 26.900 26.900 18.700

B 550 x 250 mm 1 ATD nr. 25.500 25.500 17.100

C 550 x 300 mm 1 ATD nr. 27.100 27.100 18.300

D 550 x 350 mm 1 ATD nr. 28.800 28.800 19.600

E 550 x 650 mm 5 ATD nr. 41.600 208.000 29.300

F 600 x 250 mm 2 ATD nr. 26.600 53.200 17.900

G 600 x 300 mm 1 ATD nr. 28.200 28.200 19.100

H 650 x 250 mm 1 ATD nr. 28.400 28.400 19.300

J 650 x 300 mm 1 ATD nr 30 300 30 300 20 700

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 152: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 152/300

Fire Damper (FD) (cont'd)

A 650 x 450 mm 1 ATD nr. 39.300 39.300 27.500

B 750 x 500 mm 2 ATD nr. 43.900 87.800 31.000

C 800 x 350 mm 3 ATD nr. 39.000 117.000 27.300

D 800 x 700 mm 1 ATD nr. 52.500 52.500 37.500

E 850 x 400 mm 1 ATD nr. 51.800 51.800 37.000

F 850 x 450 mm 3 ATD nr. 54.700 164.100 39.200

G 850 x 550 mm 2 ATD nr. 59.100 118.200 42.500

H 900 x 300 mm 1 ATD nr. 47.100 47.100 33.400

J 900 x 450 mm 2 ATD nr 56 000 112 000 40 200

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 153: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 153/300

Fire Damper (FD) (cont'd)

A 900 x 550 mm 1 ATD nr. 60.400 60.400 43.500

B 900 x 600 mm 1 ATD nr. 68.900 68.900 49.900

C 900 x 800 mm 3 ATD nr. 74.200 222.600 53.900

D 950 x 500 mm 1 ATD nr. 183.000 183.000 136.200

E 950 x 600 mm 55 ATD nr. 60.500 3,327.500 43.600

F 950 x 800 mm 1 ATD nr. 85.900 85.900 62.800

G 1000 x 500 mm 2 ATD nr. 71.900 143.800 51.100

H 1000 x 550 mm 2 ATD nr. 71.900 143.800 51.100

J 1000 x 600 mm 1 ATD nr 76 300 76 300 54 400

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 154: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 154/300

Fire Damper (FD) (cont'd)

A 1000 x 650 mm 2 ATD nr. 82.100 164.200 58.800

B 1000 x 700 mm 2 ATD nr. 85.500 171.000 61.400

C 1000 x 750 mm 2 ATD nr. 89.100 178.200 64.100

D 1000 x 800 mm 6 ATD nr. 114.600 687.600 83.400

E 1000 x 850 mm 1 ATD nr. 144.700 144.700 106.200

F 1000 x 1150 mm 2 ATD nr. 71.900 143.800 51.100

G 1050 x 500 mm 2 ATD nr. 80.100 160.200 57.300

H 1050 x 650 mm 1 ATD nr. 81.700 81.700 58.500

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 155: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 155/300

Fire Damper (FD) (cont'd)

A 1100 x 650 mm 1 ATD nr. 81.700 81.700 58.500

B 1100 x 700 mm 1 ATD nr. 85.400 85.400 61.300

C 1100 x 750 mm 1 ATD nr. 89.000 89.000 64.000

D 1150 x 500 mm 2 ATD nr. 74.700 149.400 53.200

E 1200 x 500 mm 2 ATD nr. 76.100 152.200 54.300

F 1200 x 600 mm 3 ATD nr. 81.200 243.600 58.100

G 1200 x 650 mm 1 ATD nr. 84.900 84.900 60.900

H 1200 x 700 mm 3 ATD nr. 88.600 265.800 63.700

J 1200 x 900 mm 1 ATD nr 140 000 140 000 102 600

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 156: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 156/300

Fire Damper (FD) (cont'd)

A 1250 x 500 mm 1 ATD nr. 79.400 79.400 56.800

B 1250 x 800 mm 18 ATD nr. 100.100 1,801.800 72.400

C 1300 x 850 mm 2 ATD nr. 148.400 296.800 109.000

D 1350 x 900 mm 2 ATD nr. 152.300 304.600 111.900

E 1400 x 700 mm 1 ATD nr. 97.000 97.000 70.100

F 1500 x 700 mm 1 ATD nr. 101.100 101.100 72.600

G 1500 x 750 mm 1 ATD nr. 105.400 105.400 75.900

H 1500 x 800 mm 1 ATD nr. 106.900 106.900 77.000

J 1600 x 700 mm 2 ATD nr 104 400 208 800 75 100

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 157: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 157/300

Diffusers

Supply, install, test and commission Supply

diffuser (600 x 600 mm face) Aluminum powder

coated with volume damper and complete with

all required accessories, quantity of air flow .

as per schedule in the drawing

A Supply diffuser 150 x 150 mm 21 ATD nr. 64.800 1,360.800 47.400

B Supply diffuser 225 x 225 mm 193 ATD nr. 64.800 12,506.400 47.400

C Supply diffuser 300 x 100 mm 11 ATD nr. 64.800 712.800 47.400

D Supply diffuser 300 x 300 mm 293 ATD nr. 64.800 18,986.400 47.400

E Supply diffuser 375 x 375 mm 78 ATD nr. 64.800 5,054.400 47.400

F Supply diffuser 450 x 450 mm 13 ATD nr. 64.800 842.400 47.400

G Supply diffuser 500 x 200 mm 5 ATD nr 64 800 324 000 47 400

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 158: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 158/300

Supply, install, test and commission Return

diffuser (600 x 600 mm face) Aluminum powder

coated with volume damper and complete with

all required accessories, quantity of air flow .

as per schedule in the drawing

A Return diffuser 225 x 225 mm 142 ATD nr. 29.300 4,160.600 20.500

B Return diffuser 225 x 255 mm 11 ATD nr. 29.300 322.300 20.500

C Return diffuser 300 x 100 mm 7 ATD nr. 29.300 205.100 20.500

D Return diffuser 300 x 300 mm 242 ATD nr. 29.300 7,090.600 20.500

E Return diffuser 375 x 375 mm 72 ATD nr. 29.300 2,109.600 20.500

F Return diffuser 450 x 450 mm 7 ATD nr. 29.300 205.100 20.500

G Return diffuser 500 x 200 mm 5 ATD nr. 29.300 146.500 20.500

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 159: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 159/300

Exhaust Diffuser

Supply, install, test and commission Exhaust

diffuser Aluminum power coated with

complete with all required accessories,

quantity of air flow . as per schedule in the

drawing

A Exhaust diffuser 150 x150 mm 118 ATD nr. 8.700 1,026.600 4.900

B Exhaust diffuser 225 x 225 mm 29 ATD nr. 17.600 510.400 11.700

C Exhaust diffuser 225 x 255 mm 2 ATD nr. 17.600 35.200 11.700

D Exhaust diffuser 300 x 100 mm 3 ATD nr. 17.600 52.800 11.700

E Exhaust diffuser 300 x 300 mm 50 ATD nr. 17.600 880.000 11.700

F Exhaust diffuser 375 x 375 mm 6 ATD nr. 24.000 144.000 16.500

G Exhaust diffuser 450 x 450 mm 3 ATD nr. 31.300 93.900 22.000

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 160: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 160/300

Supply Grilles

Supply, install, test and commission Supply

Grilles complete with all required accessories,

quantity of air flow .. as per schedule in the

drawing

A Supply Grille 200 x 100 mm 4 ATD nr. 4.800 19.200 2.300

B Supply Grille 225 x 225 mm 2 ATD nr. 7.800 15.600 4.600

C Supply Grille 300 x 100 mm 46 ATD nr. 6.000 276.000 3.200

D Supply Grille 350 x 150 mm 1 ATD nr. 8.100 8.100 4.800

E Supply Grille 400 x 150 mm 3 ATD nr. 8.900 26.700 5.400

F Supply Grille 500 x 100 mm 3 ATD nr. 8.500 25.500 5.100

G Supply Grille 500 x 150 mm 8 ATD nr. 10.600 84.800 6.700

H Supply Grille 500 x 200 mm 1 ATD nr. 12.600 12.600 8.200

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 161: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 161/300

Return Grill

Supply, install, test and commission return

grilles complete with all required accessories,

quantity of air flow .. as per schedule in the

drawing

A Return Grille 200 x 100 mm 4 ATD nr. 3.900 15.600 1.600

B Return Grille 300 x 100 mm 11 ATD nr. 4.500 49.500 2.100

C Return Grille 400 x 150 mm 3 ATD nr. 6.400 19.200 3.500

D Return Grille 500 x 100 mm 3 ATD nr. 6.100 18.300 3.300

E Return Grille 500 x 150 mm 7 ATD nr. 7.400 51.800 4.300

F Return Grille 500 x 200 mm 1 ATD nr. 8.600 8.600 5.200

163.000

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 162: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 162/300

Exhaust Grill

Supply, install, test and commission Exhaust

Grilles complete with all required accessories,

quantity of air flow .. as per schedule in the

drawing

A Exhaust Grille 200 x 100 mm 7 ATD nr. 3.900 27.300 1.600

B Exhaust Grille 300 x 100 mm 14 ATD nr. 4.500 63.000 2.100

C Exhaust Grille 350 x 150 mm 1 ATD nr. 5.800 5.800 3.100

D Exhaust Grille 500 x 150 mm 1 ATD nr. 7.400 7.400 4.300

E Exhaust Grille 1210 x 610 mm 7 ATD nr. 46.100 322.700 31.600

426.200

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 163: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 163/300

HVAC INSTALLATIONS

Exhaust cowl

Supply, install , test and commission Exhaust

cowl, complete with SS bird screen, all required

accessories and as hown on drawings.

