CDS | Spillette / DeShazo Tang / / Pavlik February 4, 2009 Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary 2
27

Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Jan 10, 2016

Download

Documents

Thyra

Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary. February 4, 2009. CDS | Spillette / DeShazo Tang /. / Pavlik. 2. Economic Analysis – basis for alternatives developed, analyzed, and designed. Strengths and Opportunities - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

CDS | Spillette / DeShazo Tang / / PavlikFebruary 4, 2009

Hurst – Bellaire Redevelopment PlanExisting Conditions and Economic Analysis Summary

2

Page 2: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Economic Analysis – basis for alternatives developed, analyzed, and designed

Strengths and Opportunities

•Support for moderately-priced new single family development based on recent sales•Large redevelopment tracts possible (8, 10, 12 acres)•Connectivity to surrounding area pretty good (SH 121/183, SH 10)•Artisan Center Theater

Weaknesses and Challenges

•Concentration, age, and condition of apartments•Retail oversupply, age and property condition, and nearby competition strong•Internal connectivity not good

Therefore, Market-Based Focus for Conceptual Design Plans:

Redevelopment into single family, limited retail, and limited mixed-use / multifamily

CDS | Spillette / DeShazo Tang / / Pavlik

Page 3: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Conceptual Design Planning Surrounding Context Map

5

Page 4: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Existing Transportation Plan: Links to freeways available.

6

Page 5: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Current Zoning

8

Page 6: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Parcel Re-Development Opportunities

9

Page 7: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Opportunities and Constraints

10

Page 8: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Critical Success Factors for any Plan or Redevelopment

• Physical connections and linkages for vehicular and non-motorized travel

• Re-orientation of the commercial strip center(s)

• Carve out under-utilized large parking fields for maximized opportunity

• Create a public plaza or permanent open space for community events, perhaps representing Hispanic community

• Link Parks to the surrounding neighborhood

• Create an arts / entertainment district

• Fill-in and connect pedestrian linkages and sidewalks with street grid design

• Find home for a police sub-station

12

Page 9: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Alternatives Concepts Investigated:

Redevelop the Theater vs. Theater Moves Away

Internal Plaza Orientation vs. Pipeline Orientation

Add Internal Roads vs. No Circulation

200,000 SF Retail vs. 100,000 SF Retail

Community Arts District Focus vs. Neighborhood Focus

Pipeline as Vehicular Thoroughfare vs. Pipeline as Pedestrian Focus

Focus Around Intersection(s) vs. Focus Around Park(s)

Not an option

The Arts / Entertainment DistrictAlternative

The NeighborhoodAlternative

13

Page 10: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Neighborhood Alternative:• Intimate, neighborhood scale; add character with a focus and attention to Bellaire Park

• Small cultural gathering opportunities such as a band stand

• Small neighborhood retail opportunities centered between Pipeline Road and the neighborhood park

• Pipeline as pedestrian oriented streetscape scale for Pipeline Road with on-street parking

• Internal street network for increased pedestrian, bicycle and vehicular circulation as link from neighborhood to park.

CDS / Spillette / DeShazo Tang / / Pavlik

The Art / Entertainment District Alternative:• Focus on creating an Art and Entertainment District and Redevelop the Artisan Theatre

•Internal focus around a main street plaza and

gathering space

•Create a larger community commercial node at the intersection of Pipeline and the re-alignment of Brown Trail

•Re-define Pipeline as a boulevard road supporting vehicular circulation as an east-west thoroughfare

• Same. Internal street network for increased pedestrian, bicycle and vehicular circulation, but more to/from central district.