A 45 Degree cowl size 300 x 150 mm 1 ATD nr. 4.400 4.400

B 45 Degree cowl size 300 x 200 mm 1 ATD nr. 4.400 4.400

C 45 Degree cowl size 400 x 200 mm 2 ATD nr. 4.400 8.800

D 45 Degree cowl size 400 x 250 mm 1 ATD nr. 4.400 4.400

E 45 Degree cowl size 500 x 300 mm 1 ATD nr. 4.400 4.400

F 45 Degree cowl size 550 x 200 mm 1 ATD nr. 4.400 4.400

G 45 Degree cowl size 550 x 300 mm 2 ATD nr. 4.400 8.800

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 164: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 164/300

Exhaust cowl

Supply, install , test and commission Exhaust

cowl, complete with SS bird screen, all required

accessories and as hown on drawings.

A 45 Degree cowl size 650 x 200 mm 1 ATD nr. 73.100 73.100 52.000

B 45 Degree cowl size 650 x 350 mm 1 ATD nr. 124.700 124.700 91.000

C 45 Degree cowl size 750 x 350 mm 1 ATD nr. 143.200 143.200 105.000

D 45 Degree cowl size 750 x 750 mm 6 ATD nr. 301.800 1,810.800 225.000

E 45 Degree cowl size 800 x 700 mm 1 ATD nr. 300.500 300.500 224.000

F 45 Degree cowl size 900 x 600 mm 1 ATD nr. 289.900 289.900 216.000

G 45 Degree cowl size 950 x 800 mm 1 ATD nr. 406.200 406.200 304.000

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 165: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 165/300

Exhaust cowl (Cont'd)

A 45 Degree cowl size 1000 x 750 mm 2 ATD nr. 400.900 801.800 300.000

B 45 Degree cowl size 1000 x 800 mm 1 ATD nr. 427.400 427.400 320.000

C 45 Degree cowl size 1000 x 900 mm 1 ATD nr. 480.200 480.200 360.000

D 45 Degree cowl size 1000 x 950 mm 1 ATD nr. 506.700 506.700 380.000

E 45 Degree cowl size 1100 x 750 mm 1 ATD nr. 440.600 440.600 330.000

F 45 Degree cowl size 1100 x 800 mm 1 ATD nr. 469.700 469.700 352.000

G 45 Degree cowl size 1200 x 700 mm 1 ATD nr. 448.500 448.500 336.000

H 45 Degree cowl size 1250 x 800 mm 1 ATD nr. 533.100 533.100 400.000

J 45 Degree cowl size 1300 x 850 mm 1 ATD nr. 588.600 588.600 442.000

K 45 Degree cowl size 1350 x 900 mm 1 ATD nr 646.800 646.800 486.000

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Mi ll

Page 166: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 166/300

Miscellaneous

AAllow for connection to al l return, Exhaust, fresh

and supply ducts as necessary at FCU AHU and

extract fans,

1 D Item 733.700 733.700 500.000

B

Allow for Control System for fan coil units including

interconnecting wiring for all control items, motors,sensors and the like as per specification

1 CS Item 0.000 -

C Ditto for Air Handling Units 1 CS Item 0.000 -

D Ditto for Fresh Air handling units 1 CS Item 0.000 -

E Ditto for smoke exhaust fans 1 CS Item 0.000 -

FAllow for Control System for Extract Fan including

interconnecting wiring for all control items, motors,

sensors and the like as per specification

1 CS Item 0.000 -

733.700

Construction of Haematology and BMT Centre Building- Issu

Bill 4 - Haematology and BMT Cen

Code AMOUNT   Unit Rate Am

Figures R.O. RO R

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Allow for providing all necessary BMS control

Page 167: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 167/300

A

Allow for providing all necessary BMS control

system including, DDC panels, work stations

interconnecting wiring, for all control items, motors,

sensors and in the installation of control panels,

sensors/ remote set points, switches, control

valves, thermostats, wiring ., and operation of the

complete BMS installation air-conditioning andventilating system comprising with commissioning

of BMS system.

1 CS Item 137596.000 137,596.000 101,650.000 101

137,596.000 101

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

 

HVAC INSTALLATION

Page 168: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 168/300

HVAC INSTALLATION

COLLECTION AMOUNT, R.O., IN FIGURES

Page HB-HVAC- Page 171,339.500 -

Page HB-HVAC- Page 24,505.050 -

Page HB-HVAC- Page 325,495.100 -

Page HB-HVAC- Page 42,651.250 -

Page HB-HVAC- Page 54,680.400 -

Page HB-HVAC- Page 651,339.200 -

Page HB-HVAC- Page 737,602.100 -

Page HB-HVAC- Page 835,601.800 -

Page HB-HVAC- Page 955,803.300 -

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC INSTALLATION

Page 169: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 169/300

HVAC INSTALLATION

COLLECTION (Cont'd) AMOUNT, R.O., IN FIGURES

Brought Forward 317,520.600 -

Page HB-HVAC- Page 113,099.200 -

Page HB-HVAC- Page 122,622.400 -

Page HB-HVAC- Page 131,402.000 -

Page HB-HVAC- Page 143,971.100 -

Page HB-HVAC- Page 15

3,911.400 -

Page HB-HVAC- Page 164,653.400 -

Page HB-HVAC- Page 172,295.200 -

Page HB-HVAC- Page 184,186.100 -

Page HB-HVAC- Page 19 5 261 900

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC INSTALLATION

Page 170: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 170/300

HVAC INSTALLATION

COLLECTION (Cont'd) AMOUNT, R.O., IN FIGURES

Brought Forward 362,228.800 -

Page HB-HVAC- Page 227,103.600 -

Page HB-HVAC- Page 235,507.300 -

Page HB-HVAC- Page 245,011.100 -

Page HB-HVAC- Page 25121,965.900 -

Page HB-HVAC- Page 26

56,097.100 -

Page HB-HVAC- Page 27198,577.600 -

Page HB-HVAC- Page 282,177.400 -

Page HB-HVAC- Page 291,795.000 -

Page HB-HVAC- Page 30 1 750 900

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC INSTALLATION

Page 171: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 171/300

HVAC INSTALLATION

COLLECTION (Cont'd) AMOUNT, R.O., IN FIGURES

Brought Forward 764,946.300 -

Page HB-HVAC- Page 33456.400 -

Page HB-HVAC- Page 34789.800 -

Page HB-HVAC- Page 354,312.200 -

Page HB-HVAC- Page 361,731.400 -

Page HB-HVAC- Page 37

1,292.000 -

Page HB-HVAC- Page 383,210.700 -

Page HB-HVAC- Page 3940,500.000 -

Page HB-HVAC- Page 4014,591.400 -

Page HB-HVAC- Page 41 2 742 900

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC INSTALLATION

Page 172: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 172/300

COLLECTION (Cont'd) AMOUNT, R.O., IN FIGURES

Brought Forward 835,690.700 - 5

Page HB-HVAC- Page 44

426.200 -

Page HB-HVAC- Page 45

44.000 -

Page HB-HVAC- Page 46

3,470.000 -

Page HB-HVAC- Page 47

5,982.300 -

Page HB-HVAC- Page 48

733.700 -

Page HB-HVAC- Page 49

137,596.000 - 1

983,942.900 - 6

Construction of Haematology and BMT Centre Building- Iss

Bill 4 - Haematology and BMT Ce

Code AMOUNT   Unit Rate A

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Additional Items

Page 173: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 173/300

Additional valves for pumps 1 V 9559.800 9,559.800 7,121.840

Additional valves for chillers 1 V 6195.900 6,195.900 4,577.100

Hepa filter for sterile room 375x375mm 4 ATD 2716.500 10,866.000 2,000.000

0.000 -

0.000 -

0.000 -

26,621.700 1

Construction of Haematology and BMT Centre Building- Is

Bill 4 - Haematology and BMT C

Code AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Total BOQ + Additional 1,010,564.600 -

Page 174: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 174/300

Items Qty Code Make Discount Total Mat Total Mhr To

Acoustic Insulation 1.00 A 9,209.050 6,566.320

Air handling units 22.00 AHU 158,810.500 1,100.000Al cladding 1.00 AL 16,616.607 3,323.321

Air terminal devices 2130.00 ATD 95,446.400 4,602.200

Chillers 0.00 C - -

Cold room outdoor unit 7.00 CR ODU 3,465.591 350.000

Control system(BMS) 6.00 CS 101,650.000 12,706.250

Ducting 77839.00 D 81,030.135 48,222.834

Ducting insulation 12422.00 DI 60,700.151 29,150.889

Dosing system 0.00 DS - -

Extract fans 42.00 EF 33,466.920 420.000

Fan coil unit 32.00 FCU 8,549.900 640.000Piping 1761.50 P 42,280.455 13,715.100

Piping insulation 1761.50 PI 17,244.985 3,636.150

Pre insulated piping 318.00 PIP - -

Pumps 0.00 PUMP - -

Pressurisation unit 0.00 PU - -

Split units 1.00 SU 345.084 50.000

Valves 100.00 V 12,766.540 298.000

Varaiable air volume 169.00 VAV 16,960.112 1,352.000

658,542.429 126,133.065

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 175: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 175/300

7,036.080 

19,303.270 

12,483.800 

5,173.900 

4,010.400 

2,336.580 

3,626.560 

53,970.590 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

1,028.720 

Page 176: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 176/300

,0 8 0

150.715 

1,131.000 

330.880 

755.160 

3,396.475 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 177: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 177/300

2,381.840 

6,788.390 

3,831.900 

1,793.350 

1,357.920 

910.440 

1,646.400 

590.040 

19,300.280 

Construction of Haematology and BMT Centre Building- Issued for Tend

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

98.470 

Page 178: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 178/300

877.500 

259.840 

708.660 

71.000 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 179: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 179/300

400.084 

3,850.591 

4,250.675 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 180: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 180/300

10,160.430 

11,014.040 

10,983.900 

10,983.900 

43,142.270 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 181: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 181/300

4,575.270 

8,536.370 

5,460.100 

5,348.270 

7,678.410 

31,598.420 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

4,044.440 

Page 182: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 182/300

5,835.890 

7,427.880 

5,878.730 

6,730.520 

29,917.460 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

7,401.380 

Page 183: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 183/300

5,459.370 

6,985.290 

8,569.770 

5,911.410 

4,797.840 

7,768.450 

46,893.510 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

8,468.840 

Page 184: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 184/300

4,503.400 

712.800 

391.600 

9,253.900 

23 330 540

Construction of Haematology and BMT Centre Building- Issued for Tend

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 185: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 185/300

300.444 

400.592 

600.888 

100.148 

300.444 

100.148 

600.888 

200.296 

2 603 848

Construction of Haematology and BMT Centre Building- Issued for Tend

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

100.148 

Page 186: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 186/300

600.888 

100.148 

300.444 

300.444 

400.592 

100.148 

200.296 

100.148 

2,203.256 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

100.148 

Page 187: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 187/300

100.148 

200.296 

107.648 

107.648 

449.792 

112.448 

1,178.128 

Construction of Haematology and BMT Centre Building- Issued for Tend

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

215.296 

Page 188: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 188/300

107.648 

322.944 

1,937.664 

107.648 

107.648 

107.648 

322.944 

107.648 

3,337.088 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

215.296 

Page 189: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 189/300

968.832 

753.536 

112.448 

112.448 

449.792 

674.688 

3,287.040 

Construction of Haematology and BMT Centre Building- Issued for Tend

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

224.896 

Page 190: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 190/300

112.448 

112.448 

112.448 

119.548 

478.192 

836.836 

1,793.220 

119.548 

3,909.584 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

478.192 

Page 191: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 191/300

239.096 

358.644 

478.192 

119.548 

127.348 

127.348 

1,928.368 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 192: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 192/300

521.300 

521.300 

433.820 

455.690 

528.590 

528.590 

528.590 

3,517.880 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

521.300 

521 300

Page 193: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 193/300

521.300 

849.350 

681.680 

521.300 

871.220 

455.690 

4,421.840 

Construction of Haematology and BMT Centre Building- Issued for TenderBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

563.580 

4,556.600 

Page 194: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 194/300

5,120.180 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 195: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 195/300

1,248.110 

669.290 

798.320 

848.620 

1,248.110 

1,248.110 

6,060.560 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

798.320 

1,131.470 

Page 196: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 196/300

,

1,248.110 

764.790 

770.620 

1,256.130 

5,969.440 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

798.320 

669.260 

Page 197: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 197/300

1,197.810 

1,197.810 

764.790 

4,627.990 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

798.320 

513.280 

Page 198: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 198/300

613.880 

798.320 

1,487.230 

4,211.030 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 199: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 199/300

648.294 

4,675.873 

24,300.781 

33,859.470 

1,495.336 

816.207 

25,738.119 

91,534.080 

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

28,405.379 

6,083.409 

Page 200: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 200/300

630.622 

149.849 

53.630 

632.521 

810.762 

5,220.000 

41,986.172 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 201: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 201/300

73,840.252 

18,925.876 

20,272.261 

16,432.002 

5,041.600 

15,318.600 

149,830.591

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

42.600 

Page 202: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 202/300

44.400 

231.000 

421.200 

149.400 

310.800 

446.400 

1,645.800 

Construction of Haematology and BMT Centre Building- Issued for TendeBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

442.800 

294 000

Page 203: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 203/300

294.000 

148.800 

148.800 

148.800 

78.000 

94.500 

1,355.700 

Construction of Haematology and BMT Centre Building- Issued for TendeBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

87.000 

64.500 

Page 204: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 204/300

90.000 

87.900 

393.900 

176.050 

425.250 

1,324.600 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

869.250 

634.200 

Page 205: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 205/300

10.850 

11.550 

11.450 

24.100 

67.250 

28.700 

1,657.350 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

40.050 

29.700 

Page 206: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 206/300

15.250 

89.700 

77.750 

32.500 

50.850 

72.200 

408.000 

Construction of Haematology and BMT Centre Building- Issued for TenBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

20.350 

19.300 

Page 207: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 207/300

20.500 

21.800 

157.500 

40.200 

21.300 

21.500 

22.900 

345.350 

Construction of Haematology and BMT Centre Building- Issued for TenBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

29.700 

66.400 

Page 208: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 208/300

88.500 

39.700 

39.200 

124.200 

89.400 

35.600 

84.800 

597.500 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

45.700 

52.100 

Page 209: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 209/300

168.300 

138.400 

2,519.000 

65.000 

108.800 

108.800 

57.700 

3,263.800 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

124.200 

129.400 

Page 210: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 210/300

134.800 

520.200 

109.500 

108.800 

121.200 

61.800 

1,309.900 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

61.800 

64.600 

Page 211: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 211/300

67.300 

113.000 

115.200 

184.200 

64.200 

201.000 

105.900 

977.200 

Construction of Haematology and BMT Centre Building- Issued for TenBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

60.100 

1,362.600 

Page 212: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 212/300

224.600 

230.400 

73.400 

76.450 

79.750 

80.850 

157.900 

82.350 

Construction of Haematology and BMT Centre Building- Issued for TendeBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

Page 213: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 213/300

1,030.050 

9,466.650 

539.550 

14,371.650 

3,825.900 

637.650 

245.250 

539.550 

30 656 250

Construction of Haematology and BMT Centre Building- Issued for TendeBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

3,145.300 

Page 214: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 214/300

,

243.650 

155.050 

5,360.300 

1,594.800 

155.050 

110.750 

265.800 

11,030.700 

Construction of Haematology and BMT Centre Building- Issued for TendeBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

772.900 

Page 215: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 215/300

387.150 

26.700 

40.050 

667.500 

108.900 

70.950 

2,074.150 

Construction of Haematology and BMT Centre Building- Issued for TenBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

14.480 

Page 216: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 216/300

11.840 

207.920 

6.120 

20.160 

19.260 

64.160 

9.520 

352.940 

14.480 

Construction of Haematology and BMT Centre Building- Issued for TenderBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