Page 11: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Neighborhood – 1st Phase Opportunity

CDS | Spillette / DeShazo Tang / / Pavlik

• Introduce opportunity for mixed-use product and replace retail displaced

• Create home for Police sub-station for additional

safety and interaction with community

•Create direct street and sidewalk access around park

for added safety and accessibility by surrounding community

16

Page 12: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Neighborhood – 2nd Phase Opportunity

CDS | Spillette / DeShazo Tang / / Pavlik

• Transition retail to mixed-use product along Pipeline

• In-fill Single Family homes to create a neighborhood with a street grid network

• Provide various lot sizes and product type opportunities

• Meet current demand for market supported single family product and establish

a neighborhood density that would then support future demand opportunity for attached housing of proposed full build-out

17

Page 13: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Neighborhood – Full Build-out of Proposed Alternative

CDS | Spillette / DeShazo Tang / / Pavlik

Unit Counts

Single Family Lots: 176

Small Single Family Lots: 55

Single Family Attached: 153

Square Feet Counts

Multi Family Attached: 525k

Mixed-Use (1st floor retail): 88k

Mixed-Use (2 floors res): 225k

Police Sub-Station: 6k

Parking Required: ~ 1,418

Parking Provided: ~ 1,300

*Off-Street Parking not included in calculations and is proposed along Pipeline to support Mixed-Use product.

*Parking requirements reduced to: 1.5/du, 1/300sqft retail. Multi Family and Mixed-Use assumed 3 floors.

18

Page 14: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

CDS | Spillette / DeShazo Tang / / Pavlik

The Neighborhood – Meeting Critical Success and Sustainable Opportunities

Critical Success Factors Physical connections and linkages for vehicular and non-motorized

Fill-in and connect pedestrian linkages

LEED-ND Opportunities

Connect street grids through project (NPDp1)

Expand street grid density and connectivity through site (NPDc8, NPDc11)

20

Page 15: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

CDS | Spillette / DeShazo Tang / / Pavlik

The Neighborhood – Meeting Critical Success and Sustainable Opportunities

Critical Success FactorsRe-orientation of commercial with Mixed-Use along Pipeline Road

Maximize use of under-utilized large parking fields for opportunity

LEED-ND Opportunities

Maintain sustainable percent of services for a mix of uses based on market demand (NPDc2)

Enhance densities (NPDp2, NPDc1)

Reduce impervious surface area of surface parking (NPDc6)

21

Page 16: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

CDS | Spillette / DeShazo Tang / / Pavlik

The Neighborhood – Meeting Critical Success and Sustainable Opportunities

Critical Success FactorsCreate a public plaza or permanent open space for community events representing Hispanic community

Link Bellaire Park to the surrounding neighborhood

LEED-ND Opportunities

Enhance outdoor public space (NPDc12)

Reduce heat island effects with landscaping (GCTc10)

22

Page 17: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

CDS | Spillette / DeShazo Tang / / Pavlik

The Neighborhood – Meeting Critical Success and Sustainable Opportunities

Critical Success FactorsFind home for a police sub-station

LEED-ND Opportunities

Introduce Internal bike network (SLLc5)

23

Page 18: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – 1st Phase Opportunity

CDS | Spillette / DeShazo Tang / / Pavlik

• Create Boulevard on Pipeline with key pedestrian

intersections

• Create home for Police sub-station for additional

safety and interaction with community

•Introduce opportunity for mixed-use product

• Align Brown Trail for direct connection to highways

• Create new home for Artisan Theatre sharing surface parking

•Create direct access of streets and sidewalks around park for safety and accessibility

26

Page 19: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – 2nd Phase Opportunity

CDS | Spillette / DeShazo Tang / / Pavlik

• In-fill retail opportunity at major intersection

• In-fill Single Family homes that create neighborhood grid street network

• Provide various lot size opportunities

• Meet current demand for market supported single family product and establish

a neighborhood density that would then support future demand opportunity for attached housing of proposed full build-out

27

Page 20: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District - Full Build-out of Proposed Alternative

CDS | Spillette / DeShazo Tang / / Pavlik

Unit Counts

Single Family Lots: 177

Small Single Family Lots: 35

Single Family Attached: 126

Square Feet Counts

Multi Family Attached: 422k

Mixed-Use (1st floor retail):108k

Mixed-Use (2 floors res): 216k

Police Sub-Station: 10k

Retail: 18k

Theatre: 30k

Parking Required:

~1,483

Parking Provided Surface:

~1,100

Parking Provided Structure:

~340

*Off Street Parking not included in calculations and is proposed along the internal main street art district.