11.680 

Page 217: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 217/300

37.620 

14.460 

13.860 

39.340 

6.520 

123.480 

Construction of Haematology and BMT Centre Building- Issued for TenderBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

20.440 

Page 218: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 218/300

47.880 

4.420 

5.620 

244.300 

322.660 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

3.300 

Page 219: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 219/300

3.300 

6.600 

3.300 

3.300 

3.300 

6.600 

3.300 

33.000 

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

55.300 

Page 220: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 220/300

94.300 

108.300 

1,369.800 

227.300 

219.300 

307.300 

243.300 

2,624.900 

Construction of Haematology and BMT Centre Building- Issued for TenBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

606.600 

323.300 

363.300 

Page 221: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 221/300

383.300 

333.300 

355.300 

339.300 

403.300 

445.300 

489.300 

483.300 

4 525 600

Construction of Haematology and BMT Centre Building- Issued for Tende

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

555.000 

-

Page 222: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 222/300

 

555.000 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

115,626.875 

115,626.875 

Page 223: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 223/300

Construction of Haematology and BMT Centre Building- Issued for TendBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

53,970.590 

3,396.475 

Page 224: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 224/300

19,300.280 

2,015.470 

4,250.675 

43,142.270 

31,598.420 

29,917.460 

46,893.510 

23,330.540 

257,815.690 

Construction of Haematology and BMT Centre Building- Issued for TeBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

257,815.690 

2,603.848 

2,203.256 

Page 225: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 225/300

1,178.128 

3,337.088 

3,287.040 

3,909.584 

1,928.368 

3,517.880 

4,421.840 

5,120.180 

Construction of Haematology and BMT Centre Building- Issued for TenBill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

295,383.462 

5,969.440 

4,627.990 

Page 226: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 226/300

4,211.030 

91,534.080 

41,986.172 

149,830.591 

1,645.800 

1,355.700 

1,324.600 

1,657.350 

Construction of Haematology and BMT Centre Building- Issued for Te

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

599,934.215 

345.350 

597.500 

Page 227: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 227/300

3,263.800 

1,309.900 

977.200 

2,428.400 

30,656.250 

11,030.700 

2,074.150 

720.880 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

653,461.825 

322.660 

33.000 

Page 228: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 228/300

2,624.900 

4,525.600 

555.000 

115,626.875 

777,149.860 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

7,231.840 

4,687.100 

8,220.000 

Page 229: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 229/300

20,138.940 

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill 4 - Haematology and BMT Centre

Amount (R.O.) 

(R.O.)

797,288.800 

Page 230: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 230/300

Construction of Haematology and BMT Centre Building - Is

Bill 5 - Corridor Connection

CODE AMOUNT   Unit Rate Amount

Figures R.O. RO RO

HVAC

CHILLED WATER PIPING

Supply, install, test and commission of Black

steel class B seamless pipe to BS 1387

including all fittings , valves, balancing valve,

brackets, clamps, clips and supports,

insulation complete all as specified in flexible

connection as shown on drawings or as

UNIT RATE ITEM 

NO. DESCRIPTION ESTIMATED 

QUANTITY  UNIT 

Page 231: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 231/300

connection . as shown on drawings or asrequire to complete the connection and

installations.

A 40 mm Dia 55 P lin m 7.700 423.500 3.380 185.

B 50 mm Dia 81 P lin m 9.300 753.300 4.590 371.

C 65 mm Dia 32 P lin m 15.500 496.000 7.290 233.

D 80 mm Dia 321 P lin m 21.400 6,869.400 9.590 3,078.

8,542.200 3,869.

Construction of Haematology and BMT Centre Building - Iss

Bill 5 - Corridor Connection

CODE AMOUNT   Unit Rate Amount

Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

preformed rigid sections PUF/ polyisocanurate

moulded in cylindrical foam 35 kg./m3 density

insulation with canvas / cloth to pipes

complete all in accordance with drawings and

specification

A 40 mm Dia 55 PI lin m 5.900 324.500 3.290 180.

Page 232: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 232/300

B 50 mm Dia 81 PI lin m 6.100 494.100 3.370 272.

C 65 mm Dia 32 PI lin m 8.900 284.800 5.330 170.

D 80 mm Dia 321 PI lin m 9.700 3,113.700 5.810 1,865.

4,217.100 2,489.4

Construction of Haematology and BMT Centre Building - Is

Bill 5 - Corridor Connection

CODE AMOUNT   Unit Rate Amount

Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

EQUIPMENT

Supply, installation of chilled water Cassette

unit; complete with integral actuator valves,

thermostatic controller, filters, 2 way

motorized valve, including all accessories,

plumbing and electrical connection to

complete the installation as per specification,

described in drawings and to the Engineer

approval

Page 233: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 233/300

approval.

ACU-1; decorative, 7 kW cooling capacity, 330 l/sair flow

12 FCU nr. 932.400 11,188.800 813.790 9,765

B

Allow for control system for cassette unitsincluding interconnecting wiring for all controlitems, motors sensors and like complete all as per

specifications and drawings

1 CS Item 0.000 Included

SUNDRIES

C

Allow for control system for complete airconditioning system including DDC panels,interconnecting wiring, for al l control items, motorssensors and the like, not included above but

deemed to be necessary to complete BMSinstallation, installation and commissioning ofBMS system.

1 CS Item 0.000 Included

11 188 800 9 765

Construction of Haematology and BMT Centre Building - Iss

Bill 5 - Corridor Connection

CODE AMOUNT   Unit Rate Amount

Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC INSTALLATION

COLLECTION AMOUNT, R.O., IN FIGURES

Page CC-HVAC- Page 18,542.200 - 3,869.3

Page CC-HVAC- Page 24,217.100 - 2,489.4

Page CC-HVAC- Page 3

Page 234: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 234/300

Page CC HVAC Page 311,188.800 - 9,765.4

23,948.100 16,124.3

Construction of Haematology and BMT Centre Building - I

Bill 5 - Corridor Connection

CODE AMOUNT   Unit Rate Amoun

Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Items Qty Code Make Discount Total Mat Total Mhr Total Mat

Acoustic Insulation 0.00 A - -

Air handling units 0.00 AHU - -

Al cladding 0.00 AL - -

Air terminal devices 0.00 ATD - -

Chillers 0.00 C - -

Cold room outdoor unit 0.00 CR ODU - -

Control system(BMS) 2.00 CS - -

Page 235: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 235/300

Control system(BMS) .00 CSDucting 0.00 D - -

Ducting insulation 0.00 DI - -

Dosing system 0.00 DS - -

Extract fans 0.00 EF - -

Fan coil unit 12.00 FCU 9,765.480 360.000 10,16

Piping 489.00 P 3,869.360 2,353.200 6,45

Piping insulation 489.00 PI 2,489.490 639.000 3,19

Pre insulated piping 0.00 PIP - -

Pumps 0.00 PUMP - -

Pressurisation unit 0.00 PU - -Split units 0.00 SU - -

Valves 0.00 V - -

Varaiable air volume 0.00 VAV - -

16,124.330 3,352.200 19,811

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amoun

CODE Figures R.O. RO RO

HVAC

CHILLED WATER PIPING

Supply, install, test and commission of Black

steel class B seamless pipe to BS 1387

including all fittings , valves, balancing valve,

brackets, clamps, clips and supports,

insulation complete all as specified in . as

shown on drawings or as require to complete

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 236: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 236/300

g q p

the connection and installations.

A 150 mm Dia 103 P lin m 44.100 4,542.300 24.030 2,475

B 125 mm Dia 14 P lin m 36.800 515.200 18.500 259

C 80 mm Dia 12 P lin m 21.400 256.800 9.590 115

D 32 mm Dia 48 P lin m 6.800 326.400 2.970 142

E 25 mm Dia 41 P lin m 5.400 221.400 2.300 94

5,862.100 3,086

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amou

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

CHILLED WATER PIPING (Cont'd)

Supply, install, test and commission of Black

steel class B seamless pipe to BS 1387

including all fittings , valves, balancing valve,

brackets, clamps, clips and supports,

insulation complete all as specified in flexible

connection . as shown on drawings or as

require to complete the connection and

installations.

Page 237: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 237/300

A 300 mm Dia 124 P lin m 122.400 15,177.600 72.230 8,956

B 200 mm Dia 44 P lin m 68.500 3,014.000 39.150 1,722

Insulation for Pipe

Thermal insulation for chilled water pipes

including Aluminium cladding complete all in

accordence with drawings and specifications

C 300 mm Dia 124 PI lin m 51.600 6,398.400 33.570 4,162

D 200 mm Dia 44 PI lin m 28.500 1,254.000 17.189 756

Construction of Haematology and BMT Centre Building- Iss

Bill 6 - Service Compound

AMOUNT  Unit Rate Amount

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

CHILLED WATER PIPING (Cont'd)

A 125 mm Dia 14 PI lin m 18.000 252.000 10.732 150.

B 80 mm Dia 12 PI lin m 13.900 166.800 7.851 94.

Page 238: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 238/300

C 32 mm Dia 48 PI lin m 7.600 364.800 4.124 197.

D 25 mm Dia 41 PI lin m 7.100 291.100 3.731 152.

1,074.700 595.

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amou

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

VALVES AND FIXING

Double regulating valves

A 150 mm Dia 10 V nr. 352.400 3,524.000 253.380 2,533

Gate valves

B 150 mm Dia 10 V nr. 212.500 2,125.000 147.550 1,47

Isolating Valves

Page 239: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 239/300

Isolating Valves

C 32 mm Dia 1 V nr. 11.800 11.800 6.140

Non Return valve 0

D 150 mm Dia 10 V nr. 186.100 1,861.000 127.570 1,27

Flexible Connection 0

E 150 mm Dia 10 V nr. 69.700 697.000 39.500 395

Strainer 0

F 150 mm Dia 10 V nr. 164.400 1,644.000 111.200 1,112

G Pressure Gauge 20 V nr. 11.800 236.000 7.800 156

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amou

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

EQUIPMENT

Supply, installation, test & commission of

Primary chilled water pumps, constant speed;

as per section 22 part 4.5 of the contract

specification and drawings; including hoisting

and setting in positin, anti vibration mountings,

control panel, wiring , labelling, final

connections and other required materials to

complete all works in accordenec with

Page 240: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 240/300

drawings and specifications. .

APrimary chilled water pump (P1 to P5); 56 L/s

water flow rate 25 m TDH, 32 kW motor rating5 PUMP nr. 2713.000 13,565.000 2,246.830 11,234

Supply, installation, test & commission of

Secondary chilled water pumps; fitted to a

propulsion headers complete with cut-off valve,

strainers, pressure switch, thermometer,

manometer, flexible connections, motorized

valve, drain valve, connecting pipes, hangers,

supports, anti vibration bases and connection

to power supply for the proper operation of the

system; including hoisting and setting in

position, anti-vibration mountings, control

panel wiring, labelling and other required

materials to complete all works in accordenec

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amoun

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

Chilled water network equipment; including

valves, controls, accessories, base frames,

vibration isolator, control panel, wiring,

labelling, and other required materials, as

specified in drawings , specifications and to

the Engineer/Client approval.

APressurization unit; including break tank,

1 PU nr 3058 900 3 058 900 2 281 050 2 281

Page 241: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 241/300

Apressurization pump and expansion vessel,

1 PU nr. 3058.900 3,058.900 2,281.050 2,281

B Automativ chemical Dosing system 1 DS nr. 1259.100 1,259.100 925.000 925

Fan coil unit; complete with heating, cooling

coils, valves, control valves, thermostatic

controller, filters, grill, including all

accessories, 2 way motorized valves plumbingand electrical connection to complete the

installation, and other required materials, as

specified in drawings , specifications and to

the Engineer/Client approval.

CFCU-1; decorative, 7 kW cooling capacity, 330 L/s

air flow.6 FCU nr. 341.400 2,048.400 264.850 1,589

6 366 400 4 795

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amoun

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC (Cont'd)

Supply and install , test and commission

ventilating fan with electrically operated

louvers, as specified on the drawings,

complete with all mounting requirements,

flexible connections, electrical connections,

support, back draft dampers, auto changeover

controller, complete all in accordence withdrawings and specifications.

Page 242: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 242/300

g p

AEXF-16 (Substation); Twin axial fan, 4000 L/s air

flow, 100 Pa.ESP, 3 kW motor capacity2 EF nr. 1356.000 2,712.000 1,128.490 2,256

B

Allow for providing all necessary BMS control

system including, DDC panels, work stations

interconnecting wiring, for all control items, motors,

sensors and in the installation of control panels,sensors/ remote set points, switches, control

valves, thermostats, wiring ., and operation of the

complete BMS installation air-conditioning and

ventilating system comprising with commisioning of

BMS sysytem.

1 CS Item 0.000 -

2,712.000 2,256

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amou

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

HVAC INSTALLATION

COLLECTION AMOUNT, R.O., IN FIGURES

Page SC-HVAC- Page 15,862.100 - 3,086

Page SC-HVAC- Page 228,058.500 - 16,930

Page SC-HVAC- Page 31,074.700 - 595

Page 243: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 243/300

,

Page SC-HVAC- Page 410,117.600 - 6,966

Page SC-HVAC- Page 551,071.900 - 42,554

Page SC-HVAC- Page 66,366.400 - 4,795

Page SC-HVAC- Page 72,712.000 - 2,256

0 263 200 8

Construction of Haematology and BMT Centre Building- Is

Bill 6 - Service Compound

AMOUNT  Unit Rate Amou

CODE Figures R.O. RO RO

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Items Qty Code Make Discount Total Mat Total Mhr Total Ma

Acoustic Insulation 0.00 A - -

Air handling units 0.00 AHU - -

Al cladding 0.00 AL - -

Air terminal devices 0.00 ATD - -

Chillers 0.00 C - -

Cold room outdoor unit 0.00 CR ODU - -

Control system(BMS) 0.00 CS - -Ducting 0.00 D - -

Page 244: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 244/300

g

Ducting insulation 0.00 DI - -

Dosing system 1.00 DS 925.000 25.000 95

Extract fans 2.00 EF 2,256.980 20.000 2,27

Fan coil unit 6.00 FCU 1,589.100 120.000 1,72

Piping 386.00 P 13,765.150 4,028.100 18,19

Piping insulation 386.00 PI 6,847.020 1,303.700 8,28

Pre insulated piping 0.00 PIP - -

Pumps 8.00 PUMP 42,554.670 330.000 42,9

Pressurisation unit 1.00 PU 2,281.050 30.000 2,3Split units 0.00 SU - -

Valves 73.00 V 6,966.140 624.500 7,65

Varaiable air volume 0.00 VAV - -

77,185.110 6,481.300 84,31

Construction of Haematology and BMT Centre Building - Issu

Bill 7 - Chiller Yard

CODE AMOUNT   Unit Rate A

Figures R.O. RO

HVAC

CHILLED WATER PIPING

Supply, install, test and commission of Black

steel class B pipe to BS 1387 including all

fittings , valves, balancing valve, brackets,

clamps, clips and supports, insulation completeall as specified in . as shown on drawings or as

UNIT RATE ITEM 

NO.DESCRIPTION 

ESTIMATED 

QUANTITY UNIT 

Page 245: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 245/300

require to complete the connection and

installations.

Above Ground

A 150 mm Dia 117 P lin m 44.100 5,159.700 24.030 2

Supply, install, test and commission of Black

steel class B seamless pipe to BS 1387including all fittings , valves, balancing valve,

brackets, clamps, clips and supports, insulation

complete all as specified in flexible connection .

as shown on drawings or as require to

complete the connection and installations.

Above Ground

B 200 mm Dia 66 P lin m 68 500 4 521 000 39 150 2

Construction of Haematology and BMT Centre Building - Issu

Bill 7 - Chiller Yard

CODE AMOUNT   Unit Rate A

Figures R.O. RO

UNIT RATE ITEM 

NO. DESCRIPTION ESTIMATED 

QUANTITY  UNIT 

Insulation for Pipe

preformed rigid sections PUF/polyisocanurate

moulded in cylindrical foam 35 kg./m3 density

insulation with canvas / cloth to cover pipes

and vapour barrier compound to pipes and

aluminium cladding to complete all in

accordance with drawings and specification

Page 246: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 246/300

A 150 mm Dia 117 PI lin m 21.500 2,515.500 12.939

B 200 mm Dia 66 PI lin m 28.500 1,881.000 17.189

C 300 mm Dia 88 PI lin m 51.600 4,540.800 33.570

Chilled water pipe specialist / accessories;

including all related fixing materials, completeall in accordence with the drawings and

specificaions.