*Parking requirements reduced to: 1.5/du, 1/300sqft retail, Multi Family and Mixed-Use assumed 3 floors, 4 floors parking structure, 500 seat theatre.

28

Page 21: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – Meeting Critical Success and Sustainable Opportunities

CDS | Spillette / DeShazo Tang / / Pavlik

Critical Success Factors Physical connections and linkages for vehicular and non-motarized

Fill-in and connect pedestrian linkages

LEED-ND Opportunities

Connect street grids through project (NPDp1)

Expand street grid density and connectivity through site (NPDc8,

NPDc11)

30

Page 22: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – Meeting Critical Success and Sustainable Opportunities

CDS | Spillette / DeShazo Tang / / Pavlik

Critical Success FactorsRe-orient commercial with Mixed-Use along Pipeline Road

Carve out under-utilized large parking fields for maximized opportunity

LEED-ND Opportunities

Enhance densities (NPDp2, NPDc1)

Maintain sustainable percent of services for a mix of uses based on market

demand (NPDc2)

Reduce impervious surface area of surface parking (NPDc2)

31

Page 23: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – Meeting Critical Success and Sustainable Opportunities

CDS | Spillette / DeShazo Tang / / Pavlik

Critical Success FactorsCreate a public plaza and internal main street

New street can be closed for events and become pedestrian zone

Maybe focus on Hispanic community

Create an arts district

LEED-ND Opportunities

Introduce bus and transportation options (Highly recommended to support reduced parking and district concept) (SLLc4)

Enhance outdoor public space (NPDc12)

32

Page 24: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – Meeting Critical Success and Sustainable Opportunities

CDS | Spillette / DeShazo Tang / / Pavlik

Critical Success FactorsLink Bellaire Park to the surrounding neighborhood

Fill-in and connect pedestrian linkages, add green spaces

LEED-ND Opportunities

Enhance outdoor public space (NPDc12)

Reduce heat island effects with landscaping (GCTc10)

33

Page 25: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

The Art / Entertainment District – Meeting Critical Success and Sustainable Opportunities

CDS | Spillette / DeShazo Tang / / Pavlik

Critical Success FactorsFind home for a police sub-station

LEED-ND Opportunities

Introduce bike network (SLLc5)

34

Page 26: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Southeast Hurst and Bellaire Sustainable Development Plan

33

Safe Routes to School

Re-Build Bellaire Dr.

Artisan Concept

Critical Success Factors• Physical connections and linkages• Link Park to the surrounding neighborhood• Re-orientation of the retail strip center(s) • Find home for a police sub-station• Re-use under-utilized large parking land • Create permanent open space for community events representing Hispanic community• Foster arts / entertainment district• Fill in with street grid design

Concept Plan

Stakeholders

• Property Owners

• Residents

• Bedford

• Artisan, tenants

• JPS, Tarrant Co., United Way, HEB ISD, Parks Dept.

Page 27: Hurst – Bellaire Redevelopment Plan Existing Conditions and Economic Analysis Summary

Next Steps

3

• Community input now to end of March• Staff outreach to stakeholders, owners, others• Newsletter, Business Quarterly• Draft Plan Preparation

• Draft back to City – mid-March• Draft financial recommendations from consultants

• Presentation to key groups• Joint P&Z, EDAC, City Council – late March• Stakeholder meeting, community meeting• Input back to consultants

• Final Report – mid- to late April• Recommended schedules, strategies, responsibilities

• If developer/owner and project identified….Potential for application to NCTCOG’s current call for sustainable development implementation projects

CDS | Spillette / DeShazo Tang / / Pavlik