Iron Isolating valves

D 150 mm Dia 10 V nr. 212.500 2,125.000 147.550

Double Regulating valves

Construction of Haematology and BMT Centre Building - Issu

Bill 7 - Chiller Yard

CODE AMOUNT   Unit Rate A

Figures R.O. RO

UNIT RATE ITEM 

NO. DESCRIPTION ESTIMATED 

QUANTITY  UNIT 

Cast Iron Y type Strainers

A 150 mm Dia 10 V nr. 164.400 1,644.000 111.200 1

Thermometer

B For 150 mm Dia 20 V nr. 21.400 428.000 15.100

Pressure Gauge

Page 247: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 247/300

Pressure Gauge

C 150 mm Dia 20 V nr. 11.800 236.000 7.800

Flow Switch

D 150 mm Dia 20 V nr. 73.400 1,468.000 50.000 1

Automatic Airvent

E 150 mm Dia 10 V nr. 9.400 94.000 6.000

Motorised Butterfly Valve

F for Chillers 150 mm Dia 5 V nr. 550.400 2,752.000 399.900 1

6,622.000 4

Construction of Haematology and BMT Centre Building - Issu

Bill 7 - Chiller Yard

CODE AMOUNT   Unit Rate A

Figures R.O. RO

UNIT RATE ITEM 

NO. DESCRIPTION ESTIMATED 

QUANTITY  UNIT 

EQUIPMENT

Supply, installation, test & commission of Air

cooled chiller; as per the contract specification

and drawings; including hoisting and setting in

positin, anti vibration mountings, control panel,

wiring , labelling, final connections and other

required materials to complete all works in

accordenec with drawings and specifications. .

Page 248: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 248/300

accordenec with drawings and specifications. .

AChiller 1 to 5 ; Screw type 1134 kW cooling

capacity 54 L/s flow Rate5 C nr. 60083.300 300,416.500 50,105.210 250

B

Allow for providing all necessary BMS control

system including, DDC panels, work stations

interconnecting wiring, for all control items, motors,

sensors and in the installation of control panels,

sensors/ remote set points, switches, control

valves, thermostats, wiring ., and operation of the

complete BMS installation air-conditioning and

ventilating system comprising with commisioning of

BMS sysytem.

1 CS Item 0.000 Included

300,416.500 250

Construction of Haematology and BMT Centre Building - Issue

Bill 7 - Chiller Yard

CODE AMOUNT   Unit Rate Am

Figures R.O. RO R

UNIT RATE ITEM 

NO. DESCRIPTION 

ESTIMATED 

QUANTITY  UNIT 

HVAC INSTALLATION

COLLECTION AMOUNT, R.O., IN FIGURES

Page CY-HVAC- Page 120,451.900 - 11,

Page CY-HVAC- Page 2

15,980.300 - 10,

Page CY-HVAC- Page 3

Page 249: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 249/300

g g6,622.000 - 4,

Page CY-HVAC- Page 4300,416.500 - 250,

343,470.700 277,

Construction of Haematology and BMT Centre Building - Iss

Bill 7 - Chiller Yard

CODE AMOUNT   Unit Rate

Figures R.O. RO

UNIT RATE ITEM 

NO. DESCRIPTION ESTIMATED 

QUANTITY  UNIT 

Items Qty Code Make Discount Total Mat Total Mhr Tota

Acoustic Insulation 0.00 A - -

Air handling units 0.00 AHU - -

Al cladding 0.00 AL - -

Air terminal devices 0.00 ATD - -

Chillers 5.00 C 250,526.050 1,750.000 2Cold room outdoor unit 0.00 CR ODU - -

Control system(BMS) 1.00 CS - -

Page 250: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 250/300

Control system(BMS) 1.00 CS

Ducting 0.00 D - -

Ducting insulation 0.00 DI - -

Dosing system 0.00 DS - -

Extract fans 0.00 EF - -

Fan coil unit 0.00 FCU - -

Piping 271.00 P 11,751.650 3,381.500

Piping insulation 271.00 PI 5,602.439 1,055.000

Pre insulated piping0.00 PIP - -

Pumps 0.00 PUMP - -

Pressurisation unit 0.00 PU - -

Split units 0.00 SU - -

Valves 125.00 V 9,428.800 825.000

Varaiable air volume 0.00 VAV - -

277,308.939 7,011.500 28

Construction of Haematology and BMT Centre Building - Issued for Tender

Bill 7 - Chiller Yard

Amount 

(R.O.) 

(R.O.)

Page 251: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 251/300

3,905.460 

3,418.800 

8,147.040 

15,471.300 

Construction of Haematology and BMT Centre Building - Issued for TendeBill 7 - Chiller Yard

Amount 

(R.O.) 

(R.O.)

1,899.905 

1,424.874 

Page 252: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 252/300

3,438.160 

1,607.500 

2,665.800 

1 054 000

Construction of Haematology and BMT Centre Building - Issued for TendeBill 7 - Chiller Yard

Amount 

(R.O.) 

(R.O.)

1,244.000 

324.000 

178.000 

Page 253: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 253/300

1,110.000 

71.000 

2,082.000 

5,009.000 

Construction of Haematology and BMT Centre Building - Issued for Tender

Bill 7 - Chiller Yard

Amount 

(R.O.) 

(R.O.)

252,451.050 

Page 254: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 254/300

252,451.050 

Construction of Haematology and BMT Centre Building - Issued for Tender

Bill 7 - Chiller Yard

Amount 

(R.O.) 

(R.O.)

15,471.300 

12,090.239 

5,009.000 

252,451.050 

Page 255: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 255/300

285,021.589 

Construction of Haematology and BMT Centre Building - Issued for Tender

Bill 7 - Chiller Yard

Amount 

(R.O.) 

(R.O.)

Page 256: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 256/300

Construction of Haematology and BMT centre Building - Issued for

Bill 9 - External services (All are Provision

CODE AMOUNT  

Figures R.O. RO R

EXTERNAL SERVICES (ALL ARE PROVISIONAL)

FOUAL DRAINAGE INSTALLATIONS

Supply, install; Unplasticized Polyvinyl chloride

(uPVC) pipe; above ground confirming to BS

4514 for above ground and BS 4660 for below

ground piping including all supports fittings,

markings, excavation, bedding, backfilling,concrete encasement (where applicable), flexible

joints , consumables and other required

Unit Rate ITEM 

NO.

DESCRIPTION QUANTITY UNIT  

UNIT RATE 

Page 257: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 257/300

materials to complete the piping installation; all

in accordance with the drawings and

specifications.

Below Ground piping, including all related civil

works

Not Applicable for

HVAC

A 160 mm. pipe 210 lin m

B 110 mm. pipe 76 lin m

C 80 mm. pipe 43 lin m

Waste drainage specialist/fixtures; including all

related fixing materials, complete; all

accordance with drawings and specifications

Gully trap double sealed access DI cover

Construction of Haematology and BMT centre Building - Issued for

Bill 9 - External services (All are Provision

CODE AMOUNT  

Figures R.O. RO R

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

MANHOLES

Construct manholes, comprising 150 mm RCC in

150 mm thick base and cover slab, medium

ductile iron grating and frame to BS 497 bedded

on and pointed in cement mortar including all

necessary reinforcement, formwork, benching,

rendering, bituminous paint externally,

excavation, backfill and disposal all in

accordence with drawings and specifications.

MH 1 ; 800 X 800 X 600 mm deep with 600 x 600

Page 258: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 258/300

AMH-1 ; 800 X 800 X 600 mm deep with 600 x 600

mm ductile iron cover1 nr.

BMH-2 ; 800 X 800 X 840 mm deep with 600 x 600

mm ductile iron cover1 nr.

Not Applicable for

HVAC

CMH-3 ; 800 X 800 X 1160 mm deep with 600 x 600

mm ductile iron cover1 nr.

DMH-4 ; 800 X 800 X 1310 mm deep with 600 x 600mm ductile iron cover

1 nr.

EMH-5 ; 800 X 800 X 1390 mm deep with 600 x 600

mm ductile iron cover1 nr.

FMH-6 ; 800 X 800 X 1440 mm deep with 600 x 600

mm ductile iron cover1 nr.

HLS1 ; 1200 X 1200 X 4000 mm with 800 x 800 mm

1 nr

Construction of Haematology and BMT centre Building - Issued for T

Bill 9 - External services (All are Provision

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

MANHOLES (Cont'd)

AMH-7 ; 800 X 800 X 1490 mm deep with 600 x 600mm ductile iron cover

1 nr.

BMH-8 ; 800 X 800 X 1620 mm deep with 600 x 600mm ductile iron cover

1 nr.

C MH-9 ; 800 X 800 X 600 mm deep with 600 x 600mm ductile iron cover 2 nr.

MH 10 800 X 800 X 720 d i h 600 600

Page 259: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 259/300

DMH-10 ; 800 X 800 X 720 mm deep with 600 x 600mm ductile iron cover

1 nr.

EMH-11 ; 800 X 800 X 920 mm deep with 600 x 600mm ductile iron cover

1 nr.Not Applicable for

HVAC

F

MH-12 ; 800 X 800 X 990 mm deep with 600 x 600

mm ductile iron cover 1 nr.

GMH-13 ; 800 X 800 X 1060 mm deep with 600 x 600mm ductile iron cover

1 nr.

HMH-13 ; 800 X 800 mm with 600 x 600 mm ductileiron cover

1 nr.

Construction of Haematology and BMT centre Building - Issued for Te

Bill 9 - External services (All are Provisiona

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

LIFTING STATION

A

Allow for providing a lifting station construct withRCC, sewage lifting pumps – duty and

standby/assist, pump control panel, pump lifting

chains, guide rail, level switches, manhole covers,

valves and associated fittings, sewage pumps shall

be self-priming centrifugal, non-clogging type suitable

for mounting on dry bed at floor level, (otherwised

measured elsewhere) complete all in accordence

with drawings and specification

1 ItemNot Applicable for

HVAC

Page 260: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 260/300

Construction of Haematology and BMT centre Building - Issued for Te

Bill 9 - External services (All are Provisiona

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

FIRE PROTECTION /CWS INSTALLATION

Wet Standpipe and Hose Sytem

Galvanised Steel pipe, confirming to BS 1387

heavy duty GI class C pipe; including all

supports, fittings , grooved couplings, markings,

paintings materials, fire stops, consumbles and

other required materials, complete all in

accordence with drawings and specification.

pipes laid below ground, including all related

civil works

A 200 mm. Dia pipe 122 lin m

Page 261: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 261/300

B 150 mm. Dia pipe 4 lin mNot Applicable for

HVAC

C 110 mm. Dia pipe 147 lin m

D 75 mm. Dia pipe 195 lin m

E 65 mm. Dia pipe 78 lin m

Construction of Haematology and BMT centre Building - Issued for Tend

Bill 9 - External services (All are Provisional)

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

FIRE PROTECTION /CWS INSTALLATION

(Cont'd)

ISOLATING VALVE

A 110 mm. Dia pipe 3 nr.

B 75 mm. Dia pipe 3 nr.

B 65 mm. Dia pipe 9 nr.

Page 262: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 262/300

Valve Chamber

C 1200 x 1200 1 nr.Not Applicable for

HVAC

FIRE HYDRANT

Fire hydrant; including all fixing accessories,complete all in accordence with drawings and

specifications.

D Fire Hydrant 4 nr.

Construction of Haematology and BMT centre Building - Issued for Ten

Bill 9 - External services (All are Provisional

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

Pipes laid below ground, including all related

civil works

A 200 mm Dia pipe 98 lin m

B 300 mm Dia pipe 97 lin m

FIRE PROTECTION /CWS INSTALLATION

(Cont'd)

Pre insulated Pipes laid below ground including

Page 263: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 263/300

Pre insulated Pipes laid below ground including

all excavation/ rock(If any), bed and backfilling,

warning tape complete with all in accordance

with drawings and specification (All are

provisional)

Not Applicable forHVAC

C 200 mm Dia pipe 98 lin m

D 300 mm Dia pipe 97 lin m

Construction of Haematology and BMT centre Building - Issued for Te

Bill 9 - External services (All are Provisiona

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

CHILLED WATER PIPES

Pre insulated Pipes laid below ground including

all excavation/ rock(If any), bed and backfilling,

warning tape complete with all in accordance

with drawings and specification (All are

provisional)

A 300 mm Dia pipe 85 PIP lin m 0.000 0.000 0.000

B 125 mm Dia pipe (55m) 1 PIP lin m 23677.000 23677.000 14048.100 14048.1

Page 264: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 264/300

C 80 mm Dia pipe 220 PIP lin m 0.000 0.000 0.000

23,677.00 14,048

Construction of Haematology and BMT centre Building - Issued fo

Bill 9 - External services (All are Provisio

CODE AMOUNT  

Figures R.O. RO R

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

ELECTRICAL INSTALLATION

Incoming primary cable from existing 11kV ring

net work utility service of the hospital; including

all cost related to the, terminations , cable joints,

final connection for electrical supply and fees

imposed and works to be carried out by the local

authorities, and laid below ground in 1000 mm

deep service trenches and the like, including

trench excavation/rock cutting in any material,

sand bedding, backfilling with selected

excavated/imported material, compact in layer,

i t PVC bl til t ti bl

Page 265: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 265/300

warning tapes, PVC cable tile protection, cable

makers for side walks and cable joint/route

markers, complete installationall other related

civil and ancilary works.

A

Supply, installation, testing and commissioning of 2 x

3C -240 sq.mm XLPE 11KV cables from proposedprimary substation. 1,020 lin m

Not Applicable for

HVAC

B

Allow for providing outdoor telephone (600 pairs)cable from BLock 3 building through existing andducts; as shown on the External services drawings.(otherwised measured elsewhere) completeinstallation all other related civil and ancilary works.

1 ItemNot Applicable for

HVAC

Construction of Haematology and BMT centre Building - Issued for T

Bill 9 - External services (All are Provisiona

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

CABLES (Cont'd)

A

Allow for providing fibre optic cables from BLock 9building, through existing and ducts; as shown on theExternal services drawings (otherwised measuredelsewhere) complete installationall other related civiland ancilary works. ,

1 ItemNot Applicable for

HVAC

LV CABLE DUCT

Excavate trench for LV cable duct; including

grading bottoms, dune sand bed and surround,

backfilling with cable tiles, cable marker ,

warning tape , complete all in accordence with

drawings and specifications.

Page 266: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 266/300

drawings and specifications.

BFor 1200 x 100 mm underground trench with 4 x 200mm dia PVC duct

40 lin mNot Applicable for

HVAC

Construction of Haematology and BMT centre Building - Issued for

Bill 9 - External services (All are Provision

CODE AMOUNT  

Figures R.O. RO R

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

CABLES

Power supply distribution copper cables with

earth continuity cable cable laid in floor trench,

drawn in conduits and the like surface fixed in

cable ladders, trays,trunkiing with approved

supports or/and laid in floor service trenches,

drawn in conduits as specified and the like, If

buried then and laid below ground in 1000 mm

deep service trenches and the like, includingtrench excavation/rock cutting in any material,

sand bedding, backfilling with selected

excavated/imported material, compact in layer ,

warning tapes PVC cable tile protection cable

Page 267: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 267/300

warning tapes, PVC cable tile protection, cable

makers for side walks and cable joint/route

markercomplete installation with terminations at

both ends; all as specified and detailed on

drawings

14 - 1C 630 sq mm XLPE/SWA/ PVC copper

cables

A From Transformer 1 1to AMF Panel 1 25 lin m

B From AMF panel 1to EMDB-1 25 lin mNot Applicable for

HVAC

C From Transformer 3 1to MDB 1 25 lin m

Construction of Haematology and BMT centre Building - Issued for Te

Bill 9 - External services (All are Provisiona

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

ELECTRICAL INSTALLATION

CABLES (Cont'd)

14 - 1C 630 sq mm XLPE/SWA/ PVC copper

cables (Cont'd)

A From Transformer 4 1to AMF Panel 2 25 lin m

B From AMF panel 2to EMDB-2 25 lin m

C From transformer and RMU -1 25 lin m

Page 268: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 268/300

D From transformer and RMU -2 25 lin m

3 - 4C x 240 sqmm XLPE + 3 - 1C 70 sq mm ECC

cables

Not Applicable for

HVAC

E From EMDB 1 to Chiller 1 spliter panel 80 lin m

F From MDB 1 to Chiller 3 spliter panel 95 lin m

G From MDB 1 to Chiller 4 spliter panel 98 lin m

H From MDB 1 to Chiller 5 spliter panel 105 lin m

Construction of Haematology and BMT centre Building - Issued for Te

Bill 9 - External services (All are Provisional

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

ELECTRICAL INSTALLATION

CABLES (Cont'd)

4C x 240 sqmm XLPE + 3 - 1C 70 sq mm ECC

cables

A From EMDB 2 to Chiller 2 spliter panel 95 lin m

4C - 16 sq mm XLPE + 1C 16 sq mm ECC

B From Kitchen SMEDB to feeder filler - 1 95 lin m

C From Kitchen SMEDB to feeder filler - 2 115 lin m

Page 269: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 269/300

D From EMDB2 to EXT DB 1 15 lin mNot Applicable for

HVAC

E From EMDB2 to Service Compound DB 15 lin m

F From EMDB2 to Transfer Pump 50 lin m

G From EMDB2 to External feeder piller - 3 92 lin m

Construction of Haematology and BMT centre Building - Issued for Ten

Bill 9 - External services (All are Provisional)

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

ELECTRICAL INSTALLATION

CABLES (Cont'd)

4C - 10 sq mm XLPE + 1C 10 sq mm ECC

A From Control panel (essential) to chiller - 1 50 lin m

B From Control panel (essential) to chiller - 2 55 lin m

C From Control panel (non essential) to chiller - 3 60 lin m Not Applicable forHVAC

D From Control panel (non essential) to chiller - 4 65 lin m

Page 270: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 270/300

E From Control panel (non essential) to chiller - 5 70 lin m

Construction of Haematology and BMT centre Building - Issued for Te

Bill 9 - External services (All are Provisional

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

FEEDER PILLER

A 63A External Feeder Pillars 2 nr.

B Feeder Pillar -3 1 nr.

HV man hole with hevy duty frame and covercomplet with engraving, including excavation,

disposal , back filling, concrete work including

all necessary reinforcement, formwork,

benching, rendering, bituminous paint

Not Applicable for

HVAC

Page 271: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 271/300

benching, rendering, bituminous paint

externally, excavation, backfill and disposal all in

accordence with drawings and specifications.

C Electrical Manhole (EMH) 3 nr.

D Man hole (ELV) 5 nr.

Construction of Haematology and BMT centre Building - Issued for

Bill 9 - External services (All are Provision

CODE AMOUNT  

Figures R.O. RO R

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

Supply and install cable conduit in concealed

installations including device boxes, cover

plates, conduits and wiring between devices and

distribution boards, switching panels ,complete

alll in accordance with drawings and

specifications

A To luminaries 21 nr.

EQUIPMENT

Supply and provide light fittings complete with

Page 272: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 272/300

Supply and provide light fittings complete with

lamps, conduit or chain suspension, flexible

cords, ceiling roses, ballast and starters to

complete the installation,

The rate shall include for cable 3C x 10 sq mm

XLPE cable from Feeder piller 2 to Type K2 pole

and Feder piller 1 to Type K1 pole referdrawings

Not Applicable for

HVAC

BType K1- single spherical luminarie mounted on 3

meter pole c/w 1x50w MBFU lamp, cable entryterminations fuse carrier + control gear

10 nr.

CType K2- single spherical luminarie mounted on 3meter pole c/w 4x50w MBFU lamp, cable entry

terminations fuse carrier + control gear

11 nr.

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

CODE AMOUNT  

Figures R.O. RO RO M

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

COLLECTION (Cont'd) AMOUNT, R.O., IN FIGURES

EX-S-Page 9-1

EX-S-Page 9-2

EX-S-Page 9-3

EX-S-Page 9-4Not Applicable for

HVAC

Page 273: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 273/300

EX-S-Page 9-5

EX-S-Page 9-6

EX-S-Page 9-7

Construction of Haematology and BMT centre Building - Issued for Ten

Bill 9 - External services (All are Provisional)

CODE AMOUNT  

Figures R.O. RO RO

Unit Rate ITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

COLLECTION (Cont'd) AMOUNT, R.O., IN FIGURES

Brought Forward

EX-S-Page 9-8

23677.000 0 14048.10

EX-S-Page 9-9

EX-S-Page 9-10

EX-S-Page 9-11

Page 274: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 274/300

EX-S-Page 9-12Not Applicable for

HVAC

EX-S-Page 9-13

EX-S-Page 9-14

EX-S-Page 9-15

Construction of Haematology and BMT centre Building - Issued

Bill 9 - External services (All are Provisi

CODE AMOUNT  

Figures R.O. RO

Unit RatITEM 

NO.DESCRIPTION QUANTITY UNIT  

UNIT RATE 

Items Qty Code Make Discount Total Mat Total Mhr Tot

Acoustic Insulation 0.00 A - -

Air handling units 0.00 AHU - -

Al cladding 0.00 AL - -

Air terminal devices 0.00 ATD - -

Chillers 0.00 C - -

Cold room outdoor unit 0.00 CR ODU - -

Control system(BMS) 0.00 CS - -Ducting 0.00 D - -

Ducting insulation 0.00 DI - -

Dosing system 0.00 DS - -

Extract fans 0.00 EF - -

Page 275: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 275/300

Fan coil unit 0.00 FCU - -

Piping 0.00 P - -

Piping insulation 0.00 PI - -

Pre insulated piping 306.00 PIP 14,048.10 3,512.03

Pumps 0.00 PUMP - -

Pressurisation unit 0.00 PU - -

Split units 0.00 SU - -

Valves 0.00 V - -

Varaiable air volume 0.00 VAV - -

14,048.10 3,512.03

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 276: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 276/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 277: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 277/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 278: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 278/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 279: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 279/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 280: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 280/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 281: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 281/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 282: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 282/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

0.000

17911.328

0.000

17,911.33 

Page 283: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 283/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 284: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 284/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 285: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 285/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 286: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 286/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 287: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 287/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 288: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 288/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 289: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 289/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 290: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 290/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 291: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 291/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 292: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 292/300

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

17911.328

Page 293: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 293/300

17,911.33 

Construction of Haematology and BMT centre Building - Issued for Tender

Bill 9 - External services (All are Provisional)

Amount 

(R.O.) 

(R.O.) 

Page 294: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 294/300

Bills Area Total Mat Total Mhr Total Mat+Mhr Selling

Bill 4-1 Main Building 658,542.43 126,133.06 797,288.80 1,010,564.60 

Bill 5-1 Corridor 16,124.33 3,352.20 19,811.75 23,948.10 

Bill 6-1 Service compound 77,185.11 6,481.30 84,314.54 105,263.20 

Bill 7-1 Chiller yard 277,308.94 7,011.50 285,021.59 343,470.70 

Bill 9 External 14,048.10 3,512.03 17,911.33 23,677.00 

1,043,208.91 146,490.09 1,204,348.01 1,506,923.60 

Items Qty Code Make

Acoustic Insulation 1.00 A

Air handling units 22.00 AHU McQuay

Al cladding 1.00 AL

Air terminal devices 2,130.00 ATD

Chillers 5 00 C McQuay

Page 295: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 295/300

Chillers 5.00 C McQuay

Cold room outdoor

unit7.00 CR ODU

Control

system(BMS) 9.00 CS Johnson

Ducting 77,839.00 D

Ducting insulation 12,422.00 DI

Dosing system 1.00 DS Ebara

Extract fans 44.00 EF Dynair

Fan coil unit 50.00 FCU McQuay

100,902.98 

Page 296: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 296/300

Equip 19%

LS 32%

SU 10%

Discount Total Mat Total Mhr Total Mat+Mhr Selling

9,209.05 6,566.32 16,432.00 21,721.50 

12.50% 158,810.50 1,100.00 160,020.50 190,424.30 

16,616.61 3,323.32 20,272.26 26,797.90 

95,446.40 4,602.20 100,508.82 132,855.00 

12.50% 250,526.05 1,750.00 252,451.05 300,416.50 

Page 297: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 297/300

, , , ,

3,465.59 350.00 3,850.59 4,239.90 

15% 101,650.00 12,706.25 115,626.88 137,596.00 

81,030.13 48,222.83 134,075.25 178,796.70 

60,700.15 29,150.89 92,766.13 123,144.00 

7.50% 925.00 25.00 952.50 1,259.10 

10% 35,723.90 440.00 36,207.90 43,087.50 

12.50% 19,904.48 1,120.00 21,136.48 24,248.40 

Page 298: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 298/300

Page 299: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 299/300

Mat Mhr

GI 141,730.29 77,373.72

Preinsulated 114,282.40 43,477.00

27,447.89 33,896.72

Ducting

Construction of Haematology and BMT Centre Building- Issued for Tender

Bill of Quantities - Grand Summary

1 Preliminaries

2 Day works

3 Provisional sum and Prime cost

4 Haematology and BMT Centre

5 Corridor connection

6 Service Compound

7 Chiller Yard

8 External works

9 External services

Sub total

Contingencies (5% Excluding Bill number 1, 2 & 3)

Total

TOTAL TENDER VALUE CARRIED TO THE FORM OF TENDER 

(In Words, the Total Tender Value in Omani Rial)

DESCRIPTION BILL

NO.AMOUNT (R.O.) 

Page 300: Hvac Costing Bmt

8/2/2019 Hvac Costing Bmt

http://slidepdf.com/reader/full/hvac-costing-bmt 300/300

Name of Tenderer Date Signature of Tenderer

…………………………………………. ………………………... ………………..………………………………

Gulf Engineering Consutancy Grand Summary - Page 1